Software Project Planning and Management (CAP 590)
Term Paper: - Project Duration Estimation
Synopsis By: - Harsh Behl Submitted To- Sahil Rampal
11100961
RD1102A27
Date: - 07 April 2014
Page 2 of 16
Index Page no
1. Introduction 3
2. Technique’s Which Are 4
Used to Estimate Project Duration
3.Top Down Approach 4-5
4.Bottom Down Approach 5-7
5. Expert Judgments 7
6.Historical comparison 7
7.Functional Points 7-8
8.Object points 8-10
9.CPM (Critical path method) 10-12
10. Pert 12-15
11. Conclusion 15
12. Bibliography 16
Page 3 of 16
Introduction
As we all know that estimating the activity duration is very important to
the success of any Software project. Like me and my team will estimate
the various requirements of cost, time, and resources throughout in our
project. As we look upon the activity duration estimation looks at the
time it takes to complete the entire project, activity duration estimation
is dependent on other time and resource estimates also.
We might start on these estimates at the Starting of our project, but we
make the most of the estimates during the planning period.
Estimates are never exact these are just guesses by the whole team. But
we can improve our accuracy by dividing the estimation task into three
distinct steps: determining a Work Breakdown Structure (WBS),
estimating the amount of work and duration of work packages, and
calculating the project schedule.
Technique’s Which Are Used to Estimate Project Duration
We can choose from many other methods, however, if neither CPM nor
PERT meets our needs. Other estimating methods include:
 Bottom-up
 Expert judgment
 Function point
 Historical comparison
 Top-down
 Objects point
Page 4 of 16
Out of all these methods I will discuss CPM and Pert in detail rest I will
discuss briefly.
So I am discussing each of them one by one…
Top Down Approach
As we all know that the effort for a project is a function of many
parameters. And the main factor which determine the effort for the project
is basically the size of the project. That is if we have larger project the
greater is the effort requirement and greater is the project duration. So top
down approach basically takes effort as a function of project size and it is
important to note down that to apply this function we first have to
determine the size of the project for which effort has to be estimated and
project duration is to be estimated.
If the past productivity for similar projects is known than we can use them
to determine the effort and time duration from the size.
A more general function for determining effort from size that is
commonly used is of the form:
EFFORT = a * SIZEb
,
where a and b are constants, and project size is generally in KLOC (size
could also be in another size measure called function points which can be
determined from requirements). Values for these constants for an
organization are determined through regression analysis, which is applied
to data about the projects that have been performed in the past. For
example, Harsh and Vinod analyzed the data of more than 60 projects
done at LPU InfoTech Division, ranging from 4000 to 467,000 lines of
delivered source code, and found that if the SIZE estimate is in thousands
of delivered lines of code (KLOC), the total effort, E, in person-months
(PM) can be given by the equation E = 5.2(SIZE).91.
It should be noted that to use the top-down approach for estimation, even
if we have a suitable function, we need to have an estimate of the project
size. In other words, we have replaced the problem of effort estimation by
size estimation because size estimation is often easier than direct effort
Page 5 of 16
estimation. This is mainly due to the fact that the system size can be
estimated from the sizes of its components by adding the size estimates of
all the components. Similar property does not hold for effort estimation,
as effort for developing a system is not the sum of effort for developing
the components as additional effort is needed for integration and other
such activities when building a system from developed components.
Clearly for top-down estimation to work well, it is important that good
estimates for the size of the software be obtained. There is no known
simple method for estimating the size and duration accurately. When
estimating software size, the best way may be to get as much detail as
possible about the software to be developed and to be aware of our biases
when estimating the size of the various components. By obtaining details
and using them for size estimation, the estimates are likely to be closer to
the actual size and duration for the final software.
Bottom up Approach
This approach works in this way that the people who are going to do
work in the project work will participate in estimation process. The team
is basically the project team members and project manager who will
develop estimating data the lowest level in the work breakdown
structure Bottom-up estimating is where the people who were going to
do the work participate in the estimating process. When the estimates of
work, duration and cost are set at that level they are aggregated upward
into estimates of higher level deliverables and the project as a whole.
Bottom-up estimating is the most accurate approach to estimating cost
and duration and also usually requires the most time. This kind of
estimating involves the entire project team and gives people the
opportunity to participate in the development of the estimates used to
measure their work. As a result, bottom-up estimating tends to develop a
much higher level of project team commitment than does top-down or
parametric estimating. In top-down, where the numbers come from an
Page 6 of 16
outside source, people feel we have imposed the estimates on them. The
drawback of the bottom-up approach is that it consumes much more time
than the other estimating techniques.
In bottom-up estimating, we follow a three-step process, working from
the lowest level of detail in the work breakdown structure. We begin
bottom-up estimating by developing a detailed work package to
accompany the WBS. In this work package, we may describe risk
elements, dependencies that affect the activity and its cost and duration.
Once the work package is complete and the team member is comfortable
with it, we can proceed to develop the actual cost or duration estimate.
In bottom-up estimating, a project manager has to be careful not to force
an estimate on the project team member. If the estimate is forced, the
project manager cannot expect to earn much commitment from the team
member. That commitment is dependent on a free and open negotiation
where the team member feels the estimate is fair and reasonable. At this
point in the process, the project manager may use the three estimates
from the PERT process, as that allows an estimate that reflects the
uncertainty inherent in the task.
Last, we aggregate the estimates for each of the activities in the lowest
level of the WBS and roll the numbers up to develop estimates for the
major deliverables and the project as a whole.
We can use a number of mathematical techniques with bottom-up
estimating although the most popular and most accurate is to use three
point estimates where the team members provide the pessimistic,
optimistic and best guess numbers for the three-point calculations.
Expert Judgments
This is basically asking someone who is knowledgeable about the
application area or the development environment to give an estimate of
the effort needed to carry out a task. This method will be used when
estimating the effort and time needed to change the existing piece of the
software or developing the similar kind of software, the estimator would
Page 7 of 16
have to carry the analysis in order to judge the proportion of code that
would be affected that derive an estimation from the person who is
familiar to be in the best position to do this.
But the true fact is that is simple guessing.
Historical comparison
This basically based on the cased based reasoning. The estimator seeks
out the projects that have been completed and that have similar
characteristics to the new project. The effort and time that has been
