SlideShare a Scribd company logo
1 of 21
Download to read offline
217
217
217
200
200
200
255
255
255
0
0
0
163
163
163
131
132
122
239
65
53
110
135
120
112
92
56
62
102
130
102
56
48
130
120
111
237
237
237
80
119
27
252
174
.59
โ€œThe views, opinions and findings contained in this report are
those of the authors(s) and should not be construed as an
official Department of the Army position, policy or decision,
unless so designated by other official documentation.โ€
HUDSON RARITAN ESTUARY ECOSYSTEM
RESTORATION โ€“ JAMAICA BAY UPDATE
JAMAICA BAY TASK FORCE MEETING
LISA BARON
PROJECT MANAGER, CIVIL WORKS
NEW YORK DISTRICT
MAY 10, 2022
1
File Name
AGENDA
โ€ข Past Marsh Island Restoration Success
โ€ข HRE Ecosystem Restoration
๏ƒผ Ongoing Projects including Stony Creek
Marsh Island
๏ƒผ Future Jamaica Bay Marsh Islands and
Perimeter Sites
โ€ข Spring Creek North Ecosystem Restoration
Project
โ€ข Spring Creek South (Howard Beach) Multi-
Purpose Feasibility Study
File Name
2
JAMAICA BAY MARSH ISLAND RESTORATION- PAST SUCCESS
Elders East
Elders West
Yellow Bar
John F. Kennedy
Airport
JoCo
Yellow Bar - 2012 (47 acres)
Elders East- 2007 (40 acres)
Elders East- 2011
โ€ข >2000 acres of Marsh
Islands have been lost
since 1924
โ€ข Restored 160 acres
โ€ข HRE Recommendation of
170 acres
Elders Center
Duck Point
Stony Creek
Pumpkin Patch
(East & West)
Elders West- 20010 (43 acres)
Black Wall and Rulers Bar (30 acres)
Black Wall and Rulers Bar
JAMAICA BAY MARSH ISLANDS CONSTRUCTION 4
BUILDING THE ISLAND - GRADING
5
VEGETATING THE ISLAND โ€“ TRANSPLANTING
6
July 2010
October 2006
Photo courtesy of Galvin Brothers, Inc.
October 2006
RESTORATION OF ELDERS EAST
Elders East 2011
ELDERS EAST - 2007
ELDERS EAST - 2011
BLACK WALL and RULERS BAR
PRE-RESTORATION
YELLOW BAR, BLACK WALL AND RULERS
BAR MARSH ISLAND RESTORATION 2012
11
Yellow Bar: 46 acres, $17.3M
Black Wall: 20 acres, $2.1M
2007
Rulers Bar: 10 acres, $1.311M
Sponsors: NYSDEC,
NYCDEP, PANYNJ, NPS
12
Yellow Bar: 44 acres, $17.3M
Black Wall: 20 acres, $2.1M 2007
Rulers Bar: 10 acres, $1.311M
Sponsors:
NYSDEC
Planting Effort at Black Wall and Rulers Bar (July 2013):
Jamaica Bay EcoWatchers, American Littoral Society,
Jamaica Bay Guardian and Community Volunteers
HRE RESTORATION PROGRAM
โ€ข Chiefโ€™s Report (May 2020)
recommended 20 individual
projects that will restore a mosaic of
621 acres of habitat including:
๏ƒผ 381 acres of estuarine wetlands (w/ 6
miles of tidal channels), 50 acres of
freshwater riverine wetlands, 27 acres
of coastal and maritime forest, 39
acres of shallow water habitat and 52
acres of oyster habitat;
๏ƒผ Installation of 2 fish ladders (or
potential removal) and modification of
3 weirs modified to improve fish
passage (24 miles) on the Bronx
River.
๏ƒผ 1.6 miles of stream bank and 72 acres
of stream bed and channel
restoration.
โ€ข Construction authorized in WRDA
2020.
Jamaica Bay
6,8
1,2,5
1,2
1,2
6,7,8
4
4
All Marsh
Islands: 1,2,5
1,2,3
1,2,3
6,7,8
6,7,8,9
8,9
1,3,5
1. Estuarine Wetlands
2. Tidal Channel Restoration
3. Maritime Forest
4. Oyster Reefs
5. Shallow Water Habitat
6. Freshwater Wetlands
7. Streambank Restoration
8. Bed Restoration
9. Fishway
10.Sediment Forebay
6,8
1,2,5
1,2
6,8, 10
Fully funded cost: $624,772,000 (FY22)
HRE ECOSYSTEM RESTORATION
Pre-Construction Engineering Design (PED) Projects
โ€ข $1,200,000 included in the 2022
Consolidated Appropriations Act
โ€ข $25,978,000 in the Addendum to
2020 Infrastructure Investment and
Jobs Act to complete PED for first 4
HRE Projects (5 sites) and
CONSTRUCT STONY CREEK
MARSH ISLAND!
โ€ข Local Sponsors: NYCDEP, NYC
Parks
โ€ข Project Partners: NY/NJ Baykeeper
(Oysters)
15
STONY CREEK MARSH ISLAND PLANNED ACTIVITIES
โ€ข Execute Design Agreement with NYCDEP (by July 1, 2022)
โ€ข Project Management Plan (ongoing)
โ€ข Field Investigations:
๏ƒผ Bathymetric/Topographic Surveys (2022/2023)
๏ƒผ Hydrodynamic Data Collection โ€“ Tide Gauges and Modeling (2023)
๏ƒผ Bio-Benchmarking (2023)
๏ƒผ Wetland Delineation (2023)
โ€ข Plans and Specifications (P&S): Designs, Quantities, Cost Estimates
๏ƒผ 30% P&S and Value Engineering Study (2023)
๏ƒผ 60% P&S (2023/2024)
๏ƒผ 90% P&S (2024)
๏ƒผ 100% P&S (2024/2025)
โ€ข Coordination with Operations Division for dredging contract (~155,000 CYD)
โ€ข Coordination with NPS throughout โ€“ Special Use Permit/MOU
โ€ข Permitting โ€“ Water Quality Certificate
โ€ข Biddability, Constructability, Operability, and Environmental Reviews (all design iterations)
and Agency Technical Review (90% P&S)
โ€ข Execute Project Partnership Agreement for Construction (2024)
โ€ข Ready to Advertise (early 2025)
โ€ข Construction (2025)
16
HRE
Restoration
Sites
327 acres of habitat
restoration:
- 206 acres of
marsh islands
- 121 acres along
perimeter
Local Sponsors:
NYCDEP and
NYSDEC (Dead
Horse Bay) in
partnership with NPS
155,000 CYD
62 acres
41 acres
80 acres
215,000 CYD
40 acres
285,000 CYD
29 acres
328,000 CYD
24 acres
352,000 CYD
29 acres
10 acres
17
https://www.nan.usace.army.mil/Portals/37/docs/Environmental/HRE/HRE%20Final%20Cost%20Appendi
x%20I_20April2020.pdf?ver=2020-05-29-085232-857 โ€“ page I-24
CONSTRUCTION SCHEDULE - SEQUENCING
Timing dependent on appropriation of funds for USACE, NYCDEP and NYSDEC
January 2025
Spring Creek North Ecosystem Restoration
(Continuing Authorities Program)
โ€ข Local Sponsor: NYC Parks
with additional funding from NYCDEP
โ€ข Total of $7.37M included in the
Infrastructure Investment and Jobs Act
โ€ข Funds to be used to complete design phase
and initiate implementation
โ€ข Restoration of 47-acres including:
๏ƒผ 18.3 acres of wetlands
๏ƒผ 29 acres of maritime uplands
โ€ข Restoration through excavating and
recontouring uplands to intertidal elevations,
removing invasives species and replanting
as well as restoring existing degraded
wetlands with Thin Layer Placement
techniques
โ€ข Construction is planned for 2023
Spring Creek South (Howard Beach) Multi-purpose Feasibility Study
Ecosystem Restoration and Coastal Storm Risk Management (CSRM)
โ€ข WRDA 2020 - expedite completion of multi-purpose feasibility study for
โ€œecosystem restoration and hurricane and storm damage reductionโ€.
โ€ข $1.2M included in the Infrastructure Bill and $500,000 in the FY22 Bill to
complete the Feasibility Study in partnership with NYSDEC and NPS
โ€ข Need to execute Feasibility Cost Share Agreement with NYSDEC for
$3,000,000/3 years.
โ€ข Project could include coastal restoration of 237 acres of degraded
habitat including tidal marsh, freshwater wetlands, scrub/shrub wetlands,
adjacent upland habitats, earthen berm with additional CSRM measures
(such as tide gates in Shellbank and Hawtree Basins).
โ€ข Build upon the foundation from information and investments
already made on prior studies, investigations, and design efforts
(including HRE, Jamaica Bay Feasibility Study, East Rockaway
Reformulation, NY Rising, NYSDEC/FEMA Hazard Mitigation
Grant Program and NPS Remedial Investigation).
โ€ข This study, in coordination with the NY/NJ Harbor and
Tributaries Study, will provide an opportunity to recommend
natural and nature-based features as well as coastal storm risk
management measures. These measures will reduce risk to
flooding and provide environmental benefits to the community
and Jamaica Bayโ€”resulting in a more resilient and sustainable
shoreline and region.
TENTATIVE OVERALL SCHEDULE
JAMAICA BAY RESTORATION
Project 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2032 2033 2034 2035
Spring Creek North
HRE-Stony Creek
Marsh Island
Spring Creek
South Feasibility
Study
HRE-Fresh Creek
HRE-Duck Point
Marsh Island
HRE-Elders Center
Marsh Island
HRE-Pumpkin
Patch West Marsh
Island
HRE- Dead Horse
Bay
HRE-Pumpkin
Patch East Marsh
Island
Feasibility Study
Pre-Construction Engineering
and Design
Construction Above schedule dependent upon funding
and execution of Design Agreements and
Project Partnership Agreements
Monitoring and Adaptive
Management
20
All Funding in-hand
All Funding in-hand
All Funding in-hand for FS
Requires appropriations for design and construction for remaining sites
Requires construction authorization and appropriations for design
and construction
21
Lisa Baron
Lisa.a.baron@usace.army.mil
646-385-1429
Questions?

