SlideShare ist ein Scribd-Unternehmen logo
1 von 10
WATER AND POWER DEVELOPMENT AUTHORITY
PRESENTATION FOR FIRST GENERAL MANAGERS / PDS
CONFERENCE
128 MW KEYAL KHWAR HPP
08TH FEB, 2023
INTRODUCTION TO PROJECT
Location: Project is located at right tributary of Indus, in Kohistan(L) KPK,
at a distance of 310 Km from Islamabad.
Cost: Project Cost (approved 2nd Rev. PC-I), is Rs. 26,084.178 M. 3rd Rev.
(Rs. 49,648.67 M) under process.
Salient Features:
Gross Head 732 m.
Plant Factor 38 %
Capacity 128 MW
Consultants: JV of Tractebel Engg. (former Lahmeyer), NDC & EASE-Pak.
Financer: KfW (Germany) Euro 97 Million (Intact)
AFD (France) Euro 120 Million (signed on 16.01.2023).
Timeline: Expected commencement of Civil Works Contract is Aug 2023.
Discharge 20 Cumecs
Mean Annual Energy 418 GWh
Construction Time 04 Years
PROJECT LAYOUT
PROJECT COMPONENTS
Concrete Gravity Dam
Power Conduit System
Headrace Tunnels and Shafts
Pressure Shaft
Main Access Tunnel
Underground Powerhouse
Mini Hydropower Station
132 KV Switch Yard
Interconnection to Grid.
Power Intake
 Desander
 Surge Tunnel
Pressure Tunnel
 Cable Ventilation Tunnel
 Tailrace System
 E&M Components
Computerized Control
System
ACHIEVEMENTS
Land: Required Land 940 Kanal & 06 Marla acquired at cost Rs. 568.9 M.
Flood 2022 completely washed-out some patches of existing access
road, which require acquisition of additional Land.
O&M Colony: WAPDA Colony at Pattan has almost been completed.
Financial Status: Loan agreement of Euro 120 Million has been signed
between EAD (GoP) & AFD (France) on 16.01.2023. Hence, the financial
close has been carried out.
Contract-01(Ventilation Tunnel): The Contract for Exploratory Adit was
completed in May 2014 at a cost of Rs.112.88 Million.
Expenditure: Rs. 4,509.11 Million have been spent till Dec 2022, on
account of land acquisition, Ventilation tunnel, O&M Colony,
Consultant’s fee, Supervisory charges & Admin expenditure.
PROJECT PROGRESS
(Overall Physical Progress 11 % & Financial Progress 18 %)
Civil & Hydraulic Steel Works Contract:
KfW issued NOL for Pre-Qualification (PQ) Evaluation on 23.09.2022.
Wapda Authority accorded approval for Qualified firms on 19.10.2022
Notification of pre-qualified companies issued to all applicants, and
published in GTAI and PPRA / WAPDA website.
Bidding Documents submitted to the lead sponsor M/s KfW on
16.12.2022, for review and issuance of NOL.
Electrical and Mechanical (E&M) EQUIPMENT Contract:
Project Consultants submitted Final Evaluation Report on 09.01.2023.
Pre-qualification Report submitted to KfW on 13.01.2023 for NOL.
Technical Challenges & Major Issues.
Termination of Civil Works Contract in Dec 2017, due to Contractor’s
non-performance (Retendering in process).
Financial gap of Euro 100 Million arose after expiry / exit of loan of
Euro 100 Million from EIB (Loan signed with AFD on 16.01.2023).
Revision of PC-I is envisaged due to inflation, devaluation of Pak Rs. &
escalation. {Energy Wing (Planning Commission) returned 3rd Rev. PC-I,
to resubmit it after getting Bid prices of Civil & E&M Contracts}.
Destruction of existing access road to Dam site due to Floods-2022,
requires update in the design of this road. (Topographic Survey Report
prepared by M/s SPATIO, funded by AFD, has been provided to KHC in
Jan 2023, for re-alignment/re-designing of the access road).
Colony and Damaged Road’s Pictures
Lessons Learnt and Recommendation
Land Acquisition: Land required for the Project (atleast the priority
areas) must be acquired prior to award of Contract to avoid delays.
Financial Closure: Financing of the Project must be secured in ICB
Contracts, prior to start of the Project.
PC-I: Project PC-I with accuracy of the Cost needs to be carried out to
avoid further revisions.
Local Contractor: For Joint Venture with International bidders, the
local contractor must be qualified, eligible and experienced in such
hydropower Projects.
Cooperation of related government departments for land acquisition,
Loan approval and other necessary matters is always required on
expedited pace to avoid unnecessary delays and future complications.
THANK YOU

