SlideShare a Scribd company logo
1 of 40
Extension of Time –Various Delay
Analysis Approaches
By
Dharmendar Pardasani
LLM, MSc(QS), FRICS, FAIQS, FCIArb, MCIOB
&
Narinder Kumar Sharma
MTech, MCIArb
20 December 2014
Few Common Terms used in Delay Analysis-Definition
 Critical Path
Longest Path in the Program –Commonly known as the path along
which float is least (generally zero in a baseline program).
 Float
This is the period by which an activity can be delayed without
delaying the subsequent activity (Free Float) or without delaying the
project completion (Total Float)
 Excusable Delay Event
This is the delay event, the risk of which lies with the Employer and
occurrence of which would entitle the Contractor for an Extension of
Time, if it cause the delay to the project completion.
 Excusable and Compensable Delay Event
This is similar to Excusable Delay Event, with the difference that
this delay event will entitle the Contractor for the cost in
addition to the time.
Various Delay Analysis Approaches
•As-Planned v As-Built
•Impacted As-Planned
•Collapsed As-Built
•Time Impact Analysis
As-Planned v As-Built
This method compares the duration of all the activities on the
As-Planned program with the corresponding activities on the
As-Built Program which are affected by the excusable delay
events especially the critical activities.
Advantages:
•Simple to use
•Inexpensive
•Disadvantages:
•Suitable for only simple programs
Impacted As-Planned
•This method adds an excusable delay event into the As-
Planned Program.
•This adding of delay can be as a separate activity or by
revising the duration of an existing activity.
•The revised completion date achieved as a result of this impact
indicates the entitlement for an Extension of Time.
•Duration considered for the new activities is generally based on
the production rate considered in the original program, unless it
is very irrational.
As Planned Impacted Approach
Pavement Layers
Road Furniture
Foundation
Finishing
Earth Works
Superstructure
Contractor’s Delay
=15 days
Employer’s Delay
=35 days
Extension of Time = 35 Days
Concurrent Delay = 15 Days
Hence Cost = 20 Days
Contractor’s Delay
=7 days Contractor’s Delay
=8 days
Employer’s Delay
=15 days
Employer’s Delay
=20 days
Contractor’s
Delay
Employer’s
Delay
“The sooner you get behind the Schedule, the
more time you have to make it up!”
An Example of How to
Insert Delay in a Program
Base Line Program
Inserting of Delay
Two New
Activities Added
Impacted As-Planned
Advantages:
 As-Built Information is not required
 There is no hassle of having arguments over correctness of
Program Updates.
 The Extension of Time is determined as per the original
intent of the parties, i.e. any float in the activities comes into
effect as per the As-Planned Program.
Disadvantages:
• This method is very theoretical since it does not take into
account that the actual program vary a lot a as compared to
As-Planned Program.
• Any errors in the program creep into the delay analysis
• Any Extension of Time assessed may not be rational if the
actual sequence/progress is substantially different to As-
Planned Program.
Does not Take into Consideration Pre-existing Delays of Other
Party
Earth Works
Pavement Layers
Road FurnitureFoundation
Superstructure
Finishing
Pavement Layers
Road Furniture
Foundation
Supers
Finishing
Earth Works
Superstructure
Contractor’s Delay
Pre-existing
Employer’s Delay will
show impact on
Program incorrectly
Delay Impact Does Not Take into Consideration the Actual
Sequence /Progress of Works
Earth Works
Pavement Layers
Road Furniture
Foundation
Superstructure
Finishing
Pavement Layers
Road Furniture
Foundation
Finishing
Earth Works
Superstructure
Case 1 –Will show delay,
while no actual delay
Case 2 –Will not show
delay, while there is
actual delay
Work Completed
Earlier by
Contractor
If Float initially consumed by the Contractor
before the Employer's Delay, still will not show
the delay if the duration of a subsequent activity
increased due to Employer’s Delay
Employer's Delay
Collapsed As-Built
In this method, all the Employer’s delays are removed from the
As-Built Program. The period by which it shrinks the As-Built
Program, reflects the total delay of the Employer or the
Extension of Time.
Advantages:
•It takes into account the actual built program, hence certainty
that delay analysis is based on the actual sequence of work
adopted in the project.
Disadvantages:
•The critical path resulting from removal of Employer’s delays
retrospectively may not result in the same critical path as existed
during the course of project.
•Creating an equivalent Baseline Program also involves lot of
subjectivity
•The logic of the program has to be rebuilt once the Employer’s
delays are removed, which is complex
As built Collapsed Approach
Pavement Layers
Road Furniture
Foundation
Finishing
Earth Works
Superstructure
Pavement Layers
Road Furniture
Foundation
Finishing
