Project : Approximate estimation of Rigid pavement
Item : Excavation in Hard Rock (by Blasting)
By
Sandeep Bora AP14003
Anchit Agrawal AP14012
Aditya Avinashe AP14079
Pratik Dalai AP14081
Shivali Kalra AP14088
Topics
 Approximate estimation of rigid pavement
 Specifications of excavation in hard rock
 Brief Specification
 Detailed Specification
 Rate Analysis for excavation in hard rock
Rigid pavement cost per km
Sr No Project
Distance
(km)
Cost (cr)
Cost/km
(cr)
1 Mudhol Maharashtra border road on SH 18 in Karnataka 107.94 317.60 2.94
Contractor- Ashoka Buildcon and GVR Infra (On going project)
2 Malavalli to Pavagada(karnataka) 193.34 313.65 1.62
Contractor- Sadbhav Engineering Ltd and GKC Projects Ltd
(On going project)
3 Trichy Karur road(4 lane road) 63.00 732.84 2.91
Contractor-Reliance Infra (completed project)
4 Construction of approach road from South Garo Hills to Jetra 17.00 28.76 1.69
(On going project)
5 Construction of road from Pakoti to Kamsha 6.50 9.50 1.46
(On going project)
AVERAGE cost per km 2.13
Brief specification
 Excavation for foundation in hard rock by blasting including trimming and levelling
the bed and removing the excavated material and stacking it into measurable heaps
within a distance of 50 meters from site area.
Lift: 0 to 1.5m
Detailed specification
 Scope and objectives
 Equipment used
 Material Used
 Workmanship
 Testing and Acceptance Criteria
 Mode of measurement and payment
Scope and Objectives
 The purpose of this procedure is to establish the methodology to be followed
for excavation work during the construction phase .
 This procedure is applicable to the execution team. It intends to co-relate and
control the entire task needed to be done in order to achieve satisfactory
construction excavation work.
 Excavation is to be done for Hard rock by the means of blasting.
 We have used a machine intensive approach .
 Scope of work- 10 cubic meter
Equipment deployed
 Hydraulic Excavator
 Tipper
 Jack hammer
Hydraulic excavator
Excavator(Hyundai 250 R)Purpose:
Digging of trenches ,holes and
foundation.
Material handling,
Pising,
Demolition
Attachment:
Bucket, Breaker,
Auger
Rent
Rs 2200/hr
Capacity:
Bucket size: 0.93 cum
Tipper
Tipper (Bharat Benz)Purpose:
 Hauling of material
Charges
 Monthly rent (1.25 lakhs
excluding diesel)
Capacity: 14 cum
Jack Hammer
Jack hammerPurpose:
Drilling of holes,
Depth of drilling is 2m in this
case
Action of drilling takes place by
percussion action.
A pilot rod is drilled into the
surface with the help of
jackhammer
Charges: Rs11/ft or Rs 400/hour
Material Used
 Explosives
 Special Gelatine (gelatine stick)
 Powergel IDL
 25 mm thick
 Rs 2000/25kg
 Each stick of 125 grams.
 Electric detonator
 SED – Rajasthan Explosives
 1.8 m long wire
 Rs 12 / Piece
Workmanship
 Preparation of surface:
o Firstly the ground for blasting should be cleared of all obstacles.
o The ground should be preferably leveled.
o The ground should be cleaned and marked.
 Method of Blasting:
o Holes are to be drilled in triangular pattern for the required length.
o The electronic detonator is inserted into the explosive gel tube which is connected to
the external wire circuit
o Explosives are placed within the hole and are then grouted with dry soil up to the top
o The connection are checked and rechecked by the blaster
o All the explosives are connected in parallel and series connection
o This wire is connected to the detonating fuse.
o warning siren are sounded at an interval of 5 minutes before blasting, all the traffic in
the area should also be halted & red flags to be placed along the way, fragile structure
should be covered by polymer or plastic sheets to avoid damage.
o The blast shed should be located at least 10 m from the blasting area.
o After the detonation has taken place the area is excavated with the help of a excavator &
loaded into the tipper.
o Small pieces of rocks are removed and ground is levelled.
Blasting pattern
Testing and Acceptance Criteria
 The dimensions of the pits will be checked as per the GFC drawings .
 All over excavations filled back to required lines, levels and grades by placing plain
cement concrete of grade M10 and/or richer and/or by compacted earth, as
directed by the Engineer, at the Contractor’s cost.
 Sand replacement method of testing the field density on site to ensure the desire
densification has been obtained i.e minimum 95% of its maximum dry density.
Mode of measurement and payment
 Mode of measurement-
As per IS 1200(Part 1),
o Mode of measurement for Excavation is in cubic meter
o Each dimension shall be measured to the nearest 0.01m
o Areas shall be worked out to the nearest 0.01 sq.m
o Cubical content shall be worked out to the nearest 0.01 cu.m
o Working Authorised working space shall be special in each case. Where authorised
working space is not so specified the following shall apply:
600 mm measured from the face of substructure ( including protective measures, if
any) at lowest level, where extra working space is required.
 Mode of payment-
o Payment shall be done as per the GFC drawings.
Rate analysis
 Rate as per calculations: Rs 680.58
 Rate as per DSR 2014: Rs 653
 Rate analysis
estimation and quantity surveying

