SlideShare ist ein Scribd-Unternehmen logo
1 von 14
Downloaden Sie, um offline zu lesen
Construction: 94% Complete
Final Design: 100% Complete
Utility Relocation: 100% Complete
Property Acquisition: All rights of entry obtained
Track Work: 100% Complete
Stations:
• McLean – 84%
• Tysons Corner – 79%
• Greensboro – 69%
• Spring Hill – 69%
• Wiehle – 90%
• First Delivery of 7000-series rail cars – February 2014
• Wiehle Garage: 96% Complete
• Garage Substantial Completions: July 19, 2013
• Roadway Improvements: 70% complete
• September 2013 completion
• Estimated Cost: $87.9M

Status

Schedule

• WMATA will determine the revenue operations
date (ROD)
• Scheduled Substantial Completion Dated (SSCD):
September 9, 2013
• Testing, commissioning, acceptance by WMATA
ongoing thru ROD
• 4 sets of 2 car trains conducting testing
• 3rd rail energized
• WMATA acceptance testing – SSCD to ROD
(Sept to Dec/Jan)
• West Falls Church Yard Completion: January 2014
• Sound Box and Tail Track – November 2013
• Estimated Passenger Revenue Service: December
2013/January 2014

•
•
•
•
•
•

SEP

OCT

NOV

Service

AUG

Start Rev

2013

JUL

Completion

JUN

substantial

MAY

Silver Line

APR

substantial

MAR

garage

FEB

Wiehle

JAN

completion

Revised Budget Authorized: $2.905B
Expended to Date: $2.443B (84% of total budget)
Fairfax County share of Project expenditures = $369.1M
$150M received from Commonwealth

Timeline

• Phase 1 Maintenance and Land Conveyance process
ongoing
• Regional planning effort underway for Phase 1 bus
service (Fairfax Connector, WMATA, Washington Flyer,
PRTC, Loudoun Transit)
• Fairfax Connector Phase 1 bus service plan
approved June 4, 2013
• WMATA lead for Phase 1 marketing and outreach
• USDOT TIFIA meeting June 21,
• Funding Partners presented financial plans

Current Milestones – Past 30 Days

Budget
•
•
•
•

June 21, 2013

DEC

1
• Packet A contract award: May 2013
• Phase 2 Team - Capital Rail Constructors, Joint Venture
of Clark Construction and Kiewit International
• Project estimate Packet A = $1.4B - $1.6B vs. $1.177B
low bid
• Positive impact on toll rates = $251M (est.)
• Packet A Notice to Proceed: July 2013
• Phase 2 Bid Packages:
• Packet A - rail Line, station, and systems (includes
Innovation Center Station) - Awarded
• Packet B – Yard and shop – Procurement Fall 2013
• Packet C – Parking garages (may not be issued)
• Parking garages
• DPWES – Building Design Branch is leading the
design/construction effort for Herndon and Innovation
Center garages
• Award for Architectural/Engineering for design and
construction administration services pending
• Coordination efforts among rail project, DOT, and DPZ staff are
underway to discuss the Special Exception (SE) and for the rail
stations and entrance pavilions.
• Results of the “Route 28 Grid Analysis” traffic study are being
reviewed by DOT planning staff. The results of this study will
be used as part of the planning effort related to development
and parking garage construction at Innovation Center south.

Status

June 21, 2013

• Cost Estimate: $3.093B
• Cost Estimate with value engineering , Packet A
savings, and garages funding outside the project:
$2.6B
• Cost to build garages in Fairfax County: $135M est.

Budget

• Substantial Completion: Summer 2018
• Revenue Operations: Late 2018

Schedule

FTA oversight of Phase 2 under discussion: Ongoing
TIFIA Letter of Interest submitted: Ongoing
WMATA Art in Transit: Selection ongoing
Town Center Parkway tunnel design under review by
WMATA and MWAA
• USDOT meeting on TIFIA and Funding Partners
financial plans held on June 21
• FTA oversight of Phase 2 under discussion

Current Milestones Past 30 Days
•
•
•
•

2
June 2013

West Falls Church yard service and inspection building. Formwork and reinforced steel being placed for the
shop floor slab. Photo courtesy Stephen Barna, Dulles Corridor Metrorail Project (DCMP).

3
June 2013

West Falls Church yard new storage tracks in various stages of construction from ballast placement thru final
alignment and surface dressing. Photo courtesy Stephen Barna, DCMP.

4
June 2013

McLean Station Kiss & Ride nearing completion with lighting, landscaping, etc… being installed.
Photo courtesy Stephen Barna, DCMP.

5
June 2013

McLean Station entrance pavilion – final window and curtain wall installation; interior finish work continues.
Photo courtesy Stephen Barna, DCMP.

6
June 2013

McLean Station plaza area looking east with Route 123 on the right. A two stall bus bay sits where the red car is
parked. Photo courtesy Stephen Barna, DCMP.

7
June 2013

McLean Station passenger platform looking south/southwest. Seam roofing system and ceiling work is complete;
platform paver and finish work continues. Photo courtesy Stephen Barna, DCMP.

8
June 2013

Wiehle Station passenger platform looking west. Installation of the concrete pavers, windscreens, lighting, etc…
continues. Photo courtesy Stephen Barna, DCMP.

9
June 2013

Reston Station Blvd construction underway. The large soil stockpile was removed, utility work is nearing
completion, and curb/gutter installation began. Photo courtesy Stephen Barna, DCMP.

10
June 2013

Wiehle Station (north)/Reston Station. View from the top of the bus plaza escalators to the pedestrian bridge.
Photo courtesy Heather Diez, FCDOT.

11
June 2013

Wiehle Station (north). View of the bus plaza platform, including sawtooth bus bays. The escalators lead to the
Reston Station pedestrian plaza. Photo courtesy Heather Diez, FCDOT.

12
June 2013

Wiehle Station (north) parking garage. Color coding by floor and other finishes to be added.
Photo courtesy Heather Diez, FCDOT.

13
June 2013

Wiehle Station. Photo courtesy Andy Miller, DPWES

14

Weitere ähnliche Inhalte

Was ist angesagt?

