1. Introduction
1.1 Project Description
1.2 Project Background
1.3 Project Objective
1.4 Project Scope
1.5 Success Criteria
2. Specification
2.1 Risk
2.2 Constraints
2.3 Assumptions
2.4 Timescales of the project
3. Project Management Team
3.1 Team Members
3.2 Objective
3.3 Tasks
4. Stakeholders
4.1 Primary Users
4.2 Government and Statutory Authorities
4.3 Other Community and User Groups
5. Budget
5.1 Preliminary Budget Structure
5.2 Exclusions
6. Reference Documents / Sources
6.1 Website
6.2 Meeting Minutes
1. INTRODUCTION
1.1 PROJECT DESCIRPTION
The project is named :" 12AM Cafe Construction Project", involves the construction of a cafe in
Taylor's University Lakeside Campus, Subang Jaya, Selangor, Malaysia. The land has a total
area of 68,797 square meters and it is owned and managed by Taylor's Education Group Sdn Bhd.
The cafe is built especially for the students who stay up late around 12am to 6am. This cafe
provide students a safe place to have a break while doing their assignments or a place to hang out
in this late night. Food and drinks can be prepared and provided for the students.
The cafe is planned to build inside the university land ,a 20m x 20m site area beside the three
academic blocks. It is a small open space area with green grass and some trees surrounding it.
Selected Site:
VIEW FROM FRONT
Selected Site:
VIEW FROM BACK
Site beside the
academic block E
This site has been a plain green area since 2010 without any construction. We have done some
site analysis and found that this site will be our ideal spot for the cafe for the following reason:
1. Ideal location for students from academic blocks
2. Windy area, hence good ventilation
Selected Site:
VIEW FROM SIDE 1
Selected Site:
VIEW FROM SIDE 2
3. Far from the main road, less sound pollution..
4. Good scenery because near the lake
5. Safe for students as it is within campus area.
6. The site is far from the hostel area hence would not disturb other students in the late night.
The agreement of this project brief is estimated to be signed on 29th July 2013 and the whole
construction is estimated to take about 3 months.
1.2 PROJECT BACKGROUND
Taylor's University Lakeside Campus is a Subang Jaya Lake area on the outskirts of Kuala
Lumpur has had many incarnations—first it was a tin mining field, then an illegal dumpsite,
finally it became a squatter occupied by the homeless.
After a major rehabilitation programme, the site has been transformed into an international
school in 2010—Taylor’s Lakeside Campus now sits on the banks of the lake, wrapped closely
around the water’s edge. The university takes advantage of this natural water body, formed
initially by early mining activities, to formulate its environmental strategies and revitalize it into
a key part of the campus
1.3 PROJECT OBJECTIVES:
Improve in the level of service in Taylor's University
Protect the students' safety in the late night
Provide an ideal spot for the students to relax in the midnight
Shorten the distance for the students to get food or drinks at the cafe instead of the
commercial block.
1.4 PROJECT SCOPE
1.5 SUCCESS CRITERIA
The cafe is built within the estimated time.
The cafe is built within the estimated budget.
The cafe is used fully by students who stay up late and recognize it as a new and ideal
place to get food and drinks.
The cafe is now part of the famous spot for late night activity with relaxing atmosphere
and comfortable ambience.
2. SPECIFICATIONS
2.1 RISK
Funding: In case the funding is not enough, the project will be slowed down, postpone or worst,
abandoned.
Approval: The Authority’s approval will really affect the project, in case the Authority do not
give out an approval for the project, the project cannot be carried out.
Failure to attract or retain top talent: If we cannot find the right talent for the construction,
there might be some problems that will be triggered and it might need to take a longer time that
will trigger more problems in the future, e.g. client will lose their interest in the project.
Injury to workers: In case something like this happens, problems will be triggered, e.g. the cost
of the treatment.
2.2 CONSTRAINTS
Pollution: The remnant of the construction materials will pollute the surroundings of the
construction site, during the construction work. The sound of the construction work will disturb
the activity around the construction site and will distribute to a sound pollution.
Safety: The safety around the construction site will be hard to guarantee, the construction
process and materials might endanger the safety of people passing by near the construction site.
2.3 ASSUMPTIONS
The working hours will be from 12:00am – 6:00am.
The customers will be the students that stayed up late.
The staffs are not from the campus students.
Students who usually go out of the campus area to have supper or to get a short break will
choose to stop by this place.
It will help in our campus facilities improvement.
It will help the students who stayed up late to have a place to have a break.
2.4 TIMESCALE FOR PROJECT
3. PROJECT MANAGEMENT TEAM
3.1 TEAM MEMBERS
Key Members Person-in-charge Company Contact Adress
Architect Mr. Edy Phung
Phone: (+60) 12-253-4128
E-mail: green&bold@gmail.com
G&B Sdn. Bhd. Level 3, JalanHua, No.
777, 47500,
Subang Jaya, Selangor
DarulEhsan,
Malaysia.
Landscape Architect Mr. Peh Ker Neng
Phone: (+60) 14-6170502
E-mail: kernengpeh@gmail.com
MajuTECH Landscape
Architecture Firm
8,jln mutiara emas 5/25,
taman perindustrian
mount austin,81100,
johor bahru, johor
Structural Engineer Miss Lee Jo Yee
Phone: (+60) 16-411-5000
E-mail: JadiEC@gmail.com
JADI Engineering
Consultants Sdn. Bhd.
No. 16, Jalan Scotland,
Taman Lumba Kuda,
Georgetown, Pulau
Pinang
Contractor Mr. Nicolas Wong
Phone: (+60) 14-882-8889
Office No: 086-338889
E-mail: nek4real@hotmail.com
Wong Xiao En Berhad No 51A, Tanjung Batu,
Jalan Tun Husseisn Onn,
97000 Bintulu, Sarawak.
Quantity Surveyor Miss Ling Hui Sim SIM Construction
Berhad
No 3,Jalan Taman
Selekoh, Lahad Datu,
Sabah.
3.2 OBJECTIVES
To completely understand the students' needs and plan, design and build a cafe for
the student.
3.3 TASKS
Architect
Observe construction of 12AM-CAFÉ to ensure that site work will meet the
specifications of construction documents when the construction have completed.
Submit modification of the design of 12AM-CAFÉ during construction to contractor.
Adapt a project to real life site conditions, correct errors and remedy omissions to the
construction documents.
Provide an estimate for the cost work of 12AM-CAFÉ. As cost requirements change,
architect has to update and refine cost estimate and share the information with contractor
and owner.
Architect recommends alternative solution to resolve any variations to original budgets.
Conduct an assessment of the site for the owner
Consider the operations and performance of the facilities and make recommendations for
maintenance and improvement.
Landscape Architect
Overseeing the design of a variety of projects, including urban regeneration schemes,
pedestrian schemes, road or retail schemes, and maintaining the character of sites of
natural beauty;
Establishing general landscape requirements with clients;
Conducting preliminary studies of the site (including contours, soil, ecology, buildings,
roads);
Assessing a site's potential to meet the client's specifications;
Carrying out environmental impact assessments;
Seeking and taking into account the views of local residents, potential users, and parties
with a vested interest in the project;
accurately preparing and presenting detailed plans and working drawings, including
applications, construction details and specifications for the project using computer-aided
design (CAD) packages or similar design software;
Presenting proposals to clients, dealing with enquiries and negotiating any amendments
to the final design;
Matching the client's wishes with your knowledge of what will work best;
Contacting and coordinating manufacturers and suppliers;
Putting work out to tender, selecting a contractor and manager (mainly for larger
projects), and leading cross-functional teams;
Making site visits;
Ensuring deadlines are met;
Liaising with other professionals on the project;
Monitoring and checking work on-site (on large projects, landscape managers may do
this type of supervisory work);
Authorising payment once work has been satisfactorily completed;
Attending public inquiries to give evidence if necessary;
Generating new business opportunities.
Structural Engineer
Design structures to withstand stresses & pressures (Do not bend, twist, collapse or
vibrate, remain strong and secure throughout their use.
Choose appropriate materials to meet design specifications
Analysis configurations of the basic structural components of 12AM-CAFÉ
Calculate pressure, stress & strains that each component (beam & lintel) will experience
from other parts of the structure due to human use or environmental pressure.
Liaising with architect to agree an safe designs and fit the aesthetic concept of
construction
Considering the strength of various material
Examining structures at risk of collapse and advising how to improve their structure
integrity
Making drawings, specifications and computer models of structures for building
contractors.
Investigating ground conditions and analysising results of site tests
Applying expert knowledge of the forces that act on various structure
Use computers and computer-aided design (CAD) technology for simulation process.
Contractor
To perform and complete a task that is assigned or created
Checking whether the clients are aware of their duties
Cooperate with other working parties
Consult with the workers in good time
Provide workers under their control with relevant information
Ensure the structure is built as per drawings
Lease with consultants, sub-traders and owner to achieve the common goal of work
being completed on time.
Quantity Surveyor
Preparation of Feasibility Studies
Estimating to define project budgets
Analysis of the effect of design changes on the project budget
Cost planning to refine the budget as the design documents develop
Preparation of Bills of Quantities to assist in the tender process
Provision of cost control services during construction
Assessment of the contractor’s progress claims
Assessment of variation and delay claims
Procurement of subcontractors and labour to carry out specialist trade works
Negotiation and settlement of accounts
Monthly forecasting and cost reporting
Monthly negotiation and agreement of payments for works carried out
Determination of the final project cost
Preparation of tax depreciation reports for investors and property owners
Expert witness reports to assist in the settlement of building disputes
4. STAKEHOLDERS
These are the stakeholders have so far been identified for the project:
4.1 PRIMARY USERS
The students of Taylor's University Lakeside Campus, especially the students from the hostel
and students who stay up late in the educational building block for their assignments, projects or
discussion.
4.2 GOVERNMENT AND STATUTORY AUTHORITIES
4.3 OTHER COMMUNITY AND USER GROUPS
5. BUDGET
5.1 PRELIMINARY BUDGET STRUCTURE
5.2 EXCLUSIONS
6. REFERENCE DOCUMENTS / SOURCES
6.1 WEBSITES
Taylor's University Background:
http://www.futurarc.com/index.cfm/projects-2013/2013-may-jun-taylors-lakeside-campus/
Sample Project Brief:
http://www.hpw.qld.gov.au/SiteCollectionDocuments/CWMFProjectDefinition.pdf
Example of the Timescale of the Project:
http://schoolsonline.swindon.gov.uk/construction_project_procedures_and_timescales
-3.pdf
6.2 MEETING MINUTES

