Lecture by: Andualem Endris (M.Sc)
andu0117@yahoo.com
Chapter Two
Madawalabu
University
College of Engineering
Construction Technology and Management Department
Procurement Management and Contract Administration
CoTM 4242
1
COTM 4242 2
• Procurement is the acquisition of goods,
works, consultancy or other services through
purchasing, hiring or obtaining by any other
contractual means.
• Tendering is a stage in the procurement
process extending from advertisement
(invitation to bid) up to signing of contract.
• Tender is an offer which incorporates the sum
of money, time and other conditions required to
carry out the contract obligations in order to
complete a project or a part of it consisting of
specified works.
COTM 4242 3
 Stage 1: Inception & Feasibility study –
identifying project objectives / set up project brief
 Stage 2: Design – develop further project brief /
develop concept & schematic design / Undertake
detailed design & detailing / prepare cost plan & budget
 Stage 3: Tendering – issue tender documents /
prepare & submit tender / evaluation of tender / award
tenders / prepare contract documents
COTM 4242 4
 Stage 4: Construction – site possession &
mobilization / undertake procurement fabrication,
installation, construction / carry out contract
administration
 Stage 5: Handover & Maintenance –
undertake all testing, commissioning & training /
handover project to owner /carry out necessary
maintenance / Defect rectification / etc
COTM 4242 5
Tendering will be started after the design completed
and project budget is approved
The process that is used to obtain offers leading to a
contract between:
client contractor
client consultant
main contractor sub-contractor
COTM 4242 6
 A tender formally means an invitation
to trade under the terms of offer.
 A contract is the term used for when
the parties have reached agreement.
COTM 4242 7
COTM 4242 8
SELECTION
CRITERIA
In this process we look at the ways to
choose between different tenderers,
reviewing the specific Criteria for
tender evaluation:
•Pre-qualification
•Technical evaluation
•Financial Evaluation
•Relationship between Technical and
Financial
COTM 4242 9
Pre-
Qualification
Technical
Evaluation
Financial
Evaluation
Interested firms or consortia,
submit experience and financial
capacity details
Contracting Authority assesses
these details
Short list the firms
Only short-listed firms can
submit a proposal
Bidders submit proposals
COTM 4242 10
Pre-
Qualification
Bidders submit Technical Proposals,
showing how they would run the contract
Bidders provide information on Financial
and technical ability
Proposals assessed using ‘technical
evaluation criteria
Bidders have to pass a ‘technical
threshold’ to be eligible for selection (e.g.
scoring at least 70 percent on technical
evaluation criteria in our country)
Technical
Qualification
Financial
Evaluation
COTM 4242 11
Pre-
Qualification
Financial proposals of only technically
acceptable bids should be opened and
evaluated.
Financial Criteria can be very simple, as
following examples:
Bidder asking for lowest tariff
Bidder asking for Lowest Fee (Least Bidder)
Bidder with best financial proposal awarded
the contract
Financial
Qualification
Technical
Evaluation
COTM 4242 12
 To select a suitable contractor at a time
appropriate to the situation of the project.
 To obtain from the contractor selected at the
proper time, an acceptable tender or offer
upon which a contract can be let.
COTM 4242 13
COTM 4242 14
Stage 2:
APPROVAL TO
TENDER
Stage 1:
PREPARATION
Stage 3:
DOCUMENTATION
Stage 4:
INVITATION
Stage 5:
PROCESSING
Stage 6:
AWARD
CONTRACT
 Final completion of drawings, specification,
measurement / take-off process.
 Choose conditions of contract.
 Parties involved: architects, engineers, QS,
client
COTM 4242 15
 Discussion and decision on type of
tender to be used.
 Selection of tender:
 Open
 Selective
 Negotiate
 Parties involved: CLIENT, CONSULTANT,
and CONTRACTOR
COTM 4242 16
Short-listed
tenderers
Contract Document
 Letter of invitation
 Checklist for submission of tender
 Articles of agreement
 Form of tender
 Specifications
 Bills of quantities
 Drawings
 Letter of acceptance form
 Schedule of day work rates
COTM 4242 17
 Based on selection of tendering methods
 Open / competitive / bid tender – produce tender
notice
 Selective – short listed contractors will be invited to
tender if they wish
 Negotiated – only one contractor is approached-
direct entry to project
COTM 4242 18
 The Tender Notice is a brief
description of the job being tendered
which is to be published in
Newspapers and on the Internet.
 The Internet is a very cost effective
way of publishing the tenders.
COTM 4242 19
a. Name of the Project.
b. Name & Address of the
Company floating the tender.
c. Name of work, materials or
services.
d. Place of work location.
e. Approximate estimated cost
of work.
f. Earnest Money.
g. Period of completion.
h. Date on which the Tender
Document sale commences.
i. Date and time up to which
tender documents can be
obtained.
j. The cost of tender
documents.
k. The date and time up to
which the tenders to be
submitted and are to be
opened.
l. Specification.
m. Eligibility Criterion.
COTM 4242 20
 Receive tender submitted by contractor
 Tender assessment / evaluation
 Completed tenders are received
 Arithmetical check
 Reasonable tender sum
 Reasonable completion time
 Capabilities of renderers' under considerations
 Tender recommendation / report – tender board
COTM 4242 21
 Pre-award meeting with contractors – validation of
lowest complying bid
 Validate lowest bid - Pre-contract meeting with
contractor for contract signing
 Approval by tender board / treasury
COTM 4242 22
COTM 4242 23
COTM 4242 24
Stage 2:
Determine
basis of
tender
Stage 1:
Decision to
tender
Stage 3:
Preparation of
cost estimates
Stage 4:
Commercial
appreciation
Stage 5:
Conversion of
estimate to
tender
Stage 6:
Submission
of tender
 Receipt of tender documents
 Pre-tender data sheet
 Decision to tender
 Consider implications of:
 Bonds
 Warranties
 Parent company
 Guarantees
 Funding
COTM 4242 25
 Abstract materials and subcontractors
 Sent out enquiries
 Consider construction methods / prepare method
statement
 Design temporary works / consider alternatives
 Prepare outline program
 Check major quantities
 Identify restrictions
 Visit site and compile site report
 Campaigning meeting (designating areas
responsibilities)
COTM 4242 26
 Calculate current rates using:
 Materials
 Equipments and
 Labour costs
 Analyze and check subcontractors’ quotations
 Price prelims / general items (in association with
members of the team
 Prepare summary sheets
COTM 4242 27
 Tender committee meeting part 1:
 Review:
 Method
 Program
 Technical and commercial risks
 Cash flow and finance
 Use of own plant
 Competition
 Commercial opportunities
 Economic climate
 Check prelims against historical cost data
COTM 4242 28
 Tender committee meeting – part 2:
 Calculate ‘spread’ and add to estimate
COTM 4242 29
 Submit in format required (Bid
submission format)
 Organize delivery.
COTM 4242 30
31
COTM 4242