recorded for the matching source case can be used as base estimate for
the target. The estimator should try to identify any differences between
the target and source and make the adjustments to the base estimate for
new project duration and effort.
Functional Points
Alan Albrecht while working for IBM, recognized the problem in size
measurement in the 1970s, and developed a technique (which he called
Function Point Analysis), which appeared to be a solution to the size
measurement problem
The principle of Albrecht’s function point analysis (FPA) is that a
system is decomposed into functional units.
Inputs : information entering the system
Outputs : information leaving the system
Enquiries : requests for instant access to
information
Internal logical files : information held within the
system
Page 8 of 16
External interface files: information held by other system
that is used by the system being
analyzed.
So on the basis of this we basically estimate the time duration for
different kind of functional points etc.
Object points
The approach was devised at the Leonard N. stern school of business,
New York University. It has similarities with FP approach, but takes
different account of features. The approach uses counts of screen,
reports and 3gl component that an application might possess it is these
that referred to as objects. Each object has to be classified as one of the
following…
1. Simple
2. Medium
3. Difficult
The number of objects at each level are multiplied by the approiate
complexity weighting as shown in the figure.
Page 9 of 16
CPM (Critical path method)
In this we basically capture the activities and their inter-relationships
using a graph
Lines are used to represent the activities.
Nodes are used to represent the start and stop of activities.
With the help of cpm we can calculate the two things
The forward pass in which we calculate the earliest state of the activities
and calculate the project completion date.
Page 10 of 16
The backward pass in which we calculate the latest start for activities
and identify the critical path from the graph.
Some common terms in this
Critical event : an event that has zero slack
Critical path : a path joining those critical events.
Example to construct a CPM
Page 11 of 16
Page 12 of 16
Pert
PERT is a planning and control tool used for defining and controlling
the tasks necessary to complete a project. PERT charts and Critical Path
Method (CPM) charts are often used interchangeably; the only
difference is how task times are computed. Both charts display the total
project with all scheduled tasks shown in sequence. The displayed tasks
show which ones are in parallel, those tasks that can be performed at the
same time. A graphic representation called a "Project Network" or
"CPM Diagram" is used to portray graphically the interrelationships of
the elements of a project and to show the order in which the activities
must be performed.
PERT planning involves the following steps:
Page 13 of 16
1. Identify the specific activities and milestones. The activities are the
tasks of the project. The milestones are the events that mark the
beginning and the end of one or more activities.
2. Determine the proper sequence of activities. This step may be
combined with #1 above since the activity sequence is evident for
some tasks. Other tasks may require some analysis to determine
the exact order in which they should be performed.
3. Construct a network diagram. Using the activity sequence
information, a network diagram can be drawn showing the
sequence of the successive and parallel activities. Arrowed lines
represent the activities and circles or "bubbles" represent
milestones.
4. Estimate the time required for each activity. Weeks are a
commonly used unit of time for activity completion, but any
consistent unit of time can be used. A distinguishing feature of
PERT is it's ability to deal with uncertainty in activity completion
times. For each activity, the model usually includes three time
estimates:
o Optimistic time - the shortest time in which the activity can
be completed.
o Most likely time - the completion time having the highest
probability.
o Pessimistic time - the longest time that an activity may take.
From this, the expected time for each activity can be calculated
using the following weighted average:
Expected Time = (Optimistic + 4 x Most Likely + Pessimistic) / 6
This helps to bias time estimates away from the unrealistically
short timescales normally assumed.
5. Determine the critical path. The critical path is determined by
adding the times for the activities in each sequence and
determining the longest path in the project. The critical path
determines the total calendar time required for the project. The
Page 14 of 16
amount of time that a non-critical path activity can be delayed
without delaying the project is referred to as slack time.
If the critical path is not immediately obvious, it may be helpful to
determine the following four times for each activity:
o ES - Earliest Start time
o EF - Earliest Finish time
o LS - Latest Start time
o LF - Latest Finish time
These times are calculated using the expected time for the relevant
activities. The earliest start and finish times of each activity are
determined by working forward through the network and
determining the earliest time at which an activity can start and
finish considering its predecessor activities. The latest start and
finish times are the latest times that an activity can start and finish
without delaying the project. LS and LF are found by working
backward through the network. The difference in the latest and
earliest finish of each activity is that activity's slack. The critical
path then is the path through the network in which none of the
activities have slack.
The variance in the project completion time can be calculated by
summing the variances in the completion times of the activities in
the critical path. Given this variance, one can calculate the
probability that the project will be completed by a certain date
assuming a normal probability distribution for the critical path. The
normal distribution assumption holds if the number of activities in
the path is large enough for the central limit theorem to be applied.
6. Update the PERT chart as the project progresses. As the project
unfolds, the estimated times can be replaced with actual times. In
cases where there are delays, additional resources may be needed
to stay on schedule and the PERT chart may be modified to reflect
the new situation. An example of a PERT chart is provided below:
Page 15 of 16
Benefits to using a PERT chart or the Critical Path Method include:
 Improved planning and scheduling of activities.
 Improved forecasting of resource requirements.
 Identification of repetitive planning patterns which can be followed
in other projects, thus simplifying the planning process.
 Ability to see and thus reschedule activities to reflect interproject
dependencies and resource limitations following know priority
rules.
 It also provides the following: expected project completion time,
probability of completion before a specified date, the critical path
activities that impact completion time, the activities that have slack
time and that can lend resources to critical path activities, and
activity start and end dates.
Conclusion
This helps us to estimate the project duration estimation which later
helps to create a comprehensive estimate which will reflect the different
tasks and real-world scheduling. This approach will removes the
uncertainty and creates a project plan that helps us to know our options
and adapt to path changes. The duration estimation also help us to
estimate the budget of our project. As we all know that estimates can
never be exact but practicing this will make our guesses better.
Page 16 of 16
Bibliography
https://4pm.com/bottom-up-estimating/
https://www.google.co.in/url?sa=t&rct=j&q=&esrc=s&source=web&cd=5&cad=rja&uact=8&ved=0CEkQ
FjAE&url=http%3A%2F%2Frpl-blog.blogspot.com%2F2010%2F03%2F411-top-down-estimation-
approach.html&ei=ajtCU6HCKoKOrQfpuYCQDw&usg=AFQjCNE1N13_-t8ZjUaaW-
01OkYFzanMaQ&sig2=svgx9iA9JqHABaLf2HeKvw&bvm=bv.64367178,d.bmk
https://slideshare.com

