SlideShare a Scribd company logo
1 of 49
Crane Safety Precautions
Purpose
 This procedure and practice is provided as a guide to
Contractor, its subcontractors their staff, and
specifically the rigging staff and rigging coordinators
to execute all crane lifts safely. This procedure shall be
implemented by Contractor and enforced by Owner
on the Project.
2
SCOPEThis procedure provides the following:
Establishes the requirement for organizing a Contractor Crane and
Rigging Group, lists personnel and defines their role in the successful
execution of this practice, identifies the responsibilities of key
personnel for this practice.
Identifies the requirements for design and review of lifting lugs.
Categorizes rigging lifts for and establishes responsibility for the
design, engineering and approval of the transportation and rigging of
all equipment and modules. This practice covers all crawler cranes,
truck cranes, carry deck cranes, monorails, boom trucks, etc.
Establishes guidelines that must be adhered to when requiring a
variance from this procedure.
3
Crane Operator
A qualified person who is licensed, trained, certified
and experienced in the use, the capabilities, and all of
the functions of a specific machine, mechanical system,
or tool. All Crane Operators must meet the following
requirements:
An up-to-date shall be on file with Contractor, detailing
specific experience in crane operation.
4
Signalman
 A designated person who is trained and experience in hand signals
used and understood by crane operators.
 One designated signalman will be responsible for the control and
coordination of any particular lift or Heavy Rigging Activity and shall
wear a green reflective vest.
 Under certain conditions, such as multiple crane lifts, or lifting "in the
blind", it may be deemed necessary for additional signalmen to
participate in a lift or Heavy Rigging Activity. One signalman will be
designated as the “Lead Signalman”.
5
Responsibilities
 Responsible Personnel - The crane operator, and the
qualified field rigger, are jointly responsible for
determination of the load weight and placement of the
crane so that it is set up within the operating radius
selected. The rigging supervisor has final
responsibility for all operations.
6
Contents
• Cranes Instructions & Standards
• Cranes Components & Stability
• Operations Responsibility
• Maintenance or Construction Responsibility
• Critical Lifts
• Precautions
• Incidents
SAFETYI THINK
SAFE
I KNOW THE
RULES
I ACT SAFE
I FOLLOW THE
RULES
If YOU THINK SAFE…
..and YOU ACT SAFE - YOU’LL BE
SAFE
Let’s take a look at, and understand ‘Stability’
Most of crane incidents within the
company are due to ‘loss of stability’
STABILITY
1.1 Outrigger spans
1.2 Outrigger set-up
1.3 Counterweight options
1.4 Center-of-gravity
1.5 Tipping axis
OUTRIGGER SPANS
Partial extension
Full extensionIT IS NOT ALLOWED TO
MIX SPANS-
ONLY ALL FULL SPANS
MAY BE USED
OR
ONLY ALL PARTIAL
SPANS MAY BE USED
OUTRIGGER
SPAN 1
 ALL MAXIMUM
SPAN
OUTRIGGER
SPAN 2
 ALL PARTIAL
SPAN
INCORRECT
OUTRIGGER SPAN 1
X
PARTIAL
SPAN
FULL
SPAN
INCORRECT
OUTRIGGER SPAN 2
X
FULL
SPAN
PARTIAL
SPAN
THE BEAMS TRANSFER LOAD TO THE CARRIER AT THE CORRECT
POSITIONS WHEN CARRIER WHEELS CLEAR THE GROUND.
SPAN OPERATION
CRANE (AND LOAD) WEIGHT
 
THIS BEAM TRANSFERS LOAD TO THE CARRIER AT AN
INCORRECT POSITION WHEN CARRIER RAISES.
THIS AREA IS
NOT STRONG
INCORRECT SPAN -
OPERATOR ERROR
X
OPERATOR ERROR
This accident is due to an
Operator Error.
He used an Incorrect
Outrigger Span……..!
No extension
beams used
OUTRIGGER SECURITY
FOR ROAD
TRAVEL, THESE
LOCKING
DEVICES MUST
BE USED