More Related Content

What's hot

Fidic flow charts final
Fidic flow charts finalFidic flow charts final
Fidic flow charts final
FitBlar Mit
 
Tendering Bidding & Award of Contract Final Draft
Tendering Bidding & Award of Contract Final DraftTendering Bidding & Award of Contract Final Draft
Tendering Bidding & Award of Contract Final Draft
Muneesh Methwani
 
Tenders contract -arti
Tenders contract -artiTenders contract -arti
Tenders contract -arti
jagadish108
 

What's hot (20)

Fidic flow charts final
Fidic flow charts finalFidic flow charts final
Fidic flow charts final
 
Tender & bidding in construction projects
Tender  & bidding in construction projectsTender  & bidding in construction projects
Tender & bidding in construction projects
 
Construction tender process
Construction tender processConstruction tender process
Construction tender process
 
Tendering process cvc_guidelines
Tendering process cvc_guidelinesTendering process cvc_guidelines
Tendering process cvc_guidelines
 
Tendering Bidding & Award of Contract Final Draft
Tendering Bidding & Award of Contract Final DraftTendering Bidding & Award of Contract Final Draft
Tendering Bidding & Award of Contract Final Draft
 
Types of tender and their processing.
Types of tender and their processing.Types of tender and their processing.
Types of tender and their processing.
 
