The document summarizes the status of several contracts and projects for a company. It notes that one SEC contract has closed while another is under closure. It also discusses obtaining prequalification to bid on future SEC substation tenders, agreeing with a Sri Lankan company to jointly obtain SEC prequalification for larger projects, and expectations to bid on and potentially secure multiple SEC substation projects worth hundreds of millions of Saudi Riyals per year.
3. Closed one contract of SEC S/S 7811,the other contract is under closer.
Closing the contract of (PP8) with AREVA.
Closing relevant pending issues of RAS AZ ZAWR.
Stood first and awaiting order of contract with the Ministry of interior
(Prisons).
Succeeded in getting a conditional prequalification from SEC to participate
in Substations up to 132kv tenders.
Succeeded in getting a contract of one S/S with SEC in wadi-al-Dawasir,the
tender was priced to be break even as assumed but managed with the help
of everybody and company resources to improve the outcome within 8%.
Agreed with a large company from Srilanka , to join efforts and obtain SEC
prequalification for 380kv S/S ,U/G cables and overhead transmission lines
,agreement and prequalification file is under processing .
4. Obtain final handing over of RAS AZ ZAWR
We will be having two projects in hand. one with the
MOI(prison) the other with SEC .
Work to complete the file of 380kv prequalification with
SEC .
Get full prequalification for SEC tenders and participate in
tenders, where we expect to bid more than 5 tenders of
132kv S/S.
5. Replacement of 13.8kv
S/G at S/S 7188 { Contract
No.10641149/00}.
Construction of S/S 7099
33kv S/S
The contract between
SEC & CAPITAL LIGHTS
CO. FOR ELECTRO-
MECHANICS .
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
18.
19.
20.
21.
22. MOI PROJECT Khamasin project
Elevator project maybe Value order 69,757,948 SR
. Date of contract :
07.05.2011 till 05.10.2013
23.
24.
25. We are expected to bid mainly sec tenders. value of
expected project depending on :
Mainly human resources .
Unavailability of visa restricts our capacity to handle
projects .
Positive steps have been taken to enhance our capacity like
approving NOUR Construction (communication) as a Civil
Sub Contractors by SEC for our projects .
Arrangement with local Sub Contractors to assist Electrical
work installations , testing and commissioning while we
build our teams .
Expected projects values could reach to multi hundreds of
millions in Saudi Riyals .if we managed to have the
required human resources.
In view of our present capacity, we expect to secure projects
of SR 200 millions value/year.