SlideShare a Scribd company logo
1 of 94
Download to read offline
1
Project Risk Management
Chapter 11
2
 Risk & Hazard
 Definitions.
 11.1 Plan Risk Management
 11.2 Identify Risk
 11.3 Perform Qualitative Risk Analysis
 11.4 Perform Quantitative Risk Analysis
 11.5 Plan Risk Response
KEY TERMS
3
Risk )Uncertainty(
Threats……Opportunities
Hazard
Project Risk Management
3
Knowledge
Area
Process
Initiating Planning Executing
Monitoring &
Control
Closing
Human
Resource
11.1 Plan Risk Management
11.2 Identify Risk
11.3 Perform Qualitative Risk
Analysis
11.4 Perform Quantitative Risk
Analysis
11.5 Plan Risk Response
11.6 control risk
Enter phase/
Start project
Exit phase/
End project
Initiating
Processes
Closing
Processes
Planning
Processes
Executing
Processes
Monitoring &
Controlling Processes
5
11.1 Plan Risk Management
The process of defining how to conduct risk
management activities for a project.
11.2 Identify Risks
The process of determining which risks may affect
the project and documenting their characteristics.
11.3 Perform Qualitative Risk Analysis
The process of prioritizing risks for further analysis
or action by assessing and combining their
probability of occurrence and impact.
6
11.4 Perform Quantitative Risk Analysis
The process of numerically analyzing the effect of
identified risks on overall project objectives.
11.5 Plan Risk Responses
The process of developing options and actions to
enhance opportunities and to reduce threats to
project objectives.
11.6 Control Risks
The process of implementing risk response plans,
tracking identified risks, monitoring residual risks,
identifying new risks, and evaluating risk process
effectiveness throughout the project.
7
Risk Factors
1. The probability that a risk event will occur
(how likely)
2. The range of possible outcomes
(impact or amount at stake)
3. Expected timing for it to occur in the project life
cycle (when)
4. The anticipated frequency of risk events from that
source (how often)
8
Sources Of Risks
• Schedule
• Cost
• Quality
• Scope
• Resources
• Customer satisfaction (stakeholder satisfaction)
Risk Categories
• External Regulatory, environmental, government, market shifts
• Internal Time, cost, or scope changes…………..
• Unforeseeable Only a small portion of risks (some say about 10
percent)
• Technical Changes in technology.
9
Risk Categories ( Risk Breakdown Structure )
10
Definitions
• Risk appetite a general, high-level description of the
acceptable level of risk.
• Risk tolerance the degree, amount, or volume of risk that
an organization or individual will accept.
• Risk threshold the specific point at which risk becomes
unacceptable
11
Definitions
• Risk Averse ( Averter ) :
someone who does not want to
take risks.
• Risk Seeker :
someone who want to take risks.
12
• Probability and Impact Matrix
• Risks are prioritized according to their potential implications
• Each risk is rated on its probability of occurrence and
impact on an objective if it does occur.
• Used in Qualitative analysis
13
• Probability and Impact Matrix
No Category Description of Risk IMPACT PROBABILITY
RISK
LEVEL
1 Resource Testing environment not available 4 B ORANGE
2 Schedule
Documentation approval took longer
time
4 A RED
Colors shows
level of
importance
14
• Probability and Impact Matrix ( PMBOK )
• Probability x Impact = Rate to categorize
15
• Expected monetary value analysis
• Decision Tree Diagram used in Quantitative Analysis
• Probability x Impact = Value to categorize
• EVM is the largest value.
16
Quiz
Prototype
setup cost
200,000 $
Don’t
Prototype
setup cost
0 $
Failure: 35% probability
and $120,000 impact
Pass: No impact
Failure: 70% probability
and $450,000 impact
Pass: No impact
?
17
Quiz
Prototype
setup cost
200,000 $
Don’t
Prototype
setup cost
0 $
Failure: 35% probability
and $120,000 impact
Pass: No impact
Failure: 70% probability
and $450,000 impact
Pass: No impact
?
EMV= 0.35X -120= 42,000$
EMV= 0.7X -450= 315,000$
EMV= -315,000$
EMV= -200-42= -242,000$
We go with prototype
We will pay less 242.000 $
18
11.1 Plan Risk Management
19
11.1 Plan Risk Management
The process of defining how to conduct risk
management activities for a project.
20
21
11.1 Plan Risk Management Inputs
1. Project Management Plan
2. Project Charter
3. Stakeholder Register
4. EEF
risk attitudes, thresholds, and tolerances
5. OPA
1. Analytical Techniques
2. Expert Judgment
3. Meetings
11.1 Plan Risk Management T & T
22
11.1 Plan Risk Management Outputs
• Risk Management Plan : includes
 Methodology
 Roles and Responsibilities
 Budgeting
 Timing
 Risk Categories
 Definition of probability and impact
 Probability and Impact Matrix
 Revised stakeholders’ tolerance
 Reporting format
 Tracking
23
11.2 Identify Risk
24
11.2 Identify Risk
The process of determining which risks may affect
the project and documenting their characteristics.
25
11.2 Identify Risk Inputs
Risk Management Plan
Cost management Plan
Schedule Management Plan
Quality Management Plan
Human Resource Management Plan
Scope Baseline
Activity Cost Estimates
Activity Duration Estimates
Stakeholder Register
Project Documents
Procurement Documents
EEF
OPA
26
11.2 Identify Risk T & T
1. Expert Judgment
2. Documentation Reviews
3. Information Gathering Techniques
Brainstorming / Delphi Technique
Interviewing / Root cause analysis
4. Checklist Analysis from
historical information / RBS
5. Assumptions Analysis
Explores the validity of assumptions as they apply
to the project
27
11.2 Identify Risk T & T
6. Diagramming Techniques
• Cause-and-effect (fishbone diagrams / Ishikawa diagrams)
Trace the problem’s source back to its “actionable root
cause”
28
11.2 Identify Risk T & T
6. Diagramming Techniques
• Flowcharting (Process Map) a graphical representation of
a process showing the relationships among process steps
and display the sequence of steps
29
11.2 Identify Risk T & T
6. Diagramming Techniques
• Influence diagrams. A graphical representations of
situations showing causal influences, time ordering of
events, and other relationships among variables and
outcomes.
30
11.2 Identify Risk T & T
7. SWOT Analysis
This analysis looks at the project to identify its strengths and
weaknesses and thereby identify risks
31
11.2 Identify Risk Outputs
Risk Register
• List of identified risks
• List of potential responses
• Root causes of risks
• Updated risk categories
32
Risk Register Template
33
11.3 Perform Qualitative Risk
Analysis
34
11.3 Perform Qualitative Risk Analysis
The process of prioritizing risks for further analysis
or action by assessing and combining their
probability of occurrence and impact.
35
36
11.3 Perform Qualitative Risk Analysis Inputs
1. Risk Management Plan
2. Scope Baseline
3. Risk Register
4. EEF
5. OPA
37
11.3 Perform Qualitative Risk Analysis T & T
1. Probability and Impact Assessment
investigates the likelihood and impact for each risk
2. Risk Probability and Impact Matrix
38
11.3 Perform Qualitative Risk Analysis T & T
2. Risk Data Quality Assessment evaluate project data
3. Risk Categorization RBS
4. Risk Urgency Assessment
Risks requiring near-term responses may be
considered more urgent to address
2. Expert Judgment
39
11.3 Perform Qualitative Risk Analysis Outputs
Risk Register
Updates
• Risk ranking for the project compared
to other projects
• List of prioritized risks and their
probability and impact
• Risk grouped by categories
• List of risks for additional analyses and
responses
• Watch list (noncritical risks)
• List of risks need analyses in the near
term
40
11.4 Perform Quantitative Risk
Analysis
41
11.4 Perform Quantitative Risk Analysis
The process of numerically analyzing the effect of
identified risks on overall project objectives.
42
43
11.4 Perform Quantitative Risk Analysis Inputs
1. Risk Management Plan
2. Cost Management Plan
3. Schedule Management Plan
4. Risk Register
5. EEF
6. OPA
44
11.4 Perform Quantitative Risk Analysis T & T
1. Data Gathering and Representation Techniques
• Interviews with experts using 3 point estimating for
cost & time
45
11.4 Perform Quantitative Risk Analysis T & T
1. Data Gathering and Representation Techniques
• Probability distributions. Using simulation software
46
11.4 Perform Quantitative Risk Analysis T & T
2. Quantitative Risk Analysis and Modeling Techniques
• Sensitivity analysis ( tornado diagram )
Determine which risks have the most potential impact.
Change one element and freeze the others to see the relationship
47
11.4 Perform Quantitative Risk Analysis T & T
2. Quantitative Risk Analysis and Modeling Techniques
• Expected monetary value analysis(Decision Tree Diagram)
• Modeling and simulation
48
11.4 Perform Quantitative Risk Analysis Outputs
Project
Documents
Updates
• Probabilistic analysis of the project
• Probability of achieving cost and
time objectives
• Prioritized list of quantified risks
• Trends in quantitative risk analysis
results
• Initial amount of contingency time
and cost reserves needed
49
11.5 Plan Risk Responses
50
11.5 Plan Risk Responses
The process of developing options and actions to
enhance opportunities and to reduce threats to
project objectives.
• Do something to eliminate the threats before they happen.
• Do something to make sure the opportunities happen.
• Decrease the probability and/ or impact of threats.
• Increase the probability and/ or impact of opportunities.
51
52
11.5 Plan Risk Responses T & T
1. Strategies for Negative Risks or Threats
 Avoidance:
• Risk prevention
• Changing the plan to eliminate a risk
by avoiding the cause/source of risk
Examples:
 Change the implementation strategy
 Do it ourselves (do not subcontract)
 Reduce scope to avoid high risk deliverables
 Adopt a familiar technology or product
53
11.5 Plan Risk Responses T & T
1. Strategies for Negative Risks or Threats
 Mitigation
• Seeks to reduce the impact or probability of the risk
• Take early actions to reduce impact/probability and
don’t wait until the risk hits your project
• Examples:
 Staging - More testing
 Redundancy planning
 Use more qualified resources
54
11.5 Plan Risk Responses T & T
1. Strategies for Negative Risks or Threats
 Transfer
• Shift responsibility of risk consequence to another party
• Does not eliminate risk
• Most effective in dealing with
financial exposure
• Examples:
 Buy/subcontract: move liabilities
 Insurance: liabilities + bonds + Warranties
 Selecting type of Procurement contracts: Fixed Price
55
11.5 Plan Risk Responses T & T
1. Strategies for Negative Risks or Threats
 Acceptance
• Used when project plan cannot be changed
& other risk response strategy cannot be
used
Active Acceptance
• Develop a contingency plan to execute if the risk occur
• Contingency plan = be ready with Plan B
Passive Acceptance
• Deal with the risks as they occur = No Plan B prepared
56
11.5 Plan Risk Responses T & T
2. Strategies for Positive Risks or Opportunities
• Exploit :
Ensure opportunity is realized.
Ex: Assigning organization most talented resources to the
project to reduce cost lower than originally planned.
• Share
• Allocating some or all of the ownership to third part best
able to capture the opportunity.
Ex: Joint ventures, special-purpose companies
57
11.5 Plan Risk Responses T & T
2. Strategies for Positive Risks or Opportunities
