SlideShare a Scribd company logo
1 of 21
INTRODUCTION

1.1 Basic Rankine Cycle:
           The Rankine cycle is the oldest functional heat cycle utilized by man.
   The Rankine cycle is the very a basic vapor power cycle which is adopted in
   all the thermal power plants. It is a four step process (Figure 1.1) which
   involves the heating of the working fluid to its saturation temperature and
   vaporizing it isothermally, expanding the vapor on a turbine (work cycle),
   condensing the steam isothermally to the liquid phase and pumping it back to
   the boiler.




                           Figure 1.1 Basic Rankine Cycle


   Figure 2 represents the temperature-entropy diagram for the simplest version
   of the Rankine cycle. Although this simple version is rarely used it gives a
   very clear and simple picture on the working of the cycle.
           Process 1-2 is the pumping of the working fliud (water) into the boiler
   drum. The power required is derived from the overall power developed.
   Process 2-3 is the heating of the water upto its saturation temperature (100°C
   at 1 atm pressure for water) is reached and then isothermal heating of the
   water where the phase change from liquid to vapor occurs. Points 3 lie on the
   saturated vapor line. The steam here is completely dry. Process 3-4 is the
adiabatic expansion of the vapor/steam on the turbine to obtain mechanical
work. It is an isentropic process. The temperature of the steam is reduced and
it falls below the saturated vapor line. The dryness fraction is reduced to less
than one and a mixed liquid vapor phase is present. Process 4-1 is the
condensation process. This mixture is condensed in a condenser isothermally
and brought to the liquid phase back to the pump.




    FIGURE 1.2 Temperature vs. Entropy diagram for Rankine cycle


The steam is however, usually, superheated so as to obtain more work output.
Increasing the superheat to greater extent would lead to more work output.
However the energy spent in superheating the fuel is also high. The overall
effect is an increase in the thermal efficiency since the average temperature at
which the heat is added increases. Moisture content at the exit of the steam is
decreased as seen in the figure 1.3.
Superheating is     usually limited    to   620°C    owing to     metallurgical
considerations.




                                                                              2
Figure1.3 Rankine cycle with superheating




1.2 Energy Analysis of the Rankine Cycle:
           All four components in the Rankine Cycle (pump, boiler, turbine and
   condenser) are steady flow devices and thus can be analyzed under steady
   flow processes. K.E and P.E changes are small compared to work and heat
   transferred and is thereby neglected.
           Thus the steady flow equation (per unit mass) reduces to:
                                  Q+hini = W+hfinal
   Boiler and condenser do not involve any work and pump and turbine are
   assumed to be isentropic. The conservation of Energy relation for each device
   is expressed as follows:
          Steam turbine:
                  As the expansion is adiabatic (Q=0) and isentropic (S3=S4),
                  then,
                                    W3-4=Wturbine= (h3-h4) kJ/kg




                                                                              3
    Condenser:
                           Heat rejected in the condenser, Q4-1+h4=h1+W4-1
                           Since W4-1=0, Q4-1=h1-h4
                           Thus,
                                                   Q4-1=-(h4-h1) kJ/kg


                Pump:
                           Work required to pump water:
                           Wpump=h1-h2 kJ/kg (-ve work)


                Boiler:
                           Heat added in boiler:
                           Q2-3=h3-h2 kJ/kg=h3-h1-Wpump kJ/kg



Thus, the Rankine Efficiency=Work done/Heat added

                                   = (h3-h4-Wp) / (h3-h1-Wp)

        Neglecting feed pump work as it is very small compared to other quantities,
the efficiency reduces to:

ηrankine= (h3-h4) / (h3-h1).




    1.3 Factors increasing the Rankine Efficiency:


  i.    Lowering the condenser pressure:
                 Lowering the condenser pressure would lead to the lowering of
        temperature os steam. Thus for the same turbine inlet state, more work is
        obtained at lower temperatures.
                 This method though cannot be extensively used as it reduces the
        dryness fraction x of the steam. This is highly undesirable as it decreases the
        turbine efficiency is reduced due to excessive erosion of the turbine blades.




                                                                                          4
ii.    Superheating the steam to high temperature:
              There is an increase in the work output if superheating of steam is
       done. It increases the thermal efficiency as the average temperature at which
       heat is added increases.
              There is also another benfit of superheating; the steam at the exit of the
       turbine is drier than in case of non superheated steam.




iii.   Increasing the boiler pressure:
              Increasing the boiler pressure raises the average temperature at which
       heat is added and thereby increases the theramal efficiency. However the
       dryness fraction decreases for the same exit temperature of the boiler. This
       problem can be solved by employing reheating procedure. If however the
       boiler pressure is raised to supercritical point greater efficiency is obtained as
       the latent heat absorbed during phase change is reduced to zero.




                                                                                            5
SUPERCRITICAL RANKINE CYCYLE

2.1 Supercritical technology:

           When temperature and pressure of live steam are increased beyond the
   critical point of water, the properties of steam will change dramatically. The
   critical point of water is at 374 °C and 221.2 bar (218 atm), Figure 2.1, and it
   is defined to be the point where gaseous component cannot be liquefied by
   increasing the pressure applied to it. Beyond this critical point water does not
   experience a phase change to vapor, but it becomes a supercritical fluid.
   Supercritical fluid is not a gas or liquid. It is best described to be an
   intermediate between these two phases. It has similar solvent power as liquid,
   but its transport properties are similar to gases.




                             Figure 2.1 Phase diagram of water




                                                                                      6
2.2 Efficiency:
            The Rankine cycle can be greatly improved by operating in the
   supercritical region of the coolant. Most modern fossil fuel plants employ the
   supercritical Rankine Steam Cycle which pushes the thermal efficiency of the
   plant (see equation 4) into the low to mid 40% range.


           ηsupercritical = (h2-h1-h3+h4 )/( h2-h1)                     -(eqn 4)


2.3 Definition:




        Figure 2.2 T-S diagram for supercritical Rankine cycle


           For water, this cycle corresponds to pressures above 221.2 bar and
   temperatures above 374.15°C (647.3 K). The T-S diagram for a supercritical
   cycle can be seen in Figure 6. With the use of reheat and regeneration
   techniques, point 3 in Figure 2.1, which corresponds to the T-S vapor state of
   the coolant after it has expanded through a turbine, can be pushed to the right
   such that the coolant remains in the gas phase. This simplifies the system by
   eliminating the need for steam separators, dryers, and turbines specially
   designed for low quality steam.




                                                                                7
2.4 Material Concerns:
           The primary concern with this cycle, at least for water, is the material
    limits of the primary and support equipment. The materials in a boiler can be
    exposed to temperatures above their limit, within reason, so long as the rate of
    heat transfer to the coolant is sufficient to “cool” the material below its given
    limit. The same holds true for the turbine materials. With the advent of
    modern materials, i.e. super alloys and ceramics, not only are the physical
    limits of the materials being pushed to extremes, but the systems are
    functioning much closer to their limits. The current super alloys and coatings
    are allowing turbine inlet temperatures of up to 700°C (973 K). the fourth
    generation super alloys with ruthenium mono-crystal structures promise
    turbine inlet temperatures up to 1097°C (1370 K). Special alloys like Iconel
    740, Haynes 230, CCA617, etc. are used.


                       The metallurgical challenges faced and solutions:
   Normal Stainless steel proves of absolutely no use in building SC and USC
    Boilers.
   The high temperature and pressure in the boiler induce huge amount of
    stresses and fatigue in the materials. Also chances of oxidation are very high at
    such high temperature and pressure.
   To resist these stress levels and oxidation different advanced materials and
    alloys should be introduced.
   Also they should me machinable and weldable. This is a great metallurgical
    challenge.




