OEE-Overall Equipment
Effectiveness




                     Guide
                 July 2010
OEE-When to use

1. Does your production have bottlenecks that you
   are not aware of?

2. Could one machine be dragging down the entire
   facility?

3. Does your equipment have excess capacity that
   could be easily and inexpensively tapped?
OEE-Benefits




HELPS YOU INSTANTLY
MAKE MORE WITH WHAT
      YOU HAVE
OEE- What is it


OEE is just a Best Practice that
 helps you monitor and improve
    the effectiveness of your
            processes
OEE- Guide



 OEE        Six Big     World
Factors     Losses    Class OEE

Formulas     OEE        Visual
            Example     OEE
OEE-Factors


                                                                                  Time Available
              Plant Operating Time                                                i.e. LMI Mex
                                                                                  10hrs

                                                                 Planned          Subtract
         Plant Operating Time                                   Shutdown
                                                                                  Lunch,Breaks,
                                                                                  Maintenace
                                                             Subtract
                                            Down Time
        Operating Time                        Loss
                                                             •Equipment failure
                                                             •Mat. Shortages,
                                                             •Changeover time
                                   Speed    Subtract
    Net Operating Time             Loss     •Different material, machine wear,
                                            operator inefficiency
                         Quality   Subtract
Fully Productive Time     Loss     •Rework time
                                   •Scrap



                               OEE Goal is to Maximize Fully
                               Productive Time
OEE-Factors

 The following table is a review of the interpretation of the core concepts.

      OEE LOSS                                           OEE Factor
Planned Shutdown     *Not part of the calculation
Down Time Loss       *Availability=Ratio of Operating Time to Planned Production Time
                     (Operating Time=Planned Production Time-Down Time Loss)
                     *100% Availability means the process has been running without any recorded stops
Speed Loss           *Performance= Ratio of Net Operating time to Operating Time
                     (Net Operating Time=Operating Time-Speed Loss)
                     *Interpreted as Ideal Cycle Time to Actual Cycle Time
                     *100% Performance means the process has been consistently running at its
                     theoretical maximun speed
Quality Loss         *Quality=Ratio of Fully Productive Time to Net Operating Time
                     (Fully Productive Time=Net Operating Time-Quality Loss)
                     *Interpreted as the ratio of Good Pieces to Total Pieces
                     *100% Qaulity means there have been no reject or rework pieces

               This factor can then drill down into productivity losses
OEE-6 Big Losses
                  Six Big Loss      OEE Loss
                   Category         Category          Event Examples              Comment
                 Breakdowns      Down Time Loss Tooling failures            There is flexibility to
                                                Unplanned maintenance         decide between a
                                                General breakdowns          breakdown and small
                                                Equipment failure                    stop
    Those        Set Up and
                 Adjustments     Down Time Loss Setup/changeover
 productivity                                   Material shortages
                                                                         This loss is adressed
                                                                            through set up
 Losses are                                     Operator shortages
                                                                          reduction projects
                                                Major adjustments
called the SIX                                  Warm-Up Time
BIG LOSSES       Small Stops       Speed Loss   Obstructed product flow
                                                Component jams
                                                                        Typically includes stops
                                                Misfeeds
                                                                          that are under five
                                                Sensored blocked
                                                                                minutes
                                                Delivery blocked
                                                Cleaning / Checking
                 Reduced
                 Speed             Speed Loss     Rough running
                                                                           Anything that prevents
                                                  Under nameplate capacity
                                                                            the process running
                                                  Under designed capacity
                                                                                normal speed
                                                  Equipment wear
                                                  Operator inefficiency
                 1.Startup                                                 1.Rejects during warm
                 Rejects           Quality Loss   Scrap                     up, start up and early
                 2.Production                     Rework                          production
                 Rejects                          In process damage           2. Rejects during
                                                  In process expiration          steady-state
                                                  Incorrect assembly              production
OEE-World Class




    Accepted World Class            OEE Factor     World Class
    Performance per Factor is:    Availability    90.0%
                                  Performance     95.0%
                                  Quality         99.9%
                                  OEE             85.0%


Studies indicate that most manufacturing plants are around 60% performance
in OEE. A world class is considered to be 85% or more.
OEE-Formulas