More Related Content

What's hot

Rate analysis and costing - Estimation, Costing and Valuation Engineering
Rate analysis and costing - Estimation, Costing and Valuation EngineeringRate analysis and costing - Estimation, Costing and Valuation Engineering
Rate analysis and costing - Estimation, Costing and Valuation EngineeringShanmugasundaram N
 
45010341 planning-estimate
45010341 planning-estimate45010341 planning-estimate
45010341 planning-estimateimaduddin91
 
Estimation and quantity surveying
Estimation and quantity surveyingEstimation and quantity surveying
Estimation and quantity surveyingAwanish Shukla
 
Specifications, reports and tenders
Specifications, reports and tendersSpecifications, reports and tenders
Specifications, reports and tendersgayu pandian
 
021 Construction Productivity (PART 1)
021 Construction Productivity (PART 1)021 Construction Productivity (PART 1)
021 Construction Productivity (PART 1)Dr Fereidoun Dejahang
 
QUANTITY SURVEYING
QUANTITY SURVEYINGQUANTITY SURVEYING
QUANTITY SURVEYINGlizwi nyandu
 
Heavy Construction Equipment Productivity
Heavy Construction Equipment Productivity Heavy Construction Equipment Productivity
Heavy Construction Equipment Productivity SSudhaVelan
 
Rate Analysis Site Meeting
Rate Analysis   Site MeetingRate Analysis   Site Meeting
Rate Analysis Site MeetingSanjay Patnaik
 
02 Construction Projects
02 Construction Projects02 Construction Projects
02 Construction Projectsakashpadole
 
Quality control in construction
Quality control in construction Quality control in construction
Quality control in construction Thanigaivel Asokan
 
Tenders contract -arti
Tenders contract -artiTenders contract -arti
Tenders contract -artijagadish108
 
THUMB RULE FOR CIVIL WORKS LABOUR PRODUCTIVITY
THUMB RULE FOR CIVIL WORKS LABOUR PRODUCTIVITYTHUMB RULE FOR CIVIL WORKS LABOUR PRODUCTIVITY
THUMB RULE FOR CIVIL WORKS LABOUR PRODUCTIVITYSSudhaVelan
 
QUANTITY SURVEYING & ESTIMATION- Nicmar
QUANTITY SURVEYING & ESTIMATION- NicmarQUANTITY SURVEYING & ESTIMATION- Nicmar
QUANTITY SURVEYING & ESTIMATION- NicmarMuneesh Methwani
 
Insepction and quality control
Insepction and quality controlInsepction and quality control
Insepction and quality controlSOURAV4798
 
