Civil Engineering and Urban Planning: An International Journal (CiVEJ) Vol.3, No.2, June 2016
DOI:10.5121/civej.2016.3205 63
PRESENT APPLICATION OFRESOURCE
MANAGEMENT IN PREFABRICATED AND
IN-SITU CONSTRUCTION
V.Yuvaraj1
and R.Dharman2
,
1
PG Scholar, M.E Construction Engineering and Management,
2
Assistant Professor, Department of Civil Engineering,
Shree Venkateshwara Hi-Tech Engineering College, Gobi, Tamil Nadu, India.
ABSTRACT
Currently, prefabricated building plays a leading role in construction. Mounting with the standardization
and mechanization, Prefabrication has brought an extensive transformation in the construction industry
around the world. Moreover the associated advancements to the local construction industry with the
espousal of more mechanization, intelligent management systems and computer aided manufacturing; the
wide-ranging use of prefabrication also contributes to sustainable development by means of cleaner and
more resources saving production process. The main aim of this paper is to present a prefabricated
construction based on time and cost utilization over than in-situ construction. Also forecast the general
idea about the development and application of prefabrication method in the construction of large-scale and
high-rise buildings. The factors like time and cost are analyzed in normal construction and in prefabricated
construction companies. The results are shown by using management software tools.
KEYWORDS
In-situ construction, prefabricated construction, Quality, Time, Cost.
1. INTRODUCTION
For many years prefabrication has been used comprehensively and commonly over the world
wide. The manufacture of building components are often illustrated by the terms such as
prefabrication, pre-assembly, system building, industrialized buildings and modularization which
are constructed on any like on site/off-site in an industrial unit covering modular, manufactured
and pre-cut/pre- engineered systems. Although the conditions/terms, are normally used
correspondingly, their specific definitions depend deeply on the users’ experience and indulgent,
which differ from countries to countries. In this paper, prefabrication is chosen with extra
prominence on the building components which are made off-site in an industrial unit. Off-site
fabrication is an area of international significance and provides an efficient construction
technique in terms of time, quality, cost, productivity, safety and function. It is adopted globally
as the ultimate resources of producing an enormous range of elements from cladding units,
structural members and bathrooms to fully-finished modular buildings.
A General Review of Prefabrication Adopted in India, if the building materials are concrete, steel
or timber based system, the benefits of prefabricated building systems must be obvious. It is an
industrialized way of construction, with the inbuilt advantages of:
• High capacity - enabling the understanding of important projects
• Factory made products
• Independent of unfavorable weather circumstances during construction
• Quality observation/surveillance system
• Shorter construction period - below half of conventional cast in-situ construction.
Civil Engineering and Urban Planning: An International Journal
Since the main goal of prefabrication is to consequence economy, enhancement in quality and
speed in construction, the choice of proper materials for prefabrication is also a significant
feature in the development of this technique. The use of locally existing materials with
essential characteristics and also owing to their inherent characteristics such as easy
workability/flexibility, light-weight, non
economy and enhanced quality may be tried in prefabrication.
In civil engineering projects, prefabrication saves engineering point in time on the construction
site. This can be fundamental to the accomplishment of projects such as bridges and landslide
galleries, where weather conditions may only permit short periods of construction.
Prefabricated bridge systems and elements offer bridge designers and contractors considerable
advantages in terms of construction time, safety, environmental impact, constructab
cost.
Figure 1. shows the comparison between the In
buildings in construction fields.
Figure 1.1. Advantages of Prefabricated buildings over In
1.1. Time
Prefabrication can give way to save timings through the capability to carry out work concurrently
on-site and off-site, in addition to helping with enhanced management with different traders.
Additionally, less onsite performance, such as scaffolding, is r
capacity to stay away from weather impacts can lessen construction time. Site conditions issue
considerably in the facility of prefabrication to crash schedule.
Civil Engineering and Urban Planning: An International Journal (CiVEJ) Vol.3, No.2, June 2016
Since the main goal of prefabrication is to consequence economy, enhancement in quality and
speed in construction, the choice of proper materials for prefabrication is also a significant
he development of this technique. The use of locally existing materials with
essential characteristics and also owing to their inherent characteristics such as easy
weight, non-combustibility and thermal insulation, effect
onomy and enhanced quality may be tried in prefabrication.
In civil engineering projects, prefabrication saves engineering point in time on the construction
site. This can be fundamental to the accomplishment of projects such as bridges and landslide
eries, where weather conditions may only permit short periods of construction.
Prefabricated bridge systems and elements offer bridge designers and contractors considerable
advantages in terms of construction time, safety, environmental impact, constructab
shows the comparison between the In-situ buildings and the proposed prefabricated
buildings in construction fields.
. Advantages of Prefabricated buildings over In-situ buildings
Prefabrication can give way to save timings through the capability to carry out work concurrently
site, in addition to helping with enhanced management with different traders.
Additionally, less onsite performance, such as scaffolding, is regularly concerned. Regionally, the
capacity to stay away from weather impacts can lessen construction time. Site conditions issue
considerably in the facility of prefabrication to crash schedule.
(CiVEJ) Vol.3, No.2, June 2016
64
Since the main goal of prefabrication is to consequence economy, enhancement in quality and
speed in construction, the choice of proper materials for prefabrication is also a significant
he development of this technique. The use of locally existing materials with
essential characteristics and also owing to their inherent characteristics such as easy
combustibility and thermal insulation, effect
In civil engineering projects, prefabrication saves engineering point in time on the construction
site. This can be fundamental to the accomplishment of projects such as bridges and landslide
eries, where weather conditions may only permit short periods of construction.
Prefabricated bridge systems and elements offer bridge designers and contractors considerable
advantages in terms of construction time, safety, environmental impact, constructability, and
situ buildings and the proposed prefabricated
Prefabrication can give way to save timings through the capability to carry out work concurrently
site, in addition to helping with enhanced management with different traders.
egularly concerned. Regionally, the
capacity to stay away from weather impacts can lessen construction time. Site conditions issue
Civil Engineering and Urban Planning: An International Journal (CiVEJ) Vol.3, No.2, June 2016
65
Currently, Two-thirds of Construction firms which uses modularization /prefabrication
observed that prefabrication reduces the schedule of the project up to 35% i.e., four weeks
or more.
On difficult/complex projects to coordinate the use of prefabrication and modularization, extra
time may be used up in the design phase. On the other hand, the time saved onsite normally
reduces the whole project schedule.
1.2.Cost
As an outcome of using prefabrication/modularization, vendor report of project cost decrease
ranging from 2% to 40%. A number of owners for these cheap costs consist of:
• Possibly Local labors are very expensive or inefficient for onsite work.
• Costly delays may occur due to unfavorable onsite environmentand weather
troubles.
cost related with onsite infrastructure and overhead can be reduced by relocating some or all of
the work to an off-site locality as some owners statement . Furthermore they state that smaller
number of workers onsite render to fewer costs for housing, scheduling onsite work and
additional onsite logistics.
For prefabrication /modularization, labor costs can be a vital factor. Owners point out that pre-
fabrication/modularization offers a less pricey alternative for very high local labor cost areas.
1.3.Quality
Quality control forms a primary part of precast construction. A proficient quality method is most
significant in the accumulation making of precast components in every project. The quality
control system implemented in a precast industrial unit is discussed in this study.
The precast industrial unit is set up for the production of large scale buildings.Processes in the
precast production are proposed with respect to the quality control procedures in the quality
inspection plan. The standard tests like concerned roles of inspectors and corrective actions on-
site are tinted. Serious issues pertaining to the quality and productivity of precast manufacture are
reviewed. These consist of the quality of maintenance and staff, which possibly will potentially
have an effect on the effectiveness of the quality system. Various considerations are supposed to
also be given to develop the workflow and efficiency of the factory.
2. NEED FOR STUDY
In the current situation the construction of buildings are very difficult thing around the world due
to over contest and necessities of client requirements.Quality of On-site buildings are mainly
affected by several reasons like poor quality of materials, environmental factors, wastage of
materials, etc..,. This proposal will used to recognize factors for good quality of production/
construction at low cost.
Civil Engineering and Urban Planning: An International Journal (CiVEJ) Vol.3, No.2, June 2016
66
3. OBJECTIVES
To Study on efficient deployment of Cost in Prefabricated and In-situ buildings.
To Study on efficient exploitation of Time in Prefabricated and In-situ buildings.
To Study on Quality of prefabricated and In-situ buildings.
Making a Study about the methodology adopted in the manufacturing of prefabrication
construction.
Management of Resources in Prefab and In-situ construction using Software.
To study on comparison of Duration, Cost, and Quality of prefabricated and In-situ
buildings.
4. LITERATURE REVIEW
Based on the Prefabrication literatures are collected. From the review various factors were
recognized.The literatures together are being used as base for the further procedures in the
project.
The author [1] Christabel M F Ho, Raymond W M Wong., emphasizes that
• Mass production prefabricated building components (precast façade, precast stair flight,
drywall and semi-precast floor planking) reduce cost and save time, with added
advantage of taking some of the most dirty and awesome work out of the process.
• Faster erection capabilities and fewer manpower requirements make prefabrication the
most viable option for public housing construction in Hong Kong.
• According to the study carried out by Tam (2002), there could be a 43 percent reduction
in site labor consumption if there is a shift from the in-situ site casting to prefabrication
design.
At the same time, prefabrication offers clients better performance to fulfill all requirements, such
as:
• Opportunities for good architecture
• Fire resistant material
• Healthy buildings
• Reduced energy consumption through the ability to store heat in the concrete mass
• Environmentally friendly way of building with optimum use of materials, recycling of
waste products, less noise and dust etc.
The authors Linda Brock, James Brown [2] stated that,
• In Canada, manufactured housing simply means that 85 percent or more of the
construction is completed in a factory.
• In fact, 24 percent of new housing starts in 1996 were manufactured-mobile houses; only
2 percent to 3 percent were other prefabricated styles (such as modular housing).
• In the same year in Canada, all styles of prefabricated homes represented only 7.5 percent
of the market, with two-thirds of these homes being single modules.
Civil Engineering and Urban Planning: An International Journal (CiVEJ) Vol.3, No.2, June 2016
67
Shri P K Adlakha, Shri H C Puri [3] describes prefabrication as In India, adoption of