More Related Content

What's hot

Project Management Games and Recreation Documentation Report
Project Management Games and Recreation Documentation ReportProject Management Games and Recreation Documentation Report
Project Management Games and Recreation Documentation ReportKohSungJie
 
Project management report project 1
Project management report project 1Project management report project 1
Project management report project 1Afiq Knick
 
Project management (1)
Project management (1)Project management (1)
Project management (1)aarenneoone
 
Project management in construction
Project management in constructionProject management in construction
Project management in constructionNAVNEET KUMAR JHA
 
Construction contracts docuements_08092008
Construction contracts docuements_08092008Construction contracts docuements_08092008
Construction contracts docuements_08092008AYM1979
 
Project management in construction
Project management in constructionProject management in construction
Project management in constructionNAVNEET KUMAR JHA
 
QUANTITY SURVEYING
QUANTITY SURVEYINGQUANTITY SURVEYING
QUANTITY SURVEYINGlizwi nyandu
 
Project Management (Project 1 - Defining and documenting a project) Presentat...
Project Management (Project 1 - Defining and documenting a project) Presentat...Project Management (Project 1 - Defining and documenting a project) Presentat...
Project Management (Project 1 - Defining and documenting a project) Presentat...Tan Jaden
 
Project Management Project 1 Report: Defining & Documenting A Project
Project Management Project 1 Report: Defining & Documenting A ProjectProject Management Project 1 Report: Defining & Documenting A Project
Project Management Project 1 Report: Defining & Documenting A ProjectNekumi Kida
 
Project Construction of 5 star hotel
Project Construction of 5 star hotelProject Construction of 5 star hotel
Project Construction of 5 star hotelMuhammad Farhan Javed
 
project on construction of house report.
project on construction of house report.project on construction of house report.
project on construction of house report.Hagi Sahib
 
Project management for engineers and architects
Project management for engineers and architectsProject management for engineers and architects
Project management for engineers and architectsCarla Fair-Wright
 
Construction Project Management
Construction Project Management Construction Project Management
Construction Project Management Rajat Nainwal
 
Thesis Defense Presentation
Thesis Defense PresentationThesis Defense Presentation
Thesis Defense PresentationDelesia Hill
 
Project Management - Recreation District in Taylor's University Subang Jaya
Project Management - Recreation District in Taylor's University Subang JayaProject Management - Recreation District in Taylor's University Subang Jaya
Project Management - Recreation District in Taylor's University Subang JayaJoe Onn Lim
 