• Enhance:
Increase the probability and/or the positive impact of
the opportunity
 Ex: Adding more resources to finish early
Accept:
Welling to take advantage of opportunity if it comes, but not
actively pursuing it.
3. Contingent Response Strategies.
4. Expert Judgment.
58
11.5 Plan Risk Responses Outputs
1. Project Management Plan Updates
2. Project Documents Updates
• Residual risks These are the risks that remain after
risk response planning
• Contingency plans are plans describing the actions
that will be taken if the opportunity or threat occurs.
• Fallback plans These plans are specific actions that
will be taken if the contingency plans are not effective.
• Risk owners the person who will be assigned to carry
out the risk response
59
• Secondary risks Any new risks created by the
implementation of selected risk responses.
• Risk triggers These are events that trigger the
contingency response. The early warning signs for each
risk.
• Contracts Before the contract is finalized, the project
manager should have completed a risk analysis and
included contract terms and conditions required.
• Reserves (contingency) Having reserves for time and
cost is required
(known-unknown) (unknown-unknown)
60
What do you do with noncritical risks?
Document them in a watch list and revisit them periodically
Would you choose only one risk response strategy?
No, you can select a combination of choices.
What risk management activities are done during the
execution of the project?
Watching out for watch-listed (noncritical) risks that
increase in importance, and looking for new risks.
What is the most important item to address in project team
meetings?
Risk.
61
11.6 Control Risk
62
11.6 Control Risk
The process of implementing risk response plans,
tracking identified risks, monitoring residual risks,
identifying new risks, and evaluating risk process
effectiveness throughout the project.
63
64
11.6 Control Risk Inputs
1. Risk Register
2. Project Management Plan
3. Work Performance Data
4. Work Performance Reports
65
11.6 Control Risk T & T
• Workarounds are unplanned responses developed to
deal with the occurrence of unanticipated events or problems
on a project (or to deal with risks that had been accepted )
• Risk Reassessment.
• Risk Audit.
• Variance and Trend Analysis to compare the planned
results to the actual results.
Technical Performance Measurement.
compares technical accomplishments during execution to
The schedule of technical achievement.
• Reserve Analysis.
• Meetings
66
11.6 Control Risk Outputs
1. Work Performance Information
2. Change Requests
• Recommended corrective actions
• Recommended preventive actions
3. Project Management Plan Updates
4. Project Documents
Updates
Risk Register Updates
• Outcomes from risk assessment & risk
audit.
• Results of risk response implementation.
• Closing of risks which are not applicable.
5. OPA
Questions
67
1. All of the following are factors in the assessment of
project risk EXCEPT:
A. Risk events.
B. Risk probability.
C. Amount at stake.
D. Insurance premiums.
Questions
68
1. All of the following are factors in the assessment of
project risk EXCEPT:
A. Risk events.
B. Risk probability.
C. Amount at stake.
D. Insurance premiums.
Answer : D
Questions
69
2. If a project has a 60 percent chance of a US $100,000
profit and a 40 percent chance of a US $100,000 loss, the
expected monetary value (EMV) for the project is:
A. $100,000 profit.
B. $60,000 loss.
C. $20,000 profit.
D. $40,000 loss.
Questions
70
2. If a project has a 60 percent chance of a US $100,000
profit and a 40 percent chance of a US $100,000 loss, the
expected monetary value (EMV) for the project is:
A. $100,000 profit.
B. $60,000 loss.
C. $20,000 profit.
D. $40,000 loss.
Answer : C
Questions
71
3. Assuming that the ends of a range of estimates are +/- 3
sigma from the mean, which of the following range
estimates involves the LEAST risk?
A. 30 days, plus or minus 5 days
B. 22 to 30 days
C. Optimistic = 26 days, most likely = 30 days, pessimistic
= 33 days
D. Mean of 28 days
Questions
72
3. Assuming that the ends of a range of estimates are +/- 3
sigma from the mean, which of the following range
estimates involves the LEAST risk?
A. 30 days, plus or minus 5 days
B. 22 to 30 days
C. Optimistic = 26 days, most likely = 30 days, pessimistic
= 33 days
D. Mean of 28 days
Answer : C
Questions
73
4. If a risk has a 20 percent chance of happening in a given
month, and the project is expected to last five months, what
is the probability that this risk event will occur during the
fourth month of the project?
A. Less than 1 percent
B. 20 percent
C. 60 percent
D. 80 percent
Questions
74
4. If a risk has a 20 percent chance of happening in a given
month, and the project is expected to last five months, what
is the probability that this risk event will occur during the
fourth month of the project?
A. Less than 1 percent
B. 20 percent
C. 60 percent
D. 80 percent
Answer : B
Questions
75
5. Most of the risks will be identified during which risk
management processes?
A. Perform Quantitative Risk Analysis and Identify Risks.
B. Identify Risks and Control Risks/
C. Perform Qualitative Risk Analysis and Control Risks.
D. Identify Risks and Perform Qualitative Risk Analysis.
Questions
76
5. Most of the risks will be identified during which risk
management processes?
A. Perform Quantitative Risk Analysis and Identify Risks.
B. Identify Risks and Control Risks/
C. Perform Qualitative Risk Analysis and Control Risks.
D. Identify Risks and Perform Qualitative Risk Analysis.
Answer : B
Questions
77
6. Risk tolerances are determined in order to help:
A. The team rank the project risks.
B. The project manager estimate the project.
C. The team schedule the project.
D. Management know how other managers will act on the
project.
Questions
78
6. Risk tolerances are determined in order to help:
A. The team rank the project risks.
B. The project manager estimate the project.
C. The team schedule the project.
D. Management know how other managers will act on the
project.
Answer : A
Questions
79
7. Purchasing insurance is BEST considered an example of
risk:
A. Mitigation.
B. Transfer.
C. Acceptance.
D. Avoidance.
Questions
80
7. Purchasing insurance is BEST considered an example of
risk:
A. Mitigation.
B. Transfer.
C. Acceptance.
D. Avoidance.
Answer : B
Questions
81
8. Workarounds are determined during which risk
management process?
A. Identify Risks
B. Perform Quantitative Risk Analysis
C. Plan Risk Responses
D. Control Risks
Questions
82
8. Workarounds are determined during which risk
management process?
A. Identify Risks
B. Perform Quantitative Risk Analysis
C. Plan Risk Responses
D. Control Risks
Answer : D
Questions
83
9. A project manager analyzed the quality of risk data and
asked various stakeholders to determine the probability
and impact of a number of risks. He is about to move to the
next process of risk management. Based on this
information, what has the project manager forgotten to do?
A. Evaluate trends in risk analysis.
B. Identify triggers.
C. Provide a standardized risk rating matrix.
D. Create a fallback plan.
Questions
84
9. A project manager analyzed the quality of risk data and
asked various stakeholders to determine the probability
and impact of a number of risks. He is about to move to the
next process of risk management. Based on this
information, what has the project manager forgotten to do?
A. Evaluate trends in risk analysis.
B. Identify triggers.
C. Provide a standardized risk rating matrix.
D. Create a fallback plan.
Answer : C
Questions
85
10. A project manager is quantifying risk for her project.
Several of her experts are off-site, but wish to be included.
How can this be done?
A. Use Monte Carlo analysis using the Internet as a tool.
B. Apply the critical path method.
C. Determine options for recommended corrective action.
D. Use the Delphi technique.
Questions
86
10. A project manager is quantifying risk for her project.
Several of her experts are off-site, but wish to be included.
How can this be done?
A. Use Monte Carlo analysis using the Internet as a tool.
B. Apply the critical path method.
C. Determine options for recommended corrective action.
D. Use the Delphi technique.
Answer : D
Questions
87
11. A system development project is nearing project dosing
when a previously unidentified risk is discovered. This could
potentially affect the project's overall ability to deliver. What
should be done NEXT?
A. Alert the project sponsor of potential impacts to cost,
scope, or schedule.
B. Qualify the risk.
C. Mitigate this risk by developing a risk response plan.
D. Develop a workaround.
Questions
88
11. A system development project is nearing project dosing
when a previously unidentified risk is discovered. This could
potentially affect the project's overall ability to deliver. What
should be done NEXT?
A. Alert the project sponsor of potential impacts to cost,
scope, or schedule.
B. Qualify the risk.
C. Mitigate this risk by developing a risk response plan.
D. Develop a workaround.
Answer : B
Qualify it because it is not happened yet , only identified. So workaround
is not correct.
Questions
89
12. During project executing, a major problem occurs that
was not included in the risk register. What should you do
FIRST?
A. Create a workaround.
B. Reevaluate the Identify Risks process.
C. Look for any unexpected effects of the problem.
D. Tell management.
Questions
90
12. During project executing, a major problem occurs that
was not included in the risk register. What should you do
FIRST?
A. Create a workaround.
B. Reevaluate the Identify Risks process.
C. Look for any unexpected effects of the problem.
D. Tell management.
Answer : A
Questions
91
13. A watch list is an output of which risk management
process?
A. Plan Risk Responses
B. Perform Quantitative Risk Analysis
C. Perform Qualitative Risk Analysis
D. Plan Risk Management
Questions
92
13. A watch list is an output of which risk management
process?
A. Plan Risk Responses
B. Perform Quantitative Risk Analysis
C. Perform Qualitative Risk Analysis
D. Plan Risk Management
Answer : C
A watch list is made up of low-priority risks that, in the Perform Qualitative
Risk Analysis process
Questions
93
14. While preparing your risk responses, you identify
additional risks. What should you do?
A. Add reserves to the project to accommodate the new risks and notify
management.
B. Document the risk items and calculate the expected monetary value
based on the probability and impact of the occurrences.
C. Determine the risk events and the associated costs, then add the cost
to the project budget as a reserve.
D. Add a 10 percent contingency to the project budget and notify the
customer.
Questions
94
14. While preparing your risk responses, you identify
additional risks. What should you do?
A. Add reserves to the project to accommodate the new risks and notify
management.
B. Document the risk items and calculate the expected monetary value
based on the probability and impact of the occurrences.
C. Determine the risk events and the associated costs, then add the cost
to the project budget as a reserve.
D. Add a 10 percent contingency to the project budget and notify the
customer.
Answer : B