Chapter 1 introduction of building construction
Chapter 1 introduction of building constructionChapter 1 introduction of building construction
Chapter 1 introduction of building constructionKHUSHBU SHAH
 
Rate analysis road work in Estimation & Rate Analyisis
Rate analysis road work in Estimation & Rate AnalyisisRate analysis road work in Estimation & Rate Analyisis
Rate analysis road work in Estimation & Rate AnalyisisJaptyesh Singh
 
01_Introduction_to_Estimation.pdf
01_Introduction_to_Estimation.pdf01_Introduction_to_Estimation.pdf
01_Introduction_to_Estimation.pdfkiransreekumar6
 

What's hot (20)

Rate analysis and costing - Estimation, Costing and Valuation Engineering
Rate analysis and costing - Estimation, Costing and Valuation EngineeringRate analysis and costing - Estimation, Costing and Valuation Engineering
Rate analysis and costing - Estimation, Costing and Valuation Engineering
 
45010341 planning-estimate
45010341 planning-estimate45010341 planning-estimate
45010341 planning-estimate
 
Estimation and quantity surveying
Estimation and quantity surveyingEstimation and quantity surveying
Estimation and quantity surveying
 
Specifications, reports and tenders
Specifications, reports and tendersSpecifications, reports and tenders
Specifications, reports and tenders
 
021 Construction Productivity (PART 1)
021 Construction Productivity (PART 1)021 Construction Productivity (PART 1)
021 Construction Productivity (PART 1)
 
QUANTITY SURVEYING
QUANTITY SURVEYINGQUANTITY SURVEYING
QUANTITY SURVEYING
 
Heavy Construction Equipment Productivity
Heavy Construction Equipment Productivity Heavy Construction Equipment Productivity
Heavy Construction Equipment Productivity
 
Rate Analysis Site Meeting
Rate Analysis   Site MeetingRate Analysis   Site Meeting
Rate Analysis Site Meeting
 
02 Construction Projects
02 Construction Projects02 Construction Projects
02 Construction Projects
 
Quality control in construction
Quality control in construction Quality control in construction
Quality control in construction
 
Rate analysis brief
Rate analysis briefRate analysis brief
Rate analysis brief
 
Tenders contract -arti
Tenders contract -artiTenders contract -arti
Tenders contract -arti
 
THUMB RULE FOR CIVIL WORKS LABOUR PRODUCTIVITY
THUMB RULE FOR CIVIL WORKS LABOUR PRODUCTIVITYTHUMB RULE FOR CIVIL WORKS LABOUR PRODUCTIVITY
THUMB RULE FOR CIVIL WORKS LABOUR PRODUCTIVITY
 
QUANTITY SURVEYING & ESTIMATION- Nicmar
QUANTITY SURVEYING & ESTIMATION- NicmarQUANTITY SURVEYING & ESTIMATION- Nicmar
QUANTITY SURVEYING & ESTIMATION- Nicmar
 
Bill Of Quantities
Bill Of QuantitiesBill Of Quantities
Bill Of Quantities
 
Insepction and quality control
Insepction and quality controlInsepction and quality control
Insepction and quality control
 
Chapter 1 introduction of building construction
Chapter 1 introduction of building constructionChapter 1 introduction of building construction
Chapter 1 introduction of building construction
 
Analysis of rates
Analysis of ratesAnalysis of rates
Analysis of rates
 
Rate analysis road work in Estimation & Rate Analyisis
Rate analysis road work in Estimation & Rate AnalyisisRate analysis road work in Estimation & Rate Analyisis
Rate analysis road work in Estimation & Rate Analyisis
 
01_Introduction_to_Estimation.pdf
01_Introduction_to_Estimation.pdf01_Introduction_to_Estimation.pdf
01_Introduction_to_Estimation.pdf
 

Similar to estimation and quantity surveying

Amit pandit presentaion gautambuddha university
Amit pandit presentaion gautambuddha universityAmit pandit presentaion gautambuddha university
Amit pandit presentaion gautambuddha universityAman Jain
 