Dulles Metrorail Silver Line Phase 2: Fairfax County Parking Garages & WMATA ...
Dulles Metrorail Silver Line Phase 2: Fairfax County Parking Garages & WMATA ...Dulles Metrorail Silver Line Phase 2: Fairfax County Parking Garages & WMATA ...
Dulles Metrorail Silver Line Phase 2: Fairfax County Parking Garages & WMATA ...Fairfax County
 
Dulles Metrorail Silver Line Phase 2 Update
Dulles Metrorail Silver Line Phase 2 UpdateDulles Metrorail Silver Line Phase 2 Update
Dulles Metrorail Silver Line Phase 2 UpdateFairfax County
 
Silver Line Update-Board Transportation Committee: Oct. 13, 2015
Silver Line Update-Board Transportation Committee: Oct. 13, 2015Silver Line Update-Board Transportation Committee: Oct. 13, 2015
Silver Line Update-Board Transportation Committee: Oct. 13, 2015Fairfax County
 
Fairfax County Countywide Transit Network Study: Sept. 17, 2013
Fairfax County Countywide Transit Network Study: Sept. 17, 2013Fairfax County Countywide Transit Network Study: Sept. 17, 2013
Fairfax County Countywide Transit Network Study: Sept. 17, 2013Fairfax County
 
Reston Network Analysis Unmitigated Results: Jan.15, 2016
Reston Network Analysis Unmitigated Results: Jan.15, 2016Reston Network Analysis Unmitigated Results: Jan.15, 2016
Reston Network Analysis Unmitigated Results: Jan.15, 2016Fairfax County
 
Silver Line Phase 1 Status Report
Silver Line Phase 1 Status ReportSilver Line Phase 1 Status Report
Silver Line Phase 1 Status ReportFairfax County
 
Silver Line Phase 1-Status Report: Feb. 4, 2014
Silver Line Phase 1-Status Report: Feb. 4, 2014Silver Line Phase 1-Status Report: Feb. 4, 2014
Silver Line Phase 1-Status Report: Feb. 4, 2014Fairfax County
 
Fairfax County Countywide Transit Network Study-February 2016 Public Meetings
Fairfax County Countywide Transit Network Study-February 2016 Public MeetingsFairfax County Countywide Transit Network Study-February 2016 Public Meetings
Fairfax County Countywide Transit Network Study-February 2016 Public MeetingsFairfax County
 
Reston Network Analysis: Mid-Buildout Results and Roadway Classifications- Ap...
Reston Network Analysis: Mid-Buildout Results and Roadway Classifications- Ap...Reston Network Analysis: Mid-Buildout Results and Roadway Classifications- Ap...
Reston Network Analysis: Mid-Buildout Results and Roadway Classifications- Ap...Fairfax County
 
Endorsement of the Recommended Design Concept (Preferred Alternative) for Tra...
Endorsement of the Recommended Design Concept (Preferred Alternative) for Tra...Endorsement of the Recommended Design Concept (Preferred Alternative) for Tra...
Endorsement of the Recommended Design Concept (Preferred Alternative) for Tra...Fairfax County
 
Braddock Road Multimodal Study: Guinea Road to I-495
Braddock Road Multimodal Study: Guinea Road to I-495Braddock Road Multimodal Study: Guinea Road to I-495
Braddock Road Multimodal Study: Guinea Road to I-495Fairfax County
 
Silver Line Phase 1-Status Report: May 6, 2014
Silver Line Phase 1-Status Report: May 6, 2014Silver Line Phase 1-Status Report: May 6, 2014
Silver Line Phase 1-Status Report: May 6, 2014Fairfax County
 
Fairfax County Countywide Transit Network Study-February 2016 Public Meeting:...
Fairfax County Countywide Transit Network Study-February 2016 Public Meeting:...Fairfax County Countywide Transit Network Study-February 2016 Public Meeting:...
Fairfax County Countywide Transit Network Study-February 2016 Public Meeting:...Fairfax County
 
Silver Line Phase 1 Status Report-Sept. 16, 2014
Silver Line Phase 1 Status Report-Sept. 16, 2014Silver Line Phase 1 Status Report-Sept. 16, 2014
Silver Line Phase 1 Status Report-Sept. 16, 2014Fairfax County
 
Snow Removal on Sidewalks
Snow Removal on SidewalksSnow Removal on Sidewalks
Snow Removal on SidewalksFairfax County
 
Hunter Mill Road and Sunset Hills Road Study
Hunter Mill Road and Sunset Hills Road StudyHunter Mill Road and Sunset Hills Road Study
Hunter Mill Road and Sunset Hills Road StudyFairfax County
 
Board of Supervisors Transportation Committee: Proposed High Quality Transit ...
Board of Supervisors Transportation Committee: Proposed High Quality Transit ...Board of Supervisors Transportation Committee: Proposed High Quality Transit ...
Board of Supervisors Transportation Committee: Proposed High Quality Transit ...Fairfax County
 
Springfield Multi-Use Parking Garage: Public Information Meeting Aug. 17, 2016
Springfield Multi-Use Parking Garage: Public Information Meeting Aug. 17, 2016Springfield Multi-Use Parking Garage: Public Information Meeting Aug. 17, 2016
Springfield Multi-Use Parking Garage: Public Information Meeting Aug. 17, 2016Fairfax County
 
Silver Line Update: Board Transportation Committee May 24, 2016
Silver Line Update: Board Transportation Committee May 24, 2016Silver Line Update: Board Transportation Committee May 24, 2016
Silver Line Update: Board Transportation Committee May 24, 2016Fairfax County
 
I-395 Express Lanes Extension
I-395 Express Lanes ExtensionI-395 Express Lanes Extension
I-395 Express Lanes ExtensionFairfax County
 

Was ist angesagt? (20)

Dulles Metrorail Silver Line Phase 2: Fairfax County Parking Garages & WMATA ...
Dulles Metrorail Silver Line Phase 2: Fairfax County Parking Garages & WMATA ...Dulles Metrorail Silver Line Phase 2: Fairfax County Parking Garages & WMATA ...
Dulles Metrorail Silver Line Phase 2: Fairfax County Parking Garages & WMATA ...
 