More Related Content

What's hot

PMI-RMP Exam Prep Presentation
PMI-RMP Exam Prep PresentationPMI-RMP Exam Prep Presentation
PMI-RMP Exam Prep Presentationscottdreynolds
 
Pmp chap13 - project stakeholder management details
Pmp chap13 - project stakeholder management detailsPmp chap13 - project stakeholder management details
Pmp chap13 - project stakeholder management detailsAnand Bobade
 
“Construction Risk Management”
“Construction Risk Management”“Construction Risk Management”
“Construction Risk Management”Ary Jamil
 
Episode 25 : Project Risk Management
Episode 25 :  Project Risk ManagementEpisode 25 :  Project Risk Management
Episode 25 : Project Risk ManagementSAJJAD KHUDHUR ABBAS
 
An introduction to primavera risk analysis - Oracle Primavera P6 Collaborate 14
An introduction to primavera risk analysis  - Oracle Primavera P6 Collaborate 14An introduction to primavera risk analysis  - Oracle Primavera P6 Collaborate 14
An introduction to primavera risk analysis - Oracle Primavera P6 Collaborate 14p6academy
 
Chap 11.2 Identify Risks
Chap 11.2 Identify RisksChap 11.2 Identify Risks
Chap 11.2 Identify RisksAnand Bobade
 
Projectriskmanagement pmbok5
Projectriskmanagement pmbok5Projectriskmanagement pmbok5
Projectriskmanagement pmbok5Dhamo daran
 
Project Management Process Groups And Knowledge Areas
Project Management Process Groups And Knowledge AreasProject Management Process Groups And Knowledge Areas
Project Management Process Groups And Knowledge Areasguestfe6ad
 
Chap 11.7 Monitor Risks
Chap 11.7 Monitor RisksChap 11.7 Monitor Risks
Chap 11.7 Monitor RisksAnand Bobade
 
Project Management Risks Review
Project Management Risks ReviewProject Management Risks Review
Project Management Risks ReviewDavid Tennant
 
Project Risk Management
Project  Risk ManagementProject  Risk Management
Project Risk ManagementKelvin Fredson
 
Project Quality Management - PMBOK
Project Quality Management - PMBOKProject Quality Management - PMBOK
Project Quality Management - PMBOKArief Rahmana
 
Project quality management (1)
Project quality management (1)Project quality management (1)
Project quality management (1)CQU
 
