2. CONTENTS
Introduction
What is demolition?????
Why demolition????
Methods of demolition
Steps before demolition
Demolition sequence
Hazards in demolition work
Persons at risk
Safety measures
Risk control
2
3. WHAT IS DEMOLITION?????
Demolition means dismantling, razing,
destroying or wrecking any building or
structure or any part by pre-planned and
controlled methods.
Demolition is the tearing-down of building and
other structures
Introduction
3
6. WHY DEMOLITION????
The structures which have already
passed their design life need to be
reconstruct, for safety and operational
requirements.
The old structures need to be
demolished for replacement by new
structures.
6
7. Methods of Demolition
1. Demolition By Hand
2. Ball And Crane
3. Demolition By Machines
4. Demolition By Hydraulic Rushers
5. Demolition By Explosives
6. Robotic Machines
7
9. 2-DEMOLITION BY WRECKING
BALL
The wrecking ball
application consists
of a crane equipped
with a steel ball.
The deconstruction
of the building is by
the impact energy of
the steel ball
suspended from the
crawler crane.
9
10. 3-DEMOLITION BY MACHINES
The sequence of
demolition by machine is
typically the same as the
top down manual
method, except that
most of the demolition is
done by mechanical
plant.
10
13. 4-DEMOLITION BY HYDRAULIC
RUSHERS
The crusher attachment breaks
the concrete and the
reinforcement by the hydraulic
thrust through the long boom arm
system.
The hydraulic crusher can be
operated from the ground
outside the building. This
method is also suitable for
dangerous buildings, silos and
other industrial facilities.
13
18. Pre-blast Considerations
The design may include pre-weakening of the
structure, the strategy in placement of the
explosives and time delay so that the building will
collapse in a safe manner.
Pre-weakening of the structure may include cutting out
a portion of the shear walls and other structural
elements.
A test blast may be conducted to verify the strength of
the structural member and to fine tune the explosive
design.
18
21. ADVANCED TECHNIQUES USING
ROBOTIC MACHINES
There is a different, specialized approach to
every demolition project.
Robotic machines meet these unique challenges.
We have large high reach equipment that has
the capability to reach some very high and
awkward areas.
Smaller Robotic demolisher machines to get into
those tight spots and if a project has some tricky
or confined spaces we have robotic equipment
on hand to get the job done.
21
24. Factors Affecting Selection of Demolition
Method
Type of structure
o Size of structure
o Available time
o Location of structure
o Limitation of noise, dust and vibrations
o Skills person
o Safety
o Availability of equipment
o Behavior of structure
24
25. Demolition Sequence
All cantilevers structures shall demolished first.
Before demolishing roof , all water tanks and lift rooms shall be
demolished first.
Demolition of floor slab shall begin at mid span and proceed
towards the supporting beams.
The order of demolition of floor beams shall be as follows
Cantilever beam
Secondary beam
Primary beam
Non load bearing walls and partition walls shall be removed prior
to demolition process.
Columns and load bearing walls shall be demolished after removal
of beams on top. 25
26. Steps before demolition
1. Surveying
2. Removal of hazardous
materials
3. Preparation of plan
4. Hazard Identification
5. Safety measures
26
27. 1-Survey for demolition
For demolition of a building ,detailed survey and
assessment of a building is necessary.
1. Building survey
Drawing records
Material survey
Hazardous materials
Photographs of a building to be demolished
Surrounding buildings
Building height, distance from nearby buildings
Type of building 27
29. Asbestos Containing
Material
In the case when
asbestos containing
material are discovered,
specialist contractor
shall be employed to
remove such asbestos
containing material.
Asbestos Material
2-Removal of hazardous materials:
29
30. Based on demolition surveys, a demolition plan is
prepared . This plan is produced with the application for
approval to the local authority.
This plan include
Plan showing the location of a building to be demolished.
Building height, structural system
Proposed sequence of demolition steps
Details of equipments used.
3-Preparation of plan
30
31. 3-Preparation of plan
Extent of damage to the building
Existing structures and facilities in the vicinity
Layout plan
Proposed method of demolition
Safety measures
31
32. Hazards in Demolation Work
Falls from height or on the same level.
Falling debris.
Premature collapse of the structure being
demolished.
