NAME OF THE JOB.




PREAMBLE TO BILL OF QUANTITIES



   1. Rates for mobilization to the site includes mobilization all and every equipment,
      ancillaries and everything required for these works unless provided for elsewhere and
      including distance traveled and allowance for difficulties of access all and everything.

   2. Setting up at location includes provisition of stable working plateform or otherwise to
      suit the type of test this item applies to

   3. Rate for boring and drilling includes provision of clean water or clean water with
      additives as approved by the SO and usage of compatible rods, core barrels and drill
      and core bits to suit the ground conditions and delivery of rock cores including core
      boxes.

   4. Rates for sampling includes proper packing, storage and delivery of samples

   5. Rates for undisturbed samples includes usage of proprietary sample tubes without
      burrs or seams and used without adapters, sealing, storage and safe delivery

   6. Standard Penetration test includes usage of proper rods, split spoon as per MS___ ,
      sample description in accordance with MS___ and packing, storing and transporting.

   7. Rate for vane test includes type of vane and equipment used to provide reliable test
      results.

   8. Setting up of CPT or Piezeocone over soft ground or water includes for provision of
      suitable stable plateform for the purpose




                                               1
NAME OF THE JOB.




BILL OF QUANTITIES NO. 1 : PRELIMINARIES


ITEM                         DESCRIPTION                             UNIT      QTY     RATE     AMOUNT
                                                                                       (RM)      (RM)

 1.0    Preliminaries

 1.1    Allow for compliance with specifications and conditions of   Lump
        the contract.                                                 sum


 1.2    Allow for compliance with all other requirements under       Lump
        the contract.                                                 sum


 1.3    Allow for provision of full time professional attendance     Lump
        on site for the duration of the site operations.              sum


 1.4    Allow for provision of two (2) number copies of Interim      Lump
        Factual Report.                                               sum


 1.5    Allow for provision of six (6) number copies of complete     Lump
        Final Factual Report, one compiled and bound set of all       sum
        raw field and Laboratory sheets and one copy of factual
        Report in electronics format.


 1.6    Allow for Licensed Surveyor for setting up of all test       Lump
        locations and taking of levels.                               sum


 1.7    Allow for provision of photographs in electronic format as   Lump
        per this specifications.                                     Sum


 1.8    Provide additional copies of final factual report.           No.       Rate               -
                                                                               Only




                                                                           Carried to summary




                                                        2
NAME OF THE JOB.




BILL OF QUANTITIES NO. 2 : BORING AND CORING


ITEM                           DESCRIPTION                            UNIT   QTY     RATE      AMOUNT
                                                                                     (RM)       (RM)

 2.0     Boring and Coring

 2.1     Mobilisation of Boring Plants and all and every required     Lump
         ancillaries to complete works under this contract to the      Sum
         site including erecting the plants at the First borehole
         location if necessary, staging on barges or any other
         means of supporting and stabilising the boring plant
         above water level, erecting, dismantling and
         demobilisation from the site after completion of works.

 2.1.1   Extra over above for Air/Foam Drilling Plant and
         Ancillaries.

 2.1.2   Moving the plant from each position to the next              No.
         including, if necessary, dismantling and re-erecting on
         ground or on supports in Item 2.1 above, including the
         provision of any staging if necessary for test location on
         land.

 2.1.3    - ditto – but for test location over water on very soft
          grounds requiring special staging.

 2.1.4    Extra over for Air/Foam Drilling Plant and Ancillaries


 2.2      Boring in Soil

 2.2.1   Carry out borings in soils as per Specification whether
         cased or uncased including the provision of "disturbed
         samples", delivery to the testing laboratory, and as
         directed by S.O.:-

 2.2.2   Depth from natural ground or water bed level not              m
         exceeding 10m.

 2.2.3   - ditto - exceeding 10 and not exceeding 20m                  m

 2.2.4   - ditto - exceeding 20m and not exceeding 30m                 m

 2.2.5   - ditto - exceeding 30m and not exceeding 40m                 m

 2.2.6   - ditto - exceeding 40m and not exceeding 50m                 m

2.2.7    Extra over item 2.3.1 to 2.3.5 for where air foam is used     m




                                                                             Carried Forward


                                                          3
NAME OF THE JOB.




BILL OF QUANTITIES NO. 2 : BORING AND CORING (Continued)


 ITEM                         DESCRIPTION                              UNIT      QTY     RATE     AMOUNT
                                                                                         (RM)      (RM)
                                                   Brought Forward


 2.3     Drilling in Rock

 2.3.1   Carrying out coring to core size 52mm nominal diameter
         in rock including extraction of complete cores, core box
         and delivery to the testing laboratory or to location
         specified by S.O. as per Specification:-

2.3.2    Depth from natural ground or water bed level not               m
         exceeding 10m.

 2.3.3   - ditto - exceeding 10 and not exceeding 20m                   m

 2.3.4   - ditto - exceeding 20m and not exceeding 30m                  m

 2.3.5   - ditto - exceeding 30m and not exceeding 40m                  m

2.3.6    - ditto - exceeding 40m                                        m

2.3.7    Extra over item 2.6.1 to 2.6.5 where air foam is used          m


 2.4     Test/Trial Pit

 2.4.1   Excavate trial/test pit in soil to depth not exceeding 2m     No.
         below ground level. Rate to include necessary timbering
         dewatering, and backfilling after excavation. Detail
         geological logging of pit face and base including provision
         for photograph

 2.4.2   - ditto – but 2m to n.e. 4m.                                  No.


 2.5     Hand Augering

 2.5.1   Carry out hand auger including the provision of                m
         collecting disturbed samples, depth from ground level
         to not exceeding (n.e.) 3.5m

 2.5.2   - ditto – but 3.5m to n.e. 7m                                  m




                                                                             Carried to summary




                                                        4
NAME OF THE JOB.




BILL OF QUANTITIES NO. 3 : SAMPLING


 ITEM                        DESCRIPTION                          UNIT   QTY     RATE      AMOUNT
                                                                                  (RM)      (RM)

  3.0    Sampling

  3.1    Small Disturbed Samples

 3.1.1   Obtain 1kg small disturbed samples with split-barrel     No.
         tubes or otherwise, depth from ground level to not
         exceeding (n. e.) 10m.ckfilling after excavation.

 3.1.2   - ditto – but 10m to n.e. 20m                            No.

 3.1.3   - ditto – but 20m to n.e. 30m                            No.

 3.1.4   - ditto – but 30m to n.e. 40m                            No.

 3.1.5   - ditto – but exceeding 40m                              No.


  3.2    Undisturbed Samples

 3.2.1   Obtain undisturbed soil samples as per specifications
         and deliver to the testing laboratory.

 3.2.2   Depth from natural ground or water bed level exceeding   No
         not exceeding 10m

 3.2.3   - ditto - exceeding 10 and not exceeding 20m             No.

 3.2.4   - ditto - exceeding 20m and not exceeding 30m            No.

 3.2.5   - ditto - exceeding 30m and not exceeding 40m            No.