Availability= Operating Time / Planned Production Time




Performance = Ideal Cycle Time / (Operating Time/Total Pieces)




Quality = Good Pieces / Total Pieces




OEE = Availability x Performance x Quality
OEE-Example
                          Item                Data
                    Shift Length     10 hrs = 600 min
                    Short Breaks     2 at 10min = 20min
                    Meetings         30 min
                    Meal Break       1 at 30 min = 30 min
                    Down Time        47 min
                    Ideal Run Rate   60 pieces per minute
                    Total Pieces     19,271 pieces
                    Reject Pieces    423


•Planned Production Time= [Shift Length –Breaks] =[600-80]=520min
•Operating Time= [Planned Production Time-Down Time]=[480-47]=433
•Good Pieces= [Total Pieces – Reject Pieces]=[19,271-423]=18,848
OEE-Example

Availability   =             Operating Time/Planned Production Time
               =   433/520
               =    0.8326923          83.3%

Performance =               (Total Pieces/operating Time)/Ideal Run Rate
            =      (19,271pieces/433minutes)/60 pieces per minute
            =       0.7417629           74.2%

Quality        =                     Good Pieces/ Total Pieces
                   18,848 / 19,271
                    0.9780499          97.8%


OEE            =                Availability x Performance x Quality
                   .8326 x .7417 x .978
               =     0.6041026          60.4%
OEE-Visual

It is very important to have performance data
          Available and In Real Time to
                  EVERYONE
 Benefits:

 •Operators quickly respond to problems
 •Gauge to make adjustments that lead to incremental
 improvements
 •Empowers operators to take immediate action
 •Helps monitor plant floor activity in real time

Weitere ähnliche Inhalte

Was ist angesagt?

Total productive maintenance(TPM)
Total productive maintenance(TPM)Total productive maintenance(TPM)
Total productive maintenance(TPM)Md.Muzahid Khan
 
Autonomous Maintenance (AM)
Autonomous Maintenance (AM)Autonomous Maintenance (AM)
Autonomous Maintenance (AM)Pramod A
 
Production Line OEE (Overall Equipment Effectiveness)
Production Line OEE (Overall Equipment Effectiveness)Production Line OEE (Overall Equipment Effectiveness)
Production Line OEE (Overall Equipment Effectiveness)Brian Thomas
 
Powerful TPM-OEE implementation details
Powerful TPM-OEE  implementation details Powerful TPM-OEE  implementation details
Powerful TPM-OEE implementation details Tan Moses
 
tpm (total productive maintenance)
tpm (total productive maintenance)tpm (total productive maintenance)
tpm (total productive maintenance)Shreya Chaudhary
 
6 OEE overview
6 OEE overview6 OEE overview
6 OEE overviewWebseology
 
Autonomous maintenance Jishu Hozen
Autonomous maintenance Jishu HozenAutonomous maintenance Jishu Hozen
Autonomous maintenance Jishu HozenChetanMehta39
 
Types of waste - lean Concept Krishna Heda
Types of waste - lean Concept Krishna HedaTypes of waste - lean Concept Krishna Heda
Types of waste - lean Concept Krishna Hedakrishnaheda
 
A Manager's Guide to OEE (Overall Equipment Effectiveness)
A Manager's Guide to OEE (Overall Equipment Effectiveness)A Manager's Guide to OEE (Overall Equipment Effectiveness)
A Manager's Guide to OEE (Overall Equipment Effectiveness)OEEsystems International
 

Was ist angesagt? (20)

Total productive maintenance(TPM)
Total productive maintenance(TPM)Total productive maintenance(TPM)
Total productive maintenance(TPM)
 
OEE
OEEOEE
OEE
 
TPM: Quality Maintenance (Hinshitsu Hozen)
TPM: Quality Maintenance (Hinshitsu Hozen)TPM: Quality Maintenance (Hinshitsu Hozen)
TPM: Quality Maintenance (Hinshitsu Hozen)
 
Overall Equipment Effectiveness
Overall Equipment EffectivenessOverall Equipment Effectiveness
Overall Equipment Effectiveness
 
Autonomous Maintenance (AM)
Autonomous Maintenance (AM)Autonomous Maintenance (AM)
Autonomous Maintenance (AM)
 