Chapter 3- Contract Management
Chapter 3- Contract ManagementChapter 3- Contract Management
Chapter 3- Contract Management
 
ACH 216 Lecture 04b (Bidding) Part 2
ACH 216 Lecture 04b (Bidding) Part 2ACH 216 Lecture 04b (Bidding) Part 2
ACH 216 Lecture 04b (Bidding) Part 2
 
Tender & Tender Notice
Tender & Tender NoticeTender & Tender Notice
Tender & Tender Notice
 
Types of tenders & stages for successful tendering
Types of tenders & stages for successful tenderingTypes of tenders & stages for successful tendering
Types of tenders & stages for successful tendering
 
report A
report Areport A
report A
 
Tendering presenation
Tendering presenationTendering presenation
Tendering presenation
 
Tender Management
Tender ManagementTender Management
Tender Management
 
PP Seminar Tutorial 7
PP Seminar Tutorial 7PP Seminar Tutorial 7
PP Seminar Tutorial 7
 
Tenders contract -arti
Tenders contract -artiTenders contract -arti
Tenders contract -arti
 
Tendering documentation
Tendering documentationTendering documentation
Tendering documentation
 
Tendering Document for the Procurement of Works
Tendering Document for the Procurement of WorksTendering Document for the Procurement of Works
Tendering Document for the Procurement of Works
 
Types of Tender and their Process
Types of Tender and their ProcessTypes of Tender and their Process
Types of Tender and their Process
 
Pp1 presentation 2
Pp1 presentation 2Pp1 presentation 2
Pp1 presentation 2
 
Tenders in professional practice
Tenders in professional practiceTenders in professional practice
Tenders in professional practice
 

Similar to Chapter 2 [compatibility mode]

Similar to Chapter 2 [compatibility mode] (20)

Lecture 2 tender process n documentation
Lecture 2 tender process n documentationLecture 2 tender process n documentation
Lecture 2 tender process n documentation
 
Tenders.ppt
 Tenders.ppt Tenders.ppt
Tenders.ppt
 
Contract monitoring & evaluation
Contract monitoring & evaluationContract monitoring & evaluation
Contract monitoring & evaluation
 
Chapter -Two (3).pdf
Chapter -Two (3).pdfChapter -Two (3).pdf
Chapter -Two (3).pdf
 
2. Project Procurement Process.pptx
2. Project Procurement Process.pptx2. Project Procurement Process.pptx
2. Project Procurement Process.pptx
 
Chapter -Two (2).pdf
Chapter -Two (2).pdfChapter -Two (2).pdf
Chapter -Two (2).pdf
 
Tendering process for traditional contracts by eng. mohammed fadlalla
Tendering process for traditional contracts  by eng. mohammed fadlallaTendering process for traditional contracts  by eng. mohammed fadlalla
Tendering process for traditional contracts by eng. mohammed fadlalla
 
contract_management.ppt
contract_management.pptcontract_management.ppt
contract_management.ppt
 
Fundamentals of Construction Contracts - English, ver. 2021
Fundamentals of Construction Contracts - English, ver. 2021Fundamentals of Construction Contracts - English, ver. 2021
Fundamentals of Construction Contracts - English, ver. 2021
 
Chapter 3 [compatibility mode]
Chapter 3 [compatibility mode]Chapter 3 [compatibility mode]
Chapter 3 [compatibility mode]
 
Chapter 3 [compatibility mode]
Chapter 3 [compatibility mode]Chapter 3 [compatibility mode]
Chapter 3 [compatibility mode]
 
CH-3-Introduction.pptx
CH-3-Introduction.pptxCH-3-Introduction.pptx
CH-3-Introduction.pptx
 
procurement overview
procurement overviewprocurement overview
procurement overview
 
