Energy adudit methodology for boiler

ENERGY AUDIT
METHODOLOGY FOR
FOR TURBINE CYCLE
Presented By
M.V.Pande
Dy.Director
NPTI, Nagpur
COAL TO ELECTRICITY PROCESS
STEAM CYCLE FOR 210 MW UNIT
EFFECT OF STEAM PARAMETERS
Effect of Increasing
Steam Temperature
On Available Energy
Effect of Increasing
Pressure on Available
Energy
Effect of Increasing
Steam Pressure &
Temperature Both on
Available Energy
P1
P2
P3
T1
P1
T2
T3
P1
P2
T1
T2
T1
H
S
H
S
S
H
EFFECT OF STEAM PARAMETERS
Effect of Changing Reheat Pressure Effect of Changing Reheat Temp.
S
S
H
H
THERMAL PROCESS LOSSES
Description Effect on Effect on
TG HR KW
1% HPT Efficiency 0.16% 0.3%
1% IPT Efficiency 0.16% 0.16%
1% LPT Efficiency 0.5 % 0.5 %
Impact of Turbine Cylinder Efficiency on
HR/Output
FOLLOW TEST CODES
• ASME PTC - 6 For Steam Turbines
• ASME PTC - 4.1 or BS- 845: 1987 for Boilers
210 MW KWU STEAM TURBINE STEAM & WATER CYCLE
TURBINE CYCLE LOSSES
STEPS INVOLVED IN CONDUCTING THE
TURBINE ENERGY AUDIT
Data collection
Observations and Analysis
Exploration for energy conservation
measures
Report preparation
DATA COLLECTION
Design Specification of turbine and associated equipment:
 Type of the turbine, make and model
 Number of cylinders
 No of stages (for HP, IP and LP)
 No of main and reheat valves
 Construction details of HP, IP LP
 Turbine extraction systems
 Control systems
 Type of governing
 Type of sealing
 Year of installation
 Major modifications carried out during the recent past
DATA COLLECTION
Turbine Cycle Heat Rate Kcal/kwh
DATA COLLECTION
INSTRUMENTS REQUIRED
 Temperature Indicator & Probe
 Pressure gauges
 Flow measuring instrument (steam and
water)
 Ultrasonic leak detector
MEASUREMENTS & OBSERVATIONS TO BE MADE
 Feed water at Inlet & Outlet of Heaters
Main steam parameters
 HP turbine extraction
 Hot reheat steam, Cold reheat Steam
 IP extraction
 IP Exhaust
 Condenser back pressure
 Cooling water flow and temperatures
 Generator output
 Barometric pressure
 Reheater spray (flow)
 Superheater spray (flow)
 Feed water (flow)
Pressure
Temperature
Flow
MEASUREMENTS & OBSERVATIONS TO BE MADE
 Past performance trends on turbine loading,
operation, PLF
 Major constraint in achieving the high PLF, load or
efficiency
 Major renovation and modifications carried out in the
recent past
 Operational failures leading to inefficient operation
 Tripping
 Performance of associated equipment (condenser,
boiler, etc)
 Plant side initiatives to improve the performance and
efficiency of the Turbine
TURBINE HR EVALUATION AND EFFICIENCY
 Turbine heat rate is defined as the heat input (Kcal)
required to generate one unit of Electrical output (KWh). The
trials are to establish heat rate (Kcal/kWh) and turbine
efficiency under, as run conditions have to be carried out
 The efficiency method given in this procedure is the
enthalpy drop efficiency method. This method determines the
ratio of actual enthalpy drop across turbine section to the
isentropic enthalpy drop
 This method provides a good measure for monitoring
purposes. Each section of the turbine must be considered as
a separated turbine
 Each section should be tested and results are trended
separately. While conducting the tests, it has to be ensured
that, it is conducted over normal operating load range
TURBINE HR EVALUATION AND EFFICIENCY
Turbine Cycle Efficiency =
860
Heat Rate
X 100
kW
kCal/hr
Turbine Heat Rate =
Q1
x (H1
– h2
) + Q2
X (H3
– H2
)
Gross Generator Output
TURBINE HR EVALUATION AND EFFICIENCY
Comparison of Actual Expansion
with Isentropic Expansion in