Production Line OEE (Overall Equipment Effectiveness)
Production Line OEE (Overall Equipment Effectiveness)Production Line OEE (Overall Equipment Effectiveness)
Production Line OEE (Overall Equipment Effectiveness)
 
TPM: Autonomous Maintenance (Jishu Hozen) Framework Poster
TPM: Autonomous Maintenance (Jishu Hozen) Framework PosterTPM: Autonomous Maintenance (Jishu Hozen) Framework Poster
TPM: Autonomous Maintenance (Jishu Hozen) Framework Poster
 
Powerful TPM-OEE implementation details
Powerful TPM-OEE  implementation details Powerful TPM-OEE  implementation details
Powerful TPM-OEE implementation details
 
tpm (total productive maintenance)
tpm (total productive maintenance)tpm (total productive maintenance)
tpm (total productive maintenance)
 
Tpm Sample
Tpm SampleTpm Sample
Tpm Sample
 
Oee Explained
Oee ExplainedOee Explained
Oee Explained
 
6 OEE overview
6 OEE overview6 OEE overview
6 OEE overview
 
Tpm principles and concepts
Tpm principles and conceptsTpm principles and concepts
Tpm principles and concepts
 
Autonomous maintenance Jishu Hozen
Autonomous maintenance Jishu HozenAutonomous maintenance Jishu Hozen
Autonomous maintenance Jishu Hozen
 
[Partial Preview:] Overall Equipment Effectiveness (OEE)
[Partial Preview:] Overall Equipment Effectiveness (OEE)[Partial Preview:] Overall Equipment Effectiveness (OEE)
[Partial Preview:] Overall Equipment Effectiveness (OEE)
 
OEE CALCULATION PPT
OEE CALCULATION PPTOEE CALCULATION PPT
OEE CALCULATION PPT
 
Tpm preview
Tpm previewTpm preview
Tpm preview
 
Types of waste - lean Concept Krishna Heda
Types of waste - lean Concept Krishna HedaTypes of waste - lean Concept Krishna Heda
Types of waste - lean Concept Krishna Heda
 
A Manager's Guide to OEE (Overall Equipment Effectiveness)
A Manager's Guide to OEE (Overall Equipment Effectiveness)A Manager's Guide to OEE (Overall Equipment Effectiveness)
A Manager's Guide to OEE (Overall Equipment Effectiveness)
 
Autonomous maintenance preview
Autonomous maintenance previewAutonomous maintenance preview
Autonomous maintenance preview
 

Ähnlich wie Oee guide

What are the Six Big Losses in OEE? - By DataToBiz
What are the Six Big Losses in OEE? - By DataToBizWhat are the Six Big Losses in OEE? - By DataToBiz
What are the Six Big Losses in OEE? - By DataToBizKavika Roy
 
D3 ver oee 3bus094475 l en_oee_white_paper_low_resolution
D3 ver oee 3bus094475 l en_oee_white_paper_low_resolutionD3 ver oee 3bus094475 l en_oee_white_paper_low_resolution
D3 ver oee 3bus094475 l en_oee_white_paper_low_resolutionMannyjg5
 
World Class Manufacturing Asset Utilization
World Class Manufacturing Asset UtilizationWorld Class Manufacturing Asset Utilization
World Class Manufacturing Asset Utilizationlksnyder
 
Ff Presdentation User Conference Mumbai Automation 2008
Ff Presdentation   User Conference Mumbai Automation 2008Ff Presdentation   User Conference Mumbai Automation 2008
Ff Presdentation User Conference Mumbai Automation 2008Jasbir Singh
 
Scheduled Shutdown Maintenance
Scheduled Shutdown MaintenanceScheduled Shutdown Maintenance
Scheduled Shutdown Maintenancejdparfett
 
Maintenance management
Maintenance managementMaintenance management
Maintenance managementAnupam Kumar
 
The role of mro in enhancing operational capability and mission readiness
The role of mro in enhancing operational capability and mission readinessThe role of mro in enhancing operational capability and mission readiness
The role of mro in enhancing operational capability and mission readinessMichael Parsons
 
EMC: Business Continuity a Disaster Recovery pre virtuálne prostredia
EMC: Business Continuity a Disaster Recovery pre virtuálne prostrediaEMC: Business Continuity a Disaster Recovery pre virtuálne prostredia
EMC: Business Continuity a Disaster Recovery pre virtuálne prostrediaASBIS SK
 