More Related Content

Similar to Jamaica Bay Task Force2- 10May22.pdf

Lake Accotink Dredge Public Meeting Combined Presentation July 29 & aug 5...
Lake Accotink Dredge Public Meeting Combined Presentation July 29 & aug 5...Lake Accotink Dredge Public Meeting Combined Presentation July 29 & aug 5...
Lake Accotink Dredge Public Meeting Combined Presentation July 29 & aug 5...Fairfax County
ย 
ACOE Coastal Storm Management Alternative for Jamaica Bay Communities
ACOE Coastal Storm Management Alternative for Jamaica Bay CommunitiesACOE Coastal Storm Management Alternative for Jamaica Bay Communities
ACOE Coastal Storm Management Alternative for Jamaica Bay Communitiesecowatchers
ย 
PortsHarborsBeaches_Capabilities_Statement
PortsHarborsBeaches_Capabilities_StatementPortsHarborsBeaches_Capabilities_Statement
PortsHarborsBeaches_Capabilities_StatementDebbie Kilbane Fawcett
ย 
0837-Petty-WV
0837-Petty-WV0837-Petty-WV
0837-Petty-WVMatthew Winans
ย 
Portfolio EP5-Zukerberg
Portfolio EP5-ZukerbergPortfolio EP5-Zukerberg
Portfolio EP5-ZukerbergMichele Zukerberg
ย 
Muskegon Lake Restoration: A Success Story
Muskegon Lake Restoration: A Success StoryMuskegon Lake Restoration: A Success Story
Muskegon Lake Restoration: A Success StoryHealthy Lakes, Healthy Lives
ย 
Jamaica bay resiliency
Jamaica bay resiliencyJamaica bay resiliency
Jamaica bay resiliencyecowatchers
ย 
Lake Accotink Dredging Public Meeting Presentation December 2020
Lake Accotink Dredging Public Meeting Presentation December 2020Lake Accotink Dredging Public Meeting Presentation December 2020
Lake Accotink Dredging Public Meeting Presentation December 2020Fairfax County
ย 
Long Branch Tributary at Long Branch Falls Park Public Meeting 8-20-2015
Long Branch Tributary at Long Branch Falls Park Public Meeting 8-20-2015Long Branch Tributary at Long Branch Falls Park Public Meeting 8-20-2015
Long Branch Tributary at Long Branch Falls Park Public Meeting 8-20-2015Fairfax County
ย 
Regueroetal_ReEng_Reefs_2015
Regueroetal_ReEng_Reefs_2015Regueroetal_ReEng_Reefs_2015
Regueroetal_ReEng_Reefs_2015Borja G. Reguero
ย 
Orlando 2015
Orlando 2015Orlando 2015
Orlando 2015Beau Williams
ย 
Beach Glass Swana Presen.
Beach Glass Swana Presen.Beach Glass Swana Presen.
Beach Glass Swana Presen.Phil Bresee
ย 
NYNJHAT Presentation slides for Jamaica Bay Task Force Meeting 17 Nov 22.pdf
NYNJHAT Presentation slides for Jamaica Bay Task Force Meeting 17 Nov 22.pdfNYNJHAT Presentation slides for Jamaica Bay Task Force Meeting 17 Nov 22.pdf
NYNJHAT Presentation slides for Jamaica Bay Task Force Meeting 17 Nov 22.pdfecowatchers
ย 
Accotink Tributary at Danbury Forest
Accotink Tributary at Danbury ForestAccotink Tributary at Danbury Forest
Accotink Tributary at Danbury ForestFairfax County
ย 
Ahmad mousa project list
Ahmad mousa   project listAhmad mousa   project list
Ahmad mousa project listAhmad Mousa
ย 
USACE Galveston: Coastal Project Updates - Sharon Manzella Tirpak
USACE Galveston: Coastal Project Updates - Sharon Manzella TirpakUSACE Galveston: Coastal Project Updates - Sharon Manzella Tirpak
USACE Galveston: Coastal Project Updates - Sharon Manzella TirpakTWCA
ย 
Hunting Creek at Fairchild MVCCA-Meeting March 7, 2018
Hunting Creek at Fairchild MVCCA-Meeting March 7, 2018Hunting Creek at Fairchild MVCCA-Meeting March 7, 2018
Hunting Creek at Fairchild MVCCA-Meeting March 7, 2018Fairfax County
ย 
Jeremy kasper-energy-research-in-alaska
Jeremy kasper-energy-research-in-alaskaJeremy kasper-energy-research-in-alaska
Jeremy kasper-energy-research-in-alaskajames hamilton
ย 
Max KroschelResume061715
Max KroschelResume061715Max KroschelResume061715
Max KroschelResume061715Max Kroschel
ย 

