NOTICE IS HEREBY GIVEN, that sealed bid Proposals are sought and requested for performance of a
contract, according to specifications, to be let by the Ontario County Industrial Development Agency
(OCIDA) for the Canandaigua Airport as follows:

                          EXTENSION & WIDENING OF RUNWAY 13-31
                                 The project includes but is not limited to:
       Base Bid: Encompasses construction of a 2,300 feet extension of Runway 13 including placement
       of fill material, full pavement section, drainage improvements, RW lighting, electrical cable &
       conduits, electrical vault modifications, temporary and permanent pavement markings, and airfield
       guidance signs.
       Add-On No. 1: Encompasses construction of a 2,500 feet extension of parallel Taxiway A
       including placement of fill material, full pavement section, drainage improvements, TW lighting,
       electrical cable & conduits, permanent pavement markings, and airfield guidance signs.
       Add-On No. 2: Encompasses widening and overlay of the existing 3,200 feet Runway 13-31
       including full pavement section in widening area, asphalt overlay of existing RW, RW & TW
       lighting, electrical cable & conduits, permanent pavement markings, and airfield guidance signs.
Separate, sealed bid Proposals for the above Project at the Canandaigua Airport in Canandaigua, NY will
be received by OCIDA at 20 Ontario St., Suite 106-B, until 1:00 pm. on June 21st, 2012. The bids
Proposals will be publicly opened by OCIDA and read at 1:00 p.m. on the same date.
A deposit of one hundred ($100.00) for each set of plans and specifications will be required by the
OCIDA from prospective bidders. Checks shall be made payable to the Ontario County Industrial
Development Agency. The deposit will be held by the OCIDA for 30 days from bid opening. During
this time, the deposit will be returned to the bidder in full, provided the plans and specifications are
returned in good condition. Non-bidders will not be refunded their deposits.
Copies of plans and specifications will be available for purchase or examination beginning at 12pm on
May 24th, 2012 at the following location(s):
McFarland Johnson
2525 SR 332
Box 6, Suite 101
Canandaigua, NY 14424
OCIDA
20 Ontario St.
Suite 106-B
Canandaigua, NY 14424
Direct all inquires to Turner Bradford, P.E. at (585) 905-0970.
A pre-bid conference will be held at Canandaigua Airport on June 11th, 2012 at 1:00 p.m. Attendance by
prospective bidders is strongly recommended.
A Cashier’s Check, drawn upon a state of national bank, or a Proposal Bond with a Surety’s Bond
Affidavit, in the penal sum of five percent (5%) of the total maximum bid price will be required with each
bid Proposal.

More Related Content

Viewers also liked

Diagnostico primer año
Diagnostico primer añoDiagnostico primer año
Diagnostico primer año
zabaneh21
 
Temas y medios o herramientas por grupos marketing internacional
Temas y medios o herramientas por grupos marketing internacionalTemas y medios o herramientas por grupos marketing internacional
Temas y medios o herramientas por grupos marketing internacional
Carmen Hevia Medina
 
Universidad autonoma de sinaloa
Universidad autonoma de sinaloaUniversidad autonoma de sinaloa
Universidad autonoma de sinaloa
Danny Yañez
 
Phasing diagram option a 2011-05_11
Phasing diagram   option a   2011-05_11Phasing diagram   option a   2011-05_11
Phasing diagram option a 2011-05_11
MKThink Strategy
 
Illinois Issues June 2012 Autism Story
Illinois Issues June 2012 Autism StoryIllinois Issues June 2012 Autism Story
Illinois Issues June 2012 Autism Story
The Hope Institute
 
Glosario de internet de informatica
Glosario de internet  de informaticaGlosario de internet  de informatica
Glosario de internet de informatica
anderxavi
 
Crazy1
Crazy1Crazy1
Crazy1
gmes96
 
Firing Workers Raise Legal Issues Under Healthcare Law, November 2012
Firing Workers Raise Legal Issues Under Healthcare Law, November 2012Firing Workers Raise Legal Issues Under Healthcare Law, November 2012
Firing Workers Raise Legal Issues Under Healthcare Law, November 2012
Employers Association of New Jersey
 
FC Sarina: Tag der offenen Tür
FC Sarina: Tag der offenen TürFC Sarina: Tag der offenen Tür
FC Sarina: Tag der offenen Tür
Katrin Schmocker
 
Informe de clase ucv febrero 2014
Informe de clase ucv febrero 2014Informe de clase ucv febrero 2014
Informe de clase ucv febrero 2014
carmencanchari
 

Viewers also liked (20)