Bayonne packaging case report
Bayonne packaging case reportBayonne packaging case report
Bayonne packaging case reportKivanc Ozuolmez
 

Ähnlich wie Oee guide (20)

Set up reduction
Set up reductionSet up reduction
Set up reduction
 
What are the Six Big Losses in OEE? - By DataToBiz
What are the Six Big Losses in OEE? - By DataToBizWhat are the Six Big Losses in OEE? - By DataToBiz
What are the Six Big Losses in OEE? - By DataToBiz
 
D3 ver oee 3bus094475 l en_oee_white_paper_low_resolution
D3 ver oee 3bus094475 l en_oee_white_paper_low_resolutionD3 ver oee 3bus094475 l en_oee_white_paper_low_resolution
D3 ver oee 3bus094475 l en_oee_white_paper_low_resolution
 
NG BB 17 Takt Time
NG BB 17 Takt TimeNG BB 17 Takt Time
NG BB 17 Takt Time
 
World Class Manufacturing Asset Utilization
World Class Manufacturing Asset UtilizationWorld Class Manufacturing Asset Utilization
World Class Manufacturing Asset Utilization
 
Ff Presdentation User Conference Mumbai Automation 2008
Ff Presdentation   User Conference Mumbai Automation 2008Ff Presdentation   User Conference Mumbai Automation 2008
Ff Presdentation User Conference Mumbai Automation 2008
 
Scheduled Shutdown Maintenance
Scheduled Shutdown MaintenanceScheduled Shutdown Maintenance
Scheduled Shutdown Maintenance
 
Maintenance management
Maintenance managementMaintenance management
Maintenance management
 
Tpm training
Tpm trainingTpm training
Tpm training
 
BLUE BELT -NIBM.pp
BLUE BELT  -NIBM.ppBLUE BELT  -NIBM.pp
BLUE BELT -NIBM.pp
 
Scrum and Lean - Om Band
Scrum and Lean - Om BandScrum and Lean - Om Band
Scrum and Lean - Om Band
 
Guia oee
Guia oeeGuia oee
Guia oee
 
Jit
JitJit
Jit
 
The role of mro in enhancing operational capability and mission readiness
The role of mro in enhancing operational capability and mission readinessThe role of mro in enhancing operational capability and mission readiness
The role of mro in enhancing operational capability and mission readiness
 
Oee part 2
Oee part  2 Oee part  2
Oee part 2
 
TPM
TPMTPM
TPM
 
EMC: Business Continuity a Disaster Recovery pre virtuálne prostredia
EMC: Business Continuity a Disaster Recovery pre virtuálne prostrediaEMC: Business Continuity a Disaster Recovery pre virtuálne prostredia
EMC: Business Continuity a Disaster Recovery pre virtuálne prostredia
 
Bayonne packaging case report
Bayonne packaging case reportBayonne packaging case report
Bayonne packaging case report
 
Office Pull Sample
Office Pull SampleOffice Pull Sample
Office Pull Sample
 
Agile Metrics Driven Management
Agile Metrics Driven ManagementAgile Metrics Driven Management
Agile Metrics Driven Management
 

Kürzlich hochgeladen

8447779800, Low rate Call girls in Rohini Delhi NCR
8447779800, Low rate Call girls in Rohini Delhi NCR8447779800, Low rate Call girls in Rohini Delhi NCR
8447779800, Low rate Call girls in Rohini Delhi NCRashishs7044
 
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deckPitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deckHajeJanKamps
 
8447779800, Low rate Call girls in Saket Delhi NCR
8447779800, Low rate Call girls in Saket Delhi NCR8447779800, Low rate Call girls in Saket Delhi NCR
8447779800, Low rate Call girls in Saket Delhi NCRashishs7044
 
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCRashishs7044
 
FULL ENJOY Call girls in Paharganj Delhi | 8377087607
FULL ENJOY Call girls in Paharganj Delhi | 8377087607FULL ENJOY Call girls in Paharganj Delhi | 8377087607
FULL ENJOY Call girls in Paharganj Delhi | 8377087607dollysharma2066
 