X
TIPPING AXIS
EXPLANATION 1
TO RIGHT SIDE
‘outriggers
nearest to
the load’
TIPPING AXIS
EXPLANATION 2
STILL TO RIGHT SIDE
ABOUT THE TIPPING
AXIS
CRANE WEIGHT
TIPPING AXIS
LOAD WEIGHT
‘outriggers
nearest to
the load’
XY
OPERATOR ERROR
This accident is due to an Operator Error.
He moved the crane Center-of-Gravity
outside the crane Tipping Axis.
Crane was on
tires only.
No outriggers
in use
 Outrig
gers
Lift Configuration
Boom
CounterweightParts-of-Line
Operating Code
LIFT CONFIGURATION
Lift
Configuration
Lift
Configuration
OPERATOR ERROR
INCORRECT CONFIGURATION
CRANE INSPECTION
I must ensure
this machine
is safe to use If it is to be
used for
traveling
If it is to
be used
for craning
Even for a
run-up,
an inspection
is needed
Operation Responsibility
• Crane, Crane Operator, Rigger Certificate.
• Maintain daily checklist
• An approved lift plan provided.
• Heavy lifts must be noted on the Work Permit.
• If load critical or man basket required operation foreman should
issue the work permit.
• Crane location and positioning.
• Critical Wind Speed.
• Stop the work
1. Obtaining a work permits from the operating Unit
Foreman before bringing the crane inside the
operating area.
2. Ensure that the crane is in good operating condition.
3. Strictly adhere to the procedures and precautions
mentioned in WP.
4. Immediately stop work if unsafe conditions or crane
incident and immediately report.
5. Ensuring that an approved Lift Plan is utilized if the
lift has been determined to be a “Critical Lift"..
Maint. / Construction Responsibility
Critical Lift
Critical lifts are defined as high risk lifts where there
is a potential for serious injury, major property loss,
or disruption of programs or projects. The following
are examples of the critical lifts:
1. Around energized electrical lines.
2. Near or over hydrocarbon loading piers.
3. On barges, vessels and hydrocarbon loading piers.
4. Around and over populated/traffic areas.
5. Tandem, multiple or tailing lifts.
6. On rubber or pick and carry lifts.
7. Personnel Platforms (man lifts)
8. High level or long reach lifts.
SAFETY PRECAUTIONS
 Crane & accessories shall be kept in good condition.
 The crane shall have a sticker updated every three
months
 Crane operated in the vicinity of spills or leaks, special
precautions must be undertaken.
 The weight of the crane shall be stenciled on the crane.
 Repair work, maintenance or refueling inside the Unit
battery limits.
 Moving of a crane into or out of an operating unit.
 The traveling of cranes with suspended loads is not
allowed in Rabigh Refinery
X
X
Poor flat
support
X
X
X
Load is
too
close
from the
crane
Telescoping out
and increasing
The load radius
Too much load
Strength
structure
failure
Stability Tripping
failure
RESULT
Incidents
Crane Incident
This accident is due to an
Operator Error. The operator
programmed the incorrect
code into the R.C.L. or it was
by-passed and then he
moved the crane Center-of-
Gravity outside the crane
Tipping Axis.
Crane Incident
10.5t
Counterweights
Stabilizers are
retracted
Crane Incident
Note the
trench here
The crane was on
tires with wheels in
the trench.
If the operator had
knowledge of drive
modes, this
accident would not
have occurred
Crane Incident
...TIPPING (OR
OVERTURNING) OCCURS
It’s as simple as that!!!
This accident is due to an Operator Error. The
operator programmed the incorrect code into the
R.C.L. or it was by-passed and then he moved the
crane Center-of-Gravity outside the crane Tipping
Axis. (Rigger was not attend)
Rigging
All manufactured rigging equipment including, but not limited to: slings
(nylon and wire),
chokers, wirerope lashing, come-alongs, chain falls, etc.
Contractor shall ensure all rigging equipment shall be free from defects,
in good operating
condition and maintained in a safe condition and shall bear the serial
number of the
manufacturer and the Safe Working (SWL) Load capacity marked on it.
All rigging equipment
will also be accompanied by the manufacturer’s certificate indicating the
serial number and
capacity.
Safe Work Practices
1. Rigging and lashing should be protected from damage by softeners or other active
means while in place.
2. Nylon, rope, or other slings subject to damage by sharp edges shall be protected during
the lift.
3. The chains or ropes of a come-along or chain fall shall not be used as chokers.
4. Lifting bays used to make lifts will be barricaded at ground level to protect employees
from walking under loads.
5. Buckets, barrels, tubs, etc. used to lift smaller objects shall be effectively covered and
secured during lifting to prevent accidental spillage of their contents.
6. Sheet metal, boiler siding, insulation or other objects of a sheet nature will not be lifted
by sheet dogs without the prior approval of the Project Manager.
7. Rigging equipment will not remain in the elements longer than necessary to do the
work, protected from mud, dirt and chemical exposures.
8. No hand spliced slings are allowed on the project.
9. Nylon slings are not allowed for hoisting structural steel.
10. Single sling lifts are not allowed.
11. Only inspected rigging equipment bearing the colour coding for the month and that
have the SWL indicated on it and with the manufacturer’s certification shall be allowed
to be used.
InspectionInspection
All rigging will be inspected on a monthly basis. The inspection will be conducted and
documented. Inspection reports are to turned in to the Project Safety Office, by the fifth
(5th) day of that month. The Rigging Supervisor, or his designee will conduct this
inspection.
Contractor shall make the inspection records and manufacture’s certifications and
specifications of the rigging equipment available to OWNER upon request. The Rigging
Supervisor or designee will insure that any item found to be defective is removed from
service immediately. These items, if found to be unacceptable, will be tagged out of
service, "DO NOT USE," and returned to the tool room/warehouse.
All rigging equipment found to be in good condition when inspected shall be color
coded for the monthly period, and valid for that period only.
Color Coding
The color coding scheme and placement of color coding
for rigging equipment on this project
will be as follows:-
Yellow Blue Orange Green Red White
January February March April May June
July August September October November December
NOTE!!! Colour coded tie-wraps may be substituted
for tape.
EQUIPMENT REQUIREMENTS
All motorized equipment must have a reverse signal alarm audible at
30 meter distance above the surrounding noise level. In addition while
the equipment is being operated shall have a flagman wearing a yellow
reflective vest and equipped with a red flag and a green flag.
All cracked and broken glass shall be replaced before bringing vehicles
on the jobsite. If glass is broken or damaged on jobsite and if damage
is severe enough to cause a potential safety problem, the machine shall
be stopped until such damage has been repaired.
Vehicles used to transport employees shall have seats firmly secured
and adequate for the number of employees to be carried and all
passengers should be properly seated. Standing on the back of moving
vehicles is prohibited. It is not allowed to transport employees in the
back of pick-up trucks or any open vehicle.
EQUIPMENT REQUIREMENTS
Owner shall review and approve locations for storage of all fuels, lubricants, starting fluids
prior to use by Contractor for storage.
Contractor shall equip all vehicles and fuel driven construction equipment with a fire
extinguisher, red triangles, flashlight and a first aid kit.
Safety Devices
Contractor shall equip all vehicles and fuel driven construction equipment with a fire
extinguisher, red triangles, flashlight and a first aid kit.
All rubber tired, self propelled scrapers, rubber tired, front-end loaders, rubber tired dozers,
wheel type agricultural and industrial tractors, crawler tractors, crawler type loaders and
motor graders shall be equipped with rollover protective structures and seat belts.
Inspection of these devices will be included as part of the operators' daily pre-operational
inspection, as well in the formal monthly inspection.
No equipment shall be operated with defective or missing safety devices.
Engineered Lifts
Engineered lifts are categorized “A” , “B” and “C” lifts.
“A” Lifts
Lifts up to one hundred (100) tons per the following requirements:
Vessels Vertical 30 tons and over
Vertical 2.4 meters (8 feet) diameter and over
Horizontal 60 tons and over
All other equipment and structures sixty (60) tons and over.
Equipment or vessels over twenty (20) tons that are inside structures, in
inaccessible locations, over operating processes or in hazardous areas as
determined by the site manager or rigging engineer. Also included is
equipment and vessels constructed of nonferrous materials, or are otherwise
prone to damage during handling.
All multiple crane lifts (exclusive of a tailing crane) in which the load could be
transferred from one crane to another during the lift.
All lifts over eighty (80) percent of the capacity chart of the crane for the boom
length and operating radius being used, or over ninety (90) percent if the crane
has an operational load indication device with an overload cut-off.
Transportation - All plant equipment over sixty (60) tons.
“B” Lifts
Lifts 100 to 600 tons.
Responsible personnel for a Type “B” engineered lift must be:
“C” Lifts
Lifts six hundred (600) tons and above.
Prior to awarding a rigging contract and approving a rigging plan,
the manager of the project along with the site manager and rigging
manager shall review the rigging plan, risk analysis, and/or
contractor bid evaluation to ensure that risk/liabilities are
understood and mitigated to the maximum extent possible.
SUMMARY
This specification describes the requirements for
furnishing all engineering, supervision, labor,
equipment, tools, materials, services, and supplies
necessary to provide transportation, erection, and
material handling services to satisfy the particular
requirements of the project/site. This specification
provides these requirements for services performed by
Contractor.