                                                                                        8
CHAPTER 3

                          DESIGN AND WORKING

    3.1 Boiler Design:
              The design of Super and Ultra supercritical boilers (also called as
       Benson Boiler) is very critical as the working pressures of these boilers are
       very high. The boiler shells, the economizer unit, super heaters, air preheaters
       are specially designed. Their location is also of great significance.
  i.   Boiler shell:
              As shown in the figure 3.1 the geometry of the boilers and the
       configuration of the inlets determine the recirculation pattern inside boiler.
       The intensive recirculation created in the symmetric boiler results in a more
       uniform temperature field, lower temperature peaks, moderate oxygen
       concentration and complete burnout of the combustible gases and char




              Fig 3.1 Predicted Recirculation inside the combustion chamber

Table 3.1 lists the peak temperatures and burnout for designs A, B and C. the table
also lists the standard deviations of the predicted temperature and oxygen fields. The



                                                                                     9
lowest values for C indicate the higher degree of homogeneity. Thus the symmetrical
boiler seems to be the most suitable design.

                          A                     B                     C
Peak Temperature (K)      2618                  2437                  2106
Burnout %                 97                    99                    100
Standard deviation of 375                       238                   90
temperature (K)
Standard deviation of 3                         5                     1
O2 concentration %
                  Table 3.1 Results of the boiler shape determination

 ii.    Location of burners:
               The number of burners in the boiler shell is also of prime importance.
        Amongst all of them the downfired boilers are most suitable and
        advantageous. Table 3.2 gives a clear idea.


                               Upfired                        Downfired
Heat transfer rate, kW/m2      220                            261
Outlet temperature, K          1722                           1568
               Table 3.2 Results of the burner location determination




 iii.   Boiler dimensions:
               One of the most important advantages of HTAC applications are high
        heat fluxes. Thus, compact combustion chambers can be built and the
        investment costs can be lowered. The fourth calculation series was carried out
        in order to find the combustion chamber dimensions which can, on one hand,
        ensure an efficient heat exchange between combustion gas and water/steam
        mixture and on the other hand, ensure high values of firing density. Three
        different sizes are tested and they are named in as the small boiler, the medium
        size boiler and the large boiler .It has been observed (see Table 3.3) that the
        small boiler is too short. At the top a region of high temperatures exists and its




                                                                                          10
enthalpy cannot be efficiently used. On the contrary, in the large boiler
          although the heat fluxes are uniform, they are two times lower than in the
          medium size boiler. Therefore, the medium size boiler configuration is chosen
          for further investigations.


                         Small boiler           Medium size boiler     Large boiler
Firing Density           774                    238                    89
      3
kW/m
Outlet temperature,      1805                   1558                   1299
K
                            Table3.3 Results of the boiler size determination


    3.2 Working:
                 As already discussed, the working of Supercritical Boilers is similar to
          the working of sub-critical boilers. It works on the supercritical rankine cycle.
          Most supercritical boilers are being run at operating pressures above of 235
          bars. The working of ultra supercritical boilers has operating pressures above
          273 bars.




                                                                                         11
MATERIAL SELECTION



4.1 Metallurgical Problems:
           The available materials today like stainless steel which are usually
   used for boiler parts are not suitable for SC and USC boilers. They do not have
   the enough creep strength to resist the high pressure. Also there is high rate of
   oxidation at such high temperature and pressures which are beyond the
   capability of these materials to resist. Capable, qualified materials must be
   available to the industry to enable development of steam generators for SC
   steam conditions. Major components, such as infurnace tubing for the
   waterwalls, superheater/ reheater sections, headers, external piping, and other
   accessories require advancements in materials technology to allow outlet
   steam temperature increases to reach 760°C (1400F). Experiences with
   projects such as the pioneering Philo and Eddystone supercritical plants and
   the problems with the stainless steel steam piping and superheater fireside
   corrosion provided a valuable precautionary lesson for SC development.
   Industry organizations thus recognized that a thorough program was required
   to develop new and improved materials and protection methods necessary for
   these high temperature steam conditions.


4.2 Materials used:
           The materials used should be sustainable to the very high pressure
   being developed and should not get oxidized due to the very high temperature.
   Different high temperature materials are being used like 9 to 12% ferritic
   steels T91/P91, T92/P92, T112/P122 steel, Advanced Austenitic alloys TP347,
   HFG, Super 304, Nickel and chrome-nickel super alloys like Inconel 740.
           Table 4.2 gives a very brief idea about the boiler materials used for
   different parts of the boiler.




                                                                                 12
Heat surface           Tube material       Header material
       Economiser             SA-210 C            SA-106 C
       Furnace Walls          SA-213 T12          SA-106 C
       Super                  SA-213 T12          SA-335 P12
       heater/Reheater        SA-213 T23          SA-335 P91
                              SA-213 TP 304H      SA-335 P911
                              SA-213
                              TP347HFG
                              SUPER 304H
       Steam Piping                               SA 335 P91
                    Table 4.1 Materials for different boiler parts




       The materials for the other parts of the power plant (like turbine) also must be
sustainable for the super critically heated steam. The following table gives a detail
idea on the turbine materials of a plant operating on a supercritical cycle. (Table 4.3)




                                                                                       13
Component          1,050° F            1,150 °F        1,300° F    1,400 °F

  Casings            CrMoV (cast)      9–10% Cr (W)       CF8C-Plus   CCA617

  (shells, valves,   10CrMoVMb         12CrW (Co)         CCA617      Inconel 740
  steam chests,
  nozzles)                             CrMoWVNbN          Inconel 625 CF8C-Plus

                                                          Nimonic
                                                          263

  Bolting            422               9–12% CrMoV        Nimonic     Nimonic
                                                          105         105
                     9–12%             CrMoWVNbN
                     CrMoV                                Nimonic     Nimonic
                                                          115         115
                     Nimonic 80A
                                                          Waspaloy    U700

  Rotors/Discs       1CrMoV            9–12 % CrWCo       CCA617      CCA617

                     12CrMoVNbN 12CrMoWVNbN Inconel 625 Inconel 740



  Nozzles/Blades 422                   9–12% CrWCo        Wrought     Wrought
                                                          Ni-based    Ni-based
                     10CrMoVNbN 10CrMoVCbN

                           Table 4.2 Materials for other parts

The following figures show some of the materials used for SC and USC boilers.
Iconel 740 is widely used for steam pipings in almost all of them.




Figure 4.1 TP347HFG                          Figure 4.2 Iconel 740




                                                                                    14
SUPERCRITICAL BOILERS

5.1 A typical Supercritical Boilers:

        Largest CFB and first supercritical CFB sold to date is the Lagisza 460 MWe
unit Ordered by Poludniowy Koncern Energetyczny SA (PKE) in Poland. The design
is Essentially complete with financial closing expected in the first quarter of 2006 at
which time Fabrication and construction will commence. The largest capacity units in
operation today are the two (2) 300 MWe JEA repowered units which were designed
to fire any Combination of petroleum coke and bituminous coals. The physically
largest Foster Wheeler boilers in operation are the 262 MWe Turow Units 4, 5, and 6
which were designed to fire a high moisture brown coal. The design and configuration
of these units with Compact solids separators and INTREX™ heat exchangers were
used as the basis for the Lagisza design as well as for this study. The Lagisza design
was adjusted to accommodate a typical bituminous coal and the steam cycle.




                 Figure 5.1 The Lagisza 300 MWe plant in Poland




                                                                                          15
The following table gives a detail report on the performance of the Lagisza 800MWe
Power plant.



Parameters                                                 Values
Steam Conditions
Main Steam Pressure(barg)                                    315
Main steam Temperature(°C)                                   604
Reheat Steam temperature(°C)                                 615
Feed Water temperature(°C)                                   289
Emissions
SO2 mg/NM3                                                   111
NOx mg/NM3                                                   100
Power generation
Gross power MWe                                              805
Net power MWe                                                739
Net Plant Efficiency %                                       40.7
                         Table 5.1 Performance Parameters



5.2 Super and Sub Critical Boilers (comparative study):

                  There are many advantages of super critical boilers over normal
subcritical boilers, the prime advantage being the increased efficiency and reduced
emissions. There are many more advantages like no need of steam dryers, higher
operating pressures leading to more work output etc.