prefabrication building techniques has many merits in the context of availability of materials,
labor and technical skills. Advantages of prefabrication are:
• In prefabricated construction, as the components are readymade, self supporting,
shuttering and scaffolding is eliminated with a saving in shuttering cost.
• In traditional construction, the repetitive use of shuttering is limited, as it gets damaged
due to frequent cutting, nailing etc. On the other hand, the mould for the precast
components can be used for large number of repetitions thereby reducing, the cost of the
mould per unit.
• In prefabricated housing system, there is saving of time as the elements can be casted
before hand during the course of foundations being laid and even after laying slab, the
finishes and services can be done below the slab immediately. While in the conventional
in-situ RCC slabs, due to props and shuttering, the work cannot be done, till they are
removed. Saving of time means saving of money.
• In prefabricated construction, there is better quality control, shape and size of precast
elements. Therefore, in structural design, full advantage of properties of cement and steel
can be exploited.
• In precast construction, similar type of components is produced repeatedly, resulting in
increased productivity and economy in cost too.
• In precast construction, the construction is not affected due to weather, rain, wind etc
5. METHODOLOGY
With the intention to get the details associated to prefabricated construction uses along with their
safety procedure and different methods of production literature study and the study of codes and
regulation were prepared. The flowchart below represents the methodology adopted for the
proposed work. After reviewing the literature the industry/company where the work is to be
adopted is identified. Then the data’s from the industry/company are collected and analyzed.
Figure 5.1. Work Flow Diagram
Civil Engineering and Urban Planning: An International Journal (CiVEJ) Vol.3, No.2, June 2016
68
6. CASE STUDY ON IN-SITU BUILDING
Raj Associates has plans to build a multi-storeyed construction in the main area of the city. In
building construction bunch of work packages and activities are mixed up. Making an effort to
use the resource optimistically and also to lessen the time and cost. The activities for customizing
different functional areas are declared as work packages and their relationship are specified.
6.1.Stages Of Work
General condition
Procurement of materials
Site preparation
Arrangement of site
Work on foundation
Erection of structures
Steel erection in 2 & 3 floor
Plumbing work
Work on roofs
Installation of windows
Finishing of building
Final clean-up and occupation
Works on floor
Final inspection
Table 6.1. Stages of Work for In-situ building
Civil Engineering and Urban Planning: An International Journal
Total duration of the Institutions building is 347 days.
Total budget of the In-situ building is Rs. 2,096,189.33/
7. CASE STUDY ON PREFABRICATED
Teemage Precast Pvt. Ltd. plans to build a multi
city. In building construction bunch of work packages and activities are
effort to use the resource optimistically and also to lessen the time and cost. The activities for
customizing different functional areas are declared as work packages and their relationship are
specified.
Civil Engineering and Urban Planning: An International Journal (CiVEJ) Vol.3, No.2, June 2016
Figure 6.1. Duration of Project
building is 347 days.
Figure 6.2. Cost of Project
situ building is Rs. 2,096,189.33/-
REFABRICATED BUILDING
Teemage Precast Pvt. Ltd. plans to build a multi-storeyed construction in the main area of the
city. In building construction bunch of work packages and activities are mixed up. Making an
effort to use the resource optimistically and also to lessen the time and cost. The activities for
customizing different functional areas are declared as work packages and their relationship are
(CiVEJ) Vol.3, No.2, June 2016
69
storeyed construction in the main area of the
mixed up. Making an
effort to use the resource optimistically and also to lessen the time and cost. The activities for
customizing different functional areas are declared as work packages and their relationship are
Civil Engineering and Urban Planning: An International Journal (CiVEJ) Vol.3, No.2, June 2016
70
7.1. Stages Of Work
General condition
Procurement of materials
Site preparation
Arrangement of site
Work on foundation
Erection of structures
Steel erection in 2 & 3 floor
Plumbing work
Work on roofs
Installation of windows
Finishing of building
Final clean-up and occupation
Works on floor
Final inspection
Table 7.1. Stages of Work of prefabricated building
Task Name Duration Cost
General condition 5 days 38,500.00
Procurement of materials 20 days 147,750.00
Site setting 16 days 87,500.00
Site preparation 6.5 days 37,200.00
Preparation of foundation 4 days 13,300.00
Erect beams, columns for ground floor 6 days 294,800.00
Erection in first floor 7 days 431,400.00
Staircase erection (b/w ground and 1 st floor) 1 day 147,600.00
Erection in second floor 7 days 563,300.00
Staircase erection (b/w 1 st and 2 nd floor) 1 day 147,100.00
Erection in Third floor 7 days 709,000.00
Staircase erection (b/w 2 nd& 3 rd floor) 1 day 147,100.00
Erect parapet wall & store room 5 days 437,700.00
Final clean-up and occupancy 24.5 days 116,675.00
Flooring 10.5 days 34,425.00
Final inspections 5 days 29,750.00
TOTAL 126.5days 3,383,100.16
Civil Engineering and Urban Planning: An International Journal
Figure 7.1
Total duration of the prefabrication building is 126.5 days.
Figure 7.2
Total budget of the Prefabrication building is Rs.3,383,100.16/
8. RESULT
From the above case studies the following results are obtained.
• In this research the aim is to achieve low cost and time than In
obtain a time and cost utilization in prefabricated construction when compared to in
situ construction.
Civil Engineering and Urban Planning: An International Journal (CiVEJ) Vol.3, No.2, June 2016
Figure 7.1.Duration of Prefabricated Building
prefabrication building is 126.5 days.
Figure 7.2.Cost of Prefabricated Building
Total budget of the Prefabrication building is Rs.3,383,100.16/-
From the above case studies the following results are obtained.
In this research the aim is to achieve low cost and time than In-situ construction. We
obtain a time and cost utilization in prefabricated construction when compared to in
(CiVEJ) Vol.3, No.2, June 2016
71
situ construction. We
obtain a time and cost utilization in prefabricated construction when compared to in-
Civil Engineering and Urban Planning: An International Journal
• The time and duration requirements of the construction activitie
prefabricated construction and in
• Data’s are analyzed by means of management software Tools like MS Project 2010.
• Project schedules are decreased by 75 % compare than in
• Project budget are increased by 31% compare than traditional construction like In
site.
Figure 8.1.ComparisionOf Duration Between Pre Fabricated And Insitu
Figure 8.2.ComparisionOf Cost Between Pre Fabricated And Insitu
9. SUGGESTIONS
Based on the literatures and case
performance of construction projects.
Civil Engineering and Urban Planning: An International Journal (CiVEJ) Vol.3, No.2, June 2016
The time and duration requirements of the construction activities are determined from
prefabricated construction and in-situ construction.
Data’s are analyzed by means of management software Tools like MS Project 2010.
Project schedules are decreased by 75 % compare than in-situ- construction.
increased by 31% compare than traditional construction like In
Figure 8.1.ComparisionOf Duration Between Pre Fabricated And Insitu
Figure 8.2.ComparisionOf Cost Between Pre Fabricated And Insitu
Based on the literatures and case study, the subsequent suggestions are used to get better
performance of construction projects.
(CiVEJ) Vol.3, No.2, June 2016
72
s are determined from
Data’s are analyzed by means of management software Tools like MS Project 2010.
construction.
increased by 31% compare than traditional construction like In-
study, the subsequent suggestions are used to get better
Civil Engineering and Urban Planning: An International Journal (CiVEJ) Vol.3, No.2, June 2016
73
• In civil engineering projects, prefabrication saves engineering point in time on the
construction site. This can be fundamental to the accomplishment of projects such as
bridges and landslide galleries, where weather conditions may only permit short periods
of construction. Prefabricated bridge systems and elements offer bridge designers and
contractors considerable advantages in terms of construction time, safety, environmental
impact, constructability, and cost.
• Prefabrication can yield time savings through the ability to conduct work simultaneously
on-site and off-site, as well as helping with better coordination among different traders.
In addition, less onsite staging, such as scaffolding, is frequently involved. Regionally,
the ability to avoid weather impacts can reduce construction time.
REFERENCES
[1] Christabel M F Ho and Raymond W M Wong., April (2002) “Prefabrication Building Construction
System Adopted In Hong Kong” vol..pp383-390I.
[2] Linda Brock and James Brown APRIL (2003), “The Prefabricated House In The Twenty-First
Century: What We Can Learn From Japan?” IE (I) Journal vol.6.
[3] Adlakha PK and Shri H C Puri., APRIL (2003) “Prefabrication Building Methodologies For Low
Cost Housing” IE(I) Journal vol.84.
[4] Tam C. M (2002). “Impact on structure of labour market resulting from large-scale implementation of
prefabrication” Advanced in Building Technology. Vol. 1. Pp399-403, Hong Kong.
[5] Andrew, M., &Yali, P. (2012, April). The Rise of the Middle Class in Asian Emerging Markets.
Retrieved February 18, 2013, from KPMG:
http://www.kpmg.com/cn/en/IssuesAndInsights/ArticlesPublications/Documents/Middle-Class-Asia-
Emerging-Markets-201206-2.pdf
[6] Arno, C. (2012, May 11). CIVETS: New Global Marketing Opportunities in Emerging Economies.
Retrieved February 17, 2013, from Search Engine Watch:
http://searchenginewatch.com/article/2174005/CIVETS-New-Global-Marketing-Opportunities-in-
Emerging-Economies
[7] BBC. (2013, January 29). Vietnam profile. Retrieved February 21, 2013, from BBC:
http://www.bbc.co.uk/news/world-asia-pacific-16567315
[8] Bowman, J. (2011, May). Vietnam - a marketer's overview. Warc Exclusive.
[9] Breu, M., Salsberg, B. S., &TĂş, H. T. (2010, August). Growing up fast: Vietnam discovers the
consumer society. Retrieved February 18, 2013, from Mckinsey Quarterly:
http://www.mckinseyquarterly.com/Growing_up_fast_Vietnam_discovers_the_consumer_society_26
55
[10] Chau, Q. (2013, January 8). Gloomy market to get darker. Retrieved February 21, 2013, from
Vietnam Investment Review: http://www.vir.com.vn/news/business/property/gloomy-market-to-get-
darker.html
[11] CIA. (2013, February 11). The World Factbook: Vietnam. Retrieved February 20, 2013, from CIA
World Factbook: https://www.cia.gov/library/publications/the-world-factbook/geos/vm.html .
[12] Euromonitor. (2011, February 18). Doing Business and investing in Vietnam: challenges and
opportunities. Retrieved March 2, 2013, from Euromonitor:
http://blog.euromonitor.com/2011/02/doing-business-and-investing-in-vietnam-challenges-and-
opportunities.html
[13] Euromonitor International. (2008, February 4). The Next 11 emerging economies. Euromonitor
International.
[14] Euromonitor International. (2013, January 25). Vietnam: Country Pulse. Euromonitor International.
[15] Franzoni, J. (2012, January 5). Modular Housing in Maryland. Retrieved February 28, 2013, from
Commercial Real Estate Property News: http://realestatenewpa.blogspot.ca/2012/01/modular-
housing-in-maryland.html
[16] Global Industry Analysts. (2012, March 2). Global Prefabricated Housing Market to Reach 829
Thousand Units by 2017, According to New Report by Global Industry Analysts Inc. Retrieved
February3,2013,fromPRWeb:
Civil Engineering and Urban Planning: An International Journal (CiVEJ) Vol.3, No.2, June 2016
74
http://www.prweb.com/releases/prefabricated_housing/manufactured_modular_home/prweb9246506.
htm
[17] Global Property Guide. (2012, November 2). Vietnamese Housing Market's Amazing Slump.
Retrieved February 22, 2013, from International business Times : http : // au.ibtimes.com / articles /
400748 / 20121102 / Vietnamese -housing-market-s-amazing slump.htm#.USRE72d0RTo
[18] Industry Canada. (2010). Industry Canada. Retrieved February 3, 2013, from Data Tables: Sawmills
and Wood Preservation(NAICS 3211): http://www.ic.gc.ca/cis-sic/cis-sic.nsf/IDE/cis-
sic3211tabe.html
[19] Jeong, T. (2011, March 28). Korea: Trending towards Prefab? Retrieved February 28, 2013, from
Canada Wood: http://canadawood.org/blog/?p=149