More Related Content

What's hot

Presentation of Rigger
Presentation of RiggerPresentation of Rigger
Presentation of RiggerMajid Hussain
 
Signalman training
Signalman trainingSignalman training
Signalman trainingRob Cowden
 
3 emergency management risk assessment templates
3 emergency management risk assessment templates3 emergency management risk assessment templates
3 emergency management risk assessment templatesDwarika Bhushan Sharma
 
Lifting & procedure
Lifting & procedureLifting & procedure
Lifting & procedurePavan Noel
 
A Part 6 Lifting Operations
A  Part 6 Lifting OperationsA  Part 6 Lifting Operations
A Part 6 Lifting OperationsJames McCann
 
Liftingproedure
LiftingproedureLiftingproedure
LiftingproedureZhai Rull
 
Crane Safety & Rigging
Crane Safety & RiggingCrane Safety & Rigging
Crane Safety & Riggingfcarlson
 
BANKSMAN TRAINING.ppt
BANKSMAN TRAINING.pptBANKSMAN TRAINING.ppt
BANKSMAN TRAINING.pptKamran Zafar
 
Rigger signalman handbook
Rigger  signalman handbookRigger  signalman handbook
Rigger signalman handbooknhivan
 
313440656 crane-lifting-calculation-sheet
313440656 crane-lifting-calculation-sheet313440656 crane-lifting-calculation-sheet
313440656 crane-lifting-calculation-sheetPhạm Thành
 
Hoisting and Rigging Safety
Hoisting and Rigging SafetyHoisting and Rigging Safety
Hoisting and Rigging SafetyNickHawkins19
 
