57. Timelines for the Development of proposed projects Phase I Year 1 Phase 1 Zoo Jamaican Paradise and Naturale Approx. 7 – 10 mths Animal Hospital Approx. 6 mths Phase 1 Gardens (including fencing & lighting) Approx. 8 mths Orchid House Approx. 4 mths Jogging Trail Approx. 3 mths Ornamental Gardens Start Nursery Development Approx. 6 mths
58. Timelines for the Development of proposed projects Phase II Year 2 –3 Phase 2 Zoo African Outpost Start to completion Phase 2 Gardens Botanical Museum 1 year JCDT Building Start Theme Park (formerly Coconut Park) Start Roads and car parks Start Ornamental Gardens Continuation
59. Timelines for the Development of proposed projects Phase III Yr 3 –5 Phase 3 Zoo: The Americas Start to completion Phase 3 Gardens Ornamental Gardens Continuation Conservation & Research Facilities Start JCDT Building Completion