3
33
3
 
Boletín 22/04/2012
Boletín 22/04/2012Boletín 22/04/2012
Boletín 22/04/2012
 
Sexualidad
SexualidadSexualidad
Sexualidad
 
Crazy1
Crazy1Crazy1
Crazy1
 
Prueba
PruebaPrueba
Prueba
 
Diagnostico primer año
Diagnostico primer añoDiagnostico primer año
Diagnostico primer año
 
Temas y medios o herramientas por grupos marketing internacional
Temas y medios o herramientas por grupos marketing internacionalTemas y medios o herramientas por grupos marketing internacional
Temas y medios o herramientas por grupos marketing internacional
 
Triptico 2014
Triptico 2014Triptico 2014
Triptico 2014
 
Universidad autonoma de sinaloa
Universidad autonoma de sinaloaUniversidad autonoma de sinaloa
Universidad autonoma de sinaloa
 
Phasing diagram option a 2011-05_11
Phasing diagram   option a   2011-05_11Phasing diagram   option a   2011-05_11
Phasing diagram option a 2011-05_11
 
Loui Byrdziak - Moroccan Winebag Collection
Loui Byrdziak - Moroccan Winebag CollectionLoui Byrdziak - Moroccan Winebag Collection
Loui Byrdziak - Moroccan Winebag Collection
 
Illinois Issues June 2012 Autism Story
Illinois Issues June 2012 Autism StoryIllinois Issues June 2012 Autism Story
Illinois Issues June 2012 Autism Story
 
Documento
DocumentoDocumento
Documento
 
Glosario de internet de informatica
Glosario de internet  de informaticaGlosario de internet  de informatica
Glosario de internet de informatica
 
Lista de funcionarios para congreso
Lista de funcionarios para congresoLista de funcionarios para congreso
Lista de funcionarios para congreso
 
Crazy1
Crazy1Crazy1
Crazy1
 
Firing Workers Raise Legal Issues Under Healthcare Law, November 2012
Firing Workers Raise Legal Issues Under Healthcare Law, November 2012Firing Workers Raise Legal Issues Under Healthcare Law, November 2012
Firing Workers Raise Legal Issues Under Healthcare Law, November 2012
 
FC Sarina: Tag der offenen Tür
FC Sarina: Tag der offenen TürFC Sarina: Tag der offenen Tür
FC Sarina: Tag der offenen Tür
 
Informe de clase ucv febrero 2014
Informe de clase ucv febrero 2014Informe de clase ucv febrero 2014
Informe de clase ucv febrero 2014
 
Rosario kopecek medina sud
Rosario kopecek medina sudRosario kopecek medina sud
Rosario kopecek medina sud
 

Similar to Bid documentfinal

CV_Amr Abdelhamid Mahrous (Update 20 Oct 2015)
CV_Amr Abdelhamid Mahrous (Update 20 Oct 2015)CV_Amr Abdelhamid Mahrous (Update 20 Oct 2015)
CV_Amr Abdelhamid Mahrous (Update 20 Oct 2015)
amr mahrous
 
Engineer and Project management CV 'Ali Al Obaidy
Engineer and Project management  CV 'Ali Al ObaidyEngineer and Project management  CV 'Ali Al Obaidy
Engineer and Project management CV 'Ali Al Obaidy
Ali Alobaidy
 
Holly Hill Drive Plans 4-11-13
Holly Hill Drive Plans 4-11-13Holly Hill Drive Plans 4-11-13
Holly Hill Drive Plans 4-11-13
Chad Henry
 
CV-Sandeep Kumar Updated
CV-Sandeep Kumar UpdatedCV-Sandeep Kumar Updated
CV-Sandeep Kumar Updated
SANDEEP KUMAR
 
- Nabil Resume - Civil - Construction-1 (3)( 2)
- Nabil Resume - Civil - Construction-1 (3)( 2)- Nabil Resume - Civil - Construction-1 (3)( 2)
- Nabil Resume - Civil - Construction-1 (3)( 2)
NABIL NASSAR
 
Jamsheer P_CV (1)
Jamsheer P_CV (1)Jamsheer P_CV (1)
Jamsheer P_CV (1)
jamsheer p
 
Rajib Ali CV (Final)
Rajib Ali CV (Final)Rajib Ali CV (Final)
Rajib Ali CV (Final)
Rajib Ali
 
ALI FAKHIR IBRAHEEM - C.V
ALI FAKHIR IBRAHEEM -  C.VALI FAKHIR IBRAHEEM -  C.V
ALI FAKHIR IBRAHEEM - C.V
Ali Fakhir
 

Similar to Bid documentfinal (20)

CMAA OHare and Midway International Airports Capital Improvement Program
CMAA OHare and Midway International Airports Capital Improvement ProgramCMAA OHare and Midway International Airports Capital Improvement Program
CMAA OHare and Midway International Airports Capital Improvement Program
 
Ashraf Suleiman.
Ashraf Suleiman.Ashraf Suleiman.
Ashraf Suleiman.
 
