SlideShare ist ein Scribd-Unternehmen logo
1 von 3
Free Float
The amount of duration in which the scheduled activity can be deferred without postponing the
subsequent scheduled activities.
In project management, free float refers to the duration that spans from the finishing point of a
scheduled activity while extending to the upcoming planned activities. It is measured by subtracting
the primary end of the activity from the early beginning of the subsequent activity. Once you identify
the time period, subtract it from the expected total time of completion of the first activity. In case
there is no following activity, you will primarily use the project end date to determine the free float
window in the project network. Free float is only measured on the final activity in an activity
sequence. It is calculated individually for each activity.
Example:
If an activity has a time period of six days and is occurring parallel with another activity which has a
duration of nine days, the former will have approximately three days of total float. It can be
postponed up to three days without affecting the overall project. On the other hand, if it is delayed by
five days, it will come with a negative float situation i.e. – 2 days. This means that the project will
take two more days than the expected duration.
Project Float
The duration in which the given task is delayed before it affects the deadline for the project.
Project managers often use float time to schedule the certain time frames for the tasks to be
accomplished on time. The project float doesn’t influence the deadlines of other following tasks. To
make the most of the float, it’s important to determine the critical path and measure the amount of
float in every non-critical task. Also, it helps in visualizing the project using Gantt chart. That way,
you can reorganize tasks into specific chains and reassign the resources and work schedules
accordingly to maximize efficiency. It’s important to revise float estimate as the project continues.
For instance, if a specific task takes longer than expected, you may want to use the estimated float to
compensate it. One simple way to calculate project float is to deduct the duration you have assigned
to complete a task from the time the task will take in real. Suppose you have assigned 12 days for a
task, though it only takes 8 days to complete. The approximate slack will be 4 days.
Total Float aka Float
The time period in which the scheduled activity may be postponed fromits early start date without
deferring the project finish date or intermediate milestone.
Total float refers to the amount of time an activity can be postponed without delaying the complete
project duration. Project managers must know the estimated total float time available at the very
beginning of the project. Total float refers to the delayed duration that doesn’t interfere with the
project completion deadline. Since unexpected occurrences can happen anytime from poor weather
conditions to the sudden emergency of a team member. For that reason, the project manager should
estimate the total float so the project is finished on time. To find a total float, one important
technique is to use a critical path that helps in identifying the earliest possible and latest finishing
point. Preferably, a project should not go beyond the latest finish date to keep the project running on
a defined schedule. Total float is calculated considering the difference between the initial and late
start date (LS – ES) or the initial and late finish date (LF – EF). Total float is common between the
activities in an arrangement. The structure is defined as the undertakings between a path convergence
and path divergence.
Important Notes on Free Float, Project Float
and Total Float
1. Any project activity with a float time that equals 0 or with negative float is considered a critical
path task.
2. Total Float is for the project and again for activities not on Critical Path
3. Free Float is on individual activities and those which are not on Critical Path
4. Buffers and Total Floats are not the same. Buffers are added as contingency reserves whereas total
float is due to its placement in the Network Diagram.
5. Same like Buffers and Total Floats, Lags and Free Float are not the same. Lags are introduced by
the scheduling team whereas Free Floats are because of their placement
6. An Activity may have different Free Float and Total Float
Formula Free Float and Total Float
 Total Float = LF – EF (or LS – ES)
 Free Float = ES of next activity – EF
Further Readings
1. Project Schedule Management
2. Planning Process Group

Weitere ähnliche Inhalte

Was ist angesagt?

Theory of structures I module 1
Theory of structures I module 1Theory of structures I module 1
Theory of structures I module 1Mredul Mv II
 
Reinforcement concrete and properties of matrial
Reinforcement concrete and properties of matrial Reinforcement concrete and properties of matrial
Reinforcement concrete and properties of matrial VIKAS4210607
 
Line of balance in civil engineering
Line of balance in civil engineeringLine of balance in civil engineering
Line of balance in civil engineeringrathodjaydeep2
 
3. construction planning. construction project management
3. construction planning. construction project management3. construction planning. construction project management
3. construction planning. construction project managementKabilan Kabi
 
determinate and indeterminate structures
determinate and indeterminate structuresdeterminate and indeterminate structures
determinate and indeterminate structuresvempatishiva
 