  3.3    Undisturbed Samples (Piston Sampler)

 3.3.1   Obtain undisturbed samples with stationery piston        No.
         sampler from the bottom of borehole, depth from ground
         level to not exceeding (n.e.) 10m.

 3.3.2   - ditto – but 10m to n.e. 20m                            No.

 3.3.3   - ditto – but 20m to n.e. 30m                            No.

 3.3.4   - ditto – but exceeding 30m                              No.




                                                                         Carried Forward




                                                     5
NAME OF THE JOB.




BILL OF QUANTITIES NO. 3: SAMPLING (Continued)


 ITEM                        DESCRIPTION                             UNIT      QTY     RATE     AMOUNT
                                                                                       (RM)      (RM)
                                                 Brought Forward


  3.4    Undisturbed Block Samples

 3.4.1   Obtain Undisturbed 300mm cube sample in wooden              No.
         packing at depth not exceeding 4.0m and insitu
         handvane and hand penetrometer testing at 0.3m
         interval to 4.0m.


  3.5    Bulk Disturbed Samples

 3.5.1   Obtain 45kg bulk disturbed samples from percussion          No.
         borehole, depth from ground level to not exceeding (n.e.)
         10m


  3.6    Water Sample

 3.6.1   Collect representative ground water sample from the         No.
         borehole as per specification or as directed by. S.O. and
         deliver to the testing laboratory




                                                                           Carried to summary




                                                      6
NAME OF THE JOB.




BILL OF QUANTITIES NO. 4: IN-SITU TESTS


 ITEM                       DESCRIPTION                           UNIT   QTY     RATE      AMOUNT
                                                                                  (RM)      (RM)

 4.0     In-situ Tests

  4.1    Standard Penetration Tests

 4.1.1   Carrying out Standard Penetration Test and obtaining
         disturbed samples including packaging and transport as
         per Specification:-

 4.1.2   Depth measured from natural ground or water bed level    No.
         not exceeding 10m.

 4.1.3   - ditto - exceeding 10 and not exceeding 20m             No.

 4.1.4   - ditto - exceeding 20m and not exceeding 30m            No.

 4.1.5   - ditto - exceeding 30m and not exceeding 40m            No.

 4.1.6   - ditto - exceeding 40m and not exceeding 50m            No.


 4.2     Vane Shear Tests In Borehole

 4.2.1   Carrying out Vane Shear Test and including disturbed
         samples as per Specification:-

 4.2.2   Depth measured from natural ground or water bed level    No.
         not exceeding 10m.

 4.2.3   - ditto - exceeding 10 and not exceeding 20m             No.

 4.2.4   - ditto - exceeding 20m and not exceeding 30m            No.

 4.2.5   - ditto - exceeding 30m and not exceeding 40m            No.

 4.2.6   - ditto - exceeding 40m and not exceeding 50m            No.                         -


 4.3     Penetration Field Vane Test

 4.3.1   Setting out of location, setting up, dismantling and
         moving equipment for penetration vane test on land.

 4.3.2    - ditto but over swampy ground or water log area        No.

 4.3.3    Advance vane, depth from ground level to not             m
          Exceeding (n.e.) 10m.



                                                                         Carried Forward   4,700.00


                                                        7
NAME OF THE JOB.




BILL OF QUANTITIES NO. 4: IN-SITU TESTS (Continued)


 ITEM                        DESCRIPTION                            UNIT   QTY     RATE      AMOUNT
                                                                                   (RM)       (RM)
                                                  Brought Forward


 4.3.4    - ditto – but from 10m to n. e. 20m.                       m

 4.3.5    - ditto – but from 20m to n. e. 30m.                       m

 4.3.6    Carry out field Vane Test                                 No.


 4.4     “Mackintosh” Probes

 4.4.1   Carrying out “Mackintosh” Probes as per Specification      No.
         to maximum depth from natural ground or water bed not
         to exceed 20m or 300 blow/300mm whichever comes
         first.


 4.5      Deep Sounding Test (Piezocone)

 4.5.1    Setting out of location, setting up, dismantling and      No.
          moving deep sounding machine of specified capacity
          and reaction on land.

 4.5.2    - ditto – but over soft/swampy ground, water loggged      No.
          areas or over water.



 4.5.3    Carry out deep sounding test (piezocone), depth from       m
          ground level to not exceeding (n.e.) 10m.

 4.5.4    - ditto – but from 10m to n.e. 20m                         m

 4.5.5    - ditto – but from 20m to n.e. 30m                         m

 4.5.6    - ditto – but from 30m to n.e. 40m                         m

 4.5.7    Carry out dissipation test.                               hrs


          Deep Sounding Test (Mechanical)

 4.5.9    Setting out of location, setting up, dismantling and      No.
          moving deep sounding machine or specified capacity
          and reaction on land.




                                                                           Carried Forward



                                                      8
NAME OF THE JOB.




BILL OF QUANTITIES NO. 4: IN-SITU TESTS (Continued)


 ITEM                         DESCRIPTION                              UNIT      QTY     RATE      AMOUNT
                                                                                          (RM)      (RM)
                                                   Brought Forward


 4.5.10     - ditto – but over soft/swampy ground, water log area      No.
            or shallow water where matting is required for
            movement and setting up.

 4.5.11     - ditto – but over deep water where fixed platform or      No.
            temporary floating platform is required.

 4.5.12     Carry out deep sounding test (mechanical), depth            m
            from ground level to not exceeding (n.e.) 10m.

 4.5.13     - ditto – but from 10m to n.e. 20m                          m

 4.5.14     - ditto – but from 20m to n.e. 30m                          m

 4.5.15     - ditto – but from 30m to n.e. 40m                          m


  4.6      Plate Bearing Tests

 4.6.1    Carry out plate bearing test of plate size of 762mm          No.
          diameter with loading to maximum pressure of 200kPa.
          Test shall be carried out as per BS 1377 or as directed
          by the Engineer.
          Two cycles of loading is required with first cycles of
          100kPa and second cycle of 200kPa. Second cycle of
          loading shall be maintained for 24 hours at the peak
          load.


  4.7     Footing Tests

 4.7.1    Test shall be carried out as per BS 1377 or as directed
          by the Engineer. When the final load increment has
          been applied and the immediate settlement has been
          measured, further measurements of settlement at
          suitable intervals of time up to a minimum period of at
          least 50 days shall be taken.

 4.7.2    To carry out 1220mm x 1220mm reinforced concrete             No.
          footing test including all required equipment, weights and
          handling all according to the specification or all as
          directed by the Engineer.


  4.8     PRESSUREMETER TESTS

                                                                              Carried to summary




                                                       9
NAME OF THE JOB.




BILL OF QUANTITIES NO. 5 : INSTRUMENTATION


 ITEM                         DESCRIPTION                           UNIT       QTY     RATE     AMOUNT
                                                                                       (RM)      (RM)

  5.0    Instrumentation

  5.1    Standpipe Piezometers

 5.1.1   Supply and install Standpipe Piezometer tip with           No.
         protective cover including concreting, sand filter, etc.

