Which contract should I be using? 
Robert Langley 
Partner, Construction & Engineering team 
Muckle LLP
Collaboration 
•“The Act or process of collaborating” 
•“Co-laborare” – to work together (latin) 
•Do we need to spell it out?
NEC3 
•10.1 “The Employer, the Contractor, the Project Manager and the Supervisor shall act as stated in this Contract and in a spirit of mutual trust and co-operation” 
•JCT Optional Schedule 8 
•the parties must work with each other and the Project Team “in good faith and in a spirit of trust and respect”
Good faith – recent guidance 
•TSG Building Services v South Anglia Housing 
•“ACA Term Partnering 2005 
•team members shall work together in a spirit of trust fairness and mutual co-operation for the benefit of the Programme” 
•Mid-Essex NHS Trust v Compass 
•“the Trust and the Contractor will co-operate with each other in good faith... for the efficient transmission of information... and to enable the Trust to derive the full benefit of the Contract”
Good faith: conclusion from the case law 
•General statements are of limited use 
•Detailed provisions are more valuable 
•e.g. provisions for reasonableness in JCT enabling PM to exercise judgment 
•clear articulation of functions and controls in NEC3
Various types of standard forms 
•All generally issued as ‘suites’ 
•CIOB – Chartered Institute of Building 
•Complex building and engineering projects 
•Fidic – Federation Internationale de Ingenieurs Conseils 
•Engineering, energy and process plant. Usually international 
•IChemE 
•Chemical and process engineering industries
Various types of standard forms 
•GC/Works 
•primarily for government contracts 
•ICC - Infrastructure Conditions of Contract 
•typically civil engineering projects 
•JCT 
•most common form, typical on commercial property and development projects 
•NEC3 – New Engineering Contracts 
•general application, recommended by government
Today’s focus 
•IChemE 
•JCT 
•NEC3 
•typical features 
•differences 
•points to note
IChemE 
•Specifically applicable to chemical and process engineering industries 
•oil & gas, water & power, food technology, pharmaceuticals 
•Results / performance based 
•generally designed for projects that will need to be tested against defined criteria once constructed
IChemE 
•Balance of risk 
•generally contain more exclusions of liability in favour of the contractor 
•due to the nature of process plants – consequential losses as a result of defects can be enormous 
•IChemE contracts include: 
•requirement that Purchaser provides construction all risks insurance 
•overall cap on liability 
•final Certificate excludes further liability 
•one year defects liability period
IChemE 
•4 main UK contracts 
•The Red Book – lump sum 
•The Green Book – reimbursable 
•The Burgundy Book – target cost 
•The Orange Book – minor works
The Red Book 
•Turnkey contract 
•contractor takes responsibility for design 
•costs of completion at Contractor’s risk 
•subject to contractual Variations 
•The relationship between the parties is typically performance based 
•caution against amending this in negotiations 
•give careful thought to the schedules 
•sets out description of the works, purchaser’s own responsibilities, scope of works
The Green Book 
•Very similar philosophy to Red Book 
•turnkey contract 
•contractor takes responsibility for design 
•Contractor fully reimbursable for actual costs incurred 
•this includes corrective costs arising from design & construction errors 
•note – Contractor must use “reasonable skill and care to be expected of a properly qualified and competent Contractor”
Which to use? 
•Red Book 
•Where purchaser wants certainty on costs 
•where full tender process is desired 
•standard package is required, with a detailed specification and engineering information is available
Which to use? 
•Green Book 
•Purchaser wants flexibility and is confident to get involved with the process 
•more power to Project Manager 
•where technology is less advanced – perhaps the performance and results of the process are uncertain 
•if project relies on Purchaser’s specific knowledge or skills
The Burgundy Book 
•Target Cost contract 
•attempts to promote co-operation and fairness between the parties through incentives 
•Typical operation 
•parties agree Target Cost for the works 
•contract includes formula that incentivises Contractor to minimise costs overspends 
•contractor records Actual Costs incurred on the project
Pain share / gain share 
•Target Cost and Actual Cost is compared 
•any savings against the Target Cost are shared 
•Contractor is paid half of the saving 
•effectively a bonus for coming in under budget 
•any overruns against the Target Cost are shared 
•Contractor is only paid half of the overrun between the Target Cost and Actual Cost 
•effectively a penalty for overrun 
•Aim is to incentivise parties to achieve lowest Actual Costs possible
Changes to costs 
•Clause 16 – variations 
•agreed variations allow an increase to the Target Cost 
•except where work is necessary for the Plant to comply with the Specification – Contractor not entitled to increase to Target Cost
Changes to costs 
•Clause 37 – defects 
•the remediation of defects is at Purchaser’s cost – i.e. Contractor’s Actual Costs is increased 
•except where defect is due to Contractor’s failure to exercise reasonable skill and care
Key considerations 
•Detailed and accurate Specification is critical 
•helps avoid costly variations arguments 
•Extensive role for Project Manager 
•important to select a strong and competent character to manage the project 
•note that PM must act impartially between the parties 
•Parties must be clear on Target & Actual Costs 
•full recording procedures and mechanisms must be included in contract Schedules
Case study 
•Firstline Engineering Co v NLP Process Power
JCT 
•Most common form of building contract 
•5 forms: 
•standard Building contract 
•design and Build (DB) Building contract 
•major Project Building contract 
•Minor works 
•intermediate
Standard Building Contract 
•3 contracts in this category 
