MIA CENTRAL TERMINAL REDEVELOPMENT
PROGRAM
Executive Briefing for
Citizens’ Transportation Advisory Committee (CTAC)
November 19, 2014
2
DRAFT – FOR PRELIMINARY AND PLANNING PURPOSES ONLY
2
Discussion Agenda
• MIA 2015 Terminal Area Configuration
• MIA 2035 Terminal Area Configuration
• Activity Summary
• Gate and Hardstand Requirements
• Terminal Space Requirements
• Other Terminal Capital Projects
• Terminal Concept
• Terminal Space Layout
• Terminal Construction Sequencing and Milestones
• Program Cost Estimates
3
DRAFT – FOR PRELIMINARY AND PLANNING PURPOSES ONLY
3
MIA Existing Terminal Area
Configuration
Aircraft
Gates
Aircraft
Hardstands
North Terminal 59 9
Central Terminal 47 3
South Terminal 26 4
TOTAL 132 16
4
DRAFT – FOR PRELIMINARY AND PLANNING PURPOSES ONLY
4
MIA 2035 Terminal Area
Configuration
Gates and Aircraft Hardstand Inventory
Aircraft
Gates
Aircraft
Hardstands
North Terminal 70 9
Central Terminal 39 0
South Terminal 24 4
TOTAL 133 13
D-West
D-East
New Landside
Terminal South
New Landside
Terminal North
Super G
Super E-Head
Super E-Connector
55
ACTIVITY SUMMARY
6
DRAFT – FOR PRELIMINARY AND PLANNING PURPOSES ONLY
6
Future Design Day Flight
Activity Summary
• Total operations (arrivals and departures) for a peak month-
average day
Sources: MIA Airside Operations Division, Baseline Schedule; Central Terminal PDD Forecasts, May 2013; MIA Carriers Input, July 2013.
Carrier Group 2012 (Baseline) 2020 2025 2030 2035
AMR Carriers 1/ 665 841 899 959 1027
Other Domestic Carriers 82 119 130 144 158
oneworld 2/ 43 55 61 67 73
Foreign Flag Carriers 3/ 112 186 209 231 261
Nonscheduled 16 18 20 22 24
TOTAL 918 1,219 1,319 1,423 1,543
Notes:
1. AMR Carriers include American Eagle and US Airways.
2. Growth rates incorporates changes in oneworld Alliance members (e.g. Mexicana, TAM, airberlin) between 2009 and 2012.
3. Assumes air service by new international entrant carriers based on discussions with MDAD Marketing Division.
4. Average annual growth rates for carriers currently operating at MIA are:
i. AMR carriers and oneworld Partners: 3.0% to 2020 and 1.3% thereafter
ii. All other carriers: 5.5% between 2012 and 2020 as a result of new entrant activity
anticipated by MDAD’s Marketing Division; 2.0% from 2020 through 2035;
7
DRAFT – FOR PRELIMINARY AND PLANNING PURPOSES ONLY
7
MIA New Routes
• New Routes Opened in 2013 and 2014:
– Guadeloupe, French Antilles
– Martinique, French Antilles
– Calgary, Canada
– San Diego
– Curitiba, Brazil
– Porto Alegre, Brazil
– San Antonio
– Cozumel, Mexico
– Milan, Italy
– Frankfurt, Germany
– Viracopos, Brazil
– Austin
– Kansas City
– Salt Lake City
8
DRAFT – FOR PRELIMINARY AND PLANNING PURPOSES ONLY
8
MIA New Entrants
• New Entrants in 2013 and 2014:
– XL Airways
– WestJet
– Jetairfly (Brussels)
– Qatar Airways (Doha)
– Air Europa (Madrid/Punta Cana)
• New Entrants Announced for 2014 and 2015:
– Frontier
– Finnair
– Thomas Cook Airlines
• New A380 flights by British Airways and Air France
• Additional new service/entrants expected for 2016 Olympics
9
DRAFT – FOR PRELIMINARY AND PLANNING PURPOSES ONLY
9
Air Carrier Historical and
Projected Statistics
Sources: MIA Airside Operations Division, Baseline Schedule; SMP Forecasts (approved by FAA on July 21, 2011);
Central Terminal PDD Forecasts, May 2013; MIA Carriers Input, July 2013.
0
100,000
200,000
300,000
400,000
500,000
600,000
AirCarrierAnnualAircraftOperations
Fiscal Year
Historical Air Carrier Operations
New Actual Data since Forecast Approval
SMP Operations Baseline Forecast - Low - AAGR*: 1.3%
SMP Operations Baseline Forecast - High - AAGR*: 2.3%
MIA PDD - Airline Derived Forecast - AAGR 2.3%
2010Actual
2011Actual
2012Actual
2013Actual
Notes:
1. AAGR* stands for Average Annual Growth Rate.
2. FAA FY2012 Terminal Area Forecast is not presented as it does not provide operations forecast for passenger aircraft specifically.
3. MIA Central Terminal Program Definition Document forecast was prepared in consultation with all airlines currently operating at MIA.
1010
GATE AND HARDSTAND
REQUIREMENTS
11
DRAFT – FOR PRELIMINARY AND PLANNING PURPOSES ONLY
11
• Gate requirements by airline groups (144 total)
1
Gate Gauge RJ-S RJ-L NB WB JB NLA Total
American Airlines (AA) and oneworld Partners (OW) 0 0 44 1 23 1 69
AA + OW Spare Gates 0 0 4 0 3 0 7
Total Contact Gate Requirements AA + OW + Spares 0 0 48 1 26 1 76
American Eagle E175 Contact Gate Requirements 0 17 0 0 0 0 17
American Eagle E145 Ground Loaded Gate Requirements 2 0 0 0 0 0 2
Total Gate Requirements American Eagle 2 17 0 0 0 0 19
Other Airlines (OAL) 0 0 29 0 15 2 46
MDAD Controlled Gates / Spares 0 0 1 0 2 0 3
Total Contact Gate Requirements OAL + MDAD-Controlled
Gates 0 0 30 0 17 2 49
Note: The gate requirements presented above assume a preferential use of the gates.
Gate Requirements - Year 2035
Gate Demand Summary
Source: MIA Central Terminal Program Definition Document Forecast, Ricondo & Associates, Inc., August 2013.
12
DRAFT – FOR PRELIMINARY AND PLANNING PURPOSES ONLY
12
Gate Requirements - Year 2035
Hardstand Positions Demand Summary
• Hardstand positions by airline groups
Gate Gauge RJ-S RJ-L NB WB JB NLA Total
American Airlines and oneworld Partners 0 0 8 0 10 0 18
American Eagle 3 6 0 0 0 0 9
Total Hardstand Requirements AMR Carriers and
oneworld 3 6 8 0 10 0 27
Other Airlines (OAL) 0 0 8 0 5 0 13
Source: MIA Central Terminal Program Definition Document Forecast, Ricondo & Associates, Inc., August 2013. 1
1313
OTHER TERMINAL CAPITAL
PROJECTS
14
DRAFT – FOR PRELIMINARY AND PLANNING PURPOSES ONLY
14
Other MIA Terminal Capital
Projects
1Source: MIA Central Terminal Program Definition Document Analysis (Refined with Air Carriers 11/01/2013), Ricondo & Associates, November 2013.
1515
TERMINAL CONCEPT
16
DRAFT – FOR PRELIMINARY AND PLANNING PURPOSES ONLY
16
Central Terminal – Airside
Refinements
1Source: Pier Configuration Terminal Concept, Ricondo & Associates Inc., with MDAD Input, October 2013.
1717
TERMINAL SPACE LAYOUT
18
DRAFT – FOR PRELIMINARY AND PLANNING PURPOSES ONLY
181
Terminal Space Plan – Level
One
Sources: Rodriguez & Quiroga Architect Chartered, May 2012; Bag Handling System Configuration, URS Corp., October 2013;
Terminal Space Program, Ricondo & Associates, October 2013.
19
DRAFT – FOR PRELIMINARY AND PLANNING PURPOSES ONLY
191
Terminal Space Plan – Level
Two
Sources: Rodriguez & Quiroga Architect Chartered, May 2012; Terminal Space Program, Ricondo & Associates, October 2013.
20
DRAFT – FOR PRELIMINARY AND PLANNING PURPOSES ONLY
20
Terminal Space Plan – Level
Three
2Sources: Rodriguez & Quiroga Architect Chartered, May 2012; Terminal Space Program, Ricondo & Associates, October 2013.
21
DRAFT – FOR PRELIMINARY AND PLANNING PURPOSES ONLY
21
Terminal Space Plan – Level
Four (Potential APM)
Sources: Rodriguez & Quiroga Architect Chartered, May 2012; Terminal Space Program, Ricondo & Associates, October 2013.
22
DRAFT – FOR PRELIMINARY AND PLANNING PURPOSES ONLY
22
Terminal Support Functions
• Items requiring further coordination to be conducted as
separate studies or during design include:
– Hotel Replacement (including site study)
– Cruise ship passengers landside accommodation / processing
– MDAD and Federal agencies’ needs inside the terminal building
– Finalization of concession program
– Decision on, and programming of previously discussed commercial
program (i.e. initially proposed for Levels 4, 5, and 6 of new Central
Terminal)
– Decision on, and integration with North Terminal of Automated People
Mover
2
2323
TERMINAL CONSTRUCTION
SEQUENCING AND MILESTONES
SOUTH TO NORTH SEQUENCING
24
DRAFT – FOR PRELIMINARY AND PLANNING PURPOSES ONLY
24
Construction Sequencing
Pre-construction Conditions
Year: 2019
Sources: Terminal Construction Sequencing, Ricondo & Associates Inc., September 2013; Cost and Duration Estimates Adjusted for
Refined Phases by Ricondo & Associates Inc. (approximated), URS Corp., December 2013 and U.S. Cost, April 2013.c
Note: revised from 2018 as shown in PDD by MDAD on June 2014.
25
DRAFT – FOR PRELIMINARY AND PLANNING PURPOSES ONLY
25
Construction Sequencing
(Cont’d)
Phase 1a (13 mo)
Start Year: 2020
Concourse H Gate Upgrades and Internationalization
Sources: Terminal Construction Sequencing, Ricondo & Associates Inc., September 2013; Cost and Duration Estimates Adjusted for
Refined Phases by Ricondo & Associates Inc. (approximated), URS Corp., December 2013 and U.S. Cost, April 2013.
Note: revised from 2018 as shown in PDD by MDAD on June 2014.
26
DRAFT – FOR PRELIMINARY AND PLANNING PURPOSES ONLY
26
Note: D-West is built within the total duration of Phase 1b.