Earth Works
Superstructure
Extension of
Time
Entitlement
Contractor’s
Delay
Employer’s
Delay
As-Built Program
Collapsed Program
Time Impact Analysis
Time Impact Analysis can be done by either of following
methods,
• Snap Shot Analysis
• Window Analysis (Or Time Slice Analysis)
Snapshot Analysis
Snapshot Analysis is normally used in contemporaneous delay
analysis. i.e. taking the progress update on the instance of
occurrence of delay and incorporating the effect of excusable
delay in the progress update. This method is recommended in
‘Delay and Disruption Protocol’ by UK SCL
Snapshot Analysis –Example 1 ( UK SCL -Delay & Disruption Protocol
EOT 4 Days
Cost 0 Days
Snapshot Analysis –Example 2 ( UK SCL -Delay & Disruption Protocol
EOT 9 Days
Cost 9 Days
Snapshot Analysis –Example 3 ( UK SCL -Delay & Disruption Protocol
EOT 4 Days
Cost 4 Days
“The nice thing about not planning is that
failure will come as a surprise rather than being
preceded by a period of worry and depression!
Time Impact Analysis
Window Analysis
In Window Analysis, the entire period of project is divided into
multiple time windows (Say one month or so depending upon the
period of updating the program).
Each Progress update is updated with the actual progress /any
change of sequence of work etc. This shall also include the effect of
delay due to any excusable events. Each window is then compared
with previous window to analyze the effect of valid delay events.
Window Analysis
Advantages:
•This method is most favored and is most robust for
retrospective delay analysis and has been adopted
internationally in many litigation and arbitration cases.
•In each window, there are few activities (with negative float)
that need to be analyzed to evolve the delay and therefore
process of delay analysis is more clearer than a global
approach. .
•It gives more realistic results, since it takes into account the
project status at the time of occurrence of delay events. Also, it
takes into account the changes by the Contractor in terms of
logic links etc.
•Calculation of Concurrent Delays is more practical to do.
.
Window Analysis
Disadvantages:
•Accurate Progress information to relate to each progress
update needs to be maintained.
•This method is more time consuming than other methods and
requires more planning skills.
Window Analysis
Progress Update 1 (End of Month 1)
Pavement
Layers
Road Furniture
Foundation
Finishing
Earth
Works
Superstructure
Pavement
Layers
Road Furniture
Foundation
Finishing
Earth Works
Superstructure
Progress Update 2 (End of Month 2)
Contractor’s
Delay = 10
Days
EOT = 0 Days
Cost = 0 Days
-10 Days
Contractor’s
Delay
Employer’s
Delay
Progress Update 2 (End of Month 2)
Pavement
Layers
Road Furniture
Foundation
Finishing
Earth Works
Superstructure
Progress Update 3 (End of Month 3)
-20 Days Contractor’s
Delay = 20
DaysPavement
Layers
Road Furniture
Foundation
Finishing
Earth Works
Superstructur
e
Employer’s
Delay = 10
Days
EOT 0 Days
Cost 0 Days
- 10 Days
Contractor’s
Delay = 10
Days
Contractor’s
Delay
Employer’s
Delay
-10 Days
Progress Update 4 (End of Month 4)
Progress Update 3 (End of Month 3)
-20 Days Contractor’s
Delay = 20
Days
Pavement
Layers
Road Furniture
Foundation
Finishing
Earth Works
Superstructur
e
- 10 Days
-20 Days
Pavement
Layers
Road Furniture
Foundation
Finishing
Earth Works
Superstructur
e
- 25 Days
Employer’s
Delay = 10
Days
-5 Days
Contractor’s
Delay = 25
Days
Employer’s
Delay = 25
Days
EOT 5 Days
Cost (View 1) 0 Days
Cost (View 2
- Sharing)
2.5 Days
Progress Update 5 (End of Month 5)
-20 Days
Pavement
Layers
Road Furniture
Foundation
Finishing
Earth Works
Superstructur
e
- 25 Days
-5 Days
Contractor’s
Delay = 25
Days
Employer’s
Delay = 25
Days
EOT 10 Days
Cost (View 1) 10 Days
Cost (View 2
- Sharing)
10 Days
-20 Days
Pavement
Layers
Road Furniture
Finishing
Earth Works
Superstructur
e
- 25 Days
-5 Days
Employer’s
Delay = 35
Days
Foundation
Contractor’s
Delay = 25
Days
- 10 Days
Progress Update 4 (End of Month 4)
Summary of EOT & Cost
Window Period EOT Cost (View
1)
Cost (View
2) Sharing
Window 1 End of Month 1 to
End of Month 2
0 Days 0 Days 0 Days
Window 2 End of Month 2 to
End of Month 3
0 Days 0 Days 0 Days
Window 3 End of Month 3 to
End of Month 4
5 Days 0 Days 2.5 Days
Window 4 End of Month 4 to
End of Month 5
10 Days 10 Days 10 Days
Total 15 Days 10 Days 12.5 Days
Concurrent Delays
•What is concurrent Delay
Where two or more events of approximate equal efficacy (one
Employer’s Risk event an other Contractor’s Risk Event),
causes the delay in almost the same period
•General Practice in the Industry
•In case of Concurrent Delays, i.e. delay by the Employer as
well as the delay by the Contractor, only entitlement would be
Extension of Time but no prolongation cost.
•Approach Advocated by Society of Construction Law
‘Delay and Disruption Protocol’
•Unless it is possible to separate out the cost caused by the
Contractor’s delay and the cost caused by the Employer’s
