This manual is intended to serve as a guideline for those interested in planning,
financing, managing or executing soil improvement and ground modification projects,
such as building hard driving surfaces using copolymers as particle binders. One of the
most common applications when using polymers to harden soil and rock mix, is to build
hard driving surfaces. Every project where a structure of any kind must be built on the
ground (soil) must follow certain rules, for example the expected loads must be
supported without ground failure. While these rules are not inherently complicated, it is
imperative that they are well understood before proceeding with a project.
PolymerPaving.com
POLYMERPAVING.COM 1
Prologue
Nothing is more important when engaging in building roads than a clear understanding
of soil improvement and ground modification techniques. Fortunately, this knowledge
is easy to acquire and the fundamentals are easy to understand. I hope you can use this
short introduction as a springboard to build your own library on the subject and continue
to learn in depth about the rules of working with soils. Having this knowledge, and with it
the ability to spot and avoid problems, will help you deliver many successful projects,
and give you much satisfaction in your professional career. It is very important that you
request on site help from someone experienced with polymer paving on your projects as
you start, or that you work with experienced geotechnical engineers. Skipping the proper
expertise is not the place to save money. The savings is inherent to the process and it
comes from the reduced logistics when possible, depending on the situation.
Soil Considerations
When a site is selected for raising a structure, such as a road or a building, special
consideration must be given to the ground's ability to support and respond to the load
that will be imposed upon it. This knowledge generally falls in the domain of
geotechnical engineers, and much of what you need to know to work with polymers is
PolymerPaving.com
POLYMERPAVING.COM 2
basic soil behavior knowledge. Over time, a number of soil behaviors and responses
has been observed, which are now well understood by civil engineers. These soil
behaviors occur in response to man-made loads or to other natural / environmental
factors. Before raising any structure on soil / with soil / made of soil, we should gain a
basic understanding of how to best prepare a work site, select an aggregate, and
conduct a job by minimizing or counteracting possible negative soil behavior in
accordance with the load requirements and guidelines of each project.
PolymerPaving.com
POLYMERPAVING.COM 3
Driving Surface - Assorted Size Particles
One of the quickest ways to raise the likelihood of success in any paving project, is to
ensure the particle mix has the proper gradation to interlock during compaction. The
ratio of the various sizes of soil particles determines the suitability and effectiveness of
the soil in a weight bearing application. The best soils for supporting weight are made of
a mixture of different size particles.
Sufficient Fine Particles and Mixing
If your soil has an adequate mix of particles of different sizes, then your next concern is
ensuring you have sufficient fine particles to cover all the spaces between the larger
rocks so that the mix of water and polymer, when thoroughly mixed, will not flush
PolymerPaving.com
POLYMERPAVING.COM 4
through the rocks to the bottom, but rather remain suspended well mixed in the well-
graded aggregate with the help of these fine particles (allow water surface tension), and
provide lubrication to the compaction process, and then later harden into place in
between the rocks, locking all the individual rocks into place, for a solid and long lasting
hard driving surface.
Preparing a Road Base
Jusl like a building needs a proper foundation, a proper road requires a road base. At a
minimum, if working on top of excellent soil, the soil on which you build the road (the
subgrade, the lowest layer in the picture) needs to be well compacted. If certain soil
weaknesses are to be expected, a base layer should be added, preferably made of
larger rocks. If you separate the subgrade (native compacted soil) and base layer (large
PolymerPaving.com
POLYMERPAVING.COM 5
rocks) with a layer of geofiber (thin, light color in the picture), it will prevent "pumping".
The water table will be able to raise and lower through the larger base rocks (the
thickest middle layer in the picture) without driving subgrade sediment into the road
structure. An additional low cost measure to compensate for a weak subgrade is to
encase the base layer (larger rocks) into a geocell grid (height of geocell you order must
match the estimated height of this layer). This additional support creates a matrix that
has been proven to provide excellent road performance even on some of the weakest
subgrades. Adding geosynthetics (geocell, geogrid, geofiber, gabion mesh, etc) to your
project ensures substantially superior performance and longevity at low cost.
PolymerPaving.com
POLYMERPAVING.COM 6
Polymer Considerations
Considering the number of variables you need to streamline in order to get your soil to
play nice, we firmly believe that it would be smart to avoid additional concerns or doubts
PolymerPaving.com
POLYMERPAVING.COM 7
about the performance of your polymer. That is why PolymerPaving.com offers you the
most suitable polymer that you can possibly find, at a competitive price. When you use
the KompaFlex MX formula, you can rest assured you are already using a product that
will give you top notch repeatable performance time after time. Having the peace of
mind that comes with using the best product, frees you to focus on ground
improvement methods to bring your project to the desired performance standards. I
speak from experience when I tell you that if you get caught between trying to do ground
improvement while still having doubts about the performance of the binder, you will
never finish a project. So do yourself "a solid" and start with KompaFlex MX, and enjoy
the peace of mind that you already selected the best possible polymer, and the freedom
of focusing strictly on ground improvement, which is what we will discuss for the
remainder of this manual.
Polymer Mix-In Methods
The best way to achieve a perfect mixing of aggregate and polymer is by pre-mixing
(image 2). However, when the size of the job makes pre-mixing too slow, in order to
PolymerPaving.com
POLYMERPAVING.COM 8
work faster you can also do the following 4 step procedure: apply aggregate (soil or rock
mix) and spread to 1 inch thick (2-3 cm); Use a spraybar to apply the proper amount of
liquid (water and polymer in the correct ratio) to reach optimum moisture (image 1).
Then immediately mix the liquid into the aggregate using a scarifier or power rake
(image 3). Repeat this process (add soil, spread, spray, scar/mix) until the desired road
surface thickness is achieved, then grade the surface to the correct angles, compact,
and allow it to cure. Follow-up with a sealing coat, regardless of the method used. After
8-24 hours, clean remaining debris (loose rock and dust) from the surface with a power
broom, and apply a second and final sealer coat to the surface.
Another fast method is to use a reclaimer connected to a water tank truck preloaded
with the water and polymer mix; this combination vehicle can wet and scar/mix the soil
at the same time while advancing without the need to stop, except to reload the tank.
Optimum Moisture Content is a humidity level that ensures all particles will receive
polymer treatment, and compaction is well lubricated. If you see liquid on the compactor
wheel or puddles, you have exceeded OMC. Never work below OMC. Exceeding it a
little is not critical, but exceeding it by a lot can reduce ability to achieve high
compaction. Try to make a ball in your hand with the mixed soil; if it crumbles in your
hand it is too dry. If you have liquid seeping through your fingers you are applying too
much liquid. When it holds shape without excess liquid showing, it is perfect for
compaction.
PolymerPaving.com
POLYMERPAVING.COM 9
"Poor" Soil Contingencies
A soil is considered "poor" if it has been determined or tested to have inadequate or
insufficient engineering characteristics to meet the minimum requirements of the
PolymerPaving.com
POLYMERPAVING.COM 10
application. Another term commonly used is "marginal" and it applies when a soil comes
very close to meeting these requirements but doesn't quite make the cut. Here are
common methods for approaching these situations:
• Excavate the "poor" soil and replace it with good aggregate.
• Redesign the project to be able to work with the poor soil (for example reinforce with