Similar to Jamaica Bay Task Force2- 10May22.pdf (20)

Lake Accotink Dredge Public Meeting Combined Presentation July 29 & aug 5...
Lake Accotink Dredge Public Meeting Combined Presentation July 29 & aug 5...Lake Accotink Dredge Public Meeting Combined Presentation July 29 & aug 5...
Lake Accotink Dredge Public Meeting Combined Presentation July 29 & aug 5...
ย 
ACOE Coastal Storm Management Alternative for Jamaica Bay Communities
ACOE Coastal Storm Management Alternative for Jamaica Bay CommunitiesACOE Coastal Storm Management Alternative for Jamaica Bay Communities
ACOE Coastal Storm Management Alternative for Jamaica Bay Communities
ย 
PortsHarborsBeaches_Capabilities_Statement
PortsHarborsBeaches_Capabilities_StatementPortsHarborsBeaches_Capabilities_Statement
PortsHarborsBeaches_Capabilities_Statement
ย 
0837-Petty-WV
0837-Petty-WV0837-Petty-WV
0837-Petty-WV
ย 
Portfolio EP5-Zukerberg
Portfolio EP5-ZukerbergPortfolio EP5-Zukerberg
Portfolio EP5-Zukerberg
ย 
Muskegon Lake Restoration: A Success Story
Muskegon Lake Restoration: A Success StoryMuskegon Lake Restoration: A Success Story
Muskegon Lake Restoration: A Success Story
ย 
Jamaica bay resiliency
Jamaica bay resiliencyJamaica bay resiliency
Jamaica bay resiliency
ย 
Lake Accotink Dredging Public Meeting Presentation December 2020
Lake Accotink Dredging Public Meeting Presentation December 2020Lake Accotink Dredging Public Meeting Presentation December 2020
Lake Accotink Dredging Public Meeting Presentation December 2020
ย 
Long Branch Tributary at Long Branch Falls Park Public Meeting 8-20-2015
Long Branch Tributary at Long Branch Falls Park Public Meeting 8-20-2015Long Branch Tributary at Long Branch Falls Park Public Meeting 8-20-2015
Long Branch Tributary at Long Branch Falls Park Public Meeting 8-20-2015
ย 
Regueroetal_ReEng_Reefs_2015
Regueroetal_ReEng_Reefs_2015Regueroetal_ReEng_Reefs_2015
Regueroetal_ReEng_Reefs_2015
ย 
Orlando 2015
Orlando 2015Orlando 2015
Orlando 2015
ย 
Beach Glass Swana Presen.
Beach Glass Swana Presen.Beach Glass Swana Presen.
Beach Glass Swana Presen.
ย 
NYNJHAT Presentation slides for Jamaica Bay Task Force Meeting 17 Nov 22.pdf
NYNJHAT Presentation slides for Jamaica Bay Task Force Meeting 17 Nov 22.pdfNYNJHAT Presentation slides for Jamaica Bay Task Force Meeting 17 Nov 22.pdf
NYNJHAT Presentation slides for Jamaica Bay Task Force Meeting 17 Nov 22.pdf
ย 
Accotink Tributary at Danbury Forest
Accotink Tributary at Danbury ForestAccotink Tributary at Danbury Forest
Accotink Tributary at Danbury Forest
ย 
Ahmad mousa project list
Ahmad mousa   project listAhmad mousa   project list
Ahmad mousa project list
ย 
USACE Galveston: Coastal Project Updates - Sharon Manzella Tirpak
USACE Galveston: Coastal Project Updates - Sharon Manzella TirpakUSACE Galveston: Coastal Project Updates - Sharon Manzella Tirpak
USACE Galveston: Coastal Project Updates - Sharon Manzella Tirpak
ย 
Hunting Creek at Fairchild MVCCA-Meeting March 7, 2018
Hunting Creek at Fairchild MVCCA-Meeting March 7, 2018Hunting Creek at Fairchild MVCCA-Meeting March 7, 2018
Hunting Creek at Fairchild MVCCA-Meeting March 7, 2018
ย 
Jeremy kasper-energy-research-in-alaska
Jeremy kasper-energy-research-in-alaskaJeremy kasper-energy-research-in-alaska
Jeremy kasper-energy-research-in-alaska
ย 
EdgeW
EdgeWEdgeW
EdgeW
ย 
Max KroschelResume061715
Max KroschelResume061715Max KroschelResume061715
Max KroschelResume061715
ย 