Construction of Utility Tunnel phase ll
Construction of Utility Tunnel phase  llConstruction of Utility Tunnel phase  ll
Construction of Utility Tunnel phase llRavi Bhadani
 
Fundamentals of Estimating and Costing
 Fundamentals of Estimating and Costing Fundamentals of Estimating and Costing
Fundamentals of Estimating and CostingGanesh Tatikonda
 
chapter1-210122051628.pdf
chapter1-210122051628.pdfchapter1-210122051628.pdf
chapter1-210122051628.pdfDeepak37004
 
Rev 01 dt 01.03.2010 - soil investigation
Rev 01 dt 01.03.2010 - soil investigationRev 01 dt 01.03.2010 - soil investigation
Rev 01 dt 01.03.2010 - soil investigationSiddhartha Bhamidipati
 
Village networking ppt
Village networking pptVillage networking ppt
Village networking pptPatel Tapan
 
Cone Penetration Test
Cone Penetration TestCone Penetration Test
Cone Penetration TestMuftah Aljoat
 
A valuable journey proposal
A valuable journey proposalA valuable journey proposal
A valuable journey proposalkjanand
 
Planning and deployment of CSM at moderate depth opencast mines-a blast free ...
Planning and deployment of CSM at moderate depth opencast mines-a blast free ...Planning and deployment of CSM at moderate depth opencast mines-a blast free ...
Planning and deployment of CSM at moderate depth opencast mines-a blast free ...Roshan Kumar Patel
 
final presentation 1 goa
final presentation 1 goafinal presentation 1 goa
final presentation 1 goaAnkit Anand
 
ROAD CONSTRUCTION (FLEXIBLE & RIGID) - SLIDES.pdf
ROAD CONSTRUCTION (FLEXIBLE & RIGID) - SLIDES.pdfROAD CONSTRUCTION (FLEXIBLE & RIGID) - SLIDES.pdf
ROAD CONSTRUCTION (FLEXIBLE & RIGID) - SLIDES.pdfDanielWisman1
 
Steps Involves in Building Construction
Steps Involves in Building ConstructionSteps Involves in Building Construction
Steps Involves in Building ConstructionAdnan. Ali
 
ULCCS - industrial visit report
ULCCS - industrial visit reportULCCS - industrial visit report
ULCCS - industrial visit reportSHAMJITH KM
 
20221110-Cap shield issue report.pptx
20221110-Cap shield issue report.pptx20221110-Cap shield issue report.pptx
20221110-Cap shield issue report.pptxArifPuguhNugroho
 

Similar to estimation and quantity surveying (20)

Summer training report
Summer training reportSummer training report
Summer training report
 
Amit pandit presentaion gautambuddha university
Amit pandit presentaion gautambuddha universityAmit pandit presentaion gautambuddha university
Amit pandit presentaion gautambuddha university
 
Construction of Utility Tunnel phase ll
Construction of Utility Tunnel phase  llConstruction of Utility Tunnel phase  ll
Construction of Utility Tunnel phase ll
 
Geotechnical Investigation
Geotechnical InvestigationGeotechnical Investigation
Geotechnical Investigation
 
RoadstaB august 2013
RoadstaB august 2013RoadstaB august 2013
RoadstaB august 2013
 
Fundamentals of Estimating and Costing
 Fundamentals of Estimating and Costing Fundamentals of Estimating and Costing
Fundamentals of Estimating and Costing
 
chapter1-210122051628.pdf
chapter1-210122051628.pdfchapter1-210122051628.pdf
chapter1-210122051628.pdf
 
Rev 01 dt 01.03.2010 - soil investigation
Rev 01 dt 01.03.2010 - soil investigationRev 01 dt 01.03.2010 - soil investigation
Rev 01 dt 01.03.2010 - soil investigation
 
Village networking ppt
Village networking pptVillage networking ppt
Village networking ppt
 