 5.1.2   Supply and install Piezometer tubing and specified          M
         backfill.

 5.1.3   Supply and installation of Piezometer Buckets complete     No.
         with weights, string etc.


  5.2    Standpipe

 5.2.1   Supply and install Standpipe tubing, specified backfill,    m
         sand filter, filter fabric, concrete, etc.


  5.3    Monitoring Water Level

 5.3.1   Monitoring water level in Standpipe Piezometer or in       Trip
         Standpipe with a dipmeter and in Piezometer Buckets
         for the duration of the soil investigation contract.


  5.4    Inclinometer




                                                                           Carried to summary




                                                       10
NAME OF THE JOB.




BILL OF QUANTITIES NO. 6: LABORATORY TESTS


ITEM                          DESCRIPTION                                UNIT     QTY   RATE   AMOUNT
                                                                                        (RM)    (RM)

 6.0     Laboratory Tests

         (Test method numbers are as per B.S. 1377:1990
         unless otherwise indicated).

 6.1     Classification Tests.

6.1.1    Moisture content (Method 3.2 B.S 1377: Part 2 : 1990)            No.

 6.1.2   Liquid Limit (Method 4.3 B.S 1377 : Part 2 : 1990)               No.

 6.1.3   Plastic Limit (Method 5.3 B.S 1377 : Part 2 : 1990)              No.

6.1.4    Specific Gravity (Method 8.2 or 8.3 or 8.4 B.S 137 :             No.
         Part 2 : 1990)

 6.1.5   Density / Bulk Density (Method 7.2 or 7.3 or 7.4 B.S 1377:       No.
         Part 2 : 1990)

 6.1.6   Particle size distribution for coarse-grained soils (Method      No.
         9.2 B.S 1377: Part 2: 1990)

6.1.7    Particle size distribution for fine-grained soils (Method 9.5    No.
         B.S 1377: Part 2: 1990)


 6.2     Soil Strength Tests

 6.2.1   Carry out strength tests on undisturbed samples

 6.2.2   One dimensional consolidation on undisturbed soil                No.
         sample (Method 3 B.S. 1377: Part 5: 1990)

 6.2.3   Isotropically Consolidated undrained triaxial compression       Series
         test on undisturbed soil sample with pore water pressure
         and volume change measurement on a set of 3 specimen
         of 50mm diameter (Method 7: B.S. 1377: Part 8: 1990)

 6.2.4   Unconsolidated undrained triaxial compression test on           Series
         undisturbed soil sample without pore water pressure and
         volume change measurement on a set of 3 specimen of
         50mm diameter (Method 8: B.S. 1377: Part 7: 1990)




                                                        11
NAME OF THE JOB.



                                                                               Carried Forward




BILL OF QUANTITIES NO. 6: LABORATORY TESTS (Continued)


 ITEM                         DESCRIPTION                           UNIT       QTY     RATE      AMOUNT
                                                                                        (RM)       (RM)
                                                 Brought Forward                                 8,700.00

 6.3     Rock Strength Test

 6.3.1   Carry out strength test on rock core samples. Unconfined   Series
         compressive strength of Rock Core Samples.

 6.4     Soil Chemical Test

 6.4.1   Organic matter content (Method 3: B.S 1377: Part 3:         No.
         1990)

 6.4.2   Sulphate content of ground water or soil (Method 5: B.S     No.
         1377: Part 3: 1990)

 6.4.3   pH value (Method 9: B.S 1377: Part 3: 1990)                 No.

 6.4.4   Chloride content (Method 7: B.S 1377: Part 3: 1990)         No.




                                                                           Carried to summary




                                                    12
NAME OF THE JOB.




GENERAL SUMMARY OF TENDER

 BILL
 NO.                                         DESCRIPTION                       PAGE NO.    AMOUNT
                                                                                            (RM)

    1              General Conditions and Preliminaries                   Page 1

    2              Boring and Coring                                      Page 2 - 3

    3              Sampling                                               Page 4 - 5

    4              In-situ Tests                                              Page 6 - 8

    5              Instrumentation                                            Page 9

    6              Laboratory Tests                                       Page 10 - 11




                                                             TOTAL TENDERED AMOUNT



Sum of Malaysian Ringgit : _______________________________________________________________



Contract No: _____________________________________ for the above works entered into on the day of

____/_______/ ________ by the undersigned parties refers to the Bill of Quantities and items included in this

General Summary which are shall be read and contrued as part of the said Contract.



Contractor




..........................................

Name:

Date:


Witness



..........................................

Name:

Date:
                                                                 13

More Related Content

What's hot

Standard bill of quantities
Standard bill of quantitiesStandard bill of quantities
Standard bill of quantitiesBt Lee
 
Estimating calculation
Estimating calculationEstimating calculation
Estimating calculationZIyeeTan
 
Final Bills of Quantity
Final Bills of QuantityFinal Bills of Quantity
Final Bills of QuantityArissa Loh
 
Mooc smm substructure_2
Mooc smm substructure_2Mooc smm substructure_2
Mooc smm substructure_2Azizan Supardi
 
Estimating calculation
Estimating calculationEstimating calculation
Estimating calculationZIyeeTan
 
Kadar denda dan gantirugi ditetapkan (LAD)
Kadar denda dan gantirugi ditetapkan (LAD)Kadar denda dan gantirugi ditetapkan (LAD)
Kadar denda dan gantirugi ditetapkan (LAD)sofyan fatimi
 
Scale of fees (rev. 2004)
Scale of fees (rev. 2004)Scale of fees (rev. 2004)
Scale of fees (rev. 2004)helmie84
 
Building technology 1 "Industrialized Building System" IBS
Building technology 1 "Industrialized Building System" IBSBuilding technology 1 "Industrialized Building System" IBS
Building technology 1 "Industrialized Building System" IBSDigital Space Consultancy Ltd
 
Smm2 second edition
Smm2 second editionSmm2 second edition
Smm2 second editionBt Lee
 
Group Assignment:IBS System
Group Assignment:IBS SystemGroup Assignment:IBS System
Group Assignment:IBS System마 이환
 
Sgp4813 measurement of quantities
Sgp4813 measurement of quantitiesSgp4813 measurement of quantities
Sgp4813 measurement of quantitiesalanchong88
 
Tender evaluation procedure
Tender evaluation procedureTender evaluation procedure
Tender evaluation procedureayushida
 
Assignment - Preliminary Cost Appraisal
Assignment - Preliminary Cost AppraisalAssignment - Preliminary Cost Appraisal
Assignment - Preliminary Cost AppraisalKai Yun Pang
 
Dokumen 132017 contoh bq
Dokumen 132017 contoh bqDokumen 132017 contoh bq
Dokumen 132017 contoh bqNoorHaliza4
 
Measurement II BQ
Measurement II BQMeasurement II BQ
Measurement II BQashleyyeap
 
Sgp4813 measurement of quantities
Sgp4813 measurement of quantitiesSgp4813 measurement of quantities
Sgp4813 measurement of quantitiesalanchong88
 
