18ME56-OM_ Module 3-Facility and Capacity Planning.pdf

  1. Module – 3: • Capacity & Location Planning: • Importance of capacity decisions, defining and measuring capacity, determinants of effective capacity, determining capacity requirement, developing capacity alternatives, evaluating alternatives. • Need for location decisions, nature of locations decisions, general procedure for making locations decisions, evaluating locations decisions, facilities layout – need for layout decisions, types of processing. (8 hours) 2 Dept. of ME, JSSATE, Bengaluru
  2. Module Outcome: At the end of this module, you will be able to: CO# Course Outcome Bloom’s Level 3 List various capacity and location plans to determine the suitable capacity required for meeting the forecast demand of an organization. 4 3 Dept. of ME, JSSATE, Bengaluru Learning Objectives: After completing this module, you should be able to:
  3. 4 Dept. of ME, JSSATE, Bengaluru • The ability to achieve, store or produce. • For an organization, capacity would be the ability of a given system to produce output within the specific time period (The max. capability to produce). • In operations management, capacity is referred as an amount of the input resources available to produce relative output over period of time. • In general terms, capacity is referred as maximum production capacity, which can be attained within a normal working schedule. • Examples…. Capacity
  4. 5 Dept. of ME, JSSATE, Bengaluru • Design Capacity: • Planned (engineered) rate of output of goods or services under normal, or full-scale, operating conditions. • Examples of ….sugar, cement, automobile, hospital, etc. • Based on long-range forecasts (5-10 years?) • Affected (~ reduced) by market conditions, need for product mix, tight quality specifications, imbalance of equipment or labour, etc. (leads to system capacity). Capacity in Organizations
  5. 6 Dept. of ME, JSSATE, Bengaluru • System Capacity: • The maximum output of a specific product or product mix that the system of workers and machines is capable of producing as an integrated whole. • Typically less than or equal to Design Capacity of the individual components. • Affected by actual demand, managerial performance – scheduling, staffing, controlling, etc., worker inefficiencies, machine inefficiencies, etc. (leads to actual output). Capacity in Organizations
  6. 7 Dept. of ME, JSSATE, Bengaluru Capacity in Organizations Design Capacity (1500 TPD) System Capacity (Effective Capacity) (1200 TPD) Actual Output (Capacity ) (900 TPD) Affected by long-range effects: Product mix, Market conditions, Tight quality specifications Inherent imbalance of equipment & labour Affected by short-range effects: Actual demand; Managerial performance, Worker (skill, effort) & Machine inefficiencies (wear, breakdown, scrap loss) Relationship among Design capacity, System capacity and Actual Output System Efficiency (or System Utilization) = Actual output / System capacity
  7. 8 Dept. of ME, JSSATE, Bengaluru Capacity in Organizations
  8. 9 Dept. of ME, JSSATE, Bengaluru • A chemical product is produced by a series of four processing steps, mixing, heating, molding & cooling at a rate of 50 litres/min. The individual capacities of the processes and the actual output of the system is given below: • Mixing – 48 litres/min.; Heating – 50 litres/min; Molding – 43 litres/min.; Cooling - 46 litres/min.; The actual output = 40 litres/min. • What is the system capacity? System efficiency? Capacity in Organizations
  9. 10 Dept. of ME, JSSATE, Bengaluru Capacity in Organizations
  10. 11 Dept. of ME, JSSATE, Bengaluru • System capacity = Capacity of most limited process • = 43 litres/min • System efficiency = actual output / system capacity • = 40/43 = 0.93 or 93% Capacity in Organizations
  11. 12 Dept. of ME, JSSATE, Bengaluru • A manufacturer of shoes has determined that the production facility has a design capacity of 300 shoes per week. The effective or system capacity, however, is 230 shoes per week. What is the manufacturer's capacity utilization relative to both design and effective capacity if output is 200 shoes per week? • Solution: • Utilization is computed as the ratio of actual output over capacity. Capacity in Organizations
  12. 13 Dept. of ME, JSSATE, Bengaluru • The design capacity of an engine repair station is 80 trucks/day. The effective capacity is 40 engines/day and the actual output is 36 engines/day. Calculate the utilization and efficiency of the operation. If the efficiency for next month is expected to be 82%, what is the expected output? • Solution: • Utilization = Actual output / Design capacity • = 36/80 = 0.45 or 45% • System efficiency = Actual output / System or effective capacity • = 36/40 = 0.90 or 90% • Expected output = Effective or System Capacity * System Efficiency • = 40*0.82 = 32.8 engines/day Capacity in Organizations
  13. 14 Dept. of ME, JSSATE, Bengaluru • A firm is willing to install automatic molding machines to produce 250,000 good castings per year. The molding operation takes 1.5 min per casting, but its output is typically about 3% defective. Determine the number of automatic molding machines the company should buy if each one of them will be used 2000 hours per year. • Actual output required = 250,000 good castings/year • Required system capacity = actual output / SE • 250,000/0.97 = 257,732 castings/year OR • 257,732/2000 = 129 castings / hour Capacity in Organizations