Turbine
Actual Expansion in HP, IP & LP
Cylinder
Actual
Process
1-2-3-4-5
TURBINE HR EVALUATION AND EFFICIENCY
Heat Rate Characteristics with
Condenser Exhaust Pressure
Variation of Heat Rate with Load
TURBINE EFFICIENCY EVALUATION DATA
Kcal/kg/oK
Effect of Condenser Vacuum on
Heat Rate
10 MM HG IMPROVEMENT IN
CONDENSER VACUUM
LEADS TO 20 Kcal/kwh (1%)
IMPROVEMENT IN HEAT RATE FOR A
210 MW UNIT
EFFECT ON HEAT RATE FOR PARAMETER
DEVIATION (500 MW UNIT)
DEVIATION IN PARAMETER EFFECT ON HEAT
RATE (KCAL/KWH)
1. HPT inlet press. by 5.0 ata 6.25
2. HPT inlet temperature by 10.0 deg C 6.0
3. IPT inlet temperature by 10.0 deg C 5.6
4. Condenser pressure by 10.0 mm of Hg 9.0
5. Re spray water quantity by 1.0% 4.0
6. HPT Cylinder efficiency by 1.0% 3.5
7. IPT Cylinder efficiency by 1.0% 4.0
IDENTIFYING FACTORS FOR HR DEVIATION
After evaluating the turbine heat rate and efficiency,
check for the deviation from the design and identify the
factors contributing for the deviations. The major factors
to be looked into are:
 Main steam and reheat steam inlet parameters
 Turbine exhaust steam parameters
 Reheater and super heater spray
 Passing of high energy draining
 Loading on the turbine
 Boiler loading and boiler performance
 Operations and maintenance constraints
IDENTIFYING FACTORS FOR HR DEVIATION
 Condenser performance and cooling water parameters
 Silica deposition and its impact on the turbine efficiency
 Inter stage sealing, balance drum and gland sealing
 Sealing fins clearances
 Nozzle blocks
 Turbine blade erosion
 Functioning of the valves
 Operational status of HP heaters
 Performance of reheaters
FEED WATER HEATERS PERFORMANCE
inlet
inlet
outlet
0 C
FEED WATER HEATERS PERFORMANCE
While collecting the heater wise parameters, collect
the following data:
 Unit load MW
 Main steam pressure, temperature & flow
 Feed water flow
 Super heater & Reheater attemperation flow
 Boiler feed pump discharge pressure
 HP Heater levels
 Condenser vacuum, Barometric pressure
FEED WATER HEATERS PERFORMANCE
After the collecting the above data, evaluate the following
 Terminal temperature difference – TTD
 Heater drain cooler approach temperature difference – DCA
 Feed water temperature rise across heater – TR
TTD = t sat – t fw outlet
FEED WATER HEATERS PERFORMANCE
DCA = t drains – t fw inlet
TR = t outlet – t fw inlet
HEATER PERFORMANCE DEVIATION
Check following if TTD, DCA, TR are deviating from the
design and actual rise in feed water temperature is low:
High terminal temperature difference, TTD
 Excessive venting (worn vents, altered set point, vent
malfunctioning)
 Excessive make up
 High water level (tube leaks, improper setting)
 Header partition leaks
 Non condensable gases on shell side
 Excessive tube bundle pressure drop (excessive number of
tubes plugged, tubes folded internally)
HEATER PERFORMANCE DEVIATION
High drain cooler approach temperature, DCA
 Drain cooler inlet not submerged
 Low drain water level (improper setting, excessive FW
heater drain bypass – bypass valve left open - bypass valve
malfunctioning / leaking)
 Excessive tube bundle pressure drop (excessive number
of tubes plugged / tubes folded internally)
 Feed water heater bypassed
 FW heater bypass valve leaking
Note: Similar approach shall be followed for LP Heaters
ADDITIONAL LOAD ON ECONOMIZER
Based on the above, if the HP heaters performance is poor,
then additional load on economizer can be estimated by using
the data sheet
economizer
Energy adudit methodology for boiler
1 von 33