                  It is thus very important to have a comparative study of both the
boilers.




                                                                                 16
Technology            Efficiency (%)      Steam                  Typical emissions
                                          pressure/temperature
Ultra Supercritical                       >242       bar   and SO2-0.408
                                          593.33°C               kg/MHh

                            33–35                                NOx-0.286
                                                                 kg/MWh
                                                                 CO2-0.96 T/MWh
Supercritical                             >221.2     bar   and SO2-0.431
                                          537°C                  kg/MHh

                            36–40                                NOx-0.304
                                                                 kg/MWh
                                                                 CO2-1.02 T/MWh
Subritical                                165 bar 537°C          SO2-0.445
                                                                 kg/MHh
                            42–45
                                                                 NOx-0.31 kg/MWh
                                                                 CO2-1.02 T/MWh
                Table 5.2 Comparison of sub and supercritical boilers




                                                                                 17
ADVANCE IN SC TECHNOLGY AND FUTURE IN INDIA

6.1 Natural Gas Production with a Supercritical Geothermal Power Application By-
product:

        In many cases, the source for Natural Gas production is geothermally heated
brine. In these cases, the brine temperatures range from 240 °F (390 K) up to 360 °F
(455 K) depending linearly upon well depth. In this temperature range, the brine
passes through a heat exchanger to feed a supercritical Rankine cycle for Propane,
which has a critical temperature of 206 °F (370 K) and a critical pressure of 616 psia.
Theoretically, the brine may be able to run the cycle directly but there are too many
contaminants and compositional variations for this to be feasible. If a power cycle like
this were employed, the sites producing Natural Gas could potentially generate power
for Grid use or, at a minimum, generate the majority of the plant’s electrical
Requirements. In the United States, there are several areas along the Texas and the
Louisiana Gulf Coast where this type of power cycle is feasible. The benefit to this
cycle is that it is extremely simple in terms of system components. The system
Requires only a single phase heat exchanger, a turbine, an air cooled condenser, and a
pump. The nominal operating pressure of this system is approximately 1000 psia,
which suggests that all of the support piping and equipment is commercially
available. Given a 15 Million BTU/hr brine source, this system could generate
approximately 400 kW net powers with a thermal efficiency of 9%. Additionally, the
system can be built to be self regulating by using the power grid as a dynamic brake
for the turbine-generator set. In effect, this acts as a speed control for the turbine
during slight variations in system demand under normal operating conditions.
Additional controls can be implemented to automate the system based on brine
temperature and flow rates, all of which minimize the need to have a full-time
operator, thus reducing operational costs.




                                                                                         18
6.2 Supercritical Boilers in India:
       There haven’t been any supercritical boilers in use in India so far. The
European countries, USA, Japan have been using supercritical technology since the
last two decades. However, there are upcoming projects to build power plants
working under the supercritical technology in India.
       The National Thermal Power Corporation (NTPC) had entrusted a techno
economic study to M/s EPDC for super-critical Vs Sub-critical Boilers for their
proposed Sipat STPS (4x500 MW) in Madhya Pradesh.
       M/s EPDC has recommended that a first step to the introduction of super-
critical technology, the most proven steam conditions may be chosen and the most
applicable steam conditions in India shall be 246 kg/cm2, 538° C/566° C. With these
steam parameters, M/s EPDC has estimated that the capital cost for a supercritical
power station (4x500 MW) shall be about 2% higher than that of sub-critical power
plant but at the same time the plant efficiency shall improve from 38.64% to 39.6%.
Being a pit head thermal power project, the saving in fuel charges is not justified by
increase in fixed charges.
       Here are some upcoming projects in India:


              North Karanpura, Jharkhand – 3x660 MW
              Darlipali, Orissa – 4x800 MW
              Lara, Chattisgarh – 5x800 MW
              Marakanam, Tamilnadu – 4x800 MW
              Tanda-II, Uttar Pradesh - 2x660 MW
              Meja, Uttar Pradesh - 2x660 MW
              Sholapur – 2x660 MW
              New Nabinagar-3x660 MW
              Many more projects including 800 MW ultra super critical units under
               consideration




                                                                                         19
CONCLUSION
        The supercritical Rankine cycle, in general, offers an additional 30% relative
improvement in the thermal efficiency as compared to the same system operating in
the subcritical region. The cycle has been successfully utilized in fossil fuel plants
but the current available materials prohibit reliable application of the supercritical
cycle to nuclear applications. There is much work to be done in order to advance
materials to the point where they will be able to reliably withstand the stresses of a
supercritical environment inside a nuclear reactor for a designed life span of 60 years.
        Supercritical boiler technology has matured, through advancements in design
and materials. Coal-fired supercritical units supplied around the world over the past
several years have been operating with high efficiency performance and high
availability.




                                                                                        20
REFERENCES
1. “Design Aspects of the Ultra-Supercritical CFB Boiler”; Stephen J.
   Goidich, Song Wu, Zhen Fan; Foster Wheeler North America Corp.
2. “Novel conceptual design of a supercritical pulverized coal boiler
   utilizing high temperature air combustion (HTAC) technology”;
   Natalia Schaffel-Mancini, Marco Mancini, Andrzej Szlek, Roman
   Weber; Institute of Energy Process Engineering and Fuel Technology,
   Clausthal University of Technology, Agricolastr. 4, 38678 Clausthal-
   Zellerfeld, Germany; 6 February 2010.
3. “Supercritical (Once Through) Boiler Technology”; J.W. Smith,
   Babcock & Wilcox, Barberton, Ohio, U.S.A.; May 1998.
4. “Steam Generator for Advanced Ultra-Supercritical Power Plants 700
   to 760°C”; P.S. Weitzel; ASME 2011 Power Conference, Denver,
   Colorado, U.S.A; July 12-14, 2011.
5. “Supercritical boiler technology for future market conditions”;
   Joachim Franke and Rudolf Kral; Siemens Power Generation; Parsons
   Conference; 2003.
6. “Steam Turbine Design Considerations for Supercritical Cycles”;
   Justin Zachary, Paul Kochis, Ram Narula; Coal Gen 2007
   Conference;1-3 August 2007.
7. “Technology status of thermal power plants in India and opportunities
   in renovation and modernization”; TERI, D S Block, India Habitat
   Centre, Lodi Road, New Delhi – 110003.
8. “Applied Thermodynamics”; Dr. H.N Sawant; January 1992; revised
   July 2004.
9. “http://en.wikipedia.org/wiki/Boiler#Supercritical_steam_generator”




                                                                         21

More Related Content

What's hot

[PPT] on Steam Turbine
[PPT] on Steam Turbine[PPT] on Steam Turbine
[PPT] on Steam TurbineSumit Sharma
 
Fireball Formation and Combustion of Coal in a Boiler
Fireball Formation and Combustion of Coal in a BoilerFireball Formation and Combustion of Coal in a Boiler
Fireball Formation and Combustion of Coal in a BoilerZalak Shah
 
Improve plant heat rate with feedwater heater control
Improve plant heat rate with feedwater heater controlImprove plant heat rate with feedwater heater control
Improve plant heat rate with feedwater heater controlHossam Zein
 
Energy adudit methodology for boiler
Energy adudit methodology for boilerEnergy adudit methodology for boiler
Energy adudit methodology for boilerKongkiert Tankayura
 
Cfb boiler basic design, operation and maintenance
Cfb boiler basic design, operation and maintenanceCfb boiler basic design, operation and maintenance
Cfb boiler basic design, operation and maintenancePichai Chaibamrung
 
Monitoring Coal mill Performance
Monitoring Coal mill PerformanceMonitoring Coal mill Performance
Monitoring Coal mill PerformanceManohar Tatwawadi
 