Weitere ähnliche Inhalte

Was ist angesagt?

Extension of Time (EoT) in Construction Project presentation
Extension of Time (EoT) in Construction Project presentationExtension of Time (EoT) in Construction Project presentation
Extension of Time (EoT) in Construction Project presentationAyush Joshi
 
10. implementation (4) risk management
10. implementation (4)   risk management 10. implementation (4)   risk management
10. implementation (4) risk management Dania Abdel-aziz
 
Exploration of risks and risk management in construction project delivery
Exploration of risks and risk management in construction project deliveryExploration of risks and risk management in construction project delivery
Exploration of risks and risk management in construction project deliveryMECandPMV
 
PMP Chap 6 - Project Time management - Part2
PMP Chap 6 - Project Time management - Part2PMP Chap 6 - Project Time management - Part2
PMP Chap 6 - Project Time management - Part2Anand Bobade
 
Project Schedule Management - PMBOK6
Project Schedule Management - PMBOK6Project Schedule Management - PMBOK6
Project Schedule Management - PMBOK6Agus Suhanto
 
2. traditional project management -ch2
2. traditional project management -ch22. traditional project management -ch2
2. traditional project management -ch2Mazhar Poohlah
 
Methods of delay analysis
Methods of delay analysisMethods of delay analysis
Methods of delay analysiskatrin enders
 
Construction Delay Analysis, Simplified
Construction Delay Analysis, SimplifiedConstruction Delay Analysis, Simplified
Construction Delay Analysis, SimplifiedMichael Pink
 
Fast Tracking a Project and Project Crashing.ppt
Fast Tracking a Project and Project Crashing.pptFast Tracking a Project and Project Crashing.ppt
Fast Tracking a Project and Project Crashing.pptJo Balucanag - Bitonio
 
Project Risk Management - PMBOK6
Project Risk Management - PMBOK6Project Risk Management - PMBOK6
Project Risk Management - PMBOK6Agus Suhanto
 
Scheduling-Resources-and-Costs.ppt
Scheduling-Resources-and-Costs.pptScheduling-Resources-and-Costs.ppt
Scheduling-Resources-and-Costs.pptTecnicoItca
 