Dulles Metrorail Silver Line Phase 2 Update
Dulles Metrorail Silver Line Phase 2 UpdateDulles Metrorail Silver Line Phase 2 Update
Dulles Metrorail Silver Line Phase 2 Update
 
Silver Line Update-Board Transportation Committee: Oct. 13, 2015
Silver Line Update-Board Transportation Committee: Oct. 13, 2015Silver Line Update-Board Transportation Committee: Oct. 13, 2015
Silver Line Update-Board Transportation Committee: Oct. 13, 2015
 
Fairfax County Countywide Transit Network Study: Sept. 17, 2013
Fairfax County Countywide Transit Network Study: Sept. 17, 2013Fairfax County Countywide Transit Network Study: Sept. 17, 2013
Fairfax County Countywide Transit Network Study: Sept. 17, 2013
 
Reston Network Analysis Unmitigated Results: Jan.15, 2016
Reston Network Analysis Unmitigated Results: Jan.15, 2016Reston Network Analysis Unmitigated Results: Jan.15, 2016
Reston Network Analysis Unmitigated Results: Jan.15, 2016
 
Silver Line Phase 1 Status Report
Silver Line Phase 1 Status ReportSilver Line Phase 1 Status Report
Silver Line Phase 1 Status Report
 
Silver Line Phase 1-Status Report: Feb. 4, 2014
Silver Line Phase 1-Status Report: Feb. 4, 2014Silver Line Phase 1-Status Report: Feb. 4, 2014
Silver Line Phase 1-Status Report: Feb. 4, 2014
 
Fairfax County Countywide Transit Network Study-February 2016 Public Meetings
Fairfax County Countywide Transit Network Study-February 2016 Public MeetingsFairfax County Countywide Transit Network Study-February 2016 Public Meetings
Fairfax County Countywide Transit Network Study-February 2016 Public Meetings
 
Reston Network Analysis: Mid-Buildout Results and Roadway Classifications- Ap...
Reston Network Analysis: Mid-Buildout Results and Roadway Classifications- Ap...Reston Network Analysis: Mid-Buildout Results and Roadway Classifications- Ap...
Reston Network Analysis: Mid-Buildout Results and Roadway Classifications- Ap...
 
Endorsement of the Recommended Design Concept (Preferred Alternative) for Tra...
Endorsement of the Recommended Design Concept (Preferred Alternative) for Tra...Endorsement of the Recommended Design Concept (Preferred Alternative) for Tra...
Endorsement of the Recommended Design Concept (Preferred Alternative) for Tra...
 
Braddock Road Multimodal Study: Guinea Road to I-495
Braddock Road Multimodal Study: Guinea Road to I-495Braddock Road Multimodal Study: Guinea Road to I-495
Braddock Road Multimodal Study: Guinea Road to I-495
 
Silver Line Phase 1-Status Report: May 6, 2014
Silver Line Phase 1-Status Report: May 6, 2014Silver Line Phase 1-Status Report: May 6, 2014
Silver Line Phase 1-Status Report: May 6, 2014
 
Fairfax County Countywide Transit Network Study-February 2016 Public Meeting:...
Fairfax County Countywide Transit Network Study-February 2016 Public Meeting:...Fairfax County Countywide Transit Network Study-February 2016 Public Meeting:...
Fairfax County Countywide Transit Network Study-February 2016 Public Meeting:...
 
Silver Line Phase 1 Status Report-Sept. 16, 2014
Silver Line Phase 1 Status Report-Sept. 16, 2014Silver Line Phase 1 Status Report-Sept. 16, 2014
Silver Line Phase 1 Status Report-Sept. 16, 2014
 
Snow Removal on Sidewalks
Snow Removal on SidewalksSnow Removal on Sidewalks
Snow Removal on Sidewalks
 
Hunter Mill Road and Sunset Hills Road Study
Hunter Mill Road and Sunset Hills Road StudyHunter Mill Road and Sunset Hills Road Study
Hunter Mill Road and Sunset Hills Road Study
 
Board of Supervisors Transportation Committee: Proposed High Quality Transit ...
Board of Supervisors Transportation Committee: Proposed High Quality Transit ...Board of Supervisors Transportation Committee: Proposed High Quality Transit ...
Board of Supervisors Transportation Committee: Proposed High Quality Transit ...
 
Springfield Multi-Use Parking Garage: Public Information Meeting Aug. 17, 2016
Springfield Multi-Use Parking Garage: Public Information Meeting Aug. 17, 2016Springfield Multi-Use Parking Garage: Public Information Meeting Aug. 17, 2016
Springfield Multi-Use Parking Garage: Public Information Meeting Aug. 17, 2016
 
Silver Line Update: Board Transportation Committee May 24, 2016
Silver Line Update: Board Transportation Committee May 24, 2016Silver Line Update: Board Transportation Committee May 24, 2016
Silver Line Update: Board Transportation Committee May 24, 2016
 
I-395 Express Lanes Extension
I-395 Express Lanes ExtensionI-395 Express Lanes Extension
I-395 Express Lanes Extension
 

Andere mochten auch

Metrorail SafeTrack Overview and Mitigation
Metrorail SafeTrack Overview and MitigationMetrorail SafeTrack Overview and Mitigation
Metrorail SafeTrack Overview and MitigationFairfax County
 
Mobile Food Vending within VDOT Right-of-Way: Board Transportation Committee ...
Mobile Food Vending within VDOT Right-of-Way: Board Transportation Committee ...Mobile Food Vending within VDOT Right-of-Way: Board Transportation Committee ...
Mobile Food Vending within VDOT Right-of-Way: Board Transportation Committee ...Fairfax County
 
Silver Line Update: Board Transportation Committee May 24, 2016
Silver Line Update: Board Transportation Committee May 24, 2016Silver Line Update: Board Transportation Committee May 24, 2016
Silver Line Update: Board Transportation Committee May 24, 2016Fairfax County
 
Update on Route 1 Multimodal Alternatives Analysis
Update on Route 1 Multimodal Alternatives AnalysisUpdate on Route 1 Multimodal Alternatives Analysis
Update on Route 1 Multimodal Alternatives AnalysisFairfax County
 
Student Free Fare Program Update and Recommendations: Board Transportation Co...
Student Free Fare Program Update and Recommendations: Board Transportation Co...Student Free Fare Program Update and Recommendations: Board Transportation Co...
Student Free Fare Program Update and Recommendations: Board Transportation Co...Fairfax County
 
Fairfax County and the NVTA TransAction Update
Fairfax County and the NVTA TransAction UpdateFairfax County and the NVTA TransAction Update
Fairfax County and the NVTA TransAction UpdateFairfax County
 
Dulles Metrorail Silver Line Phase 2: Fairfax County Parking Garages Herndon ...
Dulles Metrorail Silver Line Phase 2: Fairfax County Parking Garages Herndon ...Dulles Metrorail Silver Line Phase 2: Fairfax County Parking Garages Herndon ...
Dulles Metrorail Silver Line Phase 2: Fairfax County Parking Garages Herndon ...Fairfax County
 