Resources allocation and resources scheduling_Construction Management
Resources allocation and resources scheduling_Construction Management Resources allocation and resources scheduling_Construction Management
Resources allocation and resources scheduling_Construction Management A Makwana
 
Precedence Diagramming Method PDM
Precedence Diagramming Method PDMPrecedence Diagramming Method PDM
Precedence Diagramming Method PDMShaiful Amri Mansur
 
Elevation measurement_Surveying, Civil Engineering
Elevation measurement_Surveying, Civil EngineeringElevation measurement_Surveying, Civil Engineering
Elevation measurement_Surveying, Civil EngineeringA Makwana
 
Project Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERTProject Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERTS.Vijaya Bhaskar
 
Steel Structure Fabrication and erection (Ravi Choudhary).pptx
Steel Structure Fabrication and erection (Ravi Choudhary).pptxSteel Structure Fabrication and erection (Ravi Choudhary).pptx
Steel Structure Fabrication and erection (Ravi Choudhary).pptxmrujjavalsinghvarana
 
Network analysis by PERT and CPM
Network analysis by PERT and CPMNetwork analysis by PERT and CPM
Network analysis by PERT and CPMRajendrakumar Kadi
 
Estimating part 2
Estimating part 2Estimating part 2
Estimating part 2ArunRavi43
 
الكود الاردني احمال المباني
الكود الاردني   احمال المبانيالكود الاردني   احمال المباني
الكود الاردني احمال المبانيDr.youssef hamida
 
Critical Path Method
Critical Path MethodCritical Path Method
Critical Path MethodSimplilearn
 
03 Construction Project Planning and Scheduling
03 Construction Project Planning and Scheduling03 Construction Project Planning and Scheduling
03 Construction Project Planning and Schedulingakashpadole
 

Was ist angesagt? (20)

Critical Path Method
Critical Path MethodCritical Path Method
Critical Path Method
 
Theory of structures I module 1
Theory of structures I module 1Theory of structures I module 1
Theory of structures I module 1
 
Reinforcement concrete and properties of matrial
Reinforcement concrete and properties of matrial Reinforcement concrete and properties of matrial
Reinforcement concrete and properties of matrial
 
Line of balance in civil engineering
Line of balance in civil engineeringLine of balance in civil engineering
Line of balance in civil engineering
 
3. construction planning. construction project management
3. construction planning. construction project management3. construction planning. construction project management
3. construction planning. construction project management
 
determinate and indeterminate structures
determinate and indeterminate structuresdeterminate and indeterminate structures
determinate and indeterminate structures
 
Resources allocation and resources scheduling_Construction Management
Resources allocation and resources scheduling_Construction Management Resources allocation and resources scheduling_Construction Management
Resources allocation and resources scheduling_Construction Management
 
Precedence Diagramming Method PDM
Precedence Diagramming Method PDMPrecedence Diagramming Method PDM
Precedence Diagramming Method PDM
 
Elevation measurement_Surveying, Civil Engineering
Elevation measurement_Surveying, Civil EngineeringElevation measurement_Surveying, Civil Engineering
Elevation measurement_Surveying, Civil Engineering
 
Chapter 9 introduction to construction equipments
Chapter  9 introduction to construction equipmentsChapter  9 introduction to construction equipments
Chapter 9 introduction to construction equipments
 
Project Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERTProject Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERT
 
Steel Structure Fabrication and erection (Ravi Choudhary).pptx
Steel Structure Fabrication and erection (Ravi Choudhary).pptxSteel Structure Fabrication and erection (Ravi Choudhary).pptx
Steel Structure Fabrication and erection (Ravi Choudhary).pptx
 
Network analysis by PERT and CPM
Network analysis by PERT and CPMNetwork analysis by PERT and CPM
Network analysis by PERT and CPM
 
Estimating part 2
Estimating part 2Estimating part 2
Estimating part 2
 
Gantt PERT and CPM
Gantt PERT and CPMGantt PERT and CPM
Gantt PERT and CPM
 
الكود الاردني احمال المباني
الكود الاردني   احمال المبانيالكود الاردني   احمال المباني
الكود الاردني احمال المباني
 
Resource allocation and smoothing
Resource allocation and smoothingResource allocation and smoothing
Resource allocation and smoothing
 