geocell or a similar mechanical reinforcement).
• Modify the soil through soil remediation methods (mixing with other available soils / rocks,
mechanical or chemical, etc).
• Abandon the project - this approach is selected when you can pick a more suitable
alternative location, or when the cost of fixing the soil insufficiencies exceeds the
allocated budget.
PolymerPaving.com
POLYMERPAVING.COM 11
Soil Type Classification by Particle Size
1. Gravel
2. Sand
3. Silt
4. Clay
A "sieve analysis" is a process where a given quantity of soil is passed through a certain
size of mesh to see how much passes and how much remains, determining whether a
soil has a "variety" or a "uniformity" of particle sizes. Generally speaking, soils with a
variety of particle sizes are called "well-graded" and are desirable for their ability to
be cohesive and to compact well. Soils with mostly uniform particle size do not have
good cohesion or compaction characteristics and should be avoided or modified.
Crushed rock (angular) is desirable in the mix. Round particles (river rock, beach sand)
are to be avoided; they may pass for "acceptable" when paving with asphalt because it
is a full ring aromatic, but round particles will not work when paving with polymer as your
binder because there isn't enough surface in contact with the particles surrounding it.
PolymerPaving.com
POLYMERPAVING.COM 12
Shear Strength
Soil is different from other engineering materials because it tends to fail in shear
rather than from direct tension or compression. With this fact in mind, imagine how much
stronger and resilient to shear forces the soil on the left is (compacted, mixed size [well
graded], interlocked, angular rocks) compared to the soil on the right (silt / clay).
Foundation: Bearing Capacity & Slope Stability
Nothing is more important or critical to success than a strong foundation, whether
you construct a road or a building. This becomes particularly important when the
foundation soil (subgrade) is poor or marginal. When the soil and the climate are
optimal, you can throw a road surface right on top of a good soil compaction without
problems. Many roads in Arizona and California are built just like that and they perform
PolymerPaving.com
POLYMERPAVING.COM 13
to acceptable levels for the desired lifespan. These regions rarely see bad weather or
rain, or the deleterious effects of water penetration or frost heave. Building a road in
most other regions require a properly designed foundation to compensate for the natural
forces that work against you. For instance many tropical areas see non-stop rain for six
months out of the year. In such an instance, a large portion of your effort and budget
should be aimed at effective drainage and building the road above the water table.
When you work in muddy or volcanic silt (such as in most of Southeastern Europe) you
need to explain to your beneficiaries the importance of building roads the same way they
build their railroads (with a solid crushed rock base that allows for water drainage and
frost heave), if they want them to last as long. You should seek additional reading on
"shallow foundation design" to understand bearing capacity failure. You can imagine
the risk of slope stability failure when you think that every few square feet of your
compacted pavement surface weighs tons by itself, and there are enormous natural
shear pressures acting on a slope, especially when the pavement structure is imbibed
with water molecules in between the soil particles (a very important phenomenon that is
worth exploring in detail, to have it well understood), and subjected to additional traffic
weight. That is why we strongly recommend the use of geosynthetic materials for
reinforcement, not as a luxury, but as a way to raise project longevity and to prevent
catastrophic failure due to unforseen events (bad winter, floods, earthquakes,
liquefaction, etc). No other materials offer a better price to performance ratio for
enhancing the desirable characteristics of a road and/or road base (and also for other
soil projects - embankments, overpasses, etc).
PolymerPaving.com
POLYMERPAVING.COM 14
PolymerPaving.com
POLYMERPAVING.COM 15
Soil Densification and Consolidation
Soil densification is a process by which the air pockets are removed from soil through
compaction. Soil consolidation is a process by which water is removed from soil. There
is sufficient technology available today to literally be able to say that "no soil is
unsuitable" if you have the budget, the equipment, and use the right methods to fix it, or
to compensate for the respective defficiencies.
Types of Compactors
There are various types of compactors available, each designed for specific tasks, and
some are more suitable than others for specific jobs. It is important to know what kind of
compactor to use depending on your soil type and the desired end result which you are
PolymerPaving.com
POLYMERPAVING.COM 16
trying to achieve. Different soil types will present diverse characteristics that will affect
the soil improvement decisions you make.
Smooth Drum Rollers: a static load roller used for compaction of soils and asphalts, they
provide even weight distribution over the width of the roller and a smooth finished
surface. Also good for "proof rolling" during base preparation (to identify soft spots that
need reinforcement).
Pneumatic (rubber tire) rolles: these are engineered to apply very high static loads to a
wide variety of soils, pavements, bases and subgrades. They are even better suited at
finding soft spots, particularly because individual tires have the ability to move up and
down a small distance independently.
Combination rollers: easily identifiable as having both a steel drum and a set of
pneumatic roller wheels, with the ability to use either.
Vibratory rollers: they look similar to static rollers, with the ability to provide impact and
vibration to the soil beneath. If you have granular soils (poor cohesion aggregate) a
vibratory roller will help overcome the frictional resistance and achieve better
compaction.
Sheepsfoot / Padfoot / Wedgefoot rollers can apply very high static loads by
concentrating extreme weight on a small contact surface. These are ideal for breaking
hard dry boulders inherent in clay, silt and other cohesive soils, and in this way allowing
high and uniform compaction.
PolymerPaving.com
POLYMERPAVING.COM 17
Weight and Number of Passes
Although mathematically you should get the same result by adding the weight between
the number of passes, field experience shows that if you don't get the desired
compaction after 5-7 passes, you should perhaps switch to a heavier compactor. One
exception to this rule may be saturated sands, which have shown to improve up to 15-20
passes. However, since one of the "commandments" of working with polymer is to never
use sands or other round particles, this detail is irrelevant in our context.
PolymerPaving.com
POLYMERPAVING.COM 18
Requesting a Laboratory Test
So you are interested in polymer paving, perhaps because it is eco-friendly, or because
it is affordable or maybe because it is easy to complete and maintain. Perhaps it is for a
combination of reasons, or perhaps someone asked you to look into it. Many of the
variables you need to determine, including the suitability of a soil, can be easily and
inexpensively resolved by sending a soil sample and a small fee to our laboratory, where
we can test your soil for you and provide you with a report of your general situation. This
way you have a much better idea which approach / method / procedures we would
recommend as the most suitable for your particular project.
PolymerPaving.com
POLYMERPAVING.COM 19
Conclusions
Building an eco-friendly road with in-situ soil and polymer binder is really a process of
self-development, of becoming really good at soil improvement and ground modification
PolymerPaving.com
POLYMERPAVING.COM 20
procedures. Clean, affordable, long-lasting roads are just a result of accumulating that
knowledge and experience. I hope this brief guide served to introduce you to (or to
remind you of) some of the basics of sound soil engineering. Success in polymer paving
only requires a dilligence in following these proven and time tested principles. Soil
improvement methods are generally applicable in almost any other type of construction,
not only road building. We look forward to working with you.
PolymerPaving.com is a division of Option Quest LLC, which manages the following
properties:
• www.polymerpaving.com
• www.greenroadbuilder.com
• www.optionquest.com
• www.incentiveserver.com
• www.responsiveglass.com
• www.language-queen.com
• www.law-register.com
• www.mobileactivator.com
PolymerPaving.com
POLYMERPAVING.COM 21