Sources: Terminal Construction Sequencing, Ricondo & Associates Inc., September 2013; Cost and Duration Estimates Adjusted for
Refined Phases by Ricondo & Associates Inc. (approximated), URS Corp., December 2013 and U.S. Cost, April 2013.
Construction Sequencing
(Cont’d)
Phase 1b (33 mo)
Start Year: 2021
Note: revised from 2018 as shown in PDD by MDAD on June 2014.
27
DRAFT – FOR PRELIMINARY AND PLANNING PURPOSES ONLY
27
Phase 1c (2 mo)
Start Year: 2024
Sources: Terminal Construction Sequencing, Ricondo & Associates Inc., September 2013; Cost and Duration Estimates Adjusted for
Refined Phases by Ricondo & Associates Inc. (approximated), URS Corp., December 2013 and U.S. Cost, April 2013.
Construction Sequencing
(Cont’d)
Note: revised from 2018 as shown in PDD by MDAD on June 2014.
28
DRAFT – FOR PRELIMINARY AND PLANNING PURPOSES ONLY
28
Phase 2a (18 mo)
Start Year: 2024
Sources: Terminal Construction Sequencing, Ricondo & Associates Inc., September 2013; Cost and Duration Estimates Adjusted for
Refined Phases by Ricondo & Associates Inc. (approximated), URS Corp., December 2013 and U.S. Cost, April 2013.
Construction Sequencing
(Cont’d)
Note: revised from 2018 as shown in PDD by MDAD on June 2014.
29
DRAFT – FOR PRELIMINARY AND PLANNING PURPOSES ONLY
29
Phase 2b (29 mo)
Start Year: 2026
Temporary connection
to Super E using
Existing APM
Sources: Terminal Construction Sequencing, Ricondo & Associates Inc., September 2013; Cost and Duration Estimates Adjusted for
Refined Phases by Ricondo & Associates Inc. (approximated), URS Corp., December 2013 and U.S. Cost, April 2013.
Construction Sequencing
(Cont’d)
Note: revised from 2018 as shown in PDD by MDAD on June 2014.
30
DRAFT – FOR PRELIMINARY AND PLANNING PURPOSES ONLY
30
Phase 2c (12 mo)
Start Year: 2028
Sources: Terminal Construction Sequencing, Ricondo & Associates Inc., September 2013; Cost and Duration Estimates Adjusted for
Refined Phases by Ricondo & Associates Inc. (approximated), URS Corp., December 2013 and U.S. Cost, April 2013.
Construction Sequencing
(Cont’d)
Note: revised from 2018 as shown in PDD by MDAD on June 2014.
31
DRAFT – FOR PRELIMINARY AND PLANNING PURPOSES ONLY
31
Phase 2d (9 mo)
Start Year: 2029
Sources: Terminal Construction Sequencing, Ricondo & Associates Inc., September 2013; Cost and Duration Estimates Adjusted for
Refined Phases by Ricondo & Associates Inc. (approximated), URS Corp., December 2013 and U.S. Cost, April 2013.
Construction Sequencing
(Cont’d)
Note: revised from 2018 as shown in PDD by MDAD on June 2014.
32
DRAFT – FOR PRELIMINARY AND PLANNING PURPOSES ONLY
32
Phase 2e (6 mo)
Start Year: 2030
Sources: Terminal Construction Sequencing, Ricondo & Associates Inc., September 2013; Cost and Duration Estimates Adjusted for
Refined Phases by Ricondo & Associates Inc. (approximated), URS Corp., December 2013 and U.S. Cost, April 2013.
Construction Sequencing
(Cont’d)
Note: revised from 2018 as shown in PDD by MDAD on June 2014.
33
DRAFT – FOR PRELIMINARY AND PLANNING PURPOSES ONLY
33
Phase 2f (10 mo)
Start Year: 2030
Sources: Terminal Construction Sequencing, Ricondo & Associates Inc., September 2013; Cost and Duration Estimates Adjusted for
Refined Phases by Ricondo & Associates Inc. (approximated), URS Corp., December 2013 and U.S. Cost, April 2013.
Construction Sequencing
(Cont’d)
Note: revised from 2018 as shown in PDD by MDAD on June 2014.
34
DRAFT – FOR PRELIMINARY AND PLANNING PURPOSES ONLY
343
Phase 3a (6 mo)
Start Year: 2031
Sources: Terminal Construction Sequencing, Ricondo & Associates Inc., September 2013; Cost and Duration Estimates Adjusted for
Refined Phases by Ricondo & Associates Inc. (approximated), URS Corp., December 2013 and U.S. Cost, April 2013.
Construction Sequencing
(Cont’d)
Note: revised from 2018 as shown in PDD by MDAD on June 2014.
35
DRAFT – FOR PRELIMINARY AND PLANNING PURPOSES ONLY
353
Phase 3b (5 mo)
Start Year: 2032
Sources: Terminal Construction Sequencing, Ricondo & Associates Inc., September 2013; Cost and Duration Estimates Adjusted for
Refined Phases by Ricondo & Associates Inc. (approximated), URS Corp., December 2013 and U.S. Cost, April 2013.
Construction Sequencing
(Cont’d)
Note: revised from 2018 as shown in PDD by MDAD on June 2014.
36
DRAFT – FOR PRELIMINARY AND PLANNING PURPOSES ONLY
363
FINAL
Year: 2032
Sources: Terminal Construction Sequencing, Ricondo & Associates Inc., September 2013; Cost and Duration Estimates Adjusted for
Refined Phases by Ricondo & Associates Inc. (approximated), URS Corp., December 2013 and U.S. Cost, April 2013.
Construction Sequencing
(Cont’d)
Note: revised from 2018 as shown in PDD by MDAD on June 2014.
3737
All years represent the start/commencement of the listed program
elements except for the program completion milestone).
All durations provided in years (yrs.).
Landside Terminal
(North) Demolition (1.5 yr.)
New Landside Terminal (North) and
Super E-Head Construction (4 yrs.)
New Super E Connector
Construction (1 yr.)
Central Terminal Redevelopment
Program Completion
Concourse G and Landside
(South) Terminal Demolition (1 yr.)
Super G and New Landside
Terminal (South) Construction (3 yrs.)
2020 2021 2024 2026 2028 2031
Lower E Demolition
(0.5 yr.)
2032
Concourse F Demolition (0.5 yr.)
2030
Milestone Schedule
Sources: Terminal Construction Sequencing, Ricondo & Associates Inc., September 2013; Cost Duration Estimates
Adjusted for Refined Phases by Ricondo & Associates Inc. (approximated), URS Corp., December 2013 and U.S. Cost, April 2013.
Note: revised from 2018 as shown in PDD by MDAD on June 2014.
38
DRAFT – FOR PRELIMINARY AND PLANNING PURPOSES ONLY
38
80
90
100
110
120
130
140
Gates
Central Terminal Sequencing Period
Total Gate Capacity Gate Requirements Gate + Spare Requirements
Construction Gate Capacity vs
Demand
Sources: Terminal Construction Sequencing, Ricondo & Associates Inc., September 2013; Cost and Duration Estimates
Adjusted for New Phases by Ricondo & Associates Inc. (approximated), URS Corp., December 2013.
CentralTerminal
ConstructionCommencement
2E
EXISTING 0 1A 1B 2A 2B 2C 2F 3A 3B 3C1C 2D
Commuter Terminal Demolition
Concourse G Demolition
Super G Opening
D-West Opening
E-Head Opening
Notes:
1. Some phases may overlap, but it is not shown here for clarity.
2. Upon completion, it is assumed that the Central Terminal is operated as a
common use facility to protect the spare gate requirements and accommodate
the gate demand.
3. Gate capacity includes considerations for North Terminal enabling projects,
See Note 2
3939
PROGRAM COST ESTIMATES
40
DRAFT – FOR PRELIMINARY AND PLANNING PURPOSES ONLY
40
Central Terminal Construction
Cost Estimates
Phase Item
Estimated Construction
Costs (2012 Dollars)
Duration
(Months)
Projected
Start Year
Estimated Loaded
Costs (2012 Dollars)
Escalated and
Loaded Costs
0 Build Passenger Connector $52,333,815 24 2016 $71,958,995 $83,420,197
1A Demo Concourse G/ Terminal South $59,767,606 13 2018 $82,180,458 $101,071,598
1B Build Super G/ Terminal South $571,642,669 33 2019 $786,008,670 $995,692,267
1C Apron $5,063,924 2 2022 $6,962,896 $9,357,550
2A Demo Central Terminal North $128,538,929 18 2022 $176,741,027 $244,650,916
2B Build New Central (N) and Super E $1,104,406,734 29 2024 $1,518,559,259 $2,230,055,467
2C Build Super E Connector Building $240,222,745 12 2026 $330,306,275 $499,617,878
2D Demo Concourse E Lower $24,908,421 6 2027 $34,249,079 $53,358,949
2E Apron $16,026,570 10 2027 $22,036,533 $35,362,167
3A Demo Concourse F $22,766,757 6 2028 $31,304,291 $50,234,197
3B Apron $17,497,901 5 2029 $24,059,613 $38,608,616
TOTAL $2,243,176,070 $3,084,367,096 $4,341,429,802
Notes:
1. Total soft costs before escalation assumed to be 37.50%.
2. Escalation is calculated to the mid-point of each phase using a 3% rate, as recommended by U.S. Cost.
3. Excludes costs for proposed triturator, gas station, bus station, NTD and Concourse H gate upgrades and enabling projects,
and potential Automated People Mover.
Sources: Terminal Construction Sequencing, Ricondo & Associates Inc., September 2013; Cost and Duration Estimates
Adjusted for Refined Phases by Ricondo & Associates Inc. (approximated), URS Corp., December 2012 and U.S. Cost, April 2013.
4141
RENDERINGS
42
DRAFT – FOR PRELIMINARY AND PLANNING PURPOSES ONLY
42
View from North
43
DRAFT – FOR PRELIMINARY AND PLANNING PURPOSES ONLY
43
View from South
44
DRAFT – FOR PRELIMINARY AND PLANNING PURPOSES ONLY
44
Next Steps
• MDAD to undertake financial planning for incremental
implementation of the Central Terminal Program and other terminal
capital projects.
4545
QUESTIONS