Critical Path Method
Critical Path MethodCritical Path Method
Critical Path Method
 
03 Construction Project Planning and Scheduling
03 Construction Project Planning and Scheduling03 Construction Project Planning and Scheduling
03 Construction Project Planning and Scheduling
 
Matrix methods
Matrix methodsMatrix methods
Matrix methods
 

Ähnlich wie Free float and total float - PMP/CAPM from PMI

12 lecture project scheduling 4
12 lecture project scheduling 412 lecture project scheduling 4
12 lecture project scheduling 4Ahmad Basim Hamza
 
PERT-CPM : PROJECT MANAGEMENT TOOLS
PERT-CPM : PROJECT MANAGEMENT TOOLSPERT-CPM : PROJECT MANAGEMENT TOOLS
PERT-CPM : PROJECT MANAGEMENT TOOLSZulfiquer Ahmed Amin
 
Critical Path MethodIntroductionOnce you have the network diag.docx
Critical Path MethodIntroductionOnce you have the network diag.docxCritical Path MethodIntroductionOnce you have the network diag.docx
Critical Path MethodIntroductionOnce you have the network diag.docxannettsparrow
 
MS Project Terminology -Top 20 terms everyone must know
MS Project Terminology -Top 20 terms everyone must knowMS Project Terminology -Top 20 terms everyone must know
MS Project Terminology -Top 20 terms everyone must knowSHAZEBALIKHAN1
 
Project schedule- What, How, Tools & Techniques
Project schedule- What, How, Tools & TechniquesProject schedule- What, How, Tools & Techniques
Project schedule- What, How, Tools & TechniquesSHAZEBALIKHAN1
 
Critical path method(cpm)
Critical path method(cpm)Critical path method(cpm)
Critical path method(cpm)chandkec
 
Project Management Tools and Techniques (PERT- Project Evaluation and Review ...
Project Management Tools and Techniques (PERT- Project Evaluation and Review ...Project Management Tools and Techniques (PERT- Project Evaluation and Review ...
Project Management Tools and Techniques (PERT- Project Evaluation and Review ...Zulfiquer Ahmed Amin
 
المحاضرة السادسة: إعداد جدول المشروع
المحاضرة السادسة: إعداد جدول المشروعالمحاضرة السادسة: إعداد جدول المشروع
المحاضرة السادسة: إعداد جدول المشروعEgypt Scholars Inc.
 
Primavera presentation
Primavera presentationPrimavera presentation
Primavera presentationNithin Dev
 
Critical Path Method: Activities And Events, Float/Slacks
Critical Path Method: Activities And Events, Float/SlacksCritical Path Method: Activities And Events, Float/Slacks
Critical Path Method: Activities And Events, Float/SlacksPrasad Thanthratey
 
Program_Evaluation_and_Review_Technique.pptx
Program_Evaluation_and_Review_Technique.pptxProgram_Evaluation_and_Review_Technique.pptx
Program_Evaluation_and_Review_Technique.pptxmamtabisht10
 
MBA 6941, Managing Project Teams 1 Course Learning Outco.docx
MBA 6941, Managing Project Teams 1 Course Learning Outco.docxMBA 6941, Managing Project Teams 1 Course Learning Outco.docx
MBA 6941, Managing Project Teams 1 Course Learning Outco.docxalfredacavx97
 
Production & Operation Management Chapter 34, 35[1]
Production & Operation Management Chapter 34, 35[1]Production & Operation Management Chapter 34, 35[1]
Production & Operation Management Chapter 34, 35[1]Hariharan Ponnusamy
 
PertGanttchart
PertGanttchartPertGanttchart
PertGanttchartlearnt
 
2007 MS Project Training Instructors Manual (sample)
2007 MS Project Training Instructors Manual (sample)2007 MS Project Training Instructors Manual (sample)
2007 MS Project Training Instructors Manual (sample)Bruce Gordon
 
(PROGRAM EVALUATION AND REVIE TECHNIQUE)
(PROGRAM EVALUATION AND REVIE TECHNIQUE)(PROGRAM EVALUATION AND REVIE TECHNIQUE)
(PROGRAM EVALUATION AND REVIE TECHNIQUE)hannahpepino1
 