•approximate Quantities (measurement) 
•quantities (lump sum) 
•Without quantities (lump sum) 
•Provisions generally similar, main difference concerns way price is determined 
•lump sum price will be altered where works are varied or delayed, where delay is due to Employer 
•measurement changes to reflect the actual work carried out
Standard Building Contract 
•Typically used for larger construction projects 
•complex engineering unlikely 
•Architect has contract administration role 
•supervise the day to day works and manage administration – crucially, notices 
•Employer retains some responsibility 
•termination notices for example
Contractor’s Design Portion 
•If Contractor is to carry out some design, CDP is implemented 
•records the extent of the Contractor’s responsibility for certain elements of the works 
•may often use specialist sub-contractors
Design and Build 
•Used on similar projects as Standard contracts 
•Contractor assumes responsibility for design and build 
•Contractor typically given Employer’s Requirements 
•produces proposals for design on this basis 
•Often design is produced by professional consultants, then novated to Contractor 
•Contractor’s design liability can be capped
Differences 
•Contractor has design responsibility in DB 
•not in Standard, unless a CDP is used 
•note that Employer retains responsibility for Employers Requirements in DB – so not accurate that Contractor has ‘entire’ design responsibility wrap in DB 
•DB does not utilise a Contract Administrator, instead uses an Employer’s Agent
Differences 
•Both contracts do not expressly deal with ground conditions 
•assumption is that Contractor retains responsibility 
•Note in DB – Employer retains responsibility for design within Employer’s Requirements (potentially leads to unexpected results)
Major Building Contract 
•Intended for the largest of projects 
•Parties generally experience in large scale procurement 
•Contractor responsible for design 
•Shorter than DB contract, so suitable where parties have their own detailed procedures 
•Can be used where sectional completion is required
Minor works 
•Two forms 
•minor Works Building Contract 
•minor Works Building Contract with Contractor’s design 
•CPD used where discreet elements of design are required from Contactor
Minor works 
•Appropriate where works are simple in nature extensions, remodelling 
•Architect / Contract Administrator is used 
•Not suitable: 
•where wholesale design is required from Contractor 
•where bill of quantities are required 
•If detailed control / costs procedures required
Intermediate contracts 
•Sit between Minor Works and Standard 
•used for reasonably simple projects where the skills and trades involved are conventional 
•Can utilise a CDP where Contractor is to do some design 
•not suitable as a full DB contract though
NEC3 suite 
•Engineering and Construction Contract 
•most common 
•Professional Services Contract 
•Engineering and Construction Short Contract 
•Term Service Contract 
•Framework Contract
NEC3 
•Completely new drafting philosophy 
•different terminology used 
•some concern that the drafting is not tried and tested? 
•not lawyer friendly 
•legal precision takes a back seat in favour of promoting proactive management processes 
•Generally applicable to all types of works 
•national infrastructure particularly 
•Crossrail, Heathrow T2, London 2012 
•Recommended and endorsed by government
NEC3 philosophy 
•Intended to be a project management tool 
•aims to increase proactive risk management 
•Parties need to adopt and ‘buy into’ the philosophy 
•the look and feel of the contract is very different to typical forms 
•intention was to move away from ‘adversarial forms’
Key points and features 
•Writing style 
•plain English, written in present tense 
•each clause stands alone – no cross referencing 
•the word ‘shall’ on appears once – in clause 10.1 
•Clause 10.1 
•all parties agree to “act in a spirit of mutual trust and co-operation” 
•underpins NEC philosophy 
•concerns over legal interpretation
Key points and features 
•Project Manager takes extensive role 
•responsible for championing the NEC values 
•subject to clause 10.1 
•high level of authority is required 
•must get involved in indentifying and managing risk proactively – risk register under clause 11
Key points and features 
•Clause 11.2 (14) – risk register 
•parties must compile a risk register at the start of the project 
•must be continually updated as the project progresses 
•register describes risk and lists steps take to mitigate
Key points and features 
•Clause 16 – early warning events 
•Contractor and PM are required to give early warning notices “as soon as either becomes aware of any matter which could 
•increase total of the Prices 
•delay Completion 
•delay meeting a Key Date 
•impair the performance of the works in use” 
•Wide ranging 
•Not ‘could’ – designed to encourage early and open disclosure
Key points and features 
•Clause 60 – compensation events 
•wide ranging, detailed list 
•Clause 61.3 - Notification of compensation events 
•“the Contractor notifies the Project Manager of an event which has happened or which he expects to happen as a Compensation event...” 
•aimed at encouraging early disclosure so risk can be mitigated
Amending the NEC3? 
•Innovative approach means there is room for criticism – especially for lawyers! 
•NEC advocates say this is deliberate – move away from the traditional approach 
•Wholesale amendment is therefore discouraged
Amending the NEC3? 
•Some areas do require clarification 
•specify which documents are Contract Documents and order of precedence 
•no general obligation to comply with statutes 
•compensation event procedure is often regarded as overly bureaucratic 
•transfer of title provisions inadequate – especially where employer has paid for materials stored off site 
•Matter for parties – but remember philosophy
Any questions?
This presentation was delivered at an APM event 
To find out more about upcoming events please visit our website www.apm.org.uk/events