Weitere ähnliche Inhalte

Ähnlich wie Final Presentation for 1st GMs-PDs Conference 03.02.2023.pptx

STUDY ON BOT PROJECT WITH A CASE STUDY OF DELHI GURGAON EXPRESSWAY
STUDY ON BOT PROJECT WITH A CASE STUDY OF DELHI GURGAON EXPRESSWAYSTUDY ON BOT PROJECT WITH A CASE STUDY OF DELHI GURGAON EXPRESSWAY
STUDY ON BOT PROJECT WITH A CASE STUDY OF DELHI GURGAON EXPRESSWAYShabaz Khan
 
Performance Audit of GBPWD.pptx
Performance Audit of GBPWD.pptxPerformance Audit of GBPWD.pptx
Performance Audit of GBPWD.pptxsheikhInayat5
 
Projects Review Report
Projects  Review ReportProjects  Review Report
Projects Review ReportRamuSekar4
 
Digital construction for DSD - relocation of Sewage Treatment Plant
Digital construction for DSD - relocation of Sewage Treatment PlantDigital construction for DSD - relocation of Sewage Treatment Plant
Digital construction for DSD - relocation of Sewage Treatment PlantStephen Au
 
Annexure - Projects
Annexure - ProjectsAnnexure - Projects
Annexure - ProjectsMohit Verma
 
Tender summary for SECI 2500 MW Wind-Solar Hybrid Tender
Tender summary for SECI 2500 MW Wind-Solar Hybrid TenderTender summary for SECI 2500 MW Wind-Solar Hybrid Tender
Tender summary for SECI 2500 MW Wind-Solar Hybrid TenderGensol Engineering Limited
 
Review of PH-16 With CRB.pptx
Review of PH-16 With CRB.pptxReview of PH-16 With CRB.pptx
Review of PH-16 With CRB.pptxMayankGandhi51
 
Jr. Civil Engineer Portfolio
Jr. Civil Engineer PortfolioJr. Civil Engineer Portfolio
Jr. Civil Engineer PortfolioMahmoud Abubkr
 
Draft Bid Evaluation Report-2.docx
Draft Bid Evaluation Report-2.docxDraft Bid Evaluation Report-2.docx
Draft Bid Evaluation Report-2.docxArshadMahmood155695
 
Government recognized new advance material for sustainable construction of ro...
Government recognized new advance material for sustainable construction of ro...Government recognized new advance material for sustainable construction of ro...
Government recognized new advance material for sustainable construction of ro...Jogani Reinforcement
 
Rajasthan-Solar-Policy 2011
Rajasthan-Solar-Policy 2011Rajasthan-Solar-Policy 2011
Rajasthan-Solar-Policy 2011Exergy
 

Ähnlich wie Final Presentation for 1st GMs-PDs Conference 03.02.2023.pptx (20)

STUDY ON BOT PROJECT WITH A CASE STUDY OF DELHI GURGAON EXPRESSWAY
STUDY ON BOT PROJECT WITH A CASE STUDY OF DELHI GURGAON EXPRESSWAYSTUDY ON BOT PROJECT WITH A CASE STUDY OF DELHI GURGAON EXPRESSWAY
STUDY ON BOT PROJECT WITH A CASE STUDY OF DELHI GURGAON EXPRESSWAY
 
CV - Ahmed Mounir
CV - Ahmed MounirCV - Ahmed Mounir
CV - Ahmed Mounir
 
PPT to BPC.pptx
PPT to BPC.pptxPPT to BPC.pptx
PPT to BPC.pptx
 
Ranjith cv
Ranjith cvRanjith cv
Ranjith cv
 
Performance Audit of GBPWD.pptx
Performance Audit of GBPWD.pptxPerformance Audit of GBPWD.pptx
Performance Audit of GBPWD.pptx
 
Projects Review Report
Projects  Review ReportProjects  Review Report
Projects Review Report
 
Digital construction for DSD - relocation of Sewage Treatment Plant
Digital construction for DSD - relocation of Sewage Treatment PlantDigital construction for DSD - relocation of Sewage Treatment Plant
Digital construction for DSD - relocation of Sewage Treatment Plant
 
