SwissCasinos - Is it possible to source an ERP System in just 4 Weeks?

SwissCasinos - Is it possible to source an ERP System in just 4 Weeks?

  • Als Erste(r) kommentieren

  • Gehören Sie zu den Ersten, denen das gefällt!

SwissCasinos - Is it possible to source an ERP System in just 4 Weeks?

  1. 1. 1 HOWTOSOURCEANERPIN4WEEKS? IMPOSSIBLE?
  2. 2. HOWTOSOURCEANERPIN4WEEKS? “Impossible is just a big word thrown around by small men who find it easier to live in the world they've been given than to explore the power they have to change it. Impossible is not a fact. It's an opinion. Impossible is not a declaration. It's a dare. Impossible is potential. Impossible is temporary. Impossible is nothing.” ― Muhammad Ali
  3. 3. SwissCasinosGroup The Swiss Casinos Group is the largest swiss gambling and casino company with 4 landbased and 1 online casino in Switzerland. #1 in the market with more than 800’000 visits, 630 employees an annual revenue of CHF180 million ($ 200 mio). It is still in the early stages of transitioning to business agility.
  4. 4. 4 FROMIDEATOGO-LIVE Value Time-to-Market CONSOLIDATE GENERAL SPECIFICATION INTO VISION FOR ERP AGILE DELIVERY IDEA Start June2018 GO-LIVE Jan1,2020 Dec16,2018 BOARD APPROVED PROJECT SHAKIRA AND ROUGH BUDGET Dec17,2018 - January31,2019 SOURCING INCL. BIG ROOM EVENT (INCL. CHRISTMAS HOLIDAYS) March,2019
  5. 5. THEVISION «automated»consolidationprocessfor9subsidiariesincludingacomplexfinancial architecturewith12financialdimensionsandahighlysophisticatedreportingsystem paperlessworkflow «PUSH THE CONSOLIDATION BUTTON» Thefinancialarchitecture
  6. 6. Setupanagile,cross-functionalteam Empoweritwithmainstakeholders 1 Dec18
  7. 7. Gatherneedswithrealusers Prepareforbigroomevaluationworkshop © All rights reserved 2 Dec20
  8. 8. Alignwithpeoplethatwilldothejob Startcooperationevenbeforeacontract Invite3competitorsinthesameroom 3 Jan30
  9. 9. Co-createanagilecontract Runaproof-of-concept 3 Jan30
  10. 10. co-createthebestlicensemodel 3 Jan30
  11. 11. Co-createanAgileContract RunaProof-of-Concept © All rights reserved 11 11 3 Jan30 Resolverisks&openquestionsimmediately 3 Jan30+31
  12. 12. Demoresults Getpeer-feedback Team-decision 4 Dec31
  13. 13. ACHIEVEMENT • ONE VENDOR CONTRACTED FOR THE PROJECT • AGILE CONTRACT AGREED AND SIGNED • ANOTHER VENDOR CONTRACTED AS AN EXPERT TO ASSIST THE PRODUCT OWNER • DEVELOPED TOGETHER A LICENSE MODEL • MAJOR SAVINGS • VERY GOOD EXPERIENCE ALSO FOR THE NON-SELECTED VENDORS
  14. 14. Capacityofteammembers Handling3vendorssimultaneously CONCLUSIONS Legalasksforatemplate Challenges Yes we also had challenges and still have!-But now those are transparent and get solved. Stayinthedriver-seat Mindshift-wearealljusthuman