Critical Study on Kochi Barrage
Vaishnav S. Chachire, Dr Rajendra R. Dighade
UG Students, Department of Civil Engineering, Yeshwantrao Chavan College of Engineering, Nagpur
--------------------------------------------------------------------***--------------------------------------------------------------------------
ABSTRACT
Barrages are hydraulic constructions erected across gutters to deflect water inflow into irrigation conduits or power
generation channels. The utmost of these structures are innovated on a passable foundation. The optimum cost of those
structures is seepage forces under the structure are caused by a nonlinear function of factors. There is, still, no procedure
to determine the essential shower parameters like depth of distance piles or cut offs and the length and consistency of
bottom in a cost – effective manner.
In this paper, what was the environmental impact assessment of kanhan swash (kochi shower).
The end of the design is to develop a design proposed for supplying water for irrigation, artificial need and drinking
purposes. Being this design involves in land accession, relegation of people and submergence aspects; this is likely to
produce some adverse environmental impacts, though these are anticipated to be minimum. In order to alleviate the likely
adverse environmental and social impacts; to insure that the being environmental and socio-profitable conditions will
further ameliorate, but in no case deteriorate; an Environmental Impact Assessment (EIA) report and Environmental
Management Plan (EMP) are essential.
Keywords: Subsurface flow ·Hydraulic structures ·Barrages · Submergence.
INTRODUCTION
The Maharashtra government has prioritized the development of irrigation systems in order to transfigure unused dry
regions into perpetual green fields and enriching lives of people, particularly in the failure prone areas. The Pench Project
is one of such systems accepted in the history and flushing considerable extent of Nagpur quarter through its Left Bank
and Right Bank Conduits. The Pench Right Bank Canal (PRBC) provides irrigation to the areas falling between Kanhan
River within the north and Nag River within the south. In addition to husbandry, PRBC inventories water to Koradi
Thermal power factory (KTPS) and libation to Nagpur megacity. On account of diversion of substantial amount of PRBC
waters meant for irrigation in the command area to KTPS and Nagpur megacity, the downstream areas beyond Nagpur
megacity, have started facing water dearths for irrigation. This has forced the authorities to suspend water force to 3960
ha irrigable command area south of National Highway-6 which fall in the tail end portions of the PRBC command area in
Kamptee tehsil of Nagpur quarter. These conditions have redounded in agitations by the affected growers of the tail- end
portions of PRBC command area for restoring irrigation in their area.
In view of the very fact there aren't any other reliable water coffers away from Kanhan
River to revive irrigation installation within the affected area; and no point away from at Kochi is suitable for storing the
share of 15 TMC Kanhan River water allocated to Maharashtra with least submergence, the only most-suitable point at
Kochi has been named for construction of a barrage.
Necessity of EIA & EMP for Kochi Project
Kochi Project is a water coffers development design proposed for supplying water for irrigation, artificial needs and
drinking purposes. Being this design involves in land accession, relegation of people and submergence aspects; this is
likely to produce some adverse environmental impacts, though these are anticipated to be minimum. In order to alleviate
the likely adverse environmental and social impacts; to insure that the being environmental and socio-profitable
conditions will further ameliorate, but in no case deteriorate; an Environmental Impact Assessment (EIA) report and
Environmental Management Plan (EMP) are essential. Also from the statuary point of view, that the proposed irrigable
command area under this design is about 3960 ha; this design requires environmental concurrences from the Ministry of
Environment and Forest (MoEF). In order to satisfy the statutory conditions, the EIA and EMP are prepared by covering
the posterior major aspects
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 09 Issue: 06 | June 2022 www.irjet.net p-ISSN: 2395-0072
© 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 2841
1. Establishing the being environmental and socio-profitable conditions in the proposed design area through review of
literature and conducting primary environmental monitoring, covering Pre-monsoon, Monsoon, Post-monsoon seasons of
time 2009 and downtime season of 2010;
2. Environmental Impact Assessment i.e. assessing the impacts of the proposed design on colorful environmental and
socio-profitable parameters;
3. Developing an Environmental Management Plan for outlining mitigation measures for limiting any likely adverse
environmental and social impact due to the proposed design and to insure the environmental conditions in the design area
would ameliorate further for environmentally sustainability and in no circumstances, these would deteriorate;
4. Social Assessment for assessing the Socio-profitable status of the design affected persons and displaced persons from
the submergence area;
5. Developing a Rehabilitation & Resettlement Plan for resettling the displaced persons of 4 townlets from the levee seat
and submergence area;
6. Developing a Compensatory Afforestation Plan for compensating the loss of timber due to the design;
