Cost Baseline and Cost Budget
The term baseline refers to an accepted and approved project plan. We may have
multiple intermediaries baselines. baselining is an activity is approving a particular
version of a document to be a reference for project work performance.
Cost Baseline
The cost baseline is a significant part of the project baseline that efficiently manages the approximate
amount of finance the project is predicted to cost. It refers to an approved budget typically in a time
distribution format that is used to estimate, monitor and control the inclusive cost performance of the
project.
When it comes to calculating the sum budget of the project, certain estimates are required to be done.
As soon as the project schedule is ready and agreed, a bottom-up process is used for every activity of
the project with an estimated detailed cost. In this way, the fairly accurate cost for every major phase
and complete project is computed. The initial finance of all planned practices becomes the initial
estimated budget.
According to PMBOK, the cost baseline is a time-phased budget used as a foundation
against which to compute and manage the financial subdivision of the task.
Though there are many factors affecting the cost performance of a project so the assessed costs
established in the planning phase might not be project precisely. The accurate costs of some
particular tasks if not well-known at the planning phase eventually lead to unexpected additional
cost. Cost Baseline is managed under configuration management,
Cost Baseline = Project Cost Estimates + Contingency Reserves
Cost Budget aka Project Budget
This is the process of aggregating the estimated costs of individual activities or work
packages to establish a cost baseline.
Project budget similar to resource plans is a reflection of project work and the effectiveness of that
work. An all-inclusive budget provides management with an understanding of how capitals are
utilized and consumed over time for projects. The Work Breakdown Structure (WBS) makes for a
basis for any budget. It comprises of work essentials to create the product of the project.
The WBS is shaped through a breakdown procedure resulting in defined deliverables at
the lowest level of the WBS – what is known as a work package or a task in project
insight.
Any effort executed in creating the deliverable of each task is often defined in terms of cost. For
instance, facilities and materials might be used in producing the deliverables of the task. The totality
of all tasks in the WBS comprises the sum budget of the project, initial costs of all of the planned
activities will become the initial estimated budget.. Project insights typically perform bottom-up
budgeting which means that the chores roll up into summary tasks totals while the overall project
represents the summation of all tasks planned and actual costs.
Cost Budget = Cost Baseline+ Management Reserves
Important Notes
1. Cost Baseline, an output of Determine Budget is part of the Project Management Plan. Project
Budget, which includes management reserves are not under the management of Project manager.
1. Cost baseline includes contingency Reserves
2. Project Budget includes Management Reserves
3. Project Cost Estimates = Summed Cost Estimates of All the activities on the Project
Source: free-management-ebooks.
Other Baselines
 Scope baseline – All the work and only the work included. It consists of Scope Statement, WBS
and WBS dictionary
 Schedule baseline – The project schedule and all other supporting elements
 Quality/Risk baseline – the set of known possible changes (uncertainties) that could impact the
performance of the project
The baselines are interconnected and should be evaluated for impact if one of it is changed. All
changes to the Baseline must go through proper change management processes.
“Never base your budget requests on realistic
assumptions, as this could lead to a decrease in your
funding.” – Scott Adams, Dilbert

Weitere ähnliche Inhalte

Was ist angesagt?

TEXTILE WET PROCESSING.pptx
TEXTILE WET PROCESSING.pptxTEXTILE WET PROCESSING.pptx
TEXTILE WET PROCESSING.pptxrinseyantonyVA
 
Fabric Testing and quality control
Fabric Testing and quality controlFabric Testing and quality control
Fabric Testing and quality controllutuf Ullah
 
Process Control For Spinning.pdf
Process Control For Spinning.pdfProcess Control For Spinning.pdf
Process Control For Spinning.pdfPrincessQueen12
 
Project Manager Job Description
Project Manager Job DescriptionProject Manager Job Description
Project Manager Job DescriptionTrevor Rutter
 
textile printing defects yogesh
textile printing defects yogeshtextile printing defects yogesh
textile printing defects yogeshMulti Addiction
 