Risk & Risk Management in Construction.ppt
Risk & Risk Management in Construction.pptRisk & Risk Management in Construction.ppt
Risk & Risk Management in Construction.pptTouqeer1
 
Construction Project Management
Construction Project ManagementConstruction Project Management
Construction Project ManagementAravind Samala
 
Architecture and town planning _Unit 1_SPPU_Principles, elements, Qualities a...
Architecture and town planning _Unit 1_SPPU_Principles, elements, Qualities a...Architecture and town planning _Unit 1_SPPU_Principles, elements, Qualities a...
Architecture and town planning _Unit 1_SPPU_Principles, elements, Qualities a...Shrikant Kate
 

What's hot (20)

Project Management Games and Recreation Documentation Report
Project Management Games and Recreation Documentation ReportProject Management Games and Recreation Documentation Report
Project Management Games and Recreation Documentation Report
 
Project management report project 1
Project management report project 1Project management report project 1
Project management report project 1
 
Project management (1)
Project management (1)Project management (1)
Project management (1)
 
Project management in construction
Project management in constructionProject management in construction
Project management in construction
 
Contracts and-tenders
Contracts and-tendersContracts and-tenders
Contracts and-tenders
 
Construction contracts docuements_08092008
Construction contracts docuements_08092008Construction contracts docuements_08092008
Construction contracts docuements_08092008
 
Project management in construction
Project management in constructionProject management in construction
Project management in construction
 
QUANTITY SURVEYING
QUANTITY SURVEYINGQUANTITY SURVEYING
QUANTITY SURVEYING
 
Project Management (Project 1 - Defining and documenting a project) Presentat...
Project Management (Project 1 - Defining and documenting a project) Presentat...Project Management (Project 1 - Defining and documenting a project) Presentat...
Project Management (Project 1 - Defining and documenting a project) Presentat...
 
Project Management Project 1 Report: Defining & Documenting A Project
Project Management Project 1 Report: Defining & Documenting A ProjectProject Management Project 1 Report: Defining & Documenting A Project
Project Management Project 1 Report: Defining & Documenting A Project
 
Project Construction of 5 star hotel
Project Construction of 5 star hotelProject Construction of 5 star hotel
Project Construction of 5 star hotel
 
project on construction of house report.
project on construction of house report.project on construction of house report.
project on construction of house report.
 
Project management for engineers and architects
Project management for engineers and architectsProject management for engineers and architects
Project management for engineers and architects
 
Construction Project Management
Construction Project Management Construction Project Management
Construction Project Management
 
Thesis Defense Presentation
Thesis Defense PresentationThesis Defense Presentation
Thesis Defense Presentation
 
Project Management - Recreation District in Taylor's University Subang Jaya
Project Management - Recreation District in Taylor's University Subang JayaProject Management - Recreation District in Taylor's University Subang Jaya
Project Management - Recreation District in Taylor's University Subang Jaya
 
Risk & Risk Management in Construction.ppt
Risk & Risk Management in Construction.pptRisk & Risk Management in Construction.ppt
Risk & Risk Management in Construction.ppt
 
Procurement Methods
Procurement MethodsProcurement Methods
Procurement Methods
 
Construction Project Management
Construction Project ManagementConstruction Project Management
Construction Project Management
 
Architecture and town planning _Unit 1_SPPU_Principles, elements, Qualities a...
Architecture and town planning _Unit 1_SPPU_Principles, elements, Qualities a...Architecture and town planning _Unit 1_SPPU_Principles, elements, Qualities a...
Architecture and town planning _Unit 1_SPPU_Principles, elements, Qualities a...
 

Viewers also liked

Briefing Checklist for Advisers on Construction Projects
Briefing Checklist for Advisers on Construction ProjectsBriefing Checklist for Advisers on Construction Projects
Briefing Checklist for Advisers on Construction ProjectsSarah Fox
 
The Manhattanville Student Center Pavilion
The Manhattanville Student Center PavilionThe Manhattanville Student Center Pavilion
The Manhattanville Student Center Paviliontirellig
 
Project brief 2 b construction 2 march 2016 1
Project brief 2 b construction 2 march 2016 1Project brief 2 b construction 2 march 2016 1
Project brief 2 b construction 2 march 2016 1Chow Hong Da
 
Studio 4 arc60206 module outline (august 2015)
Studio 4 arc60206 module outline (august 2015)Studio 4 arc60206 module outline (august 2015)
Studio 4 arc60206 module outline (august 2015)Anthony Chew
 
Studio project 1 brief (1)
Studio project 1 brief (1)Studio project 1 brief (1)
Studio project 1 brief (1)Chow Hong Da
 
B sc(hons)(arch) architecture studio 3 arc60106 project 2_brief_mar 2016
B sc(hons)(arch) architecture studio 3 arc60106 project 2_brief_mar 2016B sc(hons)(arch) architecture studio 3 arc60106 project 2_brief_mar 2016
B sc(hons)(arch) architecture studio 3 arc60106 project 2_brief_mar 2016Chow Hong Da
 
NITIE Center for Student Enterprises .. What it does !
NITIE Center for Student Enterprises  .. What it does ! NITIE Center for Student Enterprises  .. What it does !
NITIE Center for Student Enterprises .. What it does ! drmandi
 
Project 2 brief architecture studio 4 arc60206 august 2015 (1)
Project 2 brief  architecture studio 4 arc60206 august 2015 (1)Project 2 brief  architecture studio 4 arc60206 august 2015 (1)
Project 2 brief architecture studio 4 arc60206 august 2015 (1)Anthony Chew
 
ICI Project 3 - The Project Brief
ICI Project 3 - The Project BriefICI Project 3 - The Project Brief
ICI Project 3 - The Project BriefRyan Kerry Jy
 
EPC Final presentation project brief
EPC Final presentation project briefEPC Final presentation project brief
EPC Final presentation project briefashleyyeap
 
Project brief 1 architecture studio 4 august2015
Project brief 1 architecture studio 4 august2015Project brief 1 architecture studio 4 august2015
Project brief 1 architecture studio 4 august2015Anthony Chew
 
SEC (Student Employment Center)
SEC (Student Employment Center)SEC (Student Employment Center)
SEC (Student Employment Center)Artyom Lakhov
 
ENBE - Experiencing Nature
ENBE - Experiencing NatureENBE - Experiencing Nature
ENBE - Experiencing NatureJ-Sern Phua
 
