SlideShare a Scribd company logo
1 of 6
Download to read offline
AMERICAN ELECTRIC POWER
Transmission Facts
1
Q1. What are AEP transmission mileage statistics?
AEP owns the nation’s largest electricity transmission system, a thirty-nine-thousand miles network
operating in 11 states that includes more 765 kV extra-high-voltage (EHV) transmission lines than all other
U.S. transmission systems combined. The following statistics summarize AEP’s transmission line circuit
miles as of December 31, 2007:
Extra-High-Voltage Transmission:
765 kV: 2,116 Miles
500 kV: 113 Miles
345 kV: 5,910 Miles
EHV Subtotal: 8,139 Miles
High-Voltage Transmission:
230 kV: 140 Miles
161 kV: 282 Miles
138 kV: 16,202 Miles
115 kV: 66 Miles
HV Subtotal: 16,690 Miles
Below 100 kV: 14,230 Miles
AEP Transmission Total: 39,059 Miles
Source:
“American Electric Power 2008 Fact Book,” 43rd EEI Financial Conference, Phoenix, AZ, November 9-12, 2008.
Q2. Why did AEP develop 765 kV transmission?
The decision to develop and implement a 765 kV transmission overlay in the 1960s (and a 345 kV overlay
in the 1950s) was founded in AEP's philosophy that a strong transmission system is essential to provide
efficient, reliable and flexible infrastructure to meet the ever growing demands of electricity consumers.
Reliable and efficient, integrated operation requires that the resources of all power plants be available,
without transmission constraints, to all parts of the system under a wide range of operating conditions and
possible future scenarios. The AEP 765 kV system provides a robust backbone transmission infrastructure
enabling the most economical and environmentally attractive generating resources to supply the growing
demand for electricity in a broad variety of operating and market conditions.
Source:
“Development of the American Electric Power System Transmission Network: From 345 kV to 765 kV to UHV,” T.J. Nagel and
G.S. Vassell, CIGRE, No. 32-13, September 1974.
Q3. In general, what is the range of cost per mile for each of the following: 765 kV, 500 kV
and 345 kV? (Recognizing that terrain, cost of ROW, etc. factor into it)
Typical installed costs for 765 kV, 500 kV and 345 kV transmission lines are:
Voltage Class Cost Range/Mile*
--------------------- ------------------
765 kV Single Circuit $2.6 – 4.0 Million
500 kV Single Circuit $2.3 - 3.5 Million
345 kV Double Circuit $1.5 - 2.5 Million
345 kV Single Circuit $1.1 – 2.0 Million
*Average construction costs in 2008 dollars; rural terrain with rolling hills;
elevations up to 4000 feet above sea level; includes siting and ROW costs; excludes
station costs.
AMERICAN ELECTRIC POWER
Transmission Facts
2
The above ranges reflect costs utilizing AEP’s current standards and do not include potential design
modifications or technology enhancements. These costs can be affected significantly by the following
factors:
• Siting, permitting and/or environmental mitigation requirements
• Land use, population density and right-of-way land value
• Terrain and geophysical conditions and their effects on line design and construction
Q4. For 765 kV, what is the breakdown of the cost on a percentage basis into labor vs.
materials? For the materials percentage, provide a further breakdown for the major
components (steel, transformers, etc.)
Based on AEP’s latest estimates, the following is an approximate cost breakdown for a typical 765 kV
transmission line built with lattice towers:
Siting: 3%
Right-of-Way (ROW): 10%
Engineering & Management: 5%
Materials: 41% (of which 60% is structures, 30% conductors, 10% other)
Construction: 41%
These percentages can vary for different projects and different project decisions. Most significant
variations exist in the costs of ROW and materials.
For a typical 765 kV transmission station, the cost breakdown is:
Materials: 70% (of which 50% is transformers, 20% circuit breakers, 30% other)
Labor: 30%
Q7. Are we seeing a shortage of skilled labor and if so, how might that impact our plans?
Presently, AEP is not experiencing a shortage of skilled labor. In the future, if a significant number of
projects were scheduled to go into construction simultaneously, a shortage of skilled labor could arise.
Were that to happen, we would work with our contractors to develop and train a larger workforce. Since
there would be some advance visibility to this issue, we would have time to respond to the need.
Q8. How does the size of the ROW compare/differ between 765 kV, 500 kV and 345 kV?
The ROW width commonly used for 765 kV, 500 kV and 345 kV lines is summarized below:
Voltage Class ROW Width - Feet
--------------------- ----------------
765 kV Single Circuit 200
500 kV Single Circuit 175 - 200
345 kV Double Circuit 150
345 kV Single Circuit 150
Q9. What is the average height of 765 kV, 500 kV and 345 kV towers?
Tower heights vary with design and terrain type, and generally increase with voltage class. Note that a
double-circuit 345 kV tower is actually taller than a single-circuit 765 kV design.
AMERICAN ELECTRIC POWER
Transmission Facts
3
Tower Height - Feet
Voltage Class Hilly Terrain Flat Terrain
--------------------- ------------- ------------
765 kV Single Circuit 135 150
500 kV Single Circuit 120 135
345 kV Double Circuit 160 175
345 kV Single Circuit 110 125
Q10. Are there altitude restrictions for transmission? If so, how can they be mitigated?
High elevations above sea level are associated with reduced air density, which affects the performance of
transmission lines. Specifically, as the air density declines so does its dielectric strength, resulting in
greater discharge of energy from energized surfaces. This effect, known as corona, can manifest itself as
audible noise and may have to be controlled to meet local regulations. Effective mitigation methods at
EHV levels are to use multiple conductors in each phase and/or optimized phase bundle geometries.
Reduced air density also can lower the flashover voltage threshold, necessitating more insulation or
effective means for overvoltage control.
Q11. What are the load carrying capabilities of 765 kV, 500 kV and 345 kV in terms of MW
and miles?
To assess the load-carrying ability, or loadability, of a transmission line, engineers commonly use the
concept of Surge Impedance Loading (SIL). SIL, a loading level at which the line attains self-sufficiency
in reactive power (i.e., no net reactive power into or out of the line), is a convenient “yardstick” for
measuring relative loadabilities of long lines operating at different nominal voltages.
Using the SIL concept, three 500 kV or six 345 kV circuits would be required to achieve the loadability of
a single 765 kV line. Specifically, a 765 kV line can reliably transmit 2200-2400 MW (i.e., 1.0 SIL) for
distances up to 300 miles, whereas the similarly situated 500 kV and 345 kV lines with bundled conductors
can deliver only about 900 MW and 400 MW, respectively. For short distances, these relationships can
differ to some extent reflecting thermal capacities established primarily by the number/size of line
conductors and station equipment ratings.
Relative loadabilities of the 765 kV, 500 kV and 345 kV lines also can be viewed in terms of transmission
“reach” over which a certain amount of power, say 1500 MW, can be delivered. For a 765 kV line, this
loading represents approximately 0.62 SIL which, according to the loadability characteristic (see below),
can be transported reliably over a distance of up to 550 miles. By contrast, a 345 kV line carrying the same
amount of power would operate at 3.8 SIL -- transportable only up to about 50 miles (assuming adequate