Project Procurement Planning
Project Procurement PlanningProject Procurement Planning
Project Procurement PlanningMartin Sillaots
 
Project cost stimating
Project cost stimatingProject cost stimating
Project cost stimatinghatim ahmed
 
Project scope, schedule, cost, quality Management
Project scope, schedule, cost, quality ManagementProject scope, schedule, cost, quality Management
Project scope, schedule, cost, quality ManagementHaykanush Ayvazyan, PMP
 
Garments Export Documents for a merchandiser
Garments Export Documents for a merchandiser Garments Export Documents for a merchandiser
Garments Export Documents for a merchandiser Md. Mazadul Hasan Shishir
 
Denim process internship report
Denim  process internship reportDenim  process internship report
Denim process internship reportSalim Chohan
 
MS Project Terminology -Top 20 terms everyone must know
MS Project Terminology -Top 20 terms everyone must knowMS Project Terminology -Top 20 terms everyone must know
MS Project Terminology -Top 20 terms everyone must knowSHAZEBALIKHAN1
 
Nonwoven Presentation
Nonwoven PresentationNonwoven Presentation
Nonwoven Presentationalaminmasum1
 
Procurement in construction
Procurement in constructionProcurement in construction
Procurement in constructionMahSobeh
 

Was ist angesagt? (20)

TEXTILE WET PROCESSING.pptx
TEXTILE WET PROCESSING.pptxTEXTILE WET PROCESSING.pptx
TEXTILE WET PROCESSING.pptx
 
Project scheduling
Project schedulingProject scheduling
Project scheduling
 
Fabric Testing and quality control
Fabric Testing and quality controlFabric Testing and quality control
Fabric Testing and quality control
 
Cost Management PMBOK
Cost Management PMBOKCost Management PMBOK
Cost Management PMBOK
 
Process Control For Spinning.pdf
Process Control For Spinning.pdfProcess Control For Spinning.pdf
Process Control For Spinning.pdf
 
Fabric spreading
Fabric spreadingFabric spreading
Fabric spreading
 
Project Manager Job Description
Project Manager Job DescriptionProject Manager Job Description
Project Manager Job Description
 
textile printing defects yogesh
textile printing defects yogeshtextile printing defects yogesh
textile printing defects yogesh
 
CCP_SEC2_ Cost Estimating
CCP_SEC2_ Cost EstimatingCCP_SEC2_ Cost Estimating
CCP_SEC2_ Cost Estimating
 
Garment washing
Garment washingGarment washing
Garment washing
 
Project Procurement Planning
Project Procurement PlanningProject Procurement Planning
Project Procurement Planning
 
Project cost stimating
Project cost stimatingProject cost stimating
Project cost stimating
 
Project scope, schedule, cost, quality Management
Project scope, schedule, cost, quality ManagementProject scope, schedule, cost, quality Management
Project scope, schedule, cost, quality Management
 
Garments Export Documents for a merchandiser
Garments Export Documents for a merchandiser Garments Export Documents for a merchandiser
Garments Export Documents for a merchandiser
 
Denim process internship report
Denim  process internship reportDenim  process internship report
Denim process internship report
 
MS Project Terminology -Top 20 terms everyone must know
MS Project Terminology -Top 20 terms everyone must knowMS Project Terminology -Top 20 terms everyone must know
MS Project Terminology -Top 20 terms everyone must know
 
Nonwoven Presentation
Nonwoven PresentationNonwoven Presentation
Nonwoven Presentation
 
Sampling Department
Sampling DepartmentSampling Department
Sampling Department
 
Process control of weaving process
Process control of weaving processProcess control of weaving process
Process control of weaving process
 
Procurement in construction
Procurement in constructionProcurement in construction
Procurement in construction
 

Ähnlich wie Cost baseline and cost budget

CPM lecture note 4,5,6&7.pdf
CPM lecture note 4,5,6&7.pdfCPM lecture note 4,5,6&7.pdf
CPM lecture note 4,5,6&7.pdfDejeneTsegaye6
 