660 mw supercritical boiler
660 mw supercritical boiler660 mw supercritical boiler
660 mw supercritical boilerAshvani Shukla
 
Pinch analysis technique to optimize heat exchanger
Pinch analysis technique to optimize heat exchangerPinch analysis technique to optimize heat exchanger
Pinch analysis technique to optimize heat exchangerK Vivek Varkey
 
Gas turbine plant
Gas turbine plantGas turbine plant
Gas turbine plantrajendrasm
 
Super Critical Technology-Fundamental Concepts about Super Critical Technolog...
Super Critical Technology-Fundamental Concepts about Super Critical Technolog...Super Critical Technology-Fundamental Concepts about Super Critical Technolog...
Super Critical Technology-Fundamental Concepts about Super Critical Technolog...Raghab Gorain
 
How Gas Turbines Work
How Gas Turbines WorkHow Gas Turbines Work
How Gas Turbines Workalidouceur
 
Boilers and its types & components
Boilers and its types & componentsBoilers and its types & components
Boilers and its types & componentsYoga Sathish
 
Hp/ lp bypass system for steam turbines
Hp/ lp bypass system for steam turbinesHp/ lp bypass system for steam turbines
Hp/ lp bypass system for steam turbinesBoben Anto Chemmannoor
 

What's hot (20)

[PPT] on Steam Turbine
[PPT] on Steam Turbine[PPT] on Steam Turbine
[PPT] on Steam Turbine
 
Boiler Introduction
Boiler IntroductionBoiler Introduction
Boiler Introduction
 
Fireball Formation and Combustion of Coal in a Boiler
Fireball Formation and Combustion of Coal in a BoilerFireball Formation and Combustion of Coal in a Boiler
Fireball Formation and Combustion of Coal in a Boiler
 
Improve plant heat rate with feedwater heater control
Improve plant heat rate with feedwater heater controlImprove plant heat rate with feedwater heater control
Improve plant heat rate with feedwater heater control
 
Steam turbine Working
Steam turbine WorkingSteam turbine Working
Steam turbine Working
 
Energy adudit methodology for boiler
Energy adudit methodology for boilerEnergy adudit methodology for boiler
Energy adudit methodology for boiler
 
Cfb boiler basic design, operation and maintenance
Cfb boiler basic design, operation and maintenanceCfb boiler basic design, operation and maintenance
Cfb boiler basic design, operation and maintenance
 
Monitoring Coal mill Performance
Monitoring Coal mill PerformanceMonitoring Coal mill Performance
Monitoring Coal mill Performance
 
660 mw supercritical boiler
660 mw supercritical boiler660 mw supercritical boiler
660 mw supercritical boiler
 
Steam turbine and its types
Steam turbine and its typesSteam turbine and its types
Steam turbine and its types
 
Ppt on boilers
Ppt on boilersPpt on boilers
Ppt on boilers
 
Steam boiler
Steam boilerSteam boiler
Steam boiler
 
Pinch analysis technique to optimize heat exchanger
Pinch analysis technique to optimize heat exchangerPinch analysis technique to optimize heat exchanger
Pinch analysis technique to optimize heat exchanger
 
Turbine.
Turbine.Turbine.
Turbine.
 
Gas turbine plant
Gas turbine plantGas turbine plant
Gas turbine plant
 
Super Critical Technology-Fundamental Concepts about Super Critical Technolog...
Super Critical Technology-Fundamental Concepts about Super Critical Technolog...Super Critical Technology-Fundamental Concepts about Super Critical Technolog...
Super Critical Technology-Fundamental Concepts about Super Critical Technolog...
 
How Gas Turbines Work
How Gas Turbines WorkHow Gas Turbines Work
How Gas Turbines Work
 
Boilers and its types & components
Boilers and its types & componentsBoilers and its types & components
Boilers and its types & components
 
Hp/ lp bypass system for steam turbines
Hp/ lp bypass system for steam turbinesHp/ lp bypass system for steam turbines
Hp/ lp bypass system for steam turbines
 
Steam turbine basics
Steam turbine basicsSteam turbine basics
Steam turbine basics
 

Viewers also liked

super critical power plant
super critical power plantsuper critical power plant
super critical power plantsridurga88
 
Water steam Circuit in Supercritical Boiler for 660MW Power Plant
Water steam Circuit in Supercritical Boiler for 660MW Power PlantWater steam Circuit in Supercritical Boiler for 660MW Power Plant
Water steam Circuit in Supercritical Boiler for 660MW Power PlantHareesh VS
 
Supercritical boiler ntpc sipat
Supercritical boiler ntpc sipatSupercritical boiler ntpc sipat
Supercritical boiler ntpc sipatpratikguptateddy
 
Seminar report on supercritical thenology
Seminar report on supercritical thenologySeminar report on supercritical thenology
Seminar report on supercritical thenologynirgudebhau111
 
ganesh ppts on supercritical thenology
ganesh ppts on supercritical thenologyganesh ppts on supercritical thenology
ganesh ppts on supercritical thenologynirgudebhau111
 
Boiler Process Instrumentation and controls
Boiler Process Instrumentation and controlsBoiler Process Instrumentation and controls
Boiler Process Instrumentation and controlsADITYA AGARWAL
 
THERMAL POWER PLANT (COAL TO POWER)
THERMAL POWER PLANT (COAL TO POWER)THERMAL POWER PLANT (COAL TO POWER)
THERMAL POWER PLANT (COAL TO POWER)Baibhav Saha
 
Dsp based implementation of field oriented control of three phase induction m...
Dsp based implementation of field oriented control of three phase induction m...Dsp based implementation of field oriented control of three phase induction m...
Dsp based implementation of field oriented control of three phase induction m...eSAT Journals
 
Fukushima-Daiichi Learning from Experience: Nuclear Power Risks
Fukushima-Daiichi Learning from Experience: Nuclear Power RisksFukushima-Daiichi Learning from Experience: Nuclear Power Risks
Fukushima-Daiichi Learning from Experience: Nuclear Power RisksHIMADRI BANERJI
 
Thyssenkrupp uhde advanced ammonia processes dual pressure
Thyssenkrupp uhde advanced ammonia processes dual pressureThyssenkrupp uhde advanced ammonia processes dual pressure
Thyssenkrupp uhde advanced ammonia processes dual pressureSteve Wittrig
 
Commisioning of Supercritical Power Units: Risks to an EPC Contractor
Commisioning of Supercritical Power Units: Risks to an EPC ContractorCommisioning of Supercritical Power Units: Risks to an EPC Contractor
Commisioning of Supercritical Power Units: Risks to an EPC ContractorHIMADRI BANERJI
 
Thermal Power plant familarisation & its Auxillaries
Thermal Power plant familarisation & its AuxillariesThermal Power plant familarisation & its Auxillaries
Thermal Power plant familarisation & its AuxillariesVaibhav Paydelwar
 

Viewers also liked (20)

Super critical boiler
Super critical boilerSuper critical boiler
Super critical boiler
 
super critical power plant
super critical power plantsuper critical power plant
super critical power plant
 
Super critical boiler
Super critical boilerSuper critical boiler
Super critical boiler
 
Water steam Circuit in Supercritical Boiler for 660MW Power Plant
Water steam Circuit in Supercritical Boiler for 660MW Power PlantWater steam Circuit in Supercritical Boiler for 660MW Power Plant
Water steam Circuit in Supercritical Boiler for 660MW Power Plant
 
Supercritical boiler ntpc sipat
Supercritical boiler ntpc sipatSupercritical boiler ntpc sipat
Supercritical boiler ntpc sipat
 
Seminar report on supercritical thenology
Seminar report on supercritical thenologySeminar report on supercritical thenology
Seminar report on supercritical thenology
 
Thermal power plant
Thermal power plantThermal power plant
Thermal power plant
 
ganesh ppts on supercritical thenology
ganesh ppts on supercritical thenologyganesh ppts on supercritical thenology
ganesh ppts on supercritical thenology
 
Thermal power plant
Thermal power plantThermal power plant
Thermal power plant
 
BOILER INSTRUMENTATION
BOILER INSTRUMENTATIONBOILER INSTRUMENTATION
BOILER INSTRUMENTATION
 
Boiler Process Instrumentation and controls
Boiler Process Instrumentation and controlsBoiler Process Instrumentation and controls
Boiler Process Instrumentation and controls
 
Steam boiler
Steam boilerSteam boiler
Steam boiler
 
THERMAL POWER PLANT (COAL TO POWER)
THERMAL POWER PLANT (COAL TO POWER)THERMAL POWER PLANT (COAL TO POWER)
THERMAL POWER PLANT (COAL TO POWER)
 
Dsp based implementation of field oriented control of three phase induction m...
Dsp based implementation of field oriented control of three phase induction m...Dsp based implementation of field oriented control of three phase induction m...
Dsp based implementation of field oriented control of three phase induction m...
 