Baseline Environmental Status
The being birth environmental conditions in the design area have been established through review of secondary data and
primary field checks covering aspects related to land use,micro-meteorology, ambient air quality, water quality, soil
quality, noise situations, submarine and terrestrial ecology, socio-profitable conditions of people, healthcare installations
and structure development. The primary checks for assessing the face and groundwater quality, and groundwater
oscillations were conducted in all 4 seasons of the time covering Pre- thunderstorm, Monsoon,Post-Monsoon seasons of
2009 and of and downtime season of 2010. All the other environmental checks were conducted during thePre-Monsoon
andPost-Monsoon seasons of time 2009. The socio-profitable checks of the Project displaced persons were conducted
formerly during the EIA period.
• Physiography of the Project Area The catchment receptacle of the design consists of colorful feathers of terrenes like
hills, bottom hills, swash denes and plains. Still the command area The design has gently leaning terrain and facilitates
irrigation by graveness. A many minor irrigation tanks and ponds live in the command area.
Environmental Impact Assessment
Kochi Project will provide immense benefits to the failure prone area by means of restoring irrigation installation in the
severely affected command area, furnishing fresh artificial water for expansion of KTPS and drinking water to Nagpur
megacity. While giving only benefits to the existing command area of PRBC, this project will not have any adverse impact
on this command area. Due to its moderate submergence area this project is not anticipated to cause major environmental
impacts, though some minor impacts related with land accession and submergence of zudpi jungle would take place;
which still would be eased with applicable operation measures.
1. Impacts during Construction Phase
2. Impact during Operational Phase
3. Impact on Social Environment
4. Impact on Land Use
5. Impact on Surface Water Resources
6. Impact on Groundwater Resources
7. Impact on Ecology and Bio-Diversity
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 09 Issue: 06 | June 2022 www.irjet.net p-ISSN: 2395-0072
© 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 2842
Environment operation plan
Kochi Project would have some social and environmental counteraccusations though they are anticipated to be the
minimum. To further minimize the environmental losses and negating adverse impacts to the possible extent through
specialized judgment and perpetration of Applicable mitigation measures, an Environmental Management Plan has been
developed
Environment Management Plan during Construction Phase
Undertaking excavations and construction conditioning at the design spots with utmost care to the environmental aspects
and safety measures;
• Using the generated muck from design spots for constructing the earthen levee if suitable, or filling the low-lying
areas;
• Stacking the fat material in linked muck disposal spots down from the design point, with applicable pitches, in a
methodical manner;
• Condensing of muck dumps, covering them with clod shoveled from construction spots and bearing colonies on them
for minimizing corrosion;
• Espousing applicable measurers for minimizing climate and noise situations during firing; completing construction
conditioning only during day so as to avoid noise impacts on the encompassing areas;
• Undertaking dust control measures similar as water smattering on the haul roads;
• Maintaining the diesel powered construction vehicles duly, for minimizing bank emigrations;
• Furnishing noise protection bias like earmuffs and earplugs to the workers operating the high noise generating
outfit;
Public Health Management
Public Health management measures include:
• Undertaking adequate curative and preventive measures for eliminating the risk of outbreak of any water borne and
parasitic disease in the area;
• Strengthening the prevailing healthcare facilities by appointing adequate number of medical and paramedical staff;
• Maintaining good environmental, health and sanitation conditions at the development camps; and Carying out
regular surveillance and health improvement programs by the Health Department for preventing health disorders in
command area.
Conclusions
The proposed Kanhan River Project will provide assured surface water irrigation facility to 3960 ha ICA. With provision of
its immense benefits to the irrigation scarce drought prone area of Kamptee tahasil in Nagpur district, this project would
lead for overall socio-economic and infrastructure development of the region. By supplying considerable quantities of food
and non-food products, this project would be beneficial even to the other areas. With impressive Benefit Cost Ratio of
1.542 and least minimal environmental and social impacts; the proposed Kochi Barrage Project is maintainable.
References
 http://shodhbhagirathi.iitr.ac.in:8081/jspui/handle/123456789/425
 https://www.researchgate.net/publication/259197930_Farakka_Barrage_the_greatest_ever_riparian_bluff_for_ups
tream_water_piracy
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 09 Issue: 06 | June 2022 www.irjet.net p-ISSN: 2395-0072
© 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 2843
 https://ui.adsabs.harvard.edu/abs/2017E&ES...70a2050A/abstract
 https://www.researchgate.net/publication/215638822_Electricity_Generation_by_the_Tidal_Barrages#:~:text=A
%20tidal%20barrage%20is%20typically,flow%20in%20both%20directions
 https://www.ijsr.net/get_abstract.php?paper_id=ART20202521

