1. Partnership To Advance Clean Energy-Deployment (PACE-D)
Technical Assistance Program
Presented by
USAID PACE-D TA Program
Apr-18
Solar PV Rooftop Training Program For Entrepreneurs
Session:
Contract Structure & Agreement
5. Project Management Fundamentals
What is Project Management?
Application of knowledge, skills, tools and techniques to a project activities to
meet project requirements
Achieved through 5 Process Groups
Initiation Planning Executing Monitoring
and control
Closing
scope
plan Actions by
respective
functions
control
delivery
6. Project Management Fundamentals
Major steps illustrated:
Identifying requirements
Addressing various needs,
concerns and expectations
at all stages of project
Balancing
Project
Constraints
Scope
Quality
Schedule
Budget
Resources
Risk
7. SPVRT Project Management Overview
Tight timelines
Tighter budgets
Lack of homework for getting projects sanctioned
Limited experience of online projects
Limited availability of specialized manpower and expertise
Entry of first timers – developers, EPC companies, consultants, financial institutes
Entry of foreign companies – suppliers, investors, developers, contractors
8. SPVRT Project Management Overview
Components required in successful delivery of a Solar PV project:
Modules
Thin Film – aSi, CIGS, CdS-CdTe
Crystalline – Mono, Poly
Mounting – Fixed, Single axis, Double axis
Inverters – Central, String
Cables and connectors
Earthing for different components
Lightning protection
Data monitoring and weather station
Locations – Spread over India, temperatures, dust, water
Surfaces – Roof, Ground (Rocky, Hard Murum, Clayee, Ash)
Interconnection – HT at different voltages
Executers – Manufacturers, EPC contractors, I&C contractors
9. Selection Criteria for SPVRT Components for a
Project
Components
Technical
Factors
Performance
Variables
Quality Risks Service Needs
Solar Modules
Temperature
coefficient
Tolerance levels
in supply
PID effect; EL
testing
Lamination, cells,
JB, frame
Inverter
Efficiency at part
load
Temperature
effect on
performance
Dust factor
Component
replacability and
availability
Structure
Galvanizing over
worked steel
Flexibility and
rigidity
Fixing stability to
the ground
Alignments,
maintenance
requirements
Cabling UV resistance
Resistance to
temperature,
moisture,
rodents
Losses in cable
lengths
Laying;
Identification
Civil
Material quality
& deliveries
Sequence of
operations
Suitability to soil
and atmosphere
Water drain
11. Requirements
Complete a project of 1 MW SPV power plant:
Within time limit
Within the given budget
Within given constraints
Should export optimum electrical units to the grid
Should perform at optimum level till the end of plant life (25 years)
12. Considerations
Time limit:
Licenses, sanctions and approvals
Rooftop
Safety
(Client) Inspection agency certification
CEI certificate
Utility grid connectivity certificate
Budget limit:
Time and Cost balance
Profitability in mind
Balancing act among in-project activities
13. Optimum Units to Grid
Design of plant, quality of used material, workmanship
Selecting and Sourcing good components
Using these components in proper way
14. Organizing Access, Clearances & Certificates
Land Non Agriculture status (Not applicable to rooftop)
Gram Panchayat / local body NOC (Not applicable to rooftop)
Access Permissions
Permissions of using water
Electrical connections for construction
Grid operator – Specifications, Inspections and Brands – for procurement
Chief Electrical Inspector for grid connection
15. Organizing Access, Clearances & Certificates
Concessional duty certificates – MNRE
Safety audits and checks – Permit to Work
Developer’s (client’s) engineer permissions and inspections
Lender’s engineer inspections
Labour Laws – Register, PF, ESI, Workman Compensation policy, Lodging and
Boarding
16. Project Implementation Models
Consulting &
EPC
Conceptualizatio
n
Financing
Design
EPC
EPC
Engineering
Procurement
Construction
EPC Lite
Engineering
Part
procurement
Construction
EPC (Part) &
O&M
EPC
Limited period
O&M with
guarantees
18. Procurement
Indian or Chinese or European or Global? Current scene:
Modules – China (cSi), USA (TF), Europe (rarely), India
Inverters – Europe, USA, India
DC cables, connectors, data monitoring, protections – Europe, China
Structures – India, Europe (rarely)
Main decision factors:
Price
Bundling with low cost finance
19. Procurement
Specifications, Part numbers
Delivery schedule
Packing and forwarding system
Accompanying documents requirement
Test certificates – Own and Third party
Warranties
Identification standards on packaging and on components
20. Terms of Trade
Payment terms
Penalties for non-performance
Spares during and post execution
Scope of suppliers on site
Testing and commissioning
21. Sub-Contractors
Contractors’ licenses to work
Precise definition of scope of work
Schedule of work and manpower allocation
Advance bank guaranties
Performance bank guaranties
Surprise checks and audits
Documentation requirements
Certification for work acceptance and payments
22. Contract Risk Management
Performance warranty:
Definitions
Conditions
Type of security
Third party insurance
Bank guaranty from public sector or scheduled
Revolving LC auto renewable
Product warranty: Group / parent company corporate guarantee, Bank guarantee
23. Payment Terms
Price vs. Payment terms
Credit types:
Credit period backed by LC
Suppliers’ credit
Participation in project profit – performance related terms
Connecting client’s terms with suppliers’
Escrow account
25. Component Cost in Rs. Lacs
Solar Modules 27,000
Module mounting structure 5,000
Inverters 7,000
Electrical Components 6,000
Miscellaneous 3,000
I&C and allied 3,000
Total 51,000
*1) Pre-commissioning charges and interest extra
2) Sample project cost for plant size of 500kWp
26. Financing Options
DE Ratio: 2.33 (debt 70% & equity 30%)
Equity:
Developer’s own funds
Private equity participation
Community / group equity
Debt:
Indian banks – nationalized / cooperative
Foreign banks or FII
IREDA
NBFCs
27. Financing Requirements
Collateral security: 100% …..20%
Project financing or balance sheet financing
Bank Guarantees or other securities to foreign lenders
29. Work Items in a Project
Sourcing and securing Rooftop
Mounting solar modules on structures
Connecting solar modules to inverter/s
Connecting inverters to step-up transformer
Connecting transformer to the Grid
Performance data monitoring and records
Protections – Earthing, lightening protections
Allied work for the plant –Scaffolding, Fencing, Drainage
Accommodation for Contractors
30. Project Example
Work Division: Sourcing Contractors for
DC Electrical Works
Structure erection
Module mounting
Module interconnections
Earthing of modules and structures
Cabling till inverters through combiner boxes
AC Electrical Works
Inverters to transformers with protective gear
Metering and Fuses
Interconnection to grid
Auxiliary power requirement like plant lighting, AC, etc.