Recomendados

Air Heater and PF Boiler Performance Indices von
Air Heater and PF Boiler Performance IndicesAir Heater and PF Boiler Performance Indices
Air Heater and PF Boiler Performance IndicesManohar Tatwawadi
4.8K views61 Folien
Heat rate audit in thermal power plant von
Heat rate audit in thermal power plantHeat rate audit in thermal power plant
Heat rate audit in thermal power plantSHIVAJI CHOUDHURY
23.4K views38 Folien
660 mw supercritical boiler von
660 mw supercritical boiler660 mw supercritical boiler
660 mw supercritical boilerAshvani Shukla
18.8K views89 Folien
Turbine cycle heat rate calculation von
Turbine  cycle heat rate calculationTurbine  cycle heat rate calculation
Turbine cycle heat rate calculationSHIVAJI CHOUDHURY
41.1K views22 Folien
210 mw turbine cycle heat rate von
210 mw turbine cycle heat rate210 mw turbine cycle heat rate
210 mw turbine cycle heat rateManohar Tatwawadi
557 views39 Folien
210 mw turbine cycle heat rate von
210 mw turbine cycle heat rate210 mw turbine cycle heat rate
210 mw turbine cycle heat rateManohar Tatwawadi
1.8K views39 Folien

Más contenido relacionado

Was ist angesagt?

Heat rate of coal fired power plant von
Heat rate of coal fired power plantHeat rate of coal fired power plant
Heat rate of coal fired power plantDr. Koteswara Rao Pothala MBA, PMP,FIE
45.1K views10 Folien
TPS EFFICIENCY AND HEAT RATE von
TPS EFFICIENCY AND HEAT RATE TPS EFFICIENCY AND HEAT RATE
TPS EFFICIENCY AND HEAT RATE Manohar Tatwawadi
961 views28 Folien
Combustion in a CFBC Boiler von
Combustion in a CFBC BoilerCombustion in a CFBC Boiler
Combustion in a CFBC BoilerTapash Nag
13.2K views22 Folien
THERMAL POWER PLANT EFFICIENCY AND HEAT RATE von
THERMAL POWER PLANT EFFICIENCY AND HEAT RATETHERMAL POWER PLANT EFFICIENCY AND HEAT RATE
THERMAL POWER PLANT EFFICIENCY AND HEAT RATEManohar Tatwawadi
761 views29 Folien
Cmc philosophy von
Cmc philosophyCmc philosophy
Cmc philosophyvikash kumar upadhyay
901 views48 Folien
Study Of LANCO 2*600 MW Udupi Thermal Power Plant von
Study Of LANCO 2*600 MW Udupi Thermal Power PlantStudy Of LANCO 2*600 MW Udupi Thermal Power Plant
Study Of LANCO 2*600 MW Udupi Thermal Power PlantSUDHEER KUMAR KALYANAM
23.6K views57 Folien

Was ist angesagt?(20)