Advanced project management mod 4
Advanced project management mod 4Advanced project management mod 4
Advanced project management mod 4POOJA UDAYAN
 

Ähnlich wie Free float and total float - PMP/CAPM from PMI (20)

12 lecture project scheduling 4
12 lecture project scheduling 412 lecture project scheduling 4
12 lecture project scheduling 4
 
PERT-CPM : PROJECT MANAGEMENT TOOLS
PERT-CPM : PROJECT MANAGEMENT TOOLSPERT-CPM : PROJECT MANAGEMENT TOOLS
PERT-CPM : PROJECT MANAGEMENT TOOLS
 
Critical Path MethodIntroductionOnce you have the network diag.docx
Critical Path MethodIntroductionOnce you have the network diag.docxCritical Path MethodIntroductionOnce you have the network diag.docx
Critical Path MethodIntroductionOnce you have the network diag.docx
 
Project time
Project timeProject time
Project time
 
MS Project Terminology -Top 20 terms everyone must know
MS Project Terminology -Top 20 terms everyone must knowMS Project Terminology -Top 20 terms everyone must know
MS Project Terminology -Top 20 terms everyone must know
 
Project schedule- What, How, Tools & Techniques
Project schedule- What, How, Tools & TechniquesProject schedule- What, How, Tools & Techniques
Project schedule- What, How, Tools & Techniques
 
pert/cpm
pert/cpmpert/cpm
pert/cpm
 
Critical path method(cpm)
Critical path method(cpm)Critical path method(cpm)
Critical path method(cpm)
 
Project Management Tools and Techniques (PERT- Project Evaluation and Review ...
Project Management Tools and Techniques (PERT- Project Evaluation and Review ...Project Management Tools and Techniques (PERT- Project Evaluation and Review ...
Project Management Tools and Techniques (PERT- Project Evaluation and Review ...
 
المحاضرة السادسة: إعداد جدول المشروع
المحاضرة السادسة: إعداد جدول المشروعالمحاضرة السادسة: إعداد جدول المشروع
المحاضرة السادسة: إعداد جدول المشروع
 
Primavera presentation
Primavera presentationPrimavera presentation
Primavera presentation
 
Critical Path Method: Activities And Events, Float/Slacks
Critical Path Method: Activities And Events, Float/SlacksCritical Path Method: Activities And Events, Float/Slacks
Critical Path Method: Activities And Events, Float/Slacks
 
Program_Evaluation_and_Review_Technique.pptx
Program_Evaluation_and_Review_Technique.pptxProgram_Evaluation_and_Review_Technique.pptx
Program_Evaluation_and_Review_Technique.pptx
 
MBA 6941, Managing Project Teams 1 Course Learning Outco.docx
MBA 6941, Managing Project Teams 1 Course Learning Outco.docxMBA 6941, Managing Project Teams 1 Course Learning Outco.docx
MBA 6941, Managing Project Teams 1 Course Learning Outco.docx
 
Production & Operation Management Chapter 34, 35[1]
Production & Operation Management Chapter 34, 35[1]Production & Operation Management Chapter 34, 35[1]
Production & Operation Management Chapter 34, 35[1]
 
Module :-5 project scheduling and resource levelling
Module :-5 project scheduling and resource levellingModule :-5 project scheduling and resource levelling
Module :-5 project scheduling and resource levelling
 
PertGanttchart
PertGanttchartPertGanttchart
PertGanttchart
 
2007 MS Project Training Instructors Manual (sample)
2007 MS Project Training Instructors Manual (sample)2007 MS Project Training Instructors Manual (sample)
2007 MS Project Training Instructors Manual (sample)
 
(PROGRAM EVALUATION AND REVIE TECHNIQUE)
(PROGRAM EVALUATION AND REVIE TECHNIQUE)(PROGRAM EVALUATION AND REVIE TECHNIQUE)
(PROGRAM EVALUATION AND REVIE TECHNIQUE)
 
Advanced project management mod 4
Advanced project management mod 4Advanced project management mod 4
Advanced project management mod 4
 

Mehr von Mudassir Iqbal

Quality assurance and control quality - PMP/CAPM by PMI
Quality assurance and control quality - PMP/CAPM by PMIQuality assurance and control quality - PMP/CAPM by PMI
Quality assurance and control quality - PMP/CAPM by PMIMudassir Iqbal
 
