This is the long presentation that goes along with the Lean Lego Game. It's about three hours long.
See full article here: https://www.isixsigma.com/training/training-materials-aids/lean-lego-game/
Good Stuff Happens in 1:1 Meetings: Why you need them and how to do them well
Lean Lego Game Slides - Long Presentation
1. THIS MATERIAL MUST NOT BE USED FOR COMMERCIAL PURPOSES.
The Lean Lego Game
Tuesday, 11 February 14
2. THIS MATERIAL MUST NOT BE USED FOR COMMERCIAL PURPOSES.
Quick Introduction
Simulating a production line
How about software ?
Agenda
Tuesday, 11 February 14
3. THIS MATERIAL MUST NOT BE USED FOR COMMERCIAL PURPOSES.
Process
Tuesday, 11 February 14
4. THIS MATERIAL MUST NOT BE USED FOR COMMERCIAL PURPOSES.
Hands On
Results
Debriefing
Process
Tuesday, 11 February 14
5. THIS MATERIAL MUST NOT BE USED FOR COMMERCIAL PURPOSES.
Hands On
Results
Debriefing
Process
3x
Tuesday, 11 February 14
6. THIS MATERIAL MUST NOT BE USED FOR COMMERCIAL PURPOSES.
Why ?
Tuesday, 11 February 14
7. THIS MATERIAL MUST NOT BE USED FOR COMMERCIAL PURPOSES.
But without much contact
with Lean principles and
practices
Lean concepts
being used in the
software world
Why ?
Tuesday, 11 February 14
8. THIS MATERIAL MUST NOT BE USED FOR COMMERCIAL PURPOSES.
Tuesday, 11 February 14
9. THIS MATERIAL MUST NOT BE USED FOR COMMERCIAL PURPOSES.
“... over the years there have been some
ostensibly ‘lean’ promoters that reduced lean
thinking to a mechanistic superficial level of
management tools such as kanban and queue
management.
... the essence of successful lean thinking is
building people, then building products and a
culture of “challenge the status quo
continuous improvement ” Lean Primer (http://tinyurl.com/owvhut)
Tuesday, 11 February 14
10. THIS MATERIAL MUST NOT BE USED FOR COMMERCIAL PURPOSES.
We’re here to introduce you to Lean
“... over the years there have been some
ostensibly ‘lean’ promoters that reduced lean
thinking to a mechanistic superficial level of
management tools such as kanban and queue
management.
... the essence of successful lean thinking is
building people, then building products and a
culture of “challenge the status quo
continuous improvement ” Lean Primer (http://tinyurl.com/owvhut)