More from ecowatchers

JBTF Nov2023 - JBRPC West Pond Living Shoreline.pdf
JBTF Nov2023 - JBRPC West Pond Living Shoreline.pdfJBTF Nov2023 - JBRPC West Pond Living Shoreline.pdf
JBTF Nov2023 - JBRPC West Pond Living Shoreline.pdfecowatchers
ย 
NYCParks_HookCreekSedimentPlacement_20231130_FINAL.pptx
NYCParks_HookCreekSedimentPlacement_20231130_FINAL.pptxNYCParks_HookCreekSedimentPlacement_20231130_FINAL.pptx
NYCParks_HookCreekSedimentPlacement_20231130_FINAL.pptxecowatchers
ย 
NPS presentation Jamaica Bay Task Force Meeting 2022-11-17.pdf
NPS presentation Jamaica Bay Task Force Meeting 2022-11-17.pdfNPS presentation Jamaica Bay Task Force Meeting 2022-11-17.pdf
NPS presentation Jamaica Bay Task Force Meeting 2022-11-17.pdfecowatchers
ย 
November 17 2022 Jam Bay Task Force.pdf
November 17 2022 Jam Bay Task Force.pdfNovember 17 2022 Jam Bay Task Force.pdf
November 17 2022 Jam Bay Task Force.pdfecowatchers
ย 
Jamaica Bay Task Force_May 2022.pdf
Jamaica Bay Task Force_May 2022.pdfJamaica Bay Task Force_May 2022.pdf
Jamaica Bay Task Force_May 2022.pdfecowatchers
ย 
Spring 2022 Task Force Meeting presentation on Adjacent Sediment Slurry Enric...
Spring 2022 Task Force Meeting presentation on Adjacent Sediment Slurry Enric...Spring 2022 Task Force Meeting presentation on Adjacent Sediment Slurry Enric...
Spring 2022 Task Force Meeting presentation on Adjacent Sediment Slurry Enric...ecowatchers
ย 
Ribbed Mussel Study Status JBTF.pdf
Ribbed Mussel Study Status JBTF.pdfRibbed Mussel Study Status JBTF.pdf
Ribbed Mussel Study Status JBTF.pdfecowatchers
ย 
Jb task force 2021 1103
Jb task force 2021 1103Jb task force 2021 1103
Jb task force 2021 1103ecowatchers
ย 
201130 west pond reduced
201130 west pond reduced201130 west pond reduced
201130 west pond reducedecowatchers
ย 
Jamaica bay ecowatchers task force presentation 12.9.2020
Jamaica bay ecowatchers task force presentation   12.9.2020Jamaica bay ecowatchers task force presentation   12.9.2020
Jamaica bay ecowatchers task force presentation 12.9.2020ecowatchers
ย 
Nyc parks marine debris removal
Nyc parks marine debris removalNyc parks marine debris removal
Nyc parks marine debris removalecowatchers
ย 
Raptor mgmt presentation12 09-2020
Raptor mgmt presentation12 09-2020Raptor mgmt presentation12 09-2020
Raptor mgmt presentation12 09-2020ecowatchers
ย 
20191113 jbfs presentation final
20191113 jbfs presentation final20191113 jbfs presentation final
20191113 jbfs presentation finalecowatchers
ย 
Jamaica Bay Wildlife refuge west pond proposal for protecting the south shore...
Jamaica Bay Wildlife refuge west pond proposal for protecting the south shore...Jamaica Bay Wildlife refuge west pond proposal for protecting the south shore...
Jamaica Bay Wildlife refuge west pond proposal for protecting the south shore...ecowatchers
ย 
Ribbed Mussel ability to remove Nitrogen from water bodies.
Ribbed Mussel ability to remove Nitrogen from water bodies.Ribbed Mussel ability to remove Nitrogen from water bodies.
Ribbed Mussel ability to remove Nitrogen from water bodies.ecowatchers
ย 
NYC DEP update on Ribbed Mussel potential for treating pathogens in water bodies
NYC DEP update on Ribbed Mussel potential for treating pathogens in water bodiesNYC DEP update on Ribbed Mussel potential for treating pathogens in water bodies
NYC DEP update on Ribbed Mussel potential for treating pathogens in water bodiesecowatchers
ย 
Shirley Chisholm State Park-Brooklyn Update on phase two work
Shirley Chisholm State Park-Brooklyn Update on phase two workShirley Chisholm State Park-Brooklyn Update on phase two work
Shirley Chisholm State Park-Brooklyn Update on phase two workecowatchers
ย 
Sunset cove restoration project -update
Sunset cove restoration project -updateSunset cove restoration project -update
Sunset cove restoration project -updateecowatchers
ย 
American Littoral Society Jamaica Bay presentation, 5 9-2019
American Littoral Society Jamaica Bay presentation, 5 9-2019 American Littoral Society Jamaica Bay presentation, 5 9-2019
American Littoral Society Jamaica Bay presentation, 5 9-2019 ecowatchers
ย 
Spring Creek South Update
Spring Creek South UpdateSpring Creek South Update
Spring Creek South Updateecowatchers
ย 

More from ecowatchers (20)