Project Quality Management - PMBOK6
Project Quality Management - PMBOK6Project Quality Management - PMBOK6
Project Quality Management - PMBOK6Agus Suhanto
 
PMP Lecture 4: Project Integration Management
PMP Lecture 4: Project Integration ManagementPMP Lecture 4: Project Integration Management
PMP Lecture 4: Project Integration ManagementMohamed Loey
 
Project Risk Management - PMBOK6
Project Risk Management - PMBOK6Project Risk Management - PMBOK6
Project Risk Management - PMBOK6Agus Suhanto
 
Introduction to Project Management
Introduction to Project ManagementIntroduction to Project Management
Introduction to Project ManagementSlav Karaslavov
 
Introduction to Project Management
Introduction to Project ManagementIntroduction to Project Management
Introduction to Project ManagementKris Kimmerle
 
PMP Chap 5 - Project Scope Management - Part1
PMP Chap 5 - Project Scope Management - Part1PMP Chap 5 - Project Scope Management - Part1
PMP Chap 5 - Project Scope Management - Part1Anand Bobade
 

What's hot (20)

PMI-RMP Exam Prep Presentation
PMI-RMP Exam Prep PresentationPMI-RMP Exam Prep Presentation
PMI-RMP Exam Prep Presentation
 
Pmp chap13 - project stakeholder management details
Pmp chap13 - project stakeholder management detailsPmp chap13 - project stakeholder management details
Pmp chap13 - project stakeholder management details
 
“Construction Risk Management”
“Construction Risk Management”“Construction Risk Management”
“Construction Risk Management”
 
Episode 25 : Project Risk Management
Episode 25 :  Project Risk ManagementEpisode 25 :  Project Risk Management
Episode 25 : Project Risk Management
 
An introduction to primavera risk analysis - Oracle Primavera P6 Collaborate 14
An introduction to primavera risk analysis  - Oracle Primavera P6 Collaborate 14An introduction to primavera risk analysis  - Oracle Primavera P6 Collaborate 14
An introduction to primavera risk analysis - Oracle Primavera P6 Collaborate 14
 
Chap 11.2 Identify Risks
Chap 11.2 Identify RisksChap 11.2 Identify Risks
Chap 11.2 Identify Risks
 
Projectriskmanagement pmbok5
Projectriskmanagement pmbok5Projectriskmanagement pmbok5
Projectriskmanagement pmbok5
 
Project Management Process Groups And Knowledge Areas
Project Management Process Groups And Knowledge AreasProject Management Process Groups And Knowledge Areas
Project Management Process Groups And Knowledge Areas
 
Chap 11.7 Monitor Risks
Chap 11.7 Monitor RisksChap 11.7 Monitor Risks
Chap 11.7 Monitor Risks
 
Pmp risk management
Pmp risk managementPmp risk management
Pmp risk management
 
Project Management Risks Review
Project Management Risks ReviewProject Management Risks Review
Project Management Risks Review
 
Project Risk Management
Project  Risk ManagementProject  Risk Management
Project Risk Management
 
Project Quality Management - PMBOK
Project Quality Management - PMBOKProject Quality Management - PMBOK
Project Quality Management - PMBOK
 
Project quality management (1)
Project quality management (1)Project quality management (1)
Project quality management (1)
 
Project Quality Management - PMBOK6
Project Quality Management - PMBOK6Project Quality Management - PMBOK6
Project Quality Management - PMBOK6
 
PMP Lecture 4: Project Integration Management
PMP Lecture 4: Project Integration ManagementPMP Lecture 4: Project Integration Management
PMP Lecture 4: Project Integration Management
 
Project Risk Management - PMBOK6
Project Risk Management - PMBOK6Project Risk Management - PMBOK6
Project Risk Management - PMBOK6
 
Introduction to Project Management
Introduction to Project ManagementIntroduction to Project Management
Introduction to Project Management
 
Introduction to Project Management
Introduction to Project ManagementIntroduction to Project Management
Introduction to Project Management
 
PMP Chap 5 - Project Scope Management - Part1
PMP Chap 5 - Project Scope Management - Part1PMP Chap 5 - Project Scope Management - Part1
PMP Chap 5 - Project Scope Management - Part1
 

Viewers also liked

PMP Flash Card
PMP Flash CardPMP Flash Card
PMP Flash Cardasim78
 
Similarities and differences between PMBOK® Guide and PRINCE2® method
Similarities and differences between PMBOK® Guide and PRINCE2® methodSimilarities and differences between PMBOK® Guide and PRINCE2® method
Similarities and differences between PMBOK® Guide and PRINCE2® methodSvetlana Sidenko
 

Viewers also liked (20)

Pmp stakeholder chapter 13
Pmp stakeholder chapter 13Pmp stakeholder chapter 13
Pmp stakeholder chapter 13
 
Pmp cost chapter 7
Pmp cost chapter 7Pmp cost chapter 7
Pmp cost chapter 7
 
Pmp time chapter 6
Pmp time chapter 6Pmp time chapter 6
Pmp time chapter 6
 
Pmp procurement chapter 12
Pmp procurement chapter 12Pmp procurement chapter 12
Pmp procurement chapter 12
 
Pmp scope chapter 5
Pmp scope chapter 5Pmp scope chapter 5
Pmp scope chapter 5
 
Pmp communication chapter 10
Pmp communication chapter 10Pmp communication chapter 10
Pmp communication chapter 10
 
Pmp integration chapter 4
Pmp integration chapter 4Pmp integration chapter 4
Pmp integration chapter 4
 
Pmp quality chapter 8
Pmp quality chapter 8Pmp quality chapter 8
Pmp quality chapter 8
 
Pmp hr chapter 9
Pmp hr chapter 9Pmp hr chapter 9
Pmp hr chapter 9
 
PMP / Framework 1 2-3
PMP / Framework 1 2-3PMP / Framework 1 2-3
PMP / Framework 1 2-3
 
PMP Flash Card
PMP Flash CardPMP Flash Card
PMP Flash Card
 
Scope creep - cylfe campain
Scope creep - cylfe campainScope creep - cylfe campain
Scope creep - cylfe campain
 
Session 3 gdas pmp study group presentation
Session 3   gdas pmp study group presentationSession 3   gdas pmp study group presentation
Session 3 gdas pmp study group presentation
 
Session 8 gdas pmp study group presentation
Session 8   gdas pmp study group presentationSession 8   gdas pmp study group presentation
Session 8 gdas pmp study group presentation
 
Session 10 gdas pmp study group presentation
Session 10   gdas pmp study group presentationSession 10   gdas pmp study group presentation
Session 10 gdas pmp study group presentation
 
Similarities and differences between PMBOK® Guide and PRINCE2® method
Similarities and differences between PMBOK® Guide and PRINCE2® methodSimilarities and differences between PMBOK® Guide and PRINCE2® method
Similarities and differences between PMBOK® Guide and PRINCE2® method
 
Session 2 gdas pmp study group presentation
Session 2   gdas pmp study group presentationSession 2   gdas pmp study group presentation
Session 2 gdas pmp study group presentation
 
Session 4 gdas pmp study group presentation
Session 4   gdas pmp study group presentationSession 4   gdas pmp study group presentation
Session 4 gdas pmp study group presentation
 
Quality Vs. Grade
Quality Vs. GradeQuality Vs. Grade
Quality Vs. Grade
 
4.contracting
4.contracting4.contracting
4.contracting
 

Similar to Pmp risk chapter 11

Project Risk Management ( With :Decision tree analysi,Simulation,Sensitivity ...
Project Risk Management ( With :Decision tree analysi,Simulation,Sensitivity ...Project Risk Management ( With :Decision tree analysi,Simulation,Sensitivity ...
Project Risk Management ( With :Decision tree analysi,Simulation,Sensitivity ...IndraYu2
 