More Related Content

What's hot

E-commerce Project Development
E-commerce Project DevelopmentE-commerce Project Development
E-commerce Project DevelopmentAmin Chowdhury
 
Integrated multi modal transportation system
Integrated multi modal transportation system Integrated multi modal transportation system
Integrated multi modal transportation system Aditya Gupta
 
Intelligent Bus Tracking System Using Android
Intelligent Bus Tracking System Using AndroidIntelligent Bus Tracking System Using Android
Intelligent Bus Tracking System Using AndroidAM Publications
 
Future Smart Mobility Solution AAM & UAM & PBV
Future Smart Mobility Solution AAM & UAM & PBVFuture Smart Mobility Solution AAM & UAM & PBV
Future Smart Mobility Solution AAM & UAM & PBVHyundai Motor Group
 
Intelligent transportation system (its) used in the public transport sector ...
Intelligent transportation system (its) used in the public transport sector  ...Intelligent transportation system (its) used in the public transport sector  ...
Intelligent transportation system (its) used in the public transport sector ...Praneeth Prabodha Dissanayaka, MILT
 
Bus Service Problems
Bus Service Problems Bus Service Problems
Bus Service Problems Saeed Badeli
 
Evaluation of Aesthetic, Functional, and Environmental Effects on the Design ...
Evaluation of Aesthetic, Functional, and Environmental Effects on the Design ...Evaluation of Aesthetic, Functional, and Environmental Effects on the Design ...
Evaluation of Aesthetic, Functional, and Environmental Effects on the Design ...Journal of Contemporary Urban Affairs
 
India modern rail service for public
India modern rail service for publicIndia modern rail service for public
India modern rail service for publicMahesh Chandra Manav
 
E Commerce Proposal
E Commerce ProposalE Commerce Proposal
E Commerce ProposalAnsar ul Haq
 
Presentation on Open Toll & Toll Systems
Presentation on Open Toll & Toll SystemsPresentation on Open Toll & Toll Systems
Presentation on Open Toll & Toll Systemsshanmuga sundaram
 
05 Business Models for E-commerce slides
05 Business Models for E-commerce slides05 Business Models for E-commerce slides
05 Business Models for E-commerce slidesmonchai sopitka
 
SOFTWARE-DEFINED SUCCESS: THE NEXT GENERATION OF AUTOMOTIVE LIDAR
SOFTWARE-DEFINED SUCCESS: THE NEXT GENERATION OF AUTOMOTIVE LIDARSOFTWARE-DEFINED SUCCESS: THE NEXT GENERATION OF AUTOMOTIVE LIDAR
SOFTWARE-DEFINED SUCCESS: THE NEXT GENERATION OF AUTOMOTIVE LIDARiQHub
 
Integrated Public Transport System - Bangalore
Integrated Public Transport System - BangaloreIntegrated Public Transport System - Bangalore
Integrated Public Transport System - BangaloreTehsin Kazi
 
Base Map and Site Plan
Base Map and Site PlanBase Map and Site Plan
Base Map and Site PlanDoug Crouch
 
The Future Development of Traffic Signals and the Impact of Autonomous Vehicles
The Future Development of Traffic Signals and the Impact of Autonomous VehiclesThe Future Development of Traffic Signals and the Impact of Autonomous Vehicles
The Future Development of Traffic Signals and the Impact of Autonomous VehiclesJumpingJaq
 
iPARK: Intelligent Parking System based on IoT & AI
iPARK: Intelligent Parking System based on IoT & AIiPARK: Intelligent Parking System based on IoT & AI
iPARK: Intelligent Parking System based on IoT & AIMithileysh Sathiyanarayanan
 
intelligent transportation system
intelligent transportation systemintelligent transportation system
intelligent transportation systemkvn virinchi
 
Parking Management System
Parking Management SystemParking Management System
Parking Management SystemIJMER
 
URBAN DESIGN - 2.pdf
URBAN DESIGN - 2.pdfURBAN DESIGN - 2.pdf
URBAN DESIGN - 2.pdfkareemulllah
 

What's hot (20)

E-commerce Project Development
E-commerce Project DevelopmentE-commerce Project Development
E-commerce Project Development
 
Integrated multi modal transportation system
Integrated multi modal transportation system Integrated multi modal transportation system
Integrated multi modal transportation system
 
Intelligent Bus Tracking System Using Android
Intelligent Bus Tracking System Using AndroidIntelligent Bus Tracking System Using Android
Intelligent Bus Tracking System Using Android
 
Future Smart Mobility Solution AAM & UAM & PBV
Future Smart Mobility Solution AAM & UAM & PBVFuture Smart Mobility Solution AAM & UAM & PBV
Future Smart Mobility Solution AAM & UAM & PBV
 
Intelligent transportation system (its) used in the public transport sector ...
Intelligent transportation system (its) used in the public transport sector  ...Intelligent transportation system (its) used in the public transport sector  ...
Intelligent transportation system (its) used in the public transport sector ...
 
Bus Service Problems
Bus Service Problems Bus Service Problems
Bus Service Problems
 
Evaluation of Aesthetic, Functional, and Environmental Effects on the Design ...
Evaluation of Aesthetic, Functional, and Environmental Effects on the Design ...Evaluation of Aesthetic, Functional, and Environmental Effects on the Design ...
Evaluation of Aesthetic, Functional, and Environmental Effects on the Design ...
 
India modern rail service for public
India modern rail service for publicIndia modern rail service for public
India modern rail service for public
 
E Commerce Proposal
E Commerce ProposalE Commerce Proposal
E Commerce Proposal
 
Presentation on Open Toll & Toll Systems
Presentation on Open Toll & Toll SystemsPresentation on Open Toll & Toll Systems
Presentation on Open Toll & Toll Systems
 
05 Business Models for E-commerce slides
05 Business Models for E-commerce slides05 Business Models for E-commerce slides
05 Business Models for E-commerce slides
 
SOFTWARE-DEFINED SUCCESS: THE NEXT GENERATION OF AUTOMOTIVE LIDAR
SOFTWARE-DEFINED SUCCESS: THE NEXT GENERATION OF AUTOMOTIVE LIDARSOFTWARE-DEFINED SUCCESS: THE NEXT GENERATION OF AUTOMOTIVE LIDAR
SOFTWARE-DEFINED SUCCESS: THE NEXT GENERATION OF AUTOMOTIVE LIDAR
 
Integrated Public Transport System - Bangalore
Integrated Public Transport System - BangaloreIntegrated Public Transport System - Bangalore
Integrated Public Transport System - Bangalore
 
Base Map and Site Plan
Base Map and Site PlanBase Map and Site Plan
Base Map and Site Plan
 
Smart parking
Smart parkingSmart parking
Smart parking
 
The Future Development of Traffic Signals and the Impact of Autonomous Vehicles
The Future Development of Traffic Signals and the Impact of Autonomous VehiclesThe Future Development of Traffic Signals and the Impact of Autonomous Vehicles
The Future Development of Traffic Signals and the Impact of Autonomous Vehicles
 
iPARK: Intelligent Parking System based on IoT & AI
iPARK: Intelligent Parking System based on IoT & AIiPARK: Intelligent Parking System based on IoT & AI
iPARK: Intelligent Parking System based on IoT & AI
 
intelligent transportation system
intelligent transportation systemintelligent transportation system
intelligent transportation system
 
Parking Management System
Parking Management SystemParking Management System
Parking Management System
 
URBAN DESIGN - 2.pdf
URBAN DESIGN - 2.pdfURBAN DESIGN - 2.pdf
URBAN DESIGN - 2.pdf
 

Viewers also liked

Corona - Downtown Redevelopment
Corona - Downtown RedevelopmentCorona - Downtown Redevelopment
Corona - Downtown RedevelopmentDarrell Talbert
 
Tsunza peninsula plots for SAle in Mombasa Kenya, a great real estate opportu...
Tsunza peninsula plots for SAle in Mombasa Kenya, a great real estate opportu...Tsunza peninsula plots for SAle in Mombasa Kenya, a great real estate opportu...
Tsunza peninsula plots for SAle in Mombasa Kenya, a great real estate opportu...NairobiRealEstates
 
Milpitas Redevelopment
Milpitas RedevelopmentMilpitas Redevelopment
Milpitas RedevelopmentOri Nagel
 
Townsend: Redevelopment Projects that Get Media Attention
Townsend: Redevelopment Projects that Get Media AttentionTownsend: Redevelopment Projects that Get Media Attention
Townsend: Redevelopment Projects that Get Media AttentionSuburbs Alliance
 
Veetil's Animation Projects of Australia
Veetil's Animation Projects of AustraliaVeetil's Animation Projects of Australia
Veetil's Animation Projects of AustraliaVeetil Digital Service
 