JBTF Nov2023 - JBRPC West Pond Living Shoreline.pdf
JBTF Nov2023 - JBRPC West Pond Living Shoreline.pdfJBTF Nov2023 - JBRPC West Pond Living Shoreline.pdf
JBTF Nov2023 - JBRPC West Pond Living Shoreline.pdf
ย 
NYCParks_HookCreekSedimentPlacement_20231130_FINAL.pptx
NYCParks_HookCreekSedimentPlacement_20231130_FINAL.pptxNYCParks_HookCreekSedimentPlacement_20231130_FINAL.pptx
NYCParks_HookCreekSedimentPlacement_20231130_FINAL.pptx
ย 
NPS presentation Jamaica Bay Task Force Meeting 2022-11-17.pdf
NPS presentation Jamaica Bay Task Force Meeting 2022-11-17.pdfNPS presentation Jamaica Bay Task Force Meeting 2022-11-17.pdf
NPS presentation Jamaica Bay Task Force Meeting 2022-11-17.pdf
ย 
November 17 2022 Jam Bay Task Force.pdf
November 17 2022 Jam Bay Task Force.pdfNovember 17 2022 Jam Bay Task Force.pdf
November 17 2022 Jam Bay Task Force.pdf
ย 
Jamaica Bay Task Force_May 2022.pdf
Jamaica Bay Task Force_May 2022.pdfJamaica Bay Task Force_May 2022.pdf
Jamaica Bay Task Force_May 2022.pdf
ย 
Spring 2022 Task Force Meeting presentation on Adjacent Sediment Slurry Enric...
Spring 2022 Task Force Meeting presentation on Adjacent Sediment Slurry Enric...Spring 2022 Task Force Meeting presentation on Adjacent Sediment Slurry Enric...
Spring 2022 Task Force Meeting presentation on Adjacent Sediment Slurry Enric...
ย 
Ribbed Mussel Study Status JBTF.pdf
Ribbed Mussel Study Status JBTF.pdfRibbed Mussel Study Status JBTF.pdf
Ribbed Mussel Study Status JBTF.pdf
ย 
Jb task force 2021 1103
Jb task force 2021 1103Jb task force 2021 1103
Jb task force 2021 1103
ย 
201130 west pond reduced
201130 west pond reduced201130 west pond reduced
201130 west pond reduced
ย 
Jamaica bay ecowatchers task force presentation 12.9.2020
Jamaica bay ecowatchers task force presentation   12.9.2020Jamaica bay ecowatchers task force presentation   12.9.2020
Jamaica bay ecowatchers task force presentation 12.9.2020
ย 
Nyc parks marine debris removal
Nyc parks marine debris removalNyc parks marine debris removal
Nyc parks marine debris removal
ย 
Raptor mgmt presentation12 09-2020
Raptor mgmt presentation12 09-2020Raptor mgmt presentation12 09-2020
Raptor mgmt presentation12 09-2020
ย 
20191113 jbfs presentation final
20191113 jbfs presentation final20191113 jbfs presentation final
20191113 jbfs presentation final
ย 
Jamaica Bay Wildlife refuge west pond proposal for protecting the south shore...
Jamaica Bay Wildlife refuge west pond proposal for protecting the south shore...Jamaica Bay Wildlife refuge west pond proposal for protecting the south shore...
Jamaica Bay Wildlife refuge west pond proposal for protecting the south shore...
ย 
Ribbed Mussel ability to remove Nitrogen from water bodies.
Ribbed Mussel ability to remove Nitrogen from water bodies.Ribbed Mussel ability to remove Nitrogen from water bodies.
Ribbed Mussel ability to remove Nitrogen from water bodies.
ย 
NYC DEP update on Ribbed Mussel potential for treating pathogens in water bodies
NYC DEP update on Ribbed Mussel potential for treating pathogens in water bodiesNYC DEP update on Ribbed Mussel potential for treating pathogens in water bodies
NYC DEP update on Ribbed Mussel potential for treating pathogens in water bodies
ย 
Shirley Chisholm State Park-Brooklyn Update on phase two work
Shirley Chisholm State Park-Brooklyn Update on phase two workShirley Chisholm State Park-Brooklyn Update on phase two work
Shirley Chisholm State Park-Brooklyn Update on phase two work
ย 
Sunset cove restoration project -update
Sunset cove restoration project -updateSunset cove restoration project -update
Sunset cove restoration project -update
ย 
American Littoral Society Jamaica Bay presentation, 5 9-2019
American Littoral Society Jamaica Bay presentation, 5 9-2019 American Littoral Society Jamaica Bay presentation, 5 9-2019
American Littoral Society Jamaica Bay presentation, 5 9-2019
ย 
Spring Creek South Update
Spring Creek South UpdateSpring Creek South Update
Spring Creek South Update
ย 

Recently uploaded

๐Ÿ’š๐Ÿ˜‹ Mathura Escort Service Call Girls, 9352852248 โ‚น5000 To 25K With AC๐Ÿ’š๐Ÿ˜‹
๐Ÿ’š๐Ÿ˜‹ Mathura Escort Service Call Girls, 9352852248 โ‚น5000 To 25K With AC๐Ÿ’š๐Ÿ˜‹๐Ÿ’š๐Ÿ˜‹ Mathura Escort Service Call Girls, 9352852248 โ‚น5000 To 25K With AC๐Ÿ’š๐Ÿ˜‹
๐Ÿ’š๐Ÿ˜‹ Mathura Escort Service Call Girls, 9352852248 โ‚น5000 To 25K With AC๐Ÿ’š๐Ÿ˜‹nirzagarg
ย 
CSR_Module5_Green Earth Initiative, Tree Planting Day
CSR_Module5_Green Earth Initiative, Tree Planting DayCSR_Module5_Green Earth Initiative, Tree Planting Day
CSR_Module5_Green Earth Initiative, Tree Planting DayGeorgeDiamandis11
ย 
VVIP Pune Call Girls Wagholi WhatSapp Number 8005736733 With Elite Staff And ...
VVIP Pune Call Girls Wagholi WhatSapp Number 8005736733 With Elite Staff And ...VVIP Pune Call Girls Wagholi WhatSapp Number 8005736733 With Elite Staff And ...