Residual risk and secondary risk - PMP/CAPM from PMI
Residual risk and secondary risk - PMP/CAPM from PMIResidual risk and secondary risk - PMP/CAPM from PMI
Residual risk and secondary risk - PMP/CAPM from PMIMudassir Iqbal
 
Event and Non-Event Risk - PMP/CAPM from PMI
Event and Non-Event Risk  - PMP/CAPM from PMIEvent and Non-Event Risk  - PMP/CAPM from PMI
Event and Non-Event Risk - PMP/CAPM from PMIMudassir Iqbal
 
EEF and OPA - PMP/CAPM from PMI
EEF and OPA - PMP/CAPM from PMIEEF and OPA - PMP/CAPM from PMI
EEF and OPA - PMP/CAPM from PMIMudassir Iqbal
 
Control account, work and planning package - PMP/CAPM from PMI
Control account, work and planning package - PMP/CAPM from PMIControl account, work and planning package - PMP/CAPM from PMI
Control account, work and planning package - PMP/CAPM from PMIMudassir Iqbal
 
Budget and cost estimates - PMP/CAPM from PMI
Budget and cost estimates - PMP/CAPM from PMIBudget and cost estimates - PMP/CAPM from PMI
Budget and cost estimates - PMP/CAPM from PMIMudassir Iqbal
 
Project scope Management - PMP/CAPM
Project scope Management - PMP/CAPMProject scope Management - PMP/CAPM
Project scope Management - PMP/CAPMMudassir Iqbal
 
Project schedule Management - PMP/CAPM
Project schedule Management - PMP/CAPMProject schedule Management - PMP/CAPM
Project schedule Management - PMP/CAPMMudassir Iqbal
 
Project Cost Management - PMP/CAPM
Project Cost Management - PMP/CAPMProject Cost Management - PMP/CAPM
Project Cost Management - PMP/CAPMMudassir Iqbal
 
Project procurement Management - PMP/CAPM
Project procurement  Management - PMP/CAPMProject procurement  Management - PMP/CAPM
Project procurement Management - PMP/CAPMMudassir Iqbal
 
Planning process group
Planning process groupPlanning process group
Planning process groupMudassir Iqbal
 
Executing process group
Executing process groupExecuting process group
Executing process groupMudassir Iqbal
 
Master schedule and milestone schedule
Master schedule and milestone scheduleMaster schedule and milestone schedule
Master schedule and milestone scheduleMudassir Iqbal
 
Cost baseline and cost budget
Cost baseline and cost budgetCost baseline and cost budget
Cost baseline and cost budgetMudassir Iqbal
 
Babok2 chapter9 daxko
Babok2 chapter9 daxko Babok2 chapter9 daxko
Babok2 chapter9 daxko Mudassir Iqbal
 

Mehr von Mudassir Iqbal (17)

Quality assurance and control quality - PMP/CAPM by PMI
Quality assurance and control quality - PMP/CAPM by PMIQuality assurance and control quality - PMP/CAPM by PMI
Quality assurance and control quality - PMP/CAPM by PMI
 
Residual risk and secondary risk - PMP/CAPM from PMI
Residual risk and secondary risk - PMP/CAPM from PMIResidual risk and secondary risk - PMP/CAPM from PMI
Residual risk and secondary risk - PMP/CAPM from PMI
 
Event and Non-Event Risk - PMP/CAPM from PMI
Event and Non-Event Risk  - PMP/CAPM from PMIEvent and Non-Event Risk  - PMP/CAPM from PMI
Event and Non-Event Risk - PMP/CAPM from PMI
 
EEF and OPA - PMP/CAPM from PMI
EEF and OPA - PMP/CAPM from PMIEEF and OPA - PMP/CAPM from PMI
EEF and OPA - PMP/CAPM from PMI
 
Control account, work and planning package - PMP/CAPM from PMI
Control account, work and planning package - PMP/CAPM from PMIControl account, work and planning package - PMP/CAPM from PMI
Control account, work and planning package - PMP/CAPM from PMI
 
Budget and cost estimates - PMP/CAPM from PMI
Budget and cost estimates - PMP/CAPM from PMIBudget and cost estimates - PMP/CAPM from PMI
Budget and cost estimates - PMP/CAPM from PMI
 