Tes p-122.08-r0
Tes p-122.08-r0Tes p-122.08-r0
Tes p-122.08-r0
 
CV_Amr Abdelhamid Mahrous (Update 20 Oct 2015)
CV_Amr Abdelhamid Mahrous (Update 20 Oct 2015)CV_Amr Abdelhamid Mahrous (Update 20 Oct 2015)
CV_Amr Abdelhamid Mahrous (Update 20 Oct 2015)
 
CV PF
CV PFCV PF
CV PF
 
Final Presentation for 1st GMs-PDs Conference 03.02.2023.pptx
Final Presentation for 1st GMs-PDs Conference 03.02.2023.pptxFinal Presentation for 1st GMs-PDs Conference 03.02.2023.pptx
Final Presentation for 1st GMs-PDs Conference 03.02.2023.pptx
 
Satham Mohamed.A-CV..
Satham Mohamed.A-CV..Satham Mohamed.A-CV..
Satham Mohamed.A-CV..
 
C V-OSAMA-Revised 2014(PDF)
C V-OSAMA-Revised 2014(PDF)C V-OSAMA-Revised 2014(PDF)
C V-OSAMA-Revised 2014(PDF)
 
Engineer and Project management CV 'Ali Al Obaidy
Engineer and Project management  CV 'Ali Al ObaidyEngineer and Project management  CV 'Ali Al Obaidy
Engineer and Project management CV 'Ali Al Obaidy
 
Holly Hill Drive Plans 4-11-13
Holly Hill Drive Plans 4-11-13Holly Hill Drive Plans 4-11-13
Holly Hill Drive Plans 4-11-13
 
Hossam salah-cv
Hossam salah-cvHossam salah-cv
Hossam salah-cv
 
411 New York Ave. NE Zoning Commission Order 15-19
411 New York Ave. NE Zoning Commission Order 15-19411 New York Ave. NE Zoning Commission Order 15-19
411 New York Ave. NE Zoning Commission Order 15-19
 
Appendix: San Diego PEV Readiness Plan
Appendix: San Diego PEV Readiness PlanAppendix: San Diego PEV Readiness Plan
Appendix: San Diego PEV Readiness Plan
 
CV-Sandeep Kumar Updated
CV-Sandeep Kumar UpdatedCV-Sandeep Kumar Updated
CV-Sandeep Kumar Updated
 
E&I Farukh
E&I FarukhE&I Farukh
E&I Farukh
 
Kd6
Kd6Kd6
Kd6
 
- Nabil Resume - Civil - Construction-1 (3)( 2)
- Nabil Resume - Civil - Construction-1 (3)( 2)- Nabil Resume - Civil - Construction-1 (3)( 2)
- Nabil Resume - Civil - Construction-1 (3)( 2)
 
Jamsheer P_CV (1)
Jamsheer P_CV (1)Jamsheer P_CV (1)
Jamsheer P_CV (1)
 
Rajib Ali CV (Final)
Rajib Ali CV (Final)Rajib Ali CV (Final)
Rajib Ali CV (Final)
 
ALI FAKHIR IBRAHEEM - C.V
ALI FAKHIR IBRAHEEM -  C.VALI FAKHIR IBRAHEEM -  C.V
ALI FAKHIR IBRAHEEM - C.V
 

Recently uploaded

Présentation About Algiers City (noureddine boureneb)
Présentation About Algiers City (noureddine boureneb)Présentation About Algiers City (noureddine boureneb)
Présentation About Algiers City (noureddine boureneb)
klaisaci
 

Recently uploaded (11)

Travel In Jhang and Visa company,"Explore, Dream,
Travel In Jhang and Visa company,"Explore, Dream,Travel In Jhang and Visa company,"Explore, Dream,
Travel In Jhang and Visa company,"Explore, Dream,
 
Sinister History Exploring Austin’s Past Through a Night Walking Tour
Sinister History Exploring Austin’s Past Through a Night Walking TourSinister History Exploring Austin’s Past Through a Night Walking Tour
Sinister History Exploring Austin’s Past Through a Night Walking Tour
 
Business Tourism Market in Katowice in The Year 2023.
Business Tourism Market in Katowice in The Year 2023.Business Tourism Market in Katowice in The Year 2023.
Business Tourism Market in Katowice in The Year 2023.
 