Arunkumar_Proc & Contr_25.12.2014
Arunkumar_Proc & Contr_25.12.2014Arunkumar_Proc & Contr_25.12.2014
Arunkumar_Proc & Contr_25.12.2014
 
Tendering
TenderingTendering
Tendering
 
Tender
TenderTender
Tender
 
Measuring tendering and estimating for CBE
Measuring tendering and estimating for CBEMeasuring tendering and estimating for CBE
Measuring tendering and estimating for CBE
 
Public Sector Procurement
Public Sector ProcurementPublic Sector Procurement
Public Sector Procurement
 
PP Seminar
PP SeminarPP Seminar
PP Seminar
 
Ak contract management
Ak contract managementAk contract management
Ak contract management
 

More from Delhi Technological University

More from Delhi Technological University (20)

Chapter 6- Contract Management
Chapter 6- Contract ManagementChapter 6- Contract Management
Chapter 6- Contract Management
 
Chapter 5- Contract Management
Chapter 5- Contract ManagementChapter 5- Contract Management
Chapter 5- Contract Management
 
Chapter 4- Contract Management
Chapter 4- Contract ManagementChapter 4- Contract Management
Chapter 4- Contract Management
 
Chapter 1- Procurement management
Chapter 1- Procurement managementChapter 1- Procurement management
Chapter 1- Procurement management
 
Chapter 4
Chapter 4Chapter 4
Chapter 4
 
Chapter 3- Construction Law
Chapter 3- Construction Law Chapter 3- Construction Law
Chapter 3- Construction Law
 
Chapter 2- Construction Law
Chapter 2- Construction Law Chapter 2- Construction Law
Chapter 2- Construction Law
 
Chapter 1-Construction Law
Chapter 1-Construction Law Chapter 1-Construction Law
Chapter 1-Construction Law
 
Chapter 5- Lecture
Chapter 5- LectureChapter 5- Lecture
Chapter 5- Lecture
 
Chapter 4- Lecture
Chapter 4- LectureChapter 4- Lecture
Chapter 4- Lecture
 
Chapter 3- Lecture
Chapter 3- LectureChapter 3- Lecture
Chapter 3- Lecture
 
Chapter 2- Lecture
Chapter 2- LectureChapter 2- Lecture
Chapter 2- Lecture
 
Chapter 1- Lecture
Chapter 1- LectureChapter 1- Lecture
Chapter 1- Lecture
 
Construction equipment management chapter 5
Construction equipment management chapter 5Construction equipment management chapter 5
Construction equipment management chapter 5
 
Construction equipment management chapter 4
Construction equipment management chapter 4Construction equipment management chapter 4
Construction equipment management chapter 4
 
Construction equipment management chapter 3
Construction equipment management chapter 3Construction equipment management chapter 3
Construction equipment management chapter 3
 
Construction equipment management chapter 2
Construction equipment management chapter 2Construction equipment management chapter 2
Construction equipment management chapter 2
 
Construction equipment management chapter 1pdf
Construction equipment management chapter 1pdfConstruction equipment management chapter 1pdf
Construction equipment management chapter 1pdf
 
Chapter 5 [compatibility mode]
Chapter 5 [compatibility mode]Chapter 5 [compatibility mode]
Chapter 5 [compatibility mode]
 
Chapter 4 [compatibility mode]
Chapter 4 [compatibility mode]Chapter 4 [compatibility mode]
Chapter 4 [compatibility mode]
 

Recently uploaded

DeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakesDeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakes
MayuraD1
 
Integrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - NeometrixIntegrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - Neometrix
Neometrix_Engineering_Pvt_Ltd
 
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
HenryBriggs2
 
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills KuwaitKuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
jaanualu31
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power Play
Epec Engineered Technologies
 

Recently uploaded (20)

Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPT
 
Work-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxWork-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptx
 
DC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationDC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equation
 
Hostel management system project report..pdf
Hostel management system project report..pdfHostel management system project report..pdf
Hostel management system project report..pdf
 
Learn the concepts of Thermodynamics on Magic Marks
Learn the concepts of Thermodynamics on Magic MarksLearn the concepts of Thermodynamics on Magic Marks
Learn the concepts of Thermodynamics on Magic Marks
 