CPM lecture note 4,5,6&7.pdf
CPM lecture note 4,5,6&7.pdfCPM lecture note 4,5,6&7.pdf
CPM lecture note 4,5,6&7.pdfDejeneTsegaye6
 
Budget and cost estimates - PMP/CAPM from PMI
Budget and cost estimates - PMP/CAPM from PMIBudget and cost estimates - PMP/CAPM from PMI
Budget and cost estimates - PMP/CAPM from PMIMudassir Iqbal
 
Project Budget.pptx.ppt
Project Budget.pptx.pptProject Budget.pptx.ppt
Project Budget.pptx.pptDejeneTsegaye6
 
3 pm3 c_3%20-%20the%20program%20budget
3 pm3 c_3%20-%20the%20program%20budget3 pm3 c_3%20-%20the%20program%20budget
3 pm3 c_3%20-%20the%20program%20budgetharwoodr
 
Wbs & Project Scheduling
Wbs & Project SchedulingWbs & Project Scheduling
Wbs & Project Schedulingsslovepk
 
2.07 cost management 1
2.07 cost management 12.07 cost management 1
2.07 cost management 1reddvise
 
3 pm3 c_2-%20estimating%20costs
3 pm3 c_2-%20estimating%20costs3 pm3 c_2-%20estimating%20costs
3 pm3 c_2-%20estimating%20costsharwoodr
 
Control account, work and planning package - PMP/CAPM from PMI
Control account, work and planning package - PMP/CAPM from PMIControl account, work and planning package - PMP/CAPM from PMI
Control account, work and planning package - PMP/CAPM from PMIMudassir Iqbal
 
Day 7 Project Cost Management .pdf
Day 7 Project Cost Management .pdfDay 7 Project Cost Management .pdf
Day 7 Project Cost Management .pdfMadhusha15
 
engineering economics lect 8-10 final.pptx
engineering economics lect 8-10 final.pptxengineering economics lect 8-10 final.pptx
engineering economics lect 8-10 final.pptxDr. ABEER KHALID MANSOUR
 
Software Project Cost Management and estimation
Software Project Cost Management and estimationSoftware Project Cost Management and estimation
Software Project Cost Management and estimationssuser9d62d6
 
Work Breakdown Structure Aritrya Kumar.pptx
Work Breakdown Structure Aritrya Kumar.pptxWork Breakdown Structure Aritrya Kumar.pptx
Work Breakdown Structure Aritrya Kumar.pptxARITRYAKUMAR
 
Software Project Management: Budget
Software Project Management: BudgetSoftware Project Management: Budget
Software Project Management: BudgetMinhas Kamal
 
5.Chapter Five.pptx
5.Chapter Five.pptx5.Chapter Five.pptx
5.Chapter Five.pptxAberraBeri
 

Ähnlich wie Cost baseline and cost budget (20)

CPM lecture note 4,5,6&7.pdf
CPM lecture note 4,5,6&7.pdfCPM lecture note 4,5,6&7.pdf
CPM lecture note 4,5,6&7.pdf
 
CPM lecture note 4,5,6&7.pdf
CPM lecture note 4,5,6&7.pdfCPM lecture note 4,5,6&7.pdf
CPM lecture note 4,5,6&7.pdf
 
Budget and cost estimates - PMP/CAPM from PMI
Budget and cost estimates - PMP/CAPM from PMIBudget and cost estimates - PMP/CAPM from PMI
Budget and cost estimates - PMP/CAPM from PMI
 
Project Budget.pptx.ppt
Project Budget.pptx.pptProject Budget.pptx.ppt
Project Budget.pptx.ppt
 
Wbs, gant charts
Wbs, gant chartsWbs, gant charts
Wbs, gant charts
 
3 pm3 c_3%20-%20the%20program%20budget
3 pm3 c_3%20-%20the%20program%20budget3 pm3 c_3%20-%20the%20program%20budget
3 pm3 c_3%20-%20the%20program%20budget
 
