1. INTERNATIONAL ISLAMIC UNIVERSITY ISLAMABAD
CONTOURING BY INDIRECT METHOD LAB MANUAL
GROUP 07
DEPARTMENT OF CIVIL ENGINEERING
FACULTY OF ENGINEERING & TECNOLOGY
2. GROUP MEMBERS
SALMAN NISAR
31-FET/BSCE/F14
MUHAMMAD YASEEN
32-FET/BSCE/F14
MUHAMMAD ISMIAL
34-FET/BSCE/F14
MUHAMMAD JUNAID
35-FET/BSCE/F14
4. i. Direct Method:
Radial method
Random method
i. Indirect Method:
Indirect method is quick, economic and less laborious than direct
method. The reduced level of a point on the surface of ground is
called spot height or spot level .In this method spot levels of selected
points are taken with a level and their levels are computed. The
horizontal positions of these points are measured or computed and
the points are plotted on the plan. The contours are then drawn by a
process called interpolation of contours from the levels of the guide
points.
It have further three categories, given below
Grid or Square method
Cross Section method
Tachometric method
Radial lines method
5. I. Grid or Square Method:
1) This method is suitable only if area is not very extensive. its
procedure is mention below.
2) Squares or grid method is suitable for contouring of plains or
gently sloping grounds.
o PROCEDURE
a) In this method area to be contoured is divided into series of squares,
and ends (corner) of each square is marked with pegs.
b) The size of square varies from 5m to 20m, depending upon the
contour intervals and nature of ground and scale of the desired map.
c) The squares not need to be same throughout and may vary depending
on requirements and field conditions.
d) The pegs are marked out and elevation of the ground at the corners of
the square are determined by a level.
e) The grid is plotted to the scale of the map and the spot levels of the
grid corners are entered.
f) The contours of desired values are then located by interpolation.
g) Special care should be taken to give the spot levels to the salient
features of the ground such as hilltops, deepest points of the
depressions.
h) The method is used for large scale mapping and at average
precision.
7. PROCEDURE:
• We have an area of 30m 30m and we want to convert it to grids or squares.
• Make 10m
.
.
• Set the auto level at a point of known reduce level, and
take a back sight by help of auto level.
• Adding B.S value to B.M will give us H.I, whose mathematical formula
is
H.I=B.M + B.S => 100’+5.4’=105.4’
• . Now place staff rod at every corner of grid and note
readings.
10m grids throughout the area
• This is F.S, by subtracting these values from H.I we get R.L of that
point.
• A1 point has a F.S of 3.84’ so subtracting 3.84’ from 105.4’ which is H.I
will
Give us 101.56’ which is the R.L of A1 point.
8. • Similarly F.S of point A3 is 3.38’ and its reduce level becomes 102.02’
• This process goes until reduce level of last point D4 is found, which is
103.35’
PROCEDURE: CON’T
9. Interpolation by estimation method:
In this method contour lines are drawn between points by estimating
distances between points
STEPS:
1) when the grid points are A2= 102.5 feet elevation and
A1=101.56 feet elevation, then a contour line of 102 feet
elevation would be half way in between.
2) For points B2=102.08ft and A1=101.56ft, then a contour
line of 102ft will be more towards 102.08ft elevation
10. 3) For points B2=102.08ft and B1=101.36ft, then a
contour line of 102ft will be more towards 102.08ft
elevation
4) For point C2=102’, so the contour point will be on c2.
11. 6) For points C1=101.98ft and D2=102.2ft, then a contour
line of 102’will be more towards C1=101.98ft elevation.
5) For points C1=101.98ft and D1=102.2ft, then a contour
line of 102ft will be more towards C1=101.98ft elevation.
12. 7) So contour lines of area 30m 30m by estimation method is given below
13. Interpolation of Grids by Arithmetical
calculation:
In method contour lines are drawn between ground
points by using formula given below:
elevationobetween twDistance
elevationLow-elevationHigh
elevationCentral-elevationHigh
=%
STEPS:
1. Start by selecting a contour interval and two grid points.
2. This example starts with point of 102ft interval.
3. The distance between A1 and A2 is 1.inch so by putting
the values in following formula gives:
14. %=0.79
4. For points A1and B2, difference between these two is 2
inch and proportion difference is 0.36 as obvious from fig
15. 5. For 102’ between B1=101.56’ and B2=102.08’ point, the
Calculation is given below;
6. For finding position of 102’ between C2=102’ and
C1=101.98’ for this there is no need of calculation.
16. 7. For finding position of 102’ between C1=101.98’ and
D1=102.2’
8. For finding position of 102’ between C1=101.98’ and
D2=102.2’
17. 9. So the contours of these lines are shown in below
diagram.
18. I. Cross Section method:
This method is most suitable for the survey of
long narrow strip such as road, railway, canal etc.
PROCEDURE:
a) Cross section are run transverse to the center line
of work and representative points are marked along
the line of cross section.
b) The cross section line need not necessarily be at
right angles to the center line of work.
c) This may be inclined at any angle to the center line
if necessary.
d) This spacing of the cross section depend on the
topography of the country and the nature of survey
the common value is 20m to 30m in hilly country and
100m in flat country.
e) The level of the points along the section line are
plotted on the plan and contour are then interpolated
as usual.