More Related Content

What's hot

IRJET- A Comparative Study on Precast Construction and Conventional Construction
IRJET- A Comparative Study on Precast Construction and Conventional ConstructionIRJET- A Comparative Study on Precast Construction and Conventional Construction
IRJET- A Comparative Study on Precast Construction and Conventional ConstructionIRJET Journal
 
Opportunities and role of the quantity surveyor in green building project dev...
Opportunities and role of the quantity surveyor in green building project dev...Opportunities and role of the quantity surveyor in green building project dev...
Opportunities and role of the quantity surveyor in green building project dev...oyinleye
 
Resource Management, Construction labour and labour acts, safety, labour prod...
Resource Management, Construction labour and labour acts, safety, labour prod...Resource Management, Construction labour and labour acts, safety, labour prod...
Resource Management, Construction labour and labour acts, safety, labour prod...Amit Kumbar
 
Experimental study on strength characteristics of concrete with recycled aggr...
Experimental study on strength characteristics of concrete with recycled aggr...Experimental study on strength characteristics of concrete with recycled aggr...
Experimental study on strength characteristics of concrete with recycled aggr...eSAT Journals
 
IRJET- Equipment Planning and Management in Road Construction Project
IRJET- Equipment Planning and Management in Road Construction ProjectIRJET- Equipment Planning and Management in Road Construction Project
IRJET- Equipment Planning and Management in Road Construction ProjectIRJET Journal
 
IRJET-Analysis of Losses Due to Breakdown of Equipments in Construction.
IRJET-Analysis of Losses Due to Breakdown of Equipments in Construction.IRJET-Analysis of Losses Due to Breakdown of Equipments in Construction.
IRJET-Analysis of Losses Due to Breakdown of Equipments in Construction.IRJET Journal
 
التصنيع الاضافي
التصنيع الاضافيالتصنيع الاضافي
التصنيع الاضافيZainab Sattar
 
IRJET- Confluence of Lean and Offsite Construction
IRJET- Confluence of Lean and Offsite ConstructionIRJET- Confluence of Lean and Offsite Construction
IRJET- Confluence of Lean and Offsite ConstructionIRJET Journal
 
Technology and design (a brief overview)
Technology and design (a brief overview)Technology and design (a brief overview)
Technology and design (a brief overview)NGO Etnika
 
A Methodology for Parametric Production Planning in Preliminary Aircraft Desi...
A Methodology for Parametric Production Planning in Preliminary Aircraft Desi...A Methodology for Parametric Production Planning in Preliminary Aircraft Desi...
A Methodology for Parametric Production Planning in Preliminary Aircraft Desi...Chandrashekar Sundaresan
 
Project management chapter 4
Project management chapter 4Project management chapter 4
Project management chapter 4VancityInstitute
 
IRJET- Literature Review on Hauling Equipment Productivity using Cycle Time C...
IRJET- Literature Review on Hauling Equipment Productivity using Cycle Time C...IRJET- Literature Review on Hauling Equipment Productivity using Cycle Time C...
IRJET- Literature Review on Hauling Equipment Productivity using Cycle Time C...IRJET Journal
 
A Production Model for Construction: A Theoretical Framework
A Production Model for Construction: A Theoretical FrameworkA Production Model for Construction: A Theoretical Framework
A Production Model for Construction: A Theoretical FrameworkRicardo Magno Antunes
 