Was ist angesagt? (20)

Extension of Time (EoT) in Construction Project presentation
Extension of Time (EoT) in Construction Project presentationExtension of Time (EoT) in Construction Project presentation
Extension of Time (EoT) in Construction Project presentation
 
10. implementation (4) risk management
10. implementation (4)   risk management 10. implementation (4)   risk management
10. implementation (4) risk management
 
Claims
ClaimsClaims
Claims
 
Exploration of risks and risk management in construction project delivery
Exploration of risks and risk management in construction project deliveryExploration of risks and risk management in construction project delivery
Exploration of risks and risk management in construction project delivery
 
PMP Chap 6 - Project Time management - Part2
PMP Chap 6 - Project Time management - Part2PMP Chap 6 - Project Time management - Part2
PMP Chap 6 - Project Time management - Part2
 
Project Risk Management
Project Risk ManagementProject Risk Management
Project Risk Management
 
Project scheduling
Project schedulingProject scheduling
Project scheduling
 
Project Schedule Management - PMBOK6
Project Schedule Management - PMBOK6Project Schedule Management - PMBOK6
Project Schedule Management - PMBOK6
 
2. traditional project management -ch2
2. traditional project management -ch22. traditional project management -ch2
2. traditional project management -ch2
 
Project Planning
Project PlanningProject Planning
Project Planning
 
Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value Management
 
Methods of delay analysis
Methods of delay analysisMethods of delay analysis
Methods of delay analysis
 
Construction Delay Analysis, Simplified
Construction Delay Analysis, SimplifiedConstruction Delay Analysis, Simplified
Construction Delay Analysis, Simplified
 
Fast Tracking a Project and Project Crashing.ppt
Fast Tracking a Project and Project Crashing.pptFast Tracking a Project and Project Crashing.ppt
Fast Tracking a Project and Project Crashing.ppt
 
Delay Analysis and Concurrent Delay
Delay Analysis and Concurrent DelayDelay Analysis and Concurrent Delay
Delay Analysis and Concurrent Delay
 
Project Risk Management - PMBOK6
Project Risk Management - PMBOK6Project Risk Management - PMBOK6
Project Risk Management - PMBOK6
 
Claim Presentation Rev 03 FINAL
Claim Presentation Rev 03 FINALClaim Presentation Rev 03 FINAL
Claim Presentation Rev 03 FINAL
 
Module :-5 project scheduling and resource levelling
Module :-5 project scheduling and resource levellingModule :-5 project scheduling and resource levelling
Module :-5 project scheduling and resource levelling
 
Scheduling-Resources-and-Costs.ppt
Scheduling-Resources-and-Costs.pptScheduling-Resources-and-Costs.ppt
Scheduling-Resources-and-Costs.ppt
 
Construction Cost Control
Construction Cost ControlConstruction Cost Control
Construction Cost Control
 

Ähnlich wie Project Duration Estimation

SPM week 6 Effort estimation slides from 7th semeter.pptx
SPM week 6 Effort estimation slides from 7th semeter.pptxSPM week 6 Effort estimation slides from 7th semeter.pptx
SPM week 6 Effort estimation slides from 7th semeter.pptxfaiz536657
 
Basic Software Effort Estimation
Basic Software Effort EstimationBasic Software Effort Estimation
Basic Software Effort Estimationumair khan
 
Project selection and estimating technique spencer o’briencpmgt303
Project selection and estimating technique spencer o’briencpmgt303Project selection and estimating technique spencer o’briencpmgt303
Project selection and estimating technique spencer o’briencpmgt303MARK547399
 
Lecture 5 Estimation techniques.ppt
Lecture 5 Estimation techniques.pptLecture 5 Estimation techniques.ppt
Lecture 5 Estimation techniques.pptMaryamShah29
 
Estimation guidelines and templates
Estimation guidelines and templatesEstimation guidelines and templates
Estimation guidelines and templatesHoa PN Thaycacac
 
Top down
Top downTop down
Top downNino Ho
 
PM Estimation techniques
PM Estimation techniquesPM Estimation techniques
PM Estimation techniquesChander Parkash
 
Basic-Project-Estimation-1999
Basic-Project-Estimation-1999Basic-Project-Estimation-1999
Basic-Project-Estimation-1999Michael Wigley
 
Baseline Compliance Analysis
Baseline Compliance AnalysisBaseline Compliance Analysis
Baseline Compliance AnalysisAcumen
 
Effort estimation for software development
Effort estimation for software developmentEffort estimation for software development
Effort estimation for software developmentSpyros Ktenas
 
Software project scheduling
Software project schedulingSoftware project scheduling
Software project schedulinglokareminakshi
 
How Should We Estimate Agile Software Development Projects and What Data Do W...
How Should We Estimate Agile Software Development Projects and What Data Do W...How Should We Estimate Agile Software Development Projects and What Data Do W...
How Should We Estimate Agile Software Development Projects and What Data Do W...Glen Alleman
 