Center for Student Activities & Leadership Development
Center for Student Activities & Leadership DevelopmentCenter for Student Activities & Leadership Development
Center for Student Activities & Leadership DevelopmentScott Millington
 
Project REO: A Student Center Initiative
Project REO: A Student Center InitiativeProject REO: A Student Center Initiative
Project REO: A Student Center Initiativedmatth22
 

Viewers also liked (19)

Briefing Checklist for Advisers on Construction Projects
Briefing Checklist for Advisers on Construction ProjectsBriefing Checklist for Advisers on Construction Projects
Briefing Checklist for Advisers on Construction Projects
 
The Manhattanville Student Center Pavilion
The Manhattanville Student Center PavilionThe Manhattanville Student Center Pavilion
The Manhattanville Student Center Pavilion
 
Project brief 2 b construction 2 march 2016 1
Project brief 2 b construction 2 march 2016 1Project brief 2 b construction 2 march 2016 1
Project brief 2 b construction 2 march 2016 1
 
Studio 4 arc60206 module outline (august 2015)
Studio 4 arc60206 module outline (august 2015)Studio 4 arc60206 module outline (august 2015)
Studio 4 arc60206 module outline (august 2015)
 
The Hive
The HiveThe Hive
The Hive
 
Studio project 1 brief (1)
Studio project 1 brief (1)Studio project 1 brief (1)
Studio project 1 brief (1)
 
B sc(hons)(arch) architecture studio 3 arc60106 project 2_brief_mar 2016
B sc(hons)(arch) architecture studio 3 arc60106 project 2_brief_mar 2016B sc(hons)(arch) architecture studio 3 arc60106 project 2_brief_mar 2016
B sc(hons)(arch) architecture studio 3 arc60106 project 2_brief_mar 2016
 
Baku Mall Project yeni
Baku Mall Project yeniBaku Mall Project yeni
Baku Mall Project yeni
 
NITIE Center for Student Enterprises .. What it does !
NITIE Center for Student Enterprises  .. What it does ! NITIE Center for Student Enterprises  .. What it does !
NITIE Center for Student Enterprises .. What it does !
 
Project 2 brief architecture studio 4 arc60206 august 2015 (1)
Project 2 brief  architecture studio 4 arc60206 august 2015 (1)Project 2 brief  architecture studio 4 arc60206 august 2015 (1)
Project 2 brief architecture studio 4 arc60206 august 2015 (1)
 
ICI Project 3 - The Project Brief
ICI Project 3 - The Project BriefICI Project 3 - The Project Brief
ICI Project 3 - The Project Brief
 
EPC Final presentation project brief
EPC Final presentation project briefEPC Final presentation project brief
EPC Final presentation project brief
 
Project brief 1 architecture studio 4 august2015
Project brief 1 architecture studio 4 august2015Project brief 1 architecture studio 4 august2015
Project brief 1 architecture studio 4 august2015
 
SEC (Student Employment Center)
SEC (Student Employment Center)SEC (Student Employment Center)
SEC (Student Employment Center)
 
ENBE - Experiencing Nature
ENBE - Experiencing NatureENBE - Experiencing Nature
ENBE - Experiencing Nature
 
Project brief
Project briefProject brief
Project brief
 
Center for Student Activities & Leadership Development
Center for Student Activities & Leadership DevelopmentCenter for Student Activities & Leadership Development
Center for Student Activities & Leadership Development
 
Construction safety management
Construction safety managementConstruction safety management
Construction safety management
 
Project REO: A Student Center Initiative
Project REO: A Student Center InitiativeProject REO: A Student Center Initiative
Project REO: A Student Center Initiative
 

Similar to Project brief

Project background (1)(1)
Project background (1)(1)Project background (1)(1)
Project background (1)(1)JamesMoy7
 
The Project Brief(group)
The Project Brief(group)The Project Brief(group)
The Project Brief(group)Pinky Chan
 
Latest project background 1
Latest project background 1Latest project background 1
Latest project background 1JamesMoy7
 
Ici project brief2
Ici project brief2Ici project brief2
Ici project brief2itsmylifesl
 
Project brief
Project brief Project brief
Project brief PK146
 
Project Management.Project 1
Project Management.Project 1Project Management.Project 1
Project Management.Project 1suzzanekan
 
Ici final project
Ici final projectIci final project
Ici final project温 庄壁
 
ici final project.pdf
ici final project.pdfici final project.pdf
ici final project.pdf温 庄壁
 
ICI final project
ICI final projectICI final project
ICI final projectLY97
 
RUNNINGHEADERCOFFEESHOPPROJECT1Quintessential’s Coffee Shop.docx
RUNNINGHEADERCOFFEESHOPPROJECT1Quintessential’s Coffee Shop.docxRUNNINGHEADERCOFFEESHOPPROJECT1Quintessential’s Coffee Shop.docx
RUNNINGHEADERCOFFEESHOPPROJECT1Quintessential’s Coffee Shop.docxagnesdcarey33086
 
Building project presentation
Building project presentationBuilding project presentation
Building project presentationemdad bhuiyan
 
Project management (1)
Project management (1)Project management (1)
Project management (1)Hetal Visaria
 
Ici final-individual-loon-jing-wei
Ici final-individual-loon-jing-weiIci final-individual-loon-jing-wei
Ici final-individual-loon-jing-weiRoy Loon
 

Similar to Project brief (20)

Project background (1)(1)
Project background (1)(1)Project background (1)(1)
Project background (1)(1)
 
Project background
Project backgroundProject background
Project background
 
The Project Brief(group)
The Project Brief(group)The Project Brief(group)
The Project Brief(group)
 
ICIP2G
ICIP2GICIP2G
ICIP2G
 
Latest project background 1
Latest project background 1Latest project background 1
Latest project background 1
 
Group Component
Group ComponentGroup Component
Group Component
 
Ici project brief2
Ici project brief2Ici project brief2
Ici project brief2
 
Project brief
Project brief Project brief
Project brief
 
Project Name
 Project Name                                       Project Name
Project Name
 
Project Management.Project 1
Project Management.Project 1Project Management.Project 1
Project Management.Project 1
 
Ici final project
Ici final projectIci final project
Ici final project
 
ici final project.pdf
ici final project.pdfici final project.pdf
ici final project.pdf
 
ICI final project
ICI final projectICI final project
ICI final project
 
RUNNINGHEADERCOFFEESHOPPROJECT1Quintessential’s Coffee Shop.docx
RUNNINGHEADERCOFFEESHOPPROJECT1Quintessential’s Coffee Shop.docxRUNNINGHEADERCOFFEESHOPPROJECT1Quintessential’s Coffee Shop.docx
RUNNINGHEADERCOFFEESHOPPROJECT1Quintessential’s Coffee Shop.docx
 