Annexure - Projects
Annexure - ProjectsAnnexure - Projects
Annexure - Projects
 
DABHOL POWER COMPANY, INDIA
DABHOL POWER COMPANY,  INDIADABHOL POWER COMPANY,  INDIA
DABHOL POWER COMPANY, INDIA
 
MCV
MCVMCV
MCV
 
Tender summary for SECI 2500 MW Wind-Solar Hybrid Tender
Tender summary for SECI 2500 MW Wind-Solar Hybrid TenderTender summary for SECI 2500 MW Wind-Solar Hybrid Tender
Tender summary for SECI 2500 MW Wind-Solar Hybrid Tender
 
Review of PH-16 With CRB.pptx
Review of PH-16 With CRB.pptxReview of PH-16 With CRB.pptx
Review of PH-16 With CRB.pptx
 
Jr. Civil Engineer Portfolio
Jr. Civil Engineer PortfolioJr. Civil Engineer Portfolio
Jr. Civil Engineer Portfolio
 
Draft Bid Evaluation Report-2.docx
Draft Bid Evaluation Report-2.docxDraft Bid Evaluation Report-2.docx
Draft Bid Evaluation Report-2.docx
 
CURRICULUM VITAE World Bank Format V3
CURRICULUM VITAE World Bank Format V3CURRICULUM VITAE World Bank Format V3
CURRICULUM VITAE World Bank Format V3
 
Ashraf Suleiman.
Ashraf Suleiman.Ashraf Suleiman.
Ashraf Suleiman.
 
Government recognized new advance material for sustainable construction of ro...
Government recognized new advance material for sustainable construction of ro...Government recognized new advance material for sustainable construction of ro...
Government recognized new advance material for sustainable construction of ro...
 
JAMES -CV -
JAMES -CV -JAMES -CV -
JAMES -CV -
 
Sajeevresume_June-28-2015
Sajeevresume_June-28-2015Sajeevresume_June-28-2015
Sajeevresume_June-28-2015
 
Rajasthan-Solar-Policy 2011
Rajasthan-Solar-Policy 2011Rajasthan-Solar-Policy 2011
Rajasthan-Solar-Policy 2011
 

Kürzlich hochgeladen

Earthing details of Electrical Substation
Earthing details of Electrical SubstationEarthing details of Electrical Substation
Earthing details of Electrical Substationstephanwindworld
 
Virtual memory management in Operating System
Virtual memory management in Operating SystemVirtual memory management in Operating System
Virtual memory management in Operating SystemRashmi Bhat
 
11. Properties of Liquid Fuels in Energy Engineering.pdf
11. Properties of Liquid Fuels in Energy Engineering.pdf11. Properties of Liquid Fuels in Energy Engineering.pdf
11. Properties of Liquid Fuels in Energy Engineering.pdfHafizMudaserAhmad
 
Indian Dairy Industry Present Status and.ppt
Indian Dairy Industry Present Status and.pptIndian Dairy Industry Present Status and.ppt
Indian Dairy Industry Present Status and.pptMadan Karki
 
Industrial Safety Unit-IV workplace health and safety.ppt
Industrial Safety Unit-IV workplace health and safety.pptIndustrial Safety Unit-IV workplace health and safety.ppt
Industrial Safety Unit-IV workplace health and safety.pptNarmatha D
 
DM Pillar Training Manual.ppt will be useful in deploying TPM in project
DM Pillar Training Manual.ppt will be useful in deploying TPM in projectDM Pillar Training Manual.ppt will be useful in deploying TPM in project
DM Pillar Training Manual.ppt will be useful in deploying TPM in projectssuserb6619e
 
US Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of ActionUS Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of ActionMebane Rash
 
Input Output Management in Operating System
Input Output Management in Operating SystemInput Output Management in Operating System
Input Output Management in Operating SystemRashmi Bhat
 
home automation using Arduino by Aditya Prasad
home automation using Arduino by Aditya Prasadhome automation using Arduino by Aditya Prasad
home automation using Arduino by Aditya Prasadaditya806802
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AIabhishek36461
 
Katarzyna Lipka-Sidor - BIM School Course
Katarzyna Lipka-Sidor - BIM School CourseKatarzyna Lipka-Sidor - BIM School Course
Katarzyna Lipka-Sidor - BIM School Coursebim.edu.pl
 
Internet of things -Arshdeep Bahga .pptx
Internet of things -Arshdeep Bahga .pptxInternet of things -Arshdeep Bahga .pptx
Internet of things -Arshdeep Bahga .pptxVelmuruganTECE
 
Correctly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleCorrectly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleAlluxio, Inc.
 