thermal capacity); this distance would increase to about 110 miles for a double-circuit 345 kV line. The
generalized line loadability characteristic incorporates the assumptions of a well-developed system at each
terminal of the line and operating criteria designed to promote system reliability.
Voltage Class Loadability (@300 Miles) “Reach” (@1500 MW)
--------------------- ------------------------ ------------------
765 kV Single Circuit 2200 – 2400 MW 550 Miles
500 kV Single Circuit 900 MW 140 Miles
345 kV Double Circuit 800 MW 110 Miles
345 kV Single Circuit 400 MW 50 Miles
AMERICAN ELECTRIC POWER
Transmission Facts
4
Source:
“Analytical Development of Loadability Characteristics for EHV and UHV Transmission Lines,” R.D. Dunlop, R. Gutman and P.P.
Marchenko, IEEE Transactions on Power Apparatus and Systems, Vol. PAS-98, No. 2, March/April 1979.
Q12. What are the standard statistics for line losses? How do line losses compare/differ
between 765 kV, 500 kV and 345 kV?
An energized transmission line carrying load incurs power losses due to heating and so-called “corona”
effects. Heating (or resistive) losses increase linearly with line resistance and quadratically with loading.
Corona losses result from undesirable discharge of electric energy, which can be visible and/or audible
especially during rain, caused by air ionization around line conductors and hardware. Corona losses
increase with voltage level and elevation above sea level of the line.
The following statistics characterize EHV transmission lines operating at different voltages, in normal
weather, carrying 1000 MW of power:
LINE LOSSES - MW/100 MILES
Resistive Corona* Total
765 kV LINE @1000 MW LOAD: --------- ------- -----------
Original 4-conductor (“Rail”) bundle 4.4 6.4 10.8 (1.1%)
Newer 4-conductor (“Dipper”) bundle 3.3 3.7 7.0 (0.7%)
Current 6-conductor (“Tern”) bundle 3.4 2.3 5.7 (0.6%)
Planned 6-trapezoidal cond. (“Kettle”) bundle 3.1 2.3 5.4 (0.5%)
500 kV LINE @1000 MW LOAD:
Typical 2-conductor bundle 11.0 1.6 12.6 (1.3%)
345 kV LINE @1000 MW LOAD:
Typical 2-conductor bundle 41.9 0.6 42.5 (4.2%)
*Yearly average corona loss at sea level based on 20%/2%/78% rain/snow/fair weather
conditions, respectively.
The markedly superior transmission efficiency of 765 kV transmission is attributable to its higher operating
voltage and thermal capacity/low resistance compared to 500 kV and 345 kV. Furthermore, by unloading
the underlying, lower-voltage systems with higher resistance, overall system losses are reduced.
AMERICAN ELECTRIC POWER
Transmission Facts
5
Q13. What is the difference between AC and DC transmission? Which do we prefer, why?
AC (or alternating current) transmission refers to the transfer of energy from a source to one or more main
receiving stations by electric current that reverses (alternates) its direction at regular intervals. DC (direct
current) transmission involves the transfer of energy from a source usually to one receiving station by
electric current that flows in one direction.[1]
Key advantages of AC transmission technology are its flexibility and widespread use by electric utilities.
AC facilitates future additions of intermediate stations, acting like exit and entrance ramps on an interstate
highway, to serve local load centers and/or provide transmission access for new generation that may locate
along the way. The ease of AC connections can encourage siting of fuel-diverse, newer technology and
environmentally-friendly generators. Also, the use of AC technology enables expansion into a high-
capacity transmission overlay that can be readily integrated with the existing systems. Integration can be
achieved using commonly available step-down autotransformers or generator step-up transformers, offering
the benefits of enhanced operating flexibility and reduced system losses.
By contrast, traditional DC technology is best suited for specialized applications, such as point-to-point
transmission traversing unpopulated areas or where the systems being connected do not operate in
synchronism. Examples include underground/undersea cables, long-distance overhead transmission
serving as outlets for generating stations, and asynchronous links between two systems that have either no
ties or very weak ties. While DC offers freedom from line charging currents and simpler line design with
only one (monopolar) or two (bipolar) power conductors, it requires DC/AC conversion at each terminal to
integrate with the existing system.[2]
Sources:
[1] “EPRI Transmission Line Reference Book – 200 kV and Above,” Third Edition, Electric Power Research Institute, December 2005.
[2] “AEP Interstate Project: 765 kV or 345 kV Transmission,” R. Gutman and A.D. Pugh,
www.aep.com/about/i765project/technicalpapers.aspx, April 24, 2007.
Q14. What are some of the new technologies we are assessing for inclusion in our existing
and new lines for reliability enhancement or other purposes?
AEP has committed to deploy state-of-the-art transmission technologies as part of its vision for a national
interstate transmission system, announced in January 2006. The system, dubbed I-765TM
, will utilize
individual phase controls and other advanced technologies to maximize power-carrying capacity and
reliability that will establish the standards and benchmarks for 21st century interstate transmission. These
technologies, some of which were pioneered by AEP, include: (1) 765 kV AC transmission with six-bundle
advanced conductors, (2) phase and shield wire transposition, (3) fiber-optic shield wires, (4) wide-area
monitoring and control, (5) remote station equipment diagnostics, (6) single-phase operation, (7) switchable
shunt reactors, and (8) static var compensators with enhanced controls.
In addition, AEP, jointly with ABB, a supplier of power equipment and solutions to the utility industry, is
developing new transmission technologies for deployment at 765 kV. The newest technology concepts that
are: (a) independent phase operation, whereby a conventional three-phase line would remain in service
with two phases only following a sustained single-phase fault to allow for reliable redispatch of the system,
(b) “dead tank” 765 kV circuit breakers with closing resistors and/or synchronized switching to improve
system reliability, and (c) innovative techniques for reducing 765 kV line and equipment losses to achieve
still greater transmission efficiencies and reduce the need for new generating plants.
Source:
“AEP Interstate Project: Technologies for 21st Century Transmission,” R. Gutman,
www.aep.com/about/i765project/technicalpapers.aspx, April 6, 2006.
Q15. What are our views on composite core cables?
Composite core conductors are part of a general class of conductors termed “High Temperature, Low Sag
(HTLS) Conductors” and are utilized on the AEP transmission system. HTLS conductors exhibit less sag
AMERICAN ELECTRIC POWER
Transmission Facts
6
at elevated operating temperatures than traditional conductors. Composite core conductors carry a
significant cost premium and are most cost effective when installed on existing transmission structures as a
quick, effective means to increase the thermal capacity of an established transmission corridor. They are
stronger and, when built with trapezoidal strands, are more compact and have lower resistance than
conventional round-strand conductors with the same diameter. We are working with the industry to
advance this emerging technology expecting to see a robust future for HTLS conductors and, specifically,
for composite core conductors. AEP has approximately 70 circuit miles of composite conductor installed
or planned on five different projects.
* * *