Risk assessment for testing & commissioning of cranes
Risk assessment for  testing & commissioning of cranesRisk assessment for  testing & commissioning of cranes
Risk assessment for testing & commissioning of cranesAzmeel Contracting Company
 
Boom lift training
Boom lift trainingBoom lift training
Boom lift trainingsheila bert
 
Crane Safety Training Presentation
Crane Safety Training PresentationCrane Safety Training Presentation
Crane Safety Training PresentationFAIZ FAREED
 

What's hot (20)

Presentation of Rigger
Presentation of RiggerPresentation of Rigger
Presentation of Rigger
 
Signalman training
Signalman trainingSignalman training
Signalman training
 
3 emergency management risk assessment templates
3 emergency management risk assessment templates3 emergency management risk assessment templates
3 emergency management risk assessment templates
 
Lifting & procedure
Lifting & procedureLifting & procedure
Lifting & procedure
 
A Part 6 Lifting Operations
A  Part 6 Lifting OperationsA  Part 6 Lifting Operations
A Part 6 Lifting Operations
 
Liftingproedure
LiftingproedureLiftingproedure
Liftingproedure
 
Lifting Operation Safety ppt.pptx
Lifting Operation Safety ppt.pptxLifting Operation Safety ppt.pptx
Lifting Operation Safety ppt.pptx
 
Safe Slinging Practices Training by PE
Safe Slinging Practices Training by PESafe Slinging Practices Training by PE
Safe Slinging Practices Training by PE
 
Lifting plan template
Lifting plan templateLifting plan template
Lifting plan template
 
Crane Safety & Rigging
Crane Safety & RiggingCrane Safety & Rigging
Crane Safety & Rigging
 
BANKSMAN TRAINING.ppt
BANKSMAN TRAINING.pptBANKSMAN TRAINING.ppt
BANKSMAN TRAINING.ppt
 
Rigger signalman handbook
Rigger  signalman handbookRigger  signalman handbook
Rigger signalman handbook
 
313440656 crane-lifting-calculation-sheet
313440656 crane-lifting-calculation-sheet313440656 crane-lifting-calculation-sheet
313440656 crane-lifting-calculation-sheet
 
Rigging Presentation by Pipeweldrig
Rigging Presentation by PipeweldrigRigging Presentation by Pipeweldrig
Rigging Presentation by Pipeweldrig
 
Hoisting and Rigging Safety
Hoisting and Rigging SafetyHoisting and Rigging Safety
Hoisting and Rigging Safety
 
Below the hook
Below the hook Below the hook
Below the hook
 
Risk assessment for testing & commissioning of cranes
Risk assessment for  testing & commissioning of cranesRisk assessment for  testing & commissioning of cranes
Risk assessment for testing & commissioning of cranes
 
Boom lift training
Boom lift trainingBoom lift training
Boom lift training
 
Crane Safety Training Presentation
Crane Safety Training PresentationCrane Safety Training Presentation
Crane Safety Training Presentation
 
Lifting & Rigging by NEIS
Lifting & Rigging by NEISLifting & Rigging by NEIS
Lifting & Rigging by NEIS
 

Viewers also liked (20)

Cranes ppt
Cranes pptCranes ppt
Cranes ppt
 
presentation on mobile cranes
presentation on mobile cranespresentation on mobile cranes
presentation on mobile cranes
 
Crane safety and_awareness_presentation_ttp
Crane safety and_awareness_presentation_ttpCrane safety and_awareness_presentation_ttp
Crane safety and_awareness_presentation_ttp
 
Wrs rigging practice
Wrs rigging practiceWrs rigging practice
Wrs rigging practice
 
SAFE USE OF LIFTING EQUIPMENT LEEA
SAFE USE OF LIFTING EQUIPMENT LEEASAFE USE OF LIFTING EQUIPMENT LEEA
SAFE USE OF LIFTING EQUIPMENT LEEA
 
Rigging & slinging
Rigging & slingingRigging & slinging
Rigging & slinging
 
Operating practices
Operating practicesOperating practices
Operating practices
 
Mobile crane
Mobile craneMobile crane
Mobile crane
 
Cranes
CranesCranes
Cranes
 
Rope handbook
Rope handbookRope handbook
Rope handbook
 
R002
R002R002
R002
 
lifting operation
lifting operationlifting operation
lifting operation
 
Wire rope
Wire ropeWire rope
Wire rope
 
Basic rigging training manual
Basic rigging training manualBasic rigging training manual
Basic rigging training manual
 
Safe Rigging Training
Safe Rigging TrainingSafe Rigging Training
Safe Rigging Training
 
CV Pete Curtis stage 3 crane operator
CV    Pete Curtis   stage 3 crane operatorCV    Pete Curtis   stage 3 crane operator
CV Pete Curtis stage 3 crane operator
 
3 D Lift Plan Slide Show
3 D Lift Plan Slide Show3 D Lift Plan Slide Show
3 D Lift Plan Slide Show
 
L02 Architecture
L02 ArchitectureL02 Architecture
L02 Architecture
 
Teknik kejuruteraan kertas 1
Teknik kejuruteraan kertas 1Teknik kejuruteraan kertas 1
Teknik kejuruteraan kertas 1
 