"Exploring the Essential Functions and Design Considerations of Spillways in ...
"Exploring the Essential Functions and Design Considerations of Spillways in ..."Exploring the Essential Functions and Design Considerations of Spillways in ...
"Exploring the Essential Functions and Design Considerations of Spillways in ...Erbil Polytechnic University
 
Crystal Structure analysis and detailed information pptx
Crystal Structure analysis and detailed information pptxCrystal Structure analysis and detailed information pptx
Crystal Structure analysis and detailed information pptxachiever3003
 
Configuration of IoT devices - Systems managament
Configuration of IoT devices - Systems managamentConfiguration of IoT devices - Systems managament
Configuration of IoT devices - Systems managamentBharaniDharan195623
 
Mine Environment II Lab_MI10448MI__________.pptx
Mine Environment II Lab_MI10448MI__________.pptxMine Environment II Lab_MI10448MI__________.pptx
Mine Environment II Lab_MI10448MI__________.pptxRomil Mishra
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 

Kürzlich hochgeladen (20)

Earthing details of Electrical Substation
Earthing details of Electrical SubstationEarthing details of Electrical Substation
Earthing details of Electrical Substation
 
Virtual memory management in Operating System
Virtual memory management in Operating SystemVirtual memory management in Operating System
Virtual memory management in Operating System
 
11. Properties of Liquid Fuels in Energy Engineering.pdf
11. Properties of Liquid Fuels in Energy Engineering.pdf11. Properties of Liquid Fuels in Energy Engineering.pdf
11. Properties of Liquid Fuels in Energy Engineering.pdf
 
Indian Dairy Industry Present Status and.ppt
Indian Dairy Industry Present Status and.pptIndian Dairy Industry Present Status and.ppt
Indian Dairy Industry Present Status and.ppt
 
Industrial Safety Unit-IV workplace health and safety.ppt
Industrial Safety Unit-IV workplace health and safety.pptIndustrial Safety Unit-IV workplace health and safety.ppt
Industrial Safety Unit-IV workplace health and safety.ppt
 
DM Pillar Training Manual.ppt will be useful in deploying TPM in project
DM Pillar Training Manual.ppt will be useful in deploying TPM in projectDM Pillar Training Manual.ppt will be useful in deploying TPM in project
DM Pillar Training Manual.ppt will be useful in deploying TPM in project
 
US Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of ActionUS Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of Action
 
Input Output Management in Operating System
Input Output Management in Operating SystemInput Output Management in Operating System
Input Output Management in Operating System
 
home automation using Arduino by Aditya Prasad
home automation using Arduino by Aditya Prasadhome automation using Arduino by Aditya Prasad
home automation using Arduino by Aditya Prasad
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AI
 
Katarzyna Lipka-Sidor - BIM School Course
Katarzyna Lipka-Sidor - BIM School CourseKatarzyna Lipka-Sidor - BIM School Course
Katarzyna Lipka-Sidor - BIM School Course
 
Internet of things -Arshdeep Bahga .pptx
Internet of things -Arshdeep Bahga .pptxInternet of things -Arshdeep Bahga .pptx
Internet of things -Arshdeep Bahga .pptx
 
Correctly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleCorrectly Loading Incremental Data at Scale
Correctly Loading Incremental Data at Scale
 
"Exploring the Essential Functions and Design Considerations of Spillways in ...
"Exploring the Essential Functions and Design Considerations of Spillways in ..."Exploring the Essential Functions and Design Considerations of Spillways in ...
"Exploring the Essential Functions and Design Considerations of Spillways in ...
 
Crystal Structure analysis and detailed information pptx
Crystal Structure analysis and detailed information pptxCrystal Structure analysis and detailed information pptx
Crystal Structure analysis and detailed information pptx
 
Designing pile caps according to ACI 318-19.pptx
Designing pile caps according to ACI 318-19.pptxDesigning pile caps according to ACI 318-19.pptx
Designing pile caps according to ACI 318-19.pptx
 
Configuration of IoT devices - Systems managament
Configuration of IoT devices - Systems managamentConfiguration of IoT devices - Systems managament
Configuration of IoT devices - Systems managament
 
Design and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdfDesign and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdf
 
Mine Environment II Lab_MI10448MI__________.pptx
Mine Environment II Lab_MI10448MI__________.pptxMine Environment II Lab_MI10448MI__________.pptx
Mine Environment II Lab_MI10448MI__________.pptx
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 