Construction Cost Control
Construction Cost ControlConstruction Cost Control
Construction Cost Control
 
Wbs & Project Scheduling
Wbs & Project SchedulingWbs & Project Scheduling
Wbs & Project Scheduling
 
EVA - Metrics.ppt
EVA - Metrics.pptEVA - Metrics.ppt
EVA - Metrics.ppt
 
Project cost control
Project cost controlProject cost control
Project cost control
 
2.07 cost management 1
2.07 cost management 12.07 cost management 1
2.07 cost management 1
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
 
3 pm3 c_2-%20estimating%20costs
3 pm3 c_2-%20estimating%20costs3 pm3 c_2-%20estimating%20costs
3 pm3 c_2-%20estimating%20costs
 
Control account, work and planning package - PMP/CAPM from PMI
Control account, work and planning package - PMP/CAPM from PMIControl account, work and planning package - PMP/CAPM from PMI
Control account, work and planning package - PMP/CAPM from PMI
 
Day 7 Project Cost Management .pdf
Day 7 Project Cost Management .pdfDay 7 Project Cost Management .pdf
Day 7 Project Cost Management .pdf
 
engineering economics lect 8-10 final.pptx
engineering economics lect 8-10 final.pptxengineering economics lect 8-10 final.pptx
engineering economics lect 8-10 final.pptx
 
Software Project Cost Management and estimation
Software Project Cost Management and estimationSoftware Project Cost Management and estimation
Software Project Cost Management and estimation
 
Work Breakdown Structure Aritrya Kumar.pptx
Work Breakdown Structure Aritrya Kumar.pptxWork Breakdown Structure Aritrya Kumar.pptx
Work Breakdown Structure Aritrya Kumar.pptx
 
Software Project Management: Budget
Software Project Management: BudgetSoftware Project Management: Budget
Software Project Management: Budget
 
5.Chapter Five.pptx
5.Chapter Five.pptx5.Chapter Five.pptx
5.Chapter Five.pptx
 

Mehr von Mudassir Iqbal

Quality assurance and control quality - PMP/CAPM by PMI
Quality assurance and control quality - PMP/CAPM by PMIQuality assurance and control quality - PMP/CAPM by PMI
Quality assurance and control quality - PMP/CAPM by PMIMudassir Iqbal
 
Residual risk and secondary risk - PMP/CAPM from PMI
Residual risk and secondary risk - PMP/CAPM from PMIResidual risk and secondary risk - PMP/CAPM from PMI
Residual risk and secondary risk - PMP/CAPM from PMIMudassir Iqbal
 
Free float and total float - PMP/CAPM from PMI
Free float and total float - PMP/CAPM from PMIFree float and total float - PMP/CAPM from PMI
Free float and total float - PMP/CAPM from PMIMudassir Iqbal
 
Event and Non-Event Risk - PMP/CAPM from PMI
Event and Non-Event Risk  - PMP/CAPM from PMIEvent and Non-Event Risk  - PMP/CAPM from PMI
Event and Non-Event Risk - PMP/CAPM from PMIMudassir Iqbal
 
EEF and OPA - PMP/CAPM from PMI
EEF and OPA - PMP/CAPM from PMIEEF and OPA - PMP/CAPM from PMI
EEF and OPA - PMP/CAPM from PMIMudassir Iqbal
 
Project scope Management - PMP/CAPM
Project scope Management - PMP/CAPMProject scope Management - PMP/CAPM
Project scope Management - PMP/CAPMMudassir Iqbal
 
Project schedule Management - PMP/CAPM
Project schedule Management - PMP/CAPMProject schedule Management - PMP/CAPM
Project schedule Management - PMP/CAPMMudassir Iqbal
 
Project Cost Management - PMP/CAPM
Project Cost Management - PMP/CAPMProject Cost Management - PMP/CAPM
Project Cost Management - PMP/CAPMMudassir Iqbal
 
Project procurement Management - PMP/CAPM
Project procurement  Management - PMP/CAPMProject procurement  Management - PMP/CAPM
Project procurement Management - PMP/CAPMMudassir Iqbal
 