  14. 15 Dept. of ME, JSSATE, Bengaluru • Individual machine capacity • = Time available in min/Time required per casting in min • = 60 min per her/1.5 min per casting • = 40 castings per machine per hour • Number of machines required • = Total number of castings required per hour / Individual machine capacity • = 129/40 = 3.2 machines Capacity in Organizations
  15. 16 Dept. of ME, JSSATE, Bengaluru • A product line manufacturing shoes has five stations in series whose individual capacities per shift are given in the following table. The actual output of the line is 500 pairs per shift. Find: • The system capacity • The system efficiency Capacity in Organizations Station No. 1 2 3 4 5 Individual capacity /shift 600 650 650 550 600
  16. 17 Dept. of ME, JSSATE, Bengaluru • Solution: • (a) The capacity of station 4 is the least. That is 550 pairs/shift. It is called station with bottleneck operations. • Hence system capacity = 550 pairs/shift • (b) The actual output is 500 pairs/shift • Hence, system efficiency • = actual output / system capacity • = 500/550 = 0.9091 = 90.91% Capacity in Organizations
  17. 18 Dept. of ME, JSSATE, Bengaluru • Rated capacity is the theoretical output that could be attained if a process were operating at full speed without interruption, exceptions, or downtime. • Effective capacity takes into account the efficiency with which a particular product or customer can be processed, and the utilization of the scheduled hours or work. • Effective daily capacity = no. of machines or workers x hours per shift x no. of shifts x utilization x efficiency • Utilization refers to the percentage of available working time that a worker actually works or a machine actually runs. Capacity in Organizations – Some terms
  18. 19 Dept. of ME, JSSATE, Bengaluru • Scheduled maintenance, lunch breaks, and setup time are examples of activities that reduce actual working time. • Efficiency refers to how well a machine or worker performs compared to a standard output level. Standards can be based on past records of performance or can be developed from the work-measurement techniques. • An efficiency of 100% is considered normal or standard performance, 125% is above normal, and 90% is below normal. Efficiency is also dependent on product mix. • Load is the standard hours of work (or equivalent units of production) assigned to a production facility. Capacity in Organizations – Some terms
  19. 20 Dept. of ME, JSSATE, Bengaluru • Facilities factors: Key factor is the design of facilities (size & provision for future expansion). Location factors such as costs of transportation, nearness to market, supply of suitable labours, energy sources, etc. are also important. • Plant layout and utilities affect labour efficiency and hence effective capacity. • Product/Service factors: Uniformity in products/services (Product lines than product mix) provides opportunities for standardisation of methods and materials. This leads to greater effective capacity. • Process factors: The quantity and quality capability of a process or equipment increase the rate of output and hence the effective capacity. Determinants of Effective Capacity
  20. 21 Dept. of ME, JSSATE, Bengaluru • Human resource factors: The actual output may be affected by job design, activities involved, training, skill & experience required to perform a job, employer motivation, employee absenteeism, etc. • Operational factors: Scheduling problems such as different capability equipment and different job requirements may hinder the effective capacity. In addition, factors such as inventory decisions, late deliveries by suppliers, quality of purchased material and parts, inspection and QC procedures may also have an impact on effective capacity. • External factors: Product standards, safety regulations, labour activities, pollution control norms, etc. may hinder effective capacity. Determinants of Effective Capacity
  21. 22 Dept. of ME, JSSATE, Bengaluru • Designing flexibility into the system • Differentiating between new and mature products or services • Taking a big-picture approach to capacity changes • Preparing to deal with chunks of capacity • Attempting to smooth out capacity requirements • Identifying the optimal operating level Developing Capacity Alternatives
  22. 23 Dept. of ME, JSSATE, Bengaluru • An auto component manufacturer has a plan of buying hydraulic forging machines that can produce 170,000 good parts per year. These machines will be a part of a product line. The system efficiency of the product line is 85%. • (a) What is the required system capacity? • (b) Assume that it takes 100 seconds to forge each part and the plant operates 2000 hours per year. If the machines are used only 60% of the time and are 90% efficient, what is the actual output of the machines per hour? • (c) How many forging machines would be required? Capacity in Organizations
  23. 24 Dept. of ME, JSSATE, Bengaluru • (a) System capacity = actual output required per year / system efficiency • = 170,000/0.85 = 200,000 parts per year • = 200,000 / 2000 hours = 100 parts per hour • (b) Output per hour = Unit capacity x % utilization x efficiency • = (3600/100) x 0.60 x 0.90 = 19.44 ≅ 20 parts / hour (..per machine) • (c) No. of machines required = System capacity / Output per hour • = 100 / 20 = 5 forging machines Capacity in Organizations
  24. 25 Dept. of ME, JSSATE, Bengaluru • A department works on 8 hours/shift, 250 days in a year and has the data on the demand of a product and standard processing time as given below: • Determine the number of machines required. Capacity in Organizations Product Annual demand, units Processing (standard) time/product in hours X 300 4 Y 400 6 Z 500 3