Cep construction of railway overbridge by abhisek panda
Cep construction of railway overbridge by abhisek pandaCep construction of railway overbridge by abhisek panda
Cep construction of railway overbridge by abhisek panda
 
Cone Penetration Test
Cone Penetration TestCone Penetration Test
Cone Penetration Test
 
A valuable journey proposal
A valuable journey proposalA valuable journey proposal
A valuable journey proposal
 
Power shovel
Power shovelPower shovel
Power shovel
 
Planning and deployment of CSM at moderate depth opencast mines-a blast free ...
Planning and deployment of CSM at moderate depth opencast mines-a blast free ...Planning and deployment of CSM at moderate depth opencast mines-a blast free ...
Planning and deployment of CSM at moderate depth opencast mines-a blast free ...
 
final presentation 1 goa
final presentation 1 goafinal presentation 1 goa
final presentation 1 goa
 
ROAD CONSTRUCTION (FLEXIBLE & RIGID) - SLIDES.pdf
ROAD CONSTRUCTION (FLEXIBLE & RIGID) - SLIDES.pdfROAD CONSTRUCTION (FLEXIBLE & RIGID) - SLIDES.pdf
ROAD CONSTRUCTION (FLEXIBLE & RIGID) - SLIDES.pdf
 
Steps Involves in Building Construction
Steps Involves in Building ConstructionSteps Involves in Building Construction
Steps Involves in Building Construction
 
ULCCS - industrial visit report
ULCCS - industrial visit reportULCCS - industrial visit report
ULCCS - industrial visit report
 
Phase 2
Phase 2Phase 2
Phase 2
 
20221110-Cap shield issue report.pptx
20221110-Cap shield issue report.pptx20221110-Cap shield issue report.pptx
20221110-Cap shield issue report.pptx
 

Recently uploaded

Graduate Outcomes Presentation Slides - English
Graduate Outcomes Presentation Slides - EnglishGraduate Outcomes Presentation Slides - English
Graduate Outcomes Presentation Slides - Englishneillewis46
 
Kodo Millet PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...
Kodo Millet  PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...Kodo Millet  PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...
Kodo Millet PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...pradhanghanshyam7136
 
HMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptx
HMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptxHMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptx
HMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptxmarlenawright1
 
Towards a code of practice for AI in AT.pptx
Towards a code of practice for AI in AT.pptxTowards a code of practice for AI in AT.pptx
Towards a code of practice for AI in AT.pptxJisc
 
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...Nguyen Thanh Tu Collection
 
Holdier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfHoldier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfagholdier
 
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptx
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptxHMCS Max Bernays Pre-Deployment Brief (May 2024).pptx
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptxEsquimalt MFRC
 
The basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptxThe basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptxheathfieldcps1
 
How to setup Pycharm environment for Odoo 17.pptx
How to setup Pycharm environment for Odoo 17.pptxHow to setup Pycharm environment for Odoo 17.pptx
How to setup Pycharm environment for Odoo 17.pptxCeline George
 
Accessible Digital Futures project (20/03/2024)
Accessible Digital Futures project (20/03/2024)Accessible Digital Futures project (20/03/2024)
Accessible Digital Futures project (20/03/2024)Jisc
 
COMMUNICATING NEGATIVE NEWS - APPROACHES .pptx
COMMUNICATING NEGATIVE NEWS - APPROACHES .pptxCOMMUNICATING NEGATIVE NEWS - APPROACHES .pptx
COMMUNICATING NEGATIVE NEWS - APPROACHES .pptxannathomasp01
 
General Principles of Intellectual Property: Concepts of Intellectual Proper...
General Principles of Intellectual Property: Concepts of Intellectual  Proper...General Principles of Intellectual Property: Concepts of Intellectual  Proper...
General Principles of Intellectual Property: Concepts of Intellectual Proper...Poonam Aher Patil
 
Basic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptxBasic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptxDenish Jangid
 