delays, the Contractor will not have an entitlement of cost in
case of concurrent delay.
Concurrent Delays
 What does the Contract Stipulates
 Most of the contracts do not have any express provision to
address the concurrent delays. As such, the parties intentions
are to be interpreted from the associated terms of contracts.
 What are other ways to deal with Concurrent Delays
 In various cases, the courts have addressed the issue of
concurrent delays in different ways, such
 Only time, but no cost based on the principle of ‘loss lies
where it falls’
 Apportioning the cost to relate to the delay caused by each
party.
 Apportioning the time as well as the cost.
Concurrent Delays
 What is the legal views that the courts in some countries may take on
this issue:
 Apportionment of damages based on the responsibility of respective
party is widely accepted in most of the jurisdictions. Accordingly, this
approach may be adopted by the courts.
 However, again, apportionment may be viewed differently by courts,
such as
 Employer to bear its own loss of not being able to levy the delay
damages and contractor to bear its own loss of prolongation cost.
 Entitlement for Extension of Time to be reduced due to delays by
both the parties. However, in that case, the cost is likely to be
awarded for the reduced Extension of Time period.
 Entire period of Employer’s delay be awarded as Extension of Time
and Cost be apportioned between the parties.
 Due to contrasting judgments by various courts across the world, it
may be difficult to arrive to a conclusion
Concurrent Delays
Recent Legal Cases in Scotland and England
City Inn and Shephard Construction
In this Scottish case, the Scottish Appeal court mainly emphasized on
two issues:
In case, the Employer’s delay and the Contractor's delays are fairly
concurrent, the Contractor is entitled for an Extension of Time.
What is ‘fair and reasonable’ is a matter of ‘common sense’ and a
critical path analysis was not always necessary.
De Beers Case
In this English case, the judge concluded that delay damages were
not recoverable as long as the contractor would have suffered same
damages due to his own delays
Heads of Prolongation Cost Claims
 Site Overheads
 Salaries or Wages of Indirect Staff such as project Manager /
Engineers/Foremen/Store man/QSs/Safety Staff/Watchmen etc.
 Engineer’s and Contractor’s Site Offices cost
 Extended Safety Requirement
 Handling /Protection works
 Material Storage Yards
 Scaffolding Extended Duration
 Bond/Insurances Extension
 Other costs
 Head Office Cost (Mostly contentious)
 Sub-Contractor’s claims
 Delayed Release of Retention
 Financing Cost for Delayed payments (Always contentious)
 Loss of Profit due to lost opportunities (Always contentious)
 Disruption (Reduced Productivity /Idle Resources etc.)
 Off-site overheads
Good Planning –To Ensure Effective Use of
Baseline Program for Delay Analysis
 Activities Duration 7-28 Days
 Activity Duration to be derived from Standard Production Rates
or the Company Standard Production Rates with reasonable
allowance for specific risks
 Ensure Milestones are included
 Ensure complete scope of work is included
 Ensure activities are linked logically (correct predecessor and
successors)
 Ensure reasonable period allowed for approvals
 Allowance for Specified Provisional Sums
 Verify critical path runs through logical chain of activities
 Avoidance of open ends
 Check for excessive floats
 Lags to be checked
Good Planning –To Ensure Effective Use of
Baseline Program for Delay Analysis
 Check Holidays/Weekly-Offs are assigned
 Resources are loaded into the program and resources are
leveled /balanced.
 Cost is loaded into the various activities
 Check for resources with respect to projected cash flow
 Avoidance of (Constraints) Must start /Must Finish dates etc. as
far as possible.
 Check what is the %age of critical activities to the total number
of activities, to ensure that it is realistically planned.
Final Word
 Follow the contract provisions related to techniques to be used
for Extension of Time Analysis, since that is what has been
agreed between the parties.
 In case the provisions in the contract are not well defined, look
for what could be acceptable the local laws by consulting the
legal experts.
 Key word in Delay Analysis is to be Fair in our approach
 Regardless of which approach we use (As Planned-Impacted or
Window Analysis), it is always good to maintain the bi-weekly or
monthly progress updates. Ensure protect the digital files.
 As QSs/Cost Professionals, ensure we all learn Primavera, so
that at least can read the Program and understand the basis
principles how the claim can be made or defended
If Contract Terms Are Not Clear… Don’t
Expect Other Party to Rescue You During
Dispute…………
What is Fair differs from case to case
Apportionment is not fair in the given case……..
QUESTIONS?
(if still awake !)