3. osh management
3. osh management3. osh management
3. osh management
 

Similar to Crane Operation - Lifting

Safety engineering module 6 shskwn ejekdndhek
Safety engineering module 6 shskwn ejekdndhekSafety engineering module 6 shskwn ejekdndhek
Safety engineering module 6 shskwn ejekdndhekRoseGaming1
 
2000 08 safe use of mobile cranes in construction sites
2000 08 safe use of mobile cranes in construction sites2000 08 safe use of mobile cranes in construction sites
2000 08 safe use of mobile cranes in construction sitesPrastowo Priyatmoko
 
HSE-BMS-011 Crane & Lifting Safety.ppt...
HSE-BMS-011 Crane & Lifting Safety.ppt...HSE-BMS-011 Crane & Lifting Safety.ppt...
HSE-BMS-011 Crane & Lifting Safety.ppt...AhmedAliKhan38
 
Crane operator safety procedure
Crane operator safety procedureCrane operator safety procedure
Crane operator safety procedureAbdul Shukur
 
Safe Operations of Cranes, Hoists and Truck Hoists by Reagan Safety
Safe Operations of Cranes, Hoists and Truck Hoists by Reagan SafetySafe Operations of Cranes, Hoists and Truck Hoists by Reagan Safety
Safe Operations of Cranes, Hoists and Truck Hoists by Reagan SafetyAtlantic Training, LLC.
 
Crane & Lifting Safety.ppt Crane lifting safety useful for construction industry
Crane & Lifting Safety.ppt Crane lifting safety useful for construction industryCrane & Lifting Safety.ppt Crane lifting safety useful for construction industry
Crane & Lifting Safety.ppt Crane lifting safety useful for construction industryRamana Reddy G
 
Crane Safety Tips for Construction Project..pdf
Crane Safety Tips for Construction Project..pdfCrane Safety Tips for Construction Project..pdf
Crane Safety Tips for Construction Project..pdfManoj Kumar
 
Crawler crane introduction
Crawler crane   introductionCrawler crane   introduction
Crawler crane introductionBhushan Goyal
 
Safety Tip: 10 Steps to Safer Crane Operation
Safety Tip: 10 Steps to Safer Crane OperationSafety Tip: 10 Steps to Safer Crane Operation
Safety Tip: 10 Steps to Safer Crane OperationComplianceSigns, LLC
 
Rig Move Management and Logistics Plan.doc
Rig Move Management and Logistics Plan.docRig Move Management and Logistics Plan.doc
Rig Move Management and Logistics Plan.docYasserAbdulkareem1
 
Truck crane training bill brown
Truck crane training bill brownTruck crane training bill brown
Truck crane training bill brownBill Brown
 
Overhead-Cranes safety training.ppt
Overhead-Cranes safety training.pptOverhead-Cranes safety training.ppt
Overhead-Cranes safety training.pptRazFazwan
 
Quality Control Operator Training &.pptx
Quality Control Operator Training &.pptxQuality Control Operator Training &.pptx
Quality Control Operator Training &.pptxAizazFarhat3
 

Similar to Crane Operation - Lifting (20)

Safety engineering module 6 shskwn ejekdndhek
Safety engineering module 6 shskwn ejekdndhekSafety engineering module 6 shskwn ejekdndhek
Safety engineering module 6 shskwn ejekdndhek
 
2000 08 safe use of mobile cranes in construction sites
2000 08 safe use of mobile cranes in construction sites2000 08 safe use of mobile cranes in construction sites
2000 08 safe use of mobile cranes in construction sites
 
HSE-BMS-011 Crane & Lifting Safety.ppt...
HSE-BMS-011 Crane & Lifting Safety.ppt...HSE-BMS-011 Crane & Lifting Safety.ppt...
HSE-BMS-011 Crane & Lifting Safety.ppt...
 
safe lift EMERSON EDUARDO RODRIGUES
safe lift EMERSON EDUARDO RODRIGUESsafe lift EMERSON EDUARDO RODRIGUES
safe lift EMERSON EDUARDO RODRIGUES
 
PA PIPE WORK 14 inch spool TH11177-06-PI-10-004-5
PA PIPE WORK 14 inch spool TH11177-06-PI-10-004-5PA PIPE WORK 14 inch spool TH11177-06-PI-10-004-5
PA PIPE WORK 14 inch spool TH11177-06-PI-10-004-5
 
Crane operator safety procedure
Crane operator safety procedureCrane operator safety procedure
Crane operator safety procedure
 
Safe Operations of Cranes, Hoists and Truck Hoists by Reagan Safety
Safe Operations of Cranes, Hoists and Truck Hoists by Reagan SafetySafe Operations of Cranes, Hoists and Truck Hoists by Reagan Safety
Safe Operations of Cranes, Hoists and Truck Hoists by Reagan Safety
 