Combustion in a CFBC Boiler von Tapash Nag
Combustion in a CFBC BoilerCombustion in a CFBC Boiler
Combustion in a CFBC Boiler
Tapash Nag13.2K views
THERMAL POWER PLANT EFFICIENCY AND HEAT RATE von Manohar Tatwawadi
THERMAL POWER PLANT EFFICIENCY AND HEAT RATETHERMAL POWER PLANT EFFICIENCY AND HEAT RATE
THERMAL POWER PLANT EFFICIENCY AND HEAT RATE
Manohar Tatwawadi761 views
Fireball Formation and Combustion of Coal in a Boiler von Zalak Shah
Fireball Formation and Combustion of Coal in a BoilerFireball Formation and Combustion of Coal in a Boiler
Fireball Formation and Combustion of Coal in a Boiler
Zalak Shah2.8K views
Calculation of Turbine Efficiency von Jahanzeb Khan
Calculation of Turbine EfficiencyCalculation of Turbine Efficiency
Calculation of Turbine Efficiency
Jahanzeb Khan15.3K views
Effect of Coal Quality and Performance of Coal pulverisers / Mills von Manohar Tatwawadi
Effect of Coal Quality and Performance of Coal pulverisers / MillsEffect of Coal Quality and Performance of Coal pulverisers / Mills
Effect of Coal Quality and Performance of Coal pulverisers / Mills
Manohar Tatwawadi660 views
Unit lightup synchronisation & shutdown von Ashvani Shukla
Unit lightup synchronisation & shutdownUnit lightup synchronisation & shutdown
Unit lightup synchronisation & shutdown
Ashvani Shukla1.4K views
Performance calculation for feed water heater von SHIVAJI CHOUDHURY
Performance calculation  for feed water heaterPerformance calculation  for feed water heater
Performance calculation for feed water heater
SHIVAJI CHOUDHURY19.8K views
Unit lightup synchronisation & shutdown von Nitin Mahalle
Unit lightup synchronisation & shutdownUnit lightup synchronisation & shutdown
Unit lightup synchronisation & shutdown
Nitin Mahalle15.4K views

Similar a Energy adudit methodology for boiler

ENERGY AUDIT METHODOLOGY FOR TURBINE CYCLE IN A POWER PLANT von
ENERGY AUDIT METHODOLOGY FOR TURBINE CYCLE IN A POWER PLANTENERGY AUDIT METHODOLOGY FOR TURBINE CYCLE IN A POWER PLANT
ENERGY AUDIT METHODOLOGY FOR TURBINE CYCLE IN A POWER PLANTManohar Tatwawadi
450 views33 Folien
Refrigeration and air conditioning system von
Refrigeration and air conditioning systemRefrigeration and air conditioning system
Refrigeration and air conditioning systembikramstalion
2.2K views60 Folien
2003 ASME Power Conference Heat Balance Techniques for Diagnosing and Evaluat... von
2003 ASME Power Conference Heat Balance Techniques for Diagnosing and Evaluat...2003 ASME Power Conference Heat Balance Techniques for Diagnosing and Evaluat...
2003 ASME Power Conference Heat Balance Techniques for Diagnosing and Evaluat...Komandur Sunder Raj, P.E.
322 views43 Folien
Ntpc (national thermal power corporation) sipat boiler haxxo24 i~i von
Ntpc (national thermal power corporation) sipat boiler haxxo24 i~iNtpc (national thermal power corporation) sipat boiler haxxo24 i~i
Ntpc (national thermal power corporation) sipat boiler haxxo24 i~ihaxxo24
15K views88 Folien
SUPER CRITICAL BOILER.pdf von
SUPER CRITICAL BOILER.pdfSUPER CRITICAL BOILER.pdf
SUPER CRITICAL BOILER.pdfVivaanRavi
45 views32 Folien
Super-Critical Boiler.ppt von
Super-Critical Boiler.pptSuper-Critical Boiler.ppt
Super-Critical Boiler.pptMarcWorld
110 views32 Folien

Similar a Energy adudit methodology for boiler(20)