Board of Supervisors Transportation Committee: Next Steps for Urban Street St...
Board of Supervisors Transportation Committee: Next Steps for Urban Street St...Board of Supervisors Transportation Committee: Next Steps for Urban Street St...
Board of Supervisors Transportation Committee: Next Steps for Urban Street St...Fairfax County
 
Fairfax County Parkway and Franconia-Springfield Parkway Corridor Study
Fairfax County Parkway and Franconia-Springfield Parkway Corridor StudyFairfax County Parkway and Franconia-Springfield Parkway Corridor Study
Fairfax County Parkway and Franconia-Springfield Parkway Corridor StudyFairfax County
 
Transportation Funding: Implementing HB 2313, Funding Process, Benefit Cost A...
Transportation Funding: Implementing HB 2313, Funding Process, Benefit Cost A...Transportation Funding: Implementing HB 2313, Funding Process, Benefit Cost A...
Transportation Funding: Implementing HB 2313, Funding Process, Benefit Cost A...Fairfax County
 
VDRPT Route 1 Multimodal Alternatives Analysis: Recommendations for Next Steps
VDRPT Route 1 Multimodal Alternatives Analysis: Recommendations for Next StepsVDRPT Route 1 Multimodal Alternatives Analysis: Recommendations for Next Steps
VDRPT Route 1 Multimodal Alternatives Analysis: Recommendations for Next StepsFairfax County
 
Dulles Metrorail Silver Line Phase 2 Status and Funding
Dulles Metrorail Silver Line Phase 2 Status and FundingDulles Metrorail Silver Line Phase 2 Status and Funding
Dulles Metrorail Silver Line Phase 2 Status and FundingFairfax County
 
Herndon Metrorail Stations Access Management Study (HMSAMS)
Herndon Metrorail Stations Access Management Study (HMSAMS)Herndon Metrorail Stations Access Management Study (HMSAMS)
Herndon Metrorail Stations Access Management Study (HMSAMS)Fairfax County
 
Transform 66 Outside the Beltway: Multimodal Solutions- 495 to Haymarket
Transform 66 Outside the Beltway: Multimodal Solutions- 495 to HaymarketTransform 66 Outside the Beltway: Multimodal Solutions- 495 to Haymarket
Transform 66 Outside the Beltway: Multimodal Solutions- 495 to HaymarketFairfax County
 
Requirements for Pedestrian Improvements on Road Projects in the Board's Six ...
Requirements for Pedestrian Improvements on Road Projects in the Board's Six ...Requirements for Pedestrian Improvements on Road Projects in the Board's Six ...
Requirements for Pedestrian Improvements on Road Projects in the Board's Six ...Fairfax County
 
Silver Line Phase 1-Status Report: Sept. 2013
Silver Line Phase 1-Status Report: Sept. 2013Silver Line Phase 1-Status Report: Sept. 2013
Silver Line Phase 1-Status Report: Sept. 2013Fairfax County
 
Board Transportation Committee Update: March 17, 2015
Board Transportation Committee Update: March 17, 2015Board Transportation Committee Update: March 17, 2015
Board Transportation Committee Update: March 17, 2015Fairfax County
 
Route 1 Multimodal Alternatives Analysis Status Update: Sept. 17, 2013
Route 1 Multimodal Alternatives Analysis Status Update: Sept. 17, 2013Route 1 Multimodal Alternatives Analysis Status Update: Sept. 17, 2013
Route 1 Multimodal Alternatives Analysis Status Update: Sept. 17, 2013Fairfax County
 
Continuation of Countywide Dialogue on Transportation: Project Selection A Si...
Continuation of Countywide Dialogue on Transportation: Project Selection A Si...Continuation of Countywide Dialogue on Transportation: Project Selection A Si...
Continuation of Countywide Dialogue on Transportation: Project Selection A Si...Fairfax County
 
Route 1 Multimodal Alternative Analysis Status Update
Route 1 Multimodal Alternative Analysis Status UpdateRoute 1 Multimodal Alternative Analysis Status Update
Route 1 Multimodal Alternative Analysis Status UpdateFairfax County
 

Andere mochten auch (20)

Metrorail SafeTrack Overview and Mitigation
Metrorail SafeTrack Overview and MitigationMetrorail SafeTrack Overview and Mitigation
Metrorail SafeTrack Overview and Mitigation
 
Mobile Food Vending within VDOT Right-of-Way: Board Transportation Committee ...
Mobile Food Vending within VDOT Right-of-Way: Board Transportation Committee ...Mobile Food Vending within VDOT Right-of-Way: Board Transportation Committee ...
Mobile Food Vending within VDOT Right-of-Way: Board Transportation Committee ...
 
Silver Line Update: Board Transportation Committee May 24, 2016
Silver Line Update: Board Transportation Committee May 24, 2016Silver Line Update: Board Transportation Committee May 24, 2016
Silver Line Update: Board Transportation Committee May 24, 2016
 
Update on Route 1 Multimodal Alternatives Analysis
Update on Route 1 Multimodal Alternatives AnalysisUpdate on Route 1 Multimodal Alternatives Analysis
Update on Route 1 Multimodal Alternatives Analysis
 
Student Free Fare Program Update and Recommendations: Board Transportation Co...
Student Free Fare Program Update and Recommendations: Board Transportation Co...Student Free Fare Program Update and Recommendations: Board Transportation Co...
Student Free Fare Program Update and Recommendations: Board Transportation Co...
 
Fairfax County and the NVTA TransAction Update
Fairfax County and the NVTA TransAction UpdateFairfax County and the NVTA TransAction Update
Fairfax County and the NVTA TransAction Update
 
Dulles Metrorail Silver Line Phase 2: Fairfax County Parking Garages Herndon ...
Dulles Metrorail Silver Line Phase 2: Fairfax County Parking Garages Herndon ...Dulles Metrorail Silver Line Phase 2: Fairfax County Parking Garages Herndon ...
Dulles Metrorail Silver Line Phase 2: Fairfax County Parking Garages Herndon ...
 
Board of Supervisors Transportation Committee: Next Steps for Urban Street St...
Board of Supervisors Transportation Committee: Next Steps for Urban Street St...Board of Supervisors Transportation Committee: Next Steps for Urban Street St...
Board of Supervisors Transportation Committee: Next Steps for Urban Street St...
 