  25. 26 Dept. of ME, JSSATE, Bengaluru • Solution: • Total processing time (hours) required • Annual production capacity of one machine • = 8 x 250 = 2000 hours per year • No. of machines required • = Workload per year / Prodn. Capacity of each machine • = 5100/2000 = 2.55 ≅ 3 machines Capacity in Organizations Product Annual demand, units Processing (standard) time/product in hours Total PT needed, Hours X 300 4 300 x 4 = 1200 Y 400 6 400 x 6 = 2400 Z 500 3 500 x 3 = 1500 Total 5100
  26. 27 Dept. of ME, JSSATE, Bengaluru • A firm operates 6 days a week on single shift of 8 hours/day basis. There are 10 machines of the same capacity in the firm. If the machines are utilized 75% of the time at a system efficiency of 80%, what is the rated output in terms of standard hours per week? • Soln.: • Maximum no. of hours of work possible per week = No. of machines x No. of days in a week x No. of hours in a day = 10 x 6 x 8 = 480 hours • When utilization is 75% only, then the above answer is = 480 x 0.75 = 360 hours • Rated output = Utilized hours x System efficiency • = 360 x 0.80 = 288 standard hours Capacity in Organizations
  27. 28 Dept. of ME, JSSATE, Bengaluru • Capacity planning is: determining optimum utilization of resource (human and equipment/machines). • Plays an important role decision-making process, for example, extension of existing operations, modification to product lines, starting new products, etc. • Capacity planning based on the timeline is classified into three main categories long range, medium range and short range. Capacity Planning
  28. 29 Dept. of ME, JSSATE, Bengaluru • Long-term capacity planning is a strategic decision that establishes a firm’s overall level of resources. • Extends over a time horizon long enough to obtain those resources—usually a year or more for building or expanding facilities or acquiring new businesses. • Capacity decisions affect product lead times, customer responsiveness, operating costs, and a firm’s ability to compete. • Inadequate capacity can lose customers and limit growth. • Excess capacity can drain a company’s resources and prevent investments in more lucrative ventures. Capacity Planning, Long-term Critical Decision: When to increase & how much to increase
  29. 30 Dept. of ME, JSSATE, Bengaluru • Capacity lead strategy: Capacity is expanded in anticipation of demand growth. • Average capacity strategy: Capacity is expanded to coincide with average expected demand. • Capacity lag strategy: Capacity is increased after an increase in demand has been documented. • How much to increase capacity depends on – the volume and certainty of anticipated demand; – strategic objectives in terms of growth, customer service, and competition; and – The costs of expansion and operation. Capacity Expansion Strategies Source: OM by Russel & Taylor
  30. 31 Dept. of ME, JSSATE, Bengaluru Capacity Expansion Strategies Source: OM by Russel & Taylor Lead Average Lag
  31. 32 Dept. of ME, JSSATE, Bengaluru • The strategic capacity planning undertaken by organization for a medium time horizon (6-18 months) is referred to as medium term capacity planning (aggregate planning). • The strategic planning undertaken by organization for a daily, weekly or quarterly time frame is referred to as short term capacity planning (CRP). Capacity Planning, Medium & Short Range
  32. 33 Dept. of ME, JSSATE, Bengaluru • Capacity requirements planning is the process of determining short-range capacity requirements. • It is a technique for determining what personnel and equipment capacities are required to meet the production objectives embodied in the ‘master schedule’ and ‘material requirement plan’ (MRP). • MRP and CRP together accomplish, specifically, what materials and capacities are needed and when they are needed. • MRP and CRP can be done, although, manually and in isolation, they are integrated within a computerized system. Capacity Requirement Planning (CRP)
  33. 34 Dept. of ME, JSSATE, Bengaluru • Inputs • Planned orders and released orders from MRP system • Loading information from the work centre status file • Routing information from the shop routing file • Changes which modify capacity • Outputs • Loading reports of planned & released orders on key work centres • Verification reports to the MRP system • Capacity modification data • Rescheduling data to the MPS Inputs and Outputs of CRP
  34. Dept. of ME, JSSATE, Bengaluru 35
  35. Dept. of ME, JSSATE, Bengaluru 36
  36. PART – II Facility Location Planning Dept. of ME, JSSATE, Bengaluru 37 • Need for location decisions, nature of locations decisions, general procedure for making locations decisions, evaluating locations decisions, facilities layout – need for layout decisions, types of processing.
  37. 38 Dept. of ME, JSSATE, Bengaluru
  38. 39 Dept. of ME, JSSATE, Bengaluru • A place where specific activities occur. • Example .., Sports and military activities occur in sports and military facilities. Nuclear research scientists work in a nuclear research facility. • The term is also used for buildings, equipment, and services that are used for a particular purpose. • Example .., – shopping facilities are places where we can buy things. – Medical facilities may refer to a hospital (medical equipment, doctors, pharmaceutical shop, etc. housed in a building), – Restaurant facilities refer to a building where rooms are available for stay, food is served, etc. – University facilities …. Facility