ENERGY AUDIT METHODOLOGY FOR TURBINE CYCLE IN A POWER PLANT von Manohar Tatwawadi
ENERGY AUDIT METHODOLOGY FOR TURBINE CYCLE IN A POWER PLANTENERGY AUDIT METHODOLOGY FOR TURBINE CYCLE IN A POWER PLANT
ENERGY AUDIT METHODOLOGY FOR TURBINE CYCLE IN A POWER PLANT
Manohar Tatwawadi450 views
Refrigeration and air conditioning system von bikramstalion
Refrigeration and air conditioning systemRefrigeration and air conditioning system
Refrigeration and air conditioning system
bikramstalion2.2K views
2003 ASME Power Conference Heat Balance Techniques for Diagnosing and Evaluat... von Komandur Sunder Raj, P.E.
2003 ASME Power Conference Heat Balance Techniques for Diagnosing and Evaluat...2003 ASME Power Conference Heat Balance Techniques for Diagnosing and Evaluat...
2003 ASME Power Conference Heat Balance Techniques for Diagnosing and Evaluat...
Ntpc (national thermal power corporation) sipat boiler haxxo24 i~i von haxxo24
Ntpc (national thermal power corporation) sipat boiler haxxo24 i~iNtpc (national thermal power corporation) sipat boiler haxxo24 i~i
Ntpc (national thermal power corporation) sipat boiler haxxo24 i~i
haxxo2415K views
SUPER CRITICAL BOILER.pdf von VivaanRavi
SUPER CRITICAL BOILER.pdfSUPER CRITICAL BOILER.pdf
SUPER CRITICAL BOILER.pdf
VivaanRavi45 views
Super-Critical Boiler.ppt von MarcWorld
Super-Critical Boiler.pptSuper-Critical Boiler.ppt
Super-Critical Boiler.ppt
MarcWorld110 views
Training presentation von Keyur Patel
Training presentation Training presentation
Training presentation
Keyur Patel1.3K views
Rankine Cycle & How to increase its efficiency von Raja Dolat
Rankine Cycle & How to increase its efficiencyRankine Cycle & How to increase its efficiency
Rankine Cycle & How to increase its efficiency
Raja Dolat9.3K views
2003 ASME Power Conference Performance Evaluation of Feedwater Heaters for Nu... von Komandur Sunder Raj, P.E.
2003 ASME Power Conference Performance Evaluation of Feedwater Heaters for Nu...2003 ASME Power Conference Performance Evaluation of Feedwater Heaters for Nu...
2003 ASME Power Conference Performance Evaluation of Feedwater Heaters for Nu...
Case study Energy Audit for Chiller Plant von Hina Gupta
Case study Energy Audit for Chiller PlantCase study Energy Audit for Chiller Plant
Case study Energy Audit for Chiller Plant
Hina Gupta2K views
Inlet Air Cooling system from Ikeuchi Improve gas Turbine efficiency von H.Ikeuchi & Co.,Ltd
Inlet Air Cooling system from Ikeuchi Improve gas Turbine efficiencyInlet Air Cooling system from Ikeuchi Improve gas Turbine efficiency
Inlet Air Cooling system from Ikeuchi Improve gas Turbine efficiency
Lecture 5.pptx von NelyJay
Lecture 5.pptxLecture 5.pptx
Lecture 5.pptx
NelyJay4 views
EMERSON Power plant applications von mirfanm
EMERSON Power plant applicationsEMERSON Power plant applications
EMERSON Power plant applications
mirfanm2.2K views
Emerson Power plant applications von mirfanm
Emerson Power plant applicationsEmerson Power plant applications
Emerson Power plant applications
mirfanm16.2K views
Feedwater heaters in thermal power plants von SHIVAJI CHOUDHURY
Feedwater heaters in thermal power plantsFeedwater heaters in thermal power plants
Feedwater heaters in thermal power plants
SHIVAJI CHOUDHURY74.1K views
Steam turbine performance & condition assessment (Case Study) von Pichai Chaibamrung
Steam turbine performance & condition assessment (Case Study)Steam turbine performance & condition assessment (Case Study)
Steam turbine performance & condition assessment (Case Study)
Pichai Chaibamrung1.3K views