PROJECT RISK MANAGEMENT.pdf
PROJECT RISK MANAGEMENT.pdfPROJECT RISK MANAGEMENT.pdf
PROJECT RISK MANAGEMENT.pdfMUST
 
Risk management concepts and learning
Risk management   concepts and learningRisk management   concepts and learning
Risk management concepts and learningVanita Ahuja
 
pmp11-risk-180412035349-2.pdf
pmp11-risk-180412035349-2.pdfpmp11-risk-180412035349-2.pdf
pmp11-risk-180412035349-2.pdfMUST
 
Risk Management Knowledge Area
Risk Management Knowledge AreaRisk Management Knowledge Area
Risk Management Knowledge AreaJoshua Render
 
11.3 Perform Qualitative Risk Analysis
11.3 Perform Qualitative Risk Analysis11.3 Perform Qualitative Risk Analysis
11.3 Perform Qualitative Risk AnalysisDavidMcLachlan1
 
Project Risk Management (10)
 Project Risk Management (10) Project Risk Management (10)
Project Risk Management (10)Serdar Temiz
 
11.4 Perform Quantitative Risk Analysis
11.4 Perform Quantitative Risk Analysis11.4 Perform Quantitative Risk Analysis
11.4 Perform Quantitative Risk AnalysisDavidMcLachlan1
 
Project risk management
Project risk managementProject risk management
Project risk managementBarnatuCoffee
 
11.1 Plan Risk Management
11.1 Plan Risk Management11.1 Plan Risk Management
11.1 Plan Risk ManagementDavidMcLachlan1
 
Perform qualitative risk analysis
Perform qualitative risk analysis Perform qualitative risk analysis
Perform qualitative risk analysis Shereef Sabri
 

Similar to Pmp risk chapter 11 (20)

Project managment 10
Project managment  10Project managment  10
Project managment 10
 
Project Risk Management ( With :Decision tree analysi,Simulation,Sensitivity ...
Project Risk Management ( With :Decision tree analysi,Simulation,Sensitivity ...Project Risk Management ( With :Decision tree analysi,Simulation,Sensitivity ...
Project Risk Management ( With :Decision tree analysi,Simulation,Sensitivity ...
 
PMP Preparation - 11 Risk Management
PMP Preparation - 11 Risk ManagementPMP Preparation - 11 Risk Management
PMP Preparation - 11 Risk Management
 
PROJECT RISK MANAGEMENT.pdf
PROJECT RISK MANAGEMENT.pdfPROJECT RISK MANAGEMENT.pdf
PROJECT RISK MANAGEMENT.pdf
 
Risk Chapter 11.pptx
Risk Chapter 11.pptxRisk Chapter 11.pptx
Risk Chapter 11.pptx
 
Risk management concepts and learning
Risk management   concepts and learningRisk management   concepts and learning
Risk management concepts and learning
 
pmp11-risk-180412035349-2.pdf
pmp11-risk-180412035349-2.pdfpmp11-risk-180412035349-2.pdf
pmp11-risk-180412035349-2.pdf
 
Risk Management Knowledge Area
Risk Management Knowledge AreaRisk Management Knowledge Area
Risk Management Knowledge Area
 
11.3 Perform Qualitative Risk Analysis
11.3 Perform Qualitative Risk Analysis11.3 Perform Qualitative Risk Analysis
11.3 Perform Qualitative Risk Analysis
 
Session 18 4th edition PMP
Session 18 4th edition PMPSession 18 4th edition PMP
Session 18 4th edition PMP
 
Project Risk Management (10)
 Project Risk Management (10) Project Risk Management (10)
Project Risk Management (10)
 
11 project risk management
11 project risk management11 project risk management
11 project risk management
 
11.4 Perform Quantitative Risk Analysis
11.4 Perform Quantitative Risk Analysis11.4 Perform Quantitative Risk Analysis
11.4 Perform Quantitative Risk Analysis
 
CAPM Week 4 Chapter 11
CAPM Week 4 Chapter 11CAPM Week 4 Chapter 11
CAPM Week 4 Chapter 11
 
Risk mgt 07.pptx
Risk mgt 07.pptxRisk mgt 07.pptx
Risk mgt 07.pptx
 
Project risk management
Project risk managementProject risk management
Project risk management
 
11.1 Plan Risk Management
11.1 Plan Risk Management11.1 Plan Risk Management
11.1 Plan Risk Management
 
bpm-risk-analysis
bpm-risk-analysisbpm-risk-analysis
bpm-risk-analysis
 
Risk management mod
Risk management modRisk management mod
Risk management mod
 
Perform qualitative risk analysis
Perform qualitative risk analysis Perform qualitative risk analysis
Perform qualitative risk analysis
 

Recently uploaded

Safety T fire missions army field Artillery
Safety T fire missions army field ArtillerySafety T fire missions army field Artillery
Safety T fire missions army field ArtilleryKennethSwanberg
 
Reviewing and summarization of university ranking system to.pptx
Reviewing and summarization of university ranking system  to.pptxReviewing and summarization of university ranking system  to.pptx
Reviewing and summarization of university ranking system to.pptxAss.Prof. Dr. Mogeeb Mosleh
 
How Software Developers Destroy Business Value.pptx
How Software Developers Destroy Business Value.pptxHow Software Developers Destroy Business Value.pptx
How Software Developers Destroy Business Value.pptxAaron Stannard
 
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort ServiceBDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort ServiceDelhi Call girls
 
Dealing with Poor Performance - get the full picture from 3C Performance Mana...
Dealing with Poor Performance - get the full picture from 3C Performance Mana...Dealing with Poor Performance - get the full picture from 3C Performance Mana...
Dealing with Poor Performance - get the full picture from 3C Performance Mana...Hedda Bird
 
Strategic Management, Vision Mission, Internal Analsysis
Strategic Management, Vision Mission, Internal AnalsysisStrategic Management, Vision Mission, Internal Analsysis
Strategic Management, Vision Mission, Internal Analsysistanmayarora45
 
Marketing Management 16th edition by Philip Kotler test bank.docx
Marketing Management 16th edition by Philip Kotler test bank.docxMarketing Management 16th edition by Philip Kotler test bank.docx
Marketing Management 16th edition by Philip Kotler test bank.docxssuserf63bd7
 
internal analysis on strategic management
internal analysis on strategic managementinternal analysis on strategic management
internal analysis on strategic managementharfimakarim
 
Agile Coaching Change Management Framework.pptx
Agile Coaching Change Management Framework.pptxAgile Coaching Change Management Framework.pptx
Agile Coaching Change Management Framework.pptxalinstan901
 
Leaders enhance communication by actively listening, providing constructive f...
Leaders enhance communication by actively listening, providing constructive f...Leaders enhance communication by actively listening, providing constructive f...
Leaders enhance communication by actively listening, providing constructive f...Ram V Chary
 
Independent Escorts Vikaspuri / 9899900591 High Profile Escort Service in Delhi
Independent Escorts Vikaspuri  / 9899900591 High Profile Escort Service in DelhiIndependent Escorts Vikaspuri  / 9899900591 High Profile Escort Service in Delhi
Independent Escorts Vikaspuri / 9899900591 High Profile Escort Service in Delhiguptaswati8536
 
International Ocean Transportation p.pdf
International Ocean Transportation p.pdfInternational Ocean Transportation p.pdf
International Ocean Transportation p.pdfAlejandromexEspino
 
Beyond the Codes_Repositioning towards sustainable development
Beyond the Codes_Repositioning towards sustainable developmentBeyond the Codes_Repositioning towards sustainable development
Beyond the Codes_Repositioning towards sustainable developmentNimot Muili
 

Recently uploaded (15)

Safety T fire missions army field Artillery
Safety T fire missions army field ArtillerySafety T fire missions army field Artillery
Safety T fire missions army field Artillery
 
Reviewing and summarization of university ranking system to.pptx
Reviewing and summarization of university ranking system  to.pptxReviewing and summarization of university ranking system  to.pptx
Reviewing and summarization of university ranking system to.pptx
 
How Software Developers Destroy Business Value.pptx
How Software Developers Destroy Business Value.pptxHow Software Developers Destroy Business Value.pptx
How Software Developers Destroy Business Value.pptx
 
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort ServiceBDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort Service
 
Dealing with Poor Performance - get the full picture from 3C Performance Mana...
Dealing with Poor Performance - get the full picture from 3C Performance Mana...Dealing with Poor Performance - get the full picture from 3C Performance Mana...
Dealing with Poor Performance - get the full picture from 3C Performance Mana...
 