VVIP Pune Call Girls Wagholi WhatSapp Number 8005736733 With Elite Staff And ...SUHANI PANDEY
ย 
GENUINE Babe,Call Girls IN Chhatarpur Delhi | +91-8377877756
GENUINE Babe,Call Girls IN Chhatarpur Delhi | +91-8377877756GENUINE Babe,Call Girls IN Chhatarpur Delhi | +91-8377877756
GENUINE Babe,Call Girls IN Chhatarpur Delhi | +91-8377877756dollysharma2066
ย 
VIP Call Girls Valsad 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Valsad 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Valsad 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Valsad 7001035870 Whatsapp Number, 24/07 Bookingdharasingh5698
ย 
Presentation: Farmer-led climate adaptation - Project launch and overview by ...
Presentation: Farmer-led climate adaptation - Project launch and overview by ...Presentation: Farmer-led climate adaptation - Project launch and overview by ...
Presentation: Farmer-led climate adaptation - Project launch and overview by ...AICCRA
ย 
Call Girls in Sakinaka Agency, { 9892124323 } Mumbai Vashi Call Girls Serivce...
Call Girls in Sakinaka Agency, { 9892124323 } Mumbai Vashi Call Girls Serivce...Call Girls in Sakinaka Agency, { 9892124323 } Mumbai Vashi Call Girls Serivce...
Call Girls in Sakinaka Agency, { 9892124323 } Mumbai Vashi Call Girls Serivce...Pooja Nehwal
ย 
RATING SYSTEMS- IGBC, GRIHA, LEED--.pptx
RATING  SYSTEMS- IGBC, GRIHA, LEED--.pptxRATING  SYSTEMS- IGBC, GRIHA, LEED--.pptx
RATING SYSTEMS- IGBC, GRIHA, LEED--.pptxJIT KUMAR GUPTA
ย 
Call Girls Talegaon Dabhade Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Talegaon Dabhade Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Talegaon Dabhade Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Talegaon Dabhade Call Me 7737669865 Budget Friendly No Advance Boo...roncy bisnoi
ย 
Call On 6297143586 Pimpri Chinchwad Call Girls In All Pune 24/7 Provide Call...
Call On 6297143586  Pimpri Chinchwad Call Girls In All Pune 24/7 Provide Call...Call On 6297143586  Pimpri Chinchwad Call Girls In All Pune 24/7 Provide Call...
Call On 6297143586 Pimpri Chinchwad Call Girls In All Pune 24/7 Provide Call...tanu pandey
ย 
VIP Model Call Girls Chakan ( Pune ) Call ON 8005736733 Starting From 5K to 2...
VIP Model Call Girls Chakan ( Pune ) Call ON 8005736733 Starting From 5K to 2...VIP Model Call Girls Chakan ( Pune ) Call ON 8005736733 Starting From 5K to 2...
VIP Model Call Girls Chakan ( Pune ) Call ON 8005736733 Starting From 5K to 2...SUHANI PANDEY
ย 
Call Now โ˜Ž๏ธ๐Ÿ” 9332606886 ๐Ÿ”ย Call Girls โค Service In Muzaffarpur Female Escorts ...
Call Now โ˜Ž๏ธ๐Ÿ” 9332606886 ๐Ÿ”ย Call Girls โค Service In Muzaffarpur Female Escorts ...Call Now โ˜Ž๏ธ๐Ÿ” 9332606886 ๐Ÿ”ย Call Girls โค Service In Muzaffarpur Female Escorts ...
Call Now โ˜Ž๏ธ๐Ÿ” 9332606886 ๐Ÿ”ย Call Girls โค Service In Muzaffarpur Female Escorts ...Anamikakaur10
ย 
VIP Model Call Girls Uruli Kanchan ( Pune ) Call ON 8005736733 Starting From ...
VIP Model Call Girls Uruli Kanchan ( Pune ) Call ON 8005736733 Starting From ...VIP Model Call Girls Uruli Kanchan ( Pune ) Call ON 8005736733 Starting From ...
VIP Model Call Girls Uruli Kanchan ( Pune ) Call ON 8005736733 Starting From ...SUHANI PANDEY
ย 
(NEHA) Call Girls Navi Mumbai Call Now 8250077686 Navi Mumbai Escorts 24x7
(NEHA) Call Girls Navi Mumbai Call Now 8250077686 Navi Mumbai Escorts 24x7(NEHA) Call Girls Navi Mumbai Call Now 8250077686 Navi Mumbai Escorts 24x7
(NEHA) Call Girls Navi Mumbai Call Now 8250077686 Navi Mumbai Escorts 24x7Call Girls in Nagpur High Profile Call Girls
ย 
Alandi Road ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready ...
Alandi Road ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready ...Alandi Road ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready ...
Alandi Road ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready ...tanu pandey
ย 
Call Girls Jejuri Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Jejuri Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Jejuri Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Jejuri Call Me 7737669865 Budget Friendly No Advance Bookingroncy bisnoi
ย 
Plastic Bank Beyond EPR - Sustainability Programs
Plastic Bank Beyond EPR - Sustainability ProgramsPlastic Bank Beyond EPR - Sustainability Programs
Plastic Bank Beyond EPR - Sustainability Programsitadmin50
ย 
Get Premium Attur Layout Call Girls (8005736733) 24x7 Rate 15999 with A/c Roo...
Get Premium Attur Layout Call Girls (8005736733) 24x7 Rate 15999 with A/c Roo...Get Premium Attur Layout Call Girls (8005736733) 24x7 Rate 15999 with A/c Roo...
Get Premium Attur Layout Call Girls (8005736733) 24x7 Rate 15999 with A/c Roo...MOHANI PANDEY
ย 
RA 7942:vThe Philippine Mining Act of 1995
RA 7942:vThe Philippine Mining Act of 1995RA 7942:vThe Philippine Mining Act of 1995
RA 7942:vThe Philippine Mining Act of 1995garthraymundo123
ย 