Planning process group
Planning process groupPlanning process group
Planning process groupMudassir Iqbal
 
Executing process group
Executing process groupExecuting process group
Executing process groupMudassir Iqbal
 
Master schedule and milestone schedule
Master schedule and milestone scheduleMaster schedule and milestone schedule
Master schedule and milestone scheduleMudassir Iqbal
 
Babok2 chapter9 daxko
Babok2 chapter9 daxko Babok2 chapter9 daxko
Babok2 chapter9 daxko Mudassir Iqbal
 

Mehr von Mudassir Iqbal (15)

Quality assurance and control quality - PMP/CAPM by PMI
Quality assurance and control quality - PMP/CAPM by PMIQuality assurance and control quality - PMP/CAPM by PMI
Quality assurance and control quality - PMP/CAPM by PMI
 
Residual risk and secondary risk - PMP/CAPM from PMI
Residual risk and secondary risk - PMP/CAPM from PMIResidual risk and secondary risk - PMP/CAPM from PMI
Residual risk and secondary risk - PMP/CAPM from PMI
 
Free float and total float - PMP/CAPM from PMI
Free float and total float - PMP/CAPM from PMIFree float and total float - PMP/CAPM from PMI
Free float and total float - PMP/CAPM from PMI
 
Event and Non-Event Risk - PMP/CAPM from PMI
Event and Non-Event Risk  - PMP/CAPM from PMIEvent and Non-Event Risk  - PMP/CAPM from PMI
Event and Non-Event Risk - PMP/CAPM from PMI
 
EEF and OPA - PMP/CAPM from PMI
EEF and OPA - PMP/CAPM from PMIEEF and OPA - PMP/CAPM from PMI
EEF and OPA - PMP/CAPM from PMI
 
Project scope Management - PMP/CAPM
Project scope Management - PMP/CAPMProject scope Management - PMP/CAPM
Project scope Management - PMP/CAPM
 
Project schedule Management - PMP/CAPM
Project schedule Management - PMP/CAPMProject schedule Management - PMP/CAPM
Project schedule Management - PMP/CAPM
 
Project Cost Management - PMP/CAPM
Project Cost Management - PMP/CAPMProject Cost Management - PMP/CAPM
Project Cost Management - PMP/CAPM
 
Project procurement Management - PMP/CAPM
Project procurement  Management - PMP/CAPMProject procurement  Management - PMP/CAPM
Project procurement Management - PMP/CAPM
 
Planning process group
Planning process groupPlanning process group
Planning process group
 
Executing process group
Executing process groupExecuting process group
Executing process group
 
Closing process group
Closing process groupClosing process group
Closing process group
 
Master schedule and milestone schedule
Master schedule and milestone scheduleMaster schedule and milestone schedule
Master schedule and milestone schedule
 
Quality and Grade
Quality and GradeQuality and Grade
Quality and Grade
 
Babok2 chapter9 daxko
Babok2 chapter9 daxko Babok2 chapter9 daxko
Babok2 chapter9 daxko
 

Kürzlich hochgeladen

APRIL2024_UKRAINE_xml_0000000000000 .pdf
APRIL2024_UKRAINE_xml_0000000000000 .pdfAPRIL2024_UKRAINE_xml_0000000000000 .pdf
APRIL2024_UKRAINE_xml_0000000000000 .pdfRbc Rbcua
 
Unveiling the Soundscape Music for Psychedelic Experiences
Unveiling the Soundscape Music for Psychedelic ExperiencesUnveiling the Soundscape Music for Psychedelic Experiences
Unveiling the Soundscape Music for Psychedelic ExperiencesDoe Paoro
 
BAILMENT & PLEDGE business law notes.pptx
BAILMENT & PLEDGE business law notes.pptxBAILMENT & PLEDGE business law notes.pptx
BAILMENT & PLEDGE business law notes.pptxran17april2001
 