How Can I Use SNAP to Improve My Estimation Practices?
How Can I Use SNAP to Improve My Estimation Practices?How Can I Use SNAP to Improve My Estimation Practices?
How Can I Use SNAP to Improve My Estimation Practices?DCG Software Value
 
SE - Lecture 11 - Software Project Estimation.pptx
SE - Lecture 11 - Software Project Estimation.pptxSE - Lecture 11 - Software Project Estimation.pptx
SE - Lecture 11 - Software Project Estimation.pptxTangZhiSiang
 

Ähnlich wie Project Duration Estimation (20)

SPM week 6 Effort estimation slides from 7th semeter.pptx
SPM week 6 Effort estimation slides from 7th semeter.pptxSPM week 6 Effort estimation slides from 7th semeter.pptx
SPM week 6 Effort estimation slides from 7th semeter.pptx
 
Estimation sharbani bhattacharya
Estimation sharbani bhattacharyaEstimation sharbani bhattacharya
Estimation sharbani bhattacharya
 
Basic Software Effort Estimation
Basic Software Effort EstimationBasic Software Effort Estimation
Basic Software Effort Estimation
 
Project selection and estimating technique spencer o’briencpmgt303
Project selection and estimating technique spencer o’briencpmgt303Project selection and estimating technique spencer o’briencpmgt303
Project selection and estimating technique spencer o’briencpmgt303
 
Unit 5
Unit   5Unit   5
Unit 5
 
Lecture 5 Estimation techniques.ppt
Lecture 5 Estimation techniques.pptLecture 5 Estimation techniques.ppt
Lecture 5 Estimation techniques.ppt
 
Software
SoftwareSoftware
Software
 
Estimation guidelines and templates
Estimation guidelines and templatesEstimation guidelines and templates
Estimation guidelines and templates
 
Top down
Top downTop down
Top down
 
Sm presentation
Sm presentationSm presentation
Sm presentation
 
Project Scheduling
Project SchedulingProject Scheduling
Project Scheduling
 
PM Estimation techniques
PM Estimation techniquesPM Estimation techniques
PM Estimation techniques
 
Unit iii
Unit iiiUnit iii
Unit iii
 
Basic-Project-Estimation-1999
Basic-Project-Estimation-1999Basic-Project-Estimation-1999
Basic-Project-Estimation-1999
 
Baseline Compliance Analysis
Baseline Compliance AnalysisBaseline Compliance Analysis
Baseline Compliance Analysis
 
Effort estimation for software development
Effort estimation for software developmentEffort estimation for software development
Effort estimation for software development
 
Software project scheduling
Software project schedulingSoftware project scheduling
Software project scheduling
 
How Should We Estimate Agile Software Development Projects and What Data Do W...
How Should We Estimate Agile Software Development Projects and What Data Do W...How Should We Estimate Agile Software Development Projects and What Data Do W...
How Should We Estimate Agile Software Development Projects and What Data Do W...
 
How Can I Use SNAP to Improve My Estimation Practices?
How Can I Use SNAP to Improve My Estimation Practices?How Can I Use SNAP to Improve My Estimation Practices?
How Can I Use SNAP to Improve My Estimation Practices?
 
SE - Lecture 11 - Software Project Estimation.pptx
SE - Lecture 11 - Software Project Estimation.pptxSE - Lecture 11 - Software Project Estimation.pptx
SE - Lecture 11 - Software Project Estimation.pptx
 

Kürzlich hochgeladen

Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsyncWhy does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsyncssuser2ae721
 
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor CatchersTechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catcherssdickerson1
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...VICTOR MAESTRE RAMIREZ
 
home automation using Arduino by Aditya Prasad
home automation using Arduino by Aditya Prasadhome automation using Arduino by Aditya Prasad
home automation using Arduino by Aditya Prasadaditya806802
 
An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...Chandu841456
 
System Simulation and Modelling with types and Event Scheduling
System Simulation and Modelling with types and Event SchedulingSystem Simulation and Modelling with types and Event Scheduling
System Simulation and Modelling with types and Event SchedulingBootNeck1
 
Earthing details of Electrical Substation
Earthing details of Electrical SubstationEarthing details of Electrical Substation
Earthing details of Electrical Substationstephanwindworld
 
Correctly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleCorrectly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleAlluxio, Inc.
 
Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...121011101441
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AIabhishek36461
 
National Level Hackathon Participation Certificate.pdf
National Level Hackathon Participation Certificate.pdfNational Level Hackathon Participation Certificate.pdf
National Level Hackathon Participation Certificate.pdfRajuKanojiya4
 
Steel Structures - Building technology.pptx
Steel Structures - Building technology.pptxSteel Structures - Building technology.pptx
Steel Structures - Building technology.pptxNikhil Raut
 
Input Output Management in Operating System
Input Output Management in Operating SystemInput Output Management in Operating System
Input Output Management in Operating SystemRashmi Bhat
 
NO1 Certified Black Magic Specialist Expert Amil baba in Uae Dubai Abu Dhabi ...
NO1 Certified Black Magic Specialist Expert Amil baba in Uae Dubai Abu Dhabi ...NO1 Certified Black Magic Specialist Expert Amil baba in Uae Dubai Abu Dhabi ...
NO1 Certified Black Magic Specialist Expert Amil baba in Uae Dubai Abu Dhabi ...Amil Baba Dawood bangali
 
Introduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHIntroduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHC Sai Kiran
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxk795866
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxKartikeyaDwivedi3
 

Kürzlich hochgeladen (20)

Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsyncWhy does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
 
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor CatchersTechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...
 
home automation using Arduino by Aditya Prasad
home automation using Arduino by Aditya Prasadhome automation using Arduino by Aditya Prasad
home automation using Arduino by Aditya Prasad
 
Design and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdfDesign and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdf
 
An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...
 
System Simulation and Modelling with types and Event Scheduling
System Simulation and Modelling with types and Event SchedulingSystem Simulation and Modelling with types and Event Scheduling
System Simulation and Modelling with types and Event Scheduling
 
Earthing details of Electrical Substation
Earthing details of Electrical SubstationEarthing details of Electrical Substation
Earthing details of Electrical Substation
 
Correctly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleCorrectly Loading Incremental Data at Scale
Correctly Loading Incremental Data at Scale
 
Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AI
 
National Level Hackathon Participation Certificate.pdf
National Level Hackathon Participation Certificate.pdfNational Level Hackathon Participation Certificate.pdf
National Level Hackathon Participation Certificate.pdf
 
POWER SYSTEMS-1 Complete notes examples
POWER SYSTEMS-1 Complete notes  examplesPOWER SYSTEMS-1 Complete notes  examples
POWER SYSTEMS-1 Complete notes examples
 
Steel Structures - Building technology.pptx
Steel Structures - Building technology.pptxSteel Structures - Building technology.pptx
Steel Structures - Building technology.pptx
 
Input Output Management in Operating System
Input Output Management in Operating SystemInput Output Management in Operating System
Input Output Management in Operating System
 
NO1 Certified Black Magic Specialist Expert Amil baba in Uae Dubai Abu Dhabi ...
NO1 Certified Black Magic Specialist Expert Amil baba in Uae Dubai Abu Dhabi ...NO1 Certified Black Magic Specialist Expert Amil baba in Uae Dubai Abu Dhabi ...
NO1 Certified Black Magic Specialist Expert Amil baba in Uae Dubai Abu Dhabi ...
 
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
 
Introduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHIntroduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECH
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptx
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptx
 