Strategic Management, Vision Mission, Internal Analsysis
Strategic Management, Vision Mission, Internal AnalsysisStrategic Management, Vision Mission, Internal Analsysis
Strategic Management, Vision Mission, Internal Analsysis
 
Marketing Management 16th edition by Philip Kotler test bank.docx
Marketing Management 16th edition by Philip Kotler test bank.docxMarketing Management 16th edition by Philip Kotler test bank.docx
Marketing Management 16th edition by Philip Kotler test bank.docx
 
Intro_University_Ranking_Introduction.pptx
Intro_University_Ranking_Introduction.pptxIntro_University_Ranking_Introduction.pptx
Intro_University_Ranking_Introduction.pptx
 
internal analysis on strategic management
internal analysis on strategic managementinternal analysis on strategic management
internal analysis on strategic management
 
Agile Coaching Change Management Framework.pptx
Agile Coaching Change Management Framework.pptxAgile Coaching Change Management Framework.pptx
Agile Coaching Change Management Framework.pptx
 
Leaders enhance communication by actively listening, providing constructive f...
Leaders enhance communication by actively listening, providing constructive f...Leaders enhance communication by actively listening, providing constructive f...
Leaders enhance communication by actively listening, providing constructive f...
 
Abortion pills in Jeddah |• +966572737505 ] GET CYTOTEC
Abortion pills in Jeddah |• +966572737505 ] GET CYTOTECAbortion pills in Jeddah |• +966572737505 ] GET CYTOTEC
Abortion pills in Jeddah |• +966572737505 ] GET CYTOTEC
 
Independent Escorts Vikaspuri / 9899900591 High Profile Escort Service in Delhi
Independent Escorts Vikaspuri  / 9899900591 High Profile Escort Service in DelhiIndependent Escorts Vikaspuri  / 9899900591 High Profile Escort Service in Delhi
Independent Escorts Vikaspuri / 9899900591 High Profile Escort Service in Delhi
 
International Ocean Transportation p.pdf
International Ocean Transportation p.pdfInternational Ocean Transportation p.pdf
International Ocean Transportation p.pdf
 
Beyond the Codes_Repositioning towards sustainable development
Beyond the Codes_Repositioning towards sustainable developmentBeyond the Codes_Repositioning towards sustainable development
Beyond the Codes_Repositioning towards sustainable development
 