Pitch Deck Teardown: Xpanceo's $40M Seed deck
Pitch Deck Teardown: Xpanceo's $40M Seed deckPitch Deck Teardown: Xpanceo's $40M Seed deck
Pitch Deck Teardown: Xpanceo's $40M Seed deckHajeJanKamps
 
Memorándum de Entendimiento (MoU) entre Codelco y SQM
Memorándum de Entendimiento (MoU) entre Codelco y SQMMemorándum de Entendimiento (MoU) entre Codelco y SQM
Memorándum de Entendimiento (MoU) entre Codelco y SQMVoces Mineras
 
PSCC - Capability Statement Presentation
PSCC - Capability Statement PresentationPSCC - Capability Statement Presentation
PSCC - Capability Statement PresentationAnamaria Contreras
 
Healthcare Feb. & Mar. Healthcare Newsletter
Healthcare Feb. & Mar. Healthcare NewsletterHealthcare Feb. & Mar. Healthcare Newsletter
Healthcare Feb. & Mar. Healthcare NewsletterJamesConcepcion7
 
Supercharge Your eCommerce Stores-acowebs
Supercharge Your eCommerce Stores-acowebsSupercharge Your eCommerce Stores-acowebs
Supercharge Your eCommerce Stores-acowebsGOKUL JS
 
Lucia Ferretti, Lead Business Designer; Matteo Meschini, Business Designer @T...
Lucia Ferretti, Lead Business Designer; Matteo Meschini, Business Designer @T...Lucia Ferretti, Lead Business Designer; Matteo Meschini, Business Designer @T...
Lucia Ferretti, Lead Business Designer; Matteo Meschini, Business Designer @T...Associazione Digital Days
 
Church Building Grants To Assist With New Construction, Additions, And Restor...
Church Building Grants To Assist With New Construction, Additions, And Restor...Church Building Grants To Assist With New Construction, Additions, And Restor...
Church Building Grants To Assist With New Construction, Additions, And Restor...Americas Got Grants
 
20200128 Ethical by Design - Whitepaper.pdf
20200128 Ethical by Design - Whitepaper.pdf20200128 Ethical by Design - Whitepaper.pdf
20200128 Ethical by Design - Whitepaper.pdfChris Skinner
 
Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.Anamaria Contreras
 
Darshan Hiranandani [News About Next CEO].pdf
Darshan Hiranandani [News About Next CEO].pdfDarshan Hiranandani [News About Next CEO].pdf
Darshan Hiranandani [News About Next CEO].pdfShashank Mehta
 
How Generative AI Is Transforming Your Business | Byond Growth Insights | Apr...
How Generative AI Is Transforming Your Business | Byond Growth Insights | Apr...How Generative AI Is Transforming Your Business | Byond Growth Insights | Apr...
How Generative AI Is Transforming Your Business | Byond Growth Insights | Apr...Hector Del Castillo, CPM, CPMM
 
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptxThe-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptxmbikashkanyari
 
business environment micro environment macro environment.pptx
business environment micro environment macro environment.pptxbusiness environment micro environment macro environment.pptx
business environment micro environment macro environment.pptxShruti Mittal
 
Go for Rakhi Bazaar and Pick the Latest Bhaiya Bhabhi Rakhi.pptx
Go for Rakhi Bazaar and Pick the Latest Bhaiya Bhabhi Rakhi.pptxGo for Rakhi Bazaar and Pick the Latest Bhaiya Bhabhi Rakhi.pptx
Go for Rakhi Bazaar and Pick the Latest Bhaiya Bhabhi Rakhi.pptxRakhi Bazaar
 
Onemonitar Android Spy App Features: Explore Advanced Monitoring Capabilities
Onemonitar Android Spy App Features: Explore Advanced Monitoring CapabilitiesOnemonitar Android Spy App Features: Explore Advanced Monitoring Capabilities
Onemonitar Android Spy App Features: Explore Advanced Monitoring CapabilitiesOne Monitar
 

Kürzlich hochgeladen (20)