More Related Content

What's hot

CONTRACTS AND ITS TYPES
CONTRACTS AND ITS TYPESCONTRACTS AND ITS TYPES
CONTRACTS AND ITS TYPES
Pundlik Rathod
 
A Report on Procurement Strategies - PP1
A Report on Procurement Strategies - PP1 A Report on Procurement Strategies - PP1
A Report on Procurement Strategies - PP1
Pang Khai Shuen
 
The architect as contract administrator a legal perspective - presentation ...
The architect as contract administrator   a legal perspective - presentation ...The architect as contract administrator   a legal perspective - presentation ...
The architect as contract administrator a legal perspective - presentation ...
Zainab Zainordin
 

What's hot (20)

Collaborative contracting strategies and the use of the NEC3 family of contracts
Collaborative contracting strategies and the use of the NEC3 family of contractsCollaborative contracting strategies and the use of the NEC3 family of contracts
Collaborative contracting strategies and the use of the NEC3 family of contracts
 
What is NEC 3?, by Dr Jon Broome, 31st March 2015 copyright leadingedgeprojec...
What is NEC 3?, by Dr Jon Broome, 31st March 2015 copyright leadingedgeprojec...What is NEC 3?, by Dr Jon Broome, 31st March 2015 copyright leadingedgeprojec...
What is NEC 3?, by Dr Jon Broome, 31st March 2015 copyright leadingedgeprojec...
 
Chapter 5- Contract Management
Chapter 5- Contract ManagementChapter 5- Contract Management
Chapter 5- Contract Management
 
CONTRACTS AND ITS TYPES
CONTRACTS AND ITS TYPESCONTRACTS AND ITS TYPES
CONTRACTS AND ITS TYPES
 
Chapter 1 [compatibility mode]
Chapter 1 [compatibility mode]Chapter 1 [compatibility mode]
Chapter 1 [compatibility mode]
 
Fidic
FidicFidic
Fidic
 
Contractors
ContractorsContractors
Contractors
 
Contract administration iowa AGC
Contract administration iowa AGCContract administration iowa AGC
Contract administration iowa AGC
 
ACH 231 Lecture 07 (Contract Documents) Part 3
ACH 231 Lecture 07 (Contract Documents) Part 3ACH 231 Lecture 07 (Contract Documents) Part 3
ACH 231 Lecture 07 (Contract Documents) Part 3
 
Chapter 6- Contract Management
Chapter 6- Contract ManagementChapter 6- Contract Management
Chapter 6- Contract Management
 
Chapter 4 [compatibility mode]
Chapter 4 [compatibility mode]Chapter 4 [compatibility mode]
Chapter 4 [compatibility mode]
 
A Report on Procurement Strategies - PP1
A Report on Procurement Strategies - PP1 A Report on Procurement Strategies - PP1
A Report on Procurement Strategies - PP1
 
Effective contract administration may 2014
Effective contract administration may 2014Effective contract administration may 2014
Effective contract administration may 2014
 
An Overview of the FIDIC FORMS OF CONTRACT and Contracts Committee Activi...
An Overview of the FIDIC FORMS OF CONTRACT and Contracts Committee Activi...An Overview of the FIDIC FORMS OF CONTRACT and Contracts Committee Activi...
An Overview of the FIDIC FORMS OF CONTRACT and Contracts Committee Activi...
 