Fairfax County Parkway and Franconia-Springfield Parkway Corridor Study
Fairfax County Parkway and Franconia-Springfield Parkway Corridor StudyFairfax County Parkway and Franconia-Springfield Parkway Corridor Study
Fairfax County Parkway and Franconia-Springfield Parkway Corridor Study
 
Transportation Funding: Implementing HB 2313, Funding Process, Benefit Cost A...
Transportation Funding: Implementing HB 2313, Funding Process, Benefit Cost A...Transportation Funding: Implementing HB 2313, Funding Process, Benefit Cost A...
Transportation Funding: Implementing HB 2313, Funding Process, Benefit Cost A...
 
VDRPT Route 1 Multimodal Alternatives Analysis: Recommendations for Next Steps
VDRPT Route 1 Multimodal Alternatives Analysis: Recommendations for Next StepsVDRPT Route 1 Multimodal Alternatives Analysis: Recommendations for Next Steps
VDRPT Route 1 Multimodal Alternatives Analysis: Recommendations for Next Steps
 
Dulles Metrorail Silver Line Phase 2 Status and Funding
Dulles Metrorail Silver Line Phase 2 Status and FundingDulles Metrorail Silver Line Phase 2 Status and Funding
Dulles Metrorail Silver Line Phase 2 Status and Funding
 
Herndon Metrorail Stations Access Management Study (HMSAMS)
Herndon Metrorail Stations Access Management Study (HMSAMS)Herndon Metrorail Stations Access Management Study (HMSAMS)
Herndon Metrorail Stations Access Management Study (HMSAMS)
 
Transform 66 Outside the Beltway: Multimodal Solutions- 495 to Haymarket
Transform 66 Outside the Beltway: Multimodal Solutions- 495 to HaymarketTransform 66 Outside the Beltway: Multimodal Solutions- 495 to Haymarket
Transform 66 Outside the Beltway: Multimodal Solutions- 495 to Haymarket
 
Requirements for Pedestrian Improvements on Road Projects in the Board's Six ...
Requirements for Pedestrian Improvements on Road Projects in the Board's Six ...Requirements for Pedestrian Improvements on Road Projects in the Board's Six ...
Requirements for Pedestrian Improvements on Road Projects in the Board's Six ...
 
Silver Line Phase 1-Status Report: Sept. 2013
Silver Line Phase 1-Status Report: Sept. 2013Silver Line Phase 1-Status Report: Sept. 2013
Silver Line Phase 1-Status Report: Sept. 2013
 
Board Transportation Committee Update: March 17, 2015
Board Transportation Committee Update: March 17, 2015Board Transportation Committee Update: March 17, 2015
Board Transportation Committee Update: March 17, 2015
 
Route 1 Multimodal Alternatives Analysis Status Update: Sept. 17, 2013
Route 1 Multimodal Alternatives Analysis Status Update: Sept. 17, 2013Route 1 Multimodal Alternatives Analysis Status Update: Sept. 17, 2013
Route 1 Multimodal Alternatives Analysis Status Update: Sept. 17, 2013
 
Continuation of Countywide Dialogue on Transportation: Project Selection A Si...
Continuation of Countywide Dialogue on Transportation: Project Selection A Si...Continuation of Countywide Dialogue on Transportation: Project Selection A Si...
Continuation of Countywide Dialogue on Transportation: Project Selection A Si...
 
Route 1 Multimodal Alternative Analysis Status Update
Route 1 Multimodal Alternative Analysis Status UpdateRoute 1 Multimodal Alternative Analysis Status Update
Route 1 Multimodal Alternative Analysis Status Update
 

Ähnlich wie Dulles Rail Phase 1-Status Report: June 21, 2013

Agenda Item 7: Silver Line Phase II Implementation
Agenda Item 7: Silver Line Phase II ImplementationAgenda Item 7: Silver Line Phase II Implementation
Agenda Item 7: Silver Line Phase II ImplementationFairfax County
 
Silver Line Update: Board Transportation Committee: Dec. 13, 2016
Silver Line Update: Board Transportation Committee: Dec. 13, 2016Silver Line Update: Board Transportation Committee: Dec. 13, 2016
Silver Line Update: Board Transportation Committee: Dec. 13, 2016Fairfax County
 
Dulles Corridor Metrorail Project - Silver Line Phase 2 Implementation : Boar...
Dulles Corridor Metrorail Project - Silver Line Phase 2 Implementation : Boar...Dulles Corridor Metrorail Project - Silver Line Phase 2 Implementation : Boar...
Dulles Corridor Metrorail Project - Silver Line Phase 2 Implementation : Boar...Fairfax County
 
Western works final
Western works final Western works final
Western works final Crosstown TO
 
Silverbrook Road at Monacan Road Walkway Project
Silverbrook Road at Monacan Road Walkway ProjectSilverbrook Road at Monacan Road Walkway Project
Silverbrook Road at Monacan Road Walkway ProjectFairfax County
 
Update on Tysons Transportation Projects - April 1, 2020
Update on Tysons Transportation Projects - April 1, 2020Update on Tysons Transportation Projects - April 1, 2020
Update on Tysons Transportation Projects - April 1, 2020Fairfax County
 
Dulles Corridor Metrorail Project: Board Transportation Committee Update- Jul...
Dulles Corridor Metrorail Project: Board Transportation Committee Update- Jul...Dulles Corridor Metrorail Project: Board Transportation Committee Update- Jul...
Dulles Corridor Metrorail Project: Board Transportation Committee Update- Jul...Fairfax County
 
Silver Line Update: Board Transportation Committee: Feb. 7, 2017
Silver Line Update: Board Transportation Committee: Feb. 7, 2017Silver Line Update: Board Transportation Committee: Feb. 7, 2017
Silver Line Update: Board Transportation Committee: Feb. 7, 2017Fairfax County
 
Glade Drive Walkway - Middle Creek Lane to Glade Bank Way
Glade Drive Walkway - Middle Creek Lane to Glade Bank WayGlade Drive Walkway - Middle Creek Lane to Glade Bank Way
Glade Drive Walkway - Middle Creek Lane to Glade Bank WayFairfax County
 
North Shore Sidewalk Improvements
North Shore Sidewalk ImprovementsNorth Shore Sidewalk Improvements
North Shore Sidewalk ImprovementsFairfax County
 
Central East Crosstown Open House Presentation
Central East Crosstown Open House PresentationCentral East Crosstown Open House Presentation
Central East Crosstown Open House PresentationCrosstown TO
 
Pharmacy kennedy clc meeting -january 29 2019
Pharmacy kennedy clc meeting -january 29 2019Pharmacy kennedy clc meeting -january 29 2019
Pharmacy kennedy clc meeting -january 29 2019Crosstown TO
 