Building Simulation, Its Role, Softwares & Their Limitations
Building Simulation, Its Role, Softwares & Their LimitationsBuilding Simulation, Its Role, Softwares & Their Limitations
Building Simulation, Its Role, Softwares & Their LimitationsPrasad Thanthratey
 
A Review on Waste Material Minimization in Construction Industry
A Review on Waste Material Minimization in Construction IndustryA Review on Waste Material Minimization in Construction Industry
A Review on Waste Material Minimization in Construction IndustryIRJET Journal
 
Introduction to construction management
Introduction to construction managementIntroduction to construction management
Introduction to construction managementXubitech
 
IRJET- Influence of Synthetic Polymer on Fresh and Hardened Properties of PSC...
IRJET- Influence of Synthetic Polymer on Fresh and Hardened Properties of PSC...IRJET- Influence of Synthetic Polymer on Fresh and Hardened Properties of PSC...
IRJET- Influence of Synthetic Polymer on Fresh and Hardened Properties of PSC...IRJET Journal
 
IRJET- Optimization in Construction Management
IRJET-  	  Optimization in Construction ManagementIRJET-  	  Optimization in Construction Management
IRJET- Optimization in Construction ManagementIRJET Journal
 

What's hot (20)

IRJET- A Comparative Study on Precast Construction and Conventional Construction
IRJET- A Comparative Study on Precast Construction and Conventional ConstructionIRJET- A Comparative Study on Precast Construction and Conventional Construction
IRJET- A Comparative Study on Precast Construction and Conventional Construction
 
Opportunities and role of the quantity surveyor in green building project dev...
Opportunities and role of the quantity surveyor in green building project dev...Opportunities and role of the quantity surveyor in green building project dev...
Opportunities and role of the quantity surveyor in green building project dev...
 
Resource Management, Construction labour and labour acts, safety, labour prod...
Resource Management, Construction labour and labour acts, safety, labour prod...Resource Management, Construction labour and labour acts, safety, labour prod...
Resource Management, Construction labour and labour acts, safety, labour prod...
 
Experimental study on strength characteristics of concrete with recycled aggr...
Experimental study on strength characteristics of concrete with recycled aggr...Experimental study on strength characteristics of concrete with recycled aggr...
Experimental study on strength characteristics of concrete with recycled aggr...
 
D0482326
D0482326D0482326
D0482326
 
IRJET- Equipment Planning and Management in Road Construction Project
IRJET- Equipment Planning and Management in Road Construction ProjectIRJET- Equipment Planning and Management in Road Construction Project
IRJET- Equipment Planning and Management in Road Construction Project
 
IRJET-Analysis of Losses Due to Breakdown of Equipments in Construction.
IRJET-Analysis of Losses Due to Breakdown of Equipments in Construction.IRJET-Analysis of Losses Due to Breakdown of Equipments in Construction.
IRJET-Analysis of Losses Due to Breakdown of Equipments in Construction.
 
التصنيع الاضافي
التصنيع الاضافيالتصنيع الاضافي
التصنيع الاضافي
 
IRJET- Confluence of Lean and Offsite Construction
IRJET- Confluence of Lean and Offsite ConstructionIRJET- Confluence of Lean and Offsite Construction
IRJET- Confluence of Lean and Offsite Construction
 
Technology and design (a brief overview)
Technology and design (a brief overview)Technology and design (a brief overview)
Technology and design (a brief overview)
 
A Methodology for Parametric Production Planning in Preliminary Aircraft Desi...
A Methodology for Parametric Production Planning in Preliminary Aircraft Desi...A Methodology for Parametric Production Planning in Preliminary Aircraft Desi...
A Methodology for Parametric Production Planning in Preliminary Aircraft Desi...
 
H0341034041
H0341034041H0341034041
H0341034041
 
Project management chapter 4
Project management chapter 4Project management chapter 4
Project management chapter 4
 
IRJET- Literature Review on Hauling Equipment Productivity using Cycle Time C...
IRJET- Literature Review on Hauling Equipment Productivity using Cycle Time C...IRJET- Literature Review on Hauling Equipment Productivity using Cycle Time C...
IRJET- Literature Review on Hauling Equipment Productivity using Cycle Time C...
 
A Production Model for Construction: A Theoretical Framework
A Production Model for Construction: A Theoretical FrameworkA Production Model for Construction: A Theoretical Framework
A Production Model for Construction: A Theoretical Framework
 
Building Simulation, Its Role, Softwares & Their Limitations
Building Simulation, Its Role, Softwares & Their LimitationsBuilding Simulation, Its Role, Softwares & Their Limitations
Building Simulation, Its Role, Softwares & Their Limitations
 
A Review on Waste Material Minimization in Construction Industry
A Review on Waste Material Minimization in Construction IndustryA Review on Waste Material Minimization in Construction Industry
A Review on Waste Material Minimization in Construction Industry
 
Introduction to construction management
Introduction to construction managementIntroduction to construction management
Introduction to construction management
 
IRJET- Influence of Synthetic Polymer on Fresh and Hardened Properties of PSC...
IRJET- Influence of Synthetic Polymer on Fresh and Hardened Properties of PSC...IRJET- Influence of Synthetic Polymer on Fresh and Hardened Properties of PSC...
IRJET- Influence of Synthetic Polymer on Fresh and Hardened Properties of PSC...
 
IRJET- Optimization in Construction Management
IRJET-  	  Optimization in Construction ManagementIRJET-  	  Optimization in Construction Management
IRJET- Optimization in Construction Management
 

Similar to PRESENT APPLICATION OFRESOURCE MANAGEMENT IN PREFABRICATED AND IN-SITU CONSTRUCTION

IRJET- Study on Comparison of Precast and Cast In-Situ Construction of the St...
IRJET- Study on Comparison of Precast and Cast In-Situ Construction of the St...IRJET- Study on Comparison of Precast and Cast In-Situ Construction of the St...
IRJET- Study on Comparison of Precast and Cast In-Situ Construction of the St...IRJET Journal
 
Time, Cost , Productivity and Quality Analysis of Precast Buildings
Time, Cost , Productivity and Quality Analysis of Precast BuildingsTime, Cost , Productivity and Quality Analysis of Precast Buildings
Time, Cost , Productivity and Quality Analysis of Precast BuildingsIRJET Journal
 
IRJET- Analysis of Modular Housing Technique Perception and Identification it...
IRJET- Analysis of Modular Housing Technique Perception and Identification it...IRJET- Analysis of Modular Housing Technique Perception and Identification it...
IRJET- Analysis of Modular Housing Technique Perception and Identification it...IRJET Journal
 
Analyze Time-Cost Required for Conventional and Prefabricated Building Compon...
Analyze Time-Cost Required for Conventional and Prefabricated Building Compon...Analyze Time-Cost Required for Conventional and Prefabricated Building Compon...
Analyze Time-Cost Required for Conventional and Prefabricated Building Compon...IRJET Journal
 
Precast Concrete Structure
Precast Concrete StructurePrecast Concrete Structure
Precast Concrete StructureArchit Ahmad
 
IRJET- Study on Economic Sustainability of Industrial Buildings
IRJET-  	  Study on Economic Sustainability of Industrial BuildingsIRJET-  	  Study on Economic Sustainability of Industrial Buildings
IRJET- Study on Economic Sustainability of Industrial BuildingsIRJET Journal
 
Cost and Quality Management in Buildings
Cost and Quality Management in BuildingsCost and Quality Management in Buildings
Cost and Quality Management in BuildingsIRJET Journal
 
IRJET- Comparative Study between RCC Structures and Prefabricated Structures
IRJET- Comparative Study between RCC Structures and Prefabricated StructuresIRJET- Comparative Study between RCC Structures and Prefabricated Structures
IRJET- Comparative Study between RCC Structures and Prefabricated StructuresIRJET Journal
 
Performance Evaluation of Cost Saving Towards Sustainability in Traditional C...
Performance Evaluation of Cost Saving Towards Sustainability in Traditional C...Performance Evaluation of Cost Saving Towards Sustainability in Traditional C...
Performance Evaluation of Cost Saving Towards Sustainability in Traditional C...IJRESJOURNAL
 
A STUDY ON THE QUALITATIVE ANALYSIS OF MATERIALS MANAGEMENT IN KERALA CONSTRU...
A STUDY ON THE QUALITATIVE ANALYSIS OF MATERIALS MANAGEMENT IN KERALA CONSTRU...A STUDY ON THE QUALITATIVE ANALYSIS OF MATERIALS MANAGEMENT IN KERALA CONSTRU...
A STUDY ON THE QUALITATIVE ANALYSIS OF MATERIALS MANAGEMENT IN KERALA CONSTRU...IRJET Journal
 