Tuesday, 11 February 14
11. THIS MATERIAL MUST NOT BE USED FOR COMMERCIAL PURPOSES.
LeanLean
Tuesday, 11 February 14
12. THIS MATERIAL MUST NOT BE USED FOR COMMERCIAL PURPOSES.
Toyota Production
System
Toyota Production
System
Tuesday, 11 February 14
13. THIS MATERIAL MUST NOT BE USED FOR COMMERCIAL PURPOSES.
Tuesday, 11 February 14
14. THIS MATERIAL MUST NOT BE USED FOR COMMERCIAL PURPOSES.
Revolutionized
manufacturing
Tuesday, 11 February 14
15. THIS MATERIAL MUST NOT BE USED FOR COMMERCIAL PURPOSES.
Revolutionized
manufacturing
Applied to
different areas
Tuesday, 11 February 14
16. THIS MATERIAL MUST NOT BE USED FOR COMMERCIAL PURPOSES.
What we want to show
Tuesday, 11 February 14
17. THIS MATERIAL MUST NOT BE USED FOR COMMERCIAL PURPOSES.
What we want to show
Push
Tuesday, 11 February 14
18. THIS MATERIAL MUST NOT BE USED FOR COMMERCIAL PURPOSES.
What we want to show
Push
Pull
Tuesday, 11 February 14
19. THIS MATERIAL MUST NOT BE USED FOR COMMERCIAL PURPOSES.
What we want to show
Push
Pull
Flow
Tuesday, 11 February 14
20. THIS MATERIAL MUST NOT BE USED FOR COMMERCIAL PURPOSES.
What we want to show
Push
Pull
Flow
Systems Thinking
Tuesday, 11 February 14
21. THIS MATERIAL MUST NOT BE USED FOR COMMERCIAL PURPOSES.
What we want to show
Push
Pull
Flow
Systems Thinking
Yatai
Tuesday, 11 February 14
22. THIS MATERIAL MUST NOT BE USED FOR COMMERCIAL PURPOSES.
What we want to show
Push
Pull
Flow
Systems Thinking
Yatai
Heijunka
Tuesday, 11 February 14
23. THIS MATERIAL MUST NOT BE USED FOR COMMERCIAL PURPOSES.
Hands on - 1st Step
Tuesday, 11 February 14
24. THIS MATERIAL MUST NOT BE USED FOR COMMERCIAL PURPOSES.
Task 1 Task 2 Task 3 Task 4
Hands on - 1st Step
Tuesday, 11 February 14
25. THIS MATERIAL MUST NOT BE USED FOR COMMERCIAL PURPOSES.
Task 1 Task 2 Task 3 Task 4
Hands on - 1st Step
4 Teams
30 secs
4 Rounds
Tuesday, 11 February 14
26. THIS MATERIAL MUST NOT BE USED FOR COMMERCIAL PURPOSES.
Task 1 Task 2 Task 3 Task 4
Hands on - 1st Step
Follow the instructions
Build houses
1 Piece = $ 1.00
1 House = $ 25.00
Tuesday, 11 February 14
27. THIS MATERIAL MUST NOT BE USED FOR COMMERCIAL PURPOSES.
Tuesday, 11 February 14
28. THIS MATERIAL MUST NOT BE USED FOR COMMERCIAL PURPOSES.
Tuesday, 11 February 14
29. THIS MATERIAL MUST NOT BE USED FOR COMMERCIAL PURPOSES.
What went wrong ?
Houston, we have a problem...