Residential parel proposal
Residential parel proposalResidential parel proposal
Residential parel proposalRAAJESH SHETH
 
9/9 FRI 8:00 | The Redevelopment of Downtown West Palm Beach
9/9 FRI 8:00 | The Redevelopment of Downtown West Palm Beach9/9 FRI 8:00 | The Redevelopment of Downtown West Palm Beach
9/9 FRI 8:00 | The Redevelopment of Downtown West Palm BeachAPA Florida
 
Presentation On the Development of The Springs Shopping Center
Presentation On the Development of The Springs Shopping CenterPresentation On the Development of The Springs Shopping Center
Presentation On the Development of The Springs Shopping CenterJohn Raymond
 
Creative Financing Methods to Fund Project Finance-PPP Projects
Creative Financing Methods to Fund Project Finance-PPP ProjectsCreative Financing Methods to Fund Project Finance-PPP Projects
Creative Financing Methods to Fund Project Finance-PPP ProjectsCherylOberdorf
 
City of Peoria, AZ- Entertainment District Presentation
City of Peoria, AZ- Entertainment District PresentationCity of Peoria, AZ- Entertainment District Presentation
City of Peoria, AZ- Entertainment District Presentationsbettencourt
 
KYC Harbour Redevelopment - AGM 2013 - Status Update
KYC Harbour Redevelopment  - AGM 2013 - Status UpdateKYC Harbour Redevelopment  - AGM 2013 - Status Update
KYC Harbour Redevelopment - AGM 2013 - Status Updatekingstonyc
 
TOD Redevelopment on the Grandest Scale by Tom Young
TOD Redevelopment on the Grandest Scale by Tom YoungTOD Redevelopment on the Grandest Scale by Tom Young
TOD Redevelopment on the Grandest Scale by Tom YoungRail~Volution
 
Case Study: Fairplex Redevelopment Project
Case Study: Fairplex Redevelopment ProjectCase Study: Fairplex Redevelopment Project
Case Study: Fairplex Redevelopment Projectsix14
 
Latin America's Media Market 2013
Latin America's Media Market 2013Latin America's Media Market 2013
Latin America's Media Market 2013USMediaConsulting
 

Viewers also liked (20)

Un cuento.com
Un cuento.comUn cuento.com
Un cuento.com
 
Corona - Downtown Redevelopment
Corona - Downtown RedevelopmentCorona - Downtown Redevelopment
Corona - Downtown Redevelopment
 
Tsunza peninsula plots for SAle in Mombasa Kenya, a great real estate opportu...
Tsunza peninsula plots for SAle in Mombasa Kenya, a great real estate opportu...Tsunza peninsula plots for SAle in Mombasa Kenya, a great real estate opportu...
Tsunza peninsula plots for SAle in Mombasa Kenya, a great real estate opportu...
 
Boston's south end
Boston's south endBoston's south end
Boston's south end
 
Milpitas Redevelopment
Milpitas RedevelopmentMilpitas Redevelopment
Milpitas Redevelopment
 
Townsend: Redevelopment Projects that Get Media Attention
Townsend: Redevelopment Projects that Get Media AttentionTownsend: Redevelopment Projects that Get Media Attention
Townsend: Redevelopment Projects that Get Media Attention
 
Veetil's Animation Projects of Australia
Veetil's Animation Projects of AustraliaVeetil's Animation Projects of Australia
Veetil's Animation Projects of Australia
 
Residential parel proposal
Residential parel proposalResidential parel proposal
Residential parel proposal
 
Launch of WoMoz Mombasa
Launch of WoMoz MombasaLaunch of WoMoz Mombasa
Launch of WoMoz Mombasa
 
9/9 FRI 8:00 | The Redevelopment of Downtown West Palm Beach
9/9 FRI 8:00 | The Redevelopment of Downtown West Palm Beach9/9 FRI 8:00 | The Redevelopment of Downtown West Palm Beach
9/9 FRI 8:00 | The Redevelopment of Downtown West Palm Beach
 
Monterey Park Economic Strategic Planning Workshop 9 May 2009
Monterey Park Economic Strategic Planning Workshop 9 May 2009Monterey Park Economic Strategic Planning Workshop 9 May 2009
Monterey Park Economic Strategic Planning Workshop 9 May 2009
 
Presentation On the Development of The Springs Shopping Center
Presentation On the Development of The Springs Shopping CenterPresentation On the Development of The Springs Shopping Center
Presentation On the Development of The Springs Shopping Center
 
Creative Financing Methods to Fund Project Finance-PPP Projects
Creative Financing Methods to Fund Project Finance-PPP ProjectsCreative Financing Methods to Fund Project Finance-PPP Projects
Creative Financing Methods to Fund Project Finance-PPP Projects
 
City of Peoria, AZ- Entertainment District Presentation
City of Peoria, AZ- Entertainment District PresentationCity of Peoria, AZ- Entertainment District Presentation
City of Peoria, AZ- Entertainment District Presentation
 
South Stockton Redevelopment Project CEE224X Final Presentation
South Stockton Redevelopment Project CEE224X Final PresentationSouth Stockton Redevelopment Project CEE224X Final Presentation
South Stockton Redevelopment Project CEE224X Final Presentation
 
KYC Harbour Redevelopment - AGM 2013 - Status Update
KYC Harbour Redevelopment  - AGM 2013 - Status UpdateKYC Harbour Redevelopment  - AGM 2013 - Status Update
KYC Harbour Redevelopment - AGM 2013 - Status Update
 
TOD Redevelopment on the Grandest Scale by Tom Young
TOD Redevelopment on the Grandest Scale by Tom YoungTOD Redevelopment on the Grandest Scale by Tom Young
TOD Redevelopment on the Grandest Scale by Tom Young
 
Case Study: Fairplex Redevelopment Project
Case Study: Fairplex Redevelopment ProjectCase Study: Fairplex Redevelopment Project
Case Study: Fairplex Redevelopment Project
 
Competition and Market Studies in Latin America: The case of Chile, Colombia,...
Competition and Market Studies in Latin America: The case of Chile, Colombia,...Competition and Market Studies in Latin America: The case of Chile, Colombia,...
Competition and Market Studies in Latin America: The case of Chile, Colombia,...
 
Latin America's Media Market 2013
Latin America's Media Market 2013Latin America's Media Market 2013
Latin America's Media Market 2013
 

Similar to MIA Central Terminal Redevelopment Program presentation, November 19, 2014

Water Infrastructure Projects in Brazil 2012
Water Infrastructure Projects in Brazil 2012Water Infrastructure Projects in Brazil 2012
Water Infrastructure Projects in Brazil 2012ReportsnReports
 
Airports economics in latin america and the caribbean world bank
Airports economics in latin america and the caribbean   world bankAirports economics in latin america and the caribbean   world bank
Airports economics in latin america and the caribbean world bankMaria Baltazar
 
Scott Hamilton
Scott HamiltonScott Hamilton
Scott HamiltonIES / IAQM
 
Presentaciones taeca kom 영문
Presentaciones taeca kom 영문Presentaciones taeca kom 영문
Presentaciones taeca kom 영문qooji
 
20131002 presentation
20131002 presentation20131002 presentation
20131002 presentationRafat Ali
 
MDC Product Presentation
MDC Product PresentationMDC Product Presentation
MDC Product PresentationDouwe Treurniet
 
Gatwick 2013 cip-published_july_2013 (1)
Gatwick 2013 cip-published_july_2013 (1)Gatwick 2013 cip-published_july_2013 (1)
Gatwick 2013 cip-published_july_2013 (1)anjunaparadiso
 
Subsea 7 Q1 2013 results presentation
Subsea 7 Q1 2013 results presentationSubsea 7 Q1 2013 results presentation
Subsea 7 Q1 2013 results presentationTradeWindsnews
 
Analyst breakfast: North American consultancy business - 19 March 2015
Analyst breakfast: North American consultancy business - 19 March 2015Analyst breakfast: North American consultancy business - 19 March 2015
Analyst breakfast: North American consultancy business - 19 March 2015Atkins
 
Generator rental sales plan , Qatar, Saudi Arbaia, UAE , Oman,United Arab emr...
Generator rental sales plan , Qatar, Saudi Arbaia, UAE , Oman,United Arab emr...Generator rental sales plan , Qatar, Saudi Arbaia, UAE , Oman,United Arab emr...
Generator rental sales plan , Qatar, Saudi Arbaia, UAE , Oman,United Arab emr...Dhananjaya Weerasooriya
 
Update-May2007-e
Update-May2007-eUpdate-May2007-e
Update-May2007-eWJ
 
Toronto Pearson Airport - Procurement Strategy Study
Toronto Pearson Airport - Procurement Strategy StudyToronto Pearson Airport - Procurement Strategy Study
Toronto Pearson Airport - Procurement Strategy StudyAhmed Mahmoud
 
Bumi Armada Q2 2013 results presentation
Bumi Armada Q2 2013 results presentationBumi Armada Q2 2013 results presentation
Bumi Armada Q2 2013 results presentationTradeWindsnews
 

Similar to MIA Central Terminal Redevelopment Program presentation, November 19, 2014 (20)

Capital Programs - O'Hare 21
Capital Programs - O'Hare 21 Capital Programs - O'Hare 21
Capital Programs - O'Hare 21
 
Water Infrastructure Projects in Brazil 2012
Water Infrastructure Projects in Brazil 2012Water Infrastructure Projects in Brazil 2012
Water Infrastructure Projects in Brazil 2012
 
Airports economics in latin america and the caribbean world bank
Airports economics in latin america and the caribbean   world bankAirports economics in latin america and the caribbean   world bank
Airports economics in latin america and the caribbean world bank
 