IRJET - Failure in Commercial Building and Management - Case Study
IRJET - Failure in Commercial Building and Management - Case StudyIRJET - Failure in Commercial Building and Management - Case Study
IRJET - Failure in Commercial Building and Management - Case StudyIRJET Journal
 
Off-site and on -site modern method of construction
Off-site and on -site modern method of constructionOff-site and on -site modern method of construction
Off-site and on -site modern method of constructionANNA REBECCA PRASAD
 
IIRJET-Cost Control Techniques for Construction Project
IIRJET-Cost Control Techniques for Construction ProjectIIRJET-Cost Control Techniques for Construction Project
IIRJET-Cost Control Techniques for Construction ProjectIRJET Journal
 
Modern methods of constructions and their impact upon estimation of cost plan...
Modern methods of constructions and their impact upon estimation of cost plan...Modern methods of constructions and their impact upon estimation of cost plan...
Modern methods of constructions and their impact upon estimation of cost plan...NellutlaKishore
 
Effects of Construction Materials to Achieve Sustainable Buildings
Effects of Construction Materials to Achieve Sustainable BuildingsEffects of Construction Materials to Achieve Sustainable Buildings
Effects of Construction Materials to Achieve Sustainable BuildingsDr. Amarjeet Singh
 
Analytical Comparison between Conventional Construction Technique and Precast...
Analytical Comparison between Conventional Construction Technique and Precast...Analytical Comparison between Conventional Construction Technique and Precast...
Analytical Comparison between Conventional Construction Technique and Precast...ijtsrd
 
IRJET- Application of Decision Making Tool in Sustainable Construction
IRJET- Application of Decision Making Tool in Sustainable ConstructionIRJET- Application of Decision Making Tool in Sustainable Construction
IRJET- Application of Decision Making Tool in Sustainable ConstructionIRJET Journal
 
1.construction plant
1.construction plant1.construction plant
1.construction plantlibfsb
 

Similar to PRESENT APPLICATION OFRESOURCE MANAGEMENT IN PREFABRICATED AND IN-SITU CONSTRUCTION (20)

IRJET- Study on Comparison of Precast and Cast In-Situ Construction of the St...
IRJET- Study on Comparison of Precast and Cast In-Situ Construction of the St...IRJET- Study on Comparison of Precast and Cast In-Situ Construction of the St...
IRJET- Study on Comparison of Precast and Cast In-Situ Construction of the St...
 
A PRESENTATION ON PREFABRICATED STRUCTURES
A PRESENTATION ON PREFABRICATED STRUCTURES A PRESENTATION ON PREFABRICATED STRUCTURES
A PRESENTATION ON PREFABRICATED STRUCTURES
 
Time, Cost , Productivity and Quality Analysis of Precast Buildings
Time, Cost , Productivity and Quality Analysis of Precast BuildingsTime, Cost , Productivity and Quality Analysis of Precast Buildings
Time, Cost , Productivity and Quality Analysis of Precast Buildings
 
IRJET- Analysis of Modular Housing Technique Perception and Identification it...
IRJET- Analysis of Modular Housing Technique Perception and Identification it...IRJET- Analysis of Modular Housing Technique Perception and Identification it...
IRJET- Analysis of Modular Housing Technique Perception and Identification it...
 
Analyze Time-Cost Required for Conventional and Prefabricated Building Compon...
Analyze Time-Cost Required for Conventional and Prefabricated Building Compon...Analyze Time-Cost Required for Conventional and Prefabricated Building Compon...
Analyze Time-Cost Required for Conventional and Prefabricated Building Compon...
 
Precast Concrete Structure
Precast Concrete StructurePrecast Concrete Structure
Precast Concrete Structure
 
IRJET- Study on Economic Sustainability of Industrial Buildings
IRJET-  	  Study on Economic Sustainability of Industrial BuildingsIRJET-  	  Study on Economic Sustainability of Industrial Buildings
IRJET- Study on Economic Sustainability of Industrial Buildings
 
Cost and Quality Management in Buildings
Cost and Quality Management in BuildingsCost and Quality Management in Buildings
Cost and Quality Management in Buildings
 
IRJET- Comparative Study between RCC Structures and Prefabricated Structures
IRJET- Comparative Study between RCC Structures and Prefabricated StructuresIRJET- Comparative Study between RCC Structures and Prefabricated Structures
IRJET- Comparative Study between RCC Structures and Prefabricated Structures
 
Performance Evaluation of Cost Saving Towards Sustainability in Traditional C...
Performance Evaluation of Cost Saving Towards Sustainability in Traditional C...Performance Evaluation of Cost Saving Towards Sustainability in Traditional C...
Performance Evaluation of Cost Saving Towards Sustainability in Traditional C...
 
A STUDY ON THE QUALITATIVE ANALYSIS OF MATERIALS MANAGEMENT IN KERALA CONSTRU...
A STUDY ON THE QUALITATIVE ANALYSIS OF MATERIALS MANAGEMENT IN KERALA CONSTRU...A STUDY ON THE QUALITATIVE ANALYSIS OF MATERIALS MANAGEMENT IN KERALA CONSTRU...
A STUDY ON THE QUALITATIVE ANALYSIS OF MATERIALS MANAGEMENT IN KERALA CONSTRU...
 
IRJET - Failure in Commercial Building and Management - Case Study
IRJET - Failure in Commercial Building and Management - Case StudyIRJET - Failure in Commercial Building and Management - Case Study
IRJET - Failure in Commercial Building and Management - Case Study
 
Off-site and on -site modern method of construction
Off-site and on -site modern method of constructionOff-site and on -site modern method of construction
Off-site and on -site modern method of construction
 
B1303020508
B1303020508B1303020508
B1303020508
 
IIRJET-Cost Control Techniques for Construction Project
IIRJET-Cost Control Techniques for Construction ProjectIIRJET-Cost Control Techniques for Construction Project
IIRJET-Cost Control Techniques for Construction Project
 
Modern methods of constructions and their impact upon estimation of cost plan...
Modern methods of constructions and their impact upon estimation of cost plan...Modern methods of constructions and their impact upon estimation of cost plan...
Modern methods of constructions and their impact upon estimation of cost plan...
 
Effects of Construction Materials to Achieve Sustainable Buildings
Effects of Construction Materials to Achieve Sustainable BuildingsEffects of Construction Materials to Achieve Sustainable Buildings
Effects of Construction Materials to Achieve Sustainable Buildings
 
Analytical Comparison between Conventional Construction Technique and Precast...
Analytical Comparison between Conventional Construction Technique and Precast...Analytical Comparison between Conventional Construction Technique and Precast...
Analytical Comparison between Conventional Construction Technique and Precast...
 
IRJET- Application of Decision Making Tool in Sustainable Construction
IRJET- Application of Decision Making Tool in Sustainable ConstructionIRJET- Application of Decision Making Tool in Sustainable Construction
IRJET- Application of Decision Making Tool in Sustainable Construction
 
1.construction plant
1.construction plant1.construction plant
1.construction plant
 

Recently uploaded

GenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day PresentationGenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day PresentationMichael W. Hawkins
 
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...Igalia
 
🐬 The future of MySQL is Postgres 🐘
🐬  The future of MySQL is Postgres   🐘🐬  The future of MySQL is Postgres   🐘
🐬 The future of MySQL is Postgres 🐘RTylerCroy
 
How to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerHow to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerThousandEyes
 
Data Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt RobisonData Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt RobisonAnna Loughnan Colquhoun
 
Workshop - Best of Both Worlds_ Combine KG and Vector search for enhanced R...
Workshop - Best of Both Worlds_ Combine  KG and Vector search for  enhanced R...Workshop - Best of Both Worlds_ Combine  KG and Vector search for  enhanced R...
Workshop - Best of Both Worlds_ Combine KG and Vector search for enhanced R...Neo4j
 
Histor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slideHistor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slidevu2urc
 
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...apidays
 
Top 5 Benefits OF Using Muvi Live Paywall For Live Streams
Top 5 Benefits OF Using Muvi Live Paywall For Live StreamsTop 5 Benefits OF Using Muvi Live Paywall For Live Streams
Top 5 Benefits OF Using Muvi Live Paywall For Live StreamsRoshan Dwivedi
 
TrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law DevelopmentsTrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law DevelopmentsTrustArc
 
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...Drew Madelung
 
08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking MenDelhi Call girls
 
IAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsIAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsEnterprise Knowledge
 
Driving Behavioral Change for Information Management through Data-Driven Gree...
Driving Behavioral Change for Information Management through Data-Driven Gree...Driving Behavioral Change for Information Management through Data-Driven Gree...
Driving Behavioral Change for Information Management through Data-Driven Gree...Enterprise Knowledge
 