Pmp risk chapter 11

  • 2. 2  Risk & Hazard  Definitions.  11.1 Plan Risk Management  11.2 Identify Risk  11.3 Perform Qualitative Risk Analysis  11.4 Perform Quantitative Risk Analysis  11.5 Plan Risk Response KEY TERMS
  • 4. Project Risk Management 3 Knowledge Area Process Initiating Planning Executing Monitoring & Control Closing Human Resource 11.1 Plan Risk Management 11.2 Identify Risk 11.3 Perform Qualitative Risk Analysis 11.4 Perform Quantitative Risk Analysis 11.5 Plan Risk Response 11.6 control risk Enter phase/ Start project Exit phase/ End project Initiating Processes Closing Processes Planning Processes Executing Processes Monitoring & Controlling Processes
  • 5. 5 11.1 Plan Risk Management The process of defining how to conduct risk management activities for a project. 11.2 Identify Risks The process of determining which risks may affect the project and documenting their characteristics. 11.3 Perform Qualitative Risk Analysis The process of prioritizing risks for further analysis or action by assessing and combining their probability of occurrence and impact.
  • 6. 6 11.4 Perform Quantitative Risk Analysis The process of numerically analyzing the effect of identified risks on overall project objectives. 11.5 Plan Risk Responses The process of developing options and actions to enhance opportunities and to reduce threats to project objectives. 11.6 Control Risks The process of implementing risk response plans, tracking identified risks, monitoring residual risks, identifying new risks, and evaluating risk process effectiveness throughout the project.
  • 7. 7 Risk Factors 1. The probability that a risk event will occur (how likely) 2. The range of possible outcomes (impact or amount at stake) 3. Expected timing for it to occur in the project life cycle (when) 4. The anticipated frequency of risk events from that source (how often)
  • 8. 8 Sources Of Risks • Schedule • Cost • Quality • Scope • Resources • Customer satisfaction (stakeholder satisfaction) Risk Categories • External Regulatory, environmental, government, market shifts • Internal Time, cost, or scope changes………….. • Unforeseeable Only a small portion of risks (some say about 10 percent) • Technical Changes in technology.
  • 9. 9 Risk Categories ( Risk Breakdown Structure )
  • 10. 10 Definitions • Risk appetite a general, high-level description of the acceptable level of risk. • Risk tolerance the degree, amount, or volume of risk that an organization or individual will accept. • Risk threshold the specific point at which risk becomes unacceptable
  • 11. 11 Definitions • Risk Averse ( Averter ) : someone who does not want to take risks. • Risk Seeker : someone who want to take risks.
  • 12. 12 • Probability and Impact Matrix • Risks are prioritized according to their potential implications • Each risk is rated on its probability of occurrence and impact on an objective if it does occur. • Used in Qualitative analysis
  • 13. 13 • Probability and Impact Matrix No Category Description of Risk IMPACT PROBABILITY RISK LEVEL 1 Resource Testing environment not available 4 B ORANGE 2 Schedule Documentation approval took longer time 4 A RED Colors shows level of importance
  • 14. 14 • Probability and Impact Matrix ( PMBOK ) • Probability x Impact = Rate to categorize
  • 15. 15 • Expected monetary value analysis • Decision Tree Diagram used in Quantitative Analysis • Probability x Impact = Value to categorize • EVM is the largest value.
  • 16. 16 Quiz Prototype setup cost 200,000 $ Don’t Prototype setup cost 0 $ Failure: 35% probability and $120,000 impact Pass: No impact Failure: 70% probability and $450,000 impact Pass: No impact ?
  • 17. 17 Quiz Prototype setup cost 200,000 $ Don’t Prototype setup cost 0 $ Failure: 35% probability and $120,000 impact Pass: No impact Failure: 70% probability and $450,000 impact Pass: No impact ? EMV= 0.35X -120= 42,000$ EMV= 0.7X -450= 315,000$ EMV= -315,000$ EMV= -200-42= -242,000$ We go with prototype We will pay less 242.000 $
  • 18. 18 11.1 Plan Risk Management
  • 19. 19 11.1 Plan Risk Management The process of defining how to conduct risk management activities for a project.
  • 20. 20
  • 21. 21 11.1 Plan Risk Management Inputs 1. Project Management Plan 2. Project Charter 3. Stakeholder Register 4. EEF risk attitudes, thresholds, and tolerances 5. OPA 1. Analytical Techniques 2. Expert Judgment 3. Meetings 11.1 Plan Risk Management T & T
  • 22. 22 11.1 Plan Risk Management Outputs • Risk Management Plan : includes  Methodology  Roles and Responsibilities  Budgeting  Timing  Risk Categories  Definition of probability and impact  Probability and Impact Matrix  Revised stakeholders’ tolerance  Reporting format  Tracking
  • 24. 24 11.2 Identify Risk The process of determining which risks may affect the project and documenting their characteristics.
  • 25. 25 11.2 Identify Risk Inputs Risk Management Plan Cost management Plan Schedule Management Plan Quality Management Plan Human Resource Management Plan Scope Baseline Activity Cost Estimates Activity Duration Estimates Stakeholder Register Project Documents Procurement Documents EEF OPA
  • 26. 26 11.2 Identify Risk T & T 1. Expert Judgment 2. Documentation Reviews 3. Information Gathering Techniques Brainstorming / Delphi Technique Interviewing / Root cause analysis 4. Checklist Analysis from historical information / RBS 5. Assumptions Analysis Explores the validity of assumptions as they apply to the project
  • 27. 27 11.2 Identify Risk T & T 6. Diagramming Techniques • Cause-and-effect (fishbone diagrams / Ishikawa diagrams) Trace the problem’s source back to its “actionable root cause”
  • 28. 28 11.2 Identify Risk T & T 6. Diagramming Techniques • Flowcharting (Process Map) a graphical representation of a process showing the relationships among process steps and display the sequence of steps
  • 29. 29 11.2 Identify Risk T & T 6. Diagramming Techniques • Influence diagrams. A graphical representations of situations showing causal influences, time ordering of events, and other relationships among variables and outcomes.
  • 30. 30 11.2 Identify Risk T & T 7. SWOT Analysis This analysis looks at the project to identify its strengths and weaknesses and thereby identify risks
  • 31. 31 11.2 Identify Risk Outputs Risk Register • List of identified risks • List of potential responses • Root causes of risks • Updated risk categories
  • 34. 34 11.3 Perform Qualitative Risk Analysis The process of prioritizing risks for further analysis or action by assessing and combining their probability of occurrence and impact.
  • 35. 35
  • 36. 36 11.3 Perform Qualitative Risk Analysis Inputs 1. Risk Management Plan 2. Scope Baseline 3. Risk Register 4. EEF 5. OPA
  • 37. 37 11.3 Perform Qualitative Risk Analysis T & T 1. Probability and Impact Assessment investigates the likelihood and impact for each risk 2. Risk Probability and Impact Matrix
  • 38. 38 11.3 Perform Qualitative Risk Analysis T & T 2. Risk Data Quality Assessment evaluate project data 3. Risk Categorization RBS 4. Risk Urgency Assessment Risks requiring near-term responses may be considered more urgent to address 2. Expert Judgment
  • 39. 39 11.3 Perform Qualitative Risk Analysis Outputs Risk Register Updates • Risk ranking for the project compared to other projects • List of prioritized risks and their probability and impact • Risk grouped by categories • List of risks for additional analyses and responses • Watch list (noncritical risks) • List of risks need analyses in the near term
  • 41. 41 11.4 Perform Quantitative Risk Analysis The process of numerically analyzing the effect of identified risks on overall project objectives.
  • 42. 42
  • 43. 43 11.4 Perform Quantitative Risk Analysis Inputs 1. Risk Management Plan 2. Cost Management Plan 3. Schedule Management Plan 4. Risk Register 5. EEF 6. OPA
  • 44. 44 11.4 Perform Quantitative Risk Analysis T & T 1. Data Gathering and Representation Techniques • Interviews with experts using 3 point estimating for cost & time
  • 45. 45 11.4 Perform Quantitative Risk Analysis T & T 1. Data Gathering and Representation Techniques • Probability distributions. Using simulation software
  • 46. 46 11.4 Perform Quantitative Risk Analysis T & T 2. Quantitative Risk Analysis and Modeling Techniques • Sensitivity analysis ( tornado diagram ) Determine which risks have the most potential impact. Change one element and freeze the others to see the relationship
  • 47. 47 11.4 Perform Quantitative Risk Analysis T & T 2. Quantitative Risk Analysis and Modeling Techniques • Expected monetary value analysis(Decision Tree Diagram) • Modeling and simulation
  • 48. 48 11.4 Perform Quantitative Risk Analysis Outputs Project Documents Updates • Probabilistic analysis of the project • Probability of achieving cost and time objectives • Prioritized list of quantified risks • Trends in quantitative risk analysis results • Initial amount of contingency time and cost reserves needed
  • 49. 49 11.5 Plan Risk Responses
  • 50. 50 11.5 Plan Risk Responses The process of developing options and actions to enhance opportunities and to reduce threats to project objectives. • Do something to eliminate the threats before they happen. • Do something to make sure the opportunities happen. • Decrease the probability and/ or impact of threats. • Increase the probability and/ or impact of opportunities.
  • 51. 51
  • 52. 52 11.5 Plan Risk Responses T & T 1. Strategies for Negative Risks or Threats  Avoidance: • Risk prevention • Changing the plan to eliminate a risk by avoiding the cause/source of risk Examples:  Change the implementation strategy  Do it ourselves (do not subcontract)  Reduce scope to avoid high risk deliverables  Adopt a familiar technology or product
  • 53. 53 11.5 Plan Risk Responses T & T 1. Strategies for Negative Risks or Threats  Mitigation • Seeks to reduce the impact or probability of the risk • Take early actions to reduce impact/probability and don’t wait until the risk hits your project • Examples:  Staging - More testing  Redundancy planning  Use more qualified resources
  • 54. 54 11.5 Plan Risk Responses T & T 1. Strategies for Negative Risks or Threats  Transfer • Shift responsibility of risk consequence to another party • Does not eliminate risk • Most effective in dealing with financial exposure • Examples:  Buy/subcontract: move liabilities  Insurance: liabilities + bonds + Warranties  Selecting type of Procurement contracts: Fixed Price
  • 55. 55 11.5 Plan Risk Responses T & T 1. Strategies for Negative Risks or Threats  Acceptance • Used when project plan cannot be changed & other risk response strategy cannot be used Active Acceptance • Develop a contingency plan to execute if the risk occur • Contingency plan = be ready with Plan B Passive Acceptance • Deal with the risks as they occur = No Plan B prepared
  • 56. 56 11.5 Plan Risk Responses T & T 2. Strategies for Positive Risks or Opportunities • Exploit : Ensure opportunity is realized. Ex: Assigning organization most talented resources to the project to reduce cost lower than originally planned. • Share • Allocating some or all of the ownership to third part best able to capture the opportunity. Ex: Joint ventures, special-purpose companies