Micro-Scholarship, What it is, How can it help me.pdf
Micro-Scholarship, What it is, How can it help me.pdfMicro-Scholarship, What it is, How can it help me.pdf
Micro-Scholarship, What it is, How can it help me.pdfPoh-Sun Goh
 
Exploring_the_Narrative_Style_of_Amitav_Ghoshs_Gun_Island.pptx
Exploring_the_Narrative_Style_of_Amitav_Ghoshs_Gun_Island.pptxExploring_the_Narrative_Style_of_Amitav_Ghoshs_Gun_Island.pptx
Exploring_the_Narrative_Style_of_Amitav_Ghoshs_Gun_Island.pptxPooja Bhuva
 
80 ĐỀ THI THỬ TUYỂN SINH TIẾNG ANH VÀO 10 SỞ GD – ĐT THÀNH PHỐ HỒ CHÍ MINH NĂ...
80 ĐỀ THI THỬ TUYỂN SINH TIẾNG ANH VÀO 10 SỞ GD – ĐT THÀNH PHỐ HỒ CHÍ MINH NĂ...80 ĐỀ THI THỬ TUYỂN SINH TIẾNG ANH VÀO 10 SỞ GD – ĐT THÀNH PHỐ HỒ CHÍ MINH NĂ...
80 ĐỀ THI THỬ TUYỂN SINH TIẾNG ANH VÀO 10 SỞ GD – ĐT THÀNH PHỐ HỒ CHÍ MINH NĂ...Nguyen Thanh Tu Collection
 
Beyond_Borders_Understanding_Anime_and_Manga_Fandom_A_Comprehensive_Audience_...
Beyond_Borders_Understanding_Anime_and_Manga_Fandom_A_Comprehensive_Audience_...Beyond_Borders_Understanding_Anime_and_Manga_Fandom_A_Comprehensive_Audience_...
Beyond_Borders_Understanding_Anime_and_Manga_Fandom_A_Comprehensive_Audience_...Pooja Bhuva
 
How to Create and Manage Wizard in Odoo 17
How to Create and Manage Wizard in Odoo 17How to Create and Manage Wizard in Odoo 17
How to Create and Manage Wizard in Odoo 17Celine George
 
ICT role in 21st century education and it's challenges.
ICT role in 21st century education and it's challenges.ICT role in 21st century education and it's challenges.
ICT role in 21st century education and it's challenges.MaryamAhmad92
 

Recently uploaded (20)

Graduate Outcomes Presentation Slides - English
Graduate Outcomes Presentation Slides - EnglishGraduate Outcomes Presentation Slides - English
Graduate Outcomes Presentation Slides - English
 
Kodo Millet PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...
Kodo Millet  PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...Kodo Millet  PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...
Kodo Millet PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...
 
HMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptx
HMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptxHMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptx
HMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptx
 
Towards a code of practice for AI in AT.pptx
Towards a code of practice for AI in AT.pptxTowards a code of practice for AI in AT.pptx
Towards a code of practice for AI in AT.pptx
 
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
 
Holdier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfHoldier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdf
 
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptx
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptxHMCS Max Bernays Pre-Deployment Brief (May 2024).pptx
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptx
 
The basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptxThe basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptx
 
How to setup Pycharm environment for Odoo 17.pptx
How to setup Pycharm environment for Odoo 17.pptxHow to setup Pycharm environment for Odoo 17.pptx
How to setup Pycharm environment for Odoo 17.pptx
 
Accessible Digital Futures project (20/03/2024)
Accessible Digital Futures project (20/03/2024)Accessible Digital Futures project (20/03/2024)
Accessible Digital Futures project (20/03/2024)
 
COMMUNICATING NEGATIVE NEWS - APPROACHES .pptx
COMMUNICATING NEGATIVE NEWS - APPROACHES .pptxCOMMUNICATING NEGATIVE NEWS - APPROACHES .pptx
COMMUNICATING NEGATIVE NEWS - APPROACHES .pptx
 
General Principles of Intellectual Property: Concepts of Intellectual Proper...
General Principles of Intellectual Property: Concepts of Intellectual  Proper...General Principles of Intellectual Property: Concepts of Intellectual  Proper...
General Principles of Intellectual Property: Concepts of Intellectual Proper...
 