Último

Integrating Talent Management Practices von
Integrating Talent Management PracticesIntegrating Talent Management Practices
Integrating Talent Management PracticesSeta Wicaksana
157 views29 Folien
HSI CareFree Service Plan 2023 (2).pdf von
HSI CareFree Service Plan 2023 (2).pdfHSI CareFree Service Plan 2023 (2).pdf
HSI CareFree Service Plan 2023 (2).pdfHomeSmart Installations
44 views1 Folie
Monthly Social Media Update November 2023 copy.pptx von
Monthly Social Media Update November 2023 copy.pptxMonthly Social Media Update November 2023 copy.pptx
Monthly Social Media Update November 2023 copy.pptxAndy Lambert
34 views49 Folien
Netflix Inc. von
Netflix Inc.Netflix Inc.
Netflix Inc.125071027
13 views11 Folien
sample.potx von
sample.potxsample.potx
sample.potxMaryna Yurchenko
22 views3 Folien

Último(20)

Integrating Talent Management Practices von Seta Wicaksana
Integrating Talent Management PracticesIntegrating Talent Management Practices
Integrating Talent Management Practices
Seta Wicaksana157 views
Monthly Social Media Update November 2023 copy.pptx von Andy Lambert
Monthly Social Media Update November 2023 copy.pptxMonthly Social Media Update November 2023 copy.pptx
Monthly Social Media Update November 2023 copy.pptx
Andy Lambert34 views
Navigating EUDR Compliance within the Coffee Industry von Peter Horsten
Navigating EUDR Compliance within the Coffee IndustryNavigating EUDR Compliance within the Coffee Industry
Navigating EUDR Compliance within the Coffee Industry
Peter Horsten56 views
Bloomerang Thank Yous Dec 2023.pdf von Bloomerang
Bloomerang Thank Yous Dec 2023.pdfBloomerang Thank Yous Dec 2023.pdf
Bloomerang Thank Yous Dec 2023.pdf
Bloomerang163 views
The Talent Management Navigator Performance Management von Seta Wicaksana
The Talent Management Navigator Performance ManagementThe Talent Management Navigator Performance Management
The Talent Management Navigator Performance Management
Seta Wicaksana37 views
Super Solar Mounting Solutions 20230509(1).pdf von carrie55bradshaw
Super Solar Mounting Solutions 20230509(1).pdfSuper Solar Mounting Solutions 20230509(1).pdf
Super Solar Mounting Solutions 20230509(1).pdf
carrie55bradshaw13 views
Why are KPIs(key performance indicators) important? von Epixel MLM Software
Why are KPIs(key performance indicators) important? Why are KPIs(key performance indicators) important?
Why are KPIs(key performance indicators) important?
Engaging Senior Leaders to Accelerate Your Continuous Improvement Program von KaiNexus
Engaging Senior Leaders to Accelerate Your Continuous Improvement ProgramEngaging Senior Leaders to Accelerate Your Continuous Improvement Program
Engaging Senior Leaders to Accelerate Your Continuous Improvement Program
KaiNexus61 views
Bloomerang_Forecasting Your Fundraising Revenue 2024.pptx.pdf von Bloomerang
Bloomerang_Forecasting Your Fundraising Revenue 2024.pptx.pdfBloomerang_Forecasting Your Fundraising Revenue 2024.pptx.pdf
Bloomerang_Forecasting Your Fundraising Revenue 2024.pptx.pdf
Bloomerang186 views
Amazing Opportunities: PCD Pharma Franchise in Kerala.pptx von SaphnixMedicure1
Amazing Opportunities: PCD Pharma Franchise in Kerala.pptxAmazing Opportunities: PCD Pharma Franchise in Kerala.pptx
Amazing Opportunities: PCD Pharma Franchise in Kerala.pptx
SaphnixMedicure124 views