Building Technology I : Project 1 : IBS
Building Technology I : Project 1 : IBSBuilding Technology I : Project 1 : IBS
Building Technology I : Project 1 : IBSJing Fan Koh
 

What's hot (20)

Spun pile
Spun pileSpun pile
Spun pile
 
bs:copbs101
bs:copbs101bs:copbs101
bs:copbs101
 
Standard bill of quantities
Standard bill of quantitiesStandard bill of quantities
Standard bill of quantities
 
Estimating calculation
Estimating calculationEstimating calculation
Estimating calculation
 
Final Bills of Quantity
Final Bills of QuantityFinal Bills of Quantity
Final Bills of Quantity
 
Mooc smm substructure_2
Mooc smm substructure_2Mooc smm substructure_2
Mooc smm substructure_2
 
Estimating calculation
Estimating calculationEstimating calculation
Estimating calculation
 
Kadar denda dan gantirugi ditetapkan (LAD)
Kadar denda dan gantirugi ditetapkan (LAD)Kadar denda dan gantirugi ditetapkan (LAD)
Kadar denda dan gantirugi ditetapkan (LAD)
 
Scale of fees (rev. 2004)
Scale of fees (rev. 2004)Scale of fees (rev. 2004)
Scale of fees (rev. 2004)
 
Building technology 1 "Industrialized Building System" IBS
Building technology 1 "Industrialized Building System" IBSBuilding technology 1 "Industrialized Building System" IBS
Building technology 1 "Industrialized Building System" IBS
 
Smm2 second edition
Smm2 second editionSmm2 second edition
Smm2 second edition
 
Pp2 chapter 1 cheeyong & yih shyang
Pp2 chapter 1 cheeyong & yih shyangPp2 chapter 1 cheeyong & yih shyang
Pp2 chapter 1 cheeyong & yih shyang
 
Group Assignment:IBS System
Group Assignment:IBS SystemGroup Assignment:IBS System
Group Assignment:IBS System
 
Sgp4813 measurement of quantities
Sgp4813 measurement of quantitiesSgp4813 measurement of quantities
Sgp4813 measurement of quantities
 
Tender evaluation procedure
Tender evaluation procedureTender evaluation procedure
Tender evaluation procedure
 
Assignment - Preliminary Cost Appraisal
Assignment - Preliminary Cost AppraisalAssignment - Preliminary Cost Appraisal
Assignment - Preliminary Cost Appraisal
 
Dokumen 132017 contoh bq
Dokumen 132017 contoh bqDokumen 132017 contoh bq
Dokumen 132017 contoh bq
 
Measurement II BQ
Measurement II BQMeasurement II BQ
Measurement II BQ
 
Sgp4813 measurement of quantities
Sgp4813 measurement of quantitiesSgp4813 measurement of quantities
Sgp4813 measurement of quantities
 
Building Technology I : Project 1 : IBS
Building Technology I : Project 1 : IBSBuilding Technology I : Project 1 : IBS
Building Technology I : Project 1 : IBS
 

Similar to Bq preamble

Rev 01 dt 01.03.2010 - soil investigation
Rev 01 dt 01.03.2010 - soil investigationRev 01 dt 01.03.2010 - soil investigation
Rev 01 dt 01.03.2010 - soil investigationSiddhartha Bhamidipati
 
Bs 1881 122(1) 1983
Bs 1881 122(1) 1983Bs 1881 122(1) 1983
Bs 1881 122(1) 1983EPMC TUNISIA
 
TL_Cons_present_Kishanpur_20[1].08.09.ppt
TL_Cons_present_Kishanpur_20[1].08.09.pptTL_Cons_present_Kishanpur_20[1].08.09.ppt
TL_Cons_present_Kishanpur_20[1].08.09.pptAshokKumar561399
 
Directive008
Directive008Directive008
Directive008Billy321
 
Vem case studies - Premix system
Vem case studies - Premix systemVem case studies - Premix system
Vem case studies - Premix systemfrancescavem
 
A REVIEW OF VARIOUS SOIL MOISTUREMEASUREMENT TECHNIQUES
A REVIEW OF VARIOUS SOIL MOISTUREMEASUREMENT TECHNIQUESA REVIEW OF VARIOUS SOIL MOISTUREMEASUREMENT TECHNIQUES
A REVIEW OF VARIOUS SOIL MOISTUREMEASUREMENT TECHNIQUESBhushan Patil
 
SOIL STABILITY INVESTIGATION WITH POLYETHYLENE (LDPE) USING LIME
SOIL STABILITY INVESTIGATION WITH POLYETHYLENE (LDPE) USING LIMESOIL STABILITY INVESTIGATION WITH POLYETHYLENE (LDPE) USING LIME
SOIL STABILITY INVESTIGATION WITH POLYETHYLENE (LDPE) USING LIMEIRJET Journal
 
Design Philosophy and Material Choice for a Tuner in an Electromagnetic Rever...
Design Philosophy and Material Choice for a Tuner in an Electromagnetic Rever...Design Philosophy and Material Choice for a Tuner in an Electromagnetic Rever...
Design Philosophy and Material Choice for a Tuner in an Electromagnetic Rever...Sarah Belkhamsa
 
GEOSYNTHETIC TESTING TECHNIQUES
GEOSYNTHETIC TESTING TECHNIQUESGEOSYNTHETIC TESTING TECHNIQUES
GEOSYNTHETIC TESTING TECHNIQUESCBRI-CSIR
 
PLAIN AND REINFORCED CONRETE (LAB MANUAL)
PLAIN AND REINFORCED CONRETE (LAB MANUAL)PLAIN AND REINFORCED CONRETE (LAB MANUAL)
PLAIN AND REINFORCED CONRETE (LAB MANUAL)Hamza Waheed
 
Activated sludge process design
Activated sludge process designActivated sludge process design
Activated sludge process designmohamedradi
 
goaves effect on subsidence
goaves effect on subsidencegoaves effect on subsidence
goaves effect on subsidenceVR M
 

Similar to Bq preamble (20)

Rev 01 dt 01.03.2010 - soil investigation
Rev 01 dt 01.03.2010 - soil investigationRev 01 dt 01.03.2010 - soil investigation
Rev 01 dt 01.03.2010 - soil investigation
 
784
784784
784
 
Bs 1881 122(1) 1983
Bs 1881 122(1) 1983Bs 1881 122(1) 1983
Bs 1881 122(1) 1983
 
Report1
Report1Report1
Report1
 
TL_Cons_present_Kishanpur_20[1].08.09.ppt
TL_Cons_present_Kishanpur_20[1].08.09.pptTL_Cons_present_Kishanpur_20[1].08.09.ppt
TL_Cons_present_Kishanpur_20[1].08.09.ppt
 
Directive008
Directive008Directive008
Directive008
 
Vod
VodVod
Vod
 
Vem case studies - Premix system
Vem case studies - Premix systemVem case studies - Premix system
Vem case studies - Premix system
 