Capital Improvement Project Highlights for Downtown Merchants
Capital Improvement Project Highlights for Downtown MerchantsCapital Improvement Project Highlights for Downtown Merchants
Capital Improvement Project Highlights for Downtown MerchantsStateCollegePA
 
West Open House (Mount Dennis Station to Keelesdale Station) - March 2018
West Open House (Mount Dennis Station to Keelesdale Station) - March 2018West Open House (Mount Dennis Station to Keelesdale Station) - March 2018
West Open House (Mount Dennis Station to Keelesdale Station) - March 2018Crosstown TO
 
Cedarvale station open house for website final2
Cedarvale station open house for website final2Cedarvale station open house for website final2
Cedarvale station open house for website final2Crosstown TO
 
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)Crosstown TO
 
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)Crosstown TO
 
Central Eastern Works Open House - October 2019
Central Eastern Works Open House - October 2019Central Eastern Works Open House - October 2019
Central Eastern Works Open House - October 2019Crosstown TO
 

Ähnlich wie Dulles Rail Phase 1-Status Report: June 21, 2013 (20)

Agenda Item 7: Silver Line Phase II Implementation
Agenda Item 7: Silver Line Phase II ImplementationAgenda Item 7: Silver Line Phase II Implementation
Agenda Item 7: Silver Line Phase II Implementation
 
Silver Line Update: Board Transportation Committee: Dec. 13, 2016
Silver Line Update: Board Transportation Committee: Dec. 13, 2016Silver Line Update: Board Transportation Committee: Dec. 13, 2016
Silver Line Update: Board Transportation Committee: Dec. 13, 2016
 
Dulles Corridor Metrorail Project - Silver Line Phase 2 Implementation : Boar...
Dulles Corridor Metrorail Project - Silver Line Phase 2 Implementation : Boar...Dulles Corridor Metrorail Project - Silver Line Phase 2 Implementation : Boar...
Dulles Corridor Metrorail Project - Silver Line Phase 2 Implementation : Boar...
 
Western works final
Western works final Western works final
Western works final
 
Fitchburg Commuter Rail Line Improvement Project
Fitchburg Commuter Rail Line Improvement ProjectFitchburg Commuter Rail Line Improvement Project
Fitchburg Commuter Rail Line Improvement Project
 
Silverbrook Road at Monacan Road Walkway Project
Silverbrook Road at Monacan Road Walkway ProjectSilverbrook Road at Monacan Road Walkway Project
Silverbrook Road at Monacan Road Walkway Project
 
Update on Tysons Transportation Projects - April 1, 2020
Update on Tysons Transportation Projects - April 1, 2020Update on Tysons Transportation Projects - April 1, 2020
Update on Tysons Transportation Projects - April 1, 2020
 
Dulles Corridor Metrorail Project: Board Transportation Committee Update- Jul...
Dulles Corridor Metrorail Project: Board Transportation Committee Update- Jul...Dulles Corridor Metrorail Project: Board Transportation Committee Update- Jul...
Dulles Corridor Metrorail Project: Board Transportation Committee Update- Jul...
 
Silver Line Update: Board Transportation Committee: Feb. 7, 2017
Silver Line Update: Board Transportation Committee: Feb. 7, 2017Silver Line Update: Board Transportation Committee: Feb. 7, 2017
Silver Line Update: Board Transportation Committee: Feb. 7, 2017
 
Glade Drive Walkway - Middle Creek Lane to Glade Bank Way
Glade Drive Walkway - Middle Creek Lane to Glade Bank WayGlade Drive Walkway - Middle Creek Lane to Glade Bank Way
Glade Drive Walkway - Middle Creek Lane to Glade Bank Way
 
North Shore Sidewalk Improvements
North Shore Sidewalk ImprovementsNorth Shore Sidewalk Improvements
North Shore Sidewalk Improvements
 
Central East Crosstown Open House Presentation
Central East Crosstown Open House PresentationCentral East Crosstown Open House Presentation
Central East Crosstown Open House Presentation
 
Pharmacy kennedy clc meeting -january 29 2019
Pharmacy kennedy clc meeting -january 29 2019Pharmacy kennedy clc meeting -january 29 2019
Pharmacy kennedy clc meeting -january 29 2019
 
Capital Improvement Project Highlights for Downtown Merchants
Capital Improvement Project Highlights for Downtown MerchantsCapital Improvement Project Highlights for Downtown Merchants
Capital Improvement Project Highlights for Downtown Merchants
 
West Open House (Mount Dennis Station to Keelesdale Station) - March 2018
West Open House (Mount Dennis Station to Keelesdale Station) - March 2018West Open House (Mount Dennis Station to Keelesdale Station) - March 2018
West Open House (Mount Dennis Station to Keelesdale Station) - March 2018
 
State of the City of Norman
State of the City of NormanState of the City of Norman
State of the City of Norman
 
Cedarvale station open house for website final2
Cedarvale station open house for website final2Cedarvale station open house for website final2
Cedarvale station open house for website final2
 
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
 
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
 
Central Eastern Works Open House - October 2019
Central Eastern Works Open House - October 2019Central Eastern Works Open House - October 2019
Central Eastern Works Open House - October 2019
 

Mehr von Fairfax County

Merrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer ReplacementMerrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer ReplacementFairfax County
 
SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS Fairfax County
 
Clarks Crossing Road Improvements 05-13-22
 Clarks Crossing Road Improvements 05-13-22 Clarks Crossing Road Improvements 05-13-22
Clarks Crossing Road Improvements 05-13-22Fairfax County
 
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptxTysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptxFairfax County
 
Lorton Volunteer Fire Station #19
Lorton Volunteer Fire Station  #19 Lorton Volunteer Fire Station  #19
Lorton Volunteer Fire Station #19 Fairfax County
 
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream RestorationScotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream RestorationFairfax County
 
Sully Community Center Construction Progress
Sully Community Center Construction ProgressSully Community Center Construction Progress
Sully Community Center Construction ProgressFairfax County
 
Riverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptxRiverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptxFairfax County
 
Burke VRE Connector Phase IV
Burke VRE Connector Phase IVBurke VRE Connector Phase IV
Burke VRE Connector Phase IVFairfax County
 
Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022Fairfax County
 
Workhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick OffpptxWorkhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick OffpptxFairfax County
 
Workhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing CouncilWorkhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing CouncilFairfax County
 
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
 Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptxFairfax County
 