Student Project
Student ProjectStudent Project
Student Project
 
Building project presentation
Building project presentationBuilding project presentation
Building project presentation
 
Project
Project Project
Project
 
Project management (1)
Project management (1)Project management (1)
Project management (1)
 
Ici final-individual-loon-jing-wei
Ici final-individual-loon-jing-weiIci final-individual-loon-jing-wei
Ici final-individual-loon-jing-wei
 
Ici individual
Ici individualIci individual
Ici individual
 

More from kerneng

Project management networking
Project management networkingProject management networking
Project management networkingkerneng
 
Final site analysis board
Final site analysis boardFinal site analysis board
Final site analysis boardkerneng
 
Merged document
Merged documentMerged document
Merged documentkerneng
 
Bscience report
Bscience reportBscience report
Bscience reportkerneng
 
Bscience board
Bscience boardBscience board
Bscience boardkerneng
 
Final bscience report compilation
Final bscience report compilationFinal bscience report compilation
Final bscience report compilationkerneng
 
C1 (3 files merged)
C1 (3 files merged)C1 (3 files merged)
C1 (3 files merged)kerneng
 
Sec 1 (5 files merged) (1)
Sec 1 (5 files merged) (1)Sec 1 (5 files merged) (1)
Sec 1 (5 files merged) (1)kerneng
 
Plan 1 (6 files merged)
Plan 1 (6 files merged)Plan 1 (6 files merged)
Plan 1 (6 files merged)kerneng
 
E1 (3 files merged)
E1 (3 files merged)E1 (3 files merged)
E1 (3 files merged)kerneng
 
Ph 4 (9 files merged)
Ph 4 (9 files merged)Ph 4 (9 files merged)
Ph 4 (9 files merged)kerneng
 
I1 (4 files merged)
I1 (4 files merged)I1 (4 files merged)
I1 (4 files merged)kerneng
 
1 (4 files merged) (1)
1 (4 files merged) (1)1 (4 files merged) (1)
1 (4 files merged) (1)kerneng
 
Theory project-2-analytical-paper
Theory project-2-analytical-paperTheory project-2-analytical-paper
Theory project-2-analytical-paperkerneng
 
5 elements-kerneng
5 elements-kerneng5 elements-kerneng
5 elements-kernengkerneng
 
R1 (5 files merged)
R1 (5 files merged)R1 (5 files merged)
R1 (5 files merged)kerneng
 

More from kerneng (20)

Project management networking
Project management networkingProject management networking
Project management networking
 
Final
FinalFinal
Final
 
btech 2
btech 2btech 2
btech 2
 
Final site analysis board
Final site analysis boardFinal site analysis board
Final site analysis board
 
Merged document
Merged documentMerged document
Merged document
 
Btech
BtechBtech
Btech
 
Images
ImagesImages
Images
 
Bscience report
Bscience reportBscience report
Bscience report
 
Bscience board
Bscience boardBscience board
Bscience board
 
Final bscience report compilation
Final bscience report compilationFinal bscience report compilation
Final bscience report compilation
 
C1 (3 files merged)
C1 (3 files merged)C1 (3 files merged)
C1 (3 files merged)
 
Sec 1 (5 files merged) (1)
Sec 1 (5 files merged) (1)Sec 1 (5 files merged) (1)
Sec 1 (5 files merged) (1)
 
Plan 1 (6 files merged)
Plan 1 (6 files merged)Plan 1 (6 files merged)
Plan 1 (6 files merged)
 
E1 (3 files merged)
E1 (3 files merged)E1 (3 files merged)
E1 (3 files merged)
 
Ph 4 (9 files merged)
Ph 4 (9 files merged)Ph 4 (9 files merged)
Ph 4 (9 files merged)
 
I1 (4 files merged)
I1 (4 files merged)I1 (4 files merged)
I1 (4 files merged)
 
1 (4 files merged) (1)
1 (4 files merged) (1)1 (4 files merged) (1)
1 (4 files merged) (1)
 
Theory project-2-analytical-paper
Theory project-2-analytical-paperTheory project-2-analytical-paper
Theory project-2-analytical-paper
 
5 elements-kerneng
5 elements-kerneng5 elements-kerneng
5 elements-kerneng
 
R1 (5 files merged)
R1 (5 files merged)R1 (5 files merged)
R1 (5 files merged)
 

Recently uploaded

Mental Health Issues of Graduate Students
Mental Health Issues of Graduate StudentsMental Health Issues of Graduate Students
Mental Health Issues of Graduate Studentsvineshkumarsajnani12
 
Mastering The Art Of 'Closing The Sale'.
Mastering The Art Of 'Closing The Sale'.Mastering The Art Of 'Closing The Sale'.
Mastering The Art Of 'Closing The Sale'.SNSW group8
 
Thompson_Taylor_MBBS_PB1_2024-03 (1)- Project & Portfolio 2.pptx
Thompson_Taylor_MBBS_PB1_2024-03 (1)- Project & Portfolio 2.pptxThompson_Taylor_MBBS_PB1_2024-03 (1)- Project & Portfolio 2.pptx
Thompson_Taylor_MBBS_PB1_2024-03 (1)- Project & Portfolio 2.pptxtmthompson1
 
Elevate Your Online Presence with SEO Services
Elevate Your Online Presence with SEO ServicesElevate Your Online Presence with SEO Services
Elevate Your Online Presence with SEO ServicesHaseebBashir5
 
obat aborsi bandung wa 081336238223 jual obat aborsi cytotec asli di bandung9...
obat aborsi bandung wa 081336238223 jual obat aborsi cytotec asli di bandung9...obat aborsi bandung wa 081336238223 jual obat aborsi cytotec asli di bandung9...
obat aborsi bandung wa 081336238223 jual obat aborsi cytotec asli di bandung9...yulianti213969
 
SCI9-Q4-MOD9.pdfetiwtitw3i3uu45w5wtitwjt
SCI9-Q4-MOD9.pdfetiwtitw3i3uu45w5wtitwjtSCI9-Q4-MOD9.pdfetiwtitw3i3uu45w5wtitwjt
SCI9-Q4-MOD9.pdfetiwtitw3i3uu45w5wtitwjtadimosmejiaslendon
 