  39. 40 Dept. of ME, JSSATE, Bengaluru • A manufacturing facility means a factory or a plant. The term may refer to any place that makes things, or plants that generate electricity. • Examples…plants that manufacture automobiles, pharmaceuticals, chemicals, petroleum products, food products, sanitary products, etc. • A service facility may refer to a place where a specific service is offered. • Examples…hospitals, hotels, petrol bunks, medical shops, banks, educational institutes, etc. Facility
  40. 41 Dept. of ME, JSSATE, Bengaluru • Facility Location is the right location for the manufacturing facility which will have sufficient access to the customers, workers, transportation, etc. • One of the most critical factors determining the success of a business firm is its location. • Facility location planning is the process of determining the right geographical site for a firm’s operations for achieving maximum operating economy and effectiveness. • The objective of facility location decision is to minimise the sum of all costs affected by location. Facility (Plant) Location
  41. 42 Dept. of ME, JSSATE, Bengaluru • Location decisions are strategic, long-term and non-repetitive in nature. The reasons for making location decisions are: • When business is newly started • When a business firm wants to expand its markets by adding new locations to the existing one • When an organization experiences growth in the demand for its products or services and the existing facility is not capable of meeting the demand • When the costs of inputs (due to depletion) and distribution of outputs increase, relocation may be thought of • Shifts in markets may cause firms to relocate • Social and economical reasons such as shortage of labours, electricity, changes in customers’ lifestyle, government regulations, etc. The Need for Location Decisions
  42. 43 Dept. of ME, JSSATE, Bengaluru • Strategic Importance – Long term commitment/costs – Impact on investments, revenues, and operations – Supply chains • Objectives – Profit potential – No single location may be better than others – Identify several locations from which to choose • Options – Expand existing facilities – Add new facilities – Move The Nature of Location Decisions Source: OM by W J Stevenson
  43. 44 Dept. of ME, JSSATE, Bengaluru • Decide on the criteria to use for evaluating location alternatives, such as increased revenues, decreased cost, or community service. • Identify important factors, such as location of markets or raw materials. • (The factors will differ depending on the type of facility. For example, retail, manufacturing, distribution, healthcare, and transportation all have differing factors that guide their location decisions). • Develop location alternatives: – Identify a country or countries for location. – Identify the general region for a location. General procedure for making location decisions Source: OM by W J Stevenson
  44. 45 Dept. of ME, JSSATE, Bengaluru • Develop location alternatives: – Identify a small number of community alternatives. – Identify site alternatives among the community alternatives. • Evaluate the alternatives and make a selection. General procedure for making location decisions Source: OM by W J Stevenson
  45. 46 Dept. of ME, JSSATE, Bengaluru Source: OM by W J Stevenson Factors Affecting Location Decisions Level Regional Factors Location of raw materials or supplies Location of markets Labour Considerations Proximity, modes and costs of transportation, quantity available Proximity, distribution costs, target market, trade practices / restrictions Availability (general and for specific skills), age distribution of workforce, work attitudes, union or nonunion, productivity, wage scales, unemployment compensation laws
  46. 47 Dept. of ME, JSSATE, Bengaluru Source: OM by W J Stevenson Factors Affecting Location Decisions Level Community Factors Quality of life Services Attitudes Taxes Environmental regulations Utilities Development support Considerations Schools, churches, shopping, housing, transportation, entertainment, recreation, cost of living Medical, fire, and police Pro / Con State/local, direct and indirect State / local Cost and availability Bond issues, tax abatement, low-cost loans, grants
  47. 48 Dept. of ME, JSSATE, Bengaluru Source: OM by W J Stevenson Factors Affecting Location Decisions Level Site Factors Land Transportation Environmental / legal Considerations Cost, degree of development required, soil characteristics and drainage, room for expansion, parking Type (access roads, rail spurs, air freight) Zoning restrictions
  48. • Locational cost-profit-volume analysis • Factor rating, and • The center of gravity method. • Cost-profit-volume analysis is also called break-even analysis. • Cost-profit-volume analysis is a technique for evaluating location choices in economic terms. • The different locations are compared economically, either numerically or graphically. Dept. of ME, JSSATE, Bengaluru 49 Source: OM by W J Stevenson Evaluating Location Alternatives
  49. • Procedure • Determine the fixed and variable costs associated with each location alternative. • Plot the total-cost lines for all location alternatives on the same graph. • Determine which location will have the lowest total cost for the expected level of output. Alternatively, determine which location will have the highest profit. • Assumptions 1. One product is involved 2. Everything produced can be sold 3. Variable cost per unit is the same regardless of volume 4. Fixed costs do not change with volume 5. Revenue per unit is constant with volume 6. Revenue per unit exceeds variable cost per unit Dept. of ME, JSSATE, Bengaluru 50 Source: OM by W J Stevenson Cost-Profit-Volume Analysis