More Related Content

Similar to Critical Study on Kochi Barrage

IRJET- Identification of Sources of Pollution & Designing of Effective Domest...
IRJET- Identification of Sources of Pollution & Designing of Effective Domest...IRJET- Identification of Sources of Pollution & Designing of Effective Domest...
IRJET- Identification of Sources of Pollution & Designing of Effective Domest...IRJET Journal
 
An Experimental Study on the Reuse of Waste Water Treatment Plant Sludge in t...
An Experimental Study on the Reuse of Waste Water Treatment Plant Sludge in t...An Experimental Study on the Reuse of Waste Water Treatment Plant Sludge in t...
An Experimental Study on the Reuse of Waste Water Treatment Plant Sludge in t...IRJET Journal
 
IN-HOUSE R&D PROPOSALS-PRT.ppt
IN-HOUSE R&D PROPOSALS-PRT.pptIN-HOUSE R&D PROPOSALS-PRT.ppt
IN-HOUSE R&D PROPOSALS-PRT.pptSrini Vasan
 
IRJET - Reaearch on Methods of Controlling Soil Erosion
IRJET - Reaearch on Methods of Controlling Soil ErosionIRJET - Reaearch on Methods of Controlling Soil Erosion
IRJET - Reaearch on Methods of Controlling Soil ErosionIRJET Journal
 
KEJORA_EIA_TRC_-_May_2021_Rev3.pptx
KEJORA_EIA_TRC_-_May_2021_Rev3.pptxKEJORA_EIA_TRC_-_May_2021_Rev3.pptx
KEJORA_EIA_TRC_-_May_2021_Rev3.pptxAnandaNair4
 
SUSTAINABLE & COST-EFFECTIVE DRAINAGE DESIGN SOLUTION FOR AN URBAN ROAD SCENA...
SUSTAINABLE & COST-EFFECTIVE DRAINAGE DESIGN SOLUTION FOR AN URBAN ROAD SCENA...SUSTAINABLE & COST-EFFECTIVE DRAINAGE DESIGN SOLUTION FOR AN URBAN ROAD SCENA...
SUSTAINABLE & COST-EFFECTIVE DRAINAGE DESIGN SOLUTION FOR AN URBAN ROAD SCENA...IRJET Journal
 
Res15-Brad Young_151221
Res15-Brad Young_151221Res15-Brad Young_151221
Res15-Brad Young_151221Brad Young
 
Sewage Treatment Plant
Sewage Treatment PlantSewage Treatment Plant
Sewage Treatment PlantDeepak Samal
 
The Northern Collector Water Tunnel Project Report
The Northern Collector Water Tunnel Project ReportThe Northern Collector Water Tunnel Project Report
The Northern Collector Water Tunnel Project ReportThe Star Newspaper
 
CURRENT WATER MANAGEMENT PRACTICES IN SINGLE UNIT RESIDENTIAL BUNGALOWS AT KO...
CURRENT WATER MANAGEMENT PRACTICES IN SINGLE UNIT RESIDENTIAL BUNGALOWS AT KO...CURRENT WATER MANAGEMENT PRACTICES IN SINGLE UNIT RESIDENTIAL BUNGALOWS AT KO...
CURRENT WATER MANAGEMENT PRACTICES IN SINGLE UNIT RESIDENTIAL BUNGALOWS AT KO...IRJET Journal
 