More Related Content

What's hot

Simulation and analysis of HVDC on MATLAB and PSCAD
Simulation and analysis of HVDC on MATLAB and PSCADSimulation and analysis of HVDC on MATLAB and PSCAD
Simulation and analysis of HVDC on MATLAB and PSCADVishal Bhimani
 
Mechanical Design of Transmission Line (In context of Nepal)
Mechanical Design of Transmission Line (In context of Nepal)Mechanical Design of Transmission Line (In context of Nepal)
Mechanical Design of Transmission Line (In context of Nepal)Kathmandu Univesity
 
Power Transmission & Distribution in India
Power Transmission & Distribution in IndiaPower Transmission & Distribution in India
Power Transmission & Distribution in IndiaIndian Energy Sector
 
Power upgrading of Transmission Line by Simultaneous AC DC transmission
Power upgrading of Transmission Line by Simultaneous AC DC transmissionPower upgrading of Transmission Line by Simultaneous AC DC transmission
Power upgrading of Transmission Line by Simultaneous AC DC transmissionVeenaVK
 
THD ANALYSIS OF LFAC TRANSMISSION SYSTEM
THD ANALYSIS OF LFAC TRANSMISSION SYSTEMTHD ANALYSIS OF LFAC TRANSMISSION SYSTEM
THD ANALYSIS OF LFAC TRANSMISSION SYSTEMijiert bestjournal
 
Improvement in Power Transmission Capacity by Simultaneous AC-DC Transmission
Improvement in Power Transmission Capacity by Simultaneous AC-DC TransmissionImprovement in Power Transmission Capacity by Simultaneous AC-DC Transmission
Improvement in Power Transmission Capacity by Simultaneous AC-DC Transmissiontheijes
 
Group 8 hvdc
Group  8 hvdcGroup  8 hvdc
Group 8 hvdcMahesh B
 
Extra high voltage long ac transmission lines
Extra high voltage long ac transmission linesExtra high voltage long ac transmission lines
Extra high voltage long ac transmission linesShivagee Raj
 
Comparative evaluation of hvdc
Comparative evaluation of hvdcComparative evaluation of hvdc
Comparative evaluation of hvdcshivamverma394
 
GENERATING OF HIGH ALTERNATING VOLTAGE
GENERATING OF HIGH ALTERNATING VOLTAGEGENERATING OF HIGH ALTERNATING VOLTAGE
GENERATING OF HIGH ALTERNATING VOLTAGEJamil Abdullah
 
Electrical transmission line
Electrical transmission lineElectrical transmission line
Electrical transmission lineDhananjay Jha
 
315564438 hvdc-transmission-ppt
315564438 hvdc-transmission-ppt315564438 hvdc-transmission-ppt
315564438 hvdc-transmission-pptLaveen Raghunam
 
Improving Fault Ride ThroughCapabilities For Offshore PMSG Wind Farms Connect...
Improving Fault Ride ThroughCapabilities For Offshore PMSG Wind Farms Connect...Improving Fault Ride ThroughCapabilities For Offshore PMSG Wind Farms Connect...
Improving Fault Ride ThroughCapabilities For Offshore PMSG Wind Farms Connect...IJERDJOURNAL
 
Hvdc transmission by pankaj chaudhary
Hvdc transmission by pankaj chaudharyHvdc transmission by pankaj chaudhary
Hvdc transmission by pankaj chaudharyPANKAJRANJANA143
 

What's hot (20)

Simulation and analysis of HVDC on MATLAB and PSCAD
Simulation and analysis of HVDC on MATLAB and PSCADSimulation and analysis of HVDC on MATLAB and PSCAD
Simulation and analysis of HVDC on MATLAB and PSCAD
 
Mechanical Design of Transmission Line (In context of Nepal)
Mechanical Design of Transmission Line (In context of Nepal)Mechanical Design of Transmission Line (In context of Nepal)
Mechanical Design of Transmission Line (In context of Nepal)
 
Power Transmission & Distribution in India
Power Transmission & Distribution in IndiaPower Transmission & Distribution in India
Power Transmission & Distribution in India
 
Power upgrading of Transmission Line by Simultaneous AC DC transmission
Power upgrading of Transmission Line by Simultaneous AC DC transmissionPower upgrading of Transmission Line by Simultaneous AC DC transmission
Power upgrading of Transmission Line by Simultaneous AC DC transmission
 
THD ANALYSIS OF LFAC TRANSMISSION SYSTEM
THD ANALYSIS OF LFAC TRANSMISSION SYSTEMTHD ANALYSIS OF LFAC TRANSMISSION SYSTEM
THD ANALYSIS OF LFAC TRANSMISSION SYSTEM
 
Improvement in Power Transmission Capacity by Simultaneous AC-DC Transmission
Improvement in Power Transmission Capacity by Simultaneous AC-DC TransmissionImprovement in Power Transmission Capacity by Simultaneous AC-DC Transmission
Improvement in Power Transmission Capacity by Simultaneous AC-DC Transmission
 
HVDC & FACTS
HVDC & FACTSHVDC & FACTS
HVDC & FACTS
 
Group 8 hvdc
Group  8 hvdcGroup  8 hvdc
Group 8 hvdc
 
Extra high voltage long ac transmission lines
Extra high voltage long ac transmission linesExtra high voltage long ac transmission lines
Extra high voltage long ac transmission lines
 
Comparative evaluation of hvdc
Comparative evaluation of hvdcComparative evaluation of hvdc
Comparative evaluation of hvdc
 
6 PHASE TRANSMISSION SYSTEM
6 PHASE TRANSMISSION SYSTEM6 PHASE TRANSMISSION SYSTEM
6 PHASE TRANSMISSION SYSTEM
 
Basics of hvdc
Basics of hvdc Basics of hvdc
Basics of hvdc
 
FAULT ANALYSIS IN HVDC & HVAC TRANSMISSION LINE
FAULT ANALYSIS IN HVDC & HVAC TRANSMISSION LINEFAULT ANALYSIS IN HVDC & HVAC TRANSMISSION LINE
FAULT ANALYSIS IN HVDC & HVAC TRANSMISSION LINE
 
GENERATING OF HIGH ALTERNATING VOLTAGE
GENERATING OF HIGH ALTERNATING VOLTAGEGENERATING OF HIGH ALTERNATING VOLTAGE
GENERATING OF HIGH ALTERNATING VOLTAGE
 
Electrical transmission line
Electrical transmission lineElectrical transmission line
Electrical transmission line
 
315564438 hvdc-transmission-ppt
315564438 hvdc-transmission-ppt315564438 hvdc-transmission-ppt
315564438 hvdc-transmission-ppt
 
Hvdc
HvdcHvdc
Hvdc
 
Improving Fault Ride ThroughCapabilities For Offshore PMSG Wind Farms Connect...
Improving Fault Ride ThroughCapabilities For Offshore PMSG Wind Farms Connect...Improving Fault Ride ThroughCapabilities For Offshore PMSG Wind Farms Connect...
Improving Fault Ride ThroughCapabilities For Offshore PMSG Wind Farms Connect...
 