QPR-1 draft.pptx
QPR-1 draft.pptxQPR-1 draft.pptx
QPR-1 draft.pptx
 
DIAL1.pptx
DIAL1.pptxDIAL1.pptx
DIAL1.pptx
 
Scott Hamilton
Scott HamiltonScott Hamilton
Scott Hamilton
 
Presentaciones taeca kom 영문
Presentaciones taeca kom 영문Presentaciones taeca kom 영문
Presentaciones taeca kom 영문
 
20131002 presentation
20131002 presentation20131002 presentation
20131002 presentation
 
MDC Product Presentation
MDC Product PresentationMDC Product Presentation
MDC Product Presentation
 
Gatwick 2013 cip-published_july_2013 (1)
Gatwick 2013 cip-published_july_2013 (1)Gatwick 2013 cip-published_july_2013 (1)
Gatwick 2013 cip-published_july_2013 (1)
 
Slqs pms part1-final
Slqs pms part1-finalSlqs pms part1-final
Slqs pms part1-final
 
Subsea 7 Q1 2013 results presentation
Subsea 7 Q1 2013 results presentationSubsea 7 Q1 2013 results presentation
Subsea 7 Q1 2013 results presentation
 
State work
State workState work
State work
 
Analyst breakfast: North American consultancy business - 19 March 2015
Analyst breakfast: North American consultancy business - 19 March 2015Analyst breakfast: North American consultancy business - 19 March 2015
Analyst breakfast: North American consultancy business - 19 March 2015
 
Generator rental sales plan , Qatar, Saudi Arbaia, UAE , Oman,United Arab emr...
Generator rental sales plan , Qatar, Saudi Arbaia, UAE , Oman,United Arab emr...Generator rental sales plan , Qatar, Saudi Arbaia, UAE , Oman,United Arab emr...
Generator rental sales plan , Qatar, Saudi Arbaia, UAE , Oman,United Arab emr...
 
Shahzad Sikandaruk
Shahzad SikandarukShahzad Sikandaruk
Shahzad Sikandaruk
 
Update-May2007-e
Update-May2007-eUpdate-May2007-e
Update-May2007-e
 
Toronto Pearson Airport - Procurement Strategy Study
Toronto Pearson Airport - Procurement Strategy StudyToronto Pearson Airport - Procurement Strategy Study
Toronto Pearson Airport - Procurement Strategy Study
 
Anchor Reliance Group Intro New
Anchor Reliance Group Intro NewAnchor Reliance Group Intro New
Anchor Reliance Group Intro New
 
Bumi Armada Q2 2013 results presentation
Bumi Armada Q2 2013 results presentationBumi Armada Q2 2013 results presentation
Bumi Armada Q2 2013 results presentation
 

More from Miami-Dade Transportation Planning Organization

More from Miami-Dade Transportation Planning Organization (20)

SMART STEP Project: SE 8th Street & Brickell Avenue
SMART STEP Project: SE 8th Street & Brickell AvenueSMART STEP Project: SE 8th Street & Brickell Avenue
SMART STEP Project: SE 8th Street & Brickell Avenue
 
November 3, 2021 CTAC Virtual Workshop
November 3, 2021 CTAC Virtual WorkshopNovember 3, 2021 CTAC Virtual Workshop
November 3, 2021 CTAC Virtual Workshop
 
September 15, 2021 TARC Virtual Workshop
September 15, 2021 TARC Virtual WorkshopSeptember 15, 2021 TARC Virtual Workshop
September 15, 2021 TARC Virtual Workshop
 
July 21, 2021 TARC Virtual Workshop
July 21, 2021 TARC Virtual WorkshopJuly 21, 2021 TARC Virtual Workshop
July 21, 2021 TARC Virtual Workshop
 
July 14, 2021 FTAC Virtual Workshop
July 14, 2021 FTAC Virtual WorkshopJuly 14, 2021 FTAC Virtual Workshop
July 14, 2021 FTAC Virtual Workshop
 
July 13, 2021 BPAC Virtual Workshop
July 13, 2021 BPAC Virtual WorkshopJuly 13, 2021 BPAC Virtual Workshop
July 13, 2021 BPAC Virtual Workshop
 
June 16, 2021 TARC Virtual Workshop
June 16, 2021 TARC Virtual WorkshopJune 16, 2021 TARC Virtual Workshop
June 16, 2021 TARC Virtual Workshop
 
June 15, 2021 BPAC Virtual Workshop
June 15, 2021 BPAC Virtual Workshop June 15, 2021 BPAC Virtual Workshop
June 15, 2021 BPAC Virtual Workshop
 
May 19, 2021 TARC Virtual Workshop
May 19, 2021 TARC Virtual WorkshopMay 19, 2021 TARC Virtual Workshop
May 19, 2021 TARC Virtual Workshop
 
May 11, 2021 BPAC Virtual Workshop
May 11, 2021 BPAC Virtual WorkshopMay 11, 2021 BPAC Virtual Workshop
May 11, 2021 BPAC Virtual Workshop
 
April 14, 2021 FTAC Virtual Workshop
April 14, 2021 FTAC Virtual Workshop April 14, 2021 FTAC Virtual Workshop
April 14, 2021 FTAC Virtual Workshop
 
April 13, 2021 BPAC Virtual Workshop
April 13, 2021 BPAC Virtual WorkshopApril 13, 2021 BPAC Virtual Workshop
April 13, 2021 BPAC Virtual Workshop
 
April 12, 2021 TPC Virtual Workshop
April 12, 2021 TPC Virtual WorkshopApril 12, 2021 TPC Virtual Workshop
April 12, 2021 TPC Virtual Workshop
 
April 7, 2021 CTAC Virtual Workshop
April 7, 2021 CTAC Virtual Workshop April 7, 2021 CTAC Virtual Workshop
April 7, 2021 CTAC Virtual Workshop
 
March 17, 2021 TARC Virtual Workshop
March 17, 2021 TARC Virtual Workshop March 17, 2021 TARC Virtual Workshop
March 17, 2021 TARC Virtual Workshop
 
March 9, 2021 BPAC Virtual Workshop
March 9, 2021 BPAC Virtual Workshop March 9, 2021 BPAC Virtual Workshop
March 9, 2021 BPAC Virtual Workshop
 
March 3, 2021 CTAC Virtual Workshop
March 3, 2021 CTAC Virtual WorkshopMarch 3, 2021 CTAC Virtual Workshop
March 3, 2021 CTAC Virtual Workshop
 
February 10, 2021 FTAC Virtual Workshop
February 10, 2021 FTAC Virtual WorkshopFebruary 10, 2021 FTAC Virtual Workshop
February 10, 2021 FTAC Virtual Workshop
 
February 9, 2021 BPAC Virtual Workshop
February 9, 2021 BPAC Virtual Workshop February 9, 2021 BPAC Virtual Workshop
February 9, 2021 BPAC Virtual Workshop
 
February 3, 2021 CTAC Virtual Workshop
February 3, 2021 CTAC Virtual Workshop February 3, 2021 CTAC Virtual Workshop
February 3, 2021 CTAC Virtual Workshop
 

Recently uploaded

The Economic and Organised Crime Office (EOCO) has been advised by the Office...
The Economic and Organised Crime Office (EOCO) has been advised by the Office...The Economic and Organised Crime Office (EOCO) has been advised by the Office...
The Economic and Organised Crime Office (EOCO) has been advised by the Office...nservice241
 
Just Call Vip call girls Wardha Escorts ☎️8617370543 Starting From 5K to 25K ...
Just Call Vip call girls Wardha Escorts ☎️8617370543 Starting From 5K to 25K ...Just Call Vip call girls Wardha Escorts ☎️8617370543 Starting From 5K to 25K ...
Just Call Vip call girls Wardha Escorts ☎️8617370543 Starting From 5K to 25K ...Dipal Arora
 
Postal Ballots-For home voting step by step process 2024.pptx
Postal Ballots-For home voting step by step process 2024.pptxPostal Ballots-For home voting step by step process 2024.pptx
Postal Ballots-For home voting step by step process 2024.pptxSwastiRanjanNayak
 
2024: The FAR, Federal Acquisition Regulations - Part 29
2024: The FAR, Federal Acquisition Regulations - Part 292024: The FAR, Federal Acquisition Regulations - Part 29
2024: The FAR, Federal Acquisition Regulations - Part 29JSchaus & Associates
 
Climate change and safety and health at work
Climate change and safety and health at workClimate change and safety and health at work
Climate change and safety and health at workChristina Parmionova
 
Regional Snapshot Atlanta Aging Trends 2024
Regional Snapshot Atlanta Aging Trends 2024Regional Snapshot Atlanta Aging Trends 2024
Regional Snapshot Atlanta Aging Trends 2024ARCResearch
 
EDUROOT SME_ Performance upto March-2024.pptx
EDUROOT SME_ Performance upto March-2024.pptxEDUROOT SME_ Performance upto March-2024.pptx
EDUROOT SME_ Performance upto March-2024.pptxaaryamanorathofficia
 
2024: The FAR, Federal Acquisition Regulations, Part 30
2024: The FAR, Federal Acquisition Regulations, Part 302024: The FAR, Federal Acquisition Regulations, Part 30
2024: The FAR, Federal Acquisition Regulations, Part 30JSchaus & Associates
 
Zechariah Boodey Farmstead Collaborative presentation - Humble Beginnings
Zechariah Boodey Farmstead Collaborative presentation -  Humble BeginningsZechariah Boodey Farmstead Collaborative presentation -  Humble Beginnings
Zechariah Boodey Farmstead Collaborative presentation - Humble Beginningsinfo695895
 
WORLD DEVELOPMENT REPORT 2024 - Economic Growth in Middle-Income Countries.
WORLD DEVELOPMENT REPORT 2024 - Economic Growth in Middle-Income Countries.WORLD DEVELOPMENT REPORT 2024 - Economic Growth in Middle-Income Countries.
WORLD DEVELOPMENT REPORT 2024 - Economic Growth in Middle-Income Countries.Christina Parmionova
 