contract administration PPT
 contract administration PPT contract administration PPT
contract administration PPT
 
Contracts in professional practice
Contracts in professional practiceContracts in professional practice
Contracts in professional practice
 
Types of contracts
Types of contracts   Types of contracts
Types of contracts
 
The architect as contract administrator a legal perspective - presentation ...
The architect as contract administrator   a legal perspective - presentation ...The architect as contract administrator   a legal perspective - presentation ...
The architect as contract administrator a legal perspective - presentation ...
 
types of contracts
 types of contracts types of contracts
types of contracts
 
Construction Law Presentation
Construction Law PresentationConstruction Law Presentation
Construction Law Presentation
 

Viewers also liked

Viewers also liked (8)

ACH 216 Lecture 04c (Project Award)
ACH 216 Lecture 04c (Project Award)ACH 216 Lecture 04c (Project Award)
ACH 216 Lecture 04c (Project Award)
 
Muckle workshop - case studies
Muckle workshop - case studiesMuckle workshop - case studies
Muckle workshop - case studies
 
fidic , jct and nec contracts
fidic , jct and nec contractsfidic , jct and nec contracts
fidic , jct and nec contracts
 
The people factor in contracts and procurement, Barry Trebes, 16th June 2016
The people factor in contracts and procurement, Barry Trebes, 16th June 2016The people factor in contracts and procurement, Barry Trebes, 16th June 2016
The people factor in contracts and procurement, Barry Trebes, 16th June 2016
 
Exploring stakeholder engagement
Exploring stakeholder engagement Exploring stakeholder engagement
Exploring stakeholder engagement
 
Managing stakeholders: core styles
Managing stakeholders: core stylesManaging stakeholders: core styles
Managing stakeholders: core styles
 
Exploring stakeholder management skills - event images
Exploring stakeholder management skills - event imagesExploring stakeholder management skills - event images
Exploring stakeholder management skills - event images
 
Types of contract
Types of contractTypes of contract
Types of contract
 

Similar to Muckle LLP - Which contract should I be using?

Professional practice-1-presentation
Professional practice-1-presentationProfessional practice-1-presentation
Professional practice-1-presentation
Timun Loh
 
Building Contracts and CDM regulations
Building Contracts and CDM regulationsBuilding Contracts and CDM regulations
Building Contracts and CDM regulations
Julian Swindell
 
20050314 tips on contract management
20050314 tips on contract management20050314 tips on contract management
20050314 tips on contract management
raymond_wan2005
 

Similar to Muckle LLP - Which contract should I be using? (20)

Construction contract
Construction contract Construction contract
Construction contract
 
TOPIC2.pdf
TOPIC2.pdfTOPIC2.pdf
TOPIC2.pdf
 
Contract Management - Contracts Types and Payment Structure
Contract Management - Contracts Types and Payment StructureContract Management - Contracts Types and Payment Structure
Contract Management - Contracts Types and Payment Structure
 
Contracting strategies for_terminal_construction
Contracting strategies for_terminal_constructionContracting strategies for_terminal_construction
Contracting strategies for_terminal_construction
 
Contracting strategies for_terminal_construction
Contracting strategies for_terminal_constructionContracting strategies for_terminal_construction
Contracting strategies for_terminal_construction
 
Professional practice-1-presentation
Professional practice-1-presentationProfessional practice-1-presentation
Professional practice-1-presentation
 
Classification of contracts
Classification of contractsClassification of contracts
Classification of contracts
 
Building Contracts and CDM regulations
Building Contracts and CDM regulationsBuilding Contracts and CDM regulations
Building Contracts and CDM regulations
 
FIDIC.RICS CPD Event Singapore 2012.ppt
FIDIC.RICS CPD Event Singapore 2012.pptFIDIC.RICS CPD Event Singapore 2012.ppt
FIDIC.RICS CPD Event Singapore 2012.ppt
 
Preparation of boq
Preparation of boqPreparation of boq
Preparation of boq
 
Legal issues associated with project management and consulting
Legal issues associated with project management and consultingLegal issues associated with project management and consulting
Legal issues associated with project management and consulting
 
20050314 tips on contract management
20050314 tips on contract management20050314 tips on contract management
20050314 tips on contract management
 
PP1 presentation slide.
PP1 presentation slide.PP1 presentation slide.
PP1 presentation slide.
 