More Related Content

What's hot

Soil stab use of-new.ppt dr msa edusat.ppt rev 1
Soil stab use of-new.ppt dr msa edusat.ppt rev 1Soil stab use of-new.ppt dr msa edusat.ppt rev 1
Soil stab use of-new.ppt dr msa edusat.ppt rev 1imtheking2088
 
Ground improvement techniques
Ground improvement techniquesGround improvement techniques
Ground improvement techniquesEsri India
 
Cement stabilisation of soil.pptx22
Cement stabilisation of soil.pptx22Cement stabilisation of soil.pptx22
Cement stabilisation of soil.pptx22ashok yadav
 
Soil stabilisation (1)
Soil stabilisation (1)Soil stabilisation (1)
Soil stabilisation (1)Safiullah Khan
 
Ground improvement technioques for high ways
Ground improvement technioques for high waysGround improvement technioques for high ways
Ground improvement technioques for high waysAMIT SHIDURKAR
 
Subgrade Stabilization: Materials & Methods
Subgrade Stabilization: Materials & MethodsSubgrade Stabilization: Materials & Methods
Subgrade Stabilization: Materials & MethodsJill Reeves
 
Soils stabilization jaffna center
Soils stabilization jaffna centerSoils stabilization jaffna center
Soils stabilization jaffna centerVeluppillai Mohan
 
Soil stabilisation clg
Soil stabilisation clg Soil stabilisation clg
Soil stabilisation clg Prabhat Sharma
 
SOIL CEMENT BRICK WITH FLY ASH
SOIL CEMENT BRICK WITH FLY ASH  SOIL CEMENT BRICK WITH FLY ASH
SOIL CEMENT BRICK WITH FLY ASH Anup Kude
 
Geotextile fo soil stabilization
Geotextile fo soil stabilizationGeotextile fo soil stabilization
Geotextile fo soil stabilizationAglaia Connect
 
Deep compaction techniques
Deep compaction techniquesDeep compaction techniques
Deep compaction techniquesJNTUK
 
Permeation grouting for remediation of dam cores
Permeation grouting for remediation of dam coresPermeation grouting for remediation of dam cores
Permeation grouting for remediation of dam coresUjwal Ujwal
 
Ground improvement technique
Ground improvement techniqueGround improvement technique
Ground improvement techniqueSatish Kambaliya
 

What's hot (20)

Siol cement ppt
Siol cement pptSiol cement ppt
Siol cement ppt
 
Grouting Methods
Grouting Methods Grouting Methods
Grouting Methods
 
civil engineer
civil engineercivil engineer
civil engineer
 
Soil stab use of-new.ppt dr msa edusat.ppt rev 1
Soil stab use of-new.ppt dr msa edusat.ppt rev 1Soil stab use of-new.ppt dr msa edusat.ppt rev 1
Soil stab use of-new.ppt dr msa edusat.ppt rev 1
 
Ground improvement techniques
Ground improvement techniquesGround improvement techniques
Ground improvement techniques
 
Soil Stabilisation using cement
Soil Stabilisation using cement Soil Stabilisation using cement
Soil Stabilisation using cement
 
Cement stabilisation of soil.pptx22
Cement stabilisation of soil.pptx22Cement stabilisation of soil.pptx22
Cement stabilisation of soil.pptx22
 
Soil stabilisation (1)
Soil stabilisation (1)Soil stabilisation (1)
Soil stabilisation (1)
 
Ground improvement technioques for high ways
Ground improvement technioques for high waysGround improvement technioques for high ways
Ground improvement technioques for high ways
 
Technology of soil stabilization
Technology of soil stabilizationTechnology of soil stabilization
Technology of soil stabilization
 
Subgrade Stabilization: Materials & Methods
Subgrade Stabilization: Materials & MethodsSubgrade Stabilization: Materials & Methods
Subgrade Stabilization: Materials & Methods
 
Soils stabilization jaffna center
Soils stabilization jaffna centerSoils stabilization jaffna center
Soils stabilization jaffna center
 
Soil cement
Soil cementSoil cement
Soil cement
 
Soil stabilisation clg
Soil stabilisation clg Soil stabilisation clg
Soil stabilisation clg
 
SOIL CEMENT BRICK WITH FLY ASH
SOIL CEMENT BRICK WITH FLY ASH  SOIL CEMENT BRICK WITH FLY ASH
SOIL CEMENT BRICK WITH FLY ASH
 
Geotextile fo soil stabilization
Geotextile fo soil stabilizationGeotextile fo soil stabilization
Geotextile fo soil stabilization
 
Grouting
GroutingGrouting
Grouting
 
Deep compaction techniques
Deep compaction techniquesDeep compaction techniques
Deep compaction techniques
 
Permeation grouting for remediation of dam cores
Permeation grouting for remediation of dam coresPermeation grouting for remediation of dam cores
Permeation grouting for remediation of dam cores
 
Ground improvement technique
Ground improvement techniqueGround improvement technique
Ground improvement technique
 

Viewers also liked

Economics and Management in Energy, Infrastructure, and Utilities
Economics and Management in Energy, Infrastructure, and UtilitiesEconomics and Management in Energy, Infrastructure, and Utilities
Economics and Management in Energy, Infrastructure, and UtilitiesAtanas Georgiev
 
Newsletter dated 24th December, 2015
Newsletter dated 24th December, 2015Newsletter dated 24th December, 2015
Newsletter dated 24th December, 2015Rajiv Bajaj
 
Final proposal youth group aileu journalism
Final proposal youth group aileu journalismFinal proposal youth group aileu journalism
Final proposal youth group aileu journalismApeu Derrop
 
Portafolios de trabajos Gerik Zambrano 2016
Portafolios de trabajos Gerik Zambrano 2016Portafolios de trabajos Gerik Zambrano 2016
Portafolios de trabajos Gerik Zambrano 2016Zerojustice
 
Paris the french revolution 1789
Paris the french revolution 1789Paris the french revolution 1789
Paris the french revolution 1789LEGERCLAIRE
 
Play Framework Tutorial
Play Framework Tutorial Play Framework Tutorial
Play Framework Tutorial AssistSoftware
 
Marco de referencia, distancia recorrida y desplazamiento
Marco de referencia, distancia recorrida y desplazamientoMarco de referencia, distancia recorrida y desplazamiento
Marco de referencia, distancia recorrida y desplazamientoGerardo González Sánchez
 
Presentation from my lecture on Magdalena design festival. May 2013.
Presentation from my lecture on Magdalena design festival. May 2013.Presentation from my lecture on Magdalena design festival. May 2013.
Presentation from my lecture on Magdalena design festival. May 2013.Rodion Arsenyev
 