Final Presentation for 1st GMs-PDs Conference 03.02.2023.pptx

  • 1. WATER AND POWER DEVELOPMENT AUTHORITY PRESENTATION FOR FIRST GENERAL MANAGERS / PDS CONFERENCE 128 MW KEYAL KHWAR HPP 08TH FEB, 2023
  • 2. INTRODUCTION TO PROJECT Location: Project is located at right tributary of Indus, in Kohistan(L) KPK, at a distance of 310 Km from Islamabad. Cost: Project Cost (approved 2nd Rev. PC-I), is Rs. 26,084.178 M. 3rd Rev. (Rs. 49,648.67 M) under process. Salient Features: Gross Head 732 m. Plant Factor 38 % Capacity 128 MW Consultants: JV of Tractebel Engg. (former Lahmeyer), NDC & EASE-Pak. Financer: KfW (Germany) Euro 97 Million (Intact) AFD (France) Euro 120 Million (signed on 16.01.2023). Timeline: Expected commencement of Civil Works Contract is Aug 2023. Discharge 20 Cumecs Mean Annual Energy 418 GWh Construction Time 04 Years
  • 4. PROJECT COMPONENTS Concrete Gravity Dam Power Conduit System Headrace Tunnels and Shafts Pressure Shaft Main Access Tunnel Underground Powerhouse Mini Hydropower Station 132 KV Switch Yard Interconnection to Grid. Power Intake  Desander  Surge Tunnel Pressure Tunnel  Cable Ventilation Tunnel  Tailrace System  E&M Components Computerized Control System
  • 5. ACHIEVEMENTS Land: Required Land 940 Kanal & 06 Marla acquired at cost Rs. 568.9 M. Flood 2022 completely washed-out some patches of existing access road, which require acquisition of additional Land. O&M Colony: WAPDA Colony at Pattan has almost been completed. Financial Status: Loan agreement of Euro 120 Million has been signed between EAD (GoP) & AFD (France) on 16.01.2023. Hence, the financial close has been carried out. Contract-01(Ventilation Tunnel): The Contract for Exploratory Adit was completed in May 2014 at a cost of Rs.112.88 Million. Expenditure: Rs. 4,509.11 Million have been spent till Dec 2022, on account of land acquisition, Ventilation tunnel, O&M Colony, Consultant’s fee, Supervisory charges & Admin expenditure.
  • 6. PROJECT PROGRESS (Overall Physical Progress 11 % & Financial Progress 18 %) Civil & Hydraulic Steel Works Contract: KfW issued NOL for Pre-Qualification (PQ) Evaluation on 23.09.2022. Wapda Authority accorded approval for Qualified firms on 19.10.2022 Notification of pre-qualified companies issued to all applicants, and published in GTAI and PPRA / WAPDA website. Bidding Documents submitted to the lead sponsor M/s KfW on 16.12.2022, for review and issuance of NOL. Electrical and Mechanical (E&M) EQUIPMENT Contract: Project Consultants submitted Final Evaluation Report on 09.01.2023. Pre-qualification Report submitted to KfW on 13.01.2023 for NOL.
  • 7. Technical Challenges & Major Issues. Termination of Civil Works Contract in Dec 2017, due to Contractor’s non-performance (Retendering in process). Financial gap of Euro 100 Million arose after expiry / exit of loan of Euro 100 Million from EIB (Loan signed with AFD on 16.01.2023). Revision of PC-I is envisaged due to inflation, devaluation of Pak Rs. & escalation. {Energy Wing (Planning Commission) returned 3rd Rev. PC-I, to resubmit it after getting Bid prices of Civil & E&M Contracts}. Destruction of existing access road to Dam site due to Floods-2022, requires update in the design of this road. (Topographic Survey Report prepared by M/s SPATIO, funded by AFD, has been provided to KHC in Jan 2023, for re-alignment/re-designing of the access road).
  • 8. Colony and Damaged Road’s Pictures
  • 9. Lessons Learnt and Recommendation Land Acquisition: Land required for the Project (atleast the priority areas) must be acquired prior to award of Contract to avoid delays. Financial Closure: Financing of the Project must be secured in ICB Contracts, prior to start of the Project. PC-I: Project PC-I with accuracy of the Cost needs to be carried out to avoid further revisions. Local Contractor: For Joint Venture with International bidders, the local contractor must be qualified, eligible and experienced in such hydropower Projects. Cooperation of related government departments for land acquisition, Loan approval and other necessary matters is always required on expedited pace to avoid unnecessary delays and future complications.