Basic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptxBasic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptx
 
Mehran University Newsletter Vol-X, Issue-I, 2024
Mehran University Newsletter Vol-X, Issue-I, 2024Mehran University Newsletter Vol-X, Issue-I, 2024
Mehran University Newsletter Vol-X, Issue-I, 2024
 
Micro-Scholarship, What it is, How can it help me.pdf
Micro-Scholarship, What it is, How can it help me.pdfMicro-Scholarship, What it is, How can it help me.pdf
Micro-Scholarship, What it is, How can it help me.pdf
 
Exploring_the_Narrative_Style_of_Amitav_Ghoshs_Gun_Island.pptx
Exploring_the_Narrative_Style_of_Amitav_Ghoshs_Gun_Island.pptxExploring_the_Narrative_Style_of_Amitav_Ghoshs_Gun_Island.pptx
Exploring_the_Narrative_Style_of_Amitav_Ghoshs_Gun_Island.pptx
 
80 ĐỀ THI THỬ TUYỂN SINH TIẾNG ANH VÀO 10 SỞ GD – ĐT THÀNH PHỐ HỒ CHÍ MINH NĂ...
80 ĐỀ THI THỬ TUYỂN SINH TIẾNG ANH VÀO 10 SỞ GD – ĐT THÀNH PHỐ HỒ CHÍ MINH NĂ...80 ĐỀ THI THỬ TUYỂN SINH TIẾNG ANH VÀO 10 SỞ GD – ĐT THÀNH PHỐ HỒ CHÍ MINH NĂ...
80 ĐỀ THI THỬ TUYỂN SINH TIẾNG ANH VÀO 10 SỞ GD – ĐT THÀNH PHỐ HỒ CHÍ MINH NĂ...
 
Beyond_Borders_Understanding_Anime_and_Manga_Fandom_A_Comprehensive_Audience_...
Beyond_Borders_Understanding_Anime_and_Manga_Fandom_A_Comprehensive_Audience_...Beyond_Borders_Understanding_Anime_and_Manga_Fandom_A_Comprehensive_Audience_...
Beyond_Borders_Understanding_Anime_and_Manga_Fandom_A_Comprehensive_Audience_...
 
How to Create and Manage Wizard in Odoo 17
How to Create and Manage Wizard in Odoo 17How to Create and Manage Wizard in Odoo 17
How to Create and Manage Wizard in Odoo 17
 
ICT role in 21st century education and it's challenges.
ICT role in 21st century education and it's challenges.ICT role in 21st century education and it's challenges.
ICT role in 21st century education and it's challenges.
 