Viewers also liked (11)

Economics and Management in Energy, Infrastructure, and Utilities
Economics and Management in Energy, Infrastructure, and UtilitiesEconomics and Management in Energy, Infrastructure, and Utilities
Economics and Management in Energy, Infrastructure, and Utilities
 
Newsletter dated 24th December, 2015
Newsletter dated 24th December, 2015Newsletter dated 24th December, 2015
Newsletter dated 24th December, 2015
 
Final proposal youth group aileu journalism
Final proposal youth group aileu journalismFinal proposal youth group aileu journalism
Final proposal youth group aileu journalism
 
S4 tarea4 cemoe
S4 tarea4 cemoeS4 tarea4 cemoe
S4 tarea4 cemoe
 
Portafolios de trabajos Gerik Zambrano 2016
Portafolios de trabajos Gerik Zambrano 2016Portafolios de trabajos Gerik Zambrano 2016
Portafolios de trabajos Gerik Zambrano 2016
 
Paris the french revolution 1789
Paris the french revolution 1789Paris the french revolution 1789
Paris the french revolution 1789
 
Play Framework Tutorial
Play Framework Tutorial Play Framework Tutorial
Play Framework Tutorial
 
Marco de referencia, distancia recorrida y desplazamiento
Marco de referencia, distancia recorrida y desplazamientoMarco de referencia, distancia recorrida y desplazamiento
Marco de referencia, distancia recorrida y desplazamiento
 
Super rubio 5
Super rubio 5Super rubio 5
Super rubio 5
 
Teme završnog rada šk. god. 2013./2014.
Teme završnog rada šk. god. 2013./2014.Teme završnog rada šk. god. 2013./2014.
Teme završnog rada šk. god. 2013./2014.
 
Presentation from my lecture on Magdalena design festival. May 2013.
Presentation from my lecture on Magdalena design festival. May 2013.Presentation from my lecture on Magdalena design festival. May 2013.
Presentation from my lecture on Magdalena design festival. May 2013.
 

Similar to Technical Manual Soil Improvement Projects

Report in Reinforced Concrete Factory.pdf
Report in Reinforced Concrete Factory.pdfReport in Reinforced Concrete Factory.pdf
Report in Reinforced Concrete Factory.pdfAdnan Alqaramani
 
Moisture_Issues_in_Concrete_Floors
Moisture_Issues_in_Concrete_FloorsMoisture_Issues_in_Concrete_Floors
Moisture_Issues_in_Concrete_FloorsMike Murray
 
REPAIR OPTIONS FOR FILLING ASPHALT CRACKS.pptx
REPAIR OPTIONS FOR FILLING ASPHALT CRACKS.pptxREPAIR OPTIONS FOR FILLING ASPHALT CRACKS.pptx
REPAIR OPTIONS FOR FILLING ASPHALT CRACKS.pptxCanandianAsphalt
 
highway materials and desihn.pptx
highway materials and desihn.pptxhighway materials and desihn.pptx
highway materials and desihn.pptxSekharJ4
 
SOIL STABILIZATION IN ROAD CONSTRUCTION AND MEASURING THE FIELD DENSITY [CO...
SOIL STABILIZATION IN ROAD CONSTRUCTION AND MEASURING  THE FIELD DENSITY  [CO...SOIL STABILIZATION IN ROAD CONSTRUCTION AND MEASURING  THE FIELD DENSITY  [CO...
SOIL STABILIZATION IN ROAD CONSTRUCTION AND MEASURING THE FIELD DENSITY [CO...Nzar Braim
 
Seal coat,prime coat and tack coat
Seal coat,prime coat and tack coatSeal coat,prime coat and tack coat
Seal coat,prime coat and tack coatMuhammadArif856
 
special problems in road construction
special problems in road constructionspecial problems in road construction
special problems in road constructionDuumeessaaGuddisaa
 
HIGHWAY CONSTRUCTION MATERIAL & PRACTICE
HIGHWAY  CONSTRUCTION  MATERIAL  &  PRACTICEHIGHWAY  CONSTRUCTION  MATERIAL  &  PRACTICE
HIGHWAY CONSTRUCTION MATERIAL & PRACTICEFresher Thinking
 
A Compatibility Study on Different Types of Cement and Plasticizer
A Compatibility Study on Different Types of Cement and PlasticizerA Compatibility Study on Different Types of Cement and Plasticizer
A Compatibility Study on Different Types of Cement and Plasticizerijsrd.com
 
Cement based building_materials_icr_aug2020
Cement based building_materials_icr_aug2020Cement based building_materials_icr_aug2020
Cement based building_materials_icr_aug2020Dr J.D. Bapat
 
25 incredible tips for concrete repair with epoxy
25 incredible tips for concrete repair with epoxy25 incredible tips for concrete repair with epoxy
25 incredible tips for concrete repair with epoxyjbors
 

Similar to Technical Manual Soil Improvement Projects (20)

Report in Reinforced Concrete Factory.pdf
Report in Reinforced Concrete Factory.pdfReport in Reinforced Concrete Factory.pdf
Report in Reinforced Concrete Factory.pdf
 
Moisture_Issues_in_Concrete_Floors
Moisture_Issues_in_Concrete_FloorsMoisture_Issues_in_Concrete_Floors
Moisture_Issues_in_Concrete_Floors
 
Z4502164171
Z4502164171Z4502164171
Z4502164171
 
Final
FinalFinal
Final
 
REPAIR OPTIONS FOR FILLING ASPHALT CRACKS.pptx
REPAIR OPTIONS FOR FILLING ASPHALT CRACKS.pptxREPAIR OPTIONS FOR FILLING ASPHALT CRACKS.pptx
REPAIR OPTIONS FOR FILLING ASPHALT CRACKS.pptx
 
highway materials and desihn.pptx
highway materials and desihn.pptxhighway materials and desihn.pptx
highway materials and desihn.pptx
 
SOIL STABILIZATION IN ROAD CONSTRUCTION AND MEASURING THE FIELD DENSITY [CO...
SOIL STABILIZATION IN ROAD CONSTRUCTION AND MEASURING  THE FIELD DENSITY  [CO...SOIL STABILIZATION IN ROAD CONSTRUCTION AND MEASURING  THE FIELD DENSITY  [CO...
SOIL STABILIZATION IN ROAD CONSTRUCTION AND MEASURING THE FIELD DENSITY [CO...
 