Fukushima-Daiichi Learning from Experience: Nuclear Power Risks
Fukushima-Daiichi Learning from Experience: Nuclear Power RisksFukushima-Daiichi Learning from Experience: Nuclear Power Risks
Fukushima-Daiichi Learning from Experience: Nuclear Power Risks
 
Thyssenkrupp uhde advanced ammonia processes dual pressure
Thyssenkrupp uhde advanced ammonia processes dual pressureThyssenkrupp uhde advanced ammonia processes dual pressure
Thyssenkrupp uhde advanced ammonia processes dual pressure
 
Commisioning of Supercritical Power Units: Risks to an EPC Contractor
Commisioning of Supercritical Power Units: Risks to an EPC ContractorCommisioning of Supercritical Power Units: Risks to an EPC Contractor
Commisioning of Supercritical Power Units: Risks to an EPC Contractor
 
Thermal Power plant familarisation & its Auxillaries
Thermal Power plant familarisation & its AuxillariesThermal Power plant familarisation & its Auxillaries
Thermal Power plant familarisation & its Auxillaries
 
Types of turbine
Types of turbineTypes of turbine
Types of turbine
 
MET 211 steam-turbines
MET 211 steam-turbinesMET 211 steam-turbines
MET 211 steam-turbines
 

Similar to Supercritical steam generators

Vapor_power cycles KM.pptx ..
Vapor_power cycles KM.pptx            ..Vapor_power cycles KM.pptx            ..
Vapor_power cycles KM.pptx ..happycocoman
 
Steam Power Cycle and Basics of Boiler
Steam Power Cycle and Basics of BoilerSteam Power Cycle and Basics of Boiler
Steam Power Cycle and Basics of BoilerMulugeta Wotango
 
vapour-power-cycle.pptx
vapour-power-cycle.pptxvapour-power-cycle.pptx
vapour-power-cycle.pptxDhruvBagade
 
vapour-power-cycle h.pptx
vapour-power-cycle                          h.pptxvapour-power-cycle                          h.pptx
vapour-power-cycle h.pptxMahamad Jawhar
 
Vapour power cycles
Vapour power cyclesVapour power cycles
Vapour power cycleskrishna khot
 
Vapour power cycle thermo veer ME201 PPT
Vapour power cycle thermo veer ME201 PPTVapour power cycle thermo veer ME201 PPT
Vapour power cycle thermo veer ME201 PPTsreddyrahul
 
ThermoDynamics (Working of steam power plant and rankine cyle)
ThermoDynamics (Working of steam power plant and rankine cyle)ThermoDynamics (Working of steam power plant and rankine cyle)
ThermoDynamics (Working of steam power plant and rankine cyle)Graphic Era University.
 
Improvement of rankine efficinecy of steam power plants
Improvement of rankine efficinecy of steam power plantsImprovement of rankine efficinecy of steam power plants
Improvement of rankine efficinecy of steam power plantsDhilip Pugalenthi
 
Lecture 5.pptx
Lecture 5.pptxLecture 5.pptx
Lecture 5.pptxNelyJay
 
performance analysis of steam power plants using ideal reheat rankin cycle
performance analysis of steam power plants using ideal reheat rankin cycleperformance analysis of steam power plants using ideal reheat rankin cycle
performance analysis of steam power plants using ideal reheat rankin cycleIJAEMSJORNAL
 
thermal project 1
thermal project 1thermal project 1
thermal project 1James Li
 
01 regenerative feed heating
01 regenerative feed heating01 regenerative feed heating
01 regenerative feed heatingAnil Palamwar
 

Similar to Supercritical steam generators (20)

Ganesh final report
Ganesh final reportGanesh final report
Ganesh final report
 
Vapor_power cycles KM.pptx ..
Vapor_power cycles KM.pptx            ..Vapor_power cycles KM.pptx            ..
Vapor_power cycles KM.pptx ..
 
Steam Power Cycle and Basics of Boiler
Steam Power Cycle and Basics of BoilerSteam Power Cycle and Basics of Boiler
Steam Power Cycle and Basics of Boiler
 
Power cycles
Power cyclesPower cycles
Power cycles
 
vapour-power-cycle.pptx
vapour-power-cycle.pptxvapour-power-cycle.pptx
vapour-power-cycle.pptx
 
vapour-power-cycle h.pptx
vapour-power-cycle                          h.pptxvapour-power-cycle                          h.pptx
vapour-power-cycle h.pptx
 
Vapour power cycles
Vapour power cyclesVapour power cycles
Vapour power cycles
 
Vapour power cycle thermo veer ME201 PPT
Vapour power cycle thermo veer ME201 PPTVapour power cycle thermo veer ME201 PPT
Vapour power cycle thermo veer ME201 PPT
 
ThermoDynamics (Working of steam power plant and rankine cyle)
ThermoDynamics (Working of steam power plant and rankine cyle)ThermoDynamics (Working of steam power plant and rankine cyle)
ThermoDynamics (Working of steam power plant and rankine cyle)
 
Steam power plant
Steam power plantSteam power plant
Steam power plant
 
Power cycles 1
Power cycles 1Power cycles 1
Power cycles 1
 
Chapter 10 lecture
Chapter 10 lectureChapter 10 lecture
Chapter 10 lecture
 
Improvement of rankine efficinecy of steam power plants
Improvement of rankine efficinecy of steam power plantsImprovement of rankine efficinecy of steam power plants
Improvement of rankine efficinecy of steam power plants
 
Unit_2_58.pdf
Unit_2_58.pdfUnit_2_58.pdf
Unit_2_58.pdf
 
Rnakine reheat regen
Rnakine reheat regenRnakine reheat regen
Rnakine reheat regen
 
Lecture 5.pptx
Lecture 5.pptxLecture 5.pptx
Lecture 5.pptx
 
performance analysis of steam power plants using ideal reheat rankin cycle
performance analysis of steam power plants using ideal reheat rankin cycleperformance analysis of steam power plants using ideal reheat rankin cycle
performance analysis of steam power plants using ideal reheat rankin cycle
 
thermal project 1
thermal project 1thermal project 1
thermal project 1
 
thermo course.ppt
thermo course.pptthermo course.ppt
thermo course.ppt
 
01 regenerative feed heating
01 regenerative feed heating01 regenerative feed heating
01 regenerative feed heating
 

Recently uploaded

Unlocking the Secrets of Affiliate Marketing.pdf
Unlocking the Secrets of Affiliate Marketing.pdfUnlocking the Secrets of Affiliate Marketing.pdf
Unlocking the Secrets of Affiliate Marketing.pdfOnline Income Engine
 
Monte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMMonte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMRavindra Nath Shukla
 
Russian Faridabad Call Girls(Badarpur) : ☎ 8168257667, @4999
Russian Faridabad Call Girls(Badarpur) : ☎ 8168257667, @4999Russian Faridabad Call Girls(Badarpur) : ☎ 8168257667, @4999
Russian Faridabad Call Girls(Badarpur) : ☎ 8168257667, @4999Tina Ji
 