More Related Content

What's hot

Construction Delay Analysis, Simplified
Construction Delay Analysis, SimplifiedConstruction Delay Analysis, Simplified
Construction Delay Analysis, SimplifiedMichael Pink
 
Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract
Session W2 - Delay Claims and Analysis Based on FIDIC Forms of ContractSession W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract
Session W2 - Delay Claims and Analysis Based on FIDIC Forms of ContractProject Controls Expo
 
VERTEX Construction Delays and Forensic Schedule Analyses
VERTEX Construction Delays and Forensic Schedule AnalysesVERTEX Construction Delays and Forensic Schedule Analyses
VERTEX Construction Delays and Forensic Schedule AnalysesThe Vertex Companies, LLC
 
Construction delays
Construction delaysConstruction delays
Construction delaysSaida Njim
 
Claims Management, Extension of Time (EOT) and Delays Analysis
Claims Management, Extension of Time (EOT) and Delays AnalysisClaims Management, Extension of Time (EOT) and Delays Analysis
Claims Management, Extension of Time (EOT) and Delays AnalysisPlanning Engineer Est.
 
A case study of Delay Analysis of construction project: Al Kut Olympic Stadiu...
A case study of Delay Analysis of construction project: Al Kut Olympic Stadiu...A case study of Delay Analysis of construction project: Al Kut Olympic Stadiu...
A case study of Delay Analysis of construction project: Al Kut Olympic Stadiu...Gaurav Verma
 
EOT Related Cost Compensation Determination
EOT Related Cost Compensation DeterminationEOT Related Cost Compensation Determination
EOT Related Cost Compensation DeterminationVimal Daluwatta
 
Baseline schedule review and analysis
Baseline schedule review and analysisBaseline schedule review and analysis
Baseline schedule review and analysisADITYA GHUMARE
 
Claims 20.1 (Flow chart)
Claims 20.1 (Flow chart)Claims 20.1 (Flow chart)
Claims 20.1 (Flow chart)Fakhar-un -Nisa
 
Extension of Time (EoT) in Construction Project presentation
Extension of Time (EoT) in Construction Project presentationExtension of Time (EoT) in Construction Project presentation
Extension of Time (EoT) in Construction Project presentationAyush Joshi
 
Fundamentals of scheduling
Fundamentals of schedulingFundamentals of scheduling
Fundamentals of schedulingjmd2011
 
Methods of delay analysis
Methods of delay analysisMethods of delay analysis
Methods of delay analysiskatrin enders
 
Project Controls Expo 18th Nov 2014 - "PACING DELAY The Practical Effect on C...
Project Controls Expo 18th Nov 2014 - "PACING DELAY The Practical Effect on C...Project Controls Expo 18th Nov 2014 - "PACING DELAY The Practical Effect on C...
Project Controls Expo 18th Nov 2014 - "PACING DELAY The Practical Effect on C...Project Controls Expo
 
Project Controls Expo 09 Nov 2011, London - DELAY AND FORENSIC ANALYSIS By Ro...
Project Controls Expo 09 Nov 2011, London - DELAY AND FORENSIC ANALYSIS By Ro...Project Controls Expo 09 Nov 2011, London - DELAY AND FORENSIC ANALYSIS By Ro...
Project Controls Expo 09 Nov 2011, London - DELAY AND FORENSIC ANALYSIS By Ro...Project Controls Expo
 
FIDIC-Relevant to Time Management
FIDIC-Relevant to Time ManagementFIDIC-Relevant to Time Management
FIDIC-Relevant to Time ManagementASHISH KUMAR SINGH
 
causes and implication of delay in construction
causes and implication of delay in constructioncauses and implication of delay in construction
causes and implication of delay in constructionsudinak
 

What's hot (20)

Construction Delay Analysis, Simplified
Construction Delay Analysis, SimplifiedConstruction Delay Analysis, Simplified
Construction Delay Analysis, Simplified
 
Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract
Session W2 - Delay Claims and Analysis Based on FIDIC Forms of ContractSession W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract
Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract
 
Claims
ClaimsClaims
Claims
 
VERTEX Construction Delays and Forensic Schedule Analyses
VERTEX Construction Delays and Forensic Schedule AnalysesVERTEX Construction Delays and Forensic Schedule Analyses
VERTEX Construction Delays and Forensic Schedule Analyses
 
Construction delays
Construction delaysConstruction delays
Construction delays
 
Claims Management, Extension of Time (EOT) and Delays Analysis
Claims Management, Extension of Time (EOT) and Delays AnalysisClaims Management, Extension of Time (EOT) and Delays Analysis
Claims Management, Extension of Time (EOT) and Delays Analysis
 
A case study of Delay Analysis of construction project: Al Kut Olympic Stadiu...
A case study of Delay Analysis of construction project: Al Kut Olympic Stadiu...A case study of Delay Analysis of construction project: Al Kut Olympic Stadiu...
A case study of Delay Analysis of construction project: Al Kut Olympic Stadiu...
 
EOT Related Cost Compensation Determination
EOT Related Cost Compensation DeterminationEOT Related Cost Compensation Determination
EOT Related Cost Compensation Determination
 
Baseline schedule review and analysis
Baseline schedule review and analysisBaseline schedule review and analysis
Baseline schedule review and analysis
 
Claims 20.1 (Flow chart)
Claims 20.1 (Flow chart)Claims 20.1 (Flow chart)
Claims 20.1 (Flow chart)
 
50 Planning Fundamentals V5.0 - procedures only
50 Planning Fundamentals V5.0 - procedures only50 Planning Fundamentals V5.0 - procedures only
50 Planning Fundamentals V5.0 - procedures only
 
Extension of Time (EoT) in Construction Project presentation
Extension of Time (EoT) in Construction Project presentationExtension of Time (EoT) in Construction Project presentation
Extension of Time (EoT) in Construction Project presentation
 
Fundamentals of scheduling
Fundamentals of schedulingFundamentals of scheduling
Fundamentals of scheduling
 
Prolongation and HOOH Costs
Prolongation and HOOH CostsProlongation and HOOH Costs
Prolongation and HOOH Costs
 
Forensic schedule analysis acesss
Forensic schedule analysis acesssForensic schedule analysis acesss
Forensic schedule analysis acesss
 
Methods of delay analysis
Methods of delay analysisMethods of delay analysis
Methods of delay analysis
 
Project Controls Expo 18th Nov 2014 - "PACING DELAY The Practical Effect on C...
Project Controls Expo 18th Nov 2014 - "PACING DELAY The Practical Effect on C...Project Controls Expo 18th Nov 2014 - "PACING DELAY The Practical Effect on C...
Project Controls Expo 18th Nov 2014 - "PACING DELAY The Practical Effect on C...
 