Seal coat,prime coat and tack coat
Seal coat,prime coat and tack coatSeal coat,prime coat and tack coat
Seal coat,prime coat and tack coat
 
Stabilized mud block
Stabilized mud blockStabilized mud block
Stabilized mud block
 
special problems in road construction
special problems in road constructionspecial problems in road construction
special problems in road construction
 
HIGHWAY CONSTRUCTION MATERIAL & PRACTICE
HIGHWAY  CONSTRUCTION  MATERIAL  &  PRACTICEHIGHWAY  CONSTRUCTION  MATERIAL  &  PRACTICE
HIGHWAY CONSTRUCTION MATERIAL & PRACTICE
 
Ref#2.pdf
Ref#2.pdfRef#2.pdf
Ref#2.pdf
 
A Compatibility Study on Different Types of Cement and Plasticizer
A Compatibility Study on Different Types of Cement and PlasticizerA Compatibility Study on Different Types of Cement and Plasticizer
A Compatibility Study on Different Types of Cement and Plasticizer
 
Highway materials and tests
Highway materials and testsHighway materials and tests
Highway materials and tests
 
1 (1)
1 (1)1 (1)
1 (1)
 
Cement based building_materials_icr_aug2020
Cement based building_materials_icr_aug2020Cement based building_materials_icr_aug2020
Cement based building_materials_icr_aug2020
 
25 incredible tips for concrete repair with epoxy
25 incredible tips for concrete repair with epoxy25 incredible tips for concrete repair with epoxy
25 incredible tips for concrete repair with epoxy
 
pothole repairs
pothole repairspothole repairs
pothole repairs
 
Characterization of soil conditioning for mechanized tunnelling
Characterization of soil conditioning for mechanized tunnellingCharacterization of soil conditioning for mechanized tunnelling
Characterization of soil conditioning for mechanized tunnelling
 
Characterization of soil conditioning for mechanized tunnelling
Characterization of soil conditioning for mechanized  tunnelling Characterization of soil conditioning for mechanized  tunnelling
Characterization of soil conditioning for mechanized tunnelling
 

Recently uploaded

Call On 6297143586 Pimpri Chinchwad Call Girls In All Pune 24/7 Provide Call...
Call On 6297143586  Pimpri Chinchwad Call Girls In All Pune 24/7 Provide Call...Call On 6297143586  Pimpri Chinchwad Call Girls In All Pune 24/7 Provide Call...
Call On 6297143586 Pimpri Chinchwad Call Girls In All Pune 24/7 Provide Call...tanu pandey
 
Call Girls In Okhla DELHI ~9654467111~ Short 1500 Night 6000
Call Girls In Okhla DELHI ~9654467111~ Short 1500 Night 6000Call Girls In Okhla DELHI ~9654467111~ Short 1500 Night 6000
Call Girls In Okhla DELHI ~9654467111~ Short 1500 Night 6000Sapana Sha
 
Call Girls Magarpatta Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Magarpatta Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Magarpatta Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Magarpatta Call Me 7737669865 Budget Friendly No Advance Bookingroncy bisnoi
 
Proposed Amendments to Chapter 15, Article X: Wetland Conservation Areas
Proposed Amendments to Chapter 15, Article X: Wetland Conservation AreasProposed Amendments to Chapter 15, Article X: Wetland Conservation Areas
Proposed Amendments to Chapter 15, Article X: Wetland Conservation Areas💥Victoria K. Colangelo
 
(ANAYA) Call Girls Hadapsar ( 7001035870 ) HI-Fi Pune Escorts Service
(ANAYA) Call Girls Hadapsar ( 7001035870 ) HI-Fi Pune Escorts Service(ANAYA) Call Girls Hadapsar ( 7001035870 ) HI-Fi Pune Escorts Service
(ANAYA) Call Girls Hadapsar ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
(NANDITA) Hadapsar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune ...
(NANDITA) Hadapsar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune ...(NANDITA) Hadapsar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune ...
(NANDITA) Hadapsar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune ...ranjana rawat
 
VVIP Pune Call Girls Moshi WhatSapp Number 8005736733 With Elite Staff And Re...
VVIP Pune Call Girls Moshi WhatSapp Number 8005736733 With Elite Staff And Re...VVIP Pune Call Girls Moshi WhatSapp Number 8005736733 With Elite Staff And Re...
VVIP Pune Call Girls Moshi WhatSapp Number 8005736733 With Elite Staff And Re...SUHANI PANDEY
 
VIP Model Call Girls Chakan ( Pune ) Call ON 8005736733 Starting From 5K to 2...
VIP Model Call Girls Chakan ( Pune ) Call ON 8005736733 Starting From 5K to 2...VIP Model Call Girls Chakan ( Pune ) Call ON 8005736733 Starting From 5K to 2...
VIP Model Call Girls Chakan ( Pune ) Call ON 8005736733 Starting From 5K to 2...SUHANI PANDEY
 
The Most Attractive Pune Call Girls Shirwal 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Shirwal 8250192130 Will You Miss This Cha...The Most Attractive Pune Call Girls Shirwal 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Shirwal 8250192130 Will You Miss This Cha...ranjana rawat
 
Hot Call Girls |Delhi |Preet Vihar ☎ 9711199171 Book Your One night Stand
Hot Call Girls |Delhi |Preet Vihar ☎ 9711199171 Book Your One night StandHot Call Girls |Delhi |Preet Vihar ☎ 9711199171 Book Your One night Stand
Hot Call Girls |Delhi |Preet Vihar ☎ 9711199171 Book Your One night Standkumarajju5765
 
Mumbai Call Girls, 💞 Prity 9892124323, Navi Mumbai Call girls
Mumbai Call Girls, 💞  Prity 9892124323, Navi Mumbai Call girlsMumbai Call Girls, 💞  Prity 9892124323, Navi Mumbai Call girls
Mumbai Call Girls, 💞 Prity 9892124323, Navi Mumbai Call girlsPooja Nehwal
 
Russian Call Girls Nashik Anjali 7001305949 Independent Escort Service Nashik
Russian Call Girls Nashik Anjali 7001305949 Independent Escort Service NashikRussian Call Girls Nashik Anjali 7001305949 Independent Escort Service Nashik
Russian Call Girls Nashik Anjali 7001305949 Independent Escort Service Nashikranjana rawat
 
Call Girls Ramtek Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Ramtek Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Ramtek Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Ramtek Call Me 7737669865 Budget Friendly No Advance Bookingroncy bisnoi
 
VIP Call Girls Mahadevpur Colony ( Hyderabad ) Phone 8250192130 | ₹5k To 25k ...
VIP Call Girls Mahadevpur Colony ( Hyderabad ) Phone 8250192130 | ₹5k To 25k ...VIP Call Girls Mahadevpur Colony ( Hyderabad ) Phone 8250192130 | ₹5k To 25k ...
VIP Call Girls Mahadevpur Colony ( Hyderabad ) Phone 8250192130 | ₹5k To 25k ...Suhani Kapoor
 
DENR EPR Law Compliance Updates April 2024
DENR EPR Law Compliance Updates April 2024DENR EPR Law Compliance Updates April 2024
DENR EPR Law Compliance Updates April 2024itadmin50
 
VVIP Pune Call Girls Koregaon Park (7001035870) Pune Escorts Nearby with Comp...
VVIP Pune Call Girls Koregaon Park (7001035870) Pune Escorts Nearby with Comp...VVIP Pune Call Girls Koregaon Park (7001035870) Pune Escorts Nearby with Comp...
VVIP Pune Call Girls Koregaon Park (7001035870) Pune Escorts Nearby with Comp...Call Girls in Nagpur High Profile
 

Recently uploaded (20)

9953056974 ,Low Rate Call Girls In Adarsh Nagar Delhi 24hrs Available
9953056974 ,Low Rate Call Girls In Adarsh Nagar  Delhi 24hrs Available9953056974 ,Low Rate Call Girls In Adarsh Nagar  Delhi 24hrs Available
9953056974 ,Low Rate Call Girls In Adarsh Nagar Delhi 24hrs Available
 
Call On 6297143586 Pimpri Chinchwad Call Girls In All Pune 24/7 Provide Call...
Call On 6297143586  Pimpri Chinchwad Call Girls In All Pune 24/7 Provide Call...Call On 6297143586  Pimpri Chinchwad Call Girls In All Pune 24/7 Provide Call...
Call On 6297143586 Pimpri Chinchwad Call Girls In All Pune 24/7 Provide Call...
 