Tuesday, 11 February 14
30. THIS MATERIAL MUST NOT BE USED FOR COMMERCIAL PURPOSES.
Visible Inventory
Over/Under Production
Waste
Tuesday, 11 February 14
31. THIS MATERIAL MUST NOT BE USED FOR COMMERCIAL PURPOSES.
Visible Inventory
Over/Under Production
Waste
Tuesday, 11 February 14
32. THIS MATERIAL MUST NOT BE USED FOR COMMERCIAL PURPOSES.
Visible Inventory
Over/Under Production
Waste
0
175
350
525
700
0 1 2 3 4
Task 1
Task 2
Task 3
Task 4
Tuesday, 11 February 14
33. THIS MATERIAL MUST NOT BE USED FOR COMMERCIAL PURPOSES.
7 Wastes of Manufacturing
Tuesday, 11 February 14
34. THIS MATERIAL MUST NOT BE USED FOR COMMERCIAL PURPOSES.
7 Wastes of Manufacturing
Overproduction
Tuesday, 11 February 14
35. THIS MATERIAL MUST NOT BE USED FOR COMMERCIAL PURPOSES.
7 Wastes of Manufacturing
Overproduction
Waiting
Tuesday, 11 February 14
36. THIS MATERIAL MUST NOT BE USED FOR COMMERCIAL PURPOSES.
7 Wastes of Manufacturing
Overproduction
Waiting
Overprocessing
Tuesday, 11 February 14
37. THIS MATERIAL MUST NOT BE USED FOR COMMERCIAL PURPOSES.
7 Wastes of Manufacturing
Overproduction
Waiting
Unnecessary
Transportation
Overprocessing
Tuesday, 11 February 14
38. THIS MATERIAL MUST NOT BE USED FOR COMMERCIAL PURPOSES.
7 Wastes of Manufacturing
Overproduction
Waiting
Unnecessary
Transportation
Overprocessing
Inventory
Tuesday, 11 February 14
39. THIS MATERIAL MUST NOT BE USED FOR COMMERCIAL PURPOSES.
7 Wastes of Manufacturing
Overproduction
Waiting
Unnecessary
Transportation
Overprocessing
Inventory
Motion
Tuesday, 11 February 14
40. THIS MATERIAL MUST NOT BE USED FOR COMMERCIAL PURPOSES.
7 Wastes of Manufacturing
Overproduction
Waiting
Unnecessary
Transportation
Overprocessing
Inventory
Motion
Defects
Tuesday, 11 February 14
41. THIS MATERIAL MUST NOT BE USED FOR COMMERCIAL PURPOSES.
Push and Pull Systems
Tuesday, 11 February 14
42. THIS MATERIAL MUST NOT BE USED FOR COMMERCIAL PURPOSES.
Push and Pull Systems
Push
Tuesday, 11 February 14
43. THIS MATERIAL MUST NOT BE USED FOR COMMERCIAL PURPOSES.
Push and Pull Systems
Push
Expected
Demand
Tuesday, 11 February 14
44. THIS MATERIAL MUST NOT BE USED FOR COMMERCIAL PURPOSES.
Push and Pull Systems
Push
Expected
Demand
Mass
Production
Tuesday, 11 February 14
45. THIS MATERIAL MUST NOT BE USED FOR COMMERCIAL PURPOSES.
Push and Pull Systems
Push
Expected
Demand
Mass
Production
Economies
of Scale
Tuesday, 11 February 14
46. THIS MATERIAL MUST NOT BE USED FOR COMMERCIAL PURPOSES.
Push and Pull Systems
Push
Tuesday, 11 February 14
47. THIS MATERIAL MUST NOT BE USED FOR COMMERCIAL PURPOSES.
Push and Pull Systems
Push
“Any colour, as
long as it’s black”