A REVIEW OF VARIOUS SOIL MOISTUREMEASUREMENT TECHNIQUES
A REVIEW OF VARIOUS SOIL MOISTUREMEASUREMENT TECHNIQUESA REVIEW OF VARIOUS SOIL MOISTUREMEASUREMENT TECHNIQUES
A REVIEW OF VARIOUS SOIL MOISTUREMEASUREMENT TECHNIQUES
 
SOIL STABILITY INVESTIGATION WITH POLYETHYLENE (LDPE) USING LIME
SOIL STABILITY INVESTIGATION WITH POLYETHYLENE (LDPE) USING LIMESOIL STABILITY INVESTIGATION WITH POLYETHYLENE (LDPE) USING LIME
SOIL STABILITY INVESTIGATION WITH POLYETHYLENE (LDPE) USING LIME
 
Design Philosophy and Material Choice for a Tuner in an Electromagnetic Rever...
Design Philosophy and Material Choice for a Tuner in an Electromagnetic Rever...Design Philosophy and Material Choice for a Tuner in an Electromagnetic Rever...
Design Philosophy and Material Choice for a Tuner in an Electromagnetic Rever...
 
2542 1 1
2542 1 12542 1 1
2542 1 1
 
1200 1
1200 11200 1
1200 1
 
Digester Feed
Digester FeedDigester Feed
Digester Feed
 
GEOSYNTHETIC TESTING TECHNIQUES
GEOSYNTHETIC TESTING TECHNIQUESGEOSYNTHETIC TESTING TECHNIQUES
GEOSYNTHETIC TESTING TECHNIQUES
 
hd2594 (8).pdf
hd2594 (8).pdfhd2594 (8).pdf
hd2594 (8).pdf
 
SPT and VST- By Daanyal Umar.pptx
SPT and VST- By Daanyal Umar.pptxSPT and VST- By Daanyal Umar.pptx
SPT and VST- By Daanyal Umar.pptx
 
PLAIN AND REINFORCED CONRETE (LAB MANUAL)
PLAIN AND REINFORCED CONRETE (LAB MANUAL)PLAIN AND REINFORCED CONRETE (LAB MANUAL)
PLAIN AND REINFORCED CONRETE (LAB MANUAL)
 
Activated sludge process design
Activated sludge process designActivated sludge process design
Activated sludge process design
 
goaves effect on subsidence
goaves effect on subsidencegoaves effect on subsidence
goaves effect on subsidence
 

Recently uploaded

Incoming and Outgoing Shipments in 2 STEPS Using Odoo 17
Incoming and Outgoing Shipments in 2 STEPS Using Odoo 17Incoming and Outgoing Shipments in 2 STEPS Using Odoo 17
Incoming and Outgoing Shipments in 2 STEPS Using Odoo 17Celine George
 
ppt your views.ppt your views of your college in your eyes
ppt your views.ppt your views of your college in your eyesppt your views.ppt your views of your college in your eyes
ppt your views.ppt your views of your college in your eyesashishpaul799
 
....................Muslim-Law notes.pdf
....................Muslim-Law notes.pdf....................Muslim-Law notes.pdf
....................Muslim-Law notes.pdfVikramadityaRaj
 
Dementia (Alzheimer & vasular dementia).
Dementia (Alzheimer & vasular dementia).Dementia (Alzheimer & vasular dementia).
Dementia (Alzheimer & vasular dementia).Mohamed Rizk Khodair
 
Basic_QTL_Marker-assisted_Selection_Sourabh.ppt
Basic_QTL_Marker-assisted_Selection_Sourabh.pptBasic_QTL_Marker-assisted_Selection_Sourabh.ppt
Basic_QTL_Marker-assisted_Selection_Sourabh.pptSourabh Kumar
 
Championnat de France de Tennis de table/
Championnat de France de Tennis de table/Championnat de France de Tennis de table/
Championnat de France de Tennis de table/siemaillard
 
Matatag-Curriculum and the 21st Century Skills Presentation.pptx
Matatag-Curriculum and the 21st Century Skills Presentation.pptxMatatag-Curriculum and the 21st Century Skills Presentation.pptx
Matatag-Curriculum and the 21st Century Skills Presentation.pptxJenilouCasareno
 
Benefits and Challenges of Using Open Educational Resources
Benefits and Challenges of Using Open Educational ResourcesBenefits and Challenges of Using Open Educational Resources
Benefits and Challenges of Using Open Educational Resourcesdimpy50
 
How to Manage Notification Preferences in the Odoo 17
How to Manage Notification Preferences in the Odoo 17How to Manage Notification Preferences in the Odoo 17
How to Manage Notification Preferences in the Odoo 17Celine George
 
Post Exam Fun(da) Intra UEM General Quiz 2024 - Prelims q&a.pdf
Post Exam Fun(da) Intra UEM General Quiz 2024 - Prelims q&a.pdfPost Exam Fun(da) Intra UEM General Quiz 2024 - Prelims q&a.pdf
Post Exam Fun(da) Intra UEM General Quiz 2024 - Prelims q&a.pdfPragya - UEM Kolkata Quiz Club
 
The Last Leaf, a short story by O. Henry
The Last Leaf, a short story by O. HenryThe Last Leaf, a short story by O. Henry
The Last Leaf, a short story by O. HenryEugene Lysak
 
Students, digital devices and success - Andreas Schleicher - 27 May 2024..pptx
Students, digital devices and success - Andreas Schleicher - 27 May 2024..pptxStudents, digital devices and success - Andreas Schleicher - 27 May 2024..pptx
Students, digital devices and success - Andreas Schleicher - 27 May 2024..pptxEduSkills OECD
 
Application of Matrices in real life. Presentation on application of matrices
Application of Matrices in real life. Presentation on application of matricesApplication of Matrices in real life. Presentation on application of matrices
Application of Matrices in real life. Presentation on application of matricesRased Khan
 
The Art Pastor's Guide to Sabbath | Steve Thomason
The Art Pastor's Guide to Sabbath | Steve ThomasonThe Art Pastor's Guide to Sabbath | Steve Thomason
The Art Pastor's Guide to Sabbath | Steve ThomasonSteve Thomason
 
Salient features of Environment protection Act 1986.pptx
Salient features of Environment protection Act 1986.pptxSalient features of Environment protection Act 1986.pptx
Salient features of Environment protection Act 1986.pptxakshayaramakrishnan21
 
INU_CAPSTONEDESIGN_비밀번호486_업로드용 발표자료.pdf
INU_CAPSTONEDESIGN_비밀번호486_업로드용 발표자료.pdfINU_CAPSTONEDESIGN_비밀번호486_업로드용 발표자료.pdf
INU_CAPSTONEDESIGN_비밀번호486_업로드용 발표자료.pdfbu07226
 

Recently uploaded (20)

Incoming and Outgoing Shipments in 2 STEPS Using Odoo 17
Incoming and Outgoing Shipments in 2 STEPS Using Odoo 17Incoming and Outgoing Shipments in 2 STEPS Using Odoo 17
Incoming and Outgoing Shipments in 2 STEPS Using Odoo 17
 
Word Stress rules esl .pptx
Word Stress rules esl               .pptxWord Stress rules esl               .pptx
Word Stress rules esl .pptx
 
ppt your views.ppt your views of your college in your eyes
ppt your views.ppt your views of your college in your eyesppt your views.ppt your views of your college in your eyes
ppt your views.ppt your views of your college in your eyes
 
....................Muslim-Law notes.pdf
....................Muslim-Law notes.pdf....................Muslim-Law notes.pdf
....................Muslim-Law notes.pdf
 
Dementia (Alzheimer & vasular dementia).
Dementia (Alzheimer & vasular dementia).Dementia (Alzheimer & vasular dementia).
Dementia (Alzheimer & vasular dementia).
 