Hvdc transmission
Hvdc transmissionHvdc transmission
Hvdc transmission
 
Hvdc transmission by pankaj chaudhary
Hvdc transmission by pankaj chaudharyHvdc transmission by pankaj chaudhary
Hvdc transmission by pankaj chaudhary
 

Similar to Transmission facts

Ppt of ehv ac transmission
Ppt of ehv ac transmissionPpt of ehv ac transmission
Ppt of ehv ac transmissionSumit Kumar
 
ppt- of- ehv-ac-transmission-pdf (1).pdf
ppt- of- ehv-ac-transmission-pdf (1).pdfppt- of- ehv-ac-transmission-pdf (1).pdf
ppt- of- ehv-ac-transmission-pdf (1).pdfSameer Suraj
 
PERFORMANCE OF LFAC SYSTEM FOR STEADY STATE
PERFORMANCE OF LFAC SYSTEM FOR STEADY STATEPERFORMANCE OF LFAC SYSTEM FOR STEADY STATE
PERFORMANCE OF LFAC SYSTEM FOR STEADY STATEijiert bestjournal
 
Presentation PT.pptx
Presentation PT.pptxPresentation PT.pptx
Presentation PT.pptxKASHIFzaman16
 
Comparison of the performance of hvdc and hvac overhead transmission lines fo...
Comparison of the performance of hvdc and hvac overhead transmission lines fo...Comparison of the performance of hvdc and hvac overhead transmission lines fo...
Comparison of the performance of hvdc and hvac overhead transmission lines fo...Mahdi Bahaghighat
 
ppt-of-ehv-ac-transmission-pdf.pptx
ppt-of-ehv-ac-transmission-pdf.pptxppt-of-ehv-ac-transmission-pdf.pptx
ppt-of-ehv-ac-transmission-pdf.pptxNagen87
 
EPT microproject Part B.pptx
EPT microproject Part B.pptxEPT microproject Part B.pptx
EPT microproject Part B.pptxAnupamTarare1
 
The Operation of the GCCIA HVDC Project and Its Potential Impacts on the Elec...
The Operation of the GCCIA HVDC Project and Its Potential Impacts on the Elec...The Operation of the GCCIA HVDC Project and Its Potential Impacts on the Elec...
The Operation of the GCCIA HVDC Project and Its Potential Impacts on the Elec...Power System Operation
 
when a coil is rotated or turned under a magnetic field, there occurs a force...
when a coil is rotated or turned under a magnetic field, there occurs a force...when a coil is rotated or turned under a magnetic field, there occurs a force...
when a coil is rotated or turned under a magnetic field, there occurs a force...theijes
 
Analysis for underground cable system, lakeside pokhara
Analysis for underground cable system, lakeside pokharaAnalysis for underground cable system, lakeside pokhara
Analysis for underground cable system, lakeside pokharaBishal Rimal
 
EEE Unit , electronic and electrical engineering
EEE Unit , electronic and electrical engineeringEEE Unit , electronic and electrical engineering
EEE Unit , electronic and electrical engineeringprithvijr056
 
Techno economic study of series current limiting reactor and its impact in th...
Techno economic study of series current limiting reactor and its impact in th...Techno economic study of series current limiting reactor and its impact in th...
Techno economic study of series current limiting reactor and its impact in th...Alexander Decker
 
Techno Economic Analysis of HVDC Links for Inter State Interconnection
Techno Economic Analysis of HVDC Links for Inter State InterconnectionTechno Economic Analysis of HVDC Links for Inter State Interconnection
Techno Economic Analysis of HVDC Links for Inter State InterconnectionYogeshIJTSRD
 
Electricpowersystem 111205110736-phpapp01
Electricpowersystem 111205110736-phpapp01Electricpowersystem 111205110736-phpapp01
Electricpowersystem 111205110736-phpapp01devendrakhoiya
 
Electricpowersystem 111205110736-phpapp01
Electricpowersystem 111205110736-phpapp01Electricpowersystem 111205110736-phpapp01
Electricpowersystem 111205110736-phpapp01devendrakhoiya
 

Similar to Transmission facts (20)

Ram
RamRam
Ram
 
Ppt of ehv ac transmission
Ppt of ehv ac transmissionPpt of ehv ac transmission
Ppt of ehv ac transmission
 
ppt- of- ehv-ac-transmission-pdf (1).pdf
ppt- of- ehv-ac-transmission-pdf (1).pdfppt- of- ehv-ac-transmission-pdf (1).pdf
ppt- of- ehv-ac-transmission-pdf (1).pdf
 
PERFORMANCE OF LFAC SYSTEM FOR STEADY STATE
PERFORMANCE OF LFAC SYSTEM FOR STEADY STATEPERFORMANCE OF LFAC SYSTEM FOR STEADY STATE
PERFORMANCE OF LFAC SYSTEM FOR STEADY STATE
 
Presentation PT.pptx
Presentation PT.pptxPresentation PT.pptx
Presentation PT.pptx
 
Comparison of the performance of hvdc and hvac overhead transmission lines fo...
Comparison of the performance of hvdc and hvac overhead transmission lines fo...Comparison of the performance of hvdc and hvac overhead transmission lines fo...
Comparison of the performance of hvdc and hvac overhead transmission lines fo...
 
ppt-of-ehv-ac-transmission-pdf.pptx
ppt-of-ehv-ac-transmission-pdf.pptxppt-of-ehv-ac-transmission-pdf.pptx
ppt-of-ehv-ac-transmission-pdf.pptx
 
transmission&distribution.ppt
transmission&distribution.ppttransmission&distribution.ppt
transmission&distribution.ppt
 
EPT microproject Part B.pptx
EPT microproject Part B.pptxEPT microproject Part B.pptx
EPT microproject Part B.pptx
 