Marketplace and Quality Assurance Presentation - Vincent Chirchir
Marketplace and Quality Assurance Presentation - Vincent ChirchirMarketplace and Quality Assurance Presentation - Vincent Chirchir
Marketplace and Quality Assurance Presentation - Vincent Chirchirictsugar
 
Call Us 📲8800102216📞 Call Girls In DLF City Gurgaon
Call Us 📲8800102216📞 Call Girls In DLF City GurgaonCall Us 📲8800102216📞 Call Girls In DLF City Gurgaon
Call Us 📲8800102216📞 Call Girls In DLF City Gurgaoncallgirls2057
 
Buy gmail accounts.pdf Buy Old Gmail Accounts
Buy gmail accounts.pdf Buy Old Gmail AccountsBuy gmail accounts.pdf Buy Old Gmail Accounts
Buy gmail accounts.pdf Buy Old Gmail AccountsBuy Verified Accounts
 
Cyber Security Training in Office Environment
Cyber Security Training in Office EnvironmentCyber Security Training in Office Environment
Cyber Security Training in Office Environmentelijahj01012
 
Investment in The Coconut Industry by Nancy Cheruiyot
Investment in The Coconut Industry by Nancy CheruiyotInvestment in The Coconut Industry by Nancy Cheruiyot
Investment in The Coconut Industry by Nancy Cheruiyotictsugar
 
International Business Environments and Operations 16th Global Edition test b...
International Business Environments and Operations 16th Global Edition test b...International Business Environments and Operations 16th Global Edition test b...
International Business Environments and Operations 16th Global Edition test b...ssuserf63bd7
 
Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024Kirill Klimov
 
Independent Call Girls Andheri Nightlaila 9967584737
Independent Call Girls Andheri Nightlaila 9967584737Independent Call Girls Andheri Nightlaila 9967584737
Independent Call Girls Andheri Nightlaila 9967584737Riya Pathan
 
PSCC - Capability Statement Presentation
PSCC - Capability Statement PresentationPSCC - Capability Statement Presentation
PSCC - Capability Statement PresentationAnamaria Contreras
 
NewBase 19 April 2024 Energy News issue - 1717 by Khaled Al Awadi.pdf
NewBase  19 April  2024  Energy News issue - 1717 by Khaled Al Awadi.pdfNewBase  19 April  2024  Energy News issue - 1717 by Khaled Al Awadi.pdf
NewBase 19 April 2024 Energy News issue - 1717 by Khaled Al Awadi.pdfKhaled Al Awadi
 
APRIL2024_UKRAINE_xml_0000000000000 .pdf
APRIL2024_UKRAINE_xml_0000000000000 .pdfAPRIL2024_UKRAINE_xml_0000000000000 .pdf
APRIL2024_UKRAINE_xml_0000000000000 .pdfRbc Rbcua
 
TriStar Gold Corporate Presentation - April 2024
TriStar Gold Corporate Presentation - April 2024TriStar Gold Corporate Presentation - April 2024
TriStar Gold Corporate Presentation - April 2024Adnet Communications
 
Memorándum de Entendimiento (MoU) entre Codelco y SQM
Memorándum de Entendimiento (MoU) entre Codelco y SQMMemorándum de Entendimiento (MoU) entre Codelco y SQM
Memorándum de Entendimiento (MoU) entre Codelco y SQMVoces Mineras
 

Kürzlich hochgeladen (20)

8447779800, Low rate Call girls in Rohini Delhi NCR
8447779800, Low rate Call girls in Rohini Delhi NCR8447779800, Low rate Call girls in Rohini Delhi NCR
8447779800, Low rate Call girls in Rohini Delhi NCR
 
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deckPitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
 
8447779800, Low rate Call girls in Saket Delhi NCR
8447779800, Low rate Call girls in Saket Delhi NCR8447779800, Low rate Call girls in Saket Delhi NCR
8447779800, Low rate Call girls in Saket Delhi NCR
 
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
 
Enjoy ➥8448380779▻ Call Girls In Sector 18 Noida Escorts Delhi NCR
Enjoy ➥8448380779▻ Call Girls In Sector 18 Noida Escorts Delhi NCREnjoy ➥8448380779▻ Call Girls In Sector 18 Noida Escorts Delhi NCR
Enjoy ➥8448380779▻ Call Girls In Sector 18 Noida Escorts Delhi NCR
 