Measure And Pay Contract
Measure And Pay Contract Measure And Pay Contract
Measure And Pay Contract
 
Types of Contract in Construction Management
Types of Contract in Construction ManagementTypes of Contract in Construction Management
Types of Contract in Construction Management
 
types-170309142854.pptx
types-170309142854.pptxtypes-170309142854.pptx
types-170309142854.pptx
 
Types of contracts
Types of contractsTypes of contracts
Types of contracts
 
05 Contract Management.pptx . DEFINITION
05 Contract Management.pptx . DEFINITION05 Contract Management.pptx . DEFINITION
05 Contract Management.pptx . DEFINITION
 
Chapter 1 [compatibility mode]
Chapter 1 [compatibility mode]Chapter 1 [compatibility mode]
Chapter 1 [compatibility mode]
 
contract procedure
contract procedurecontract procedure
contract procedure
 

More from Association for Project Management

Team Lead Succeed – Helping you and your team achieve high-performance teamwo...
Team Lead Succeed – Helping you and your team achieve high-performance teamwo...Team Lead Succeed – Helping you and your team achieve high-performance teamwo...
Team Lead Succeed – Helping you and your team achieve high-performance teamwo...
Association for Project Management
 
If AI changes everything – do feelings still matter?
If AI changes everything – do feelings still matter?If AI changes everything – do feelings still matter?
If AI changes everything – do feelings still matter?
Association for Project Management
 
Personal Resilience in Project Management 2 - TV Edit 1a.pdf
Personal Resilience in Project Management 2 - TV Edit 1a.pdfPersonal Resilience in Project Management 2 - TV Edit 1a.pdf
Personal Resilience in Project Management 2 - TV Edit 1a.pdf
Association for Project Management
 

More from Association for Project Management (20)

Making communications land - Are they received and understood as intended? we...
Making communications land - Are they received and understood as intended? we...Making communications land - Are they received and understood as intended? we...
Making communications land - Are they received and understood as intended? we...
 
Spatium Project Simulation student brief
Spatium Project Simulation student briefSpatium Project Simulation student brief
Spatium Project Simulation student brief
 
APM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAPM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across Sectors
 
Projecting for the Future: Harmonising Energy and Environment, APM North West...
Projecting for the Future: Harmonising Energy and Environment, APM North West...Projecting for the Future: Harmonising Energy and Environment, APM North West...
Projecting for the Future: Harmonising Energy and Environment, APM North West...
 
New to Nuclear - Transition into nuclear from other sectors, APM North West N...
New to Nuclear - Transition into nuclear from other sectors, APM North West N...New to Nuclear - Transition into nuclear from other sectors, APM North West N...
New to Nuclear - Transition into nuclear from other sectors, APM North West N...
 
Tell us what to do, not how to do it, APM North West Network Conference, Syne...
Tell us what to do, not how to do it, APM North West Network Conference, Syne...Tell us what to do, not how to do it, APM North West Network Conference, Syne...
Tell us what to do, not how to do it, APM North West Network Conference, Syne...
 
The Future is Fractional, APM North West Network Conference, Synergies Across...
The Future is Fractional, APM North West Network Conference, Synergies Across...The Future is Fractional, APM North West Network Conference, Synergies Across...
The Future is Fractional, APM North West Network Conference, Synergies Across...
 
Lessons learned across projects, APM North West Network Conference, Synergies...
Lessons learned across projects, APM North West Network Conference, Synergies...Lessons learned across projects, APM North West Network Conference, Synergies...
Lessons learned across projects, APM North West Network Conference, Synergies...
 
Agile Adaptability: Navigating Project Management in a Dynamic World, APM Nor...
Agile Adaptability: Navigating Project Management in a Dynamic World, APM Nor...Agile Adaptability: Navigating Project Management in a Dynamic World, APM Nor...
Agile Adaptability: Navigating Project Management in a Dynamic World, APM Nor...
 
Inclusive Practices in Project Management: Leveraging Digital Frameworks for ...
Inclusive Practices in Project Management: Leveraging Digital Frameworks for ...Inclusive Practices in Project Management: Leveraging Digital Frameworks for ...
Inclusive Practices in Project Management: Leveraging Digital Frameworks for ...
 
Leadership - the project professionals secret weapon, 24 April 2024
Leadership - the project professionals secret weapon, 24 April 2024Leadership - the project professionals secret weapon, 24 April 2024
Leadership - the project professionals secret weapon, 24 April 2024
 
APM Project Management Awards - Hints and tips for a winning award entry webi...
APM Project Management Awards - Hints and tips for a winning award entry webi...APM Project Management Awards - Hints and tips for a winning award entry webi...
APM Project Management Awards - Hints and tips for a winning award entry webi...
 