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779Delhi Call girls
 
Best Basmati Rice Manufacturers in India
Best Basmati Rice Manufacturers in IndiaBest Basmati Rice Manufacturers in India
Best Basmati Rice Manufacturers in IndiaShree Krishna Exports
 
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...Any kyc Account
 
GD Birla and his contribution in management
GD Birla and his contribution in managementGD Birla and his contribution in management
GD Birla and his contribution in managementchhavia330
 
Keppel Ltd. 1Q 2024 Business Update Presentation Slides
Keppel Ltd. 1Q 2024 Business Update  Presentation SlidesKeppel Ltd. 1Q 2024 Business Update  Presentation Slides
Keppel Ltd. 1Q 2024 Business Update Presentation SlidesKeppelCorporation
 
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...anilsa9823
 
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRLMONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRLSeo
 
Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Roland Driesen
 
Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Neil Kimberley
 
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesMysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesDipal Arora
 
It will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayIt will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayNZSG
 
Event mailer assignment progress report .pdf
Event mailer assignment progress report .pdfEvent mailer assignment progress report .pdf
Event mailer assignment progress report .pdftbatkhuu1
 
Monthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxMonthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxAndy Lambert
 
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...Lviv Startup Club
 
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableCall Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableDipal Arora
 
7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...Paul Menig
 

Recently uploaded (20)

Unlocking the Secrets of Affiliate Marketing.pdf
Unlocking the Secrets of Affiliate Marketing.pdfUnlocking the Secrets of Affiliate Marketing.pdf
Unlocking the Secrets of Affiliate Marketing.pdf
 
Monte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMMonte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSM
 
Russian Faridabad Call Girls(Badarpur) : ☎ 8168257667, @4999
Russian Faridabad Call Girls(Badarpur) : ☎ 8168257667, @4999Russian Faridabad Call Girls(Badarpur) : ☎ 8168257667, @4999
Russian Faridabad Call Girls(Badarpur) : ☎ 8168257667, @4999
 
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
 
Best Basmati Rice Manufacturers in India
Best Basmati Rice Manufacturers in IndiaBest Basmati Rice Manufacturers in India
Best Basmati Rice Manufacturers in India
 
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
 
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
 
GD Birla and his contribution in management
GD Birla and his contribution in managementGD Birla and his contribution in management
GD Birla and his contribution in management
 
Keppel Ltd. 1Q 2024 Business Update Presentation Slides
Keppel Ltd. 1Q 2024 Business Update  Presentation SlidesKeppel Ltd. 1Q 2024 Business Update  Presentation Slides
Keppel Ltd. 1Q 2024 Business Update Presentation Slides
 
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
 
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRLMONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
 
Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...
 
Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023
 
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesMysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
 
It will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayIt will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 May
 
Event mailer assignment progress report .pdf
Event mailer assignment progress report .pdfEvent mailer assignment progress report .pdf
Event mailer assignment progress report .pdf
 
Monthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxMonthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptx
 
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
 
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableCall Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
 
7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...
 