Henry Ford
Tuesday, 11 February 14
48. THIS MATERIAL MUST NOT BE USED FOR COMMERCIAL PURPOSES.
Push and Pull Systems
Push
Mass
Production
Economies
of Scale
Expected
Demand
Tuesday, 11 February 14
49. THIS MATERIAL MUST NOT BE USED FOR COMMERCIAL PURPOSES.
Push and Pull Systems
Pull
Push
Mass
Production
Economies
of Scale
Expected
Demand
Tuesday, 11 February 14
50. THIS MATERIAL MUST NOT BE USED FOR COMMERCIAL PURPOSES.
Push and Pull Systems
Customer
Requirements
Pull
Push
Mass
Production
Economies
of Scale
Expected
Demand
Tuesday, 11 February 14
51. THIS MATERIAL MUST NOT BE USED FOR COMMERCIAL PURPOSES.
Push and Pull Systems
On Demand
Production
Customer
Requirements
Pull
Push
Mass
Production
Economies
of Scale
Expected
Demand
Tuesday, 11 February 14
52. THIS MATERIAL MUST NOT BE USED FOR COMMERCIAL PURPOSES.
Push and Pull Systems
Adaptation
On Demand
Production
Customer
Requirements
Pull
Push
Mass
Production
Economies
of Scale
Expected
Demand
Tuesday, 11 February 14
53. THIS MATERIAL MUST NOT BE USED FOR COMMERCIAL PURPOSES.
Push and Pull Systems
Pull
Tuesday, 11 February 14
54. THIS MATERIAL MUST NOT BE USED FOR COMMERCIAL PURPOSES.
Push and Pull Systems
Pull
Tuesday, 11 February 14
55. THIS MATERIAL MUST NOT BE USED FOR COMMERCIAL PURPOSES.
Kanban
TASK1
TASK2
Tuesday, 11 February 14
56. THIS MATERIAL MUST NOT BE USED FOR COMMERCIAL PURPOSES.
Kanban
TASK1
TASK2
Tuesday, 11 February 14
57. THIS MATERIAL MUST NOT BE USED FOR COMMERCIAL PURPOSES.
Kanban
TASK1
TASK2
Tuesday, 11 February 14
58. THIS MATERIAL MUST NOT BE USED FOR COMMERCIAL PURPOSES.
Kanban
TASK1
TASK2
Tuesday, 11 February 14
59. THIS MATERIAL MUST NOT BE USED FOR COMMERCIAL PURPOSES.
Kanban
TASK1
TASK2
Signals demand
Regulates demand
Limits Work in Process
Aids visual control
Self-directing
Tuesday, 11 February 14
60. THIS MATERIAL MUST NOT BE USED FOR COMMERCIAL PURPOSES.
Kanban
Signals demand
Regulates demand
Limits Work in Process
Aids visual control
Self-directing
Tuesday, 11 February 14
61. THIS MATERIAL MUST NOT BE USED FOR COMMERCIAL PURPOSES.
Kanban
Signals demand
Regulates demand
Limits Work in Process
Aids visual control
Self-directing
Tuesday, 11 February 14
62. THIS MATERIAL MUST NOT BE USED FOR COMMERCIAL PURPOSES.
Hands on - 2nd Step
Pull System
Tuesday, 11 February 14
63. THIS MATERIAL MUST NOT BE USED FOR COMMERCIAL PURPOSES.
Task 4Task 1 Task 2 Task 3
Hands on - 2nd Step
Pull System
Tuesday, 11 February 14
64. THIS MATERIAL MUST NOT BE USED FOR COMMERCIAL PURPOSES.
Task 4Task 1 Task 2 Task 3
Hands on - 2nd Step
4 Teams
30 secs
4 RoundsPull System
Tuesday, 11 February 14
65. THIS MATERIAL MUST NOT BE USED FOR COMMERCIAL PURPOSES.
Hands on - 2nd Step
Pull System
Setup minimum buffers at intermediate steps
Demand comes first
Items are produced to fill gaps in the buffers
Task 4Task 1 Task 2 Task 3
Tuesday, 11 February 14
66. THIS MATERIAL MUST NOT BE USED FOR COMMERCIAL PURPOSES.
Hands on - 2nd Step
Pull System
Setup minimum buffers at intermediate steps
Demand comes first
Items are produced to fill gaps in the buffers
Task 4Task 1 Task 2 Task 3
Kanban
Tuesday, 11 February 14
67. THIS MATERIAL MUST NOT BE USED FOR COMMERCIAL PURPOSES.
Tuesday, 11 February 14
68. THIS MATERIAL MUST NOT BE USED FOR COMMERCIAL PURPOSES.
Tuesday, 11 February 14
69. THIS MATERIAL MUST NOT BE USED FOR COMMERCIAL PURPOSES.
What went wrong ?
Houston, we have a problem...
Tuesday, 11 February 14
70. THIS MATERIAL MUST NOT BE USED FOR COMMERCIAL PURPOSES.
Unleveled Process
Another type of waste
Some people working more than others
Mura (Unevenness)
Heijunka
Tuesday, 11 February 14
71. THIS MATERIAL MUST NOT BE USED FOR COMMERCIAL PURPOSES.
Flow
Goal is a leveled process
Production line must be a continuous flow
One piece is bought when one piece is delivered
Sustainable pace
Tuesday, 11 February 14
72. THIS MATERIAL MUST NOT BE USED FOR COMMERCIAL PURPOSES.
Flow
Goal is a leveled process
Production line must be a continuous flow
One piece is bought when one piece is delivered
Sustainable pace
Watch the baton, not the runners
Lean Primer (http://tinyurl.com/owvhut)
Tuesday, 11 February 14
73. THIS MATERIAL MUST NOT BE USED FOR COMMERCIAL PURPOSES.
Goal is a leveled process
Production line must be a continuous flow
One piece is bought when one piece is delivered
Sustainable pace
Watch the baton, not the runners
Lean Primer (http://tinyurl.com/owvhut)
Flow
Tuesday, 11 February 14
74. THIS MATERIAL MUST NOT BE USED FOR COMMERCIAL PURPOSES.
Flow
http://www.youtube.com/watch?v=nq9SnHXIG00
Tuesday, 11 February 14
75. THIS MATERIAL MUST NOT BE USED FOR COMMERCIAL PURPOSES.
Systems Thinking
Why does it still feel wrong?
What are the other teams doing?
What’s the purpose of the system?
Tuesday, 11 February 14
76. THIS MATERIAL MUST NOT BE USED FOR COMMERCIAL PURPOSES.
Systems Thinking
“A bad system
will beat a
good person
every time”
W. Eduards Deming
Tuesday, 11 February 14
77. THIS MATERIAL MUST NOT BE USED FOR COMMERCIAL PURPOSES.
Do we need 4 teams to build a house?
