7. Project Selection Matrix
■ Objective
■ Complexity
■ Permitting Status
■ Public Interest
■ Funding
■ Size
Project Characteristics
Likely Candidate for Delivery as
D/B/B CM/GC D/B
Primary project delivery objective
NDOR control of detailed design
Completion schedule
Cost
Early cost and schedule certainty
Reduced NDOR staff involvement
Technical innovation
Funding
Programmed and funding committed
Programmed but full funding not committed
Not programmed
Project size
Greater than $50 million
$10 million to $49 million
Less than $10 million
ITS projects
Project complexity
Numerous primary features (road, bridges, ITS)
Closely interrelated features
Constrained construction phasing
Unique or unusual site conditions
Specialized skills need for design or construction
Emerging technology included
Extensive temporary features required
Delivery Method is Compatible with the Characteristic
Delivery Method May Be Compatible with the Characteristic
Delivery Method is Not Compatible with the Characteristic
9. ■ Construction Manager/General Contractor
■ Construction Manager at-Risk (CMR)
■ Owner engages contractor during design
■ Provides constructability input
■ Contract “target price” at 60%-90% Design
level
Owner
ContractorDesign
Agree on Build
Contract?
YES NO
CM/GC
Construction Phase
Same Contractor New Contractor
Design Phase
12. US-275
Expressway
■ 1988 Expressway System
Regional Connectivity
New priority to complete the
Expressway System
Build Nebraska
Original intent to developing
Expressway
13. 2 Plus 2 Approach
Criteria
■ Existing lanes
Remain in place
Asset Preservation
Resurface
■ New lanes
Offset of existing
New & Reconstruction
New embankment &
pavement
Goals
■ Stay consistent with 2+2
concept
■ Minimize
Impacts to existing
New lanes crossing over
the existing lanes
Analyze the system
14. Project Scope
■ 4-lane Divided Expressway
Majority of project to use 2+2
Concept
Construction of a new bypass
around Scribner
Pebble Creek Levee System
Project Length: 18.5 miles
Total Project Cost $109M
18. RFQ
■ Advertised
9/6/17
■ SOQ’s Due
11/17/17
■ Evaluated
Tech. Review Committee
■ Announced
1/12/18
Request For Qualifications
19. Graham Group
Werner Construction
WSP USA Inc.
Olsson
Graham-Werner JV Hawkins DBTeam Kiewit Inf. Co.
Hawkins Construction
Clarkson Construction
Burns & McDonnell
Alfred Benesch & Co.
Kiewit Inf. Co.
Kiewit Engineering
Felsburg Holt & Ullevig
37. 275 Corridor
Scribner –West Point
■ Award a Design-BuildContractor in
late 2019
■ Final Design and Construction
Norfolk –West Point
■ RFQ released for design and
environmental services
■ Phase 1
– Preliminary Design and NEPA
■ Phase 2
– Final Design for a portion of the
corridor
Provides the details for the Submittal of Qualifications (SOQ)
SOQ’s identify the teams and important personnel
We went through a Q/A phase and issued 2 addenda to respond to questions and concerns
NDOT had a technical review committee perform the SOQ evaluations
Decision announced at the beginning of the year
Similarities across the teams that are positive
Construction entities with design-build experience
Large, international design firms with design-build experience
Design firms more prominent locally included
Provides the details for the Submittal of Qualifications (SOQ)
SOQ’s identify the teams and important personnel
We went through a Q/A phase and issued 2 addenda to respond to questions and concerns
NDOT had a technical review committee perform the SOQ evaluations
Decision announced at the beginning of the year
- Following a typical process
3 Volumes (or Books or Parts)
ITP – Lays out what needs to be in the proposals.
Gives technical, financial, schedule requirements.
Lays out the evaluation criteria at a high level.
Standardizes the proposal for ease of review (and preparation)
Reference Documents
Non contractual unless referenced in
Preliminary Engineering and associated documentation
Contract – What NDOT and the design builder sign
Commercial Terms (who pays for what)
Technical Requirements for Design & Construction