The Operation of the GCCIA HVDC Project and Its Potential Impacts on the Elec...
The Operation of the GCCIA HVDC Project and Its Potential Impacts on the Elec...The Operation of the GCCIA HVDC Project and Its Potential Impacts on the Elec...
The Operation of the GCCIA HVDC Project and Its Potential Impacts on the Elec...
 
when a coil is rotated or turned under a magnetic field, there occurs a force...
when a coil is rotated or turned under a magnetic field, there occurs a force...when a coil is rotated or turned under a magnetic field, there occurs a force...
when a coil is rotated or turned under a magnetic field, there occurs a force...
 
powtech2.pdf
powtech2.pdfpowtech2.pdf
powtech2.pdf
 
Analysis for underground cable system, lakeside pokhara
Analysis for underground cable system, lakeside pokharaAnalysis for underground cable system, lakeside pokhara
Analysis for underground cable system, lakeside pokhara
 
Wbsetcl report
Wbsetcl reportWbsetcl report
Wbsetcl report
 
EEE Unit , electronic and electrical engineering
EEE Unit , electronic and electrical engineeringEEE Unit , electronic and electrical engineering
EEE Unit , electronic and electrical engineering
 
Techno economic study of series current limiting reactor and its impact in th...
Techno economic study of series current limiting reactor and its impact in th...Techno economic study of series current limiting reactor and its impact in th...
Techno economic study of series current limiting reactor and its impact in th...
 
Underground cables vs overhead lines
Underground cables vs overhead linesUnderground cables vs overhead lines
Underground cables vs overhead lines
 
Techno Economic Analysis of HVDC Links for Inter State Interconnection
Techno Economic Analysis of HVDC Links for Inter State InterconnectionTechno Economic Analysis of HVDC Links for Inter State Interconnection
Techno Economic Analysis of HVDC Links for Inter State Interconnection
 
Electricpowersystem 111205110736-phpapp01
Electricpowersystem 111205110736-phpapp01Electricpowersystem 111205110736-phpapp01
Electricpowersystem 111205110736-phpapp01
 
Electricpowersystem 111205110736-phpapp01
Electricpowersystem 111205110736-phpapp01Electricpowersystem 111205110736-phpapp01
Electricpowersystem 111205110736-phpapp01
 

Recently uploaded

Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost Saving
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost SavingRepurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost Saving
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost SavingEdi Saputra
 
TrustArc Webinar - Unlock the Power of AI-Driven Data Discovery
TrustArc Webinar - Unlock the Power of AI-Driven Data DiscoveryTrustArc Webinar - Unlock the Power of AI-Driven Data Discovery
TrustArc Webinar - Unlock the Power of AI-Driven Data DiscoveryTrustArc
 
Vector Search -An Introduction in Oracle Database 23ai.pptx
Vector Search -An Introduction in Oracle Database 23ai.pptxVector Search -An Introduction in Oracle Database 23ai.pptx
Vector Search -An Introduction in Oracle Database 23ai.pptxRemote DBA Services
 
Exploring Multimodal Embeddings with Milvus
Exploring Multimodal Embeddings with MilvusExploring Multimodal Embeddings with Milvus
Exploring Multimodal Embeddings with MilvusZilliz
 
ICT role in 21st century education and its challenges
ICT role in 21st century education and its challengesICT role in 21st century education and its challenges
ICT role in 21st century education and its challengesrafiqahmad00786416
 
Artificial Intelligence Chap.5 : Uncertainty
Artificial Intelligence Chap.5 : UncertaintyArtificial Intelligence Chap.5 : Uncertainty
Artificial Intelligence Chap.5 : UncertaintyKhushali Kathiriya
 
MINDCTI Revenue Release Quarter One 2024
MINDCTI Revenue Release Quarter One 2024MINDCTI Revenue Release Quarter One 2024
MINDCTI Revenue Release Quarter One 2024MIND CTI
 
AI+A11Y 11MAY2024 HYDERBAD GAAD 2024 - HelloA11Y (11 May 2024)
AI+A11Y 11MAY2024 HYDERBAD GAAD 2024 - HelloA11Y (11 May 2024)AI+A11Y 11MAY2024 HYDERBAD GAAD 2024 - HelloA11Y (11 May 2024)
AI+A11Y 11MAY2024 HYDERBAD GAAD 2024 - HelloA11Y (11 May 2024)Samir Dash
 
Rising Above_ Dubai Floods and the Fortitude of Dubai International Airport.pdf
Rising Above_ Dubai Floods and the Fortitude of Dubai International Airport.pdfRising Above_ Dubai Floods and the Fortitude of Dubai International Airport.pdf
Rising Above_ Dubai Floods and the Fortitude of Dubai International Airport.pdfOrbitshub
 
Spring Boot vs Quarkus the ultimate battle - DevoxxUK
Spring Boot vs Quarkus the ultimate battle - DevoxxUKSpring Boot vs Quarkus the ultimate battle - DevoxxUK
Spring Boot vs Quarkus the ultimate battle - DevoxxUKJago de Vreede
 
Modular Monolith - a Practical Alternative to Microservices @ Devoxx UK 2024
Modular Monolith - a Practical Alternative to Microservices @ Devoxx UK 2024Modular Monolith - a Practical Alternative to Microservices @ Devoxx UK 2024
Modular Monolith - a Practical Alternative to Microservices @ Devoxx UK 2024Victor Rentea
 
Apidays New York 2024 - Accelerating FinTech Innovation by Vasa Krishnan, Fin...
Apidays New York 2024 - Accelerating FinTech Innovation by Vasa Krishnan, Fin...Apidays New York 2024 - Accelerating FinTech Innovation by Vasa Krishnan, Fin...
Apidays New York 2024 - Accelerating FinTech Innovation by Vasa Krishnan, Fin...apidays
 
JohnPollard-hybrid-app-RailsConf2024.pptx
JohnPollard-hybrid-app-RailsConf2024.pptxJohnPollard-hybrid-app-RailsConf2024.pptx
JohnPollard-hybrid-app-RailsConf2024.pptxJohnPollard37
 
DBX First Quarter 2024 Investor Presentation
DBX First Quarter 2024 Investor PresentationDBX First Quarter 2024 Investor Presentation
DBX First Quarter 2024 Investor PresentationDropbox
 
Apidays New York 2024 - APIs in 2030: The Risk of Technological Sleepwalk by ...
Apidays New York 2024 - APIs in 2030: The Risk of Technological Sleepwalk by ...Apidays New York 2024 - APIs in 2030: The Risk of Technological Sleepwalk by ...
Apidays New York 2024 - APIs in 2030: The Risk of Technological Sleepwalk by ...apidays
 