The Vyrnwy Aqueduct Modernisation Programme webinar, 17 April 2024
The Vyrnwy Aqueduct Modernisation Programme webinar, 17 April 2024The Vyrnwy Aqueduct Modernisation Programme webinar, 17 April 2024
The Vyrnwy Aqueduct Modernisation Programme webinar, 17 April 2024
 
Team Lead Succeed – Helping you and your team achieve high-performance teamwo...
Team Lead Succeed – Helping you and your team achieve high-performance teamwo...Team Lead Succeed – Helping you and your team achieve high-performance teamwo...
Team Lead Succeed – Helping you and your team achieve high-performance teamwo...
 
Staurt Earl - ARCC Programme for APM Awards.pptx
Staurt Earl - ARCC Programme for APM Awards.pptxStaurt Earl - ARCC Programme for APM Awards.pptx
Staurt Earl - ARCC Programme for APM Awards.pptx
 
If AI changes everything – do feelings still matter?
If AI changes everything – do feelings still matter?If AI changes everything – do feelings still matter?
If AI changes everything – do feelings still matter?
 
AI in the project profession: examples of current use and roadmaps to adoptio...
AI in the project profession: examples of current use and roadmaps to adoptio...AI in the project profession: examples of current use and roadmaps to adoptio...
AI in the project profession: examples of current use and roadmaps to adoptio...
 
Katharine Fox, WRAP - Valuing sustainability
Katharine Fox, WRAP - Valuing sustainabilityKatharine Fox, WRAP - Valuing sustainability
Katharine Fox, WRAP - Valuing sustainability
 
The silent project disruptor: Building AI solutions
The silent project disruptor: Building AI solutionsThe silent project disruptor: Building AI solutions
The silent project disruptor: Building AI solutions
 
Personal Resilience in Project Management 2 - TV Edit 1a.pdf
Personal Resilience in Project Management 2 - TV Edit 1a.pdfPersonal Resilience in Project Management 2 - TV Edit 1a.pdf
Personal Resilience in Project Management 2 - TV Edit 1a.pdf
 

Recently uploaded

FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
dollysharma2066
 
Insurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageInsurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usage
Matteo Carbone
 
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
amitlee9823
 
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
lizamodels9
 

Recently uploaded (20)

The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
 
Cracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptxCracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptx
 
(Anamika) VIP Call Girls Napur Call Now 8617697112 Napur Escorts 24x7
(Anamika) VIP Call Girls Napur Call Now 8617697112 Napur Escorts 24x7(Anamika) VIP Call Girls Napur Call Now 8617697112 Napur Escorts 24x7
(Anamika) VIP Call Girls Napur Call Now 8617697112 Napur Escorts 24x7
 
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
 
Value Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and painsValue Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and pains
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
 
Insurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageInsurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usage
 
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
 
Famous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st CenturyFamous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st Century
 
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesMysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
 
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRLMONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
 
Falcon Invoice Discounting platform in india
Falcon Invoice Discounting platform in indiaFalcon Invoice Discounting platform in india
Falcon Invoice Discounting platform in india
 
BAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
BAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRLBAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
BAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
 
👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...
👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...
👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...
 
Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023
 
Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...
Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...
Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...
 
Dr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdfDr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdf
 
Eluru Call Girls Service ☎ ️93326-06886 ❤️‍🔥 Enjoy 24/7 Escort Service
Eluru Call Girls Service ☎ ️93326-06886 ❤️‍🔥 Enjoy 24/7 Escort ServiceEluru Call Girls Service ☎ ️93326-06886 ❤️‍🔥 Enjoy 24/7 Escort Service
Eluru Call Girls Service ☎ ️93326-06886 ❤️‍🔥 Enjoy 24/7 Escort Service
 
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
 
Uneak White's Personal Brand Exploration Presentation
Uneak White's Personal Brand Exploration PresentationUneak White's Personal Brand Exploration Presentation
Uneak White's Personal Brand Exploration Presentation
 

Muckle LLP - Which contract should I be using?