APRIL2024_UKRAINE_xml_0000000000000 .pdf
APRIL2024_UKRAINE_xml_0000000000000 .pdfAPRIL2024_UKRAINE_xml_0000000000000 .pdf
APRIL2024_UKRAINE_xml_0000000000000 .pdf
 
Unveiling the Soundscape Music for Psychedelic Experiences
Unveiling the Soundscape Music for Psychedelic ExperiencesUnveiling the Soundscape Music for Psychedelic Experiences
Unveiling the Soundscape Music for Psychedelic Experiences
 
BAILMENT & PLEDGE business law notes.pptx
BAILMENT & PLEDGE business law notes.pptxBAILMENT & PLEDGE business law notes.pptx
BAILMENT & PLEDGE business law notes.pptx
 
Pitch Deck Teardown: Xpanceo's $40M Seed deck
Pitch Deck Teardown: Xpanceo's $40M Seed deckPitch Deck Teardown: Xpanceo's $40M Seed deck
Pitch Deck Teardown: Xpanceo's $40M Seed deck
 
Memorándum de Entendimiento (MoU) entre Codelco y SQM
Memorándum de Entendimiento (MoU) entre Codelco y SQMMemorándum de Entendimiento (MoU) entre Codelco y SQM
Memorándum de Entendimiento (MoU) entre Codelco y SQM
 
PSCC - Capability Statement Presentation
PSCC - Capability Statement PresentationPSCC - Capability Statement Presentation
PSCC - Capability Statement Presentation
 
Healthcare Feb. & Mar. Healthcare Newsletter
Healthcare Feb. & Mar. Healthcare NewsletterHealthcare Feb. & Mar. Healthcare Newsletter
Healthcare Feb. & Mar. Healthcare Newsletter
 
The Bizz Quiz-E-Summit-E-Cell-IITPatna.pptx
The Bizz Quiz-E-Summit-E-Cell-IITPatna.pptxThe Bizz Quiz-E-Summit-E-Cell-IITPatna.pptx
The Bizz Quiz-E-Summit-E-Cell-IITPatna.pptx
 
Supercharge Your eCommerce Stores-acowebs
Supercharge Your eCommerce Stores-acowebsSupercharge Your eCommerce Stores-acowebs
Supercharge Your eCommerce Stores-acowebs
 
Lucia Ferretti, Lead Business Designer; Matteo Meschini, Business Designer @T...
Lucia Ferretti, Lead Business Designer; Matteo Meschini, Business Designer @T...Lucia Ferretti, Lead Business Designer; Matteo Meschini, Business Designer @T...
Lucia Ferretti, Lead Business Designer; Matteo Meschini, Business Designer @T...
 
Church Building Grants To Assist With New Construction, Additions, And Restor...
Church Building Grants To Assist With New Construction, Additions, And Restor...Church Building Grants To Assist With New Construction, Additions, And Restor...
Church Building Grants To Assist With New Construction, Additions, And Restor...
 
20200128 Ethical by Design - Whitepaper.pdf
20200128 Ethical by Design - Whitepaper.pdf20200128 Ethical by Design - Whitepaper.pdf
20200128 Ethical by Design - Whitepaper.pdf
 
Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.
 
Darshan Hiranandani [News About Next CEO].pdf
Darshan Hiranandani [News About Next CEO].pdfDarshan Hiranandani [News About Next CEO].pdf
Darshan Hiranandani [News About Next CEO].pdf
 
How Generative AI Is Transforming Your Business | Byond Growth Insights | Apr...
How Generative AI Is Transforming Your Business | Byond Growth Insights | Apr...How Generative AI Is Transforming Your Business | Byond Growth Insights | Apr...
How Generative AI Is Transforming Your Business | Byond Growth Insights | Apr...
 
