3. CONTENTS
PROJECT OVERVIEW
PROJECT COVERD AREA
PROJECT DIRECT COST/SQ.M IN DIFFERENT TYPE OF
VILLAS
PLANED AND ACTUAL CASH FLOW WITH S-CURVE AND
HISTOGRAME
PLANED AND ACTUAL MAN POWER HISTOGRAME AND S-
CURVE
PLANED AND ACTUAL MACHINERY REQUIRMENTS WITH
S-CURVE AND HISTOGRAME.
MANPOWER PRODUCTIVITY COMPARISION BEWEEN
RADIC WORKERS AND SUBCONTRACTRS WORKERS
BASE LINE PROGRAME
TARGETD SECHEDULE
6/6/2023 3
4. PROJECT OVERVIEW
THE PROJECTS INCLUDES THE CONSTRUCTION
OF 2200 VILLAS OF THREE ,FOUR AND FIVE BED
ROOMS RESPECTIVELY ,
THE DETAILS OF NUMBER OF VILLAS OF EACH
TYPE IS AS BELOW
6/6/2023 4
SR.NO VILLA TYPE NUMBER OF
VILLAS
1 3 BED ROOM 666
2 4 BED ROOM 726
3 5 BED ROOM 808
5. PROJECT COVERD AREA
TOTAL COVERD AREA OF THE PROJECT IS
591695 SQUARE METERS
THE DETAILS OF COVERD AREA PER TYPE OF
VILLA IS AS BELOW
6/6/2023 5
SR.NO TYPE OF VILLA COVERD AREA
(SQ.M)
1 3 BED ROOM 228.657
2 4 BED ROOM 276.123
3 5 BED ROOM 295.983
6. DIRECT COST PER SQUARE METER
FOR 3 BED ROOM VILLAS
6/6/2023 6
THE DIRECT COST OF 3 BED ROOM VILLAS PER
SQUARE METER (FOR BARKA-2 SITE ) IS 166.56
R.O
THE SUMMRY SHEET FOR COSTING ANALYSIS IS
AS
New folder (2)3 bed room cost.xlsx
7. DIRECT COST PER SQUARE METER
FOR 5 BED ROOM VILLAS
THE DIRECT COST OF 5 BED ROOM VILLAS PER
SQUARE METER (AT BARKA-2 SITE) IS 152.45 R.O
THE SUMMRY SHEET FOR COSTING ANALYSIS IS
AS
New folder (2)5 bed room cost.xlsx
6/6/2023 7
8. DIRECT COST PER SQUARE METER
FOR 4 BED ROOM VILLAS
THE DIRECT COST OF 4 BED ROOM VILLAS PER
SQUARE METER (AT BARKA -2 SITE) IS 160.52
R.O
THE SUMMRY SHEET FOR COSTING ANALYSIS IS
AS
New folder (2)4 bed room cost.xlsx
6/6/2023 8
9. PLANNED AND ACTUAL CASH
FLOW ,S-CURVE & HISTOGRAME
THE DETAILS OF PLANNED AND CASH FLOW
WITH S CURVE & HISTOGRAME IS AS
New folder (2)s-cuves and histograme final1.xlsx
6/6/2023 9
10. PLANED AND ACTUAL MANPOWER
AND HISTOGRAME
THE DETAILS OF PLANED AND ACTUAL
MANPOWER ,S-CURVE AND HISTOGRAME ARE AS
New folder (2)MANPOWER COMPARISON111.xlsx
6/6/2023 10
11. PLANED AND ACTUAL MACHINERY
REQUIRED WITH S-CURVE AND
HISTOGRAME
THE DETAILS OF PLANED AND ACTUAL
MACHINERY REQUIRED WITH S-CURVE AND
HISTOGRAME ARE
New folder (2)MACHINERY 1111.xlsx
6/6/2023 11
12. MANPOWER PRODUCTIVITY
COMPARISION BEWEEN RADIC
WORKERS AND SUBCONTRACTRS
WORKERS
GENRALLY THE PRODUCTIVITY OF THE RADIC
WORKERS AND SUBCONTRACTOR IS MATCHING IN
ALL THE ACTIVITIES HOWEVER IN BLOCK WORK THE
PRODUCTIVITY OF RADIC WORKERS IS LOWER AND
INCESTIVE SCHEME HAS BEEN LAUNCHED TO
INCREASE THE PRODUCTIVITY OF OUR WORKERS ,
THE DETAILS ARE AS
New folder (2)MANPOWER COMPARISON111.xlsx
6/6/2023 12