Teams 1 and 2 have overlapping tasks
Systems Thinking
Tuesday, 11 February 14
78. THIS MATERIAL MUST NOT BE USED FOR COMMERCIAL PURPOSES.
Yatai (Work Cell)
Multi-skilled worker
Single piece flow
Tuesday, 11 February 14
79. THIS MATERIAL MUST NOT BE USED FOR COMMERCIAL PURPOSES.
Hands on - 3rd Step
Tuesday, 11 February 14
80. THIS MATERIAL MUST NOT BE USED FOR COMMERCIAL PURPOSES.
Sell house Build
Hands on - 3rd Step
Tuesday, 11 February 14
81. THIS MATERIAL MUST NOT BE USED FOR COMMERCIAL PURPOSES.
Sell house Build
Hands on - 3rd Step
Tuesday, 11 February 14
82. THIS MATERIAL MUST NOT BE USED FOR COMMERCIAL PURPOSES.
Sell house Build
Hands on - 3rd Step
Each person builds a house
Round of 120 seconds
Signal if you finish it
Tuesday, 11 February 14
83. THIS MATERIAL MUST NOT BE USED FOR COMMERCIAL PURPOSES.
Tuesday, 11 February 14
84. THIS MATERIAL MUST NOT BE USED FOR COMMERCIAL PURPOSES.
Tuesday, 11 February 14
85. THIS MATERIAL MUST NOT BE USED FOR COMMERCIAL PURPOSES.
What went wrong ?
Houston, we have a problem...
Tuesday, 11 February 14
86. THIS MATERIAL MUST NOT BE USED FOR COMMERCIAL PURPOSES.
Kaizen
Continuous Improvement
Reflect and adapt
Learn by standardizing
Long term thinking
Respect People
Tuesday, 11 February 14
87. THIS MATERIAL MUST NOT BE USED FOR COMMERCIAL PURPOSES.
Kaizen
Continuous Improvement
Reflect and adapt
Learn by standardizing
Long term thinking
Respect People
Tuesday, 11 February 14
88. THIS MATERIAL MUST NOT BE USED FOR COMMERCIAL PURPOSES.
Kaizen
Continuous Improvement
Reflect and adapt
Learn by standardizing
Long term thinking
Respect People
“Toyota’s real advantage was its ability to
harness the intellect of ‘ordinary’ employees”
Gary Hamel
Tuesday, 11 February 14
89. THIS MATERIAL MUST NOT BE USED FOR COMMERCIAL PURPOSES.
Is that all ?
Tuesday, 11 February 14
90. THIS MATERIAL MUST NOT BE USED FOR COMMERCIAL PURPOSES.
Is that all ?
Push System
Tuesday, 11 February 14
91. THIS MATERIAL MUST NOT BE USED FOR COMMERCIAL PURPOSES.
Is that all ?
Push System
Pull System
Tuesday, 11 February 14
92. THIS MATERIAL MUST NOT BE USED FOR COMMERCIAL PURPOSES.
Is that all ?
Push System
Pull System
Yatai
Tuesday, 11 February 14
93. THIS MATERIAL MUST NOT BE USED FOR COMMERCIAL PURPOSES.
Is that all ?
Push System
Pull System
Yatai
What’s next ?
Tuesday, 11 February 14
94. THIS MATERIAL MUST NOT BE USED FOR COMMERCIAL PURPOSES.
Is that all ?
We saw some of the practices
Practices are contextual
Principles must be understood
Push System
Pull System
Yatai
Tuesday, 11 February 14
95. THIS MATERIAL MUST NOT BE USED FOR COMMERCIAL PURPOSES.
What is Lean ?
What TPS is Not
A recipe for success
A management project or program
A set of tools for implementation
A system for production floor only
Implementable in a short- or mid- term period
Tuesday, 11 February 14
96. THIS MATERIAL MUST NOT BE USED FOR COMMERCIAL PURPOSES.
What is Lean ?