  • 1. Which contract should I be using? Robert Langley Partner, Construction & Engineering team Muckle LLP
  • 2. Collaboration •“The Act or process of collaborating” •“Co-laborare” – to work together (latin) •Do we need to spell it out?
  • 3. NEC3 •10.1 “The Employer, the Contractor, the Project Manager and the Supervisor shall act as stated in this Contract and in a spirit of mutual trust and co-operation” •JCT Optional Schedule 8 •the parties must work with each other and the Project Team “in good faith and in a spirit of trust and respect”
  • 4. Good faith – recent guidance •TSG Building Services v South Anglia Housing •“ACA Term Partnering 2005 •team members shall work together in a spirit of trust fairness and mutual co-operation for the benefit of the Programme” •Mid-Essex NHS Trust v Compass •“the Trust and the Contractor will co-operate with each other in good faith... for the efficient transmission of information... and to enable the Trust to derive the full benefit of the Contract”
  • 5. Good faith: conclusion from the case law •General statements are of limited use •Detailed provisions are more valuable •e.g. provisions for reasonableness in JCT enabling PM to exercise judgment •clear articulation of functions and controls in NEC3
  • 6. Various types of standard forms •All generally issued as ‘suites’ •CIOB – Chartered Institute of Building •Complex building and engineering projects •Fidic – Federation Internationale de Ingenieurs Conseils •Engineering, energy and process plant. Usually international •IChemE •Chemical and process engineering industries
  • 7. Various types of standard forms •GC/Works •primarily for government contracts •ICC - Infrastructure Conditions of Contract •typically civil engineering projects •JCT •most common form, typical on commercial property and development projects •NEC3 – New Engineering Contracts •general application, recommended by government
  • 8. Today’s focus •IChemE •JCT •NEC3 •typical features •differences •points to note
  • 9. IChemE •Specifically applicable to chemical and process engineering industries •oil & gas, water & power, food technology, pharmaceuticals •Results / performance based •generally designed for projects that will need to be tested against defined criteria once constructed
  • 10. IChemE •Balance of risk •generally contain more exclusions of liability in favour of the contractor •due to the nature of process plants – consequential losses as a result of defects can be enormous •IChemE contracts include: •requirement that Purchaser provides construction all risks insurance •overall cap on liability •final Certificate excludes further liability •one year defects liability period
  • 11. IChemE •4 main UK contracts •The Red Book – lump sum •The Green Book – reimbursable •The Burgundy Book – target cost •The Orange Book – minor works
  • 12. The Red Book •Turnkey contract •contractor takes responsibility for design •costs of completion at Contractor’s risk •subject to contractual Variations •The relationship between the parties is typically performance based •caution against amending this in negotiations •give careful thought to the schedules •sets out description of the works, purchaser’s own responsibilities, scope of works
  • 13. The Green Book •Very similar philosophy to Red Book •turnkey contract •contractor takes responsibility for design •Contractor fully reimbursable for actual costs incurred •this includes corrective costs arising from design & construction errors •note – Contractor must use “reasonable skill and care to be expected of a properly qualified and competent Contractor”
  • 14. Which to use? •Red Book •Where purchaser wants certainty on costs •where full tender process is desired •standard package is required, with a detailed specification and engineering information is available
  • 15. Which to use? •Green Book •Purchaser wants flexibility and is confident to get involved with the process •more power to Project Manager •where technology is less advanced – perhaps the performance and results of the process are uncertain •if project relies on Purchaser’s specific knowledge or skills
  • 16. The Burgundy Book •Target Cost contract •attempts to promote co-operation and fairness between the parties through incentives •Typical operation •parties agree Target Cost for the works •contract includes formula that incentivises Contractor to minimise costs overspends •contractor records Actual Costs incurred on the project
  • 17. Pain share / gain share •Target Cost and Actual Cost is compared •any savings against the Target Cost are shared •Contractor is paid half of the saving •effectively a bonus for coming in under budget •any overruns against the Target Cost are shared •Contractor is only paid half of the overrun between the Target Cost and Actual Cost •effectively a penalty for overrun •Aim is to incentivise parties to achieve lowest Actual Costs possible
  • 18. Changes to costs •Clause 16 – variations •agreed variations allow an increase to the Target Cost •except where work is necessary for the Plant to comply with the Specification – Contractor not entitled to increase to Target Cost
  • 19. Changes to costs •Clause 37 – defects •the remediation of defects is at Purchaser’s cost – i.e. Contractor’s Actual Costs is increased •except where defect is due to Contractor’s failure to exercise reasonable skill and care
  • 20. Key considerations •Detailed and accurate Specification is critical •helps avoid costly variations arguments •Extensive role for Project Manager •important to select a strong and competent character to manage the project •note that PM must act impartially between the parties •Parties must be clear on Target & Actual Costs •full recording procedures and mechanisms must be included in contract Schedules
  • 21. Case study •Firstline Engineering Co v NLP Process Power
  • 22. JCT •Most common form of building contract •5 forms: •standard Building contract •design and Build (DB) Building contract •major Project Building contract •Minor works •intermediate