The Vietnam Believer Newsletter_May 13th, 2024_ENVol. 007.pdf
The Vietnam Believer Newsletter_May 13th, 2024_ENVol. 007.pdfThe Vietnam Believer Newsletter_May 13th, 2024_ENVol. 007.pdf
The Vietnam Believer Newsletter_May 13th, 2024_ENVol. 007.pdfbelieveminhh
 
The Art of Decision-Making: Navigating Complexity and Uncertainty
The Art of Decision-Making: Navigating Complexity and UncertaintyThe Art of Decision-Making: Navigating Complexity and Uncertainty
The Art of Decision-Making: Navigating Complexity and Uncertaintycapivisgroup
 
What are the differences between an international company, a global company, ...
What are the differences between an international company, a global company, ...What are the differences between an international company, a global company, ...
What are the differences between an international company, a global company, ...AbhishekSharma823325
 
Navigating Tax Season with Confidence Streamlines CPA Firms
Navigating Tax Season with Confidence Streamlines CPA FirmsNavigating Tax Season with Confidence Streamlines CPA Firms
Navigating Tax Season with Confidence Streamlines CPA FirmsYourLegal Accounting
 
如何办理(SUT毕业证书)斯威本科技大学毕业证成绩单本科硕士学位证留信学历认证
如何办理(SUT毕业证书)斯威本科技大学毕业证成绩单本科硕士学位证留信学历认证如何办理(SUT毕业证书)斯威本科技大学毕业证成绩单本科硕士学位证留信学历认证
如何办理(SUT毕业证书)斯威本科技大学毕业证成绩单本科硕士学位证留信学历认证ogawka
 
Unlocking Growth The Power of Outsourcing for CPA Firms
Unlocking Growth The Power of Outsourcing for CPA FirmsUnlocking Growth The Power of Outsourcing for CPA Firms
Unlocking Growth The Power of Outsourcing for CPA FirmsYourLegal Accounting
 
A DAY IN LIFE OF A NEGOTIATOR By Pondicherry University MBA Students.pptx
A DAY IN LIFE OF A NEGOTIATOR By Pondicherry University MBA Students.pptxA DAY IN LIFE OF A NEGOTIATOR By Pondicherry University MBA Students.pptx
A DAY IN LIFE OF A NEGOTIATOR By Pondicherry University MBA Students.pptxLokeshwariOrchid1
 
A BUSINESS PROPOSAL FOR SLAUGHTER HOUSE WASTE MANAGEMENT IN MYSORE MUNICIPAL ...
A BUSINESS PROPOSAL FOR SLAUGHTER HOUSE WASTE MANAGEMENT IN MYSORE MUNICIPAL ...A BUSINESS PROPOSAL FOR SLAUGHTER HOUSE WASTE MANAGEMENT IN MYSORE MUNICIPAL ...
A BUSINESS PROPOSAL FOR SLAUGHTER HOUSE WASTE MANAGEMENT IN MYSORE MUNICIPAL ...prakheeshc
 

Recently uploaded (20)

Obat Aborsi Malang 0851\7696\3835 Jual Obat Cytotec Di Malang
Obat Aborsi Malang 0851\7696\3835 Jual Obat Cytotec Di MalangObat Aborsi Malang 0851\7696\3835 Jual Obat Cytotec Di Malang
Obat Aborsi Malang 0851\7696\3835 Jual Obat Cytotec Di Malang
 
Obat Aborsi Surabaya 0851\7696\3835 Jual Obat Cytotec Di Surabaya
Obat Aborsi Surabaya 0851\7696\3835 Jual Obat Cytotec Di SurabayaObat Aborsi Surabaya 0851\7696\3835 Jual Obat Cytotec Di Surabaya
Obat Aborsi Surabaya 0851\7696\3835 Jual Obat Cytotec Di Surabaya
 
WAM Corporate Presentation May 2024_w.pdf
WAM Corporate Presentation May 2024_w.pdfWAM Corporate Presentation May 2024_w.pdf
WAM Corporate Presentation May 2024_w.pdf
 
Home Furnishings Ecommerce Platform Short Pitch 2024
Home Furnishings Ecommerce Platform Short Pitch 2024Home Furnishings Ecommerce Platform Short Pitch 2024
Home Furnishings Ecommerce Platform Short Pitch 2024
 
WheelTug Short Pitch Deck 2024 | Byond Insights
WheelTug Short Pitch Deck 2024 | Byond InsightsWheelTug Short Pitch Deck 2024 | Byond Insights
WheelTug Short Pitch Deck 2024 | Byond Insights
 
Contact +971581248768 for 100% original and safe abortion pills available for...
Contact +971581248768 for 100% original and safe abortion pills available for...Contact +971581248768 for 100% original and safe abortion pills available for...
Contact +971581248768 for 100% original and safe abortion pills available for...
 
Mental Health Issues of Graduate Students
Mental Health Issues of Graduate StudentsMental Health Issues of Graduate Students
Mental Health Issues of Graduate Students
 
Mastering The Art Of 'Closing The Sale'.
Mastering The Art Of 'Closing The Sale'.Mastering The Art Of 'Closing The Sale'.
Mastering The Art Of 'Closing The Sale'.
 
Thompson_Taylor_MBBS_PB1_2024-03 (1)- Project & Portfolio 2.pptx
Thompson_Taylor_MBBS_PB1_2024-03 (1)- Project & Portfolio 2.pptxThompson_Taylor_MBBS_PB1_2024-03 (1)- Project & Portfolio 2.pptx
Thompson_Taylor_MBBS_PB1_2024-03 (1)- Project & Portfolio 2.pptx
 
Elevate Your Online Presence with SEO Services
Elevate Your Online Presence with SEO ServicesElevate Your Online Presence with SEO Services
Elevate Your Online Presence with SEO Services
 
obat aborsi bandung wa 081336238223 jual obat aborsi cytotec asli di bandung9...
obat aborsi bandung wa 081336238223 jual obat aborsi cytotec asli di bandung9...obat aborsi bandung wa 081336238223 jual obat aborsi cytotec asli di bandung9...
obat aborsi bandung wa 081336238223 jual obat aborsi cytotec asli di bandung9...
 