estimation and quantity surveying

  • 1. Project : Approximate estimation of Rigid pavement Item : Excavation in Hard Rock (by Blasting) By Sandeep Bora AP14003 Anchit Agrawal AP14012 Aditya Avinashe AP14079 Pratik Dalai AP14081 Shivali Kalra AP14088
  • 2. Topics  Approximate estimation of rigid pavement  Specifications of excavation in hard rock  Brief Specification  Detailed Specification  Rate Analysis for excavation in hard rock
  • 3. Rigid pavement cost per km Sr No Project Distance (km) Cost (cr) Cost/km (cr) 1 Mudhol Maharashtra border road on SH 18 in Karnataka 107.94 317.60 2.94 Contractor- Ashoka Buildcon and GVR Infra (On going project) 2 Malavalli to Pavagada(karnataka) 193.34 313.65 1.62 Contractor- Sadbhav Engineering Ltd and GKC Projects Ltd (On going project) 3 Trichy Karur road(4 lane road) 63.00 732.84 2.91 Contractor-Reliance Infra (completed project) 4 Construction of approach road from South Garo Hills to Jetra 17.00 28.76 1.69 (On going project) 5 Construction of road from Pakoti to Kamsha 6.50 9.50 1.46 (On going project) AVERAGE cost per km 2.13
  • 4. Brief specification  Excavation for foundation in hard rock by blasting including trimming and levelling the bed and removing the excavated material and stacking it into measurable heaps within a distance of 50 meters from site area. Lift: 0 to 1.5m
  • 5. Detailed specification  Scope and objectives  Equipment used  Material Used  Workmanship  Testing and Acceptance Criteria  Mode of measurement and payment
  • 6. Scope and Objectives  The purpose of this procedure is to establish the methodology to be followed for excavation work during the construction phase .  This procedure is applicable to the execution team. It intends to co-relate and control the entire task needed to be done in order to achieve satisfactory construction excavation work.  Excavation is to be done for Hard rock by the means of blasting.  We have used a machine intensive approach .  Scope of work- 10 cubic meter
  • 7. Equipment deployed  Hydraulic Excavator  Tipper  Jack hammer
  • 8. Hydraulic excavator Excavator(Hyundai 250 R)Purpose: Digging of trenches ,holes and foundation. Material handling, Pising, Demolition Attachment: Bucket, Breaker, Auger Rent Rs 2200/hr Capacity: Bucket size: 0.93 cum
  • 9. Tipper Tipper (Bharat Benz)Purpose:  Hauling of material Charges  Monthly rent (1.25 lakhs excluding diesel) Capacity: 14 cum
  • 10. Jack Hammer Jack hammerPurpose: Drilling of holes, Depth of drilling is 2m in this case Action of drilling takes place by percussion action. A pilot rod is drilled into the surface with the help of jackhammer Charges: Rs11/ft or Rs 400/hour
  • 11. Material Used  Explosives  Special Gelatine (gelatine stick)  Powergel IDL  25 mm thick  Rs 2000/25kg  Each stick of 125 grams.  Electric detonator  SED – Rajasthan Explosives  1.8 m long wire  Rs 12 / Piece
  • 12. Workmanship  Preparation of surface: o Firstly the ground for blasting should be cleared of all obstacles. o The ground should be preferably leveled. o The ground should be cleaned and marked.  Method of Blasting: o Holes are to be drilled in triangular pattern for the required length. o The electronic detonator is inserted into the explosive gel tube which is connected to the external wire circuit o Explosives are placed within the hole and are then grouted with dry soil up to the top o The connection are checked and rechecked by the blaster o All the explosives are connected in parallel and series connection o This wire is connected to the detonating fuse. o warning siren are sounded at an interval of 5 minutes before blasting, all the traffic in the area should also be halted & red flags to be placed along the way, fragile structure should be covered by polymer or plastic sheets to avoid damage. o The blast shed should be located at least 10 m from the blasting area. o After the detonation has taken place the area is excavated with the help of a excavator & loaded into the tipper. o Small pieces of rocks are removed and ground is levelled.
  • 14. Testing and Acceptance Criteria  The dimensions of the pits will be checked as per the GFC drawings .  All over excavations filled back to required lines, levels and grades by placing plain cement concrete of grade M10 and/or richer and/or by compacted earth, as directed by the Engineer, at the Contractor’s cost.  Sand replacement method of testing the field density on site to ensure the desire densification has been obtained i.e minimum 95% of its maximum dry density.
  • 15. Mode of measurement and payment  Mode of measurement- As per IS 1200(Part 1), o Mode of measurement for Excavation is in cubic meter o Each dimension shall be measured to the nearest 0.01m o Areas shall be worked out to the nearest 0.01 sq.m o Cubical content shall be worked out to the nearest 0.01 cu.m o Working Authorised working space shall be special in each case. Where authorised working space is not so specified the following shall apply: 600 mm measured from the face of substructure ( including protective measures, if any) at lowest level, where extra working space is required.  Mode of payment- o Payment shall be done as per the GFC drawings.
  • 16. Rate analysis  Rate as per calculations: Rs 680.58  Rate as per DSR 2014: Rs 653  Rate analysis