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptxEIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptxEarley Information Science
 
Slack Application Development 101 Slides
Slack Application Development 101 SlidesSlack Application Development 101 Slides
Slack Application Development 101 Slidespraypatel2
 
Unblocking The Main Thread Solving ANRs and Frozen Frames
Unblocking The Main Thread Solving ANRs and Frozen FramesUnblocking The Main Thread Solving ANRs and Frozen Frames
Unblocking The Main Thread Solving ANRs and Frozen FramesSinan KOZAK
 
Boost PC performance: How more available memory can improve productivity
Boost PC performance: How more available memory can improve productivityBoost PC performance: How more available memory can improve productivity
Boost PC performance: How more available memory can improve productivityPrincipled Technologies
 
Automating Google Workspace (GWS) & more with Apps Script
Automating Google Workspace (GWS) & more with Apps ScriptAutomating Google Workspace (GWS) & more with Apps Script
Automating Google Workspace (GWS) & more with Apps Scriptwesley chun
 
CNv6 Instructor Chapter 6 Quality of Service
CNv6 Instructor Chapter 6 Quality of ServiceCNv6 Instructor Chapter 6 Quality of Service
CNv6 Instructor Chapter 6 Quality of Servicegiselly40
 

Recently uploaded (20)

GenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day PresentationGenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day Presentation
 
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
 
🐬 The future of MySQL is Postgres 🐘
🐬  The future of MySQL is Postgres   🐘🐬  The future of MySQL is Postgres   🐘
🐬 The future of MySQL is Postgres 🐘
 
How to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerHow to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected Worker
 
Data Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt RobisonData Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt Robison
 
Workshop - Best of Both Worlds_ Combine KG and Vector search for enhanced R...
Workshop - Best of Both Worlds_ Combine  KG and Vector search for  enhanced R...Workshop - Best of Both Worlds_ Combine  KG and Vector search for  enhanced R...
Workshop - Best of Both Worlds_ Combine KG and Vector search for enhanced R...
 
Histor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slideHistor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slide
 
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
 
Top 5 Benefits OF Using Muvi Live Paywall For Live Streams
Top 5 Benefits OF Using Muvi Live Paywall For Live StreamsTop 5 Benefits OF Using Muvi Live Paywall For Live Streams
Top 5 Benefits OF Using Muvi Live Paywall For Live Streams
 
TrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law DevelopmentsTrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
 
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
 
08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men
 
IAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsIAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI Solutions
 
Driving Behavioral Change for Information Management through Data-Driven Gree...
Driving Behavioral Change for Information Management through Data-Driven Gree...Driving Behavioral Change for Information Management through Data-Driven Gree...
Driving Behavioral Change for Information Management through Data-Driven Gree...
 
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptxEIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
 
Slack Application Development 101 Slides
Slack Application Development 101 SlidesSlack Application Development 101 Slides
Slack Application Development 101 Slides
 
Unblocking The Main Thread Solving ANRs and Frozen Frames
Unblocking The Main Thread Solving ANRs and Frozen FramesUnblocking The Main Thread Solving ANRs and Frozen Frames
Unblocking The Main Thread Solving ANRs and Frozen Frames
 
Boost PC performance: How more available memory can improve productivity
Boost PC performance: How more available memory can improve productivityBoost PC performance: How more available memory can improve productivity
Boost PC performance: How more available memory can improve productivity
 
Automating Google Workspace (GWS) & more with Apps Script
Automating Google Workspace (GWS) & more with Apps ScriptAutomating Google Workspace (GWS) & more with Apps Script
Automating Google Workspace (GWS) & more with Apps Script
 
CNv6 Instructor Chapter 6 Quality of Service
CNv6 Instructor Chapter 6 Quality of ServiceCNv6 Instructor Chapter 6 Quality of Service
CNv6 Instructor Chapter 6 Quality of Service
 