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptxThe-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
 
business environment micro environment macro environment.pptx
business environment micro environment macro environment.pptxbusiness environment micro environment macro environment.pptx
business environment micro environment macro environment.pptx
 
Go for Rakhi Bazaar and Pick the Latest Bhaiya Bhabhi Rakhi.pptx
Go for Rakhi Bazaar and Pick the Latest Bhaiya Bhabhi Rakhi.pptxGo for Rakhi Bazaar and Pick the Latest Bhaiya Bhabhi Rakhi.pptx
Go for Rakhi Bazaar and Pick the Latest Bhaiya Bhabhi Rakhi.pptx
 
WAM Corporate Presentation April 12 2024.pdf
WAM Corporate Presentation April 12 2024.pdfWAM Corporate Presentation April 12 2024.pdf
WAM Corporate Presentation April 12 2024.pdf
 
Onemonitar Android Spy App Features: Explore Advanced Monitoring Capabilities
Onemonitar Android Spy App Features: Explore Advanced Monitoring CapabilitiesOnemonitar Android Spy App Features: Explore Advanced Monitoring Capabilities
Onemonitar Android Spy App Features: Explore Advanced Monitoring Capabilities
 

Cost baseline and cost budget

  • 1. Cost Baseline and Cost Budget The term baseline refers to an accepted and approved project plan. We may have multiple intermediaries baselines. baselining is an activity is approving a particular version of a document to be a reference for project work performance. Cost Baseline The cost baseline is a significant part of the project baseline that efficiently manages the approximate amount of finance the project is predicted to cost. It refers to an approved budget typically in a time distribution format that is used to estimate, monitor and control the inclusive cost performance of the project. When it comes to calculating the sum budget of the project, certain estimates are required to be done. As soon as the project schedule is ready and agreed, a bottom-up process is used for every activity of the project with an estimated detailed cost. In this way, the fairly accurate cost for every major phase and complete project is computed. The initial finance of all planned practices becomes the initial estimated budget. According to PMBOK, the cost baseline is a time-phased budget used as a foundation against which to compute and manage the financial subdivision of the task. Though there are many factors affecting the cost performance of a project so the assessed costs established in the planning phase might not be project precisely. The accurate costs of some particular tasks if not well-known at the planning phase eventually lead to unexpected additional cost. Cost Baseline is managed under configuration management, Cost Baseline = Project Cost Estimates + Contingency Reserves Cost Budget aka Project Budget This is the process of aggregating the estimated costs of individual activities or work packages to establish a cost baseline. Project budget similar to resource plans is a reflection of project work and the effectiveness of that work. An all-inclusive budget provides management with an understanding of how capitals are utilized and consumed over time for projects. The Work Breakdown Structure (WBS) makes for a basis for any budget. It comprises of work essentials to create the product of the project. The WBS is shaped through a breakdown procedure resulting in defined deliverables at the lowest level of the WBS – what is known as a work package or a task in project insight. Any effort executed in creating the deliverable of each task is often defined in terms of cost. For instance, facilities and materials might be used in producing the deliverables of the task. The totality of all tasks in the WBS comprises the sum budget of the project, initial costs of all of the planned activities will become the initial estimated budget.. Project insights typically perform bottom-up
  • 2. budgeting which means that the chores roll up into summary tasks totals while the overall project represents the summation of all tasks planned and actual costs. Cost Budget = Cost Baseline+ Management Reserves Important Notes 1. Cost Baseline, an output of Determine Budget is part of the Project Management Plan. Project Budget, which includes management reserves are not under the management of Project manager. 1. Cost baseline includes contingency Reserves 2. Project Budget includes Management Reserves 3. Project Cost Estimates = Summed Cost Estimates of All the activities on the Project Source: free-management-ebooks. Other Baselines  Scope baseline – All the work and only the work included. It consists of Scope Statement, WBS and WBS dictionary  Schedule baseline – The project schedule and all other supporting elements  Quality/Risk baseline – the set of known possible changes (uncertainties) that could impact the performance of the project The baselines are interconnected and should be evaluated for impact if one of it is changed. All changes to the Baseline must go through proper change management processes. “Never base your budget requests on realistic assumptions, as this could lead to a decrease in your funding.” – Scott Adams, Dilbert