NCERT Solutions Power Sharing Class 10 Notes pdf
NCERT Solutions Power Sharing Class 10 Notes pdfNCERT Solutions Power Sharing Class 10 Notes pdf
NCERT Solutions Power Sharing Class 10 Notes pdf
 
Basic_QTL_Marker-assisted_Selection_Sourabh.ppt
Basic_QTL_Marker-assisted_Selection_Sourabh.pptBasic_QTL_Marker-assisted_Selection_Sourabh.ppt
Basic_QTL_Marker-assisted_Selection_Sourabh.ppt
 
Championnat de France de Tennis de table/
Championnat de France de Tennis de table/Championnat de France de Tennis de table/
Championnat de France de Tennis de table/
 
Matatag-Curriculum and the 21st Century Skills Presentation.pptx
Matatag-Curriculum and the 21st Century Skills Presentation.pptxMatatag-Curriculum and the 21st Century Skills Presentation.pptx
Matatag-Curriculum and the 21st Century Skills Presentation.pptx
 
Benefits and Challenges of Using Open Educational Resources
Benefits and Challenges of Using Open Educational ResourcesBenefits and Challenges of Using Open Educational Resources
Benefits and Challenges of Using Open Educational Resources
 
How to Manage Notification Preferences in the Odoo 17
How to Manage Notification Preferences in the Odoo 17How to Manage Notification Preferences in the Odoo 17
How to Manage Notification Preferences in the Odoo 17
 
Post Exam Fun(da) Intra UEM General Quiz 2024 - Prelims q&a.pdf
Post Exam Fun(da) Intra UEM General Quiz 2024 - Prelims q&a.pdfPost Exam Fun(da) Intra UEM General Quiz 2024 - Prelims q&a.pdf
Post Exam Fun(da) Intra UEM General Quiz 2024 - Prelims q&a.pdf
 
The Last Leaf, a short story by O. Henry
The Last Leaf, a short story by O. HenryThe Last Leaf, a short story by O. Henry
The Last Leaf, a short story by O. Henry
 
“O BEIJO” EM ARTE .
“O BEIJO” EM ARTE                       .“O BEIJO” EM ARTE                       .
“O BEIJO” EM ARTE .
 
Students, digital devices and success - Andreas Schleicher - 27 May 2024..pptx
Students, digital devices and success - Andreas Schleicher - 27 May 2024..pptxStudents, digital devices and success - Andreas Schleicher - 27 May 2024..pptx
Students, digital devices and success - Andreas Schleicher - 27 May 2024..pptx
 
Application of Matrices in real life. Presentation on application of matrices
Application of Matrices in real life. Presentation on application of matricesApplication of Matrices in real life. Presentation on application of matrices
Application of Matrices in real life. Presentation on application of matrices
 
The Art Pastor's Guide to Sabbath | Steve Thomason
The Art Pastor's Guide to Sabbath | Steve ThomasonThe Art Pastor's Guide to Sabbath | Steve Thomason
The Art Pastor's Guide to Sabbath | Steve Thomason
 
Operations Management - Book1.p - Dr. Abdulfatah A. Salem
Operations Management - Book1.p  - Dr. Abdulfatah A. SalemOperations Management - Book1.p  - Dr. Abdulfatah A. Salem
Operations Management - Book1.p - Dr. Abdulfatah A. Salem
 
Salient features of Environment protection Act 1986.pptx
Salient features of Environment protection Act 1986.pptxSalient features of Environment protection Act 1986.pptx
Salient features of Environment protection Act 1986.pptx
 
INU_CAPSTONEDESIGN_비밀번호486_업로드용 발표자료.pdf
INU_CAPSTONEDESIGN_비밀번호486_업로드용 발표자료.pdfINU_CAPSTONEDESIGN_비밀번호486_업로드용 발표자료.pdf
INU_CAPSTONEDESIGN_비밀번호486_업로드용 발표자료.pdf
 