PRESENT APPLICATION OFRESOURCE MANAGEMENT IN PREFABRICATED AND IN-SITU CONSTRUCTION

  • 1. Civil Engineering and Urban Planning: An International Journal (CiVEJ) Vol.3, No.2, June 2016 DOI:10.5121/civej.2016.3205 63 PRESENT APPLICATION OFRESOURCE MANAGEMENT IN PREFABRICATED AND IN-SITU CONSTRUCTION V.Yuvaraj1 and R.Dharman2 , 1 PG Scholar, M.E Construction Engineering and Management, 2 Assistant Professor, Department of Civil Engineering, Shree Venkateshwara Hi-Tech Engineering College, Gobi, Tamil Nadu, India. ABSTRACT Currently, prefabricated building plays a leading role in construction. Mounting with the standardization and mechanization, Prefabrication has brought an extensive transformation in the construction industry around the world. Moreover the associated advancements to the local construction industry with the espousal of more mechanization, intelligent management systems and computer aided manufacturing; the wide-ranging use of prefabrication also contributes to sustainable development by means of cleaner and more resources saving production process. The main aim of this paper is to present a prefabricated construction based on time and cost utilization over than in-situ construction. Also forecast the general idea about the development and application of prefabrication method in the construction of large-scale and high-rise buildings. The factors like time and cost are analyzed in normal construction and in prefabricated construction companies. The results are shown by using management software tools. KEYWORDS In-situ construction, prefabricated construction, Quality, Time, Cost. 1. INTRODUCTION For many years prefabrication has been used comprehensively and commonly over the world wide. The manufacture of building components are often illustrated by the terms such as prefabrication, pre-assembly, system building, industrialized buildings and modularization which are constructed on any like on site/off-site in an industrial unit covering modular, manufactured and pre-cut/pre- engineered systems. Although the conditions/terms, are normally used correspondingly, their specific definitions depend deeply on the users’ experience and indulgent, which differ from countries to countries. In this paper, prefabrication is chosen with extra prominence on the building components which are made off-site in an industrial unit. Off-site fabrication is an area of international significance and provides an efficient construction technique in terms of time, quality, cost, productivity, safety and function. It is adopted globally as the ultimate resources of producing an enormous range of elements from cladding units, structural members and bathrooms to fully-finished modular buildings. A General Review of Prefabrication Adopted in India, if the building materials are concrete, steel or timber based system, the benefits of prefabricated building systems must be obvious. It is an industrialized way of construction, with the inbuilt advantages of: • High capacity - enabling the understanding of important projects • Factory made products • Independent of unfavorable weather circumstances during construction • Quality observation/surveillance system • Shorter construction period - below half of conventional cast in-situ construction.
  • 2. Civil Engineering and Urban Planning: An International Journal Since the main goal of prefabrication is to consequence economy, enhancement in quality and speed in construction, the choice of proper materials for prefabrication is also a significant feature in the development of this technique. The use of locally existing materials with essential characteristics and also owing to their inherent characteristics such as easy workability/flexibility, light-weight, non economy and enhanced quality may be tried in prefabrication. In civil engineering projects, prefabrication saves engineering point in time on the construction site. This can be fundamental to the accomplishment of projects such as bridges and landslide galleries, where weather conditions may only permit short periods of construction. Prefabricated bridge systems and elements offer bridge designers and contractors considerable advantages in terms of construction time, safety, environmental impact, constructab cost. Figure 1. shows the comparison between the In buildings in construction fields. Figure 1.1. Advantages of Prefabricated buildings over In 1.1. Time Prefabrication can give way to save timings through the capability to carry out work concurrently on-site and off-site, in addition to helping with enhanced management with different traders. Additionally, less onsite performance, such as scaffolding, is r capacity to stay away from weather impacts can lessen construction time. Site conditions issue considerably in the facility of prefabrication to crash schedule. Civil Engineering and Urban Planning: An International Journal (CiVEJ) Vol.3, No.2, June 2016 Since the main goal of prefabrication is to consequence economy, enhancement in quality and speed in construction, the choice of proper materials for prefabrication is also a significant he development of this technique. The use of locally existing materials with essential characteristics and also owing to their inherent characteristics such as easy weight, non-combustibility and thermal insulation, effect onomy and enhanced quality may be tried in prefabrication. In civil engineering projects, prefabrication saves engineering point in time on the construction site. This can be fundamental to the accomplishment of projects such as bridges and landslide eries, where weather conditions may only permit short periods of construction. Prefabricated bridge systems and elements offer bridge designers and contractors considerable advantages in terms of construction time, safety, environmental impact, constructab shows the comparison between the In-situ buildings and the proposed prefabricated buildings in construction fields. . Advantages of Prefabricated buildings over In-situ buildings Prefabrication can give way to save timings through the capability to carry out work concurrently site, in addition to helping with enhanced management with different traders. Additionally, less onsite performance, such as scaffolding, is regularly concerned. Regionally, the capacity to stay away from weather impacts can lessen construction time. Site conditions issue considerably in the facility of prefabrication to crash schedule. (CiVEJ) Vol.3, No.2, June 2016 64 Since the main goal of prefabrication is to consequence economy, enhancement in quality and speed in construction, the choice of proper materials for prefabrication is also a significant he development of this technique. The use of locally existing materials with essential characteristics and also owing to their inherent characteristics such as easy combustibility and thermal insulation, effect In civil engineering projects, prefabrication saves engineering point in time on the construction site. This can be fundamental to the accomplishment of projects such as bridges and landslide eries, where weather conditions may only permit short periods of construction. Prefabricated bridge systems and elements offer bridge designers and contractors considerable advantages in terms of construction time, safety, environmental impact, constructability, and situ buildings and the proposed prefabricated Prefabrication can give way to save timings through the capability to carry out work concurrently site, in addition to helping with enhanced management with different traders. egularly concerned. Regionally, the capacity to stay away from weather impacts can lessen construction time. Site conditions issue
  • 3. Civil Engineering and Urban Planning: An International Journal (CiVEJ) Vol.3, No.2, June 2016 65 Currently, Two-thirds of Construction firms which uses modularization /prefabrication observed that prefabrication reduces the schedule of the project up to 35% i.e., four weeks or more. On difficult/complex projects to coordinate the use of prefabrication and modularization, extra time may be used up in the design phase. On the other hand, the time saved onsite normally reduces the whole project schedule. 1.2.Cost As an outcome of using prefabrication/modularization, vendor report of project cost decrease ranging from 2% to 40%. A number of owners for these cheap costs consist of: • Possibly Local labors are very expensive or inefficient for onsite work. • Costly delays may occur due to unfavorable onsite environmentand weather troubles. cost related with onsite infrastructure and overhead can be reduced by relocating some or all of the work to an off-site locality as some owners statement . Furthermore they state that smaller number of workers onsite render to fewer costs for housing, scheduling onsite work and additional onsite logistics. For prefabrication /modularization, labor costs can be a vital factor. Owners point out that pre- fabrication/modularization offers a less pricey alternative for very high local labor cost areas. 1.3.Quality Quality control forms a primary part of precast construction. A proficient quality method is most significant in the accumulation making of precast components in every project. The quality control system implemented in a precast industrial unit is discussed in this study. The precast industrial unit is set up for the production of large scale buildings.Processes in the precast production are proposed with respect to the quality control procedures in the quality inspection plan. The standard tests like concerned roles of inspectors and corrective actions on- site are tinted. Serious issues pertaining to the quality and productivity of precast manufacture are reviewed. These consist of the quality of maintenance and staff, which possibly will potentially have an effect on the effectiveness of the quality system. Various considerations are supposed to also be given to develop the workflow and efficiency of the factory. 2. NEED FOR STUDY In the current situation the construction of buildings are very difficult thing around the world due to over contest and necessities of client requirements.Quality of On-site buildings are mainly affected by several reasons like poor quality of materials, environmental factors, wastage of materials, etc..,. This proposal will used to recognize factors for good quality of production/ construction at low cost.
  • 4. Civil Engineering and Urban Planning: An International Journal (CiVEJ) Vol.3, No.2, June 2016 66 3. OBJECTIVES To Study on efficient deployment of Cost in Prefabricated and In-situ buildings. To Study on efficient exploitation of Time in Prefabricated and In-situ buildings. To Study on Quality of prefabricated and In-situ buildings. Making a Study about the methodology adopted in the manufacturing of prefabrication construction. Management of Resources in Prefab and In-situ construction using Software. To study on comparison of Duration, Cost, and Quality of prefabricated and In-situ buildings. 4. LITERATURE REVIEW Based on the Prefabrication literatures are collected. From the review various factors were recognized.The literatures together are being used as base for the further procedures in the project. The author [1] Christabel M F Ho, Raymond W M Wong., emphasizes that • Mass production prefabricated building components (precast façade, precast stair flight, drywall and semi-precast floor planking) reduce cost and save time, with added advantage of taking some of the most dirty and awesome work out of the process. • Faster erection capabilities and fewer manpower requirements make prefabrication the most viable option for public housing construction in Hong Kong. • According to the study carried out by Tam (2002), there could be a 43 percent reduction in site labor consumption if there is a shift from the in-situ site casting to prefabrication design. At the same time, prefabrication offers clients better performance to fulfill all requirements, such as: • Opportunities for good architecture • Fire resistant material • Healthy buildings • Reduced energy consumption through the ability to store heat in the concrete mass • Environmentally friendly way of building with optimum use of materials, recycling of waste products, less noise and dust etc. The authors Linda Brock, James Brown [2] stated that, • In Canada, manufactured housing simply means that 85 percent or more of the construction is completed in a factory. • In fact, 24 percent of new housing starts in 1996 were manufactured-mobile houses; only 2 percent to 3 percent were other prefabricated styles (such as modular housing). • In the same year in Canada, all styles of prefabricated homes represented only 7.5 percent of the market, with two-thirds of these homes being single modules.