19. Example:
1. In this example the base line is 50m.
2. Two points are taken at each side of base line at 5m.
3. First of all H.I is found from the B.S=5ft and B.M=100ft
By formula mention below;
H.I=B.S+B.M
H.I=5ft+100ft
H.I=105ft
4. The reduce level of each point is found by simply
subtracting F.S of that point from H.I
’.
20. 6. For point A3, F.S=4.44ft it’s R.L=100.56’.
7. F.S of point A2=4.29ft, its R.L becomes 100.71ft
8. F.S of point A1=4.33ft, its R.L becomes 100.67ft.
9. F.S of point A is 4.5ft and its R.L is 100.5ft
10. Similarly for last point F4, F.S=3.36ft and its R.L is
101.64ft.
11. So by this process the elevation of each point of this
example is found, and is shown in diagram below;
5. Suppose F.S of A4 is 4.54ft so its reduce level is
R.D=H.I-F.S=> R.L=105ft-4.54ft
R.L of point A4=100.49ft
21.
22. Interpolation of cross section by estimation
method:
In this example we try to find contour intervals of 101ft,
so for finding this contour interval throughout the cross
section steps are given below in details;
As 101ft is closer to point D4=100.76’ than
E4=101.75’so this shows that contour interval=101ft
will be close to point D4.
23. For point D4=100.76ft and E3=101.9’, again 101ft contour interval will
be near point D4.
For point E3=101.9’ and D3=100.98ft, 101ft contour
interval will be near point D3.
24. For point D3=100.98ft and E=101.3ft contour interval
of 101ft will be near point D3.
For point D=100.86ft and E=101.3ft contour interval of
101ft will be near point D.
25. For point D=100.86ft and E1=101.07ft, 101ft contour
interval will be near point E1.
For point D1=100.27ft and E2=101.8ft, 101ft contour
interval will be closer to point D1.
26. For point D1=100.27ft and E1=101.07ft, 101ft contour interval
will be more near to point E1.
28. Interpolation of cross section by arithmetical
method:
In this method interpolation of points is done by the
process of proportion formula given below:
elevationobetween twDistance
elevationLow-elevationHigh
elevationCentral-elevationHigh
=%
STEPS:
1) The contour interval between D4 and E4 is given
below:
29. 2) For points D4 and E3 calculation is given below along
with fig:
30. 3) For point E3 and D3 the calculation are given below
along with fig:
4)For point E and D3 calculation is given:
31. 5) For points E and D calculation are given below:
6) For points D and E1 arithmetic calculation is given
below:
32. 7) For points D1 and E1 calculation are given below:
8) For point D1 and E2 arithmetic calculation is given
below:
34. I. Tachometric method:
Whenever contouring of very steep area such
as a “hill” is required tachometric method is used.
Procedure is given below.
PROCEDURE:
a) Set up the tachometer at the top of the steep hill.
Tachometer is a theodolite fitted with stadia
diaphragm. The stadia diaphragm has three horizontal
parallel hairs instead of one as found in a conventional
cross hair diaphragm.
b) With the help of a tachometer it is possible to
determine the horizontal distance of the point from
the telescope as well its vertical level.
c) The steep hill is surveyed at three levels – the base of
the hill, the mid-level of the hill and the top level of the
hill.
35. I. Radial line method:
This method is convenient in hilly terrain
PORCEDURE:
a. Radial line method in this method, a number of radial
lines are set out at known angular interval at each
station and points are marked at the ground at
convenient distance apart on the rays that are set.
b. Spot levels of these points are determined by leveling.
c. The points are plotted to the scale of the map and spot
levels are entered.
d. The contours of desired values are then located by
interpolation.
d) Using the tachometer reading are taken all around the
hill at equal angular intervals on all these three levels.
e) The radial plot thus obtained is worked in the office to
interpolate points of equal elevation for contour mapping.
36. Interpolation of contours:
• Drawing contour lines to produce a contouring of an area
requires the process of interpolation between points.
• Interpolation process means spacing the contours
proportionally between the plotted ground points.
• Contours can be interpolated by :
1. By estimation method
2. By arithmetical calculation method
3. By graphical method
37. 1. Estimatiom method:
The position of contour points between ground points
are estimated.
The contour lines are then drawn through these points.
This method is used for rough and usually used on
small scale maps.
Interpolating can be done by estimation for low
precision maps.
38. 2. Arithmetical calculation method:
This method is employed when greater accuracy is
required.
This is time consuming also.
Positions of contours points among guide points are located
by arithmetic calculations.
Formula is given below:
elevationobetween twDistance
elevationLow-elevationHigh
elevationCentral-elevationHigh
=%
39. 3. Graphical method:
When higher accuracy is required and many contours
are to be made, this method is employed.
This method of interpolation proves to be rapid and
easy.
For this purpose a tracing paper is used.