FULL ENJOY Call girls in Paharganj Delhi | 8377087607
FULL ENJOY Call girls in Paharganj Delhi | 8377087607FULL ENJOY Call girls in Paharganj Delhi | 8377087607
FULL ENJOY Call girls in Paharganj Delhi | 8377087607
 
Marketplace and Quality Assurance Presentation - Vincent Chirchir
Marketplace and Quality Assurance Presentation - Vincent ChirchirMarketplace and Quality Assurance Presentation - Vincent Chirchir
Marketplace and Quality Assurance Presentation - Vincent Chirchir
 
Call Us 📲8800102216📞 Call Girls In DLF City Gurgaon
Call Us 📲8800102216📞 Call Girls In DLF City GurgaonCall Us 📲8800102216📞 Call Girls In DLF City Gurgaon
Call Us 📲8800102216📞 Call Girls In DLF City Gurgaon
 
Buy gmail accounts.pdf Buy Old Gmail Accounts
Buy gmail accounts.pdf Buy Old Gmail AccountsBuy gmail accounts.pdf Buy Old Gmail Accounts
Buy gmail accounts.pdf Buy Old Gmail Accounts
 
Cyber Security Training in Office Environment
Cyber Security Training in Office EnvironmentCyber Security Training in Office Environment
Cyber Security Training in Office Environment
 
Investment in The Coconut Industry by Nancy Cheruiyot
Investment in The Coconut Industry by Nancy CheruiyotInvestment in The Coconut Industry by Nancy Cheruiyot
Investment in The Coconut Industry by Nancy Cheruiyot
 
Japan IT Week 2024 Brochure by 47Billion (English)
Japan IT Week 2024 Brochure by 47Billion (English)Japan IT Week 2024 Brochure by 47Billion (English)
Japan IT Week 2024 Brochure by 47Billion (English)
 
International Business Environments and Operations 16th Global Edition test b...
International Business Environments and Operations 16th Global Edition test b...International Business Environments and Operations 16th Global Edition test b...
International Business Environments and Operations 16th Global Edition test b...
 
Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024
 
Independent Call Girls Andheri Nightlaila 9967584737
Independent Call Girls Andheri Nightlaila 9967584737Independent Call Girls Andheri Nightlaila 9967584737
Independent Call Girls Andheri Nightlaila 9967584737
 
PSCC - Capability Statement Presentation
PSCC - Capability Statement PresentationPSCC - Capability Statement Presentation
PSCC - Capability Statement Presentation
 
NewBase 19 April 2024 Energy News issue - 1717 by Khaled Al Awadi.pdf
NewBase  19 April  2024  Energy News issue - 1717 by Khaled Al Awadi.pdfNewBase  19 April  2024  Energy News issue - 1717 by Khaled Al Awadi.pdf
NewBase 19 April 2024 Energy News issue - 1717 by Khaled Al Awadi.pdf
 
APRIL2024_UKRAINE_xml_0000000000000 .pdf
APRIL2024_UKRAINE_xml_0000000000000 .pdfAPRIL2024_UKRAINE_xml_0000000000000 .pdf
APRIL2024_UKRAINE_xml_0000000000000 .pdf
 
TriStar Gold Corporate Presentation - April 2024
TriStar Gold Corporate Presentation - April 2024TriStar Gold Corporate Presentation - April 2024
TriStar Gold Corporate Presentation - April 2024
 
Memorándum de Entendimiento (MoU) entre Codelco y SQM
Memorándum de Entendimiento (MoU) entre Codelco y SQMMemorándum de Entendimiento (MoU) entre Codelco y SQM
Memorándum de Entendimiento (MoU) entre Codelco y SQM
 