IRJET - Reaearch on Erosion Controlling Methods
IRJET - Reaearch on Erosion Controlling MethodsIRJET - Reaearch on Erosion Controlling Methods
IRJET - Reaearch on Erosion Controlling MethodsIRJET Journal
 
KISHANGARH AIRPORT EIA
KISHANGARH AIRPORT EIAKISHANGARH AIRPORT EIA
KISHANGARH AIRPORT EIAMNIT,JAIPUR
 
DISASTER MANAGEMENT OF FLOOD AND ITS RETAINING TECHNIQUES
DISASTER MANAGEMENT OF FLOOD AND ITS RETAINING TECHNIQUESDISASTER MANAGEMENT OF FLOOD AND ITS RETAINING TECHNIQUES
DISASTER MANAGEMENT OF FLOOD AND ITS RETAINING TECHNIQUESIRJET Journal
 
IRJET- Planning and Analysis of Sewage Treatment Plant (43 MLD) in Sagar ...
IRJET-  	  Planning and Analysis of Sewage Treatment Plant (43 MLD) in Sagar ...IRJET-  	  Planning and Analysis of Sewage Treatment Plant (43 MLD) in Sagar ...
IRJET- Planning and Analysis of Sewage Treatment Plant (43 MLD) in Sagar ...IRJET Journal
 
EIA Report Analysis of Rampal Power Plant
EIA Report Analysis of Rampal Power PlantEIA Report Analysis of Rampal Power Plant
EIA Report Analysis of Rampal Power Plantsaifulalamsuahag
 

Similar to Critical Study on Kochi Barrage (20)

IRJET- Identification of Sources of Pollution & Designing of Effective Domest...
IRJET- Identification of Sources of Pollution & Designing of Effective Domest...IRJET- Identification of Sources of Pollution & Designing of Effective Domest...
IRJET- Identification of Sources of Pollution & Designing of Effective Domest...
 
An Experimental Study on the Reuse of Waste Water Treatment Plant Sludge in t...
An Experimental Study on the Reuse of Waste Water Treatment Plant Sludge in t...An Experimental Study on the Reuse of Waste Water Treatment Plant Sludge in t...
An Experimental Study on the Reuse of Waste Water Treatment Plant Sludge in t...
 
SIDA Kandiaro emp
SIDA Kandiaro empSIDA Kandiaro emp
SIDA Kandiaro emp
 
IN-HOUSE R&D PROPOSALS-PRT.ppt
IN-HOUSE R&D PROPOSALS-PRT.pptIN-HOUSE R&D PROPOSALS-PRT.ppt
IN-HOUSE R&D PROPOSALS-PRT.ppt
 
EIA Report of Orange Line Train
EIA Report of Orange Line TrainEIA Report of Orange Line Train
EIA Report of Orange Line Train
 
Vijayakanth CV_ 27 Oct 15
Vijayakanth CV_ 27 Oct 15Vijayakanth CV_ 27 Oct 15
Vijayakanth CV_ 27 Oct 15
 
IRJET - Reaearch on Methods of Controlling Soil Erosion
IRJET - Reaearch on Methods of Controlling Soil ErosionIRJET - Reaearch on Methods of Controlling Soil Erosion
IRJET - Reaearch on Methods of Controlling Soil Erosion
 
CV_Jagannath Hosmani
CV_Jagannath HosmaniCV_Jagannath Hosmani
CV_Jagannath Hosmani
 
KEJORA_EIA_TRC_-_May_2021_Rev3.pptx
KEJORA_EIA_TRC_-_May_2021_Rev3.pptxKEJORA_EIA_TRC_-_May_2021_Rev3.pptx
KEJORA_EIA_TRC_-_May_2021_Rev3.pptx
 
SUSTAINABLE & COST-EFFECTIVE DRAINAGE DESIGN SOLUTION FOR AN URBAN ROAD SCENA...
SUSTAINABLE & COST-EFFECTIVE DRAINAGE DESIGN SOLUTION FOR AN URBAN ROAD SCENA...SUSTAINABLE & COST-EFFECTIVE DRAINAGE DESIGN SOLUTION FOR AN URBAN ROAD SCENA...
SUSTAINABLE & COST-EFFECTIVE DRAINAGE DESIGN SOLUTION FOR AN URBAN ROAD SCENA...
 