  • 23. Standard Building Contract •3 contracts in this category •approximate Quantities (measurement) •quantities (lump sum) •Without quantities (lump sum) •Provisions generally similar, main difference concerns way price is determined •lump sum price will be altered where works are varied or delayed, where delay is due to Employer •measurement changes to reflect the actual work carried out
  • 24. Standard Building Contract •Typically used for larger construction projects •complex engineering unlikely •Architect has contract administration role •supervise the day to day works and manage administration – crucially, notices •Employer retains some responsibility •termination notices for example
  • 25. Contractor’s Design Portion •If Contractor is to carry out some design, CDP is implemented •records the extent of the Contractor’s responsibility for certain elements of the works •may often use specialist sub-contractors
  • 26. Design and Build •Used on similar projects as Standard contracts •Contractor assumes responsibility for design and build •Contractor typically given Employer’s Requirements •produces proposals for design on this basis •Often design is produced by professional consultants, then novated to Contractor •Contractor’s design liability can be capped
  • 27. Differences •Contractor has design responsibility in DB •not in Standard, unless a CDP is used •note that Employer retains responsibility for Employers Requirements in DB – so not accurate that Contractor has ‘entire’ design responsibility wrap in DB •DB does not utilise a Contract Administrator, instead uses an Employer’s Agent
  • 28. Differences •Both contracts do not expressly deal with ground conditions •assumption is that Contractor retains responsibility •Note in DB – Employer retains responsibility for design within Employer’s Requirements (potentially leads to unexpected results)
  • 29. Major Building Contract •Intended for the largest of projects •Parties generally experience in large scale procurement •Contractor responsible for design •Shorter than DB contract, so suitable where parties have their own detailed procedures •Can be used where sectional completion is required
  • 30. Minor works •Two forms •minor Works Building Contract •minor Works Building Contract with Contractor’s design •CPD used where discreet elements of design are required from Contactor
  • 31. Minor works •Appropriate where works are simple in nature extensions, remodelling •Architect / Contract Administrator is used •Not suitable: •where wholesale design is required from Contractor •where bill of quantities are required •If detailed control / costs procedures required
  • 32. Intermediate contracts •Sit between Minor Works and Standard •used for reasonably simple projects where the skills and trades involved are conventional •Can utilise a CDP where Contractor is to do some design •not suitable as a full DB contract though
  • 33. NEC3 suite •Engineering and Construction Contract •most common •Professional Services Contract •Engineering and Construction Short Contract •Term Service Contract •Framework Contract
  • 34. NEC3 •Completely new drafting philosophy •different terminology used •some concern that the drafting is not tried and tested? •not lawyer friendly •legal precision takes a back seat in favour of promoting proactive management processes •Generally applicable to all types of works •national infrastructure particularly •Crossrail, Heathrow T2, London 2012 •Recommended and endorsed by government
  • 35. NEC3 philosophy •Intended to be a project management tool •aims to increase proactive risk management •Parties need to adopt and ‘buy into’ the philosophy •the look and feel of the contract is very different to typical forms •intention was to move away from ‘adversarial forms’
  • 36. Key points and features •Writing style •plain English, written in present tense •each clause stands alone – no cross referencing •the word ‘shall’ on appears once – in clause 10.1 •Clause 10.1 •all parties agree to “act in a spirit of mutual trust and co-operation” •underpins NEC philosophy •concerns over legal interpretation
  • 37. Key points and features •Project Manager takes extensive role •responsible for championing the NEC values •subject to clause 10.1 •high level of authority is required •must get involved in indentifying and managing risk proactively – risk register under clause 11
  • 38. Key points and features •Clause 11.2 (14) – risk register •parties must compile a risk register at the start of the project •must be continually updated as the project progresses •register describes risk and lists steps take to mitigate
  • 39. Key points and features •Clause 16 – early warning events •Contractor and PM are required to give early warning notices “as soon as either becomes aware of any matter which could •increase total of the Prices •delay Completion •delay meeting a Key Date •impair the performance of the works in use” •Wide ranging •Not ‘could’ – designed to encourage early and open disclosure
  • 40. Key points and features •Clause 60 – compensation events •wide ranging, detailed list •Clause 61.3 - Notification of compensation events •“the Contractor notifies the Project Manager of an event which has happened or which he expects to happen as a Compensation event...” •aimed at encouraging early disclosure so risk can be mitigated
  • 41. Amending the NEC3? •Innovative approach means there is room for criticism – especially for lawyers! •NEC advocates say this is deliberate – move away from the traditional approach •Wholesale amendment is therefore discouraged
  • 42. Amending the NEC3? •Some areas do require clarification •specify which documents are Contract Documents and order of precedence •no general obligation to comply with statutes •compensation event procedure is often regarded as overly bureaucratic •transfer of title provisions inadequate – especially where employer has paid for materials stored off site •Matter for parties – but remember philosophy
  • 44.