DEV meet-up UiPath Document Understanding May 7 2024 Amsterdam
DEV meet-up UiPath Document Understanding May 7 2024 AmsterdamDEV meet-up UiPath Document Understanding May 7 2024 Amsterdam
DEV meet-up UiPath Document Understanding May 7 2024 AmsterdamUiPathCommunity
 
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers:  A Deep Dive into Serverless Spatial Data and FMECloud Frontiers:  A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FMESafe Software
 
AI in Action: Real World Use Cases by Anitaraj
AI in Action: Real World Use Cases by AnitarajAI in Action: Real World Use Cases by Anitaraj
AI in Action: Real World Use Cases by AnitarajAnitaRaj43
 
[BuildWithAI] Introduction to Gemini.pdf
[BuildWithAI] Introduction to Gemini.pdf[BuildWithAI] Introduction to Gemini.pdf
[BuildWithAI] Introduction to Gemini.pdfSandro Moreira
 
Web Form Automation for Bonterra Impact Management (fka Social Solutions Apri...
Web Form Automation for Bonterra Impact Management (fka Social Solutions Apri...Web Form Automation for Bonterra Impact Management (fka Social Solutions Apri...
Web Form Automation for Bonterra Impact Management (fka Social Solutions Apri...Jeffrey Haguewood
 

Recently uploaded (20)

Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost Saving
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost SavingRepurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost Saving
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost Saving
 
TrustArc Webinar - Unlock the Power of AI-Driven Data Discovery
TrustArc Webinar - Unlock the Power of AI-Driven Data DiscoveryTrustArc Webinar - Unlock the Power of AI-Driven Data Discovery
TrustArc Webinar - Unlock the Power of AI-Driven Data Discovery
 
Vector Search -An Introduction in Oracle Database 23ai.pptx
Vector Search -An Introduction in Oracle Database 23ai.pptxVector Search -An Introduction in Oracle Database 23ai.pptx
Vector Search -An Introduction in Oracle Database 23ai.pptx
 
Exploring Multimodal Embeddings with Milvus
Exploring Multimodal Embeddings with MilvusExploring Multimodal Embeddings with Milvus
Exploring Multimodal Embeddings with Milvus
 
ICT role in 21st century education and its challenges
ICT role in 21st century education and its challengesICT role in 21st century education and its challenges
ICT role in 21st century education and its challenges
 
Artificial Intelligence Chap.5 : Uncertainty
Artificial Intelligence Chap.5 : UncertaintyArtificial Intelligence Chap.5 : Uncertainty
Artificial Intelligence Chap.5 : Uncertainty
 
MINDCTI Revenue Release Quarter One 2024
MINDCTI Revenue Release Quarter One 2024MINDCTI Revenue Release Quarter One 2024
MINDCTI Revenue Release Quarter One 2024
 
AI+A11Y 11MAY2024 HYDERBAD GAAD 2024 - HelloA11Y (11 May 2024)
AI+A11Y 11MAY2024 HYDERBAD GAAD 2024 - HelloA11Y (11 May 2024)AI+A11Y 11MAY2024 HYDERBAD GAAD 2024 - HelloA11Y (11 May 2024)
AI+A11Y 11MAY2024 HYDERBAD GAAD 2024 - HelloA11Y (11 May 2024)
 
Rising Above_ Dubai Floods and the Fortitude of Dubai International Airport.pdf
Rising Above_ Dubai Floods and the Fortitude of Dubai International Airport.pdfRising Above_ Dubai Floods and the Fortitude of Dubai International Airport.pdf
Rising Above_ Dubai Floods and the Fortitude of Dubai International Airport.pdf
 
Spring Boot vs Quarkus the ultimate battle - DevoxxUK
Spring Boot vs Quarkus the ultimate battle - DevoxxUKSpring Boot vs Quarkus the ultimate battle - DevoxxUK
Spring Boot vs Quarkus the ultimate battle - DevoxxUK
 
Modular Monolith - a Practical Alternative to Microservices @ Devoxx UK 2024
Modular Monolith - a Practical Alternative to Microservices @ Devoxx UK 2024Modular Monolith - a Practical Alternative to Microservices @ Devoxx UK 2024
Modular Monolith - a Practical Alternative to Microservices @ Devoxx UK 2024
 
Apidays New York 2024 - Accelerating FinTech Innovation by Vasa Krishnan, Fin...
Apidays New York 2024 - Accelerating FinTech Innovation by Vasa Krishnan, Fin...Apidays New York 2024 - Accelerating FinTech Innovation by Vasa Krishnan, Fin...
Apidays New York 2024 - Accelerating FinTech Innovation by Vasa Krishnan, Fin...
 
JohnPollard-hybrid-app-RailsConf2024.pptx
JohnPollard-hybrid-app-RailsConf2024.pptxJohnPollard-hybrid-app-RailsConf2024.pptx
JohnPollard-hybrid-app-RailsConf2024.pptx
 
DBX First Quarter 2024 Investor Presentation
DBX First Quarter 2024 Investor PresentationDBX First Quarter 2024 Investor Presentation
DBX First Quarter 2024 Investor Presentation
 
Apidays New York 2024 - APIs in 2030: The Risk of Technological Sleepwalk by ...
Apidays New York 2024 - APIs in 2030: The Risk of Technological Sleepwalk by ...Apidays New York 2024 - APIs in 2030: The Risk of Technological Sleepwalk by ...
Apidays New York 2024 - APIs in 2030: The Risk of Technological Sleepwalk by ...
 
DEV meet-up UiPath Document Understanding May 7 2024 Amsterdam
DEV meet-up UiPath Document Understanding May 7 2024 AmsterdamDEV meet-up UiPath Document Understanding May 7 2024 Amsterdam
DEV meet-up UiPath Document Understanding May 7 2024 Amsterdam
 
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers:  A Deep Dive into Serverless Spatial Data and FMECloud Frontiers:  A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
 
AI in Action: Real World Use Cases by Anitaraj
AI in Action: Real World Use Cases by AnitarajAI in Action: Real World Use Cases by Anitaraj
AI in Action: Real World Use Cases by Anitaraj
 
[BuildWithAI] Introduction to Gemini.pdf
[BuildWithAI] Introduction to Gemini.pdf[BuildWithAI] Introduction to Gemini.pdf
[BuildWithAI] Introduction to Gemini.pdf
 
Web Form Automation for Bonterra Impact Management (fka Social Solutions Apri...
Web Form Automation for Bonterra Impact Management (fka Social Solutions Apri...Web Form Automation for Bonterra Impact Management (fka Social Solutions Apri...
Web Form Automation for Bonterra Impact Management (fka Social Solutions Apri...
 

Transmission facts

  • 1. AMERICAN ELECTRIC POWER Transmission Facts 1 Q1. What are AEP transmission mileage statistics? AEP owns the nation’s largest electricity transmission system, a thirty-nine-thousand miles network operating in 11 states that includes more 765 kV extra-high-voltage (EHV) transmission lines than all other U.S. transmission systems combined. The following statistics summarize AEP’s transmission line circuit miles as of December 31, 2007: Extra-High-Voltage Transmission: 765 kV: 2,116 Miles 500 kV: 113 Miles 345 kV: 5,910 Miles EHV Subtotal: 8,139 Miles High-Voltage Transmission: 230 kV: 140 Miles 161 kV: 282 Miles 138 kV: 16,202 Miles 115 kV: 66 Miles HV Subtotal: 16,690 Miles Below 100 kV: 14,230 Miles AEP Transmission Total: 39,059 Miles Source: “American Electric Power 2008 Fact Book,” 43rd EEI Financial Conference, Phoenix, AZ, November 9-12, 2008. Q2. Why did AEP develop 765 kV transmission? The decision to develop and implement a 765 kV transmission overlay in the 1960s (and a 345 kV overlay in the 1950s) was founded in AEP's philosophy that a strong transmission system is essential to provide efficient, reliable and flexible infrastructure to meet the ever growing demands of electricity consumers. Reliable and efficient, integrated operation requires that the resources of all power plants be available, without transmission constraints, to all parts of the system under a wide range of operating conditions and possible future scenarios. The AEP 765 kV system provides a robust backbone transmission infrastructure enabling the most economical and environmentally attractive generating resources to supply the growing demand for electricity in a broad variety of operating and market conditions. Source: “Development of the American Electric Power System Transmission Network: From 345 kV to 765 kV to UHV,” T.J. Nagel and G.S. Vassell, CIGRE, No. 32-13, September 1974. Q3. In general, what is the range of cost per mile for each of the following: 765 kV, 500 kV and 345 kV? (Recognizing that terrain, cost of ROW, etc. factor into it) Typical installed costs for 765 kV, 500 kV and 345 kV transmission lines are: Voltage Class Cost Range/Mile* --------------------- ------------------ 765 kV Single Circuit $2.6 – 4.0 Million 500 kV Single Circuit $2.3 - 3.5 Million 345 kV Double Circuit $1.5 - 2.5 Million 345 kV Single Circuit $1.1 – 2.0 Million *Average construction costs in 2008 dollars; rural terrain with rolling hills; elevations up to 4000 feet above sea level; includes siting and ROW costs; excludes station costs.
  • 2. AMERICAN ELECTRIC POWER Transmission Facts 2 The above ranges reflect costs utilizing AEP’s current standards and do not include potential design modifications or technology enhancements. These costs can be affected significantly by the following factors: • Siting, permitting and/or environmental mitigation requirements • Land use, population density and right-of-way land value • Terrain and geophysical conditions and their effects on line design and construction Q4. For 765 kV, what is the breakdown of the cost on a percentage basis into labor vs. materials? For the materials percentage, provide a further breakdown for the major components (steel, transformers, etc.) Based on AEP’s latest estimates, the following is an approximate cost breakdown for a typical 765 kV transmission line built with lattice towers: Siting: 3% Right-of-Way (ROW): 10% Engineering & Management: 5% Materials: 41% (of which 60% is structures, 30% conductors, 10% other) Construction: 41% These percentages can vary for different projects and different project decisions. Most significant variations exist in the costs of ROW and materials. For a typical 765 kV transmission station, the cost breakdown is: Materials: 70% (of which 50% is transformers, 20% circuit breakers, 30% other) Labor: 30% Q7. Are we seeing a shortage of skilled labor and if so, how might that impact our plans? Presently, AEP is not experiencing a shortage of skilled labor. In the future, if a significant number of projects were scheduled to go into construction simultaneously, a shortage of skilled labor could arise. Were that to happen, we would work with our contractors to develop and train a larger workforce. Since there would be some advance visibility to this issue, we would have time to respond to the need. Q8. How does the size of the ROW compare/differ between 765 kV, 500 kV and 345 kV? The ROW width commonly used for 765 kV, 500 kV and 345 kV lines is summarized below: Voltage Class ROW Width - Feet --------------------- ---------------- 765 kV Single Circuit 200 500 kV Single Circuit 175 - 200 345 kV Double Circuit 150 345 kV Single Circuit 150 Q9. What is the average height of 765 kV, 500 kV and 345 kV towers? Tower heights vary with design and terrain type, and generally increase with voltage class. Note that a double-circuit 345 kV tower is actually taller than a single-circuit 765 kV design.
  • 3. AMERICAN ELECTRIC POWER Transmission Facts 3 Tower Height - Feet Voltage Class Hilly Terrain Flat Terrain --------------------- ------------- ------------ 765 kV Single Circuit 135 150 500 kV Single Circuit 120 135 345 kV Double Circuit 160 175 345 kV Single Circuit 110 125 Q10. Are there altitude restrictions for transmission? If so, how can they be mitigated? High elevations above sea level are associated with reduced air density, which affects the performance of transmission lines. Specifically, as the air density declines so does its dielectric strength, resulting in greater discharge of energy from energized surfaces. This effect, known as corona, can manifest itself as audible noise and may have to be controlled to meet local regulations. Effective mitigation methods at EHV levels are to use multiple conductors in each phase and/or optimized phase bundle geometries. Reduced air density also can lower the flashover voltage threshold, necessitating more insulation or effective means for overvoltage control. Q11. What are the load carrying capabilities of 765 kV, 500 kV and 345 kV in terms of MW and miles? To assess the load-carrying ability, or loadability, of a transmission line, engineers commonly use the concept of Surge Impedance Loading (SIL). SIL, a loading level at which the line attains self-sufficiency in reactive power (i.e., no net reactive power into or out of the line), is a convenient “yardstick” for measuring relative loadabilities of long lines operating at different nominal voltages. Using the SIL concept, three 500 kV or six 345 kV circuits would be required to achieve the loadability of a single 765 kV line. Specifically, a 765 kV line can reliably transmit 2200-2400 MW (i.e., 1.0 SIL) for distances up to 300 miles, whereas the similarly situated 500 kV and 345 kV lines with bundled conductors can deliver only about 900 MW and 400 MW, respectively. For short distances, these relationships can differ to some extent reflecting thermal capacities established primarily by the number/size of line conductors and station equipment ratings. Relative loadabilities of the 765 kV, 500 kV and 345 kV lines also can be viewed in terms of transmission “reach” over which a certain amount of power, say 1500 MW, can be delivered. For a 765 kV line, this loading represents approximately 0.62 SIL which, according to the loadability characteristic (see below), can be transported reliably over a distance of up to 550 miles. By contrast, a 345 kV line carrying the same amount of power would operate at 3.8 SIL -- transportable only up to about 50 miles (assuming adequate thermal capacity); this distance would increase to about 110 miles for a double-circuit 345 kV line. The generalized line loadability characteristic incorporates the assumptions of a well-developed system at each terminal of the line and operating criteria designed to promote system reliability. Voltage Class Loadability (@300 Miles) “Reach” (@1500 MW) --------------------- ------------------------ ------------------ 765 kV Single Circuit 2200 – 2400 MW 550 Miles 500 kV Single Circuit 900 MW 140 Miles 345 kV Double Circuit 800 MW 110 Miles 345 kV Single Circuit 400 MW 50 Miles
  • 4. AMERICAN ELECTRIC POWER Transmission Facts 4 Source: “Analytical Development of Loadability Characteristics for EHV and UHV Transmission Lines,” R.D. Dunlop, R. Gutman and P.P. Marchenko, IEEE Transactions on Power Apparatus and Systems, Vol. PAS-98, No. 2, March/April 1979. Q12. What are the standard statistics for line losses? How do line losses compare/differ between 765 kV, 500 kV and 345 kV? An energized transmission line carrying load incurs power losses due to heating and so-called “corona” effects. Heating (or resistive) losses increase linearly with line resistance and quadratically with loading. Corona losses result from undesirable discharge of electric energy, which can be visible and/or audible especially during rain, caused by air ionization around line conductors and hardware. Corona losses increase with voltage level and elevation above sea level of the line. The following statistics characterize EHV transmission lines operating at different voltages, in normal weather, carrying 1000 MW of power: LINE LOSSES - MW/100 MILES Resistive Corona* Total 765 kV LINE @1000 MW LOAD: --------- ------- ----------- Original 4-conductor (“Rail”) bundle 4.4 6.4 10.8 (1.1%) Newer 4-conductor (“Dipper”) bundle 3.3 3.7 7.0 (0.7%) Current 6-conductor (“Tern”) bundle 3.4 2.3 5.7 (0.6%) Planned 6-trapezoidal cond. (“Kettle”) bundle 3.1 2.3 5.4 (0.5%) 500 kV LINE @1000 MW LOAD: Typical 2-conductor bundle 11.0 1.6 12.6 (1.3%) 345 kV LINE @1000 MW LOAD: Typical 2-conductor bundle 41.9 0.6 42.5 (4.2%) *Yearly average corona loss at sea level based on 20%/2%/78% rain/snow/fair weather conditions, respectively. The markedly superior transmission efficiency of 765 kV transmission is attributable to its higher operating voltage and thermal capacity/low resistance compared to 500 kV and 345 kV. Furthermore, by unloading the underlying, lower-voltage systems with higher resistance, overall system losses are reduced.
  • 5. AMERICAN ELECTRIC POWER Transmission Facts 5 Q13. What is the difference between AC and DC transmission? Which do we prefer, why? AC (or alternating current) transmission refers to the transfer of energy from a source to one or more main receiving stations by electric current that reverses (alternates) its direction at regular intervals. DC (direct current) transmission involves the transfer of energy from a source usually to one receiving station by electric current that flows in one direction.[1] Key advantages of AC transmission technology are its flexibility and widespread use by electric utilities. AC facilitates future additions of intermediate stations, acting like exit and entrance ramps on an interstate highway, to serve local load centers and/or provide transmission access for new generation that may locate along the way. The ease of AC connections can encourage siting of fuel-diverse, newer technology and environmentally-friendly generators. Also, the use of AC technology enables expansion into a high- capacity transmission overlay that can be readily integrated with the existing systems. Integration can be achieved using commonly available step-down autotransformers or generator step-up transformers, offering the benefits of enhanced operating flexibility and reduced system losses. By contrast, traditional DC technology is best suited for specialized applications, such as point-to-point transmission traversing unpopulated areas or where the systems being connected do not operate in synchronism. Examples include underground/undersea cables, long-distance overhead transmission serving as outlets for generating stations, and asynchronous links between two systems that have either no ties or very weak ties. While DC offers freedom from line charging currents and simpler line design with only one (monopolar) or two (bipolar) power conductors, it requires DC/AC conversion at each terminal to integrate with the existing system.[2] Sources: [1] “EPRI Transmission Line Reference Book – 200 kV and Above,” Third Edition, Electric Power Research Institute, December 2005. [2] “AEP Interstate Project: 765 kV or 345 kV Transmission,” R. Gutman and A.D. Pugh, www.aep.com/about/i765project/technicalpapers.aspx, April 24, 2007. Q14. What are some of the new technologies we are assessing for inclusion in our existing and new lines for reliability enhancement or other purposes? AEP has committed to deploy state-of-the-art transmission technologies as part of its vision for a national interstate transmission system, announced in January 2006. The system, dubbed I-765TM , will utilize individual phase controls and other advanced technologies to maximize power-carrying capacity and reliability that will establish the standards and benchmarks for 21st century interstate transmission. These technologies, some of which were pioneered by AEP, include: (1) 765 kV AC transmission with six-bundle advanced conductors, (2) phase and shield wire transposition, (3) fiber-optic shield wires, (4) wide-area monitoring and control, (5) remote station equipment diagnostics, (6) single-phase operation, (7) switchable shunt reactors, and (8) static var compensators with enhanced controls. In addition, AEP, jointly with ABB, a supplier of power equipment and solutions to the utility industry, is developing new transmission technologies for deployment at 765 kV. The newest technology concepts that are: (a) independent phase operation, whereby a conventional three-phase line would remain in service with two phases only following a sustained single-phase fault to allow for reliable redispatch of the system, (b) “dead tank” 765 kV circuit breakers with closing resistors and/or synchronized switching to improve system reliability, and (c) innovative techniques for reducing 765 kV line and equipment losses to achieve still greater transmission efficiencies and reduce the need for new generating plants. Source: “AEP Interstate Project: Technologies for 21st Century Transmission,” R. Gutman, www.aep.com/about/i765project/technicalpapers.aspx, April 6, 2006. Q15. What are our views on composite core cables? Composite core conductors are part of a general class of conductors termed “High Temperature, Low Sag (HTLS) Conductors” and are utilized on the AEP transmission system. HTLS conductors exhibit less sag
  • 6. AMERICAN ELECTRIC POWER Transmission Facts 6 at elevated operating temperatures than traditional conductors. Composite core conductors carry a significant cost premium and are most cost effective when installed on existing transmission structures as a quick, effective means to increase the thermal capacity of an established transmission corridor. They are stronger and, when built with trapezoidal strands, are more compact and have lower resistance than conventional round-strand conductors with the same diameter. We are working with the industry to advance this emerging technology expecting to see a robust future for HTLS conductors and, specifically, for composite core conductors. AEP has approximately 70 circuit miles of composite conductor installed or planned on five different projects. * * *