Supercritical steam generators

  • 1. INTRODUCTION 1.1 Basic Rankine Cycle: The Rankine cycle is the oldest functional heat cycle utilized by man. The Rankine cycle is the very a basic vapor power cycle which is adopted in all the thermal power plants. It is a four step process (Figure 1.1) which involves the heating of the working fluid to its saturation temperature and vaporizing it isothermally, expanding the vapor on a turbine (work cycle), condensing the steam isothermally to the liquid phase and pumping it back to the boiler. Figure 1.1 Basic Rankine Cycle Figure 2 represents the temperature-entropy diagram for the simplest version of the Rankine cycle. Although this simple version is rarely used it gives a very clear and simple picture on the working of the cycle. Process 1-2 is the pumping of the working fliud (water) into the boiler drum. The power required is derived from the overall power developed. Process 2-3 is the heating of the water upto its saturation temperature (100°C at 1 atm pressure for water) is reached and then isothermal heating of the water where the phase change from liquid to vapor occurs. Points 3 lie on the saturated vapor line. The steam here is completely dry. Process 3-4 is the
  • 2. adiabatic expansion of the vapor/steam on the turbine to obtain mechanical work. It is an isentropic process. The temperature of the steam is reduced and it falls below the saturated vapor line. The dryness fraction is reduced to less than one and a mixed liquid vapor phase is present. Process 4-1 is the condensation process. This mixture is condensed in a condenser isothermally and brought to the liquid phase back to the pump. FIGURE 1.2 Temperature vs. Entropy diagram for Rankine cycle The steam is however, usually, superheated so as to obtain more work output. Increasing the superheat to greater extent would lead to more work output. However the energy spent in superheating the fuel is also high. The overall effect is an increase in the thermal efficiency since the average temperature at which the heat is added increases. Moisture content at the exit of the steam is decreased as seen in the figure 1.3. Superheating is usually limited to 620°C owing to metallurgical considerations. 2
  • 3. Figure1.3 Rankine cycle with superheating 1.2 Energy Analysis of the Rankine Cycle: All four components in the Rankine Cycle (pump, boiler, turbine and condenser) are steady flow devices and thus can be analyzed under steady flow processes. K.E and P.E changes are small compared to work and heat transferred and is thereby neglected. Thus the steady flow equation (per unit mass) reduces to: Q+hini = W+hfinal Boiler and condenser do not involve any work and pump and turbine are assumed to be isentropic. The conservation of Energy relation for each device is expressed as follows:  Steam turbine: As the expansion is adiabatic (Q=0) and isentropic (S3=S4), then, W3-4=Wturbine= (h3-h4) kJ/kg 3
  • 4. Condenser: Heat rejected in the condenser, Q4-1+h4=h1+W4-1 Since W4-1=0, Q4-1=h1-h4 Thus, Q4-1=-(h4-h1) kJ/kg  Pump: Work required to pump water: Wpump=h1-h2 kJ/kg (-ve work)  Boiler: Heat added in boiler: Q2-3=h3-h2 kJ/kg=h3-h1-Wpump kJ/kg Thus, the Rankine Efficiency=Work done/Heat added = (h3-h4-Wp) / (h3-h1-Wp) Neglecting feed pump work as it is very small compared to other quantities, the efficiency reduces to: ηrankine= (h3-h4) / (h3-h1). 1.3 Factors increasing the Rankine Efficiency: i. Lowering the condenser pressure: Lowering the condenser pressure would lead to the lowering of temperature os steam. Thus for the same turbine inlet state, more work is obtained at lower temperatures. This method though cannot be extensively used as it reduces the dryness fraction x of the steam. This is highly undesirable as it decreases the turbine efficiency is reduced due to excessive erosion of the turbine blades. 4
  • 5. ii. Superheating the steam to high temperature: There is an increase in the work output if superheating of steam is done. It increases the thermal efficiency as the average temperature at which heat is added increases. There is also another benfit of superheating; the steam at the exit of the turbine is drier than in case of non superheated steam. iii. Increasing the boiler pressure: Increasing the boiler pressure raises the average temperature at which heat is added and thereby increases the theramal efficiency. However the dryness fraction decreases for the same exit temperature of the boiler. This problem can be solved by employing reheating procedure. If however the boiler pressure is raised to supercritical point greater efficiency is obtained as the latent heat absorbed during phase change is reduced to zero. 5
  • 6. SUPERCRITICAL RANKINE CYCYLE 2.1 Supercritical technology: When temperature and pressure of live steam are increased beyond the critical point of water, the properties of steam will change dramatically. The critical point of water is at 374 °C and 221.2 bar (218 atm), Figure 2.1, and it is defined to be the point where gaseous component cannot be liquefied by increasing the pressure applied to it. Beyond this critical point water does not experience a phase change to vapor, but it becomes a supercritical fluid. Supercritical fluid is not a gas or liquid. It is best described to be an intermediate between these two phases. It has similar solvent power as liquid, but its transport properties are similar to gases. Figure 2.1 Phase diagram of water 6
  • 7. 2.2 Efficiency: The Rankine cycle can be greatly improved by operating in the supercritical region of the coolant. Most modern fossil fuel plants employ the supercritical Rankine Steam Cycle which pushes the thermal efficiency of the plant (see equation 4) into the low to mid 40% range. ηsupercritical = (h2-h1-h3+h4 )/( h2-h1) -(eqn 4) 2.3 Definition: Figure 2.2 T-S diagram for supercritical Rankine cycle For water, this cycle corresponds to pressures above 221.2 bar and temperatures above 374.15°C (647.3 K). The T-S diagram for a supercritical cycle can be seen in Figure 6. With the use of reheat and regeneration techniques, point 3 in Figure 2.1, which corresponds to the T-S vapor state of the coolant after it has expanded through a turbine, can be pushed to the right such that the coolant remains in the gas phase. This simplifies the system by eliminating the need for steam separators, dryers, and turbines specially designed for low quality steam. 7
  • 8. 2.4 Material Concerns: The primary concern with this cycle, at least for water, is the material limits of the primary and support equipment. The materials in a boiler can be exposed to temperatures above their limit, within reason, so long as the rate of heat transfer to the coolant is sufficient to “cool” the material below its given limit. The same holds true for the turbine materials. With the advent of modern materials, i.e. super alloys and ceramics, not only are the physical limits of the materials being pushed to extremes, but the systems are functioning much closer to their limits. The current super alloys and coatings are allowing turbine inlet temperatures of up to 700°C (973 K). the fourth generation super alloys with ruthenium mono-crystal structures promise turbine inlet temperatures up to 1097°C (1370 K). Special alloys like Iconel 740, Haynes 230, CCA617, etc. are used. The metallurgical challenges faced and solutions:  Normal Stainless steel proves of absolutely no use in building SC and USC Boilers.  The high temperature and pressure in the boiler induce huge amount of stresses and fatigue in the materials. Also chances of oxidation are very high at such high temperature and pressure.  To resist these stress levels and oxidation different advanced materials and alloys should be introduced.  Also they should me machinable and weldable. This is a great metallurgical challenge. 8
  • 9. CHAPTER 3 DESIGN AND WORKING 3.1 Boiler Design: The design of Super and Ultra supercritical boilers (also called as Benson Boiler) is very critical as the working pressures of these boilers are very high. The boiler shells, the economizer unit, super heaters, air preheaters are specially designed. Their location is also of great significance. i. Boiler shell: As shown in the figure 3.1 the geometry of the boilers and the configuration of the inlets determine the recirculation pattern inside boiler. The intensive recirculation created in the symmetric boiler results in a more uniform temperature field, lower temperature peaks, moderate oxygen concentration and complete burnout of the combustible gases and char Fig 3.1 Predicted Recirculation inside the combustion chamber Table 3.1 lists the peak temperatures and burnout for designs A, B and C. the table also lists the standard deviations of the predicted temperature and oxygen fields. The 9
  • 10. lowest values for C indicate the higher degree of homogeneity. Thus the symmetrical boiler seems to be the most suitable design. A B C Peak Temperature (K) 2618 2437 2106 Burnout % 97 99 100 Standard deviation of 375 238 90 temperature (K) Standard deviation of 3 5 1 O2 concentration % Table 3.1 Results of the boiler shape determination ii. Location of burners: The number of burners in the boiler shell is also of prime importance. Amongst all of them the downfired boilers are most suitable and advantageous. Table 3.2 gives a clear idea. Upfired Downfired Heat transfer rate, kW/m2 220 261 Outlet temperature, K 1722 1568 Table 3.2 Results of the burner location determination iii. Boiler dimensions: One of the most important advantages of HTAC applications are high heat fluxes. Thus, compact combustion chambers can be built and the investment costs can be lowered. The fourth calculation series was carried out in order to find the combustion chamber dimensions which can, on one hand, ensure an efficient heat exchange between combustion gas and water/steam mixture and on the other hand, ensure high values of firing density. Three different sizes are tested and they are named in as the small boiler, the medium size boiler and the large boiler .It has been observed (see Table 3.3) that the small boiler is too short. At the top a region of high temperatures exists and its 10
  • 11. enthalpy cannot be efficiently used. On the contrary, in the large boiler although the heat fluxes are uniform, they are two times lower than in the medium size boiler. Therefore, the medium size boiler configuration is chosen for further investigations. Small boiler Medium size boiler Large boiler Firing Density 774 238 89 3 kW/m Outlet temperature, 1805 1558 1299 K Table3.3 Results of the boiler size determination 3.2 Working: As already discussed, the working of Supercritical Boilers is similar to the working of sub-critical boilers. It works on the supercritical rankine cycle. Most supercritical boilers are being run at operating pressures above of 235 bars. The working of ultra supercritical boilers has operating pressures above 273 bars. 11