Energy adudit methodology for boiler

  • 1. ENERGY AUDIT METHODOLOGY FOR FOR TURBINE CYCLE Presented By M.V.Pande Dy.Director NPTI, Nagpur
  • 3. STEAM CYCLE FOR 210 MW UNIT
  • 4. EFFECT OF STEAM PARAMETERS Effect of Increasing Steam Temperature On Available Energy Effect of Increasing Pressure on Available Energy Effect of Increasing Steam Pressure & Temperature Both on Available Energy P1 P2 P3 T1 P1 T2 T3 P1 P2 T1 T2 T1 H S H S S H
  • 5. EFFECT OF STEAM PARAMETERS Effect of Changing Reheat Pressure Effect of Changing Reheat Temp. S S H H
  • 7. Description Effect on Effect on TG HR KW 1% HPT Efficiency 0.16% 0.3% 1% IPT Efficiency 0.16% 0.16% 1% LPT Efficiency 0.5 % 0.5 % Impact of Turbine Cylinder Efficiency on HR/Output FOLLOW TEST CODES • ASME PTC - 6 For Steam Turbines • ASME PTC - 4.1 or BS- 845: 1987 for Boilers
  • 8. 210 MW KWU STEAM TURBINE STEAM & WATER CYCLE
  • 10. STEPS INVOLVED IN CONDUCTING THE TURBINE ENERGY AUDIT Data collection Observations and Analysis Exploration for energy conservation measures Report preparation
  • 11. DATA COLLECTION Design Specification of turbine and associated equipment:  Type of the turbine, make and model  Number of cylinders  No of stages (for HP, IP and LP)  No of main and reheat valves  Construction details of HP, IP LP  Turbine extraction systems  Control systems  Type of governing  Type of sealing  Year of installation  Major modifications carried out during the recent past
  • 12. DATA COLLECTION Turbine Cycle Heat Rate Kcal/kwh
  • 14. INSTRUMENTS REQUIRED  Temperature Indicator & Probe  Pressure gauges  Flow measuring instrument (steam and water)  Ultrasonic leak detector
  • 15. MEASUREMENTS & OBSERVATIONS TO BE MADE  Feed water at Inlet & Outlet of Heaters Main steam parameters  HP turbine extraction  Hot reheat steam, Cold reheat Steam  IP extraction  IP Exhaust  Condenser back pressure  Cooling water flow and temperatures  Generator output  Barometric pressure  Reheater spray (flow)  Superheater spray (flow)  Feed water (flow) Pressure Temperature Flow
  • 16. MEASUREMENTS & OBSERVATIONS TO BE MADE  Past performance trends on turbine loading, operation, PLF  Major constraint in achieving the high PLF, load or efficiency  Major renovation and modifications carried out in the recent past  Operational failures leading to inefficient operation  Tripping  Performance of associated equipment (condenser, boiler, etc)  Plant side initiatives to improve the performance and efficiency of the Turbine
  • 17. TURBINE HR EVALUATION AND EFFICIENCY  Turbine heat rate is defined as the heat input (Kcal) required to generate one unit of Electrical output (KWh). The trials are to establish heat rate (Kcal/kWh) and turbine efficiency under, as run conditions have to be carried out  The efficiency method given in this procedure is the enthalpy drop efficiency method. This method determines the ratio of actual enthalpy drop across turbine section to the isentropic enthalpy drop  This method provides a good measure for monitoring purposes. Each section of the turbine must be considered as a separated turbine  Each section should be tested and results are trended separately. While conducting the tests, it has to be ensured that, it is conducted over normal operating load range
  • 18. TURBINE HR EVALUATION AND EFFICIENCY Turbine Cycle Efficiency = 860 Heat Rate X 100 kW kCal/hr Turbine Heat Rate = Q1 x (H1 – h2 ) + Q2 X (H3 – H2 ) Gross Generator Output
  • 19. TURBINE HR EVALUATION AND EFFICIENCY Comparison of Actual Expansion with Isentropic Expansion in Turbine Actual Expansion in HP, IP & LP Cylinder Actual Process 1-2-3-4-5