SCI9-Q4-MOD9.pdfetiwtitw3i3uu45w5wtitwjt
SCI9-Q4-MOD9.pdfetiwtitw3i3uu45w5wtitwjtSCI9-Q4-MOD9.pdfetiwtitw3i3uu45w5wtitwjt
SCI9-Q4-MOD9.pdfetiwtitw3i3uu45w5wtitwjt
 
The Vietnam Believer Newsletter_May 13th, 2024_ENVol. 007.pdf
The Vietnam Believer Newsletter_May 13th, 2024_ENVol. 007.pdfThe Vietnam Believer Newsletter_May 13th, 2024_ENVol. 007.pdf
The Vietnam Believer Newsletter_May 13th, 2024_ENVol. 007.pdf
 
The Art of Decision-Making: Navigating Complexity and Uncertainty
The Art of Decision-Making: Navigating Complexity and UncertaintyThe Art of Decision-Making: Navigating Complexity and Uncertainty
The Art of Decision-Making: Navigating Complexity and Uncertainty
 
What are the differences between an international company, a global company, ...
What are the differences between an international company, a global company, ...What are the differences between an international company, a global company, ...
What are the differences between an international company, a global company, ...
 
Navigating Tax Season with Confidence Streamlines CPA Firms
Navigating Tax Season with Confidence Streamlines CPA FirmsNavigating Tax Season with Confidence Streamlines CPA Firms
Navigating Tax Season with Confidence Streamlines CPA Firms
 
如何办理(SUT毕业证书)斯威本科技大学毕业证成绩单本科硕士学位证留信学历认证
如何办理(SUT毕业证书)斯威本科技大学毕业证成绩单本科硕士学位证留信学历认证如何办理(SUT毕业证书)斯威本科技大学毕业证成绩单本科硕士学位证留信学历认证
如何办理(SUT毕业证书)斯威本科技大学毕业证成绩单本科硕士学位证留信学历认证
 
Unlocking Growth The Power of Outsourcing for CPA Firms
Unlocking Growth The Power of Outsourcing for CPA FirmsUnlocking Growth The Power of Outsourcing for CPA Firms
Unlocking Growth The Power of Outsourcing for CPA Firms
 
A DAY IN LIFE OF A NEGOTIATOR By Pondicherry University MBA Students.pptx
A DAY IN LIFE OF A NEGOTIATOR By Pondicherry University MBA Students.pptxA DAY IN LIFE OF A NEGOTIATOR By Pondicherry University MBA Students.pptx
A DAY IN LIFE OF A NEGOTIATOR By Pondicherry University MBA Students.pptx
 
A BUSINESS PROPOSAL FOR SLAUGHTER HOUSE WASTE MANAGEMENT IN MYSORE MUNICIPAL ...
A BUSINESS PROPOSAL FOR SLAUGHTER HOUSE WASTE MANAGEMENT IN MYSORE MUNICIPAL ...A BUSINESS PROPOSAL FOR SLAUGHTER HOUSE WASTE MANAGEMENT IN MYSORE MUNICIPAL ...
A BUSINESS PROPOSAL FOR SLAUGHTER HOUSE WASTE MANAGEMENT IN MYSORE MUNICIPAL ...
 