Res15-Brad Young_151221
Res15-Brad Young_151221Res15-Brad Young_151221
Res15-Brad Young_151221
 
Sewage Treatment Plant
Sewage Treatment PlantSewage Treatment Plant
Sewage Treatment Plant
 
The Northern Collector Water Tunnel Project Report
The Northern Collector Water Tunnel Project ReportThe Northern Collector Water Tunnel Project Report
The Northern Collector Water Tunnel Project Report
 
CURRENT WATER MANAGEMENT PRACTICES IN SINGLE UNIT RESIDENTIAL BUNGALOWS AT KO...
CURRENT WATER MANAGEMENT PRACTICES IN SINGLE UNIT RESIDENTIAL BUNGALOWS AT KO...CURRENT WATER MANAGEMENT PRACTICES IN SINGLE UNIT RESIDENTIAL BUNGALOWS AT KO...
CURRENT WATER MANAGEMENT PRACTICES IN SINGLE UNIT RESIDENTIAL BUNGALOWS AT KO...
 
IRJET - Reaearch on Erosion Controlling Methods
IRJET - Reaearch on Erosion Controlling MethodsIRJET - Reaearch on Erosion Controlling Methods
IRJET - Reaearch on Erosion Controlling Methods
 
KISHANGARH AIRPORT EIA
KISHANGARH AIRPORT EIAKISHANGARH AIRPORT EIA
KISHANGARH AIRPORT EIA
 
DISASTER MANAGEMENT OF FLOOD AND ITS RETAINING TECHNIQUES
DISASTER MANAGEMENT OF FLOOD AND ITS RETAINING TECHNIQUESDISASTER MANAGEMENT OF FLOOD AND ITS RETAINING TECHNIQUES
DISASTER MANAGEMENT OF FLOOD AND ITS RETAINING TECHNIQUES
 
IRJET- Planning and Analysis of Sewage Treatment Plant (43 MLD) in Sagar ...
IRJET-  	  Planning and Analysis of Sewage Treatment Plant (43 MLD) in Sagar ...IRJET-  	  Planning and Analysis of Sewage Treatment Plant (43 MLD) in Sagar ...
IRJET- Planning and Analysis of Sewage Treatment Plant (43 MLD) in Sagar ...
 
EIA Report Analysis of Rampal Power Plant
EIA Report Analysis of Rampal Power PlantEIA Report Analysis of Rampal Power Plant
EIA Report Analysis of Rampal Power Plant
 
Iee ppt
Iee pptIee ppt
Iee ppt
 

More from IRJET Journal

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...IRJET Journal
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTUREIRJET Journal
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...IRJET Journal
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsIRJET Journal
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...IRJET Journal
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...IRJET Journal
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...IRJET Journal
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...IRJET Journal
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASIRJET Journal
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...IRJET Journal
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProIRJET Journal
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...IRJET Journal
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemIRJET Journal
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesIRJET Journal
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web applicationIRJET Journal
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...IRJET Journal
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.IRJET Journal
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...IRJET Journal
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignIRJET Journal
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...IRJET Journal
 

More from IRJET Journal (20)

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil Characteristics
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADAS
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare System
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridges
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web application
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
 

Recently uploaded

UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSISrknatarajan
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...roncy bisnoi
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college projectTonystark477637
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)Suman Mia
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlysanyuktamishra911
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...ranjana rawat
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...Call Girls in Nagpur High Profile
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 

Recently uploaded (20)

UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSIS
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college project
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 
Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 