  • 20. TURBINE HR EVALUATION AND EFFICIENCY Heat Rate Characteristics with Condenser Exhaust Pressure Variation of Heat Rate with Load
  • 21. TURBINE EFFICIENCY EVALUATION DATA Kcal/kg/oK
  • 22. Effect of Condenser Vacuum on Heat Rate 10 MM HG IMPROVEMENT IN CONDENSER VACUUM LEADS TO 20 Kcal/kwh (1%) IMPROVEMENT IN HEAT RATE FOR A 210 MW UNIT
  • 23. EFFECT ON HEAT RATE FOR PARAMETER DEVIATION (500 MW UNIT) DEVIATION IN PARAMETER EFFECT ON HEAT RATE (KCAL/KWH) 1. HPT inlet press. by 5.0 ata 6.25 2. HPT inlet temperature by 10.0 deg C 6.0 3. IPT inlet temperature by 10.0 deg C 5.6 4. Condenser pressure by 10.0 mm of Hg 9.0 5. Re spray water quantity by 1.0% 4.0 6. HPT Cylinder efficiency by 1.0% 3.5 7. IPT Cylinder efficiency by 1.0% 4.0
  • 24. IDENTIFYING FACTORS FOR HR DEVIATION After evaluating the turbine heat rate and efficiency, check for the deviation from the design and identify the factors contributing for the deviations. The major factors to be looked into are:  Main steam and reheat steam inlet parameters  Turbine exhaust steam parameters  Reheater and super heater spray  Passing of high energy draining  Loading on the turbine  Boiler loading and boiler performance  Operations and maintenance constraints
  • 25. IDENTIFYING FACTORS FOR HR DEVIATION  Condenser performance and cooling water parameters  Silica deposition and its impact on the turbine efficiency  Inter stage sealing, balance drum and gland sealing  Sealing fins clearances  Nozzle blocks  Turbine blade erosion  Functioning of the valves  Operational status of HP heaters  Performance of reheaters
  • 26. FEED WATER HEATERS PERFORMANCE inlet inlet outlet 0 C
  • 27. FEED WATER HEATERS PERFORMANCE While collecting the heater wise parameters, collect the following data:  Unit load MW  Main steam pressure, temperature & flow  Feed water flow  Super heater & Reheater attemperation flow  Boiler feed pump discharge pressure  HP Heater levels  Condenser vacuum, Barometric pressure
  • 28. FEED WATER HEATERS PERFORMANCE After the collecting the above data, evaluate the following  Terminal temperature difference – TTD  Heater drain cooler approach temperature difference – DCA  Feed water temperature rise across heater – TR TTD = t sat – t fw outlet
  • 29. FEED WATER HEATERS PERFORMANCE DCA = t drains – t fw inlet TR = t outlet – t fw inlet
  • 30. HEATER PERFORMANCE DEVIATION Check following if TTD, DCA, TR are deviating from the design and actual rise in feed water temperature is low: High terminal temperature difference, TTD  Excessive venting (worn vents, altered set point, vent malfunctioning)  Excessive make up  High water level (tube leaks, improper setting)  Header partition leaks  Non condensable gases on shell side  Excessive tube bundle pressure drop (excessive number of tubes plugged, tubes folded internally)
  • 31. HEATER PERFORMANCE DEVIATION High drain cooler approach temperature, DCA  Drain cooler inlet not submerged  Low drain water level (improper setting, excessive FW heater drain bypass – bypass valve left open - bypass valve malfunctioning / leaking)  Excessive tube bundle pressure drop (excessive number of tubes plugged / tubes folded internally)  Feed water heater bypassed  FW heater bypass valve leaking Note: Similar approach shall be followed for LP Heaters
  • 32. ADDITIONAL LOAD ON ECONOMIZER Based on the above, if the HP heaters performance is poor, then additional load on economizer can be estimated by using the data sheet economizer