  50. • The total cost (TC) is given by • Total cost = FC + v *Q, where, • FC - fixed cost; v – variable cost/unit; Q – quantity or volume of output • The volume of output is shown along abscissa and the cost or sales revenue along ordinate • Fixed cost line is a horizontal line from x = 0, and y = fixed cost • Total cost line is an inclined line from the beginning of fixed cost line • Total revenue line is an inclined line from the origin. • The intersection of TC and TR line is called break-even point Dept. of ME, JSSATE, Bengaluru 51 Source: OM by W J Stevenson Cost-Profit-Volume Analysis
  51. Dept. of ME, JSSATE, Bengaluru 52 Source: OM by W J Stevenson Cost-Profit-Volume Analysis
  52. • Total Revenue = Unit Selling Price (SP) x Sales quantity, (Q) • Total Cost = Total Fixed Cost (FC) + Total Variable Cost (VC) • Total profit, P = Total revenue – Total cost • P = (Q x SP) – (FC + v x Q) • P = Q (SP -v) – FC Dept. of ME, JSSATE, Bengaluru 53 Source: OM by W J Stevenson Cost-Profit-Volume Analysis Where, SP – Selling Price / unit; VC – Variable Cost/unit
  53. 1. Jayna Steel India is planning to start a new factory for manufacturing steel utensils. It is considering three location options, viz. Bokaro, Jamshedpur and Bhilai. The fixed costs at the three locations have been estimated as Rs. 8.15 million, 7.377 million, and 7.093 million respectively. The variable costs/unit at the three locations are estimated at Rs. 500, Rs. 580, and Rs. 490 respectively. The factory will have an annual production capacity of 10,000 utensils and in the initial years it will operate at 75% efficiency. Find the best location option. Dept. of ME, JSSATE, Bengaluru 54 Source: POM by Kanishka Bedi Cost-Profit-Volume Analysis - Examples Location Fixed cost, Rs. Million Variable cost/unit, Rs Annual utensils required Bokaro 8.15 500 10,000 Jemshedpur 7.377 580 Bhilai 7.093 490
  54. Solution: • Find the total cost (TC) at each location. • Choose the one that yields the least cost • Q = 10,000 units/year; Efficiency = 75% or 0.75 • Hence, the production output/year = 10,000*0.75 = 7,500 units Dept. of ME, JSSATE, Bengaluru 55 Source: POM by Kanishka Bedi Cost-Profit-Volume Analysis - Examples Location Fixed cost, Rs. Million Variable cost/unit, Rs Total Cost = FC + v*Q Rs./year Bokaro 8.15 500 81,50,000 + 500*7,500 = 1,19,00,000 Jemshedpur 7.377 580 73,77,000 + 580*7,500 = 1,17,27,000 Bhilai 7.093 490 70,93,000 + 490*7,500 = 1,07,68,000
  55. Solution: • Find the total cost (TC) at each location. • Choose the one that yields the least cost • Q = 10,000 units/year; Efficiency = 75% or 0.75 • Hence, the production output/year = 10,000*0.75 = 7,500 units Dept. of ME, JSSATE, Bengaluru 56 Source: POM by Kanishka Bedi Cost-Profit-Volume Analysis - Examples Location Fixed cost, Rs. Million Variable cost/unit, Rs Total Cost = FC + v*Q Rs./year Bokaro 8.15 500 81,50,000 + 500*7,500 = 1,19,00,000 Jemshedpur 7.377 580 73,77,000 + 500*7,500 = 1,17,27,000 Bhilai (Best location) 7.093 490 70,93,000 + 490*7,500 = 1,07,68,000
  56. 2. A manufacturer of farm equipment is considering three locations or sites (A, B, and C) for a new plant. Cost studies show that fixed costs per year at the sites are $240,000, $270,000, and $252,000 respectively. The variable cost per unit are estimated to be $100, $90, and $95 respectively. If the plant is designed to have an effective system capacity of 2,500 units per year and is expected to operate at 80% efficiency, what is the most economic location on the basis of actual output? Dept. of ME, JSSATE, Bengaluru 57 Source: OM by Joseph Monks Cost-Profit-Volume Analysis - Examples Location Fixed cost, $ Variable cost/unit, $ Annual output required A 240,000 100 2500 B 270,000 90 C 252,000 95
  57. Solution: • Find the total cost (TC) at each location. • Choose the one that yields the least cost • Q = 2,500 units/year; Efficiency = 80% or 0.80 • Hence, the production output/year = 2500*0.80 = 2000 units Dept. of ME, JSSATE, Bengaluru 58 Cost-Profit-Volume Analysis - Examples Location Fixed cost, $ Variable cost/unit, $ Total Cost = FC + v*Q $/year A 240,000 100 240000 + 100*2000 = 440,000 B 270,000 90 270000 + 90*2000 = 450,000 C 252,000 95 252000 + 95*2000 = 442,000 Source: OM by Joseph Monks
  58. Solution: • Find the total cost (TC) at each location. • Choose the one that yields the least cost • Q = 2,500 units/year; Efficiency = 80% or 0.80 • Hence, the production output/year = 2500*0.80 = 2000 units Dept. of ME, JSSATE, Bengaluru 59 Cost-Profit-Volume Analysis - Examples Location Fixed cost, $ Variable cost/unit, $ Total Cost = FC + v*Q $/year A (Best) 240,000 100 240000 + 100*2000 = 440,000 B 270,000 90 270000 + 90*2000 = 450,000 C 252,000 95 252000 + 95*2000 = 442,000 Source: OM by Joseph Monks
  59. • Fixed and variable costs for four potential plant locations are shown as follows. • Expected output level = 10,000 units/year • (a) Plot the total-cost lines for these locations on a single graph. • (b) Identify the range of output for which each location (alternative) is superior (i.e., has the lowest total cost). • (c) If expected output at the selected location is to be 8,000 units per year, which location would provide the lowest total cost? Dept. of ME, JSSATE, Bengaluru 60 Source: OM by W J Stevenson Cost-Profit-Volume Analysis - Examples 3
