Anzeige

COST MANAGEMENT REPORT

Professor/Program Coordinator um Private and State Universities
21. Nov 2022
Anzeige

Más contenido relacionado

Anzeige

COST MANAGEMENT REPORT

  1. COST MANAGEMENT MPA 209 PROJECT PLANNING AND DEVELOPMENT
  2. - is the process of estimating, budgeting and controlling costs throughout the project life cycle, with the objective of keeping expenditures within the approved budget. WHAT IS COST MANAGEMENT?
  3. it is VITAL to an organization’s project planning process because without a detailed budget, you cannot effectively map out the resources needed for your project. Why COST MANAGEMENT important?
  4. Prevents overruns Avoids risk Aids future planning Benefits of Cost Management
  5. Direct Costs Indirect Costs - fixed labor - materials - equipment - utilities expenses - travel expenses Types of expenses
  6. Project Resource Planning Cost Estimation Cost Budgeting Cost Control Steps in Project Cost Management
  7. Project Resource Planning - is the process of identifying the resources required to execute a project and take it to completion Steps in Project Cost Management
  8. Cost Estimation - is the process of quantifying the costs associated with all the resources required to execute the project Steps in Project Cost Management
  9. Labor Materials and Equipment Actual Cost The Cost Variance Return on Investment (ROI) Cost estimation factors
  10. Cost Budgeting - it creates a cost baseline against which we can continue to measure and evaluate the project cost performance Steps in Project Cost Management
  11. Cost Control - is the process of measuring cost variances from the baseline, such as increasing the budget allocated or reducing the scope of work, to correct that gap Steps in Project Cost Management
  12. Earned value management (EVM) - is one of the most popular approaches to measuring project performance and progress in an objective manner
  13. Key Concepts Actual Cost (AC) Cost of the work performed Planned Value (PV) Budgeted Cost of the Work Scheduled Earned Value (EV) Budgeted Cost of the Work Performed Formulas Cost Variance (CV): EV - AC = over/under budget Cost Performance Index: CPI = EV/AC = Project Performance Scheduled Performance Index: SPI = EV/PV = Project Performance
  14. budgeted cost of a project at P100,000.00 10 months after a month, you have completed 5% at a total expenses of P20,000.00 Example: (today the total project completed should be at 10%)
  15. Given: Budgeted Cost: P100,000.00 Actual Cost: P20,000.00 Compute for Planned Value (PV) PV = Planned completion % x BC = 10% x P100,000.00 = P10,000.00
  16. Compute for Earned Value (EV) EV = Actual completion (%) x BC = 5% x P100,000.00 = P5,000.00 Given: Budgeted Cost: P100,000.00 Actual Cost: P20,000.00
  17. Cost Performance Index: CPI = EV/AC CPI = P5,000.00 / P20,000 = 0.25 ...that means that for every peso that is being spent the project is producing only 25 cents of work.
  18. Schedule Performance Index: SPI = EV/PV SPI = P5,000.00 / P10,000 = 0.50 (30minutes) ...that means that for every estimated hour of work, only half an hour is being spent in doing a job/work
  19. Thank you!
Anzeige