Project Controls Expo 09 Nov 2011, London - DELAY AND FORENSIC ANALYSIS By Ro...
Project Controls Expo 09 Nov 2011, London - DELAY AND FORENSIC ANALYSIS By Ro...Project Controls Expo 09 Nov 2011, London - DELAY AND FORENSIC ANALYSIS By Ro...
Project Controls Expo 09 Nov 2011, London - DELAY AND FORENSIC ANALYSIS By Ro...
 
FIDIC-Relevant to Time Management
FIDIC-Relevant to Time ManagementFIDIC-Relevant to Time Management
FIDIC-Relevant to Time Management
 
causes and implication of delay in construction
causes and implication of delay in constructioncauses and implication of delay in construction
causes and implication of delay in construction
 

Similar to Extension of time Analysis

Traditional Management System.ppt
Traditional Management System.pptTraditional Management System.ppt
Traditional Management System.pptUtkarshDwivedi74
 
7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..ppt7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..pptPedadaSaikumar
 
Critical path presentation for timely project completion
Critical path presentation for timely project completionCritical path presentation for timely project completion
Critical path presentation for timely project completionAniruddha Kulkarni
 
(Presentation) Cis utilization of earned value management for monitoring prod...
(Presentation) Cis utilization of earned value management for monitoring prod...(Presentation) Cis utilization of earned value management for monitoring prod...
(Presentation) Cis utilization of earned value management for monitoring prod...Скоробогатов Дмитрий
 
CPM, Network Analysis A-O-A, A-O-N, Resource management
CPM, Network Analysis A-O-A, A-O-N, Resource managementCPM, Network Analysis A-O-A, A-O-N, Resource management
CPM, Network Analysis A-O-A, A-O-N, Resource managementAmit Kumbar
 
Quantitative analysis for business decision- Program Evaluation and Review Te...
Quantitative analysis for business decision- Program Evaluation and Review Te...Quantitative analysis for business decision- Program Evaluation and Review Te...
Quantitative analysis for business decision- Program Evaluation and Review Te...Chandra Shekar Immani
 
Primavera presentation
Primavera presentationPrimavera presentation
Primavera presentationNithin Dev
 
Software project plannings
Software project planningsSoftware project plannings
Software project planningsAman Adhikari
 
Software project plannings
Software project planningsSoftware project plannings
Software project planningsAman Adhikari
 
Chapt5.pptx it is notes of the 5th chapter
Chapt5.pptx it is notes of the 5th chapterChapt5.pptx it is notes of the 5th chapter
Chapt5.pptx it is notes of the 5th chapterpreetidamakale
 
Critical path method & pert
Critical path method & pertCritical path method & pert
Critical path method & pertBhim Upadhyaya
 
Minor project by priyanshu kumar, 9608684800
Minor project by priyanshu kumar, 9608684800Minor project by priyanshu kumar, 9608684800
Minor project by priyanshu kumar, 9608684800PRIYANSHU KUMAR
 
Monitoring and information systems
Monitoring and information systemsMonitoring and information systems
Monitoring and information systemsLibra chudry
 

Similar to Extension of time Analysis (20)

Traditional Management System.ppt
Traditional Management System.pptTraditional Management System.ppt
Traditional Management System.ppt
 
7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..ppt7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..ppt
 
Critical path presentation for timely project completion
Critical path presentation for timely project completionCritical path presentation for timely project completion
Critical path presentation for timely project completion
 
1587310189-week6.pptx
1587310189-week6.pptx1587310189-week6.pptx
1587310189-week6.pptx
 
(Presentation) Cis utilization of earned value management for monitoring prod...
(Presentation) Cis utilization of earned value management for monitoring prod...(Presentation) Cis utilization of earned value management for monitoring prod...
(Presentation) Cis utilization of earned value management for monitoring prod...
 