  60. • a. Plot the graph • Compute the total cost for each location at the given output level: • Plot each location’s fixed cost (at Output = 0) and the total cost at 10,000 units; and connect the two points with a straight line. Dept. of ME, JSSATE, Bengaluru 61 Source: OM by W J Stevenson Cost-Profit-Volume Analysis - Examples
  61. Dept. of ME, JSSATE, Bengaluru 62 Source: OM by W J Stevenson Cost-Profit-Volume Analysis - Examples Total cost lines for two locations are shown TC for both the locations is equal TC of location B is less than that of A till this point
  62. Dept. of ME, JSSATE, Bengaluru 63 Source: OM by W J Stevenson Cost-Profit-Volume Analysis - Examples
  63. • (b) The approximate ranges for which the various alternatives will yield the lowest costs are shown in the graph: • Location A: More than (beyond) 11,200 units/year --- approx. • Location B: From 0 to 5000 units/year • Location C: Between 5000 to 11,200 units/year • Location D: Not at all suitable. • (c) From the graph, for 8,000 units per year, location C provides the lowest total cost. Dept. of ME, JSSATE, Bengaluru 64 Source: OM by W J Stevenson Cost-Profit-Volume Analysis - Examples
  64. 4. Sigma Instruments Pvt. Ltd. is considering three locations for its new factory – Bengaluru, Hyderabad, and Chennai. The estimates of different costs at the three location options are given below. The company is financed by SBI for its construction at an interest rate of 15% p.a. Find an economic location for the production of 5000 – 10,000 units per annum. Dept. of ME, JSSATE, Bengaluru 65 Cost-Profit-Volume Analysis - Examples Cost details Bengaluru Hyderabad Chennai Transportation cost, Rs./unit 10 20 9 Cost of materials, Rs./unit 120 110 100 Taxes, Rs./year 40,000 35,000 45,000 Cost of construction of the factory, Rs. 5 million 4 million 4.7 million Electricity, Rs./year 22,000 15,000 25,000 Labour, Rs./unit 26 21 23 Source: POM by Kanishka Bedi
  65. • Find the total FC and VC for each location • Find the TC for each location for outputs of 5000 units and 10,000 units/year. • Plot the Break-even chart • Decide the economic location for the given output range. • For 5000 units/year (Q), the Total Cost at: • Location B: TC = FC + v*Q = 812,000+156*5000 = Rs. 15,92,000 • Location H: TC = FC + v*Q = 650,000+151*5000 = Rs. 14,05,000 • Location C: TC = FC + v*Q = 775,000+132*5000 = Rs. 14,35,000 Dept. of ME, JSSATE, Bengaluru 66 Cost-Profit-Volume Analysis - Examples Location FC, Rs./year VC, (v) Rs./unit B 812,000 156 H 650,000 151 C 775,000 132 Source: POM by Kanishka Bedi
  66. • For 10,000 units/year (Q), the Total Cost at: • Location B: TC = FC + v*Q = 812,000+156*10000 • = Rs. 23,72,000 • Location H: TC = FC + v*Q = 650,000+151*5000 • = Rs. 21,60,000 • Location C: TC = FC + v*Q = 775,000+132*5000 • = Rs. 20,95,000 Dept. of ME, JSSATE, Bengaluru 67 Cost-Profit-Volume Analysis - Examples Source: POM by Kanishka Bedi Units Bengaluru Hyderabad Chennai 0 812,000 650,000 775,000 5,000 15,92,000 14,05,000 14,35,000 10,000 23,72,000 21,60,000 20,95,000
  67. Dept. of ME, JSSATE, Bengaluru 68 TC at Hyderabad = TC at Chennai 650,000+151*Q = 775,000+132*Q Hence, Q = 6580 units
  68. 5. Potential locations, A, B and C have the cost structures shown in the table for a product expected to sell at $130. • (a) Find the most economic location for an expected volume of 6000 units/year. • (b) What is the expected profit, if the selected site is used? • (c) For what output range each location is suitable? Dept. of ME, JSSATE, Bengaluru 69 Cost-Profit-Volume Analysis - Examples Source: POM by Kanishka Bedi Potential Location FC, $/year VC, (v) $/unit A 150,000 75 B 200,000 50 C 400,000 25
  69. • (a) • For 6,000 units/year (Q), the Total Cost at: • Location A: TC = FC + v*Q = 150,000 + 75*6000 = $ 600,000 • Location B: TC = FC + v*Q = 200,000 + 50*6000 = $ 500,000 • Location C: TC = FC + v*Q = 400,000 + 25*6000 = $ 550,000 • Conclusion: The most economical location is B. • (b) Expected profit = $(130 *6000) – 500,000 = $280,000 • (c) Preference of locations Dept. of ME, JSSATE, Bengaluru 70 Cost-Profit-Volume Analysis - Examples Source: POM by Kanishka Bedi
  70. Dept. of ME, JSSATE, Bengaluru 71 Cost-Profit-Volume Analysis - Examples Source: POM by Kanishka Bedi
  71. • (c) Preference of locations: • From the graph, • Up to 2000 units/year, Location A is suitable • Between 2000 to 7400 units, Location B is suitable • Beyond 7400 units, Location C is suitable. • Analytically: • Compare A & B: • TC at A = TC at B to find a quantity, Q • 150,000 + 75*Q = 200,000 + 50*Q • Hence, Q = 50000/25 = 2000 units • Compare B & C: • TC at B = TC at C to find a quantity, Q • 200,000 + 50*Q = 400,000 + 25*Q; Hence Q = 8000 units Dept. of ME, JSSATE, Bengaluru 72 Cost-Profit-Volume Analysis - Examples Source: POM by Kanishka Bedi
  72. • 6. A dry cleaning firm is considering four possible sites for its new operation. They expect to clean 10,000 garments/month. The table below shows the various cost elements: • Find the most economic location and range of output where each location is suitable. Dept. of ME, JSSATE, Bengaluru 73 Cost-Profit-Volume Analysis - Examples Source: POM by Sanders
  73. Dept. of ME, JSSATE, Bengaluru 74