  • 57. 57 11.5 Plan Risk Responses T & T 2. Strategies for Positive Risks or Opportunities • Enhance: Increase the probability and/or the positive impact of the opportunity  Ex: Adding more resources to finish early Accept: Welling to take advantage of opportunity if it comes, but not actively pursuing it. 3. Contingent Response Strategies. 4. Expert Judgment.
  • 58. 58 11.5 Plan Risk Responses Outputs 1. Project Management Plan Updates 2. Project Documents Updates • Residual risks These are the risks that remain after risk response planning • Contingency plans are plans describing the actions that will be taken if the opportunity or threat occurs. • Fallback plans These plans are specific actions that will be taken if the contingency plans are not effective. • Risk owners the person who will be assigned to carry out the risk response
  • 59. 59 • Secondary risks Any new risks created by the implementation of selected risk responses. • Risk triggers These are events that trigger the contingency response. The early warning signs for each risk. • Contracts Before the contract is finalized, the project manager should have completed a risk analysis and included contract terms and conditions required. • Reserves (contingency) Having reserves for time and cost is required (known-unknown) (unknown-unknown)
  • 60. 60 What do you do with noncritical risks? Document them in a watch list and revisit them periodically Would you choose only one risk response strategy? No, you can select a combination of choices. What risk management activities are done during the execution of the project? Watching out for watch-listed (noncritical) risks that increase in importance, and looking for new risks. What is the most important item to address in project team meetings? Risk.
  • 62. 62 11.6 Control Risk The process of implementing risk response plans, tracking identified risks, monitoring residual risks, identifying new risks, and evaluating risk process effectiveness throughout the project.
  • 63. 63
  • 64. 64 11.6 Control Risk Inputs 1. Risk Register 2. Project Management Plan 3. Work Performance Data 4. Work Performance Reports
  • 65. 65 11.6 Control Risk T & T • Workarounds are unplanned responses developed to deal with the occurrence of unanticipated events or problems on a project (or to deal with risks that had been accepted ) • Risk Reassessment. • Risk Audit. • Variance and Trend Analysis to compare the planned results to the actual results. Technical Performance Measurement. compares technical accomplishments during execution to The schedule of technical achievement. • Reserve Analysis. • Meetings
  • 66. 66 11.6 Control Risk Outputs 1. Work Performance Information 2. Change Requests • Recommended corrective actions • Recommended preventive actions 3. Project Management Plan Updates 4. Project Documents Updates Risk Register Updates • Outcomes from risk assessment & risk audit. • Results of risk response implementation. • Closing of risks which are not applicable. 5. OPA
  • 67. Questions 67 1. All of the following are factors in the assessment of project risk EXCEPT: A. Risk events. B. Risk probability. C. Amount at stake. D. Insurance premiums.
  • 68. Questions 68 1. All of the following are factors in the assessment of project risk EXCEPT: A. Risk events. B. Risk probability. C. Amount at stake. D. Insurance premiums. Answer : D
  • 69. Questions 69 2. If a project has a 60 percent chance of a US $100,000 profit and a 40 percent chance of a US $100,000 loss, the expected monetary value (EMV) for the project is: A. $100,000 profit. B. $60,000 loss. C. $20,000 profit. D. $40,000 loss.
  • 70. Questions 70 2. If a project has a 60 percent chance of a US $100,000 profit and a 40 percent chance of a US $100,000 loss, the expected monetary value (EMV) for the project is: A. $100,000 profit. B. $60,000 loss. C. $20,000 profit. D. $40,000 loss. Answer : C
  • 71. Questions 71 3. Assuming that the ends of a range of estimates are +/- 3 sigma from the mean, which of the following range estimates involves the LEAST risk? A. 30 days, plus or minus 5 days B. 22 to 30 days C. Optimistic = 26 days, most likely = 30 days, pessimistic = 33 days D. Mean of 28 days
  • 72. Questions 72 3. Assuming that the ends of a range of estimates are +/- 3 sigma from the mean, which of the following range estimates involves the LEAST risk? A. 30 days, plus or minus 5 days B. 22 to 30 days C. Optimistic = 26 days, most likely = 30 days, pessimistic = 33 days D. Mean of 28 days Answer : C
  • 73. Questions 73 4. If a risk has a 20 percent chance of happening in a given month, and the project is expected to last five months, what is the probability that this risk event will occur during the fourth month of the project? A. Less than 1 percent B. 20 percent C. 60 percent D. 80 percent
  • 74. Questions 74 4. If a risk has a 20 percent chance of happening in a given month, and the project is expected to last five months, what is the probability that this risk event will occur during the fourth month of the project? A. Less than 1 percent B. 20 percent C. 60 percent D. 80 percent Answer : B
  • 75. Questions 75 5. Most of the risks will be identified during which risk management processes? A. Perform Quantitative Risk Analysis and Identify Risks. B. Identify Risks and Control Risks/ C. Perform Qualitative Risk Analysis and Control Risks. D. Identify Risks and Perform Qualitative Risk Analysis.
  • 76. Questions 76 5. Most of the risks will be identified during which risk management processes? A. Perform Quantitative Risk Analysis and Identify Risks. B. Identify Risks and Control Risks/ C. Perform Qualitative Risk Analysis and Control Risks. D. Identify Risks and Perform Qualitative Risk Analysis. Answer : B
  • 77. Questions 77 6. Risk tolerances are determined in order to help: A. The team rank the project risks. B. The project manager estimate the project. C. The team schedule the project. D. Management know how other managers will act on the project.
  • 78. Questions 78 6. Risk tolerances are determined in order to help: A. The team rank the project risks. B. The project manager estimate the project. C. The team schedule the project. D. Management know how other managers will act on the project. Answer : A
  • 79. Questions 79 7. Purchasing insurance is BEST considered an example of risk: A. Mitigation. B. Transfer. C. Acceptance. D. Avoidance.
  • 80. Questions 80 7. Purchasing insurance is BEST considered an example of risk: A. Mitigation. B. Transfer. C. Acceptance. D. Avoidance. Answer : B
  • 81. Questions 81 8. Workarounds are determined during which risk management process? A. Identify Risks B. Perform Quantitative Risk Analysis C. Plan Risk Responses D. Control Risks
  • 82. Questions 82 8. Workarounds are determined during which risk management process? A. Identify Risks B. Perform Quantitative Risk Analysis C. Plan Risk Responses D. Control Risks Answer : D
  • 83. Questions 83 9. A project manager analyzed the quality of risk data and asked various stakeholders to determine the probability and impact of a number of risks. He is about to move to the next process of risk management. Based on this information, what has the project manager forgotten to do? A. Evaluate trends in risk analysis. B. Identify triggers. C. Provide a standardized risk rating matrix. D. Create a fallback plan.
  • 84. Questions 84 9. A project manager analyzed the quality of risk data and asked various stakeholders to determine the probability and impact of a number of risks. He is about to move to the next process of risk management. Based on this information, what has the project manager forgotten to do? A. Evaluate trends in risk analysis. B. Identify triggers. C. Provide a standardized risk rating matrix. D. Create a fallback plan. Answer : C
  • 85. Questions 85 10. A project manager is quantifying risk for her project. Several of her experts are off-site, but wish to be included. How can this be done? A. Use Monte Carlo analysis using the Internet as a tool. B. Apply the critical path method. C. Determine options for recommended corrective action. D. Use the Delphi technique.
  • 86. Questions 86 10. A project manager is quantifying risk for her project. Several of her experts are off-site, but wish to be included. How can this be done? A. Use Monte Carlo analysis using the Internet as a tool. B. Apply the critical path method. C. Determine options for recommended corrective action. D. Use the Delphi technique. Answer : D
  • 87. Questions 87 11. A system development project is nearing project dosing when a previously unidentified risk is discovered. This could potentially affect the project's overall ability to deliver. What should be done NEXT? A. Alert the project sponsor of potential impacts to cost, scope, or schedule. B. Qualify the risk. C. Mitigate this risk by developing a risk response plan. D. Develop a workaround.
  • 88. Questions 88 11. A system development project is nearing project dosing when a previously unidentified risk is discovered. This could potentially affect the project's overall ability to deliver. What should be done NEXT? A. Alert the project sponsor of potential impacts to cost, scope, or schedule. B. Qualify the risk. C. Mitigate this risk by developing a risk response plan. D. Develop a workaround. Answer : B Qualify it because it is not happened yet , only identified. So workaround is not correct.
  • 89. Questions 89 12. During project executing, a major problem occurs that was not included in the risk register. What should you do FIRST? A. Create a workaround. B. Reevaluate the Identify Risks process. C. Look for any unexpected effects of the problem. D. Tell management.
  • 90. Questions 90 12. During project executing, a major problem occurs that was not included in the risk register. What should you do FIRST? A. Create a workaround. B. Reevaluate the Identify Risks process. C. Look for any unexpected effects of the problem. D. Tell management. Answer : A
  • 91. Questions 91 13. A watch list is an output of which risk management process? A. Plan Risk Responses B. Perform Quantitative Risk Analysis C. Perform Qualitative Risk Analysis D. Plan Risk Management
  • 92. Questions 92 13. A watch list is an output of which risk management process? A. Plan Risk Responses B. Perform Quantitative Risk Analysis C. Perform Qualitative Risk Analysis D. Plan Risk Management Answer : C A watch list is made up of low-priority risks that, in the Perform Qualitative Risk Analysis process
  • 93. Questions 93 14. While preparing your risk responses, you identify additional risks. What should you do? A. Add reserves to the project to accommodate the new risks and notify management. B. Document the risk items and calculate the expected monetary value based on the probability and impact of the occurrences. C. Determine the risk events and the associated costs, then add the cost to the project budget as a reserve. D. Add a 10 percent contingency to the project budget and notify the customer.
  • 94. Questions 94 14. While preparing your risk responses, you identify additional risks. What should you do? A. Add reserves to the project to accommodate the new risks and notify management. B. Document the risk items and calculate the expected monetary value based on the probability and impact of the occurrences. C. Determine the risk events and the associated costs, then add the cost to the project budget as a reserve. D. Add a 10 percent contingency to the project budget and notify the customer. Answer : B