CPM, Network Analysis A-O-A, A-O-N, Resource management
CPM, Network Analysis A-O-A, A-O-N, Resource managementCPM, Network Analysis A-O-A, A-O-N, Resource management
CPM, Network Analysis A-O-A, A-O-N, Resource management
 
vk1
vk1vk1
vk1
 
Quantitative analysis for business decision- Program Evaluation and Review Te...
Quantitative analysis for business decision- Program Evaluation and Review Te...Quantitative analysis for business decision- Program Evaluation and Review Te...
Quantitative analysis for business decision- Program Evaluation and Review Te...
 
pm--basic.pptx
pm--basic.pptxpm--basic.pptx
pm--basic.pptx
 
Lean construction
Lean constructionLean construction
Lean construction
 
Primavera presentation
Primavera presentationPrimavera presentation
Primavera presentation
 
Project lifecycle
Project lifecycleProject lifecycle
Project lifecycle
 
Microsoft Project.pptx
Microsoft Project.pptxMicrosoft Project.pptx
Microsoft Project.pptx
 
Software project plannings
Software project planningsSoftware project plannings
Software project plannings
 
Software project plannings
Software project planningsSoftware project plannings
Software project plannings
 
Project management techniques
Project management techniquesProject management techniques
Project management techniques
 
Chapt5.pptx it is notes of the 5th chapter
Chapt5.pptx it is notes of the 5th chapterChapt5.pptx it is notes of the 5th chapter
Chapt5.pptx it is notes of the 5th chapter
 
Critical path method & pert
Critical path method & pertCritical path method & pert
Critical path method & pert
 
Minor project by priyanshu kumar, 9608684800
Minor project by priyanshu kumar, 9608684800Minor project by priyanshu kumar, 9608684800
Minor project by priyanshu kumar, 9608684800
 
Monitoring and information systems
Monitoring and information systemsMonitoring and information systems
Monitoring and information systems
 

Recently uploaded

CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordAsst.prof M.Gokilavani
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduitsrknatarajan
 
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur EscortsRussian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...ranjana rawat
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfKamal Acharya
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...roncy bisnoi
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college projectTonystark477637
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 

Recently uploaded (20)

CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduits
 
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur EscortsRussian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
 
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college project
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 