  74. • 7. Titan Ltd., is considering two location options for its new clock manufacturing facility, Pune and Noida. The company estimates that the FC and VC at Pune are Rs. 2 million and Rs. 30/clock. At Noida, the estimates are Rs. 1.8 million and Rs. 40 respectively. The selling prices are different at Pune and Noida, Rs. 120/clock and Rs. 100/clock respectively. • The company would like to choose a location where the break- even volume is less. Choose the best location. • Solution: • BE Volume at Pune = FC/(SP-VC) = 2000000/(120-30) = 22,222 • BE Volume at Noida = FC/(SP-VC) = 1800000/(100-40) = 30,000 • Pune is the best location Dept. of ME, JSSATE, Bengaluru 75 Cost-Profit-Volume Analysis - Examples Source: POM by Kanishka Bedi
  75. 8. A firm is considering four locations for its new factory – A, B, C, and D. The estimates of different costs at the four location options are given below. The firm will finance the new plant from bonds bearing an interest of 10% p.a. Find an economic location for the production of 50,000 – 100,000 units per annum. Dept. of ME, JSSATE, Bengaluru 76 Cost-Profit-Volume Analysis - Examples Cost ($) details A B C D Transportation cost, per unit 0.02 0.10 0.10 0.05 Materials & equipment, per unit 0.43 0.60 0.40 0.55 Taxes, per year 33k 28k 63k 35k Plant construction cost, $ million 4.60 3.90 1.0 4.80 Electricity, per year 30k 26k 30k 28k Labour, per unit 0.75 1.10 0.80 0.90 Water, per year 7k 6k 7k 7k Source: POM by J. Monks
  76. • Find the total FC and VC for each location • Find the TC for each location for outputs of -- units and -- units/year. • Plot the Break-even chart • Decide the economic location for the given output range. • For 100,000 units/year (Q), the Total Cost at: • Location A: TC = FC + v*Q = 530,000+1.2*100k = $650,000 • Location B: TC = FC + v*Q = 450,000+1.8*100k = $630,000 Dept. of ME, JSSATE, Bengaluru 77 Cost-Profit-Volume Analysis - Examples Location FC, $./year VC, (v) $./unit A 530,000 1.2 B 450,000 1.8 C 500,000 1.3 D 550,000 1.5 Source: POM by Kanishka Bedi
  77. • Location C: TC = FC + v*Q = 500,000+1.3*100k = $630,000 • Location D: TC = FC + v*Q = 550,000+1.5*100k = $700,000 • From the BE Chart: • Location B is suitable for a volume of 50,000 to 100,000 units. • Location C is suitable for a quantity 100,000 to130,000 units Dept. of ME, JSSATE, Bengaluru 78 Cost-Profit-Volume Analysis - Examples Source: POM by Kanishka Bedi
  78. • A means of assigning weights (quantitative value) to all the factors related to each location alternative and deriving a composite score that can be used for comparison. • Both qualitative and quantitative factors are considered. • Steps: • Develop a list of factors • Assign a weight to each factor (from 0 to 1 or 1 to 100) • Determine the composite score for each location using: Composite score = Σwi*si where, • wi is the weight for factor , i; si is the score for factor, i • Choose the location with maximum composite score Dept. of ME, JSSATE, Bengaluru 79 Factor Rating Analysis
  79. • A company is evaluating four locations for a new plant and has weighed the relevant factors as shown below. Develop a quantitative factor comparison for the location and identify the best one. Dept. of ME, JSSATE, Bengaluru 80 Factor Rating Analysis - Examples Factor Assigned weight Score of Location 1 2 3 4 Production cost 0.33 50 40 35 30 Raw material supply 0.25 70 80 75 80 Labour availability 0.20 55 70 60 45 Cost of living 0.05 80 70 40 50 Environment 0.02 60 60 60 90 Market 0.15 80 90 85 50
  80. Dept. of ME, JSSATE, Bengaluru 81 Factor Rating Analysis - Examples Factor Assigned weight Weighted Score of Location 1 2 3 4 Production cost 0.33 50*0.33 = 16.50 40*0.33 = 13.20 35 30 Raw material supply 0.25 70*0.25 = 17.50 80*0.25 = 20.00 75 80 Labour availability 0.20 55*0.20 = 11.00 70*0.20 = 14.00 60 45 Cost of living 0.05 80*0.05 = 4.00 70*0.05 = 3.50 40 50 Environment 0.02 60*0.02 = 1.2 60*0.02 = 1.20 60 90 Market 0.15 80*0.15 = 12 90*0.15 = 13.50 85 50 Total score 62.00 65.40 58.20 50.70
  81. • A company is evaluating two locations for a new plant and has weighed the relevant factors as shown below. Develop a quantitative factor comparison for the location and identify the best one. Dept. of ME, JSSATE, Bengaluru 82 Factor Rating Analysis - Examples
  82. Dept. of ME, JSSATE, Bengaluru 83 Factor Rating Analysis - Examples Decision: Location 2 is the best
  83. • Location of a production centre or warehouse which will minimize the costs of distributing (transporting) specified volumes of a product to surrounding markets or locations. • It is an approach that seeks to compute geographic coordinates for a potential single new facility that will minimize costs. • The main inputs considered are: • Distances of markets • Volume of goods shipped • Shipping costs Dept. of ME, JSSATE, Bengaluru 84 Centre of Gravity Method
  84. • Steps: • Determine the relative distances between existing facilities. • The distances are established by placing existing facilities on a co-ordinate grid system. • Find the best location of the new facility using the formula, • Cx = X coordinate of center of gravity; Cy = Y coordinate of center of gravity; dix = X coordinate of the ith location; diy = Y coordinate of the ith location; Vi = volume of goods moved to or from ith location Dept. of ME, JSSATE, Bengaluru 85 Centre of Gravity Method V V d = C i i ix x ∑ ∑ C = d V V y iy i i ∑ ∑
  85. Dept. of ME, JSSATE, Bengaluru 86 Centre of Gravity Method
  86. Dept. of ME, JSSATE, Bengaluru 87 Centre of Gravity Method
  87. • A food delivery firm would like to establish a new food production & distribution centre in a suitable location. It has estimated the possible number of food containers to be distributed every day to eight market locations whose distances are given below: • Identify the economic food production/distribution centre. Dept. of ME, JSSATE, Bengaluru 88 Centre of Gravity Method - Example Market # Volume X, km Y, km 1 8 2.5 10 2 20 3 5 3 12 6.5 8 4 10 11 10 5 30 11 8 6 20 10 4 7 40 13 3.5 8 30 12 2