Critical Study on Kochi Barrage

  • 1. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 09 Issue: 06 | June 2022 www.irjet.net p-ISSN: 2395-0072 © 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 2840 Critical Study on Kochi Barrage Vaishnav S. Chachire, Dr Rajendra R. Dighade UG Students, Department of Civil Engineering, Yeshwantrao Chavan College of Engineering, Nagpur --------------------------------------------------------------------***-------------------------------------------------------------------------- ABSTRACT Barrages are hydraulic constructions erected across gutters to deflect water inflow into irrigation conduits or power generation channels. The utmost of these structures are innovated on a passable foundation. The optimum cost of those structures is seepage forces under the structure are caused by a nonlinear function of factors. There is, still, no procedure to determine the essential shower parameters like depth of distance piles or cut offs and the length and consistency of bottom in a cost – effective manner. In this paper, what was the environmental impact assessment of kanhan swash (kochi shower). The end of the design is to develop a design proposed for supplying water for irrigation, artificial need and drinking purposes. Being this design involves in land accession, relegation of people and submergence aspects; this is likely to produce some adverse environmental impacts, though these are anticipated to be minimum. In order to alleviate the likely adverse environmental and social impacts; to insure that the being environmental and socio-profitable conditions will further ameliorate, but in no case deteriorate; an Environmental Impact Assessment (EIA) report and Environmental Management Plan (EMP) are essential. Keywords: Subsurface flow ·Hydraulic structures ·Barrages · Submergence. INTRODUCTION The Maharashtra government has prioritized the development of irrigation systems in order to transfigure unused dry regions into perpetual green fields and enriching lives of people, particularly in the failure prone areas. The Pench Project is one of such systems accepted in the history and flushing considerable extent of Nagpur quarter through its Left Bank and Right Bank Conduits. The Pench Right Bank Canal (PRBC) provides irrigation to the areas falling between Kanhan River within the north and Nag River within the south. In addition to husbandry, PRBC inventories water to Koradi Thermal power factory (KTPS) and libation to Nagpur megacity. On account of diversion of substantial amount of PRBC waters meant for irrigation in the command area to KTPS and Nagpur megacity, the downstream areas beyond Nagpur megacity, have started facing water dearths for irrigation. This has forced the authorities to suspend water force to 3960 ha irrigable command area south of National Highway-6 which fall in the tail end portions of the PRBC command area in Kamptee tehsil of Nagpur quarter. These conditions have redounded in agitations by the affected growers of the tail- end portions of PRBC command area for restoring irrigation in their area. In view of the very fact there aren't any other reliable water coffers away from Kanhan River to revive irrigation installation within the affected area; and no point away from at Kochi is suitable for storing the share of 15 TMC Kanhan River water allocated to Maharashtra with least submergence, the only most-suitable point at Kochi has been named for construction of a barrage. Necessity of EIA & EMP for Kochi Project Kochi Project is a water coffers development design proposed for supplying water for irrigation, artificial needs and drinking purposes. Being this design involves in land accession, relegation of people and submergence aspects; this is likely to produce some adverse environmental impacts, though these are anticipated to be minimum. In order to alleviate the likely adverse environmental and social impacts; to insure that the being environmental and socio-profitable conditions will further ameliorate, but in no case deteriorate; an Environmental Impact Assessment (EIA) report and Environmental Management Plan (EMP) are essential. Also from the statuary point of view, that the proposed irrigable command area under this design is about 3960 ha; this design requires environmental concurrences from the Ministry of Environment and Forest (MoEF). In order to satisfy the statutory conditions, the EIA and EMP are prepared by covering the posterior major aspects
  • 2. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 09 Issue: 06 | June 2022 www.irjet.net p-ISSN: 2395-0072 © 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 2841 1. Establishing the being environmental and socio-profitable conditions in the proposed design area through review of literature and conducting primary environmental monitoring, covering Pre-monsoon, Monsoon, Post-monsoon seasons of time 2009 and downtime season of 2010; 2. Environmental Impact Assessment i.e. assessing the impacts of the proposed design on colorful environmental and socio-profitable parameters; 3. Developing an Environmental Management Plan for outlining mitigation measures for limiting any likely adverse environmental and social impact due to the proposed design and to insure the environmental conditions in the design area would ameliorate further for environmentally sustainability and in no circumstances, these would deteriorate; 4. Social Assessment for assessing the Socio-profitable status of the design affected persons and displaced persons from the submergence area; 5. Developing a Rehabilitation & Resettlement Plan for resettling the displaced persons of 4 townlets from the levee seat and submergence area; 6. Developing