Extension of time Analysis

  • 1. Extension of Time –Various Delay Analysis Approaches By Dharmendar Pardasani LLM, MSc(QS), FRICS, FAIQS, FCIArb, MCIOB & Narinder Kumar Sharma MTech, MCIArb 20 December 2014
  • 2. Few Common Terms used in Delay Analysis-Definition  Critical Path Longest Path in the Program –Commonly known as the path along which float is least (generally zero in a baseline program).  Float This is the period by which an activity can be delayed without delaying the subsequent activity (Free Float) or without delaying the project completion (Total Float)  Excusable Delay Event This is the delay event, the risk of which lies with the Employer and occurrence of which would entitle the Contractor for an Extension of Time, if it cause the delay to the project completion.  Excusable and Compensable Delay Event This is similar to Excusable Delay Event, with the difference that this delay event will entitle the Contractor for the cost in addition to the time.
  • 3. Various Delay Analysis Approaches •As-Planned v As-Built •Impacted As-Planned •Collapsed As-Built •Time Impact Analysis
  • 4. As-Planned v As-Built This method compares the duration of all the activities on the As-Planned program with the corresponding activities on the As-Built Program which are affected by the excusable delay events especially the critical activities. Advantages: •Simple to use •Inexpensive •Disadvantages: •Suitable for only simple programs
  • 5. Impacted As-Planned •This method adds an excusable delay event into the As- Planned Program. •This adding of delay can be as a separate activity or by revising the duration of an existing activity. •The revised completion date achieved as a result of this impact indicates the entitlement for an Extension of Time. •Duration considered for the new activities is generally based on the production rate considered in the original program, unless it is very irrational.
  • 6. As Planned Impacted Approach Pavement Layers Road Furniture Foundation Finishing Earth Works Superstructure Contractor’s Delay =15 days Employer’s Delay =35 days Extension of Time = 35 Days Concurrent Delay = 15 Days Hence Cost = 20 Days Contractor’s Delay =7 days Contractor’s Delay =8 days Employer’s Delay =15 days Employer’s Delay =20 days Contractor’s Delay Employer’s Delay
  • 7. “The sooner you get behind the Schedule, the more time you have to make it up!”
  • 8. An Example of How to Insert Delay in a Program
  • 10. Inserting of Delay Two New Activities Added
  • 11. Impacted As-Planned Advantages:  As-Built Information is not required  There is no hassle of having arguments over correctness of Program Updates.  The Extension of Time is determined as per the original intent of the parties, i.e. any float in the activities comes into effect as per the As-Planned Program. Disadvantages: • This method is very theoretical since it does not take into account that the actual program vary a lot a as compared to As-Planned Program. • Any errors in the program creep into the delay analysis • Any Extension of Time assessed may not be rational if the actual sequence/progress is substantially different to As- Planned Program.
  • 12. Does not Take into Consideration Pre-existing Delays of Other Party Earth Works Pavement Layers Road FurnitureFoundation Superstructure Finishing Pavement Layers Road Furniture Foundation Supers Finishing Earth Works Superstructure Contractor’s Delay Pre-existing Employer’s Delay will show impact on Program incorrectly
  • 13. Delay Impact Does Not Take into Consideration the Actual Sequence /Progress of Works Earth Works Pavement Layers Road Furniture Foundation Superstructure Finishing Pavement Layers Road Furniture Foundation Finishing Earth Works Superstructure Case 1 –Will show delay, while no actual delay Case 2 –Will not show delay, while there is actual delay Work Completed Earlier by Contractor If Float initially consumed by the Contractor before the Employer's Delay, still will not show the delay if the duration of a subsequent activity increased due to Employer’s Delay Employer's Delay
  • 14. Collapsed As-Built In this method, all the Employer’s delays are removed from the As-Built Program. The period by which it shrinks the As-Built Program, reflects the total delay of the Employer or the Extension of Time. Advantages: •It takes into account the actual built program, hence certainty that delay analysis is based on the actual sequence of work adopted in the project. Disadvantages: •The critical path resulting from removal of Employer’s delays retrospectively may not result in the same critical path as existed during the course of project. •Creating an equivalent Baseline Program also involves lot of subjectivity •The logic of the program has to be rebuilt once the Employer’s delays are removed, which is complex
  • 15. As built Collapsed Approach Pavement Layers Road Furniture Foundation Finishing Earth Works Superstructure Pavement Layers Road Furniture Foundation Finishing Earth Works Superstructure Extension of Time Entitlement Contractor’s Delay Employer’s Delay As-Built Program Collapsed Program
  • 16. Time Impact Analysis Time Impact Analysis can be done by either of following methods, • Snap Shot Analysis • Window Analysis (Or Time Slice Analysis) Snapshot Analysis Snapshot Analysis is normally used in contemporaneous delay analysis. i.e. taking the progress update on the instance of occurrence of delay and incorporating the effect of excusable delay in the progress update. This method is recommended in ‘Delay and Disruption Protocol’ by UK SCL
  • 17. Snapshot Analysis –Example 1 ( UK SCL -Delay & Disruption Protocol EOT 4 Days Cost 0 Days
  • 18. Snapshot Analysis –Example 2 ( UK SCL -Delay & Disruption Protocol EOT 9 Days Cost 9 Days
  • 19. Snapshot Analysis –Example 3 ( UK SCL -Delay & Disruption Protocol EOT 4 Days Cost 4 Days
  • 20. “The nice thing about not planning is that failure will come as a surprise rather than being preceded by a period of worry and depression!
  • 21. Time Impact Analysis Window Analysis In Window Analysis, the entire period of project is divided into multiple time windows (Say one month or so depending upon the period of updating the program). Each Progress update is updated with the actual progress /any change of sequence of work etc. This shall also include the effect of delay due to any excusable events. Each window is then compared with previous window to analyze the effect of valid delay events.
  • 22. Window Analysis Advantages: •This method is most favored and is most robust for retrospective delay analysis and has been adopted internationally in many litigation and arbitration cases. •In each window, there are few activities (with negative float) that need to be analyzed to evolve the delay and therefore process of delay analysis is more clearer than a global approach. . •It gives more realistic results, since it takes into account the project status at the time of occurrence of delay events. Also, it takes into account the changes by the Contractor in terms of logic links etc. •Calculation of Concurrent Delays is more practical to do. .
  • 23. Window Analysis Disadvantages: •Accurate Progress information to relate to each progress update needs to be maintained. •This method is more time consuming than other methods and requires more planning skills.