The Most Attractive Pune Call Girls Handewadi Road 8250192130 Will You Miss T...
The Most Attractive Pune Call Girls Handewadi Road 8250192130 Will You Miss T...The Most Attractive Pune Call Girls Handewadi Road 8250192130 Will You Miss T...
The Most Attractive Pune Call Girls Handewadi Road 8250192130 Will You Miss T...ranjana rawat
 
Junnar ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For S...
Junnar ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For S...Junnar ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For S...
Junnar ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For S...tanu pandey
 
Expressive clarity oral presentation.pptx
Expressive clarity oral presentation.pptxExpressive clarity oral presentation.pptx
Expressive clarity oral presentation.pptxtsionhagos36
 
Night 7k to 12k Call Girls Service In Navi Mumbai 👉 BOOK NOW 9833363713 👈 ♀️...
Night 7k to 12k  Call Girls Service In Navi Mumbai 👉 BOOK NOW 9833363713 👈 ♀️...Night 7k to 12k  Call Girls Service In Navi Mumbai 👉 BOOK NOW 9833363713 👈 ♀️...
Night 7k to 12k Call Girls Service In Navi Mumbai 👉 BOOK NOW 9833363713 👈 ♀️...aartirawatdelhi
 
Antisemitism Awareness Act: pénaliser la critique de l'Etat d'Israël
Antisemitism Awareness Act: pénaliser la critique de l'Etat d'IsraëlAntisemitism Awareness Act: pénaliser la critique de l'Etat d'Israël
Antisemitism Awareness Act: pénaliser la critique de l'Etat d'IsraëlEdouardHusson
 
Call On 6297143586 Viman Nagar Call Girls In All Pune 24/7 Provide Call With...
Call On 6297143586  Viman Nagar Call Girls In All Pune 24/7 Provide Call With...Call On 6297143586  Viman Nagar Call Girls In All Pune 24/7 Provide Call With...
Call On 6297143586 Viman Nagar Call Girls In All Pune 24/7 Provide Call With...tanu pandey
 
Call Girls Nanded City Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Nanded City Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Nanded City Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Nanded City Call Me 7737669865 Budget Friendly No Advance Bookingroncy bisnoi
 
Top Rated Pune Call Girls Hadapsar ⟟ 6297143586 ⟟ Call Me For Genuine Sex Se...
Top Rated  Pune Call Girls Hadapsar ⟟ 6297143586 ⟟ Call Me For Genuine Sex Se...Top Rated  Pune Call Girls Hadapsar ⟟ 6297143586 ⟟ Call Me For Genuine Sex Se...
Top Rated Pune Call Girls Hadapsar ⟟ 6297143586 ⟟ Call Me For Genuine Sex Se...Call Girls in Nagpur High Profile
 
The U.S. Budget and Economic Outlook (Presentation)
The U.S. Budget and Economic Outlook (Presentation)The U.S. Budget and Economic Outlook (Presentation)
The U.S. Budget and Economic Outlook (Presentation)Congressional Budget Office
 

Recently uploaded (20)

The Economic and Organised Crime Office (EOCO) has been advised by the Office...
The Economic and Organised Crime Office (EOCO) has been advised by the Office...The Economic and Organised Crime Office (EOCO) has been advised by the Office...
The Economic and Organised Crime Office (EOCO) has been advised by the Office...
 
Just Call Vip call girls Wardha Escorts ☎️8617370543 Starting From 5K to 25K ...
Just Call Vip call girls Wardha Escorts ☎️8617370543 Starting From 5K to 25K ...Just Call Vip call girls Wardha Escorts ☎️8617370543 Starting From 5K to 25K ...
Just Call Vip call girls Wardha Escorts ☎️8617370543 Starting From 5K to 25K ...
 
Postal Ballots-For home voting step by step process 2024.pptx
Postal Ballots-For home voting step by step process 2024.pptxPostal Ballots-For home voting step by step process 2024.pptx
Postal Ballots-For home voting step by step process 2024.pptx
 
2024: The FAR, Federal Acquisition Regulations - Part 29
2024: The FAR, Federal Acquisition Regulations - Part 292024: The FAR, Federal Acquisition Regulations - Part 29
2024: The FAR, Federal Acquisition Regulations - Part 29
 
Climate change and safety and health at work
Climate change and safety and health at workClimate change and safety and health at work
Climate change and safety and health at work
 
Regional Snapshot Atlanta Aging Trends 2024
Regional Snapshot Atlanta Aging Trends 2024Regional Snapshot Atlanta Aging Trends 2024
Regional Snapshot Atlanta Aging Trends 2024
 
EDUROOT SME_ Performance upto March-2024.pptx
EDUROOT SME_ Performance upto March-2024.pptxEDUROOT SME_ Performance upto March-2024.pptx
EDUROOT SME_ Performance upto March-2024.pptx
 
2024: The FAR, Federal Acquisition Regulations, Part 30
2024: The FAR, Federal Acquisition Regulations, Part 302024: The FAR, Federal Acquisition Regulations, Part 30
2024: The FAR, Federal Acquisition Regulations, Part 30
 
Zechariah Boodey Farmstead Collaborative presentation - Humble Beginnings
Zechariah Boodey Farmstead Collaborative presentation -  Humble BeginningsZechariah Boodey Farmstead Collaborative presentation -  Humble Beginnings
Zechariah Boodey Farmstead Collaborative presentation - Humble Beginnings
 
WORLD DEVELOPMENT REPORT 2024 - Economic Growth in Middle-Income Countries.
WORLD DEVELOPMENT REPORT 2024 - Economic Growth in Middle-Income Countries.WORLD DEVELOPMENT REPORT 2024 - Economic Growth in Middle-Income Countries.
WORLD DEVELOPMENT REPORT 2024 - Economic Growth in Middle-Income Countries.
 
The Most Attractive Pune Call Girls Handewadi Road 8250192130 Will You Miss T...
The Most Attractive Pune Call Girls Handewadi Road 8250192130 Will You Miss T...The Most Attractive Pune Call Girls Handewadi Road 8250192130 Will You Miss T...
The Most Attractive Pune Call Girls Handewadi Road 8250192130 Will You Miss T...
 
Rohini Sector 37 Call Girls Delhi 9999965857 @Sabina Saikh No Advance
Rohini Sector 37 Call Girls Delhi 9999965857 @Sabina Saikh No AdvanceRohini Sector 37 Call Girls Delhi 9999965857 @Sabina Saikh No Advance
Rohini Sector 37 Call Girls Delhi 9999965857 @Sabina Saikh No Advance
 
Junnar ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For S...
Junnar ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For S...Junnar ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For S...
Junnar ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For S...
 
Expressive clarity oral presentation.pptx
Expressive clarity oral presentation.pptxExpressive clarity oral presentation.pptx
Expressive clarity oral presentation.pptx
 
Night 7k to 12k Call Girls Service In Navi Mumbai 👉 BOOK NOW 9833363713 👈 ♀️...
Night 7k to 12k  Call Girls Service In Navi Mumbai 👉 BOOK NOW 9833363713 👈 ♀️...Night 7k to 12k  Call Girls Service In Navi Mumbai 👉 BOOK NOW 9833363713 👈 ♀️...
Night 7k to 12k Call Girls Service In Navi Mumbai 👉 BOOK NOW 9833363713 👈 ♀️...
 
Antisemitism Awareness Act: pénaliser la critique de l'Etat d'Israël
Antisemitism Awareness Act: pénaliser la critique de l'Etat d'IsraëlAntisemitism Awareness Act: pénaliser la critique de l'Etat d'Israël
Antisemitism Awareness Act: pénaliser la critique de l'Etat d'Israël
 
Call On 6297143586 Viman Nagar Call Girls In All Pune 24/7 Provide Call With...
Call On 6297143586  Viman Nagar Call Girls In All Pune 24/7 Provide Call With...Call On 6297143586  Viman Nagar Call Girls In All Pune 24/7 Provide Call With...
Call On 6297143586 Viman Nagar Call Girls In All Pune 24/7 Provide Call With...
 
Call Girls Nanded City Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Nanded City Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Nanded City Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Nanded City Call Me 7737669865 Budget Friendly No Advance Booking
 
Top Rated Pune Call Girls Hadapsar ⟟ 6297143586 ⟟ Call Me For Genuine Sex Se...
Top Rated  Pune Call Girls Hadapsar ⟟ 6297143586 ⟟ Call Me For Genuine Sex Se...Top Rated  Pune Call Girls Hadapsar ⟟ 6297143586 ⟟ Call Me For Genuine Sex Se...
Top Rated Pune Call Girls Hadapsar ⟟ 6297143586 ⟟ Call Me For Genuine Sex Se...
 