Oee guide

  • 2. OEE-When to use 1. Does your production have bottlenecks that you are not aware of? 2. Could one machine be dragging down the entire facility? 3. Does your equipment have excess capacity that could be easily and inexpensively tapped?
  • 3. OEE-Benefits HELPS YOU INSTANTLY MAKE MORE WITH WHAT YOU HAVE
  • 4. OEE- What is it OEE is just a Best Practice that helps you monitor and improve the effectiveness of your processes
  • 5. OEE- Guide OEE Six Big World Factors Losses Class OEE Formulas OEE Visual Example OEE
  • 6. OEE-Factors Time Available Plant Operating Time i.e. LMI Mex 10hrs Planned Subtract Plant Operating Time Shutdown Lunch,Breaks, Maintenace Subtract Down Time Operating Time Loss •Equipment failure •Mat. Shortages, •Changeover time Speed Subtract Net Operating Time Loss •Different material, machine wear, operator inefficiency Quality Subtract Fully Productive Time Loss •Rework time •Scrap OEE Goal is to Maximize Fully Productive Time
  • 7. OEE-Factors The following table is a review of the interpretation of the core concepts. OEE LOSS OEE Factor Planned Shutdown *Not part of the calculation Down Time Loss *Availability=Ratio of Operating Time to Planned Production Time (Operating Time=Planned Production Time-Down Time Loss) *100% Availability means the process has been running without any recorded stops Speed Loss *Performance= Ratio of Net Operating time to Operating Time (Net Operating Time=Operating Time-Speed Loss) *Interpreted as Ideal Cycle Time to Actual Cycle Time *100% Performance means the process has been consistently running at its theoretical maximun speed Quality Loss *Quality=Ratio of Fully Productive Time to Net Operating Time (Fully Productive Time=Net Operating Time-Quality Loss) *Interpreted as the ratio of Good Pieces to Total Pieces *100% Qaulity means there have been no reject or rework pieces This factor can then drill down into productivity losses
  • 8. OEE-6 Big Losses Six Big Loss OEE Loss Category Category Event Examples Comment Breakdowns Down Time Loss Tooling failures There is flexibility to Unplanned maintenance decide between a General breakdowns breakdown and small Equipment failure stop Those Set Up and Adjustments Down Time Loss Setup/changeover productivity Material shortages This loss is adressed through set up Losses are Operator shortages reduction projects Major adjustments called the SIX Warm-Up Time BIG LOSSES Small Stops Speed Loss Obstructed product flow Component jams Typically includes stops Misfeeds that are under five Sensored blocked minutes Delivery blocked Cleaning / Checking Reduced Speed Speed Loss Rough running Anything that prevents Under nameplate capacity the process running Under designed capacity normal speed Equipment wear Operator inefficiency 1.Startup 1.Rejects during warm Rejects Quality Loss Scrap up, start up and early 2.Production Rework production Rejects In process damage 2. Rejects during In process expiration steady-state Incorrect assembly production
  • 9. OEE-World Class Accepted World Class OEE Factor World Class Performance per Factor is: Availability 90.0% Performance 95.0% Quality 99.9% OEE 85.0% Studies indicate that most manufacturing plants are around 60% performance in OEE. A world class is considered to be 85% or more.
  • 10. OEE-Formulas Availability= Operating Time / Planned Production Time Performance = Ideal Cycle Time / (Operating Time/Total Pieces) Quality = Good Pieces / Total Pieces OEE = Availability x Performance x Quality
  • 11. OEE-Example Item Data Shift Length 10 hrs = 600 min Short Breaks 2 at 10min = 20min Meetings 30 min Meal Break 1 at 30 min = 30 min Down Time 47 min Ideal Run Rate 60 pieces per minute Total Pieces 19,271 pieces Reject Pieces 423 •Planned Production Time= [Shift Length –Breaks] =[600-80]=520min •Operating Time= [Planned Production Time-Down Time]=[480-47]=433 •Good Pieces= [Total Pieces – Reject Pieces]=[19,271-423]=18,848
  • 12. OEE-Example Availability = Operating Time/Planned Production Time = 433/520 = 0.8326923 83.3% Performance = (Total Pieces/operating Time)/Ideal Run Rate = (19,271pieces/433minutes)/60 pieces per minute = 0.7417629 74.2% Quality = Good Pieces/ Total Pieces 18,848 / 19,271 0.9780499 97.8% OEE = Availability x Performance x Quality .8326 x .7417 x .978 = 0.6041026 60.4%
  • 13. OEE-Visual It is very important to have performance data Available and In Real Time to EVERYONE Benefits: •Operators quickly respond to problems •Gauge to make adjustments that lead to incremental improvements •Empowers operators to take immediate action •Helps monitor plant floor activity in real time