(NEHA) Call Girls Navi Mumbai Call Now 8250077686 Navi Mumbai Escorts 24x7
(NEHA) Call Girls Navi Mumbai Call Now 8250077686 Navi Mumbai Escorts 24x7(NEHA) Call Girls Navi Mumbai Call Now 8250077686 Navi Mumbai Escorts 24x7
(NEHA) Call Girls Navi Mumbai Call Now 8250077686 Navi Mumbai Escorts 24x7
 
Call Girls In Okhla DELHI ~9654467111~ Short 1500 Night 6000
Call Girls In Okhla DELHI ~9654467111~ Short 1500 Night 6000Call Girls In Okhla DELHI ~9654467111~ Short 1500 Night 6000
Call Girls In Okhla DELHI ~9654467111~ Short 1500 Night 6000
 
Call Girls Magarpatta Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Magarpatta Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Magarpatta Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Magarpatta Call Me 7737669865 Budget Friendly No Advance Booking
 
Proposed Amendments to Chapter 15, Article X: Wetland Conservation Areas
Proposed Amendments to Chapter 15, Article X: Wetland Conservation AreasProposed Amendments to Chapter 15, Article X: Wetland Conservation Areas
Proposed Amendments to Chapter 15, Article X: Wetland Conservation Areas
 
Call Girls In Yamuna Vihar꧁❤ 🔝 9953056974🔝❤꧂ Escort ServiCe
Call Girls In Yamuna Vihar꧁❤ 🔝 9953056974🔝❤꧂ Escort ServiCeCall Girls In Yamuna Vihar꧁❤ 🔝 9953056974🔝❤꧂ Escort ServiCe
Call Girls In Yamuna Vihar꧁❤ 🔝 9953056974🔝❤꧂ Escort ServiCe
 
(ANAYA) Call Girls Hadapsar ( 7001035870 ) HI-Fi Pune Escorts Service
(ANAYA) Call Girls Hadapsar ( 7001035870 ) HI-Fi Pune Escorts Service(ANAYA) Call Girls Hadapsar ( 7001035870 ) HI-Fi Pune Escorts Service
(ANAYA) Call Girls Hadapsar ( 7001035870 ) HI-Fi Pune Escorts Service
 
(NANDITA) Hadapsar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune ...
(NANDITA) Hadapsar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune ...(NANDITA) Hadapsar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune ...
(NANDITA) Hadapsar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune ...
 
VVIP Pune Call Girls Moshi WhatSapp Number 8005736733 With Elite Staff And Re...
VVIP Pune Call Girls Moshi WhatSapp Number 8005736733 With Elite Staff And Re...VVIP Pune Call Girls Moshi WhatSapp Number 8005736733 With Elite Staff And Re...
VVIP Pune Call Girls Moshi WhatSapp Number 8005736733 With Elite Staff And Re...
 
VIP Model Call Girls Chakan ( Pune ) Call ON 8005736733 Starting From 5K to 2...
VIP Model Call Girls Chakan ( Pune ) Call ON 8005736733 Starting From 5K to 2...VIP Model Call Girls Chakan ( Pune ) Call ON 8005736733 Starting From 5K to 2...
VIP Model Call Girls Chakan ( Pune ) Call ON 8005736733 Starting From 5K to 2...
 
The Most Attractive Pune Call Girls Shirwal 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Shirwal 8250192130 Will You Miss This Cha...The Most Attractive Pune Call Girls Shirwal 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Shirwal 8250192130 Will You Miss This Cha...
 
Hot Call Girls |Delhi |Preet Vihar ☎ 9711199171 Book Your One night Stand
Hot Call Girls |Delhi |Preet Vihar ☎ 9711199171 Book Your One night StandHot Call Girls |Delhi |Preet Vihar ☎ 9711199171 Book Your One night Stand
Hot Call Girls |Delhi |Preet Vihar ☎ 9711199171 Book Your One night Stand
 
Mumbai Call Girls, 💞 Prity 9892124323, Navi Mumbai Call girls
Mumbai Call Girls, 💞  Prity 9892124323, Navi Mumbai Call girlsMumbai Call Girls, 💞  Prity 9892124323, Navi Mumbai Call girls
Mumbai Call Girls, 💞 Prity 9892124323, Navi Mumbai Call girls
 
Russian Call Girls Nashik Anjali 7001305949 Independent Escort Service Nashik
Russian Call Girls Nashik Anjali 7001305949 Independent Escort Service NashikRussian Call Girls Nashik Anjali 7001305949 Independent Escort Service Nashik
Russian Call Girls Nashik Anjali 7001305949 Independent Escort Service Nashik
 
Call Girls Ramtek Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Ramtek Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Ramtek Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Ramtek Call Me 7737669865 Budget Friendly No Advance Booking
 
VIP Call Girls Mahadevpur Colony ( Hyderabad ) Phone 8250192130 | ₹5k To 25k ...
VIP Call Girls Mahadevpur Colony ( Hyderabad ) Phone 8250192130 | ₹5k To 25k ...VIP Call Girls Mahadevpur Colony ( Hyderabad ) Phone 8250192130 | ₹5k To 25k ...
VIP Call Girls Mahadevpur Colony ( Hyderabad ) Phone 8250192130 | ₹5k To 25k ...
 
DENR EPR Law Compliance Updates April 2024
DENR EPR Law Compliance Updates April 2024DENR EPR Law Compliance Updates April 2024
DENR EPR Law Compliance Updates April 2024
 
VVIP Pune Call Girls Koregaon Park (7001035870) Pune Escorts Nearby with Comp...
VVIP Pune Call Girls Koregaon Park (7001035870) Pune Escorts Nearby with Comp...VVIP Pune Call Girls Koregaon Park (7001035870) Pune Escorts Nearby with Comp...
VVIP Pune Call Girls Koregaon Park (7001035870) Pune Escorts Nearby with Comp...
 
young Whatsapp Call Girls in Delhi Cantt🔝 9953056974 🔝 escort service
young Whatsapp Call Girls in Delhi Cantt🔝 9953056974 🔝 escort serviceyoung Whatsapp Call Girls in Delhi Cantt🔝 9953056974 🔝 escort service
young Whatsapp Call Girls in Delhi Cantt🔝 9953056974 🔝 escort service
 