Présentation About Algiers City (noureddine boureneb)
Présentation About Algiers City (noureddine boureneb)Présentation About Algiers City (noureddine boureneb)
Présentation About Algiers City (noureddine boureneb)
 
Tourist Places to Visit in Darjeeling Article.docx
Tourist Places to Visit in Darjeeling Article.docxTourist Places to Visit in Darjeeling Article.docx
Tourist Places to Visit in Darjeeling Article.docx
 
Expect On a Voodoo Cemetery Tour in New Orleans.pptx
Expect On a Voodoo Cemetery Tour in New Orleans.pptxExpect On a Voodoo Cemetery Tour in New Orleans.pptx
Expect On a Voodoo Cemetery Tour in New Orleans.pptx
 
Top Places To Visit In Sikkim Tour Package.pdf
Top Places To Visit In Sikkim Tour Package.pdfTop Places To Visit In Sikkim Tour Package.pdf
Top Places To Visit In Sikkim Tour Package.pdf
 
🕉️MAHANAVABHARATAADISREERAMAYANAGH.docx
🕉️MAHANAVABHARATAADISREERAMAYANAGH.docx🕉️MAHANAVABHARATAADISREERAMAYANAGH.docx
🕉️MAHANAVABHARATAADISREERAMAYANAGH.docx
 
Everything you need to know about adventure tourism in Nepal
Everything you need to know about adventure tourism in NepalEverything you need to know about adventure tourism in Nepal
Everything you need to know about adventure tourism in Nepal
 
Pune Baramati Visit Education Tour Report
Pune Baramati  Visit Education Tour ReportPune Baramati  Visit Education Tour Report
Pune Baramati Visit Education Tour Report
 
Book A Romantic Honeymoon Trip to the Andaman Islands
Book A Romantic Honeymoon Trip to the Andaman IslandsBook A Romantic Honeymoon Trip to the Andaman Islands
Book A Romantic Honeymoon Trip to the Andaman Islands
 

Bid documentfinal

  • 1. NOTICE IS HEREBY GIVEN, that sealed bid Proposals are sought and requested for performance of a contract, according to specifications, to be let by the Ontario County Industrial Development Agency (OCIDA) for the Canandaigua Airport as follows: EXTENSION & WIDENING OF RUNWAY 13-31 The project includes but is not limited to: Base Bid: Encompasses construction of a 2,300 feet extension of Runway 13 including placement of fill material, full pavement section, drainage improvements, RW lighting, electrical cable & conduits, electrical vault modifications, temporary and permanent pavement markings, and airfield guidance signs. Add-On No. 1: Encompasses construction of a 2,500 feet extension of parallel Taxiway A including placement of fill material, full pavement section, drainage improvements, TW lighting, electrical cable & conduits, permanent pavement markings, and airfield guidance signs. Add-On No. 2: Encompasses widening and overlay of the existing 3,200 feet Runway 13-31 including full pavement section in widening area, asphalt overlay of existing RW, RW & TW lighting, electrical cable & conduits, permanent pavement markings, and airfield guidance signs. Separate, sealed bid Proposals for the above Project at the Canandaigua Airport in Canandaigua, NY will be received by OCIDA at 20 Ontario St., Suite 106-B, until 1:00 pm. on June 21st, 2012. The bids Proposals will be publicly opened by OCIDA and read at 1:00 p.m. on the same date. A deposit of one hundred ($100.00) for each set of plans and specifications will be required by the OCIDA from prospective bidders. Checks shall be made payable to the Ontario County Industrial Development Agency. The deposit will be held by the OCIDA for 30 days from bid opening. During this time, the deposit will be returned to the bidder in full, provided the plans and specifications are returned in good condition. Non-bidders will not be refunded their deposits. Copies of plans and specifications will be available for purchase or examination beginning at 12pm on May 24th, 2012 at the following location(s): McFarland Johnson 2525 SR 332 Box 6, Suite 101 Canandaigua, NY 14424 OCIDA 20 Ontario St. Suite 106-B Canandaigua, NY 14424 Direct all inquires to Turner Bradford, P.E. at (585) 905-0970. A pre-bid conference will be held at Canandaigua Airport on June 11th, 2012 at 1:00 p.m. Attendance by prospective bidders is strongly recommended. A Cashier’s Check, drawn upon a state of national bank, or a Proposal Bond with a Surety’s Bond Affidavit, in the penal sum of five percent (5%) of the total maximum bid price will be required with each bid Proposal.