Project Duration Estimation

  • 1. Page 1 of 16 Software Project Planning and Management (CAP 590) Term Paper: - Project Duration Estimation Synopsis By: - Harsh Behl Submitted To- Sahil Rampal 11100961 RD1102A27 Date: - 07 April 2014
  • 2. Page 2 of 16 Index Page no 1. Introduction 3 2. Technique’s Which Are 4 Used to Estimate Project Duration 3.Top Down Approach 4-5 4.Bottom Down Approach 5-7 5. Expert Judgments 7 6.Historical comparison 7 7.Functional Points 7-8 8.Object points 8-10 9.CPM (Critical path method) 10-12 10. Pert 12-15 11. Conclusion 15 12. Bibliography 16
  • 3. Page 3 of 16 Introduction As we all know that estimating the activity duration is very important to the success of any Software project. Like me and my team will estimate the various requirements of cost, time, and resources throughout in our project. As we look upon the activity duration estimation looks at the time it takes to complete the entire project, activity duration estimation is dependent on other time and resource estimates also. We might start on these estimates at the Starting of our project, but we make the most of the estimates during the planning period. Estimates are never exact these are just guesses by the whole team. But we can improve our accuracy by dividing the estimation task into three distinct steps: determining a Work Breakdown Structure (WBS), estimating the amount of work and duration of work packages, and calculating the project schedule. Technique’s Which Are Used to Estimate Project Duration We can choose from many other methods, however, if neither CPM nor PERT meets our needs. Other estimating methods include:  Bottom-up  Expert judgment  Function point  Historical comparison  Top-down  Objects point
  • 4. Page 4 of 16 Out of all these methods I will discuss CPM and Pert in detail rest I will discuss briefly. So I am discussing each of them one by one… Top Down Approach As we all know that the effort for a project is a function of many parameters. And the main factor which determine the effort for the project is basically the size of the project. That is if we have larger project the greater is the effort requirement and greater is the project duration. So top down approach basically takes effort as a function of project size and it is important to note down that to apply this function we first have to determine the size of the project for which effort has to be estimated and project duration is to be estimated. If the past productivity for similar projects is known than we can use them to determine the effort and time duration from the size. A more general function for determining effort from size that is commonly used is of the form: EFFORT = a * SIZEb , where a and b are constants, and project size is generally in KLOC (size could also be in another size measure called function points which can be determined from requirements). Values for these constants for an organization are determined through regression analysis, which is applied to data about the projects that have been performed in the past. For example, Harsh and Vinod analyzed the data of more than 60 projects done at LPU InfoTech Division, ranging from 4000 to 467,000 lines of delivered source code, and found that if the SIZE estimate is in thousands of delivered lines of code (KLOC), the total effort, E, in person-months (PM) can be given by the equation E = 5.2(SIZE).91. It should be noted that to use the top-down approach for estimation, even if we have a suitable function, we need to have an estimate of the project size. In other words, we have replaced the problem of effort estimation by size estimation because size estimation is often easier than direct effort
  • 5. Page 5 of 16 estimation. This is mainly due to the fact that the system size can be estimated from the sizes of its components by adding the size estimates of all the components. Similar property does not hold for effort estimation, as effort for developing a system is not the sum of effort for developing the components as additional effort is needed for integration and other such activities when building a system from developed components. Clearly for top-down estimation to work well, it is important that good estimates for the size of the software be obtained. There is no known simple method for estimating the size and duration accurately. When estimating software size, the best way may be to get as much detail as possible about the software to be developed and to be aware of our biases when estimating the size of the various components. By obtaining details and using them for size estimation, the estimates are likely to be closer to the actual size and duration for the final software. Bottom up Approach This approach works in this way that the people who are going to do work in the project work will participate in estimation process. The team is basically the project team members and project manager who will develop estimating data the lowest level in the work breakdown structure Bottom-up estimating is where the people who were going to do the work participate in the estimating process. When the estimates of work, duration and cost are set at that level they are aggregated upward into estimates of higher level deliverables and the project as a whole. Bottom-up estimating is the most accurate approach to estimating cost and duration and also usually requires the most time. This kind of estimating involves the entire project team and gives people the opportunity to participate in the development of the estimates used to measure their work. As a result, bottom-up estimating tends to develop a much higher level of project team commitment than does top-down or parametric estimating. In top-down, where the numbers come from an
  • 6. Page 6 of 16 outside source, people feel we have imposed the estimates on them. The drawback of the bottom-up approach is that it consumes much more time than the other estimating techniques. In bottom-up estimating, we follow a three-step process, working from the lowest level of detail in the work breakdown structure. We begin bottom-up estimating by developing a detailed work package to accompany the WBS. In this work package, we may describe risk elements, dependencies that affect the activity and its cost and duration. Once the work package is complete and the team member is comfortable with it, we can proceed to develop the actual cost or duration estimate. In bottom-up estimating, a project manager has to be careful not to force an estimate on the project team member. If the estimate is forced, the project manager cannot expect to earn much commitment from the team member. That commitment is dependent on a free and open negotiation where the team member feels the estimate is fair and reasonable. At this point in the process, the project manager may use the three estimates from the PERT process, as that allows an estimate that reflects the uncertainty inherent in the task. Last, we aggregate the estimates for each of the activities in the lowest level of the WBS and roll the numbers up to develop estimates for the major deliverables and the project as a whole. We can use a number of mathematical techniques with bottom-up estimating although the most popular and most accurate is to use three point estimates where the team members provide the pessimistic, optimistic and best guess numbers for the three-point calculations. Expert Judgments This is basically asking someone who is knowledgeable about the application area or the development environment to give an estimate of the effort needed to carry out a task. This method will be used when estimating the effort and time needed to change the existing piece of the software or developing the similar kind of software, the estimator would