Project brief

  • 1. PROJECT BRIEF For the Construction of 12AM Cafe Taylor's University Lakeside Campus, Subang Jaya, Selangor, Malaysia Prepared by Taylor's Students 24th June 2013 Revision 1.1
  • 2. Contents 1. Introduction 1.1 Project Description 1.2 Project Background 1.3 Project Objective 1.4 Project Scope 1.5 Success Criteria 2. Specification 2.1 Risk 2.2 Constraints 2.3 Assumptions 2.4 Timescales of the project 3. Project Management Team 3.1 Team Members 3.2 Objective 3.3 Tasks 4. Stakeholders 4.1 Primary Users 4.2 Government and Statutory Authorities 4.3 Other Community and User Groups 5. Budget 5.1 Preliminary Budget Structure 5.2 Exclusions 6. Reference Documents / Sources
  • 4. 1. INTRODUCTION 1.1 PROJECT DESCIRPTION The project is named :" 12AM Cafe Construction Project", involves the construction of a cafe in Taylor's University Lakeside Campus, Subang Jaya, Selangor, Malaysia. The land has a total area of 68,797 square meters and it is owned and managed by Taylor's Education Group Sdn Bhd. The cafe is built especially for the students who stay up late around 12am to 6am. This cafe provide students a safe place to have a break while doing their assignments or a place to hang out in this late night. Food and drinks can be prepared and provided for the students. The cafe is planned to build inside the university land ,a 20m x 20m site area beside the three academic blocks. It is a small open space area with green grass and some trees surrounding it. Selected Site: VIEW FROM FRONT Selected Site: VIEW FROM BACK
  • 6. This site has been a plain green area since 2010 without any construction. We have done some site analysis and found that this site will be our ideal spot for the cafe for the following reason: 1. Ideal location for students from academic blocks 2. Windy area, hence good ventilation Selected Site: VIEW FROM SIDE 1 Selected Site: VIEW FROM SIDE 2
  • 7. 3. Far from the main road, less sound pollution.. 4. Good scenery because near the lake 5. Safe for students as it is within campus area. 6. The site is far from the hostel area hence would not disturb other students in the late night. The agreement of this project brief is estimated to be signed on 29th July 2013 and the whole construction is estimated to take about 3 months. 1.2 PROJECT BACKGROUND Taylor's University Lakeside Campus is a Subang Jaya Lake area on the outskirts of Kuala Lumpur has had many incarnations—first it was a tin mining field, then an illegal dumpsite, finally it became a squatter occupied by the homeless. After a major rehabilitation programme, the site has been transformed into an international school in 2010—Taylor’s Lakeside Campus now sits on the banks of the lake, wrapped closely around the water’s edge. The university takes advantage of this natural water body, formed initially by early mining activities, to formulate its environmental strategies and revitalize it into a key part of the campus 1.3 PROJECT OBJECTIVES: Improve in the level of service in Taylor's University Protect the students' safety in the late night Provide an ideal spot for the students to relax in the midnight Shorten the distance for the students to get food or drinks at the cafe instead of the commercial block. 1.4 PROJECT SCOPE 1.5 SUCCESS CRITERIA The cafe is built within the estimated time. The cafe is built within the estimated budget. The cafe is used fully by students who stay up late and recognize it as a new and ideal place to get food and drinks. The cafe is now part of the famous spot for late night activity with relaxing atmosphere and comfortable ambience.
  • 8. 2. SPECIFICATIONS 2.1 RISK Funding: In case the funding is not enough, the project will be slowed down, postpone or worst, abandoned. Approval: The Authority’s approval will really affect the project, in case the Authority do not give out an approval for the project, the project cannot be carried out. Failure to attract or retain top talent: If we cannot find the right talent for the construction, there might be some problems that will be triggered and it might need to take a longer time that will trigger more problems in the future, e.g. client will lose their interest in the project. Injury to workers: In case something like this happens, problems will be triggered, e.g. the cost of the treatment. 2.2 CONSTRAINTS Pollution: The remnant of the construction materials will pollute the surroundings of the construction site, during the construction work. The sound of the construction work will disturb the activity around the construction site and will distribute to a sound pollution. Safety: The safety around the construction site will be hard to guarantee, the construction process and materials might endanger the safety of people passing by near the construction site. 2.3 ASSUMPTIONS The working hours will be from 12:00am – 6:00am. The customers will be the students that stayed up late. The staffs are not from the campus students. Students who usually go out of the campus area to have supper or to get a short break will choose to stop by this place. It will help in our campus facilities improvement. It will help the students who stayed up late to have a place to have a break. 2.4 TIMESCALE FOR PROJECT
  • 9. 3. PROJECT MANAGEMENT TEAM 3.1 TEAM MEMBERS Key Members Person-in-charge Company Contact Adress Architect Mr. Edy Phung Phone: (+60) 12-253-4128 E-mail: green&bold@gmail.com G&B Sdn. Bhd. Level 3, JalanHua, No. 777, 47500, Subang Jaya, Selangor DarulEhsan, Malaysia. Landscape Architect Mr. Peh Ker Neng Phone: (+60) 14-6170502 E-mail: kernengpeh@gmail.com MajuTECH Landscape Architecture Firm 8,jln mutiara emas 5/25, taman perindustrian mount austin,81100, johor bahru, johor Structural Engineer Miss Lee Jo Yee Phone: (+60) 16-411-5000 E-mail: JadiEC@gmail.com JADI Engineering Consultants Sdn. Bhd. No. 16, Jalan Scotland, Taman Lumba Kuda, Georgetown, Pulau Pinang Contractor Mr. Nicolas Wong Phone: (+60) 14-882-8889 Office No: 086-338889 E-mail: nek4real@hotmail.com Wong Xiao En Berhad No 51A, Tanjung Batu, Jalan Tun Husseisn Onn, 97000 Bintulu, Sarawak. Quantity Surveyor Miss Ling Hui Sim SIM Construction Berhad No 3,Jalan Taman Selekoh, Lahad Datu, Sabah. 3.2 OBJECTIVES To completely understand the students' needs and plan, design and build a cafe for the student. 3.3 TASKS Architect Observe construction of 12AM-CAFÉ to ensure that site work will meet the specifications of construction documents when the construction have completed. Submit modification of the design of 12AM-CAFÉ during construction to contractor. Adapt a project to real life site conditions, correct errors and remedy omissions to the construction documents. Provide an estimate for the cost work of 12AM-CAFÉ. As cost requirements change, architect has to update and refine cost estimate and share the information with contractor and owner. Architect recommends alternative solution to resolve any variations to original budgets. Conduct an assessment of the site for the owner
  • 10. Consider the operations and performance of the facilities and make recommendations for maintenance and improvement. Landscape Architect Overseeing the design of a variety of projects, including urban regeneration schemes, pedestrian schemes, road or retail schemes, and maintaining the character of sites of natural beauty; Establishing general landscape requirements with clients; Conducting preliminary studies of the site (including contours, soil, ecology, buildings, roads); Assessing a site's potential to meet the client's specifications; Carrying out environmental impact assessments; Seeking and taking into account the views of local residents, potential users, and parties with a vested interest in the project; accurately preparing and presenting detailed plans and working drawings, including applications, construction details and specifications for the project using computer-aided design (CAD) packages or similar design software; Presenting proposals to clients, dealing with enquiries and negotiating any amendments to the final design; Matching the client's wishes with your knowledge of what will work best; Contacting and coordinating manufacturers and suppliers; Putting work out to tender, selecting a contractor and manager (mainly for larger projects), and leading cross-functional teams; Making site visits; Ensuring deadlines are met; Liaising with other professionals on the project; Monitoring and checking work on-site (on large projects, landscape managers may do this type of supervisory work); Authorising payment once work has been satisfactorily completed; Attending public inquiries to give evidence if necessary; Generating new business opportunities. Structural Engineer Design structures to withstand stresses & pressures (Do not bend, twist, collapse or vibrate, remain strong and secure throughout their use. Choose appropriate materials to meet design specifications Analysis configurations of the basic structural components of 12AM-CAFÉ
  • 11. Calculate pressure, stress & strains that each component (beam & lintel) will experience from other parts of the structure due to human use or environmental pressure. Liaising with architect to agree an safe designs and fit the aesthetic concept of construction Considering the strength of various material Examining structures at risk of collapse and advising how to improve their structure integrity Making drawings, specifications and computer models of structures for building contractors. Investigating ground conditions and analysising results of site tests Applying expert knowledge of the forces that act on various structure Use computers and computer-aided design (CAD) technology for simulation process. Contractor To perform and complete a task that is assigned or created Checking whether the clients are aware of their duties Cooperate with other working parties Consult with the workers in good time Provide workers under their control with relevant information Ensure the structure is built as per drawings Lease with consultants, sub-traders and owner to achieve the common goal of work being completed on time. Quantity Surveyor Preparation of Feasibility Studies Estimating to define project budgets Analysis of the effect of design changes on the project budget Cost planning to refine the budget as the design documents develop Preparation of Bills of Quantities to assist in the tender process Provision of cost control services during construction Assessment of the contractor’s progress claims Assessment of variation and delay claims Procurement of subcontractors and labour to carry out specialist trade works Negotiation and settlement of accounts Monthly forecasting and cost reporting Monthly negotiation and agreement of payments for works carried out Determination of the final project cost
  • 12. Preparation of tax depreciation reports for investors and property owners Expert witness reports to assist in the settlement of building disputes 4. STAKEHOLDERS These are the stakeholders have so far been identified for the project: 4.1 PRIMARY USERS
  • 13. The students of Taylor's University Lakeside Campus, especially the students from the hostel and students who stay up late in the educational building block for their assignments, projects or discussion. 4.2 GOVERNMENT AND STATUTORY AUTHORITIES 4.3 OTHER COMMUNITY AND USER GROUPS 5. BUDGET 5.1 PRELIMINARY BUDGET STRUCTURE 5.2 EXCLUSIONS
  • 14. 6. REFERENCE DOCUMENTS / SOURCES 6.1 WEBSITES Taylor's University Background: http://www.futurarc.com/index.cfm/projects-2013/2013-may-jun-taylors-lakeside-campus/ Sample Project Brief: http://www.hpw.qld.gov.au/SiteCollectionDocuments/CWMFProjectDefinition.pdf Example of the Timescale of the Project: