Project Definition
    •   Objective: To strengthen its presence in the hospitality sector (the Parent
        Group already has a strong foothold in the real estate sector and owns some
        Hotels as well) by foraying into the domain of fine dining. The deliverable of
        the project would be a fully operational Fine Dining Restaurant catering to
        the needs of high end customers.
    •   Major Milestones: Location Finalization, POP false ceiling, Order System
        testing, Preparing Housekeeping schedule, Registration of licence for Food
        business & sale of liquor, Menu Preparation and Pricing and Restaurant
        Inauguration.
    •   Specifications: The restaurant is to be set up in 3 months and processes and
        quality standards are to be defined.
    •   Tasks & Responsibilities: The setting up of restaurant involves five tasks:
        Planning, Need Specification and Advertising, Facilities installation and
        setup, Operations Management and Food Quality maintenance. Each task
        comes      under      the    purview     of     four     departments,     viz.
        Marketing, Facilities, Operations and Food. Every department is headed by a
        supervisor who is assisted by an analyst and a trainee. Project Manager takes
        care of planning in coordination with supervisors.
Organization Structure




     •   Dedicated Project Team Structure for setting up restaurant
     •   Resources are borrowed from departments of the
         organization
Time & Cost Estimation
 •   Top down method is being used for time and cost estimation as this is a
     novel project. Much of the information to derive accurate time and cost
     estimates is not available at the initial phase. Hence the top down
     approach. The esti
 •   Consensus Method is being used wherein meetings and discussions are
     conducted between top level and middle level managers to reach a
     consensus on total project duration and cost.
 •   For the estimates, three categories are chosen, viz. Optimistic, Pessimistic
     and Median values and the average is taken.
Work Breakdown Structure
Network Diagram
Thank You!!!

More Related Content

What's hot

Restaurant Design: 18 Considerations to Remember
Restaurant Design: 18 Considerations to RememberRestaurant Design: 18 Considerations to Remember
Restaurant Design: 18 Considerations to Remember
Aaron Allen
 
MGMT404 - FINAL PROJECT
MGMT404 - FINAL PROJECTMGMT404 - FINAL PROJECT
MGMT404 - FINAL PROJECT
gsb100
 
Restaurant business
Restaurant businessRestaurant business
Restaurant business
ideluca10
 
Business plan_Restaurant
Business plan_RestaurantBusiness plan_Restaurant
Business plan_Restaurant
Arnav Soni
 
Pizza Hut value chain analysis
Pizza Hut value chain analysisPizza Hut value chain analysis
Pizza Hut value chain analysis
Shubham Singhal
 
Business Plan Powerpoint 1
Business Plan Powerpoint 1Business Plan Powerpoint 1
Business Plan Powerpoint 1
haleydawn
 
Reekita Quality Management Plan- Final project for OPEN A SALON
Reekita Quality Management Plan- Final project for OPEN A SALONReekita Quality Management Plan- Final project for OPEN A SALON
Reekita Quality Management Plan- Final project for OPEN A SALON
Reekita Shah Alias Gala
 

What's hot (20)

Cafe construction project report
Cafe construction project reportCafe construction project report
Cafe construction project report
 
Business plan or business proposal on restaurant business @soauniversity #ibcs
Business plan or business proposal on restaurant business @soauniversity #ibcsBusiness plan or business proposal on restaurant business @soauniversity #ibcs
Business plan or business proposal on restaurant business @soauniversity #ibcs
 
Restaurant business plan
Restaurant business planRestaurant business plan
Restaurant business plan
 
Restaurant Design: 18 Considerations to Remember
Restaurant Design: 18 Considerations to RememberRestaurant Design: 18 Considerations to Remember
Restaurant Design: 18 Considerations to Remember
 
MGMT404 - FINAL PROJECT
MGMT404 - FINAL PROJECTMGMT404 - FINAL PROJECT
MGMT404 - FINAL PROJECT
 
OnLine Restaurant Business plan for an entrepreneur
OnLine Restaurant Business plan for an entrepreneurOnLine Restaurant Business plan for an entrepreneur
OnLine Restaurant Business plan for an entrepreneur
 
Business plan on restaurant Hungry 24
Business plan on restaurant Hungry 24  Business plan on restaurant Hungry 24
Business plan on restaurant Hungry 24
 
Restaurant business
Restaurant businessRestaurant business
Restaurant business
 
business proposal for sunshine bakery
business proposal for sunshine bakerybusiness proposal for sunshine bakery
business proposal for sunshine bakery
 
Business plan_Restaurant
Business plan_RestaurantBusiness plan_Restaurant
Business plan_Restaurant
 
Pizza Hut value chain analysis
Pizza Hut value chain analysisPizza Hut value chain analysis
Pizza Hut value chain analysis
 
Restaurant business plan
Restaurant business planRestaurant business plan
Restaurant business plan
 
Business plan on restaurant
Business plan on restaurantBusiness plan on restaurant
Business plan on restaurant
 
QSR Columbia 2015
QSR Columbia 2015QSR Columbia 2015
QSR Columbia 2015
 
Business Plan Powerpoint 1
Business Plan Powerpoint 1Business Plan Powerpoint 1
Business Plan Powerpoint 1
 
Business plan for fast food restaurant
Business plan for fast food restaurantBusiness plan for fast food restaurant
Business plan for fast food restaurant
 
business plan
business planbusiness plan
business plan
 
Element Food Columbia 2015
Element Food Columbia 2015Element Food Columbia 2015
Element Food Columbia 2015
 
Business Plan PPT of Restaurant
Business Plan PPT of RestaurantBusiness Plan PPT of Restaurant
Business Plan PPT of Restaurant
 
Reekita Quality Management Plan- Final project for OPEN A SALON
Reekita Quality Management Plan- Final project for OPEN A SALONReekita Quality Management Plan- Final project for OPEN A SALON
Reekita Quality Management Plan- Final project for OPEN A SALON
 

Viewers also liked

Project Work on fast food restaurants
Project Work on fast food restaurantsProject Work on fast food restaurants
Project Work on fast food restaurants
gulab sharma
 
How to write architectural thesis
How to write architectural thesisHow to write architectural thesis
How to write architectural thesis
Pranay Kumar Tode
 
Site selection, site planning, site divelepment
Site selection, site planning, site divelepmentSite selection, site planning, site divelepment
Site selection, site planning, site divelepment
Sidharth Ravva
 

Viewers also liked (11)

Project Work on fast food restaurants
Project Work on fast food restaurantsProject Work on fast food restaurants
Project Work on fast food restaurants
 
Wo-Men-X Cafe
Wo-Men-X Cafe Wo-Men-X Cafe
Wo-Men-X Cafe
 
Interior architectural design-cad outsourcing
Interior architectural design-cad outsourcingInterior architectural design-cad outsourcing
Interior architectural design-cad outsourcing
 
Arnotts Chocolate Bar Concept
Arnotts Chocolate Bar ConceptArnotts Chocolate Bar Concept
Arnotts Chocolate Bar Concept
 
Lantern Hotel Analysis - Part 1B
Lantern Hotel Analysis - Part 1BLantern Hotel Analysis - Part 1B
Lantern Hotel Analysis - Part 1B
 
Bathroom Design Presentation Vartika Khandelwal M.sc.I.D
 Bathroom Design Presentation Vartika Khandelwal M.sc.I.D Bathroom Design Presentation Vartika Khandelwal M.sc.I.D
Bathroom Design Presentation Vartika Khandelwal M.sc.I.D
 
cafe coffee day
cafe coffee daycafe coffee day
cafe coffee day
 
How to write architectural thesis
How to write architectural thesisHow to write architectural thesis
How to write architectural thesis
 
Shyam Thesis Report
Shyam Thesis ReportShyam Thesis Report
Shyam Thesis Report
 
Site selection, site planning, site divelepment
Site selection, site planning, site divelepmentSite selection, site planning, site divelepment
Site selection, site planning, site divelepment
 
2010 Thesis Project
2010 Thesis Project2010 Thesis Project
2010 Thesis Project
 

Similar to Restaurant project

A Restaurant have an interest in creating a new grading.docx
A Restaurant have an interest in creating a new grading.docxA Restaurant have an interest in creating a new grading.docx
A Restaurant have an interest in creating a new grading.docx
write4
 
[Design and Layout] Week 2 - Preliminary Planning.pptx
[Design and Layout] Week 2 - Preliminary Planning.pptx[Design and Layout] Week 2 - Preliminary Planning.pptx
[Design and Layout] Week 2 - Preliminary Planning.pptx
JoebertArcueno
 
C. Mark Frost Resume
C. Mark Frost ResumeC. Mark Frost Resume
C. Mark Frost Resume
Mark Frost
 
Total Quality Process (TQP)
Total Quality Process (TQP)Total Quality Process (TQP)
Total Quality Process (TQP)
Flevy.com Best Practices
 
ResumeFinal-RebeccaTurcotteKish2-11-14
ResumeFinal-RebeccaTurcotteKish2-11-14ResumeFinal-RebeccaTurcotteKish2-11-14
ResumeFinal-RebeccaTurcotteKish2-11-14
Rebecca Turcotte
 

Similar to Restaurant project (20)

A Restaurant have an interest in creating a new grading.docx
A Restaurant have an interest in creating a new grading.docxA Restaurant have an interest in creating a new grading.docx
A Restaurant have an interest in creating a new grading.docx
 
[Design and Layout] Week 2 - Preliminary Planning.pptx
[Design and Layout] Week 2 - Preliminary Planning.pptx[Design and Layout] Week 2 - Preliminary Planning.pptx
[Design and Layout] Week 2 - Preliminary Planning.pptx
 
C. Mark Frost Resume
C. Mark Frost ResumeC. Mark Frost Resume
C. Mark Frost Resume
 
Foster elease resume.1
Foster elease resume.1Foster elease resume.1
Foster elease resume.1
 
ravi new
ravi newravi new
ravi new
 
Pinaki Mondal-2016
Pinaki Mondal-2016Pinaki Mondal-2016
Pinaki Mondal-2016
 
Final Presentation.pptx
Final Presentation.pptxFinal Presentation.pptx
Final Presentation.pptx
 
Total Quality Process (TQP)
Total Quality Process (TQP)Total Quality Process (TQP)
Total Quality Process (TQP)
 
Resume(Nethaji) (1)
Resume(Nethaji) (1)Resume(Nethaji) (1)
Resume(Nethaji) (1)
 
CV_final
CV_finalCV_final
CV_final
 
ResumeHoJY 290316
ResumeHoJY 290316ResumeHoJY 290316
ResumeHoJY 290316
 
Amit_Resume
Amit_ResumeAmit_Resume
Amit_Resume
 
Pmss Service Deliverymaster
Pmss Service DeliverymasterPmss Service Deliverymaster
Pmss Service Deliverymaster
 
T359
T359T359
T359
 
Ananth_Resume
Ananth_ResumeAnanth_Resume
Ananth_Resume
 
Total quality management
Total quality managementTotal quality management
Total quality management
 
Concepts of tqm
Concepts of tqmConcepts of tqm
Concepts of tqm
 
ResumeFinal-RebeccaTurcotteKish2-11-14
ResumeFinal-RebeccaTurcotteKish2-11-14ResumeFinal-RebeccaTurcotteKish2-11-14
ResumeFinal-RebeccaTurcotteKish2-11-14
 
Baldev Raj
Baldev RajBaldev Raj
Baldev Raj
 
7 Themes of Prince2
7 Themes of Prince27 Themes of Prince2
7 Themes of Prince2
 

More from Arun Kabra (7)

Leadership & emotional intelligence
Leadership & emotional  intelligenceLeadership & emotional  intelligence
Leadership & emotional intelligence
 
Leadership and firms performance negetive context
Leadership and firms performance   negetive contextLeadership and firms performance   negetive context
Leadership and firms performance negetive context
 
Ethical issues after walmarts entry in Indai
Ethical issues after walmarts entry in IndaiEthical issues after walmarts entry in Indai
Ethical issues after walmarts entry in Indai
 
Siemens daimler case
Siemens daimler caseSiemens daimler case
Siemens daimler case
 
Shraddha
ShraddhaShraddha
Shraddha
 
West marine case
West marine caseWest marine case
West marine case
 
POM - ACC case
POM - ACC casePOM - ACC case
POM - ACC case
 

Recently uploaded

The basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptxThe basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptx
heathfieldcps1
 

Recently uploaded (20)

COMMUNICATING NEGATIVE NEWS - APPROACHES .pptx
COMMUNICATING NEGATIVE NEWS - APPROACHES .pptxCOMMUNICATING NEGATIVE NEWS - APPROACHES .pptx
COMMUNICATING NEGATIVE NEWS - APPROACHES .pptx
 
Jamworks pilot and AI at Jisc (20/03/2024)
Jamworks pilot and AI at Jisc (20/03/2024)Jamworks pilot and AI at Jisc (20/03/2024)
Jamworks pilot and AI at Jisc (20/03/2024)
 
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptx
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptxHMCS Max Bernays Pre-Deployment Brief (May 2024).pptx
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptx
 
Sensory_Experience_and_Emotional_Resonance_in_Gabriel_Okaras_The_Piano_and_Th...
Sensory_Experience_and_Emotional_Resonance_in_Gabriel_Okaras_The_Piano_and_Th...Sensory_Experience_and_Emotional_Resonance_in_Gabriel_Okaras_The_Piano_and_Th...
Sensory_Experience_and_Emotional_Resonance_in_Gabriel_Okaras_The_Piano_and_Th...
 
How to Manage Global Discount in Odoo 17 POS
How to Manage Global Discount in Odoo 17 POSHow to Manage Global Discount in Odoo 17 POS
How to Manage Global Discount in Odoo 17 POS
 
SOC 101 Demonstration of Learning Presentation
SOC 101 Demonstration of Learning PresentationSOC 101 Demonstration of Learning Presentation
SOC 101 Demonstration of Learning Presentation
 
Kodo Millet PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...
Kodo Millet  PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...Kodo Millet  PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...
Kodo Millet PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...
 
Accessible Digital Futures project (20/03/2024)
Accessible Digital Futures project (20/03/2024)Accessible Digital Futures project (20/03/2024)
Accessible Digital Futures project (20/03/2024)
 
Philosophy of china and it's charactistics
Philosophy of china and it's charactisticsPhilosophy of china and it's charactistics
Philosophy of china and it's charactistics
 
Sociology 101 Demonstration of Learning Exhibit
Sociology 101 Demonstration of Learning ExhibitSociology 101 Demonstration of Learning Exhibit
Sociology 101 Demonstration of Learning Exhibit
 
Basic Intentional Injuries Health Education
Basic Intentional Injuries Health EducationBasic Intentional Injuries Health Education
Basic Intentional Injuries Health Education
 
Food safety_Challenges food safety laboratories_.pdf
Food safety_Challenges food safety laboratories_.pdfFood safety_Challenges food safety laboratories_.pdf
Food safety_Challenges food safety laboratories_.pdf
 
latest AZ-104 Exam Questions and Answers
latest AZ-104 Exam Questions and Answerslatest AZ-104 Exam Questions and Answers
latest AZ-104 Exam Questions and Answers
 
Plant propagation: Sexual and Asexual propapagation.pptx
Plant propagation: Sexual and Asexual propapagation.pptxPlant propagation: Sexual and Asexual propapagation.pptx
Plant propagation: Sexual and Asexual propapagation.pptx
 
The basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptxThe basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptx
 
Single or Multiple melodic lines structure
Single or Multiple melodic lines structureSingle or Multiple melodic lines structure
Single or Multiple melodic lines structure
 
Understanding Accommodations and Modifications
Understanding  Accommodations and ModificationsUnderstanding  Accommodations and Modifications
Understanding Accommodations and Modifications
 
Tatlong Kwento ni Lola basyang-1.pdf arts
Tatlong Kwento ni Lola basyang-1.pdf artsTatlong Kwento ni Lola basyang-1.pdf arts
Tatlong Kwento ni Lola basyang-1.pdf arts
 
Mehran University Newsletter Vol-X, Issue-I, 2024
Mehran University Newsletter Vol-X, Issue-I, 2024Mehran University Newsletter Vol-X, Issue-I, 2024
Mehran University Newsletter Vol-X, Issue-I, 2024
 
This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.
 

Restaurant project

  • 1. Restaurant Project Arun Kabra Leelaram T Mouli Ghatak Raman Murty Rucha Pundle
  • 2. Project Definition • Objective: To strengthen its presence in the hospitality sector (the Parent Group already has a strong foothold in the real estate sector and owns some Hotels as well) by foraying into the domain of fine dining. The deliverable of the project would be a fully operational Fine Dining Restaurant catering to the needs of high end customers. • Major Milestones: Location Finalization, POP false ceiling, Order System testing, Preparing Housekeeping schedule, Registration of licence for Food business & sale of liquor, Menu Preparation and Pricing and Restaurant Inauguration. • Specifications: The restaurant is to be set up in 3 months and processes and quality standards are to be defined. • Tasks & Responsibilities: The setting up of restaurant involves five tasks: Planning, Need Specification and Advertising, Facilities installation and setup, Operations Management and Food Quality maintenance. Each task comes under the purview of four departments, viz. Marketing, Facilities, Operations and Food. Every department is headed by a supervisor who is assisted by an analyst and a trainee. Project Manager takes care of planning in coordination with supervisors.
  • 3. Organization Structure • Dedicated Project Team Structure for setting up restaurant • Resources are borrowed from departments of the organization
  • 4. Time & Cost Estimation • Top down method is being used for time and cost estimation as this is a novel project. Much of the information to derive accurate time and cost estimates is not available at the initial phase. Hence the top down approach. The esti • Consensus Method is being used wherein meetings and discussions are conducted between top level and middle level managers to reach a consensus on total project duration and cost. • For the estimates, three categories are chosen, viz. Optimistic, Pessimistic and Median values and the average is taken.