Liffting supervisor
Liffting supervisorLiffting supervisor
Liffting supervisor
 
Lifting tools
Lifting toolsLifting tools
Lifting tools
 
Crane & Lifting Safety.ppt Crane lifting safety useful for construction industry
Crane & Lifting Safety.ppt Crane lifting safety useful for construction industryCrane & Lifting Safety.ppt Crane lifting safety useful for construction industry
Crane & Lifting Safety.ppt Crane lifting safety useful for construction industry
 
SDV-20253 VALVE MOD 9 lift plan 1
SDV-20253 VALVE MOD 9 lift plan 1SDV-20253 VALVE MOD 9 lift plan 1
SDV-20253 VALVE MOD 9 lift plan 1
 
Failure analysis mtn526
Failure analysis mtn526Failure analysis mtn526
Failure analysis mtn526
 
Crane Safety Tips for Construction Project..pdf
Crane Safety Tips for Construction Project..pdfCrane Safety Tips for Construction Project..pdf
Crane Safety Tips for Construction Project..pdf
 
Crawler crane introduction
Crawler crane   introductionCrawler crane   introduction
Crawler crane introduction
 
HSE
HSEHSE
HSE
 
Safety Tip: 10 Steps to Safer Crane Operation
Safety Tip: 10 Steps to Safer Crane OperationSafety Tip: 10 Steps to Safer Crane Operation
Safety Tip: 10 Steps to Safer Crane Operation
 
Rig Move Management and Logistics Plan.doc
Rig Move Management and Logistics Plan.docRig Move Management and Logistics Plan.doc
Rig Move Management and Logistics Plan.doc
 
Truck crane training bill brown
Truck crane training bill brownTruck crane training bill brown
Truck crane training bill brown
 
Overhead-Cranes safety training.ppt
Overhead-Cranes safety training.pptOverhead-Cranes safety training.ppt
Overhead-Cranes safety training.ppt
 
Quality Control Operator Training &.pptx
Quality Control Operator Training &.pptxQuality Control Operator Training &.pptx
Quality Control Operator Training &.pptx
 