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced LoadsFEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
 
kiln thermal load.pptx kiln tgermal load
kiln thermal load.pptx kiln tgermal loadkiln thermal load.pptx kiln tgermal load
kiln thermal load.pptx kiln tgermal load
 
DeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakesDeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakes
 
Integrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - NeometrixIntegrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - Neometrix
 
A Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna MunicipalityA Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna Municipality
 
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
COST-EFFETIVE  and Energy Efficient BUILDINGS ptxCOST-EFFETIVE  and Energy Efficient BUILDINGS ptx
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
 
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
 
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptxA CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
 
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills KuwaitKuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . ppt
 
Computer Networks Basics of Network Devices
Computer Networks  Basics of Network DevicesComputer Networks  Basics of Network Devices
Computer Networks Basics of Network Devices
 
Engineering Drawing focus on projection of planes
Engineering Drawing focus on projection of planesEngineering Drawing focus on projection of planes
Engineering Drawing focus on projection of planes
 
School management system project Report.pdf
School management system project Report.pdfSchool management system project Report.pdf
School management system project Report.pdf
 
Computer Lecture 01.pptxIntroduction to Computers
Computer Lecture 01.pptxIntroduction to ComputersComputer Lecture 01.pptxIntroduction to Computers
Computer Lecture 01.pptxIntroduction to Computers
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power Play
 

Chapter 2 [compatibility mode]

