SlideShare a Scribd company logo
1 of 65
Group Members
Bilal Bhati
Muhammad Abbas
Usman Tahir
Demolition - Hazards and Controls
CONTENTS
Introduction
What is demolition?????
Why demolition????
Methods of demolition
Steps before demolition
Demolition sequence
Hazards in demolition work
Persons at risk
Safety measures
Risk control
2
WHAT IS DEMOLITION?????
 Demolition means dismantling, razing,
destroying or wrecking any building or
structure or any part by pre-planned and
controlled methods.
 Demolition is the tearing-down of building and
other structures
Introduction
3
Introduction
Demolitio
n work is
in
progress.
4
Introduction
Demoliton is
in Progress
and
supervised
by Safety
officer
5
WHY DEMOLITION????
 The structures which have already
passed their design life need to be
reconstruct, for safety and operational
requirements.
 The old structures need to be
demolished for replacement by new
structures.
6
Methods of Demolition
1. Demolition By Hand
2. Ball And Crane
3. Demolition By Machines
4. Demolition By Hydraulic Rushers
5. Demolition By Explosives
6. Robotic Machines
7
1-Demolition By Hand
Demolition is done
manually by labor
using hammers
8
2-DEMOLITION BY WRECKING
BALL
 The wrecking ball
application consists
of a crane equipped
with a steel ball.
 The deconstruction
of the building is by
the impact energy of
the steel ball
suspended from the
crawler crane.
9
3-DEMOLITION BY MACHINES
 The sequence of
demolition by machine is
typically the same as the
top down manual
method, except that
most of the demolition is
done by mechanical
plant.
10
Demolition By Machines
11
Demolition By Machines
12
4-DEMOLITION BY HYDRAULIC
RUSHERS
 The crusher attachment breaks
the concrete and the
reinforcement by the hydraulic
thrust through the long boom arm
system.
 The hydraulic crusher can be
operated from the ground
outside the building. This
method is also suitable for
dangerous buildings, silos and
other industrial facilities.
13
4-EMOLITION BY HYDRAULIC
RUSHERS
14
5-DEMOLITION BY
EXPLOSIVES
15
Columns are fully loaded with
explosives
16
Pre-blast Considerations
 The design may include pre-weakening of the
structure, the strategy in placement of the
explosives and time delay so that the building will
collapse in a safe manner.
 Pre-weakening of the structure may include cutting out
a portion of the shear walls and other structural
elements.
 A test blast may be conducted to verify the strength of
the structural member and to fine tune the explosive
design.
18
Process of
Implosion
19
Building Implosion 20
ADVANCED TECHNIQUES USING
ROBOTIC MACHINES
 There is a different, specialized approach to
every demolition project.
 Robotic machines meet these unique challenges.
 We have large high reach equipment that has
the capability to reach some very high and
awkward areas.
 Smaller Robotic demolisher machines to get into
those tight spots and if a project has some tricky
or confined spaces we have robotic equipment
on hand to get the job done.
21
ADVANCED TECHNIQUES USING
ROBOTIC MACHINES
22
ADVANCED TECHNIQUES USING
ROBOTIC MACHINES
23
Factors Affecting Selection of Demolition
Method
 Type of structure
o Size of structure
o Available time
o Location of structure
o Limitation of noise, dust and vibrations
o Skills person
o Safety
o Availability of equipment
o Behavior of structure
24
Demolition Sequence
 All cantilevers structures shall demolished first.
 Before demolishing roof , all water tanks and lift rooms shall be
demolished first.
 Demolition of floor slab shall begin at mid span and proceed
towards the supporting beams.
 The order of demolition of floor beams shall be as follows
 Cantilever beam
 Secondary beam
 Primary beam
 Non load bearing walls and partition walls shall be removed prior
to demolition process.
 Columns and load bearing walls shall be demolished after removal
of beams on top. 25
Steps before demolition
1. Surveying
2. Removal of hazardous
materials
3. Preparation of plan
4. Hazard Identification
5. Safety measures
26
1-Survey for demolition
 For demolition of a building ,detailed survey and
assessment of a building is necessary.
1. Building survey
Drawing records
Material survey
Hazardous materials
Photographs of a building to be demolished
Surrounding buildings
Building height, distance from nearby buildings
Type of building 27
Structural survey
Drawing records
Special structure
Behaviour of structure
Structural support system
Degree of deterioration
28
Asbestos Containing
Material
 In the case when
asbestos containing
material are discovered,
specialist contractor
shall be employed to
remove such asbestos
containing material.
Asbestos Material
2-Removal of hazardous materials:
29
 Based on demolition surveys, a demolition plan is
prepared . This plan is produced with the application for
approval to the local authority.
 This plan include
 Plan showing the location of a building to be demolished.
 Building height, structural system
 Proposed sequence of demolition steps
 Details of equipments used.
3-Preparation of plan
30
3-Preparation of plan
 Extent of damage to the building
 Existing structures and facilities in the vicinity
 Layout plan
 Proposed method of demolition
 Safety measures
31
Hazards in Demolation Work
 Falls from height or on the same level.
 Falling debris.
 Premature collapse of the structure being
demolished.
 Dust and fumes.
 The silting up of drainage systems by dust.
 The problems arising from spilt fuel oils.
 Manual handling.
 Presence of asbestos and other hazardous
substances.
32
Hazards in Demolation Work
 Noise and vibration from heavy plant and equipment
 Electric shock
 Pires and explosions from the use of flammable and
 Explosive substances
 Smoke from burning waste timber
 Pneumatic drills and power tools
