12. Using Manometer we found
that ESP is Very Low,
because FAN is not selected
for High Static.
ESP: External
Static Pressure
Drop that ensure
the ability to blow
air out through long
duct
13. Total Water Flow: 165.5 gpm
(110 TR-As Per Drawing)
Reading-2 Reading-1
23040 l/h
= 84.5 gpm =49.1 TR-
45% of Total Load
12120 l/h
= 44.4 gpm =26.8 TR
24% of Total Load
28. Since available CH. W. Pipe: 1”
Maximum Customize AHU: 2400 cfm, 11% better
than existing 2166 cfm
Design Best Practice Best Possible
336 cfm180 cfm 200 cfm
29. Since available CH. W. Pipe: 1”
Maximum Customize AHU can deliver: 60.1
TMBH of Cooling, 5.6% better than 56.9 TMBH
Design Best Practice Best Possible
336 cfm180 cfm 200 cfm
4.74 TMBH
0.4 TR
10.1 TMBH
0.84 TR
0.5 TMBH
0.60 TR
30. ecoCool AHU equipped with
two Blowers powered by
Stronger Motors driven by
adjustable Belts.
Increase ESP by Empower FAN
Motors
31. The New AHU from
ecoCool is
Dynamically Balanced
Unit that over come
both main reasons of
less cooling:
• Less Chilled Water Flow.
• More Air Flow
32. Total Water Flow: 165.5 gpm
(110 TR-As Per Drawing)
Reading-1
12120 l/h
= 44.4 gpm =26.8 TR
24% of Total Load
Reading-3
23040 l/h
= 148 gpm =89.9 TR-
90% of Total Load
33. By shifting Unit to corridor in order
to reduce duct and the negative
effect on Air Flow.
Duct
ecoCool
34. 1) Connect VFD.
2) Add new control
to signal VFD.
3) Utilize PICV
benefits
4) Shift the Make-
up Pressurization
Pump.
Convert to Dynamically Control Ch.
W. Sys.
35. 1d
Now VFD are disconnected and
Pumps are connected directly
38. Now VFD Vary the
Chilled Water
according to actual
demand
39. 2d
Exist signal to VFD from ETS* Reducing CH. W.
Flow inside the
Building while
trying to Maintain
Delta-T .
* Casing less
cooling effect.
* Reducing
emiCool BTU-
Meter-Bill.
40. 2d
Add new control to signal
VFD.
* Right Control
Method.
* With Right
Signal.
* At Right
Location.
46. 4d
Make-up Pressurization Pump @ GF
Pressurization Make-
up Pump located at
GF-Pumps Room and
can’t function as per
design.
47. 4d
Shift the Make-up Pressurization
Pump
Must shift the
Make-up
Pressurization
Pump to maintain
the minimum
pressure at the
weakest point.Shifted
to the
Roof
50. Static Pressure is Monitored and
Maintained at Fixed Level
Fixed
Static
Pressure
51. Dynamic Pressure is Monitored and
Maintained at Fixed Level
Self
Balancing
Dynamic
Pressure
52. Our Solution is Molded in One Unit
CoolDynamically Balanced Solution
53. Replaced all the
24 AHUs with
ecoCool
Activate Variable
Pumps
Fix the Right
Flow Signal
Replace 6
FAHUs
الخطوة
التالية
Shift Press.
Pump to
weakest point
54. ETS Control System
is maintaining
around
6.2’C
all the time
Reading:
09/5/2015
Reading:
21/3/2015
55. But Chilled Water
Flow in
Ltr/Hour (l/h)
has been increased
by: 330%
after correction
Reading:
09/5/2015
Reading:
21/3/2015
56. Most important that
Cooling Capacity in
KWc
delivered the
building
has been increased
by: 260%
Reading:
12/5/2015
Reading:
21/3/2015
63. Convert to
Dynamically
Control Ch. W.
Sys
1) Connect VFD.
2) Add new
control to signal
VFD.
3) Utilize PICV
benefits
4) Shift Make-up
Pressurization
Pump.
Reduce
Long
Duct by
fixing
AHU at
Corridor
when
possible
Increase
ESP by
Empowe
r FAN
Motors
From 0.75 kw
to 1-kw
Enlarge
FCU to
AHU
from
2230 to
2400 cfm
Summary
Of Work Done
64. بين حقيقي وتكامل برمجة
منظومة و التكييف أجهزة
إيميكوول من الذكية التحكم
Make Real
Integration
between you’re A/C
Units and emiCool
Smart Controller
التالية الخطوة
Next
Step
66. To benefit from our
Integration Services:
Consultancies.
Corrections.
Call:
Dr. Taoufik A. Hadi
Eng. Juma Yousef
بنا تتصل كيفHow to Call us ?
Mobile: +971-50-5439078 Fax: 06-5439079
jumayjuma@gmail.com