  • 5. Civil Engineering and Urban Planning: An International Journal (CiVEJ) Vol.3, No.2, June 2016 67 Shri P K Adlakha, Shri H C Puri [3] describes prefabrication as In India, adoption of prefabrication building techniques has many merits in the context of availability of materials, labor and technical skills. Advantages of prefabrication are: • In prefabricated construction, as the components are readymade, self supporting, shuttering and scaffolding is eliminated with a saving in shuttering cost. • In traditional construction, the repetitive use of shuttering is limited, as it gets damaged due to frequent cutting, nailing etc. On the other hand, the mould for the precast components can be used for large number of repetitions thereby reducing, the cost of the mould per unit. • In prefabricated housing system, there is saving of time as the elements can be casted before hand during the course of foundations being laid and even after laying slab, the finishes and services can be done below the slab immediately. While in the conventional in-situ RCC slabs, due to props and shuttering, the work cannot be done, till they are removed. Saving of time means saving of money. • In prefabricated construction, there is better quality control, shape and size of precast elements. Therefore, in structural design, full advantage of properties of cement and steel can be exploited. • In precast construction, similar type of components is produced repeatedly, resulting in increased productivity and economy in cost too. • In precast construction, the construction is not affected due to weather, rain, wind etc 5. METHODOLOGY With the intention to get the details associated to prefabricated construction uses along with their safety procedure and different methods of production literature study and the study of codes and regulation were prepared. The flowchart below represents the methodology adopted for the proposed work. After reviewing the literature the industry/company where the work is to be adopted is identified. Then the data’s from the industry/company are collected and analyzed. Figure 5.1. Work Flow Diagram
  • 6. Civil Engineering and Urban Planning: An International Journal (CiVEJ) Vol.3, No.2, June 2016 68 6. CASE STUDY ON IN-SITU BUILDING Raj Associates has plans to build a multi-storeyed construction in the main area of the city. In building construction bunch of work packages and activities are mixed up. Making an effort to use the resource optimistically and also to lessen the time and cost. The activities for customizing different functional areas are declared as work packages and their relationship are specified. 6.1.Stages Of Work General condition Procurement of materials Site preparation Arrangement of site Work on foundation Erection of structures Steel erection in 2 & 3 floor Plumbing work Work on roofs Installation of windows Finishing of building Final clean-up and occupation Works on floor Final inspection Table 6.1. Stages of Work for In-situ building
  • 7. Civil Engineering and Urban Planning: An International Journal Total duration of the Institutions building is 347 days. Total budget of the In-situ building is Rs. 2,096,189.33/ 7. CASE STUDY ON PREFABRICATED Teemage Precast Pvt. Ltd. plans to build a multi city. In building construction bunch of work packages and activities are effort to use the resource optimistically and also to lessen the time and cost. The activities for customizing different functional areas are declared as work packages and their relationship are specified. Civil Engineering and Urban Planning: An International Journal (CiVEJ) Vol.3, No.2, June 2016 Figure 6.1. Duration of Project building is 347 days. Figure 6.2. Cost of Project situ building is Rs. 2,096,189.33/- REFABRICATED BUILDING Teemage Precast Pvt. Ltd. plans to build a multi-storeyed construction in the main area of the city. In building construction bunch of work packages and activities are mixed up. Making an effort to use the resource optimistically and also to lessen the time and cost. The activities for customizing different functional areas are declared as work packages and their relationship are (CiVEJ) Vol.3, No.2, June 2016 69 storeyed construction in the main area of the mixed up. Making an effort to use the resource optimistically and also to lessen the time and cost. The activities for customizing different functional areas are declared as work packages and their relationship are
  • 8. Civil Engineering and Urban Planning: An International Journal (CiVEJ) Vol.3, No.2, June 2016 70 7.1. Stages Of Work General condition Procurement of materials Site preparation Arrangement of site Work on foundation Erection of structures Steel erection in 2 & 3 floor Plumbing work Work on roofs Installation of windows Finishing of building Final clean-up and occupation Works on floor Final inspection Table 7.1. Stages of Work of prefabricated building Task Name Duration Cost General condition 5 days 38,500.00 Procurement of materials 20 days 147,750.00 Site setting 16 days 87,500.00 Site preparation 6.5 days 37,200.00 Preparation of foundation 4 days 13,300.00 Erect beams, columns for ground floor 6 days 294,800.00 Erection in first floor 7 days 431,400.00 Staircase erection (b/w ground and 1 st floor) 1 day 147,600.00 Erection in second floor 7 days 563,300.00 Staircase erection (b/w 1 st and 2 nd floor) 1 day 147,100.00 Erection in Third floor 7 days 709,000.00 Staircase erection (b/w 2 nd& 3 rd floor) 1 day 147,100.00 Erect parapet wall & store room 5 days 437,700.00 Final clean-up and occupancy 24.5 days 116,675.00 Flooring 10.5 days 34,425.00 Final inspections 5 days 29,750.00 TOTAL 126.5days 3,383,100.16
  • 9. Civil Engineering and Urban Planning: An International Journal Figure 7.1 Total duration of the prefabrication building is 126.5 days. Figure 7.2 Total budget of the Prefabrication building is Rs.3,383,100.16/ 8. RESULT From the above case studies the following results are obtained. • In this research the aim is to achieve low cost and time than In obtain a time and cost utilization in prefabricated construction when compared to in situ construction. Civil Engineering and Urban Planning: An International Journal (CiVEJ) Vol.3, No.2, June 2016 Figure 7.1.Duration of Prefabricated Building prefabrication building is 126.5 days. Figure 7.2.Cost of Prefabricated Building Total budget of the Prefabrication building is Rs.3,383,100.16/- From the above case studies the following results are obtained. In this research the aim is to achieve low cost and time than In-situ construction. We obtain a time and cost utilization in prefabricated construction when compared to in (CiVEJ) Vol.3, No.2, June 2016 71 situ construction. We obtain a time and cost utilization in prefabricated construction when compared to in-
  • 10. Civil Engineering and Urban Planning: An International Journal • The time and duration requirements of the construction activitie prefabricated construction and in • Data’s are analyzed by means of management software Tools like MS Project 2010. • Project schedules are decreased by 75 % compare than in • Project budget are increased by 31% compare than traditional construction like In site. Figure 8.1.ComparisionOf Duration Between Pre Fabricated And Insitu Figure 8.2.ComparisionOf Cost Between Pre Fabricated And Insitu 9. SUGGESTIONS Based on the literatures and case performance of construction projects. Civil Engineering and Urban Planning: An International Journal (CiVEJ) Vol.3, No.2, June 2016 The time and duration requirements of the construction activities are determined from prefabricated construction and in-situ construction. Data’s are analyzed by means of management software Tools like MS Project 2010. Project schedules are decreased by 75 % compare than in-situ- construction. increased by 31% compare than traditional construction like In Figure 8.1.ComparisionOf Duration Between Pre Fabricated And Insitu Figure 8.2.ComparisionOf Cost Between Pre Fabricated And Insitu Based on the literatures and case study, the subsequent suggestions are used to get better performance of construction projects. (CiVEJ) Vol.3, No.2, June 2016 72 s are determined from Data’s are analyzed by means of management software Tools like MS Project 2010. construction. increased by 31% compare than traditional construction like In- study, the subsequent suggestions are used to get better
  • 11. Civil Engineering and Urban Planning: An International Journal (CiVEJ) Vol.3, No.2, June 2016 73 • In civil engineering projects, prefabrication saves engineering point in time on the construction site. This can be fundamental to the accomplishment of projects such as bridges and landslide galleries, where weather conditions may only permit short periods of construction. Prefabricated bridge systems and elements offer bridge designers and contractors considerable advantages in terms of construction time, safety, environmental impact, constructability, and cost. • Prefabrication can yield time savings through the ability to conduct work simultaneously on-site and off-site, as well as helping with better coordination among different traders. In addition, less onsite staging, such as scaffolding, is frequently involved. Regionally, the ability to avoid weather impacts can reduce construction time. REFERENCES [1] Christabel M F Ho and Raymond W M Wong., April (2002) “Prefabrication Building Construction System Adopted In Hong Kong” vol..pp383-390I. [2] Linda Brock and James Brown APRIL (2003), “The Prefabricated House In The Twenty-First Century: What We Can Learn From Japan?” IE (I) Journal vol.6. [3] Adlakha PK and Shri H C Puri., APRIL (2003) “Prefabrication Building Methodologies For Low Cost Housing” IE(I) Journal vol.84. [4] Tam C. M (2002). “Impact on structure of labour market resulting from large-scale implementation of prefabrication” Advanced in Building Technology. Vol. 1. Pp399-403, Hong Kong. [5] Andrew, M., &Yali, P. (2012, April). The Rise of the Middle Class in Asian Emerging Markets. Retrieved February 18, 2013, from KPMG: http://www.kpmg.com/cn/en/IssuesAndInsights/ArticlesPublications/Documents/Middle-Class-Asia- Emerging-Markets-201206-2.pdf [6] Arno, C. (2012, May 11). CIVETS: New Global Marketing Opportunities in Emerging Economies. Retrieved February 17, 2013, from Search Engine Watch: http://searchenginewatch.com/article/2174005/CIVETS-New-Global-Marketing-Opportunities-in- Emerging-Economies [7] BBC. (2013, January 29). Vietnam profile. Retrieved February 21, 2013, from BBC: http://www.bbc.co.uk/news/world-asia-pacific-16567315 [8] Bowman, J. (2011, May). Vietnam - a marketer's overview. Warc Exclusive. [9] Breu, M., Salsberg, B. S., &TĂş, H. T. (2010, August). Growing up fast: Vietnam discovers the consumer society. Retrieved February 18, 2013, from Mckinsey Quarterly: http://www.mckinseyquarterly.com/Growing_up_fast_Vietnam_discovers_the_consumer_society_26 55 [10] Chau, Q. (2013, January 8). Gloomy market to get darker. Retrieved February 21, 2013, from Vietnam Investment Review: http://www.vir.com.vn/news/business/property/gloomy-market-to-get- darker.html [11] CIA. (2013, February 11). The World Factbook: Vietnam. Retrieved February 20, 2013, from CIA World Factbook: https://www.cia.gov/library/publications/the-world-factbook/geos/vm.html . [12] Euromonitor. (2011, February 18). Doing Business and investing in Vietnam: challenges and opportunities. Retrieved March 2, 2013, from Euromonitor: http://blog.euromonitor.com/2011/02/doing-business-and-investing-in-vietnam-challenges-and- opportunities.html [13] Euromonitor International. (2008, February 4). The Next 11 emerging economies. Euromonitor International. [14] Euromonitor International. (2013, January 25). Vietnam: Country Pulse. Euromonitor International. [15] Franzoni, J. (2012, January 5). Modular Housing in Maryland. Retrieved February 28, 2013, from Commercial Real Estate Property News: http://realestatenewpa.blogspot.ca/2012/01/modular- housing-in-maryland.html [16] Global Industry Analysts. (2012, March 2). Global Prefabricated Housing Market to Reach 829 Thousand Units by 2017, According to New Report by Global Industry Analysts Inc. Retrieved February3,2013,fromPRWeb:
  • 12. Civil Engineering and Urban Planning: An International Journal (CiVEJ) Vol.3, No.2, June 2016 74 http://www.prweb.com/releases/prefabricated_housing/manufactured_modular_home/prweb9246506. htm [17] Global Property Guide. (2012, November 2). Vietnamese Housing Market's Amazing Slump. Retrieved February 22, 2013, from International business Times : http : // au.ibtimes.com / articles / 400748 / 20121102 / Vietnamese -housing-market-s-amazing slump.htm#.USRE72d0RTo [18] Industry Canada. (2010). Industry Canada. Retrieved February 3, 2013, from Data Tables: Sawmills and Wood Preservation(NAICS 3211): http://www.ic.gc.ca/cis-sic/cis-sic.nsf/IDE/cis- sic3211tabe.html [19] Jeong, T. (2011, March 28). Korea: Trending towards Prefab? Retrieved February 28, 2013, from Canada Wood: http://canadawood.org/blog/?p=149