The U.S. Budget and Economic Outlook (Presentation)
The U.S. Budget and Economic Outlook (Presentation)The U.S. Budget and Economic Outlook (Presentation)
The U.S. Budget and Economic Outlook (Presentation)
 

MIA Central Terminal Redevelopment Program presentation, November 19, 2014

  • 1. 1 DRAFT – FOR PRELIMINARY AND PLANNING PURPOSES ONLY 1 MIA CENTRAL TERMINAL REDEVELOPMENT PROGRAM Executive Briefing for Citizens’ Transportation Advisory Committee (CTAC) November 19, 2014
  • 2. 2 DRAFT – FOR PRELIMINARY AND PLANNING PURPOSES ONLY 2 Discussion Agenda • MIA 2015 Terminal Area Configuration • MIA 2035 Terminal Area Configuration • Activity Summary • Gate and Hardstand Requirements • Terminal Space Requirements • Other Terminal Capital Projects • Terminal Concept • Terminal Space Layout • Terminal Construction Sequencing and Milestones • Program Cost Estimates
  • 3. 3 DRAFT – FOR PRELIMINARY AND PLANNING PURPOSES ONLY 3 MIA Existing Terminal Area Configuration Aircraft Gates Aircraft Hardstands North Terminal 59 9 Central Terminal 47 3 South Terminal 26 4 TOTAL 132 16
  • 4. 4 DRAFT – FOR PRELIMINARY AND PLANNING PURPOSES ONLY 4 MIA 2035 Terminal Area Configuration Gates and Aircraft Hardstand Inventory Aircraft Gates Aircraft Hardstands North Terminal 70 9 Central Terminal 39 0 South Terminal 24 4 TOTAL 133 13 D-West D-East New Landside Terminal South New Landside Terminal North Super G Super E-Head Super E-Connector
  • 6. 6 DRAFT – FOR PRELIMINARY AND PLANNING PURPOSES ONLY 6 Future Design Day Flight Activity Summary • Total operations (arrivals and departures) for a peak month- average day Sources: MIA Airside Operations Division, Baseline Schedule; Central Terminal PDD Forecasts, May 2013; MIA Carriers Input, July 2013. Carrier Group 2012 (Baseline) 2020 2025 2030 2035 AMR Carriers 1/ 665 841 899 959 1027 Other Domestic Carriers 82 119 130 144 158 oneworld 2/ 43 55 61 67 73 Foreign Flag Carriers 3/ 112 186 209 231 261 Nonscheduled 16 18 20 22 24 TOTAL 918 1,219 1,319 1,423 1,543 Notes: 1. AMR Carriers include American Eagle and US Airways. 2. Growth rates incorporates changes in oneworld Alliance members (e.g. Mexicana, TAM, airberlin) between 2009 and 2012. 3. Assumes air service by new international entrant carriers based on discussions with MDAD Marketing Division. 4. Average annual growth rates for carriers currently operating at MIA are: i. AMR carriers and oneworld Partners: 3.0% to 2020 and 1.3% thereafter ii. All other carriers: 5.5% between 2012 and 2020 as a result of new entrant activity anticipated by MDAD’s Marketing Division; 2.0% from 2020 through 2035;
  • 7. 7 DRAFT – FOR PRELIMINARY AND PLANNING PURPOSES ONLY 7 MIA New Routes • New Routes Opened in 2013 and 2014: – Guadeloupe, French Antilles – Martinique, French Antilles – Calgary, Canada – San Diego – Curitiba, Brazil – Porto Alegre, Brazil – San Antonio – Cozumel, Mexico – Milan, Italy – Frankfurt, Germany – Viracopos, Brazil – Austin – Kansas City – Salt Lake City
  • 8. 8 DRAFT – FOR PRELIMINARY AND PLANNING PURPOSES ONLY 8 MIA New Entrants • New Entrants in 2013 and 2014: – XL Airways – WestJet – Jetairfly (Brussels) – Qatar Airways (Doha) – Air Europa (Madrid/Punta Cana) • New Entrants Announced for 2014 and 2015: – Frontier – Finnair – Thomas Cook Airlines • New A380 flights by British Airways and Air France • Additional new service/entrants expected for 2016 Olympics
  • 9. 9 DRAFT – FOR PRELIMINARY AND PLANNING PURPOSES ONLY 9 Air Carrier Historical and Projected Statistics Sources: MIA Airside Operations Division, Baseline Schedule; SMP Forecasts (approved by FAA on July 21, 2011); Central Terminal PDD Forecasts, May 2013; MIA Carriers Input, July 2013. 0 100,000 200,000 300,000 400,000 500,000 600,000 AirCarrierAnnualAircraftOperations Fiscal Year Historical Air Carrier Operations New Actual Data since Forecast Approval SMP Operations Baseline Forecast - Low - AAGR*: 1.3% SMP Operations Baseline Forecast - High - AAGR*: 2.3% MIA PDD - Airline Derived Forecast - AAGR 2.3% 2010Actual 2011Actual 2012Actual 2013Actual Notes: 1. AAGR* stands for Average Annual Growth Rate. 2. FAA FY2012 Terminal Area Forecast is not presented as it does not provide operations forecast for passenger aircraft specifically. 3. MIA Central Terminal Program Definition Document forecast was prepared in consultation with all airlines currently operating at MIA.
  • 11. 11 DRAFT – FOR PRELIMINARY AND PLANNING PURPOSES ONLY 11 • Gate requirements by airline groups (144 total) 1 Gate Gauge RJ-S RJ-L NB WB JB NLA Total American Airlines (AA) and oneworld Partners (OW) 0 0 44 1 23 1 69 AA + OW Spare Gates 0 0 4 0 3 0 7 Total Contact Gate Requirements AA + OW + Spares 0 0 48 1 26 1 76 American Eagle E175 Contact Gate Requirements 0 17 0 0 0 0 17 American Eagle E145 Ground Loaded Gate Requirements 2 0 0 0 0 0 2 Total Gate Requirements American Eagle 2 17 0 0 0 0 19 Other Airlines (OAL) 0 0 29 0 15 2 46 MDAD Controlled Gates / Spares 0 0 1 0 2 0 3 Total Contact Gate Requirements OAL + MDAD-Controlled Gates 0 0 30 0 17 2 49 Note: The gate requirements presented above assume a preferential use of the gates. Gate Requirements - Year 2035 Gate Demand Summary Source: MIA Central Terminal Program Definition Document Forecast, Ricondo & Associates, Inc., August 2013.
  • 12. 12 DRAFT – FOR PRELIMINARY AND PLANNING PURPOSES ONLY 12 Gate Requirements - Year 2035 Hardstand Positions Demand Summary • Hardstand positions by airline groups Gate Gauge RJ-S RJ-L NB WB JB NLA Total American Airlines and oneworld Partners 0 0 8 0 10 0 18 American Eagle 3 6 0 0 0 0 9 Total Hardstand Requirements AMR Carriers and oneworld 3 6 8 0 10 0 27 Other Airlines (OAL) 0 0 8 0 5 0 13 Source: MIA Central Terminal Program Definition Document Forecast, Ricondo & Associates, Inc., August 2013. 1
  • 14. 14 DRAFT – FOR PRELIMINARY AND PLANNING PURPOSES ONLY 14 Other MIA Terminal Capital Projects 1Source: MIA Central Terminal Program Definition Document Analysis (Refined with Air Carriers 11/01/2013), Ricondo & Associates, November 2013.
  • 16. 16 DRAFT – FOR PRELIMINARY AND PLANNING PURPOSES ONLY 16 Central Terminal – Airside Refinements 1Source: Pier Configuration Terminal Concept, Ricondo & Associates Inc., with MDAD Input, October 2013.
  • 18. 18 DRAFT – FOR PRELIMINARY AND PLANNING PURPOSES ONLY 181 Terminal Space Plan – Level One Sources: Rodriguez & Quiroga Architect Chartered, May 2012; Bag Handling System Configuration, URS Corp., October 2013; Terminal Space Program, Ricondo & Associates, October 2013.
  • 19. 19 DRAFT – FOR PRELIMINARY AND PLANNING PURPOSES ONLY 191 Terminal Space Plan – Level Two Sources: Rodriguez & Quiroga Architect Chartered, May 2012; Terminal Space Program, Ricondo & Associates, October 2013.
  • 20. 20 DRAFT – FOR PRELIMINARY AND PLANNING PURPOSES ONLY 20 Terminal Space Plan – Level Three 2Sources: Rodriguez & Quiroga Architect Chartered, May 2012; Terminal Space Program, Ricondo & Associates, October 2013.
  • 21. 21 DRAFT – FOR PRELIMINARY AND PLANNING PURPOSES ONLY 21 Terminal Space Plan – Level Four (Potential APM) Sources: Rodriguez & Quiroga Architect Chartered, May 2012; Terminal Space Program, Ricondo & Associates, October 2013.
  • 22. 22 DRAFT – FOR PRELIMINARY AND PLANNING PURPOSES ONLY 22 Terminal Support Functions • Items requiring further coordination to be conducted as separate studies or during design include: – Hotel Replacement (including site study) – Cruise ship passengers landside accommodation / processing – MDAD and Federal agencies’ needs inside the terminal building – Finalization of concession program – Decision on, and programming of previously discussed commercial program (i.e. initially proposed for Levels 4, 5, and 6 of new Central Terminal) – Decision on, and integration with North Terminal of Automated People Mover 2
  • 23. 2323 TERMINAL CONSTRUCTION SEQUENCING AND MILESTONES SOUTH TO NORTH SEQUENCING
  • 24. 24 DRAFT – FOR PRELIMINARY AND PLANNING PURPOSES ONLY 24 Construction Sequencing Pre-construction Conditions Year: 2019 Sources: Terminal Construction Sequencing, Ricondo & Associates Inc., September 2013; Cost and Duration Estimates Adjusted for Refined Phases by Ricondo & Associates Inc. (approximated), URS Corp., December 2013 and U.S. Cost, April 2013.c Note: revised from 2018 as shown in PDD by MDAD on June 2014.
  • 25. 25 DRAFT – FOR PRELIMINARY AND PLANNING PURPOSES ONLY 25 Construction Sequencing (Cont’d) Phase 1a (13 mo) Start Year: 2020 Concourse H Gate Upgrades and Internationalization Sources: Terminal Construction Sequencing, Ricondo & Associates Inc., September 2013; Cost and Duration Estimates Adjusted for Refined Phases by Ricondo & Associates Inc. (approximated), URS Corp., December 2013 and U.S. Cost, April 2013. Note: revised from 2018 as shown in PDD by MDAD on June 2014.