Recently uploaded (20)

๐Ÿ’š๐Ÿ˜‹ Mathura Escort Service Call Girls, 9352852248 โ‚น5000 To 25K With AC๐Ÿ’š๐Ÿ˜‹
๐Ÿ’š๐Ÿ˜‹ Mathura Escort Service Call Girls, 9352852248 โ‚น5000 To 25K With AC๐Ÿ’š๐Ÿ˜‹๐Ÿ’š๐Ÿ˜‹ Mathura Escort Service Call Girls, 9352852248 โ‚น5000 To 25K With AC๐Ÿ’š๐Ÿ˜‹
๐Ÿ’š๐Ÿ˜‹ Mathura Escort Service Call Girls, 9352852248 โ‚น5000 To 25K With AC๐Ÿ’š๐Ÿ˜‹
ย 
CSR_Module5_Green Earth Initiative, Tree Planting Day
CSR_Module5_Green Earth Initiative, Tree Planting DayCSR_Module5_Green Earth Initiative, Tree Planting Day
CSR_Module5_Green Earth Initiative, Tree Planting Day
ย 
VVIP Pune Call Girls Wagholi WhatSapp Number 8005736733 With Elite Staff And ...
VVIP Pune Call Girls Wagholi WhatSapp Number 8005736733 With Elite Staff And ...VVIP Pune Call Girls Wagholi WhatSapp Number 8005736733 With Elite Staff And ...
VVIP Pune Call Girls Wagholi WhatSapp Number 8005736733 With Elite Staff And ...
ย 
GENUINE Babe,Call Girls IN Chhatarpur Delhi | +91-8377877756
GENUINE Babe,Call Girls IN Chhatarpur Delhi | +91-8377877756GENUINE Babe,Call Girls IN Chhatarpur Delhi | +91-8377877756
GENUINE Babe,Call Girls IN Chhatarpur Delhi | +91-8377877756
ย 
VIP Call Girls Valsad 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Valsad 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Valsad 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Valsad 7001035870 Whatsapp Number, 24/07 Booking
ย 
Presentation: Farmer-led climate adaptation - Project launch and overview by ...
Presentation: Farmer-led climate adaptation - Project launch and overview by ...Presentation: Farmer-led climate adaptation - Project launch and overview by ...
Presentation: Farmer-led climate adaptation - Project launch and overview by ...
ย 
Call Girls in Sakinaka Agency, { 9892124323 } Mumbai Vashi Call Girls Serivce...
Call Girls in Sakinaka Agency, { 9892124323 } Mumbai Vashi Call Girls Serivce...Call Girls in Sakinaka Agency, { 9892124323 } Mumbai Vashi Call Girls Serivce...
Call Girls in Sakinaka Agency, { 9892124323 } Mumbai Vashi Call Girls Serivce...
ย 
RATING SYSTEMS- IGBC, GRIHA, LEED--.pptx
RATING  SYSTEMS- IGBC, GRIHA, LEED--.pptxRATING  SYSTEMS- IGBC, GRIHA, LEED--.pptx
RATING SYSTEMS- IGBC, GRIHA, LEED--.pptx
ย 
Call Girls Talegaon Dabhade Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Talegaon Dabhade Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Talegaon Dabhade Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Talegaon Dabhade Call Me 7737669865 Budget Friendly No Advance Boo...
ย 
Call On 6297143586 Pimpri Chinchwad Call Girls In All Pune 24/7 Provide Call...
Call On 6297143586  Pimpri Chinchwad Call Girls In All Pune 24/7 Provide Call...Call On 6297143586  Pimpri Chinchwad Call Girls In All Pune 24/7 Provide Call...
Call On 6297143586 Pimpri Chinchwad Call Girls In All Pune 24/7 Provide Call...
ย 
VIP Model Call Girls Chakan ( Pune ) Call ON 8005736733 Starting From 5K to 2...
VIP Model Call Girls Chakan ( Pune ) Call ON 8005736733 Starting From 5K to 2...VIP Model Call Girls Chakan ( Pune ) Call ON 8005736733 Starting From 5K to 2...
VIP Model Call Girls Chakan ( Pune ) Call ON 8005736733 Starting From 5K to 2...
ย 
Call Now โ˜Ž๏ธ๐Ÿ” 9332606886 ๐Ÿ”ย Call Girls โค Service In Muzaffarpur Female Escorts ...
Call Now โ˜Ž๏ธ๐Ÿ” 9332606886 ๐Ÿ”ย Call Girls โค Service In Muzaffarpur Female Escorts ...Call Now โ˜Ž๏ธ๐Ÿ” 9332606886 ๐Ÿ”ย Call Girls โค Service In Muzaffarpur Female Escorts ...
Call Now โ˜Ž๏ธ๐Ÿ” 9332606886 ๐Ÿ”ย Call Girls โค Service In Muzaffarpur Female Escorts ...
ย 
VIP Model Call Girls Uruli Kanchan ( Pune ) Call ON 8005736733 Starting From ...
VIP Model Call Girls Uruli Kanchan ( Pune ) Call ON 8005736733 Starting From ...VIP Model Call Girls Uruli Kanchan ( Pune ) Call ON 8005736733 Starting From ...
VIP Model Call Girls Uruli Kanchan ( Pune ) Call ON 8005736733 Starting From ...
ย 
(NEHA) Call Girls Navi Mumbai Call Now 8250077686 Navi Mumbai Escorts 24x7
(NEHA) Call Girls Navi Mumbai Call Now 8250077686 Navi Mumbai Escorts 24x7(NEHA) Call Girls Navi Mumbai Call Now 8250077686 Navi Mumbai Escorts 24x7
(NEHA) Call Girls Navi Mumbai Call Now 8250077686 Navi Mumbai Escorts 24x7
ย 
Green Marketing
Green MarketingGreen Marketing
Green Marketing
ย 
Alandi Road ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready ...
Alandi Road ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready ...Alandi Road ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready ...
Alandi Road ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready ...
ย 
Call Girls Jejuri Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Jejuri Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Jejuri Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Jejuri Call Me 7737669865 Budget Friendly No Advance Booking
ย 
Plastic Bank Beyond EPR - Sustainability Programs
Plastic Bank Beyond EPR - Sustainability ProgramsPlastic Bank Beyond EPR - Sustainability Programs
Plastic Bank Beyond EPR - Sustainability Programs
ย 
Get Premium Attur Layout Call Girls (8005736733) 24x7 Rate 15999 with A/c Roo...
Get Premium Attur Layout Call Girls (8005736733) 24x7 Rate 15999 with A/c Roo...Get Premium Attur Layout Call Girls (8005736733) 24x7 Rate 15999 with A/c Roo...
Get Premium Attur Layout Call Girls (8005736733) 24x7 Rate 15999 with A/c Roo...
ย 
RA 7942:vThe Philippine Mining Act of 1995
RA 7942:vThe Philippine Mining Act of 1995RA 7942:vThe Philippine Mining Act of 1995
RA 7942:vThe Philippine Mining Act of 1995
ย 