a Compensatory Afforestation Plan for compensating the loss of timber due to the design; Baseline Environmental Status The being birth environmental conditions in the design area have been established through review of secondary data and primary field checks covering aspects related to land use,micro-meteorology, ambient air quality, water quality, soil quality, noise situations, submarine and terrestrial ecology, socio-profitable conditions of people, healthcare installations and structure development. The primary checks for assessing the face and groundwater quality, and groundwater oscillations were conducted in all 4 seasons of the time covering Pre- thunderstorm, Monsoon,Post-Monsoon seasons of 2009 and of and downtime season of 2010. All the other environmental checks were conducted during thePre-Monsoon andPost-Monsoon seasons of time 2009. The socio-profitable checks of the Project displaced persons were conducted formerly during the EIA period. • Physiography of the Project Area The catchment receptacle of the design consists of colorful feathers of terrenes like hills, bottom hills, swash denes and plains. Still the command area The design has gently leaning terrain and facilitates irrigation by graveness. A many minor irrigation tanks and ponds live in the command area. Environmental Impact Assessment Kochi Project will provide immense benefits to the failure prone area by means of restoring irrigation installation in the severely affected command area, furnishing fresh artificial water for expansion of KTPS and drinking water to Nagpur megacity. While giving only benefits to the existing command area of PRBC, this project will not have any adverse impact on this command area. Due to its moderate submergence area this project is not anticipated to cause major environmental impacts, though some minor impacts related with land accession and submergence of zudpi jungle would take place; which still would be eased with applicable operation measures. 1. Impacts during Construction Phase 2. Impact during Operational Phase 3. Impact on Social Environment 4. Impact on Land Use 5. Impact on Surface Water Resources 6. Impact on Groundwater Resources 7. Impact on Ecology and Bio-Diversity
  • 3. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 09 Issue: 06 | June 2022 www.irjet.net p-ISSN: 2395-0072 © 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 2842 Environment operation plan Kochi Project would have some social and environmental counteraccusations though they are anticipated to be the minimum. To further minimize the environmental losses and negating adverse impacts to the possible extent through specialized judgment and perpetration of Applicable mitigation measures, an Environmental Management Plan has been developed Environment Management Plan during Construction Phase Undertaking excavations and construction conditioning at the design spots with utmost care to the environmental aspects and safety measures; • Using the generated muck from design spots for constructing the earthen levee if suitable, or filling the low-lying areas; • Stacking the fat material in linked muck disposal spots down from the design point, with applicable pitches, in a methodical manner; • Condensing of muck dumps, covering them with clod shoveled from construction spots and bearing colonies on them for minimizing corrosion; • Espousing applicable measurers for minimizing climate and noise situations during firing; completing construction conditioning only during day so as to avoid noise impacts on the encompassing areas; • Undertaking dust control measures similar as water smattering on the haul roads; • Maintaining the diesel powered construction vehicles duly, for minimizing bank emigrations; • Furnishing noise protection bias like earmuffs and earplugs to the workers operating the high noise generating outfit; Public Health Management Public Health management measures include: • Undertaking adequate curative and preventive measures for eliminating the risk of outbreak of any water borne and parasitic disease in the area; • Strengthening the prevailing healthcare facilities by appointing adequate number of medical and paramedical staff; • Maintaining good environmental, health and sanitation conditions at the development camps; and Carying out regular surveillance and health improvement programs by the Health Department for preventing health disorders in command area. Conclusions The proposed Kanhan River Project will provide assured surface water irrigation facility to 3960 ha ICA. With provision of its immense benefits to the irrigation scarce drought prone area of Kamptee tahasil in Nagpur district, this project would lead for overall socio-economic and infrastructure development of the region. By supplying considerable quantities of food and non-food products, this project would be beneficial even to the other areas. With impressive Benefit Cost Ratio of 1.542 and least minimal environmental and social impacts; the proposed Kochi Barrage Project is maintainable. References  http://shodhbhagirathi.iitr.ac.in:8081/jspui/handle/123456789/425  https://www.researchgate.net/publication/259197930_Farakka_Barrage_the_greatest_ever_riparian_bluff_for_ups tream_water_piracy
  • 4. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 09 Issue: 06 | June 2022 www.irjet.net p-ISSN: 2395-0072 © 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 2843  https://ui.adsabs.harvard.edu/abs/2017E&ES...70a2050A/abstract  https://www.researchgate.net/publication/215638822_Electricity_Generation_by_the_Tidal_Barrages#:~:text=A %20tidal%20barrage%20is%20typically,flow%20in%20both%20directions  https://www.ijsr.net/get_abstract.php?paper_id=ART20202521