Project scope Management - PMP/CAPM
Project scope Management - PMP/CAPMProject scope Management - PMP/CAPM
Project scope Management - PMP/CAPM
 
Project schedule Management - PMP/CAPM
Project schedule Management - PMP/CAPMProject schedule Management - PMP/CAPM
Project schedule Management - PMP/CAPM
 
Project Cost Management - PMP/CAPM
Project Cost Management - PMP/CAPMProject Cost Management - PMP/CAPM
Project Cost Management - PMP/CAPM
 
Project procurement Management - PMP/CAPM
Project procurement  Management - PMP/CAPMProject procurement  Management - PMP/CAPM
Project procurement Management - PMP/CAPM
 
Planning process group
Planning process groupPlanning process group
Planning process group
 
Executing process group
Executing process groupExecuting process group
Executing process group
 
Closing process group
Closing process groupClosing process group
Closing process group
 
Master schedule and milestone schedule
Master schedule and milestone scheduleMaster schedule and milestone schedule
Master schedule and milestone schedule
 
Quality and Grade
Quality and GradeQuality and Grade
Quality and Grade
 
Cost baseline and cost budget
Cost baseline and cost budgetCost baseline and cost budget
Cost baseline and cost budget
 
Babok2 chapter9 daxko
Babok2 chapter9 daxko Babok2 chapter9 daxko
Babok2 chapter9 daxko
 

Kürzlich hochgeladen

8447779800, Low rate Call girls in Saket Delhi NCR
8447779800, Low rate Call girls in Saket Delhi NCR8447779800, Low rate Call girls in Saket Delhi NCR
8447779800, Low rate Call girls in Saket Delhi NCRashishs7044
 
8447779800, Low rate Call girls in Tughlakabad Delhi NCR
8447779800, Low rate Call girls in Tughlakabad Delhi NCR8447779800, Low rate Call girls in Tughlakabad Delhi NCR
8447779800, Low rate Call girls in Tughlakabad Delhi NCRashishs7044
 
8447779800, Low rate Call girls in Rohini Delhi NCR
8447779800, Low rate Call girls in Rohini Delhi NCR8447779800, Low rate Call girls in Rohini Delhi NCR
8447779800, Low rate Call girls in Rohini Delhi NCRashishs7044
 
Organizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessOrganizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessSeta Wicaksana
 
Case study on tata clothing brand zudio in detail
Case study on tata clothing brand zudio in detailCase study on tata clothing brand zudio in detail
Case study on tata clothing brand zudio in detailAriel592675
 
Annual General Meeting Presentation Slides
Annual General Meeting Presentation SlidesAnnual General Meeting Presentation Slides
Annual General Meeting Presentation SlidesKeppelCorporation
 
MAHA Global and IPR: Do Actions Speak Louder Than Words?
MAHA Global and IPR: Do Actions Speak Louder Than Words?MAHA Global and IPR: Do Actions Speak Louder Than Words?
MAHA Global and IPR: Do Actions Speak Louder Than Words?Olivia Kresic
 
Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024Kirill Klimov
 
Memorándum de Entendimiento (MoU) entre Codelco y SQM
Memorándum de Entendimiento (MoU) entre Codelco y SQMMemorándum de Entendimiento (MoU) entre Codelco y SQM
Memorándum de Entendimiento (MoU) entre Codelco y SQMVoces Mineras
 
Marketplace and Quality Assurance Presentation - Vincent Chirchir
Marketplace and Quality Assurance Presentation - Vincent ChirchirMarketplace and Quality Assurance Presentation - Vincent Chirchir
Marketplace and Quality Assurance Presentation - Vincent Chirchirictsugar
 
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort Service
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort ServiceCall US-88OO1O2216 Call Girls In Mahipalpur Female Escort Service
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort Servicecallgirls2057
 
Investment in The Coconut Industry by Nancy Cheruiyot
Investment in The Coconut Industry by Nancy CheruiyotInvestment in The Coconut Industry by Nancy Cheruiyot
Investment in The Coconut Industry by Nancy Cheruiyotictsugar
 
Kenya Coconut Production Presentation by Dr. Lalith Perera
Kenya Coconut Production Presentation by Dr. Lalith PereraKenya Coconut Production Presentation by Dr. Lalith Perera
Kenya Coconut Production Presentation by Dr. Lalith Pereraictsugar
 
