2. 27/07/1436
Seismic Damage2
• 1- due to ground movements and soil changes.
• 2- Damage due to building shape or dimensions
• 3- Damage due to structural elements.
Main causes of structural damage
Landslides
Ground liquefaction
Seismic sea waves (Tsunami’s)
Fault movements.
Due to ground movements and soil
changes.
5. 27/07/1436
Seismic Damage5
Soft story failure
1- Shows a significant decrease in lateral stiffness from that immediately above.
How:
- Height of this floor is higher than the rest of floors.
- Change of section that reduce the stiffness.
- Removing of infill walls
Soft Story: one floor has less
stiffness than the adjacent
floors
10. 27/07/1436
Seismic Damage10
Pounding
If the distance between two buildings are very
small, they may collide with each other during
earthquake. The forces due to collision is ver
high. To prevent this damage:
• You must leave a minimum separation distance.
• Design the two building for these forces.
• Add special walls to resist this force.
Pounding failure.
11. 27/07/1436
Seismic Damage11
• 1- Column failure.
• 2- Beam failure.
• 3- Beam-column failure.
• 4- Shear wall failure.
Damage of structural elements
1- Column failure.
Buckling of longitudinal steel due to
large spacing of stirrups.
12. 27/07/1436
Seismic Damage12
1- Column failure.
Using confinement in columns
Confined with spiral stirrups
Using separate stirrups
with large spacing
1- Column failure.
Bond failure at the lap splice joint
13. 27/07/1436
Seismic Damage13
1- Column failure.
Bond failure :Short length of column extension in the
beam
1- Column failure.
Bond failure at the lap splice joint
16. 27/07/1436
Seismic Damage16
splice failure of beam
2- Beam failure.
3- Beam-Column Joint failure.
• Longitudinal beam bars
not confined within
column longitudinal
bars or ties
17. 27/07/1436
Seismic Damage17
3- Beam-Column Joint failure.
No intermediate ties in
joint normal to outside
face of joint
3- Beam-Column Joint failure.
-No transverse reinforcement through joint
-Insufficient anchorage for hooked bars
-Widely spaced ties outside of joint
-No intermediate ties in column