  88. • X-coordinate of proposed location = 1678/170 = 9.9 km • Y-coordinate of proposed location = 896/170 = 5.3 km Dept. of ME, JSSATE, Bengaluru 89 Centre of Gravity Method - Example Market # Volume, Vi Xi, km Yi, km Vi*Xi Vi*Yi 1 8 2.5 10 20 80 2 20 3 5 60 100 3 12 6.5 8 78 96 4 10 11 10 110 100 5 30 11 8 330 240 6 20 10 4 200 80 7 40 13 3.5 520 140 8 30 12 2 360 60 Total ΣV = 170 Σ=1678 Σ=896
  89. Dept. of ME, JSSATE, Bengaluru 90 Centre of Gravity Method - Example
  90. • X-coordinate of proposed warehouse = 1360/200 = 6.8 miles • Y-coordinate of proposed warehouse = 1520/200 = 7.6 miles • TC of market A = {(8-6.8)+(12-7.6)}*40*0.12 = $26.88 • TC of market B = {(6-6.8)  + (4-7.6) } *20*0.10 = $8.80 • TC of market C = {(2-6.8)  + (8-7.6) } *60*0.10 = $31.20 • TC of market D = {(10-6.8)+(6-7.6) } *80*0.10 = $38.40 Dept. of ME, JSSATE, Bengaluru 91 Centre of Gravity Method - Example Market # Demand in tons, Vi Xi, miles Yi, miles Vi*Xi Vi*Yi A 40 8 12 320 480 B 20 6 4 120 80 C 60 2 8 120 480 D 80 10 6 800 480 Total ΣV = 200 Σ=1360 Σ=1520
  91. Facility Layout Planning Dept. of ME, JSSATE, Bengaluru 92
  92. • After the site location decision has been made, the next focus in production planning is the facility’s layout. • The goal is to determine the most efficient and effective design for the particular production process. • A manufacturer might opt for a U-shaped production line, for example, rather than a long, straight one, to allow products and workers to move more quickly from one area to another. • Facility layout is the physical arrangement of various departments/units, machines/equipment within the departments, stores, walking spaces, etc. within the plant premises. Dept. of ME, JSSATE, Bengaluru 93 Facility Layout
  93. Dept. of ME, JSSATE, Bengaluru 94
  94. Dept. of ME, JSSATE, Bengaluru 95
  95. Dept. of ME, JSSATE, Bengaluru 96
  96. • The basic objective of layout is to ensure a smooth flow of work, material, and information through a system. • The layout and design of the space within the facility (plant premises) impact greatly on how the work is done • The key to good facility layout and design is the integration of the needs of people (personnel and customers), materials (raw, finished, and in process), and machinery in such a way that they create a single, well-functioning system. Dept. of ME, JSSATE, Bengaluru 97 Facility Layout
  97. • Space utilization • Shipping and receiving • Ease of communication and support • Impact on employee morale and job satisfaction • Promotional value (small businesses where visitors in the form of customers, vendors, investors, etc., - the facility layout must be an attractive one that further burnishes the company's reputation) • Safety—The facility layout should enable the firm to effectively operate in accordance with Occupational Safety and Health Administration guidelines and other legal restrictions. Dept. of ME, JSSATE, Bengaluru 98 Facility Layout –Factors Affecting
  98. Dept. of ME, JSSATE, Bengaluru 99 Facility Layout –Types Source: OM by Gaither, et al Process Layout The process layout arranges workflow around the production process. All workers (machines/equipment) performing similar tasks are grouped together. Products pass from one workstation to another (but not necessarily to every workstation). This layout is best for firms that produce small numbers of a wide variety of products.
  99. Dept. of ME, JSSATE, Bengaluru 100 Facility Layout –Types Source: OM by Gaither, et al Product or Assembly line Layout • Products that require a continuous or repetitive production process use the product (or assembly-line) layout. • When large quantities of a product must be processed on an ongoing basis, the workstations or departments are arranged in a line with products moving along the line. Ex., Automobiles, food-processing plants, pharmaceuticals, consumer goods, etc.
  100. Dept. of ME, JSSATE, Bengaluru 101 Facility Layout –Types Source: OM by Gaither, et al Fixed Position Layout
  101. • Some products cannot be put on an assembly line or moved about in a plant. • A fixed-position layout lets the product stay in one place while workers and machinery move to it as needed. • Products that are impossible to move—ships, airplanes, and construction projects—are typically produced using a fixed-position layout. • The fixed-position layout is also common for on-site services such as housecleaning services, pest control, and landscaping. • https://www.youtube.com/watch?v=-ovNi1cB7a4&feature=emb_logo Dept. of ME, JSSATE, Bengaluru 102 Facility Layout –Types
  102. • Cellular layouts combine some aspects of both product and fixed-position layouts. • Work cells are small, self-contained production units that include several machines and workers arranged in a compact, sequential order. • Each work cell performs all or most of the tasks necessary to complete a manufacturing order. • There are usually five to 10 workers in a cell, and they are trained to be able to do any of the steps in the production process. • The goal is to create a team environment wherein team members are involved in production from beginning to end. Dept. of ME, JSSATE, Bengaluru 103 Facility Layout –Types Cellular Layout
  103. Dept. of ME, JSSATE, Bengaluru 104 Cellular Layout Facility Layout –Types