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607dollysharma2066
 
Market Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 EditionMarket Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 EditionMintel Group
 
2024 Numerator Consumer Study of Cannabis Usage
2024 Numerator Consumer Study of Cannabis Usage2024 Numerator Consumer Study of Cannabis Usage
2024 Numerator Consumer Study of Cannabis UsageNeil Kimberley
 
Islamabad Escorts | Call 03070433345 | Escort Service in Islamabad
Islamabad Escorts | Call 03070433345 | Escort Service in IslamabadIslamabad Escorts | Call 03070433345 | Escort Service in Islamabad
Islamabad Escorts | Call 03070433345 | Escort Service in IslamabadAyesha Khan
 
Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03DallasHaselhorst
 
International Business Environments and Operations 16th Global Edition test b...
International Business Environments and Operations 16th Global Edition test b...International Business Environments and Operations 16th Global Edition test b...
International Business Environments and Operations 16th Global Edition test b...ssuserf63bd7
 

Kürzlich hochgeladen (20)

8447779800, Low rate Call girls in Saket Delhi NCR
8447779800, Low rate Call girls in Saket Delhi NCR8447779800, Low rate Call girls in Saket Delhi NCR
8447779800, Low rate Call girls in Saket Delhi NCR
 
8447779800, Low rate Call girls in Tughlakabad Delhi NCR
8447779800, Low rate Call girls in Tughlakabad Delhi NCR8447779800, Low rate Call girls in Tughlakabad Delhi NCR
8447779800, Low rate Call girls in Tughlakabad Delhi NCR
 
8447779800, Low rate Call girls in Rohini Delhi NCR
8447779800, Low rate Call girls in Rohini Delhi NCR8447779800, Low rate Call girls in Rohini Delhi NCR
8447779800, Low rate Call girls in Rohini Delhi NCR
 
Organizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessOrganizational Structure Running A Successful Business
Organizational Structure Running A Successful Business
 
Case study on tata clothing brand zudio in detail
Case study on tata clothing brand zudio in detailCase study on tata clothing brand zudio in detail
Case study on tata clothing brand zudio in detail
 
Annual General Meeting Presentation Slides
Annual General Meeting Presentation SlidesAnnual General Meeting Presentation Slides
Annual General Meeting Presentation Slides
 
MAHA Global and IPR: Do Actions Speak Louder Than Words?
MAHA Global and IPR: Do Actions Speak Louder Than Words?MAHA Global and IPR: Do Actions Speak Louder Than Words?
MAHA Global and IPR: Do Actions Speak Louder Than Words?
 
Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024
 
Memorándum de Entendimiento (MoU) entre Codelco y SQM
Memorándum de Entendimiento (MoU) entre Codelco y SQMMemorándum de Entendimiento (MoU) entre Codelco y SQM
Memorándum de Entendimiento (MoU) entre Codelco y SQM
 
Marketplace and Quality Assurance Presentation - Vincent Chirchir
Marketplace and Quality Assurance Presentation - Vincent ChirchirMarketplace and Quality Assurance Presentation - Vincent Chirchir
Marketplace and Quality Assurance Presentation - Vincent Chirchir
 
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort Service
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort ServiceCall US-88OO1O2216 Call Girls In Mahipalpur Female Escort Service
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort Service
 
Investment in The Coconut Industry by Nancy Cheruiyot
Investment in The Coconut Industry by Nancy CheruiyotInvestment in The Coconut Industry by Nancy Cheruiyot
Investment in The Coconut Industry by Nancy Cheruiyot
 
Kenya Coconut Production Presentation by Dr. Lalith Perera
Kenya Coconut Production Presentation by Dr. Lalith PereraKenya Coconut Production Presentation by Dr. Lalith Perera
Kenya Coconut Production Presentation by Dr. Lalith Perera
 
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
 
Market Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 EditionMarket Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 Edition
 
2024 Numerator Consumer Study of Cannabis Usage
2024 Numerator Consumer Study of Cannabis Usage2024 Numerator Consumer Study of Cannabis Usage
2024 Numerator Consumer Study of Cannabis Usage
 