  • 26. 26 DRAFT – FOR PRELIMINARY AND PLANNING PURPOSES ONLY 26 Note: D-West is built within the total duration of Phase 1b. Sources: Terminal Construction Sequencing, Ricondo & Associates Inc., September 2013; Cost and Duration Estimates Adjusted for Refined Phases by Ricondo & Associates Inc. (approximated), URS Corp., December 2013 and U.S. Cost, April 2013. Construction Sequencing (Cont’d) Phase 1b (33 mo) Start Year: 2021 Note: revised from 2018 as shown in PDD by MDAD on June 2014.
  • 27. 27 DRAFT – FOR PRELIMINARY AND PLANNING PURPOSES ONLY 27 Phase 1c (2 mo) Start Year: 2024 Sources: Terminal Construction Sequencing, Ricondo & Associates Inc., September 2013; Cost and Duration Estimates Adjusted for Refined Phases by Ricondo & Associates Inc. (approximated), URS Corp., December 2013 and U.S. Cost, April 2013. Construction Sequencing (Cont’d) Note: revised from 2018 as shown in PDD by MDAD on June 2014.
  • 28. 28 DRAFT – FOR PRELIMINARY AND PLANNING PURPOSES ONLY 28 Phase 2a (18 mo) Start Year: 2024 Sources: Terminal Construction Sequencing, Ricondo & Associates Inc., September 2013; Cost and Duration Estimates Adjusted for Refined Phases by Ricondo & Associates Inc. (approximated), URS Corp., December 2013 and U.S. Cost, April 2013. Construction Sequencing (Cont’d) Note: revised from 2018 as shown in PDD by MDAD on June 2014.
  • 29. 29 DRAFT – FOR PRELIMINARY AND PLANNING PURPOSES ONLY 29 Phase 2b (29 mo) Start Year: 2026 Temporary connection to Super E using Existing APM Sources: Terminal Construction Sequencing, Ricondo & Associates Inc., September 2013; Cost and Duration Estimates Adjusted for Refined Phases by Ricondo & Associates Inc. (approximated), URS Corp., December 2013 and U.S. Cost, April 2013. Construction Sequencing (Cont’d) Note: revised from 2018 as shown in PDD by MDAD on June 2014.
  • 30. 30 DRAFT – FOR PRELIMINARY AND PLANNING PURPOSES ONLY 30 Phase 2c (12 mo) Start Year: 2028 Sources: Terminal Construction Sequencing, Ricondo & Associates Inc., September 2013; Cost and Duration Estimates Adjusted for Refined Phases by Ricondo & Associates Inc. (approximated), URS Corp., December 2013 and U.S. Cost, April 2013. Construction Sequencing (Cont’d) Note: revised from 2018 as shown in PDD by MDAD on June 2014.
  • 31. 31 DRAFT – FOR PRELIMINARY AND PLANNING PURPOSES ONLY 31 Phase 2d (9 mo) Start Year: 2029 Sources: Terminal Construction Sequencing, Ricondo & Associates Inc., September 2013; Cost and Duration Estimates Adjusted for Refined Phases by Ricondo & Associates Inc. (approximated), URS Corp., December 2013 and U.S. Cost, April 2013. Construction Sequencing (Cont’d) Note: revised from 2018 as shown in PDD by MDAD on June 2014.
  • 32. 32 DRAFT – FOR PRELIMINARY AND PLANNING PURPOSES ONLY 32 Phase 2e (6 mo) Start Year: 2030 Sources: Terminal Construction Sequencing, Ricondo & Associates Inc., September 2013; Cost and Duration Estimates Adjusted for Refined Phases by Ricondo & Associates Inc. (approximated), URS Corp., December 2013 and U.S. Cost, April 2013. Construction Sequencing (Cont’d) Note: revised from 2018 as shown in PDD by MDAD on June 2014.
  • 33. 33 DRAFT – FOR PRELIMINARY AND PLANNING PURPOSES ONLY 33 Phase 2f (10 mo) Start Year: 2030 Sources: Terminal Construction Sequencing, Ricondo & Associates Inc., September 2013; Cost and Duration Estimates Adjusted for Refined Phases by Ricondo & Associates Inc. (approximated), URS Corp., December 2013 and U.S. Cost, April 2013. Construction Sequencing (Cont’d) Note: revised from 2018 as shown in PDD by MDAD on June 2014.
  • 34. 34 DRAFT – FOR PRELIMINARY AND PLANNING PURPOSES ONLY 343 Phase 3a (6 mo) Start Year: 2031 Sources: Terminal Construction Sequencing, Ricondo & Associates Inc., September 2013; Cost and Duration Estimates Adjusted for Refined Phases by Ricondo & Associates Inc. (approximated), URS Corp., December 2013 and U.S. Cost, April 2013. Construction Sequencing (Cont’d) Note: revised from 2018 as shown in PDD by MDAD on June 2014.
  • 35. 35 DRAFT – FOR PRELIMINARY AND PLANNING PURPOSES ONLY 353 Phase 3b (5 mo) Start Year: 2032 Sources: Terminal Construction Sequencing, Ricondo & Associates Inc., September 2013; Cost and Duration Estimates Adjusted for Refined Phases by Ricondo & Associates Inc. (approximated), URS Corp., December 2013 and U.S. Cost, April 2013. Construction Sequencing (Cont’d) Note: revised from 2018 as shown in PDD by MDAD on June 2014.
  • 36. 36 DRAFT – FOR PRELIMINARY AND PLANNING PURPOSES ONLY 363 FINAL Year: 2032 Sources: Terminal Construction Sequencing, Ricondo & Associates Inc., September 2013; Cost and Duration Estimates Adjusted for Refined Phases by Ricondo & Associates Inc. (approximated), URS Corp., December 2013 and U.S. Cost, April 2013. Construction Sequencing (Cont’d) Note: revised from 2018 as shown in PDD by MDAD on June 2014.
  • 37. 3737 All years represent the start/commencement of the listed program elements except for the program completion milestone). All durations provided in years (yrs.). Landside Terminal (North) Demolition (1.5 yr.) New Landside Terminal (North) and Super E-Head Construction (4 yrs.) New Super E Connector Construction (1 yr.) Central Terminal Redevelopment Program Completion Concourse G and Landside (South) Terminal Demolition (1 yr.) Super G and New Landside Terminal (South) Construction (3 yrs.) 2020 2021 2024 2026 2028 2031 Lower E Demolition (0.5 yr.) 2032 Concourse F Demolition (0.5 yr.) 2030 Milestone Schedule Sources: Terminal Construction Sequencing, Ricondo & Associates Inc., September 2013; Cost Duration Estimates Adjusted for Refined Phases by Ricondo & Associates Inc. (approximated), URS Corp., December 2013 and U.S. Cost, April 2013. Note: revised from 2018 as shown in PDD by MDAD on June 2014.
  • 38. 38 DRAFT – FOR PRELIMINARY AND PLANNING PURPOSES ONLY 38 80 90 100 110 120 130 140 Gates Central Terminal Sequencing Period Total Gate Capacity Gate Requirements Gate + Spare Requirements Construction Gate Capacity vs Demand Sources: Terminal Construction Sequencing, Ricondo & Associates Inc., September 2013; Cost and Duration Estimates Adjusted for New Phases by Ricondo & Associates Inc. (approximated), URS Corp., December 2013. CentralTerminal ConstructionCommencement 2E EXISTING 0 1A 1B 2A 2B 2C 2F 3A 3B 3C1C 2D Commuter Terminal Demolition Concourse G Demolition Super G Opening D-West Opening E-Head Opening Notes: 1. Some phases may overlap, but it is not shown here for clarity. 2. Upon completion, it is assumed that the Central Terminal is operated as a common use facility to protect the spare gate requirements and accommodate the gate demand. 3. Gate capacity includes considerations for North Terminal enabling projects, See Note 2
  • 40. 40 DRAFT – FOR PRELIMINARY AND PLANNING PURPOSES ONLY 40 Central Terminal Construction Cost Estimates Phase Item Estimated Construction Costs (2012 Dollars) Duration (Months) Projected Start Year Estimated Loaded Costs (2012 Dollars) Escalated and Loaded Costs 0 Build Passenger Connector $52,333,815 24 2016 $71,958,995 $83,420,197 1A Demo Concourse G/ Terminal South $59,767,606 13 2018 $82,180,458 $101,071,598 1B Build Super G/ Terminal South $571,642,669 33 2019 $786,008,670 $995,692,267 1C Apron $5,063,924 2 2022 $6,962,896 $9,357,550 2A Demo Central Terminal North $128,538,929 18 2022 $176,741,027 $244,650,916 2B Build New Central (N) and Super E $1,104,406,734 29 2024 $1,518,559,259 $2,230,055,467 2C Build Super E Connector Building $240,222,745 12 2026 $330,306,275 $499,617,878 2D Demo Concourse E Lower $24,908,421 6 2027 $34,249,079 $53,358,949 2E Apron $16,026,570 10 2027 $22,036,533 $35,362,167 3A Demo Concourse F $22,766,757 6 2028 $31,304,291 $50,234,197 3B Apron $17,497,901 5 2029 $24,059,613 $38,608,616 TOTAL $2,243,176,070 $3,084,367,096 $4,341,429,802 Notes: 1. Total soft costs before escalation assumed to be 37.50%. 2. Escalation is calculated to the mid-point of each phase using a 3% rate, as recommended by U.S. Cost. 3. Excludes costs for proposed triturator, gas station, bus station, NTD and Concourse H gate upgrades and enabling projects, and potential Automated People Mover. Sources: Terminal Construction Sequencing, Ricondo & Associates Inc., September 2013; Cost and Duration Estimates Adjusted for Refined Phases by Ricondo & Associates Inc. (approximated), URS Corp., December 2012 and U.S. Cost, April 2013.
  • 42. 42 DRAFT – FOR PRELIMINARY AND PLANNING PURPOSES ONLY 42 View from North
  • 43. 43 DRAFT – FOR PRELIMINARY AND PLANNING PURPOSES ONLY 43 View from South
  • 44. 44 DRAFT – FOR PRELIMINARY AND PLANNING PURPOSES ONLY 44 Next Steps • MDAD to undertake financial planning for incremental implementation of the Central Terminal Program and other terminal capital projects.