  • 25. Progress Update 1 (End of Month 1) Pavement Layers Road Furniture Foundation Finishing Earth Works Superstructure Pavement Layers Road Furniture Foundation Finishing Earth Works Superstructure Progress Update 2 (End of Month 2) Contractor’s Delay = 10 Days EOT = 0 Days Cost = 0 Days -10 Days Contractor’s Delay Employer’s Delay
  • 26. Progress Update 2 (End of Month 2) Pavement Layers Road Furniture Foundation Finishing Earth Works Superstructure Progress Update 3 (End of Month 3) -20 Days Contractor’s Delay = 20 DaysPavement Layers Road Furniture Foundation Finishing Earth Works Superstructur e Employer’s Delay = 10 Days EOT 0 Days Cost 0 Days - 10 Days Contractor’s Delay = 10 Days Contractor’s Delay Employer’s Delay -10 Days
  • 27. Progress Update 4 (End of Month 4) Progress Update 3 (End of Month 3) -20 Days Contractor’s Delay = 20 Days Pavement Layers Road Furniture Foundation Finishing Earth Works Superstructur e - 10 Days -20 Days Pavement Layers Road Furniture Foundation Finishing Earth Works Superstructur e - 25 Days Employer’s Delay = 10 Days -5 Days Contractor’s Delay = 25 Days Employer’s Delay = 25 Days EOT 5 Days Cost (View 1) 0 Days Cost (View 2 - Sharing) 2.5 Days
  • 28. Progress Update 5 (End of Month 5) -20 Days Pavement Layers Road Furniture Foundation Finishing Earth Works Superstructur e - 25 Days -5 Days Contractor’s Delay = 25 Days Employer’s Delay = 25 Days EOT 10 Days Cost (View 1) 10 Days Cost (View 2 - Sharing) 10 Days -20 Days Pavement Layers Road Furniture Finishing Earth Works Superstructur e - 25 Days -5 Days Employer’s Delay = 35 Days Foundation Contractor’s Delay = 25 Days - 10 Days Progress Update 4 (End of Month 4)
  • 29. Summary of EOT & Cost Window Period EOT Cost (View 1) Cost (View 2) Sharing Window 1 End of Month 1 to End of Month 2 0 Days 0 Days 0 Days Window 2 End of Month 2 to End of Month 3 0 Days 0 Days 0 Days Window 3 End of Month 3 to End of Month 4 5 Days 0 Days 2.5 Days Window 4 End of Month 4 to End of Month 5 10 Days 10 Days 10 Days Total 15 Days 10 Days 12.5 Days
  • 30. Concurrent Delays •What is concurrent Delay Where two or more events of approximate equal efficacy (one Employer’s Risk event an other Contractor’s Risk Event), causes the delay in almost the same period •General Practice in the Industry •In case of Concurrent Delays, i.e. delay by the Employer as well as the delay by the Contractor, only entitlement would be Extension of Time but no prolongation cost. •Approach Advocated by Society of Construction Law ‘Delay and Disruption Protocol’ •Unless it is possible to separate out the cost caused by the Contractor’s delay and the cost caused by the Employer’s delays, the Contractor will not have an entitlement of cost in case of concurrent delay.
  • 31. Concurrent Delays  What does the Contract Stipulates  Most of the contracts do not have any express provision to address the concurrent delays. As such, the parties intentions are to be interpreted from the associated terms of contracts.  What are other ways to deal with Concurrent Delays  In various cases, the courts have addressed the issue of concurrent delays in different ways, such  Only time, but no cost based on the principle of ‘loss lies where it falls’  Apportioning the cost to relate to the delay caused by each party.  Apportioning the time as well as the cost.
  • 32. Concurrent Delays  What is the legal views that the courts in some countries may take on this issue:  Apportionment of damages based on the responsibility of respective party is widely accepted in most of the jurisdictions. Accordingly, this approach may be adopted by the courts.  However, again, apportionment may be viewed differently by courts, such as  Employer to bear its own loss of not being able to levy the delay damages and contractor to bear its own loss of prolongation cost.  Entitlement for Extension of Time to be reduced due to delays by both the parties. However, in that case, the cost is likely to be awarded for the reduced Extension of Time period.  Entire period of Employer’s delay be awarded as Extension of Time and Cost be apportioned between the parties.  Due to contrasting judgments by various courts across the world, it may be difficult to arrive to a conclusion
  • 33. Concurrent Delays Recent Legal Cases in Scotland and England City Inn and Shephard Construction In this Scottish case, the Scottish Appeal court mainly emphasized on two issues: In case, the Employer’s delay and the Contractor's delays are fairly concurrent, the Contractor is entitled for an Extension of Time. What is ‘fair and reasonable’ is a matter of ‘common sense’ and a critical path analysis was not always necessary. De Beers Case In this English case, the judge concluded that delay damages were not recoverable as long as the contractor would have suffered same damages due to his own delays
  • 34. Heads of Prolongation Cost Claims  Site Overheads  Salaries or Wages of Indirect Staff such as project Manager / Engineers/Foremen/Store man/QSs/Safety Staff/Watchmen etc.  Engineer’s and Contractor’s Site Offices cost  Extended Safety Requirement  Handling /Protection works  Material Storage Yards  Scaffolding Extended Duration  Bond/Insurances Extension  Other costs  Head Office Cost (Mostly contentious)  Sub-Contractor’s claims  Delayed Release of Retention  Financing Cost for Delayed payments (Always contentious)  Loss of Profit due to lost opportunities (Always contentious)  Disruption (Reduced Productivity /Idle Resources etc.)  Off-site overheads
  • 35. Good Planning –To Ensure Effective Use of Baseline Program for Delay Analysis  Activities Duration 7-28 Days  Activity Duration to be derived from Standard Production Rates or the Company Standard Production Rates with reasonable allowance for specific risks  Ensure Milestones are included  Ensure complete scope of work is included  Ensure activities are linked logically (correct predecessor and successors)  Ensure reasonable period allowed for approvals  Allowance for Specified Provisional Sums  Verify critical path runs through logical chain of activities  Avoidance of open ends  Check for excessive floats  Lags to be checked
  • 36. Good Planning –To Ensure Effective Use of Baseline Program for Delay Analysis  Check Holidays/Weekly-Offs are assigned  Resources are loaded into the program and resources are leveled /balanced.  Cost is loaded into the various activities  Check for resources with respect to projected cash flow  Avoidance of (Constraints) Must start /Must Finish dates etc. as far as possible.  Check what is the %age of critical activities to the total number of activities, to ensure that it is realistically planned.
  • 37. Final Word  Follow the contract provisions related to techniques to be used for Extension of Time Analysis, since that is what has been agreed between the parties.  In case the provisions in the contract are not well defined, look for what could be acceptable the local laws by consulting the legal experts.  Key word in Delay Analysis is to be Fair in our approach  Regardless of which approach we use (As Planned-Impacted or Window Analysis), it is always good to maintain the bi-weekly or monthly progress updates. Ensure protect the digital files.  As QSs/Cost Professionals, ensure we all learn Primavera, so that at least can read the Program and understand the basis principles how the claim can be made or defended
  • 38. If Contract Terms Are Not Clear… Don’t Expect Other Party to Rescue You During Dispute…………
  • 39. What is Fair differs from case to case Apportionment is not fair in the given case……..