  • 7. Page 7 of 16 have to carry the analysis in order to judge the proportion of code that would be affected that derive an estimation from the person who is familiar to be in the best position to do this. But the true fact is that is simple guessing. Historical comparison This basically based on the cased based reasoning. The estimator seeks out the projects that have been completed and that have similar characteristics to the new project. The effort and time that has been recorded for the matching source case can be used as base estimate for the target. The estimator should try to identify any differences between the target and source and make the adjustments to the base estimate for new project duration and effort. Functional Points Alan Albrecht while working for IBM, recognized the problem in size measurement in the 1970s, and developed a technique (which he called Function Point Analysis), which appeared to be a solution to the size measurement problem The principle of Albrecht’s function point analysis (FPA) is that a system is decomposed into functional units. Inputs : information entering the system Outputs : information leaving the system Enquiries : requests for instant access to information Internal logical files : information held within the system
  • 8. Page 8 of 16 External interface files: information held by other system that is used by the system being analyzed. So on the basis of this we basically estimate the time duration for different kind of functional points etc. Object points The approach was devised at the Leonard N. stern school of business, New York University. It has similarities with FP approach, but takes different account of features. The approach uses counts of screen, reports and 3gl component that an application might possess it is these that referred to as objects. Each object has to be classified as one of the following… 1. Simple 2. Medium 3. Difficult The number of objects at each level are multiplied by the approiate complexity weighting as shown in the figure.
  • 9. Page 9 of 16 CPM (Critical path method) In this we basically capture the activities and their inter-relationships using a graph Lines are used to represent the activities. Nodes are used to represent the start and stop of activities. With the help of cpm we can calculate the two things The forward pass in which we calculate the earliest state of the activities and calculate the project completion date.
  • 10. Page 10 of 16 The backward pass in which we calculate the latest start for activities and identify the critical path from the graph. Some common terms in this Critical event : an event that has zero slack Critical path : a path joining those critical events. Example to construct a CPM
  • 12. Page 12 of 16 Pert PERT is a planning and control tool used for defining and controlling the tasks necessary to complete a project. PERT charts and Critical Path Method (CPM) charts are often used interchangeably; the only difference is how task times are computed. Both charts display the total project with all scheduled tasks shown in sequence. The displayed tasks show which ones are in parallel, those tasks that can be performed at the same time. A graphic representation called a "Project Network" or "CPM Diagram" is used to portray graphically the interrelationships of the elements of a project and to show the order in which the activities must be performed. PERT planning involves the following steps:
  • 13. Page 13 of 16 1. Identify the specific activities and milestones. The activities are the tasks of the project. The milestones are the events that mark the beginning and the end of one or more activities. 2. Determine the proper sequence of activities. This step may be combined with #1 above since the activity sequence is evident for some tasks. Other tasks may require some analysis to determine the exact order in which they should be performed. 3. Construct a network diagram. Using the activity sequence information, a network diagram can be drawn showing the sequence of the successive and parallel activities. Arrowed lines represent the activities and circles or "bubbles" represent milestones. 4. Estimate the time required for each activity. Weeks are a commonly used unit of time for activity completion, but any consistent unit of time can be used. A distinguishing feature of PERT is it's ability to deal with uncertainty in activity completion times. For each activity, the model usually includes three time estimates: o Optimistic time - the shortest time in which the activity can be completed. o Most likely time - the completion time having the highest probability. o Pessimistic time - the longest time that an activity may take. From this, the expected time for each activity can be calculated using the following weighted average: Expected Time = (Optimistic + 4 x Most Likely + Pessimistic) / 6 This helps to bias time estimates away from the unrealistically short timescales normally assumed. 5. Determine the critical path. The critical path is determined by adding the times for the activities in each sequence and determining the longest path in the project. The critical path determines the total calendar time required for the project. The
  • 14. Page 14 of 16 amount of time that a non-critical path activity can be delayed without delaying the project is referred to as slack time. If the critical path is not immediately obvious, it may be helpful to determine the following four times for each activity: o ES - Earliest Start time o EF - Earliest Finish time o LS - Latest Start time o LF - Latest Finish time These times are calculated using the expected time for the relevant activities. The earliest start and finish times of each activity are determined by working forward through the network and determining the earliest time at which an activity can start and finish considering its predecessor activities. The latest start and finish times are the latest times that an activity can start and finish without delaying the project. LS and LF are found by working backward through the network. The difference in the latest and earliest finish of each activity is that activity's slack. The critical path then is the path through the network in which none of the activities have slack. The variance in the project completion time can be calculated by summing the variances in the completion times of the activities in the critical path. Given this variance, one can calculate the probability that the project will be completed by a certain date assuming a normal probability distribution for the critical path. The normal distribution assumption holds if the number of activities in the path is large enough for the central limit theorem to be applied. 6. Update the PERT chart as the project progresses. As the project unfolds, the estimated times can be replaced with actual times. In cases where there are delays, additional resources may be needed to stay on schedule and the PERT chart may be modified to reflect the new situation. An example of a PERT chart is provided below:
  • 15. Page 15 of 16 Benefits to using a PERT chart or the Critical Path Method include:  Improved planning and scheduling of activities.  Improved forecasting of resource requirements.  Identification of repetitive planning patterns which can be followed in other projects, thus simplifying the planning process.  Ability to see and thus reschedule activities to reflect interproject dependencies and resource limitations following know priority rules.  It also provides the following: expected project completion time, probability of completion before a specified date, the critical path activities that impact completion time, the activities that have slack time and that can lend resources to critical path activities, and activity start and end dates. Conclusion This helps us to estimate the project duration estimation which later helps to create a comprehensive estimate which will reflect the different tasks and real-world scheduling. This approach will removes the uncertainty and creates a project plan that helps us to know our options and adapt to path changes. The duration estimation also help us to estimate the budget of our project. As we all know that estimates can never be exact but practicing this will make our guesses better.
  • 16. Page 16 of 16 Bibliography https://4pm.com/bottom-up-estimating/ https://www.google.co.in/url?sa=t&rct=j&q=&esrc=s&source=web&cd=5&cad=rja&uact=8&ved=0CEkQ FjAE&url=http%3A%2F%2Frpl-blog.blogspot.com%2F2010%2F03%2F411-top-down-estimation- approach.html&ei=ajtCU6HCKoKOrQfpuYCQDw&usg=AFQjCNE1N13_-t8ZjUaaW- 01OkYFzanMaQ&sig2=svgx9iA9JqHABaLf2HeKvw&bvm=bv.64367178,d.bmk https://slideshare.com