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT Fairfax County
 
Reston Arts Community Center Feasibility - Wrap Up
 Reston Arts Community Center Feasibility - Wrap Up Reston Arts Community Center Feasibility - Wrap Up
Reston Arts Community Center Feasibility - Wrap UpFairfax County
 
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022Fairfax County
 
Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022Fairfax County
 
Oak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction ProjectOak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction ProjectFairfax County
 
Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022Fairfax County
 
Reston Arts Center Feasibility - Focus Group Visual Arts
Reston Arts Center Feasibility -  Focus Group Visual ArtsReston Arts Center Feasibility -  Focus Group Visual Arts
Reston Arts Center Feasibility - Focus Group Visual ArtsFairfax County
 

Mehr von Fairfax County (20)

Merrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer ReplacementMerrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer Replacement
 
SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS
 
Clarks Crossing Road Improvements 05-13-22
 Clarks Crossing Road Improvements 05-13-22 Clarks Crossing Road Improvements 05-13-22
Clarks Crossing Road Improvements 05-13-22
 
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptxTysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
 
Lorton Volunteer Fire Station #19
Lorton Volunteer Fire Station  #19 Lorton Volunteer Fire Station  #19
Lorton Volunteer Fire Station #19
 
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream RestorationScotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
 
Sully Community Center Construction Progress
Sully Community Center Construction ProgressSully Community Center Construction Progress
Sully Community Center Construction Progress
 
Riverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptxRiverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptx
 
Burke VRE Connector Phase IV
Burke VRE Connector Phase IVBurke VRE Connector Phase IV
Burke VRE Connector Phase IV
 
Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022
 
Workhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick OffpptxWorkhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick Offpptx
 
Workhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing CouncilWorkhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing Council
 
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
 Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
 
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
 
Reston Arts Community Center Feasibility - Wrap Up
 Reston Arts Community Center Feasibility - Wrap Up Reston Arts Community Center Feasibility - Wrap Up
Reston Arts Community Center Feasibility - Wrap Up
 
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
 
Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022
 
Oak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction ProjectOak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction Project
 
Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022
 
Reston Arts Center Feasibility - Focus Group Visual Arts
Reston Arts Center Feasibility -  Focus Group Visual ArtsReston Arts Center Feasibility -  Focus Group Visual Arts
Reston Arts Center Feasibility - Focus Group Visual Arts
 

Kürzlich hochgeladen

Por estos dos motivos, defensa de JOH solicita repetir juicio
Por estos dos motivos, defensa de JOH solicita repetir juicioPor estos dos motivos, defensa de JOH solicita repetir juicio
Por estos dos motivos, defensa de JOH solicita repetir juicioAlexisTorres963861
 
Ministry of Justice Extradition Eswatini 3.pdf
Ministry of Justice Extradition Eswatini 3.pdfMinistry of Justice Extradition Eswatini 3.pdf
Ministry of Justice Extradition Eswatini 3.pdfSABC News
 
19032024_First India Newspaper Jaipur.pdf
19032024_First India Newspaper Jaipur.pdf19032024_First India Newspaper Jaipur.pdf
19032024_First India Newspaper Jaipur.pdfFIRST INDIA
 
Another Day, Another Default Judgment Against Gabe Whitley
Another Day, Another Default Judgment Against Gabe WhitleyAnother Day, Another Default Judgment Against Gabe Whitley
Another Day, Another Default Judgment Against Gabe WhitleyAbdul-Hakim Shabazz
 
One India vs United India by Dream Tamilnadu
One India vs United India by Dream TamilnaduOne India vs United India by Dream Tamilnadu
One India vs United India by Dream TamilnaduDreamTamilnadu
 
Européennes 2024 : projection du Parlement européen à trois mois du scrutin
Européennes 2024 : projection du Parlement européen à trois mois du scrutinEuropéennes 2024 : projection du Parlement européen à trois mois du scrutin
Européennes 2024 : projection du Parlement européen à trois mois du scrutinIpsos France
 
Light Rail in Canberra: Too much, too little, too late: Is the price worth th...
Light Rail in Canberra: Too much, too little, too late: Is the price worth th...Light Rail in Canberra: Too much, too little, too late: Is the price worth th...
Light Rail in Canberra: Too much, too little, too late: Is the price worth th...University of Canberra
 
Anantkumar Hegde
Anantkumar Hegde  Anantkumar Hegde
Anantkumar Hegde NewsFeed1
 
Green Aesthetic Ripped Paper Thesis Defense Presentation_20240311_111012_0000...
Green Aesthetic Ripped Paper Thesis Defense Presentation_20240311_111012_0000...Green Aesthetic Ripped Paper Thesis Defense Presentation_20240311_111012_0000...
Green Aesthetic Ripped Paper Thesis Defense Presentation_20240311_111012_0000...virgfern3011
 

Kürzlich hochgeladen (9)

Por estos dos motivos, defensa de JOH solicita repetir juicio
Por estos dos motivos, defensa de JOH solicita repetir juicioPor estos dos motivos, defensa de JOH solicita repetir juicio
Por estos dos motivos, defensa de JOH solicita repetir juicio
 
Ministry of Justice Extradition Eswatini 3.pdf
Ministry of Justice Extradition Eswatini 3.pdfMinistry of Justice Extradition Eswatini 3.pdf
Ministry of Justice Extradition Eswatini 3.pdf
 
19032024_First India Newspaper Jaipur.pdf
19032024_First India Newspaper Jaipur.pdf19032024_First India Newspaper Jaipur.pdf
19032024_First India Newspaper Jaipur.pdf
 
Another Day, Another Default Judgment Against Gabe Whitley
Another Day, Another Default Judgment Against Gabe WhitleyAnother Day, Another Default Judgment Against Gabe Whitley
Another Day, Another Default Judgment Against Gabe Whitley
 
One India vs United India by Dream Tamilnadu
One India vs United India by Dream TamilnaduOne India vs United India by Dream Tamilnadu
One India vs United India by Dream Tamilnadu
 
Européennes 2024 : projection du Parlement européen à trois mois du scrutin
Européennes 2024 : projection du Parlement européen à trois mois du scrutinEuropéennes 2024 : projection du Parlement européen à trois mois du scrutin
Européennes 2024 : projection du Parlement européen à trois mois du scrutin
 
Light Rail in Canberra: Too much, too little, too late: Is the price worth th...
Light Rail in Canberra: Too much, too little, too late: Is the price worth th...Light Rail in Canberra: Too much, too little, too late: Is the price worth th...
Light Rail in Canberra: Too much, too little, too late: Is the price worth th...
 