  • 1. Lecture by: Andualem Endris (M.Sc) andu0117@yahoo.com Chapter Two Madawalabu University College of Engineering Construction Technology and Management Department Procurement Management and Contract Administration CoTM 4242 1
  • 3. • Procurement is the acquisition of goods, works, consultancy or other services through purchasing, hiring or obtaining by any other contractual means. • Tendering is a stage in the procurement process extending from advertisement (invitation to bid) up to signing of contract. • Tender is an offer which incorporates the sum of money, time and other conditions required to carry out the contract obligations in order to complete a project or a part of it consisting of specified works. COTM 4242 3
  • 4.  Stage 1: Inception & Feasibility study – identifying project objectives / set up project brief  Stage 2: Design – develop further project brief / develop concept & schematic design / Undertake detailed design & detailing / prepare cost plan & budget  Stage 3: Tendering – issue tender documents / prepare & submit tender / evaluation of tender / award tenders / prepare contract documents COTM 4242 4
  • 5.  Stage 4: Construction – site possession & mobilization / undertake procurement fabrication, installation, construction / carry out contract administration  Stage 5: Handover & Maintenance – undertake all testing, commissioning & training / handover project to owner /carry out necessary maintenance / Defect rectification / etc COTM 4242 5
  • 6. Tendering will be started after the design completed and project budget is approved The process that is used to obtain offers leading to a contract between: client contractor client consultant main contractor sub-contractor COTM 4242 6
  • 7.  A tender formally means an invitation to trade under the terms of offer.  A contract is the term used for when the parties have reached agreement. COTM 4242 7
  • 8. COTM 4242 8 SELECTION CRITERIA In this process we look at the ways to choose between different tenderers, reviewing the specific Criteria for tender evaluation: •Pre-qualification •Technical evaluation •Financial Evaluation •Relationship between Technical and Financial
  • 9. COTM 4242 9 Pre- Qualification Technical Evaluation Financial Evaluation Interested firms or consortia, submit experience and financial capacity details Contracting Authority assesses these details Short list the firms Only short-listed firms can submit a proposal Bidders submit proposals
  • 10. COTM 4242 10 Pre- Qualification Bidders submit Technical Proposals, showing how they would run the contract Bidders provide information on Financial and technical ability Proposals assessed using ‘technical evaluation criteria Bidders have to pass a ‘technical threshold’ to be eligible for selection (e.g. scoring at least 70 percent on technical evaluation criteria in our country) Technical Qualification Financial Evaluation
  • 11. COTM 4242 11 Pre- Qualification Financial proposals of only technically acceptable bids should be opened and evaluated. Financial Criteria can be very simple, as following examples: Bidder asking for lowest tariff Bidder asking for Lowest Fee (Least Bidder) Bidder with best financial proposal awarded the contract Financial Qualification Technical Evaluation
  • 13.  To select a suitable contractor at a time appropriate to the situation of the project.  To obtain from the contractor selected at the proper time, an acceptable tender or offer upon which a contract can be let. COTM 4242 13
  • 14. COTM 4242 14 Stage 2: APPROVAL TO TENDER Stage 1: PREPARATION Stage 3: DOCUMENTATION Stage 4: INVITATION Stage 5: PROCESSING Stage 6: AWARD CONTRACT
  • 15.  Final completion of drawings, specification, measurement / take-off process.  Choose conditions of contract.  Parties involved: architects, engineers, QS, client COTM 4242 15
  • 16.  Discussion and decision on type of tender to be used.  Selection of tender:  Open  Selective  Negotiate  Parties involved: CLIENT, CONSULTANT, and CONTRACTOR COTM 4242 16 Short-listed tenderers
  • 17. Contract Document  Letter of invitation  Checklist for submission of tender  Articles of agreement  Form of tender  Specifications  Bills of quantities  Drawings  Letter of acceptance form  Schedule of day work rates COTM 4242 17
  • 18.  Based on selection of tendering methods  Open / competitive / bid tender – produce tender notice  Selective – short listed contractors will be invited to tender if they wish  Negotiated – only one contractor is approached- direct entry to project COTM 4242 18
  • 19.  The Tender Notice is a brief description of the job being tendered which is to be published in Newspapers and on the Internet.  The Internet is a very cost effective way of publishing the tenders. COTM 4242 19
  • 20. a. Name of the Project. b. Name & Address of the Company floating the tender. c. Name of work, materials or services. d. Place of work location. e. Approximate estimated cost of work. f. Earnest Money. g. Period of completion. h. Date on which the Tender Document sale commences. i. Date and time up to which tender documents can be obtained. j. The cost of tender documents. k. The date and time up to which the tenders to be submitted and are to be opened. l. Specification. m. Eligibility Criterion. COTM 4242 20
  • 21.  Receive tender submitted by contractor  Tender assessment / evaluation  Completed tenders are received  Arithmetical check  Reasonable tender sum  Reasonable completion time  Capabilities of renderers' under considerations  Tender recommendation / report – tender board COTM 4242 21
  • 22.  Pre-award meeting with contractors – validation of lowest complying bid  Validate lowest bid - Pre-contract meeting with contractor for contract signing  Approval by tender board / treasury COTM 4242 22
  • 24. COTM 4242 24 Stage 2: Determine basis of tender Stage 1: Decision to tender Stage 3: Preparation of cost estimates Stage 4: Commercial appreciation Stage 5: Conversion of estimate to tender Stage 6: Submission of tender
  • 25.  Receipt of tender documents  Pre-tender data sheet  Decision to tender  Consider implications of:  Bonds  Warranties  Parent company  Guarantees  Funding COTM 4242 25
  • 26.  Abstract materials and subcontractors  Sent out enquiries  Consider construction methods / prepare method statement  Design temporary works / consider alternatives  Prepare outline program  Check major quantities  Identify restrictions  Visit site and compile site report  Campaigning meeting (designating areas responsibilities) COTM 4242 26
  • 27.  Calculate current rates using:  Materials  Equipments and  Labour costs  Analyze and check subcontractors’ quotations  Price prelims / general items (in association with members of the team  Prepare summary sheets COTM 4242 27
  • 28.  Tender committee meeting part 1:  Review:  Method  Program  Technical and commercial risks  Cash flow and finance  Use of own plant  Competition  Commercial opportunities  Economic climate  Check prelims against historical cost data COTM 4242 28
  • 29.  Tender committee meeting – part 2:  Calculate ‘spread’ and add to estimate COTM 4242 29
  • 30.  Submit in format required (Bid submission format)  Organize delivery. COTM 4242 30