Dust and fumes.
The silting up of drainage systems by dust.
The problems arising from spilt fuel oils.
Manual handling.
Presence of asbestos and other hazardous
substances.
32
33. Hazards in Demolation Work
Noise and vibration from heavy plant and equipment
Electric shock
Pires and explosions from the use of flammable and
Explosive substances
Smoke from burning waste timber
Pneumatic drills and power tools
the existence of services, such as electricity, gas and
water
Collision with heavy plant
Plant and vehicles overturning.
33
44. Training and
Communication:
Demolition workers,
including plant or
equipment operators, shall
go through proper job
safety training and be
informed of the potential
hazards by attending
training sessions as well as
on-the-job training.
Safety measures/Controls
44
45. Safety Measures
Equipment Maintenance:
All equipment shall be
tested and examined
before use. They shall be
properly stored and
maintained. The
equipment shall be
inspected daily and results
of the inspection shall be
recorded accordingly.
45
46. Electrical Safety
A properly connected
power source from a
local electric utility
supplier or a mobile
electricity generator
shall be utilized in
demolition sites.
Safety Measures
46
47. Fire:
All flammable goods shall
be removed from site
unless they are necessary
for the works involved.
Any remaining flammable
goods shall be stored in
proper storage facilities.
Safety Measures
47
48. Vibration:
Demolition work will cause vibration to
neighboring buildings or structures to various
extent, depending on the method of
demolition, which should be controlled by
suitable monitoring. The most serious
vibration is caused by implosion.
Safety Measures
48
49. Safety Measures
Air Pollution:
Concrete breaking, handling of debris and hauling
process are main sources of dust from building
demolition. Dust mitigation measures, such as water
spray, shall be adopted to minimise dust emissions.
Burning of waste shall not be allowed.
Diesel fumes generated by mechanical plant or
equipment shall be controlled.
49
51. NOISE
Noise pollution arising from the demolition
works due the use of powered mechanical
equipment such as pneumatic breakers,
excavators and generators, loading and
transportation of debris, etc. affects the
workers, and the sensitive receivers in the
vicinity of the demolition site.
51
58. Table of Hazardous activites Pesrsons at
Risk and Control Measures
Activity:- What is
Hazard?
Harm:- Who or What? Safety Measure/ What
are you doing?
Public Entering Site Injuries To Persons Site Must be Securely
Fenced off and Locked at
the end of working day.
Signage Warning of
Danger
Gas/Elec Explosion/Fire/Shoks Services To Be
disconnected and
Confirmed to be
disconnected by
Liacensed Person.
Working at height/ Fall
From Height
Injury To Persons Use of Scaffolding , Use of
Fall arrest System.
58
59. Table of Hazardous activites Pesrsons
at Risk and Control Measures
Activity:- What is
Hazard?
Harm:- Who or What? Safety Measure/ What
are you doing?
Road users and
Padestrians During
movement of lorries
Injury To Persons Use of Banks man at all
times warning signs and
Physical Barriears
General site Hazards like
dust and cuts.
Injury To Persons Use of PPE,s at all times.
Dust suppression system
Planned,Full site
Coverage of water mist
when required.
Manual Handeling Injury To Persons All Times to be checked
before manual lifting.
Slips/Trips Injury To Persons Good House
Keeping/Remove All Trip
Hazards
59
60. Table of Hazardous activites Pesrsons
at Risk and Control Measures
Activity:- What is
Hazard?
Harm:- Who or What? Safety Measure/ What
are you doing?
Falling Massonary
uncontrolled Collapse
Site Opperative, Possible
Public
Whilst Carrying out the
soft strip state of the
contract the structural
stability will be assessed.
If any part of the building
is deemed at risk then All
persons are to be
evacuated and
mechanical means use to
remove and make safe
any required area of the
building
60
61. Conclusion
Demolition is the most dangerous/hazardous activity
as compare to the other civil activities.
Demolition must be wellplanned to avoid fatalities
and injuries
Development in techniques allows rapid demolition
with no harm to the environment.
61
62. Conclusion
It can be concluded that demolishing/imploding
the building structure will prove very useful,
economical and quickest for reconstruction.
Leads to a safe and controlled demolition for the
occupants and neighbourhood.
62