Crane Operation - Lifting

  • 2. Purpose  This procedure and practice is provided as a guide to Contractor, its subcontractors their staff, and specifically the rigging staff and rigging coordinators to execute all crane lifts safely. This procedure shall be implemented by Contractor and enforced by Owner on the Project. 2
  • 3. SCOPEThis procedure provides the following: Establishes the requirement for organizing a Contractor Crane and Rigging Group, lists personnel and defines their role in the successful execution of this practice, identifies the responsibilities of key personnel for this practice. Identifies the requirements for design and review of lifting lugs. Categorizes rigging lifts for and establishes responsibility for the design, engineering and approval of the transportation and rigging of all equipment and modules. This practice covers all crawler cranes, truck cranes, carry deck cranes, monorails, boom trucks, etc. Establishes guidelines that must be adhered to when requiring a variance from this procedure. 3
  • 4. Crane Operator A qualified person who is licensed, trained, certified and experienced in the use, the capabilities, and all of the functions of a specific machine, mechanical system, or tool. All Crane Operators must meet the following requirements: An up-to-date shall be on file with Contractor, detailing specific experience in crane operation. 4
  • 5. Signalman  A designated person who is trained and experience in hand signals used and understood by crane operators.  One designated signalman will be responsible for the control and coordination of any particular lift or Heavy Rigging Activity and shall wear a green reflective vest.  Under certain conditions, such as multiple crane lifts, or lifting "in the blind", it may be deemed necessary for additional signalmen to participate in a lift or Heavy Rigging Activity. One signalman will be designated as the “Lead Signalman”. 5
  • 6. Responsibilities  Responsible Personnel - The crane operator, and the qualified field rigger, are jointly responsible for determination of the load weight and placement of the crane so that it is set up within the operating radius selected. The rigging supervisor has final responsibility for all operations. 6
  • 7. Contents • Cranes Instructions & Standards • Cranes Components & Stability • Operations Responsibility • Maintenance or Construction Responsibility • Critical Lifts • Precautions • Incidents
  • 8. SAFETYI THINK SAFE I KNOW THE RULES I ACT SAFE I FOLLOW THE RULES If YOU THINK SAFE… ..and YOU ACT SAFE - YOU’LL BE SAFE
  • 9. Let’s take a look at, and understand ‘Stability’ Most of crane incidents within the company are due to ‘loss of stability’
  • 10. STABILITY 1.1 Outrigger spans 1.2 Outrigger set-up 1.3 Counterweight options 1.4 Center-of-gravity 1.5 Tipping axis
  • 11. OUTRIGGER SPANS Partial extension Full extensionIT IS NOT ALLOWED TO MIX SPANS- ONLY ALL FULL SPANS MAY BE USED OR ONLY ALL PARTIAL SPANS MAY BE USED
  • 12. OUTRIGGER SPAN 1  ALL MAXIMUM SPAN
  • 13. OUTRIGGER SPAN 2  ALL PARTIAL SPAN
  • 16. THE BEAMS TRANSFER LOAD TO THE CARRIER AT THE CORRECT POSITIONS WHEN CARRIER WHEELS CLEAR THE GROUND. SPAN OPERATION CRANE (AND LOAD) WEIGHT  
  • 17. THIS BEAM TRANSFERS LOAD TO THE CARRIER AT AN INCORRECT POSITION WHEN CARRIER RAISES. THIS AREA IS NOT STRONG INCORRECT SPAN - OPERATOR ERROR X
  • 18. OPERATOR ERROR This accident is due to an Operator Error. He used an Incorrect Outrigger Span……..! No extension beams used
  • 19. OUTRIGGER SECURITY FOR ROAD TRAVEL, THESE LOCKING DEVICES MUST BE USED  X
  • 20. TIPPING AXIS EXPLANATION 1 TO RIGHT SIDE ‘outriggers nearest to the load’
  • 22. ABOUT THE TIPPING AXIS CRANE WEIGHT TIPPING AXIS LOAD WEIGHT ‘outriggers nearest to the load’ XY
  • 23. OPERATOR ERROR This accident is due to an Operator Error. He moved the crane Center-of-Gravity outside the crane Tipping Axis. Crane was on tires only. No outriggers in use
  • 24.  Outrig gers Lift Configuration Boom CounterweightParts-of-Line Operating Code LIFT CONFIGURATION Lift Configuration Lift Configuration
  • 26. CRANE INSPECTION I must ensure this machine is safe to use If it is to be used for traveling If it is to be used for craning Even for a run-up, an inspection is needed
  • 27. Operation Responsibility • Crane, Crane Operator, Rigger Certificate. • Maintain daily checklist • An approved lift plan provided. • Heavy lifts must be noted on the Work Permit. • If load critical or man basket required operation foreman should issue the work permit. • Crane location and positioning. • Critical Wind Speed. • Stop the work
  • 28. 1. Obtaining a work permits from the operating Unit Foreman before bringing the crane inside the operating area. 2. Ensure that the crane is in good operating condition. 3. Strictly adhere to the procedures and precautions mentioned in WP. 4. Immediately stop work if unsafe conditions or crane incident and immediately report. 5. Ensuring that an approved Lift Plan is utilized if the lift has been determined to be a “Critical Lift".. Maint. / Construction Responsibility
  • 29. Critical Lift Critical lifts are defined as high risk lifts where there is a potential for serious injury, major property loss, or disruption of programs or projects. The following are examples of the critical lifts: 1. Around energized electrical lines. 2. Near or over hydrocarbon loading piers. 3. On barges, vessels and hydrocarbon loading piers. 4. Around and over populated/traffic areas. 5. Tandem, multiple or tailing lifts. 6. On rubber or pick and carry lifts. 7. Personnel Platforms (man lifts) 8. High level or long reach lifts.
  • 30. SAFETY PRECAUTIONS  Crane & accessories shall be kept in good condition.  The crane shall have a sticker updated every three months  Crane operated in the vicinity of spills or leaks, special precautions must be undertaken.  The weight of the crane shall be stenciled on the crane.  Repair work, maintenance or refueling inside the Unit battery limits.  Moving of a crane into or out of an operating unit.  The traveling of cranes with suspended loads is not allowed in Rabigh Refinery
  • 32. X X X
  • 33. Load is too close from the crane Telescoping out and increasing The load radius Too much load Strength structure failure Stability Tripping failure RESULT
  • 35. Crane Incident This accident is due to an Operator Error. The operator programmed the incorrect code into the R.C.L. or it was by-passed and then he moved the crane Center-of- Gravity outside the crane Tipping Axis.
  • 37. Crane Incident Note the trench here The crane was on tires with wheels in the trench. If the operator had knowledge of drive modes, this accident would not have occurred
  • 38. Crane Incident ...TIPPING (OR OVERTURNING) OCCURS It’s as simple as that!!! This accident is due to an Operator Error. The operator programmed the incorrect code into the R.C.L. or it was by-passed and then he moved the crane Center-of-Gravity outside the crane Tipping Axis. (Rigger was not attend)