  • 12. MATERIAL SELECTION 4.1 Metallurgical Problems: The available materials today like stainless steel which are usually used for boiler parts are not suitable for SC and USC boilers. They do not have the enough creep strength to resist the high pressure. Also there is high rate of oxidation at such high temperature and pressures which are beyond the capability of these materials to resist. Capable, qualified materials must be available to the industry to enable development of steam generators for SC steam conditions. Major components, such as infurnace tubing for the waterwalls, superheater/ reheater sections, headers, external piping, and other accessories require advancements in materials technology to allow outlet steam temperature increases to reach 760°C (1400F). Experiences with projects such as the pioneering Philo and Eddystone supercritical plants and the problems with the stainless steel steam piping and superheater fireside corrosion provided a valuable precautionary lesson for SC development. Industry organizations thus recognized that a thorough program was required to develop new and improved materials and protection methods necessary for these high temperature steam conditions. 4.2 Materials used: The materials used should be sustainable to the very high pressure being developed and should not get oxidized due to the very high temperature. Different high temperature materials are being used like 9 to 12% ferritic steels T91/P91, T92/P92, T112/P122 steel, Advanced Austenitic alloys TP347, HFG, Super 304, Nickel and chrome-nickel super alloys like Inconel 740. Table 4.2 gives a very brief idea about the boiler materials used for different parts of the boiler. 12
  • 13. Heat surface Tube material Header material Economiser SA-210 C SA-106 C Furnace Walls SA-213 T12 SA-106 C Super SA-213 T12 SA-335 P12 heater/Reheater SA-213 T23 SA-335 P91 SA-213 TP 304H SA-335 P911 SA-213 TP347HFG SUPER 304H Steam Piping SA 335 P91 Table 4.1 Materials for different boiler parts The materials for the other parts of the power plant (like turbine) also must be sustainable for the super critically heated steam. The following table gives a detail idea on the turbine materials of a plant operating on a supercritical cycle. (Table 4.3) 13
  • 14. Component 1,050° F 1,150 °F 1,300° F 1,400 °F Casings CrMoV (cast) 9–10% Cr (W) CF8C-Plus CCA617 (shells, valves, 10CrMoVMb 12CrW (Co) CCA617 Inconel 740 steam chests, nozzles) CrMoWVNbN Inconel 625 CF8C-Plus Nimonic 263 Bolting 422 9–12% CrMoV Nimonic Nimonic 105 105 9–12% CrMoWVNbN CrMoV Nimonic Nimonic 115 115 Nimonic 80A Waspaloy U700 Rotors/Discs 1CrMoV 9–12 % CrWCo CCA617 CCA617 12CrMoVNbN 12CrMoWVNbN Inconel 625 Inconel 740 Nozzles/Blades 422 9–12% CrWCo Wrought Wrought Ni-based Ni-based 10CrMoVNbN 10CrMoVCbN Table 4.2 Materials for other parts The following figures show some of the materials used for SC and USC boilers. Iconel 740 is widely used for steam pipings in almost all of them. Figure 4.1 TP347HFG Figure 4.2 Iconel 740 14
  • 15. SUPERCRITICAL BOILERS 5.1 A typical Supercritical Boilers: Largest CFB and first supercritical CFB sold to date is the Lagisza 460 MWe unit Ordered by Poludniowy Koncern Energetyczny SA (PKE) in Poland. The design is Essentially complete with financial closing expected in the first quarter of 2006 at which time Fabrication and construction will commence. The largest capacity units in operation today are the two (2) 300 MWe JEA repowered units which were designed to fire any Combination of petroleum coke and bituminous coals. The physically largest Foster Wheeler boilers in operation are the 262 MWe Turow Units 4, 5, and 6 which were designed to fire a high moisture brown coal. The design and configuration of these units with Compact solids separators and INTREX™ heat exchangers were used as the basis for the Lagisza design as well as for this study. The Lagisza design was adjusted to accommodate a typical bituminous coal and the steam cycle. Figure 5.1 The Lagisza 300 MWe plant in Poland 15
  • 16. The following table gives a detail report on the performance of the Lagisza 800MWe Power plant. Parameters Values Steam Conditions Main Steam Pressure(barg) 315 Main steam Temperature(°C) 604 Reheat Steam temperature(°C) 615 Feed Water temperature(°C) 289 Emissions SO2 mg/NM3 111 NOx mg/NM3 100 Power generation Gross power MWe 805 Net power MWe 739 Net Plant Efficiency % 40.7 Table 5.1 Performance Parameters 5.2 Super and Sub Critical Boilers (comparative study): There are many advantages of super critical boilers over normal subcritical boilers, the prime advantage being the increased efficiency and reduced emissions. There are many more advantages like no need of steam dryers, higher operating pressures leading to more work output etc. It is thus very important to have a comparative study of both the boilers. 16
  • 17. Technology Efficiency (%) Steam Typical emissions pressure/temperature Ultra Supercritical >242 bar and SO2-0.408 593.33°C kg/MHh 33–35 NOx-0.286 kg/MWh CO2-0.96 T/MWh Supercritical >221.2 bar and SO2-0.431 537°C kg/MHh 36–40 NOx-0.304 kg/MWh CO2-1.02 T/MWh Subritical 165 bar 537°C SO2-0.445 kg/MHh 42–45 NOx-0.31 kg/MWh CO2-1.02 T/MWh Table 5.2 Comparison of sub and supercritical boilers 17
  • 18. ADVANCE IN SC TECHNOLGY AND FUTURE IN INDIA 6.1 Natural Gas Production with a Supercritical Geothermal Power Application By- product: In many cases, the source for Natural Gas production is geothermally heated brine. In these cases, the brine temperatures range from 240 °F (390 K) up to 360 °F (455 K) depending linearly upon well depth. In this temperature range, the brine passes through a heat exchanger to feed a supercritical Rankine cycle for Propane, which has a critical temperature of 206 °F (370 K) and a critical pressure of 616 psia. Theoretically, the brine may be able to run the cycle directly but there are too many contaminants and compositional variations for this to be feasible. If a power cycle like this were employed, the sites producing Natural Gas could potentially generate power for Grid use or, at a minimum, generate the majority of the plant’s electrical Requirements. In the United States, there are several areas along the Texas and the Louisiana Gulf Coast where this type of power cycle is feasible. The benefit to this cycle is that it is extremely simple in terms of system components. The system Requires only a single phase heat exchanger, a turbine, an air cooled condenser, and a pump. The nominal operating pressure of this system is approximately 1000 psia, which suggests that all of the support piping and equipment is commercially available. Given a 15 Million BTU/hr brine source, this system could generate approximately 400 kW net powers with a thermal efficiency of 9%. Additionally, the system can be built to be self regulating by using the power grid as a dynamic brake for the turbine-generator set. In effect, this acts as a speed control for the turbine during slight variations in system demand under normal operating conditions. Additional controls can be implemented to automate the system based on brine temperature and flow rates, all of which minimize the need to have a full-time operator, thus reducing operational costs. 18
  • 19. 6.2 Supercritical Boilers in India: There haven’t been any supercritical boilers in use in India so far. The European countries, USA, Japan have been using supercritical technology since the last two decades. However, there are upcoming projects to build power plants working under the supercritical technology in India. The National Thermal Power Corporation (NTPC) had entrusted a techno economic study to M/s EPDC for super-critical Vs Sub-critical Boilers for their proposed Sipat STPS (4x500 MW) in Madhya Pradesh. M/s EPDC has recommended that a first step to the introduction of super- critical technology, the most proven steam conditions may be chosen and the most applicable steam conditions in India shall be 246 kg/cm2, 538° C/566° C. With these steam parameters, M/s EPDC has estimated that the capital cost for a supercritical power station (4x500 MW) shall be about 2% higher than that of sub-critical power plant but at the same time the plant efficiency shall improve from 38.64% to 39.6%. Being a pit head thermal power project, the saving in fuel charges is not justified by increase in fixed charges. Here are some upcoming projects in India:  North Karanpura, Jharkhand – 3x660 MW  Darlipali, Orissa – 4x800 MW  Lara, Chattisgarh – 5x800 MW  Marakanam, Tamilnadu – 4x800 MW  Tanda-II, Uttar Pradesh - 2x660 MW  Meja, Uttar Pradesh - 2x660 MW  Sholapur – 2x660 MW  New Nabinagar-3x660 MW  Many more projects including 800 MW ultra super critical units under consideration 19
  • 20. CONCLUSION The supercritical Rankine cycle, in general, offers an additional 30% relative improvement in the thermal efficiency as compared to the same system operating in the subcritical region. The cycle has been successfully utilized in fossil fuel plants but the current available materials prohibit reliable application of the supercritical cycle to nuclear applications. There is much work to be done in order to advance materials to the point where they will be able to reliably withstand the stresses of a supercritical environment inside a nuclear reactor for a designed life span of 60 years. Supercritical boiler technology has matured, through advancements in design and materials. Coal-fired supercritical units supplied around the world over the past several years have been operating with high efficiency performance and high availability. 20
  • 21. REFERENCES 1. “Design Aspects of the Ultra-Supercritical CFB Boiler”; Stephen J. Goidich, Song Wu, Zhen Fan; Foster Wheeler North America Corp. 2. “Novel conceptual design of a supercritical pulverized coal boiler utilizing high temperature air combustion (HTAC) technology”; Natalia Schaffel-Mancini, Marco Mancini, Andrzej Szlek, Roman Weber; Institute of Energy Process Engineering and Fuel Technology, Clausthal University of Technology, Agricolastr. 4, 38678 Clausthal- Zellerfeld, Germany; 6 February 2010. 3. “Supercritical (Once Through) Boiler Technology”; J.W. Smith, Babcock & Wilcox, Barberton, Ohio, U.S.A.; May 1998. 4. “Steam Generator for Advanced Ultra-Supercritical Power Plants 700 to 760°C”; P.S. Weitzel; ASME 2011 Power Conference, Denver, Colorado, U.S.A; July 12-14, 2011. 5. “Supercritical boiler technology for future market conditions”; Joachim Franke and Rudolf Kral; Siemens Power Generation; Parsons Conference; 2003. 6. “Steam Turbine Design Considerations for Supercritical Cycles”; Justin Zachary, Paul Kochis, Ram Narula; Coal Gen 2007 Conference;1-3 August 2007. 7. “Technology status of thermal power plants in India and opportunities in renovation and modernization”; TERI, D S Block, India Habitat Centre, Lodi Road, New Delhi – 110003. 8. “Applied Thermodynamics”; Dr. H.N Sawant; January 1992; revised July 2004. 9. “http://en.wikipedia.org/wiki/Boiler#Supercritical_steam_generator” 21