31. Project Example
Work Division: Sourcing Contractors for Civil Works
Foundations for structures
Waterproofing
Cabling routing structures if needed
Water layout and Drainage
Security
32. Project Example Illustrated
Civil teams for
plot level work
DC Electrical
teams
Civil for internal
work
AC Electrical
&
Civil internal
work
Protection &
Monitoring &
Commissioning
Mechanized;
About 20
persons
Labour
Intensive;
About 100
persons
Mechanized
plus labour;
About 30
persons
Skilled
labour;
labour
intensive civil
Skilled job;
About 5
persons
34. Scheduling
Requirement analysis
Time action planning of material, manpower and equipment
Facility and amenity requirements
Contingency planning – emergency response
Local support and hindrance
Impact of environment on the project
35. Logistics
Just In Time deliveries
Movement of material – up to the site and within the site
Availability of tools and tackles
Warehousing
Record keeping
Manpower management, welfare, efficiency improvement
36. Certifications, Licenses
Clearances for work and material
Equipment and vehicles
Safety and security
Medical aid, emergency arrangements
Frequency of audits by clients, authorities
Certification of work
37. Suggested Goals for Execution Phase
Timely
Cost effective
Lowest possible surprises
Ensuring lifetime performance
Avoid later phase investments
Customer delight
Compliance to applicable rules and regulations
Zero accidents
39. SPVRT System Monitoring
Most inverters are equipped with webconnect data module which sends daily
generation through registered e-mail
Devices/Plants
Total yield
Meter Change [kWh]
3/3/2014
Total yield
Meter Change [kWh]
March 2014
Total yield
Meter Change [kWh]
2014
AKDN-15KW 48.85 117.08 1406.51
48.85
[Total]
117.08
[Total]
1406.51
[Total]
Dwipen Boruah <dwipen.boruah@gses.com.au>
Sunny Portal Info Report for plant: AKDN-15KW for the 3/3/2014 Daily Production: 48.848
kWh / Daily Revenue: --- USD / Daily CO2 Reduction: 34.194 kg
1 message
service@sunnyportal.com <service@sunnyportal.com> 4 March 2014 05:00
To: "nirdosh.gupta@su-kam.com" <nirdosh.gupta@su-kam.com>, "parshant.kalra@su-kam.com" <parshant.kalra@su-kam.com>,
"vijay.singh@su-kam.com" <vijay.singh@su-kam.com>, "ashish.sethi@su-kam.com" <ashish.sethi@su-kam.com>,
"dwipen.boruah@gses.in" <dwipen.boruah@gses.in>, "shveta.mathur@akdn.org" <shveta.mathur@akdn.org>,
"hardeep.thakur@akdn.org" <hardeep.thakur@akdn.org>
Sunny Portal Info Report for plant: AKDN-15KW for the 3/3/2014
Daily Production: 48.848 kWh
Daily Revenue: --- USD
Daily CO2 Reduction: 34.194 kg
AKDN-15KW Daily report
Gses.com.au Mail - Sunny Portal Info Report for plant: AKDN-... https://mail.google.com/mail/u/0/?ui=2&ik=69bac842a0&view=p...
40. Large SPVRT Systems / Plants Monitoring
Weather data and system performance and system yield are continuously monitored
and recorded through data logger.
41. When digital screens are provided on an inverter the instantaneous data that is
generally available includes:
Array voltage (V DC)
Array current (A DC)
Grid voltage (V AC)
Current to grid (A AC)
Power out (kW AC)
Energy generated that day (kWh)
42. 42
Anurag Mishra
Senior Clean Energy Specialist
USAID/India
Email: amishra@usaid.gov
Disclaimer:
This training material is made possible by the support of the American
People through the United States Agency for International
Development (USAID). The contents of this material are the sole
responsibility of Nexant, Inc. and do not necessarily reflect the views of
USAID or the United States Government. This material was prepared
under Contract Number AID-386-C-12-00001.