Jamaica Bay Task Force2- 10May22.pdf

  • 1. 217 217 217 200 200 200 255 255 255 0 0 0 163 163 163 131 132 122 239 65 53 110 135 120 112 92 56 62 102 130 102 56 48 130 120 111 237 237 237 80 119 27 252 174 .59 โ€œThe views, opinions and findings contained in this report are those of the authors(s) and should not be construed as an official Department of the Army position, policy or decision, unless so designated by other official documentation.โ€ HUDSON RARITAN ESTUARY ECOSYSTEM RESTORATION โ€“ JAMAICA BAY UPDATE JAMAICA BAY TASK FORCE MEETING LISA BARON PROJECT MANAGER, CIVIL WORKS NEW YORK DISTRICT MAY 10, 2022 1 File Name
  • 2. AGENDA โ€ข Past Marsh Island Restoration Success โ€ข HRE Ecosystem Restoration ๏ƒผ Ongoing Projects including Stony Creek Marsh Island ๏ƒผ Future Jamaica Bay Marsh Islands and Perimeter Sites โ€ข Spring Creek North Ecosystem Restoration Project โ€ข Spring Creek South (Howard Beach) Multi- Purpose Feasibility Study File Name 2
  • 3. JAMAICA BAY MARSH ISLAND RESTORATION- PAST SUCCESS Elders East Elders West Yellow Bar John F. Kennedy Airport JoCo Yellow Bar - 2012 (47 acres) Elders East- 2007 (40 acres) Elders East- 2011 โ€ข >2000 acres of Marsh Islands have been lost since 1924 โ€ข Restored 160 acres โ€ข HRE Recommendation of 170 acres Elders Center Duck Point Stony Creek Pumpkin Patch (East & West) Elders West- 20010 (43 acres) Black Wall and Rulers Bar (30 acres) Black Wall and Rulers Bar
  • 4. JAMAICA BAY MARSH ISLANDS CONSTRUCTION 4
  • 5. BUILDING THE ISLAND - GRADING 5
  • 6. VEGETATING THE ISLAND โ€“ TRANSPLANTING 6
  • 7. July 2010 October 2006 Photo courtesy of Galvin Brothers, Inc. October 2006 RESTORATION OF ELDERS EAST
  • 10. BLACK WALL and RULERS BAR PRE-RESTORATION
  • 11. YELLOW BAR, BLACK WALL AND RULERS BAR MARSH ISLAND RESTORATION 2012 11 Yellow Bar: 46 acres, $17.3M Black Wall: 20 acres, $2.1M 2007 Rulers Bar: 10 acres, $1.311M Sponsors: NYSDEC, NYCDEP, PANYNJ, NPS
  • 12. 12 Yellow Bar: 44 acres, $17.3M Black Wall: 20 acres, $2.1M 2007 Rulers Bar: 10 acres, $1.311M Sponsors: NYSDEC Planting Effort at Black Wall and Rulers Bar (July 2013): Jamaica Bay EcoWatchers, American Littoral Society, Jamaica Bay Guardian and Community Volunteers
  • 13. HRE RESTORATION PROGRAM โ€ข Chiefโ€™s Report (May 2020) recommended 20 individual projects that will restore a mosaic of 621 acres of habitat including: ๏ƒผ 381 acres of estuarine wetlands (w/ 6 miles of tidal channels), 50 acres of freshwater riverine wetlands, 27 acres of coastal and maritime forest, 39 acres of shallow water habitat and 52 acres of oyster habitat; ๏ƒผ Installation of 2 fish ladders (or potential removal) and modification of 3 weirs modified to improve fish passage (24 miles) on the Bronx River. ๏ƒผ 1.6 miles of stream bank and 72 acres of stream bed and channel restoration. โ€ข Construction authorized in WRDA 2020. Jamaica Bay 6,8 1,2,5 1,2 1,2 6,7,8 4 4 All Marsh Islands: 1,2,5 1,2,3 1,2,3 6,7,8 6,7,8,9 8,9 1,3,5 1. Estuarine Wetlands 2. Tidal Channel Restoration 3. Maritime Forest 4. Oyster Reefs 5. Shallow Water Habitat 6. Freshwater Wetlands 7. Streambank Restoration 8. Bed Restoration 9. Fishway 10.Sediment Forebay 6,8 1,2,5 1,2 6,8, 10 Fully funded cost: $624,772,000 (FY22)
  • 14. HRE ECOSYSTEM RESTORATION Pre-Construction Engineering Design (PED) Projects โ€ข $1,200,000 included in the 2022 Consolidated Appropriations Act โ€ข $25,978,000 in the Addendum to 2020 Infrastructure Investment and Jobs Act to complete PED for first 4 HRE Projects (5 sites) and CONSTRUCT STONY CREEK MARSH ISLAND! โ€ข Local Sponsors: NYCDEP, NYC Parks โ€ข Project Partners: NY/NJ Baykeeper (Oysters)
  • 15. 15 STONY CREEK MARSH ISLAND PLANNED ACTIVITIES โ€ข Execute Design Agreement with NYCDEP (by July 1, 2022) โ€ข Project Management Plan (ongoing) โ€ข Field Investigations: ๏ƒผ Bathymetric/Topographic Surveys (2022/2023) ๏ƒผ Hydrodynamic Data Collection โ€“ Tide Gauges and Modeling (2023) ๏ƒผ Bio-Benchmarking (2023) ๏ƒผ Wetland Delineation (2023) โ€ข Plans and Specifications (P&S): Designs, Quantities, Cost Estimates ๏ƒผ 30% P&S and Value Engineering Study (2023) ๏ƒผ 60% P&S (2023/2024) ๏ƒผ 90% P&S (2024) ๏ƒผ 100% P&S (2024/2025) โ€ข Coordination with Operations Division for dredging contract (~155,000 CYD) โ€ข Coordination with NPS throughout โ€“ Special Use Permit/MOU โ€ข Permitting โ€“ Water Quality Certificate โ€ข Biddability, Constructability, Operability, and Environmental Reviews (all design iterations) and Agency Technical Review (90% P&S) โ€ข Execute Project Partnership Agreement for Construction (2024) โ€ข Ready to Advertise (early 2025) โ€ข Construction (2025)
  • 16. 16 HRE Restoration Sites 327 acres of habitat restoration: - 206 acres of marsh islands - 121 acres along perimeter Local Sponsors: NYCDEP and NYSDEC (Dead Horse Bay) in partnership with NPS 155,000 CYD 62 acres 41 acres 80 acres 215,000 CYD 40 acres 285,000 CYD 29 acres 328,000 CYD 24 acres 352,000 CYD 29 acres 10 acres
  • 17. 17 https://www.nan.usace.army.mil/Portals/37/docs/Environmental/HRE/HRE%20Final%20Cost%20Appendi x%20I_20April2020.pdf?ver=2020-05-29-085232-857 โ€“ page I-24 CONSTRUCTION SCHEDULE - SEQUENCING Timing dependent on appropriation of funds for USACE, NYCDEP and NYSDEC January 2025
  • 18. Spring Creek North Ecosystem Restoration (Continuing Authorities Program) โ€ข Local Sponsor: NYC Parks with additional funding from NYCDEP โ€ข Total of $7.37M included in the Infrastructure Investment and Jobs Act โ€ข Funds to be used to complete design phase and initiate implementation โ€ข Restoration of 47-acres including: ๏ƒผ 18.3 acres of wetlands ๏ƒผ 29 acres of maritime uplands โ€ข Restoration through excavating and recontouring uplands to intertidal elevations, removing invasives species and replanting as well as restoring existing degraded wetlands with Thin Layer Placement techniques โ€ข Construction is planned for 2023
  • 19. Spring Creek South (Howard Beach) Multi-purpose Feasibility Study Ecosystem Restoration and Coastal Storm Risk Management (CSRM) โ€ข WRDA 2020 - expedite completion of multi-purpose feasibility study for โ€œecosystem restoration and hurricane and storm damage reductionโ€. โ€ข $1.2M included in the Infrastructure Bill and $500,000 in the FY22 Bill to complete the Feasibility Study in partnership with NYSDEC and NPS โ€ข Need to execute Feasibility Cost Share Agreement with NYSDEC for $3,000,000/3 years. โ€ข Project could include coastal restoration of 237 acres of degraded habitat including tidal marsh, freshwater wetlands, scrub/shrub wetlands, adjacent upland habitats, earthen berm with additional CSRM measures (such as tide gates in Shellbank and Hawtree Basins). โ€ข Build upon the foundation from information and investments already made on prior studies, investigations, and design efforts (including HRE, Jamaica Bay Feasibility Study, East Rockaway Reformulation, NY Rising, NYSDEC/FEMA Hazard Mitigation Grant Program and NPS Remedial Investigation). โ€ข This study, in coordination with the NY/NJ Harbor and Tributaries Study, will provide an opportunity to recommend natural and nature-based features as well as coastal storm risk management measures. These measures will reduce risk to flooding and provide environmental benefits to the community and Jamaica Bayโ€”resulting in a more resilient and sustainable shoreline and region.
  • 20. TENTATIVE OVERALL SCHEDULE JAMAICA BAY RESTORATION Project 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2032 2033 2034 2035 Spring Creek North HRE-Stony Creek Marsh Island Spring Creek South Feasibility Study HRE-Fresh Creek HRE-Duck Point Marsh Island HRE-Elders Center Marsh Island HRE-Pumpkin Patch West Marsh Island HRE- Dead Horse Bay HRE-Pumpkin Patch East Marsh Island Feasibility Study Pre-Construction Engineering and Design Construction Above schedule dependent upon funding and execution of Design Agreements and Project Partnership Agreements Monitoring and Adaptive Management 20 All Funding in-hand All Funding in-hand All Funding in-hand for FS Requires appropriations for design and construction for remaining sites Requires construction authorization and appropriations for design and construction