What TPS is
A consistent way of thinking
A total management philosophy
Focus on total customer satisfaction
An environment of teamwork and improvement
A never ending search for a better way
Tuesday, 11 February 14
97. THIS MATERIAL MUST NOT BE USED FOR COMMERCIAL PURPOSES.
Lean in Software Development
Tuesday, 11 February 14
98. THIS MATERIAL MUST NOT BE USED FOR COMMERCIAL PURPOSES.
Lean in Software Development
X
Tuesday, 11 February 14
99. THIS MATERIAL MUST NOT BE USED FOR COMMERCIAL PURPOSES.
Lean in Software Development
Overproduction
Waiting
Unnecessary Transportation
Overprocessing
Inventory
Motion
Defects
Tuesday, 11 February 14
100. THIS MATERIAL MUST NOT BE USED FOR COMMERCIAL PURPOSES.
Lean in Software Development
Overproduction
Waiting
Overprocessing
Inventory
Motion
Defects
Unnecessary Transportation
Tuesday, 11 February 14
101. THIS MATERIAL MUST NOT BE USED FOR COMMERCIAL PURPOSES.
Lean in Software Development
Overproduction
Waiting
Overprocessing
Inventory
Motion
Defects
Unnecessary Transportation
Tuesday, 11 February 14
102. THIS MATERIAL MUST NOT BE USED FOR COMMERCIAL PURPOSES.
Lean in Software Development
Overproduction
Waiting
Overprocessing
Inventory
Motion
Defects
Unnecessary Transportation
Extra Features
Gold Plating
Partially Completed Work
Unused Employee Creativity
Tuesday, 11 February 14
103. THIS MATERIAL MUST NOT BE USED FOR COMMERCIAL PURPOSES.
Lean in Software Development
Kanban Board
Tuesday, 11 February 14
104. THIS MATERIAL MUST NOT BE USED FOR COMMERCIAL PURPOSES.
Lean in Software Development
Kanban Board
Tuesday, 11 February 14
105. THIS MATERIAL MUST NOT BE USED FOR COMMERCIAL PURPOSES.
Lean in Software Development
Kanban Board
Tuesday, 11 February 14
106. THIS MATERIAL MUST NOT BE USED FOR COMMERCIAL PURPOSES.
Lean in Software Development
Controlling Kanban
Do you have a stable process ?
Tuesday, 11 February 14
107. THIS MATERIAL MUST NOT BE USED FOR COMMERCIAL PURPOSES.
Lean in Software Development
Controlling Kanban
Tuesday, 11 February 14
108. THIS MATERIAL MUST NOT BE USED FOR COMMERCIAL PURPOSES.
Lean in Software Development
Controlling Kanban
Tuesday, 11 February 14
109. THIS MATERIAL MUST NOT BE USED FOR COMMERCIAL PURPOSES.
Lean in Software Development
Controlling Kanban
Tuesday, 11 February 14
110. THIS MATERIAL MUST NOT BE USED FOR COMMERCIAL PURPOSES.
Lean in Software Development
Controlling Kanban
Tuesday, 11 February 14
111. THIS MATERIAL MUST NOT BE USED FOR COMMERCIAL PURPOSES.
Much more:
Lean in Software Development
Tuesday, 11 February 14
112. THIS MATERIAL MUST NOT BE USED FOR COMMERCIAL PURPOSES.
Eliminate Waste
Create Knowledge
Build Quality In
Defer Commitment
Deliver Fast
Respect People
Improve System
Much more:
Lean in Software Development
Tuesday, 11 February 14
113. THIS MATERIAL MUST NOT BE USED FOR COMMERCIAL PURPOSES.
Eliminate Waste
Create Knowledge
Build Quality In
Defer Commitment
Deliver Fast
Respect People
Improve System
Much more:
Lean in Software Development
Genchi Genbutsu
A3
5 Whys?
Stop the Line
Andon
Jidoka
Mistake Proofing
Tuesday, 11 February 14
114. THIS MATERIAL MUST NOT BE USED FOR COMMERCIAL PURPOSES.
Lean in Software Development
Tuesday, 11 February 14
115. THIS MATERIAL MUST NOT BE USED FOR COMMERCIAL PURPOSES.
Lean in Software Development
X
Tuesday, 11 February 14
116. THIS MATERIAL MUST NOT BE USED FOR COMMERCIAL PURPOSES.
Thank You!
Questions ?
Tuesday, 11 February 14