2. L&T Construction| 2
Sensitivity: LNT Construction Internal Use
Design & Build- Free Trade Warehousing Zone at JNPT,
Mumbai
Weekly Progress Report
26-Dec-2022 to 01-Jan-2023 (Week No-114)
3. L&T Construction| 3
Sensitivity: LNT Construction Internal Use
Contents
1 General Details
2 EHS Report
3 Overall Progress
4 Schedule Progress Update
5 Agency approvals
6 Finishing Schedule
7 Statutory approvals
8 Progress Report Pictorial View
9 Methodology/Risk assessment approval summary
10 Material / Agency Approval Summary
11 Resource Report
12 Quality report
13 Document submission status/Input required- Client
14 List of Action points among DP World and JNPT SEZ Team
15 Photographic report
16 Insurance Details
4. L&T Construction| 4
Sensitivity: LNT Construction Internal Use
General Details
Name of Employer M/s Nhava Sheva Business Park Pvt. Ltd.
Name of Design Consultant M/s C R Narayan Rao Pvt. Ltd.
Name of the Contractor M/s Larsen & Toubro Ltd.
Name of Project Design & Build – Mumbai Free Trade Warehouse Zone at JNPT, Mumbai
Project Start Date 20th Oct 20
Scheduled End Date
Phase 1- 19th Dec 2021
Phase 2- 19th Apr 2022
No. of Days of Contract 546 Days
Scope of Work Design & Build – Mumbai Free Trade Warehouse Zone at JNPT, Mumbai
5. L&T Construction| 5
Sensitivity: LNT Construction Internal Use
EHS Report- Photographs
PEP talk given to workmen about Repairing Work PEP talk about Safe Work during Material handling
6. L&T Construction| 6
Sensitivity: LNT Construction Internal Use
EHS Report
Sl. No. Description This week Total
1 No. of Manhours Worked 20048 4595400
2 No. of accidents reported - 1
3 No. of near misses - 6
4 Lost time injury (LTI) - 1
5 Safety Observation 2 298
6 Safety Induction 12 7639
7 Training / Awareness Session. 2 201
8 Mass Toolbox Talks conducted 2 370
9 No. of safety site walks conducted 1 106
7. L&T Construction| 7
Sensitivity: LNT Construction Internal Use
Admin Interior Work
Task Name Remarks
•Admin (GF)
Painting – Final Coat- Pending
Carpet laying & aluminum skirting- Completed
Granite on ledge wall fixing- Completed
Flooring in Reception area – Lift lobby floor tile pending
Toilet Cubical installation- Completed
MEP accessories in Toilet- Completed
•Admin (FF)
Painting – Final Coat- Pending
Carpet laying & aluminum skirting- Completed
Granite on ledge wall fixing –Completed
Toilet Cubical installation- Completed
MEP accessories in Toilet- Completed
8. L&T Construction| 8
Sensitivity: LNT Construction Internal Use
Admin Interior Work
Task Name Remarks
•Admin (SF)
Painting –Pending
Carpet laying & aluminum skirting- Ongoing
Granite on ledge wall fixing – Completed
Toilet Cubical installation- Completed
MEP accessories in Toilet- Almost Completed
Terrace
Granite Counter- Almost Completed
Painting
9. L&T Construction| 9
Sensitivity: LNT Construction Internal Use
Progress Report Pictorial View
Subgrade
GSB
DLC
Flooring
W-3
W-2
W-1
WMM
W-3
SUB.
W-6
Paver Block
DBM
Parking
UG
BC
W-6
Grass Crete
PQC
W-4
W-5
W-4
11. L&T Construction| 11
Sensitivity: LNT Construction Internal Use
IGBC Critical Client Points
S No Description Remarks
1 Landscape Drawing AutoCAD format with the mentioned area marked – Tree Area, Shrub Area, Total Landscape
Area, Lawn (Turf) Area, and Number of Trees. Plant & Trees Species to be specified.
Pending
2 Tkm calculation Sheet to satisfy Case A & Case B mentioned in via Email Need to modify
3 MHE vehicles Invoice (Fork lift + Pallet Truck + Reach Truck) till date. Received
4 MHE vehicles and charging point photos (With signage) Photo Shared, Signages Required
5 Golf cart Invoice Received
6 Golf Cart calculation ensuring 5% of occupants (excluding visitors) are catered Received
7
Declaration mentioning
Organise atleast two outreach/ educational programmes in a year on eco-friendly practices/ green initiatives.
The outreach/ educational programmes can include, but not limited to, clean & green, water conservation, energy
conservation, waste segregation & recycling, use bio-degradable plastic/ avoid single use plastic, air pollution, world
green building week and earth hour
-
8
Declaration mentioning
Atleast 75 % of the fleet (road fleet) complies with BS IV or latest emissions norms.
(And)
Entire fleet (road fleet) of the service provider will be periodically serviced to ensure efficient vehicle performance.
(And)
Awareness programmes will be organised periodically, by the service provider, to train the drivers on vehicle maintenance
and driving etiquette.
-
12. L&T Construction| 12
Sensitivity: LNT Construction Internal Use
IGBC Critical Client Points
S No Description Remarks
9 Provide Posters with education material for drivers shall be placed in drivers’ dormitories or resting areas (vehicle
maintenance and driving etiquette)
Pending
10 No smoking area photos with signage
Pending
11 Floor plans with waste bins Proposal Received, Yet to send to CEFD Team
12 Organic Waste Composter with capacity of 160Kg/day to be installed (occupant number considered – 1650)
Pending
12
Install permanent educational signage in common areas of the park/ warehouse with green concepts such as Go Green,
Save Earth; Water is Precious, Save it; Turn off Lights, when not in use; Say no to Mixed Waste; Plant a Tree, Save the
Environment, etc
-
14
Undertaking for shuttle service connecting local public transit stops in the operating stage – Kindly reshare as the document
file got corrupted
-
15
Project Activity to be identified for Green activity beyond fence. Below are the IGBC recommended projects –
• RainWater Harvesting
• Sewage Treatment Plant
• Water Body
• Public Parks/Avenues
• Mass Plantation
• Renewable Energy
• Basic Facilities like – Provide at least four of the following : Bus Shelters, Street Lighting, Public toilets, Play area &
Sports kit, Tot-lot, Drinking water ATM or equipment, Organic waste management, other basic facilities
-
13. L&T Construction| 13
Sensitivity: LNT Construction Internal Use
Document submission status/Input required- Client
Handover for Wh-1 & 2 – Taking Over Certificate issuance
Disbursement of RAB-22 Main works
Tax Invoice raise confirmation against of RAB-3 Interior works
Tax Invoice raise confirmation against of RAB-24 Interior works
EOT approval
Road Marking details approval
Column guard proposal confirmation
Admin Building High resolution graphics details
Cold Storage Cage ladder finalization
View confirmation of cladding fixed over WH-1 & 2 wall along Grid 22
Change order confirmation (Reefer & ELV)