Anantkumar Hegde
Anantkumar Hegde  Anantkumar Hegde
Anantkumar Hegde
 
Green Aesthetic Ripped Paper Thesis Defense Presentation_20240311_111012_0000...
Green Aesthetic Ripped Paper Thesis Defense Presentation_20240311_111012_0000...Green Aesthetic Ripped Paper Thesis Defense Presentation_20240311_111012_0000...
Green Aesthetic Ripped Paper Thesis Defense Presentation_20240311_111012_0000...
 

Dulles Rail Phase 1-Status Report: June 21, 2013

  • 1. Construction: 94% Complete Final Design: 100% Complete Utility Relocation: 100% Complete Property Acquisition: All rights of entry obtained Track Work: 100% Complete Stations: • McLean – 84% • Tysons Corner – 79% • Greensboro – 69% • Spring Hill – 69% • Wiehle – 90% • First Delivery of 7000-series rail cars – February 2014 • Wiehle Garage: 96% Complete • Garage Substantial Completions: July 19, 2013 • Roadway Improvements: 70% complete • September 2013 completion • Estimated Cost: $87.9M Status Schedule • WMATA will determine the revenue operations date (ROD) • Scheduled Substantial Completion Dated (SSCD): September 9, 2013 • Testing, commissioning, acceptance by WMATA ongoing thru ROD • 4 sets of 2 car trains conducting testing • 3rd rail energized • WMATA acceptance testing – SSCD to ROD (Sept to Dec/Jan) • West Falls Church Yard Completion: January 2014 • Sound Box and Tail Track – November 2013 • Estimated Passenger Revenue Service: December 2013/January 2014 • • • • • • SEP OCT NOV Service AUG Start Rev 2013 JUL Completion JUN substantial MAY Silver Line APR substantial MAR garage FEB Wiehle JAN completion Revised Budget Authorized: $2.905B Expended to Date: $2.443B (84% of total budget) Fairfax County share of Project expenditures = $369.1M $150M received from Commonwealth Timeline • Phase 1 Maintenance and Land Conveyance process ongoing • Regional planning effort underway for Phase 1 bus service (Fairfax Connector, WMATA, Washington Flyer, PRTC, Loudoun Transit) • Fairfax Connector Phase 1 bus service plan approved June 4, 2013 • WMATA lead for Phase 1 marketing and outreach • USDOT TIFIA meeting June 21, • Funding Partners presented financial plans Current Milestones – Past 30 Days Budget • • • • June 21, 2013 DEC 1
  • 2. • Packet A contract award: May 2013 • Phase 2 Team - Capital Rail Constructors, Joint Venture of Clark Construction and Kiewit International • Project estimate Packet A = $1.4B - $1.6B vs. $1.177B low bid • Positive impact on toll rates = $251M (est.) • Packet A Notice to Proceed: July 2013 • Phase 2 Bid Packages: • Packet A - rail Line, station, and systems (includes Innovation Center Station) - Awarded • Packet B – Yard and shop – Procurement Fall 2013 • Packet C – Parking garages (may not be issued) • Parking garages • DPWES – Building Design Branch is leading the design/construction effort for Herndon and Innovation Center garages • Award for Architectural/Engineering for design and construction administration services pending • Coordination efforts among rail project, DOT, and DPZ staff are underway to discuss the Special Exception (SE) and for the rail stations and entrance pavilions. • Results of the “Route 28 Grid Analysis” traffic study are being reviewed by DOT planning staff. The results of this study will be used as part of the planning effort related to development and parking garage construction at Innovation Center south. Status June 21, 2013 • Cost Estimate: $3.093B • Cost Estimate with value engineering , Packet A savings, and garages funding outside the project: $2.6B • Cost to build garages in Fairfax County: $135M est. Budget • Substantial Completion: Summer 2018 • Revenue Operations: Late 2018 Schedule FTA oversight of Phase 2 under discussion: Ongoing TIFIA Letter of Interest submitted: Ongoing WMATA Art in Transit: Selection ongoing Town Center Parkway tunnel design under review by WMATA and MWAA • USDOT meeting on TIFIA and Funding Partners financial plans held on June 21 • FTA oversight of Phase 2 under discussion Current Milestones Past 30 Days • • • • 2
  • 3. June 2013 West Falls Church yard service and inspection building. Formwork and reinforced steel being placed for the shop floor slab. Photo courtesy Stephen Barna, Dulles Corridor Metrorail Project (DCMP). 3
  • 4. June 2013 West Falls Church yard new storage tracks in various stages of construction from ballast placement thru final alignment and surface dressing. Photo courtesy Stephen Barna, DCMP. 4
  • 5. June 2013 McLean Station Kiss & Ride nearing completion with lighting, landscaping, etc… being installed. Photo courtesy Stephen Barna, DCMP. 5
  • 6. June 2013 McLean Station entrance pavilion – final window and curtain wall installation; interior finish work continues. Photo courtesy Stephen Barna, DCMP. 6
  • 7. June 2013 McLean Station plaza area looking east with Route 123 on the right. A two stall bus bay sits where the red car is parked. Photo courtesy Stephen Barna, DCMP. 7
  • 8. June 2013 McLean Station passenger platform looking south/southwest. Seam roofing system and ceiling work is complete; platform paver and finish work continues. Photo courtesy Stephen Barna, DCMP. 8
  • 9. June 2013 Wiehle Station passenger platform looking west. Installation of the concrete pavers, windscreens, lighting, etc… continues. Photo courtesy Stephen Barna, DCMP. 9
  • 10. June 2013 Reston Station Blvd construction underway. The large soil stockpile was removed, utility work is nearing completion, and curb/gutter installation began. Photo courtesy Stephen Barna, DCMP. 10
  • 11. June 2013 Wiehle Station (north)/Reston Station. View from the top of the bus plaza escalators to the pedestrian bridge. Photo courtesy Heather Diez, FCDOT. 11
  • 12. June 2013 Wiehle Station (north). View of the bus plaza platform, including sawtooth bus bays. The escalators lead to the Reston Station pedestrian plaza. Photo courtesy Heather Diez, FCDOT. 12
  • 13. June 2013 Wiehle Station (north) parking garage. Color coding by floor and other finishes to be added. Photo courtesy Heather Diez, FCDOT. 13
  • 14. June 2013 Wiehle Station. Photo courtesy Andy Miller, DPWES 14