Technical Manual Soil Improvement Projects

  • 1. Illustrated Technical Manual Introduction This manual is intended to serve as a guideline for those interested in planning, financing, managing or executing soil improvement and ground modification projects, such as building hard driving surfaces using copolymers as particle binders. One of the most common applications when using polymers to harden soil and rock mix, is to build hard driving surfaces. Every project where a structure of any kind must be built on the ground (soil) must follow certain rules, for example the expected loads must be supported without ground failure. While these rules are not inherently complicated, it is imperative that they are well understood before proceeding with a project. PolymerPaving.com POLYMERPAVING.COM 1
  • 2. Prologue Nothing is more important when engaging in building roads than a clear understanding of soil improvement and ground modification techniques. Fortunately, this knowledge is easy to acquire and the fundamentals are easy to understand. I hope you can use this short introduction as a springboard to build your own library on the subject and continue to learn in depth about the rules of working with soils. Having this knowledge, and with it the ability to spot and avoid problems, will help you deliver many successful projects, and give you much satisfaction in your professional career. It is very important that you request on site help from someone experienced with polymer paving on your projects as you start, or that you work with experienced geotechnical engineers. Skipping the proper expertise is not the place to save money. The savings is inherent to the process and it comes from the reduced logistics when possible, depending on the situation. Soil Considerations When a site is selected for raising a structure, such as a road or a building, special consideration must be given to the ground's ability to support and respond to the load that will be imposed upon it. This knowledge generally falls in the domain of geotechnical engineers, and much of what you need to know to work with polymers is PolymerPaving.com POLYMERPAVING.COM 2
  • 3. basic soil behavior knowledge. Over time, a number of soil behaviors and responses has been observed, which are now well understood by civil engineers. These soil behaviors occur in response to man-made loads or to other natural / environmental factors. Before raising any structure on soil / with soil / made of soil, we should gain a basic understanding of how to best prepare a work site, select an aggregate, and conduct a job by minimizing or counteracting possible negative soil behavior in accordance with the load requirements and guidelines of each project. PolymerPaving.com POLYMERPAVING.COM 3
  • 4. Driving Surface - Assorted Size Particles One of the quickest ways to raise the likelihood of success in any paving project, is to ensure the particle mix has the proper gradation to interlock during compaction. The ratio of the various sizes of soil particles determines the suitability and effectiveness of the soil in a weight bearing application. The best soils for supporting weight are made of a mixture of different size particles. Sufficient Fine Particles and Mixing If your soil has an adequate mix of particles of different sizes, then your next concern is ensuring you have sufficient fine particles to cover all the spaces between the larger rocks so that the mix of water and polymer, when thoroughly mixed, will not flush PolymerPaving.com POLYMERPAVING.COM 4
  • 5. through the rocks to the bottom, but rather remain suspended well mixed in the well- graded aggregate with the help of these fine particles (allow water surface tension), and provide lubrication to the compaction process, and then later harden into place in between the rocks, locking all the individual rocks into place, for a solid and long lasting hard driving surface. Preparing a Road Base Jusl like a building needs a proper foundation, a proper road requires a road base. At a minimum, if working on top of excellent soil, the soil on which you build the road (the subgrade, the lowest layer in the picture) needs to be well compacted. If certain soil weaknesses are to be expected, a base layer should be added, preferably made of larger rocks. If you separate the subgrade (native compacted soil) and base layer (large PolymerPaving.com POLYMERPAVING.COM 5
  • 6. rocks) with a layer of geofiber (thin, light color in the picture), it will prevent "pumping". The water table will be able to raise and lower through the larger base rocks (the thickest middle layer in the picture) without driving subgrade sediment into the road structure. An additional low cost measure to compensate for a weak subgrade is to encase the base layer (larger rocks) into a geocell grid (height of geocell you order must match the estimated height of this layer). This additional support creates a matrix that has been proven to provide excellent road performance even on some of the weakest subgrades. Adding geosynthetics (geocell, geogrid, geofiber, gabion mesh, etc) to your project ensures substantially superior performance and longevity at low cost. PolymerPaving.com POLYMERPAVING.COM 6
  • 7. Polymer Considerations Considering the number of variables you need to streamline in order to get your soil to play nice, we firmly believe that it would be smart to avoid additional concerns or doubts PolymerPaving.com POLYMERPAVING.COM 7
  • 8. about the performance of your polymer. That is why PolymerPaving.com offers you the most suitable polymer that you can possibly find, at a competitive price. When you use the KompaFlex MX formula, you can rest assured you are already using a product that will give you top notch repeatable performance time after time. Having the peace of mind that comes with using the best product, frees you to focus on ground improvement methods to bring your project to the desired performance standards. I speak from experience when I tell you that if you get caught between trying to do ground improvement while still having doubts about the performance of the binder, you will never finish a project. So do yourself "a solid" and start with KompaFlex MX, and enjoy the peace of mind that you already selected the best possible polymer, and the freedom of focusing strictly on ground improvement, which is what we will discuss for the remainder of this manual. Polymer Mix-In Methods The best way to achieve a perfect mixing of aggregate and polymer is by pre-mixing (image 2). However, when the size of the job makes pre-mixing too slow, in order to PolymerPaving.com POLYMERPAVING.COM 8
  • 9. work faster you can also do the following 4 step procedure: apply aggregate (soil or rock mix) and spread to 1 inch thick (2-3 cm); Use a spraybar to apply the proper amount of liquid (water and polymer in the correct ratio) to reach optimum moisture (image 1). Then immediately mix the liquid into the aggregate using a scarifier or power rake (image 3). Repeat this process (add soil, spread, spray, scar/mix) until the desired road surface thickness is achieved, then grade the surface to the correct angles, compact, and allow it to cure. Follow-up with a sealing coat, regardless of the method used. After 8-24 hours, clean remaining debris (loose rock and dust) from the surface with a power broom, and apply a second and final sealer coat to the surface. Another fast method is to use a reclaimer connected to a water tank truck preloaded with the water and polymer mix; this combination vehicle can wet and scar/mix the soil at the same time while advancing without the need to stop, except to reload the tank. Optimum Moisture Content is a humidity level that ensures all particles will receive polymer treatment, and compaction is well lubricated. If you see liquid on the compactor wheel or puddles, you have exceeded OMC. Never work below OMC. Exceeding it a little is not critical, but exceeding it by a lot can reduce ability to achieve high compaction. Try to make a ball in your hand with the mixed soil; if it crumbles in your hand it is too dry. If you have liquid seeping through your fingers you are applying too much liquid. When it holds shape without excess liquid showing, it is perfect for compaction. PolymerPaving.com POLYMERPAVING.COM 9
  • 10. "Poor" Soil Contingencies A soil is considered "poor" if it has been determined or tested to have inadequate or insufficient engineering characteristics to meet the minimum requirements of the PolymerPaving.com POLYMERPAVING.COM 10