Bq preamble

  • 1. NAME OF THE JOB. PREAMBLE TO BILL OF QUANTITIES 1. Rates for mobilization to the site includes mobilization all and every equipment, ancillaries and everything required for these works unless provided for elsewhere and including distance traveled and allowance for difficulties of access all and everything. 2. Setting up at location includes provisition of stable working plateform or otherwise to suit the type of test this item applies to 3. Rate for boring and drilling includes provision of clean water or clean water with additives as approved by the SO and usage of compatible rods, core barrels and drill and core bits to suit the ground conditions and delivery of rock cores including core boxes. 4. Rates for sampling includes proper packing, storage and delivery of samples 5. Rates for undisturbed samples includes usage of proprietary sample tubes without burrs or seams and used without adapters, sealing, storage and safe delivery 6. Standard Penetration test includes usage of proper rods, split spoon as per MS___ , sample description in accordance with MS___ and packing, storing and transporting. 7. Rate for vane test includes type of vane and equipment used to provide reliable test results. 8. Setting up of CPT or Piezeocone over soft ground or water includes for provision of suitable stable plateform for the purpose 1
  • 2. NAME OF THE JOB. BILL OF QUANTITIES NO. 1 : PRELIMINARIES ITEM DESCRIPTION UNIT QTY RATE AMOUNT (RM) (RM) 1.0 Preliminaries 1.1 Allow for compliance with specifications and conditions of Lump the contract. sum 1.2 Allow for compliance with all other requirements under Lump the contract. sum 1.3 Allow for provision of full time professional attendance Lump on site for the duration of the site operations. sum 1.4 Allow for provision of two (2) number copies of Interim Lump Factual Report. sum 1.5 Allow for provision of six (6) number copies of complete Lump Final Factual Report, one compiled and bound set of all sum raw field and Laboratory sheets and one copy of factual Report in electronics format. 1.6 Allow for Licensed Surveyor for setting up of all test Lump locations and taking of levels. sum 1.7 Allow for provision of photographs in electronic format as Lump per this specifications. Sum 1.8 Provide additional copies of final factual report. No. Rate - Only Carried to summary 2
  • 3. NAME OF THE JOB. BILL OF QUANTITIES NO. 2 : BORING AND CORING ITEM DESCRIPTION UNIT QTY RATE AMOUNT (RM) (RM) 2.0 Boring and Coring 2.1 Mobilisation of Boring Plants and all and every required Lump ancillaries to complete works under this contract to the Sum site including erecting the plants at the First borehole location if necessary, staging on barges or any other means of supporting and stabilising the boring plant above water level, erecting, dismantling and demobilisation from the site after completion of works. 2.1.1 Extra over above for Air/Foam Drilling Plant and Ancillaries. 2.1.2 Moving the plant from each position to the next No. including, if necessary, dismantling and re-erecting on ground or on supports in Item 2.1 above, including the provision of any staging if necessary for test location on land. 2.1.3 - ditto – but for test location over water on very soft grounds requiring special staging. 2.1.4 Extra over for Air/Foam Drilling Plant and Ancillaries 2.2 Boring in Soil 2.2.1 Carry out borings in soils as per Specification whether cased or uncased including the provision of "disturbed samples", delivery to the testing laboratory, and as directed by S.O.:- 2.2.2 Depth from natural ground or water bed level not m exceeding 10m. 2.2.3 - ditto - exceeding 10 and not exceeding 20m m 2.2.4 - ditto - exceeding 20m and not exceeding 30m m 2.2.5 - ditto - exceeding 30m and not exceeding 40m m 2.2.6 - ditto - exceeding 40m and not exceeding 50m m 2.2.7 Extra over item 2.3.1 to 2.3.5 for where air foam is used m Carried Forward 3
  • 4. NAME OF THE JOB. BILL OF QUANTITIES NO. 2 : BORING AND CORING (Continued) ITEM DESCRIPTION UNIT QTY RATE AMOUNT (RM) (RM) Brought Forward 2.3 Drilling in Rock 2.3.1 Carrying out coring to core size 52mm nominal diameter in rock including extraction of complete cores, core box and delivery to the testing laboratory or to location specified by S.O. as per Specification:- 2.3.2 Depth from natural ground or water bed level not m exceeding 10m. 2.3.3 - ditto - exceeding 10 and not exceeding 20m m 2.3.4 - ditto - exceeding 20m and not exceeding 30m m 2.3.5 - ditto - exceeding 30m and not exceeding 40m m 2.3.6 - ditto - exceeding 40m m 2.3.7 Extra over item 2.6.1 to 2.6.5 where air foam is used m 2.4 Test/Trial Pit 2.4.1 Excavate trial/test pit in soil to depth not exceeding 2m No. below ground level. Rate to include necessary timbering dewatering, and backfilling after excavation. Detail geological logging of pit face and base including provision for photograph 2.4.2 - ditto – but 2m to n.e. 4m. No. 2.5 Hand Augering 2.5.1 Carry out hand auger including the provision of m collecting disturbed samples, depth from ground level to not exceeding (n.e.) 3.5m 2.5.2 - ditto – but 3.5m to n.e. 7m m Carried to summary 4
  • 5. NAME OF THE JOB. BILL OF QUANTITIES NO. 3 : SAMPLING ITEM DESCRIPTION UNIT QTY RATE AMOUNT (RM) (RM) 3.0 Sampling 3.1 Small Disturbed Samples 3.1.1 Obtain 1kg small disturbed samples with split-barrel No. tubes or otherwise, depth from ground level to not exceeding (n. e.) 10m.ckfilling after excavation. 3.1.2 - ditto – but 10m to n.e. 20m No. 3.1.3 - ditto – but 20m to n.e. 30m No. 3.1.4 - ditto – but 30m to n.e. 40m No. 3.1.5 - ditto – but exceeding 40m No. 3.2 Undisturbed Samples 3.2.1 Obtain undisturbed soil samples as per specifications and deliver to the testing laboratory. 3.2.2 Depth from natural ground or water bed level exceeding No not exceeding 10m 3.2.3 - ditto - exceeding 10 and not exceeding 20m No. 3.2.4 - ditto - exceeding 20m and not exceeding 30m No. 3.2.5 - ditto - exceeding 30m and not exceeding 40m No. 3.3 Undisturbed Samples (Piston Sampler) 3.3.1 Obtain undisturbed samples with stationery piston No. sampler from the bottom of borehole, depth from ground level to not exceeding (n.e.) 10m. 3.3.2 - ditto – but 10m to n.e. 20m No. 3.3.3 - ditto – but 20m to n.e. 30m No. 3.3.4 - ditto – but exceeding 30m No. Carried Forward 5
  • 6. NAME OF THE JOB. BILL OF QUANTITIES NO. 3: SAMPLING (Continued) ITEM DESCRIPTION UNIT QTY RATE AMOUNT (RM) (RM) Brought Forward 3.4 Undisturbed Block Samples 3.4.1 Obtain Undisturbed 300mm cube sample in wooden No. packing at depth not exceeding 4.0m and insitu handvane and hand penetrometer testing at 0.3m interval to 4.0m. 3.5 Bulk Disturbed Samples 3.5.1 Obtain 45kg bulk disturbed samples from percussion No. borehole, depth from ground level to not exceeding (n.e.) 10m 3.6 Water Sample 3.6.1 Collect representative ground water sample from the No. borehole as per specification or as directed by. S.O. and deliver to the testing laboratory Carried to summary 6