  • 39.
  • 40.
  • 41. Rigging All manufactured rigging equipment including, but not limited to: slings (nylon and wire), chokers, wirerope lashing, come-alongs, chain falls, etc. Contractor shall ensure all rigging equipment shall be free from defects, in good operating condition and maintained in a safe condition and shall bear the serial number of the manufacturer and the Safe Working (SWL) Load capacity marked on it. All rigging equipment will also be accompanied by the manufacturer’s certificate indicating the serial number and capacity.
  • 42. Safe Work Practices 1. Rigging and lashing should be protected from damage by softeners or other active means while in place. 2. Nylon, rope, or other slings subject to damage by sharp edges shall be protected during the lift. 3. The chains or ropes of a come-along or chain fall shall not be used as chokers. 4. Lifting bays used to make lifts will be barricaded at ground level to protect employees from walking under loads. 5. Buckets, barrels, tubs, etc. used to lift smaller objects shall be effectively covered and secured during lifting to prevent accidental spillage of their contents. 6. Sheet metal, boiler siding, insulation or other objects of a sheet nature will not be lifted by sheet dogs without the prior approval of the Project Manager. 7. Rigging equipment will not remain in the elements longer than necessary to do the work, protected from mud, dirt and chemical exposures. 8. No hand spliced slings are allowed on the project. 9. Nylon slings are not allowed for hoisting structural steel. 10. Single sling lifts are not allowed. 11. Only inspected rigging equipment bearing the colour coding for the month and that have the SWL indicated on it and with the manufacturer’s certification shall be allowed to be used.
  • 43. InspectionInspection All rigging will be inspected on a monthly basis. The inspection will be conducted and documented. Inspection reports are to turned in to the Project Safety Office, by the fifth (5th) day of that month. The Rigging Supervisor, or his designee will conduct this inspection. Contractor shall make the inspection records and manufacture’s certifications and specifications of the rigging equipment available to OWNER upon request. The Rigging Supervisor or designee will insure that any item found to be defective is removed from service immediately. These items, if found to be unacceptable, will be tagged out of service, "DO NOT USE," and returned to the tool room/warehouse. All rigging equipment found to be in good condition when inspected shall be color coded for the monthly period, and valid for that period only.
  • 44. Color Coding The color coding scheme and placement of color coding for rigging equipment on this project will be as follows:- Yellow Blue Orange Green Red White January February March April May June July August September October November December NOTE!!! Colour coded tie-wraps may be substituted for tape.
  • 45. EQUIPMENT REQUIREMENTS All motorized equipment must have a reverse signal alarm audible at 30 meter distance above the surrounding noise level. In addition while the equipment is being operated shall have a flagman wearing a yellow reflective vest and equipped with a red flag and a green flag. All cracked and broken glass shall be replaced before bringing vehicles on the jobsite. If glass is broken or damaged on jobsite and if damage is severe enough to cause a potential safety problem, the machine shall be stopped until such damage has been repaired. Vehicles used to transport employees shall have seats firmly secured and adequate for the number of employees to be carried and all passengers should be properly seated. Standing on the back of moving vehicles is prohibited. It is not allowed to transport employees in the back of pick-up trucks or any open vehicle.
  • 46. EQUIPMENT REQUIREMENTS Owner shall review and approve locations for storage of all fuels, lubricants, starting fluids prior to use by Contractor for storage. Contractor shall equip all vehicles and fuel driven construction equipment with a fire extinguisher, red triangles, flashlight and a first aid kit. Safety Devices Contractor shall equip all vehicles and fuel driven construction equipment with a fire extinguisher, red triangles, flashlight and a first aid kit. All rubber tired, self propelled scrapers, rubber tired, front-end loaders, rubber tired dozers, wheel type agricultural and industrial tractors, crawler tractors, crawler type loaders and motor graders shall be equipped with rollover protective structures and seat belts. Inspection of these devices will be included as part of the operators' daily pre-operational inspection, as well in the formal monthly inspection. No equipment shall be operated with defective or missing safety devices.
  • 47. Engineered Lifts Engineered lifts are categorized “A” , “B” and “C” lifts. “A” Lifts Lifts up to one hundred (100) tons per the following requirements: Vessels Vertical 30 tons and over Vertical 2.4 meters (8 feet) diameter and over Horizontal 60 tons and over All other equipment and structures sixty (60) tons and over. Equipment or vessels over twenty (20) tons that are inside structures, in inaccessible locations, over operating processes or in hazardous areas as determined by the site manager or rigging engineer. Also included is equipment and vessels constructed of nonferrous materials, or are otherwise prone to damage during handling. All multiple crane lifts (exclusive of a tailing crane) in which the load could be transferred from one crane to another during the lift. All lifts over eighty (80) percent of the capacity chart of the crane for the boom length and operating radius being used, or over ninety (90) percent if the crane has an operational load indication device with an overload cut-off. Transportation - All plant equipment over sixty (60) tons.
  • 48. “B” Lifts Lifts 100 to 600 tons. Responsible personnel for a Type “B” engineered lift must be: “C” Lifts Lifts six hundred (600) tons and above. Prior to awarding a rigging contract and approving a rigging plan, the manager of the project along with the site manager and rigging manager shall review the rigging plan, risk analysis, and/or contractor bid evaluation to ensure that risk/liabilities are understood and mitigated to the maximum extent possible.
  • 49. SUMMARY This specification describes the requirements for furnishing all engineering, supervision, labor, equipment, tools, materials, services, and supplies necessary to provide transportation, erection, and material handling services to satisfy the particular requirements of the project/site. This specification provides these requirements for services performed by Contractor.

Editor's Notes

  1. QJF
  2. QJF
  3. QJF
  4. QJF
  5. QJF
  6. QJF
  7. QJF
  8. QJF
  9. QJF
  10. QJF
  11. QJF
  12. QJF
  13. QJF
  14. QJF
  15. QJF
  16. QJF