  • 11. application. Another term commonly used is "marginal" and it applies when a soil comes very close to meeting these requirements but doesn't quite make the cut. Here are common methods for approaching these situations: • Excavate the "poor" soil and replace it with good aggregate. • Redesign the project to be able to work with the poor soil (for example reinforce with geocell or a similar mechanical reinforcement). • Modify the soil through soil remediation methods (mixing with other available soils / rocks, mechanical or chemical, etc). • Abandon the project - this approach is selected when you can pick a more suitable alternative location, or when the cost of fixing the soil insufficiencies exceeds the allocated budget. PolymerPaving.com POLYMERPAVING.COM 11
  • 12. Soil Type Classification by Particle Size 1. Gravel 2. Sand 3. Silt 4. Clay A "sieve analysis" is a process where a given quantity of soil is passed through a certain size of mesh to see how much passes and how much remains, determining whether a soil has a "variety" or a "uniformity" of particle sizes. Generally speaking, soils with a variety of particle sizes are called "well-graded" and are desirable for their ability to be cohesive and to compact well. Soils with mostly uniform particle size do not have good cohesion or compaction characteristics and should be avoided or modified. Crushed rock (angular) is desirable in the mix. Round particles (river rock, beach sand) are to be avoided; they may pass for "acceptable" when paving with asphalt because it is a full ring aromatic, but round particles will not work when paving with polymer as your binder because there isn't enough surface in contact with the particles surrounding it. PolymerPaving.com POLYMERPAVING.COM 12
  • 13. Shear Strength Soil is different from other engineering materials because it tends to fail in shear rather than from direct tension or compression. With this fact in mind, imagine how much stronger and resilient to shear forces the soil on the left is (compacted, mixed size [well graded], interlocked, angular rocks) compared to the soil on the right (silt / clay). Foundation: Bearing Capacity & Slope Stability Nothing is more important or critical to success than a strong foundation, whether you construct a road or a building. This becomes particularly important when the foundation soil (subgrade) is poor or marginal. When the soil and the climate are optimal, you can throw a road surface right on top of a good soil compaction without problems. Many roads in Arizona and California are built just like that and they perform PolymerPaving.com POLYMERPAVING.COM 13
  • 14. to acceptable levels for the desired lifespan. These regions rarely see bad weather or rain, or the deleterious effects of water penetration or frost heave. Building a road in most other regions require a properly designed foundation to compensate for the natural forces that work against you. For instance many tropical areas see non-stop rain for six months out of the year. In such an instance, a large portion of your effort and budget should be aimed at effective drainage and building the road above the water table. When you work in muddy or volcanic silt (such as in most of Southeastern Europe) you need to explain to your beneficiaries the importance of building roads the same way they build their railroads (with a solid crushed rock base that allows for water drainage and frost heave), if they want them to last as long. You should seek additional reading on "shallow foundation design" to understand bearing capacity failure. You can imagine the risk of slope stability failure when you think that every few square feet of your compacted pavement surface weighs tons by itself, and there are enormous natural shear pressures acting on a slope, especially when the pavement structure is imbibed with water molecules in between the soil particles (a very important phenomenon that is worth exploring in detail, to have it well understood), and subjected to additional traffic weight. That is why we strongly recommend the use of geosynthetic materials for reinforcement, not as a luxury, but as a way to raise project longevity and to prevent catastrophic failure due to unforseen events (bad winter, floods, earthquakes, liquefaction, etc). No other materials offer a better price to performance ratio for enhancing the desirable characteristics of a road and/or road base (and also for other soil projects - embankments, overpasses, etc). PolymerPaving.com POLYMERPAVING.COM 14
  • 16. Soil Densification and Consolidation Soil densification is a process by which the air pockets are removed from soil through compaction. Soil consolidation is a process by which water is removed from soil. There is sufficient technology available today to literally be able to say that "no soil is unsuitable" if you have the budget, the equipment, and use the right methods to fix it, or to compensate for the respective defficiencies. Types of Compactors There are various types of compactors available, each designed for specific tasks, and some are more suitable than others for specific jobs. It is important to know what kind of compactor to use depending on your soil type and the desired end result which you are PolymerPaving.com POLYMERPAVING.COM 16
  • 17. trying to achieve. Different soil types will present diverse characteristics that will affect the soil improvement decisions you make. Smooth Drum Rollers: a static load roller used for compaction of soils and asphalts, they provide even weight distribution over the width of the roller and a smooth finished surface. Also good for "proof rolling" during base preparation (to identify soft spots that need reinforcement). Pneumatic (rubber tire) rolles: these are engineered to apply very high static loads to a wide variety of soils, pavements, bases and subgrades. They are even better suited at finding soft spots, particularly because individual tires have the ability to move up and down a small distance independently. Combination rollers: easily identifiable as having both a steel drum and a set of pneumatic roller wheels, with the ability to use either. Vibratory rollers: they look similar to static rollers, with the ability to provide impact and vibration to the soil beneath. If you have granular soils (poor cohesion aggregate) a vibratory roller will help overcome the frictional resistance and achieve better compaction. Sheepsfoot / Padfoot / Wedgefoot rollers can apply very high static loads by concentrating extreme weight on a small contact surface. These are ideal for breaking hard dry boulders inherent in clay, silt and other cohesive soils, and in this way allowing high and uniform compaction. PolymerPaving.com POLYMERPAVING.COM 17
  • 18. Weight and Number of Passes Although mathematically you should get the same result by adding the weight between the number of passes, field experience shows that if you don't get the desired compaction after 5-7 passes, you should perhaps switch to a heavier compactor. One exception to this rule may be saturated sands, which have shown to improve up to 15-20 passes. However, since one of the "commandments" of working with polymer is to never use sands or other round particles, this detail is irrelevant in our context. PolymerPaving.com POLYMERPAVING.COM 18
  • 19. Requesting a Laboratory Test So you are interested in polymer paving, perhaps because it is eco-friendly, or because it is affordable or maybe because it is easy to complete and maintain. Perhaps it is for a combination of reasons, or perhaps someone asked you to look into it. Many of the variables you need to determine, including the suitability of a soil, can be easily and inexpensively resolved by sending a soil sample and a small fee to our laboratory, where we can test your soil for you and provide you with a report of your general situation. This way you have a much better idea which approach / method / procedures we would recommend as the most suitable for your particular project. PolymerPaving.com POLYMERPAVING.COM 19
  • 20. Conclusions Building an eco-friendly road with in-situ soil and polymer binder is really a process of self-development, of becoming really good at soil improvement and ground modification PolymerPaving.com POLYMERPAVING.COM 20
  • 21. procedures. Clean, affordable, long-lasting roads are just a result of accumulating that knowledge and experience. I hope this brief guide served to introduce you to (or to remind you of) some of the basics of sound soil engineering. Success in polymer paving only requires a dilligence in following these proven and time tested principles. Soil improvement methods are generally applicable in almost any other type of construction, not only road building. We look forward to working with you. PolymerPaving.com is a division of Option Quest LLC, which manages the following properties: • www.polymerpaving.com • www.greenroadbuilder.com • www.optionquest.com • www.incentiveserver.com • www.responsiveglass.com • www.language-queen.com • www.law-register.com • www.mobileactivator.com PolymerPaving.com POLYMERPAVING.COM 21