  • 7. NAME OF THE JOB. BILL OF QUANTITIES NO. 4: IN-SITU TESTS ITEM DESCRIPTION UNIT QTY RATE AMOUNT (RM) (RM) 4.0 In-situ Tests 4.1 Standard Penetration Tests 4.1.1 Carrying out Standard Penetration Test and obtaining disturbed samples including packaging and transport as per Specification:- 4.1.2 Depth measured from natural ground or water bed level No. not exceeding 10m. 4.1.3 - ditto - exceeding 10 and not exceeding 20m No. 4.1.4 - ditto - exceeding 20m and not exceeding 30m No. 4.1.5 - ditto - exceeding 30m and not exceeding 40m No. 4.1.6 - ditto - exceeding 40m and not exceeding 50m No. 4.2 Vane Shear Tests In Borehole 4.2.1 Carrying out Vane Shear Test and including disturbed samples as per Specification:- 4.2.2 Depth measured from natural ground or water bed level No. not exceeding 10m. 4.2.3 - ditto - exceeding 10 and not exceeding 20m No. 4.2.4 - ditto - exceeding 20m and not exceeding 30m No. 4.2.5 - ditto - exceeding 30m and not exceeding 40m No. 4.2.6 - ditto - exceeding 40m and not exceeding 50m No. - 4.3 Penetration Field Vane Test 4.3.1 Setting out of location, setting up, dismantling and moving equipment for penetration vane test on land. 4.3.2 - ditto but over swampy ground or water log area No. 4.3.3 Advance vane, depth from ground level to not m Exceeding (n.e.) 10m. Carried Forward 4,700.00 7
  • 8. NAME OF THE JOB. BILL OF QUANTITIES NO. 4: IN-SITU TESTS (Continued) ITEM DESCRIPTION UNIT QTY RATE AMOUNT (RM) (RM) Brought Forward 4.3.4 - ditto – but from 10m to n. e. 20m. m 4.3.5 - ditto – but from 20m to n. e. 30m. m 4.3.6 Carry out field Vane Test No. 4.4 “Mackintosh” Probes 4.4.1 Carrying out “Mackintosh” Probes as per Specification No. to maximum depth from natural ground or water bed not to exceed 20m or 300 blow/300mm whichever comes first. 4.5 Deep Sounding Test (Piezocone) 4.5.1 Setting out of location, setting up, dismantling and No. moving deep sounding machine of specified capacity and reaction on land. 4.5.2 - ditto – but over soft/swampy ground, water loggged No. areas or over water. 4.5.3 Carry out deep sounding test (piezocone), depth from m ground level to not exceeding (n.e.) 10m. 4.5.4 - ditto – but from 10m to n.e. 20m m 4.5.5 - ditto – but from 20m to n.e. 30m m 4.5.6 - ditto – but from 30m to n.e. 40m m 4.5.7 Carry out dissipation test. hrs Deep Sounding Test (Mechanical) 4.5.9 Setting out of location, setting up, dismantling and No. moving deep sounding machine or specified capacity and reaction on land. Carried Forward 8
  • 9. NAME OF THE JOB. BILL OF QUANTITIES NO. 4: IN-SITU TESTS (Continued) ITEM DESCRIPTION UNIT QTY RATE AMOUNT (RM) (RM) Brought Forward 4.5.10 - ditto – but over soft/swampy ground, water log area No. or shallow water where matting is required for movement and setting up. 4.5.11 - ditto – but over deep water where fixed platform or No. temporary floating platform is required. 4.5.12 Carry out deep sounding test (mechanical), depth m from ground level to not exceeding (n.e.) 10m. 4.5.13 - ditto – but from 10m to n.e. 20m m 4.5.14 - ditto – but from 20m to n.e. 30m m 4.5.15 - ditto – but from 30m to n.e. 40m m 4.6 Plate Bearing Tests 4.6.1 Carry out plate bearing test of plate size of 762mm No. diameter with loading to maximum pressure of 200kPa. Test shall be carried out as per BS 1377 or as directed by the Engineer. Two cycles of loading is required with first cycles of 100kPa and second cycle of 200kPa. Second cycle of loading shall be maintained for 24 hours at the peak load. 4.7 Footing Tests 4.7.1 Test shall be carried out as per BS 1377 or as directed by the Engineer. When the final load increment has been applied and the immediate settlement has been measured, further measurements of settlement at suitable intervals of time up to a minimum period of at least 50 days shall be taken. 4.7.2 To carry out 1220mm x 1220mm reinforced concrete No. footing test including all required equipment, weights and handling all according to the specification or all as directed by the Engineer. 4.8 PRESSUREMETER TESTS Carried to summary 9
  • 10. NAME OF THE JOB. BILL OF QUANTITIES NO. 5 : INSTRUMENTATION ITEM DESCRIPTION UNIT QTY RATE AMOUNT (RM) (RM) 5.0 Instrumentation 5.1 Standpipe Piezometers 5.1.1 Supply and install Standpipe Piezometer tip with No. protective cover including concreting, sand filter, etc. 5.1.2 Supply and install Piezometer tubing and specified M backfill. 5.1.3 Supply and installation of Piezometer Buckets complete No. with weights, string etc. 5.2 Standpipe 5.2.1 Supply and install Standpipe tubing, specified backfill, m sand filter, filter fabric, concrete, etc. 5.3 Monitoring Water Level 5.3.1 Monitoring water level in Standpipe Piezometer or in Trip Standpipe with a dipmeter and in Piezometer Buckets for the duration of the soil investigation contract. 5.4 Inclinometer Carried to summary 10
  • 11. NAME OF THE JOB. BILL OF QUANTITIES NO. 6: LABORATORY TESTS ITEM DESCRIPTION UNIT QTY RATE AMOUNT (RM) (RM) 6.0 Laboratory Tests (Test method numbers are as per B.S. 1377:1990 unless otherwise indicated). 6.1 Classification Tests. 6.1.1 Moisture content (Method 3.2 B.S 1377: Part 2 : 1990) No. 6.1.2 Liquid Limit (Method 4.3 B.S 1377 : Part 2 : 1990) No. 6.1.3 Plastic Limit (Method 5.3 B.S 1377 : Part 2 : 1990) No. 6.1.4 Specific Gravity (Method 8.2 or 8.3 or 8.4 B.S 137 : No. Part 2 : 1990) 6.1.5 Density / Bulk Density (Method 7.2 or 7.3 or 7.4 B.S 1377: No. Part 2 : 1990) 6.1.6 Particle size distribution for coarse-grained soils (Method No. 9.2 B.S 1377: Part 2: 1990) 6.1.7 Particle size distribution for fine-grained soils (Method 9.5 No. B.S 1377: Part 2: 1990) 6.2 Soil Strength Tests 6.2.1 Carry out strength tests on undisturbed samples 6.2.2 One dimensional consolidation on undisturbed soil No. sample (Method 3 B.S. 1377: Part 5: 1990) 6.2.3 Isotropically Consolidated undrained triaxial compression Series test on undisturbed soil sample with pore water pressure and volume change measurement on a set of 3 specimen of 50mm diameter (Method 7: B.S. 1377: Part 8: 1990) 6.2.4 Unconsolidated undrained triaxial compression test on Series undisturbed soil sample without pore water pressure and volume change measurement on a set of 3 specimen of 50mm diameter (Method 8: B.S. 1377: Part 7: 1990) 11
  • 12. NAME OF THE JOB. Carried Forward BILL OF QUANTITIES NO. 6: LABORATORY TESTS (Continued) ITEM DESCRIPTION UNIT QTY RATE AMOUNT (RM) (RM) Brought Forward 8,700.00 6.3 Rock Strength Test 6.3.1 Carry out strength test on rock core samples. Unconfined Series compressive strength of Rock Core Samples. 6.4 Soil Chemical Test 6.4.1 Organic matter content (Method 3: B.S 1377: Part 3: No. 1990) 6.4.2 Sulphate content of ground water or soil (Method 5: B.S No. 1377: Part 3: 1990) 6.4.3 pH value (Method 9: B.S 1377: Part 3: 1990) No. 6.4.4 Chloride content (Method 7: B.S 1377: Part 3: 1990) No. Carried to summary 12
  • 13. NAME OF THE JOB. GENERAL SUMMARY OF TENDER BILL NO. DESCRIPTION PAGE NO. AMOUNT (RM) 1 General Conditions and Preliminaries Page 1 2 Boring and Coring Page 2 - 3 3 Sampling Page 4 - 5 4 In-situ Tests Page 6 - 8 5 Instrumentation Page 9 6 Laboratory Tests Page 10 - 11 TOTAL TENDERED AMOUNT Sum of Malaysian Ringgit : _______________________________________________________________ Contract No: _____________________________________ for the above works entered into on the day of ____/_______/ ________ by the undersigned parties refers to the Bill of Quantities and items included in this General Summary which are shall be read and contrued as part of the said Contract. Contractor .......................................... Name: Date: Witness .......................................... Name: Date: 13