Islamabad Escorts | Call 03070433345 | Escort Service in Islamabad
Islamabad Escorts | Call 03070433345 | Escort Service in IslamabadIslamabad Escorts | Call 03070433345 | Escort Service in Islamabad
Islamabad Escorts | Call 03070433345 | Escort Service in Islamabad
 
No-1 Call Girls In Goa 93193 VIP 73153 Escort service In North Goa Panaji, Ca...
No-1 Call Girls In Goa 93193 VIP 73153 Escort service In North Goa Panaji, Ca...No-1 Call Girls In Goa 93193 VIP 73153 Escort service In North Goa Panaji, Ca...
No-1 Call Girls In Goa 93193 VIP 73153 Escort service In North Goa Panaji, Ca...
 
Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03
 
International Business Environments and Operations 16th Global Edition test b...
International Business Environments and Operations 16th Global Edition test b...International Business Environments and Operations 16th Global Edition test b...
International Business Environments and Operations 16th Global Edition test b...
 

Free float and total float - PMP/CAPM from PMI

  • 1. Free Float The amount of duration in which the scheduled activity can be deferred without postponing the subsequent scheduled activities. In project management, free float refers to the duration that spans from the finishing point of a scheduled activity while extending to the upcoming planned activities. It is measured by subtracting the primary end of the activity from the early beginning of the subsequent activity. Once you identify the time period, subtract it from the expected total time of completion of the first activity. In case there is no following activity, you will primarily use the project end date to determine the free float window in the project network. Free float is only measured on the final activity in an activity sequence. It is calculated individually for each activity. Example: If an activity has a time period of six days and is occurring parallel with another activity which has a duration of nine days, the former will have approximately three days of total float. It can be postponed up to three days without affecting the overall project. On the other hand, if it is delayed by five days, it will come with a negative float situation i.e. – 2 days. This means that the project will take two more days than the expected duration. Project Float The duration in which the given task is delayed before it affects the deadline for the project. Project managers often use float time to schedule the certain time frames for the tasks to be accomplished on time. The project float doesn’t influence the deadlines of other following tasks. To make the most of the float, it’s important to determine the critical path and measure the amount of float in every non-critical task. Also, it helps in visualizing the project using Gantt chart. That way, you can reorganize tasks into specific chains and reassign the resources and work schedules accordingly to maximize efficiency. It’s important to revise float estimate as the project continues. For instance, if a specific task takes longer than expected, you may want to use the estimated float to compensate it. One simple way to calculate project float is to deduct the duration you have assigned
  • 2. to complete a task from the time the task will take in real. Suppose you have assigned 12 days for a task, though it only takes 8 days to complete. The approximate slack will be 4 days. Total Float aka Float The time period in which the scheduled activity may be postponed fromits early start date without deferring the project finish date or intermediate milestone. Total float refers to the amount of time an activity can be postponed without delaying the complete project duration. Project managers must know the estimated total float time available at the very beginning of the project. Total float refers to the delayed duration that doesn’t interfere with the project completion deadline. Since unexpected occurrences can happen anytime from poor weather conditions to the sudden emergency of a team member. For that reason, the project manager should estimate the total float so the project is finished on time. To find a total float, one important technique is to use a critical path that helps in identifying the earliest possible and latest finishing point. Preferably, a project should not go beyond the latest finish date to keep the project running on a defined schedule. Total float is calculated considering the difference between the initial and late start date (LS – ES) or the initial and late finish date (LF – EF). Total float is common between the
  • 3. activities in an arrangement. The structure is defined as the undertakings between a path convergence and path divergence. Important Notes on Free Float, Project Float and Total Float 1. Any project activity with a float time that equals 0 or with negative float is considered a critical path task. 2. Total Float is for the project and again for activities not on Critical Path 3. Free Float is on individual activities and those which are not on Critical Path 4. Buffers and Total Floats are not the same. Buffers are added as contingency reserves whereas total float is due to its placement in the Network Diagram. 5. Same like Buffers and Total Floats, Lags and Free Float are not the same. Lags are introduced by the scheduling team whereas Free Floats are because of their placement 6. An Activity may have different Free Float and Total Float Formula Free Float and Total Float  Total Float = LF – EF (or LS – ES)  Free Float = ES of next activity – EF Further Readings 1. Project Schedule Management 2. Planning Process Group