 the existence of services, such as electricity, gas and
water
 Collision with heavy plant
 Plant and vehicles overturning.
33
Hazards in Demolation Work
Hazard
of falling
from
Height
34
Hazards in Demolation Work
Falling Hazards
35
Hazards in Demolation
Work
Collapse
36
Hazards in Demolation Work
Dust Hazard
37
Hazards in Demolation Work
Asbestos
Dust
Hazard is
there
38
Persons at Risk
•Site workers
involve in
demolition
39
Persons at Risk
•Worker
at site
40
Persons at Risk
•Passerby
41
Persons at Risk
•Machiner
y
operators
42
Safety Measures/Controls
43
Training and
Communication:
 Demolition workers,
including plant or
equipment operators, shall
go through proper job
safety training and be
informed of the potential
hazards by attending
training sessions as well as
on-the-job training.
Safety measures/Controls
44
Safety Measures
Equipment Maintenance:
 All equipment shall be
tested and examined
before use. They shall be
properly stored and
maintained. The
equipment shall be
inspected daily and results
of the inspection shall be
recorded accordingly.
45
Electrical Safety
 A properly connected
power source from a
local electric utility
supplier or a mobile
electricity generator
shall be utilized in
demolition sites.
Safety Measures
46
Fire:
 All flammable goods shall
be removed from site
unless they are necessary
for the works involved.
Any remaining flammable
goods shall be stored in
proper storage facilities.
Safety Measures
47
Vibration:
 Demolition work will cause vibration to
neighboring buildings or structures to various
extent, depending on the method of
demolition, which should be controlled by
suitable monitoring. The most serious
vibration is caused by implosion.
Safety Measures
48
Safety Measures
Air Pollution:
 Concrete breaking, handling of debris and hauling
process are main sources of dust from building
demolition. Dust mitigation measures, such as water
spray, shall be adopted to minimise dust emissions.
Burning of waste shall not be allowed.
 Diesel fumes generated by mechanical plant or
equipment shall be controlled.
49
Safety Measures
Controlig
air
polution
by
supraying
water
50
NOISE
 Noise pollution arising from the demolition
works due the use of powered mechanical
equipment such as pneumatic breakers,
excavators and generators, loading and
transportation of debris, etc. affects the
workers, and the sensitive receivers in the
vicinity of the demolition site.
51
Noise Pollution
Use of ear
plug/ear
defender for
avoiding
noise
pollution
52
DEBRIS AND WASTE HANDLING
53
PROTECTIVE
SCREENS
 Protective screen
covers shall be
placed, where
necessary, to
prevent flying
pieces from
injuring the fellow
workmen.
54
Personel Protective Equipments
Protection of
worker with
PPE is very
important.PPE
s come in the
last as safety
measures.
55
Personel Protective
Equipments
Use of hard
hat gloves
safety shoes
glasses
jacket ear
plug must be
compulsory
56
Safety Signs
Safety
signs must
be thear to
aware the
Persons at
work and
public
57
Table of Hazardous activites Pesrsons at
Risk and Control Measures
Activity:- What is
Hazard?
Harm:- Who or What? Safety Measure/ What
are you doing?
Public Entering Site Injuries To Persons Site Must be Securely
Fenced off and Locked at
the end of working day.
Signage Warning of
Danger
Gas/Elec Explosion/Fire/Shoks Services To Be
disconnected and
Confirmed to be
disconnected by
Liacensed Person.
Working at height/ Fall
From Height
Injury To Persons Use of Scaffolding , Use of
Fall arrest System.
58
Table of Hazardous activites Pesrsons
at Risk and Control Measures
Activity:- What is
Hazard?
Harm:- Who or What? Safety Measure/ What
are you doing?
Road users and
Padestrians During
movement of lorries
Injury To Persons Use of Banks man at all
times warning signs and
Physical Barriears
General site Hazards like
dust and cuts.
Injury To Persons Use of PPE,s at all times.
Dust suppression system
Planned,Full site
Coverage of water mist
when required.
Manual Handeling Injury To Persons All Times to be checked
before manual lifting.
Slips/Trips Injury To Persons Good House
Keeping/Remove All Trip
Hazards
59
Table of Hazardous activites Pesrsons
at Risk and Control Measures
Activity:- What is
Hazard?
Harm:- Who or What? Safety Measure/ What
are you doing?
Falling Massonary
uncontrolled Collapse
Site Opperative, Possible
Public
Whilst Carrying out the
soft strip state of the
contract the structural
stability will be assessed.
If any part of the building
is deemed at risk then All
persons are to be
evacuated and
mechanical means use to
remove and make safe
any required area of the
building
60
Conclusion
 Demolition is the most dangerous/hazardous activity
as compare to the other civil activities.
 Demolition must be wellplanned to avoid fatalities
and injuries
 Development in techniques allows rapid demolition
with no harm to the environment.
61
Conclusion
 It can be concluded that demolishing/imploding
the building structure will prove very useful,
economical and quickest for reconstruction.
 Leads to a safe and controlled demolition for the
occupants and neighbourhood.
62
References
 http://www.implosionworld.com/history.html
 www.wikipedia.com
 http://archsd.gov.hk/media/11640/demolition_e2004.pdf
 http://wiki.iricen.gov.in/doku/lib/exe/fetch.php?media=m
%E0%A4%BEr%E0%A5%8Dc_march_2013:achuta_ra
o.pdf
 http://www.concreteconstruction.net/Images/Demolition
%20of%20Concrete%20Structures_tcm45-341335.pdf
 https://www.cdc.gov/niosh/topics/noisecontrol/
 https://www.pinterest.com/pin/854065516804139130/
63
Any
Question...
64
iuiuut

More Related Content

What's hot

Lifting plan
Lifting planLifting plan
Lifting plantnsv22
 
9 lifting operations with tower crane risk assessment templates
9 lifting operations with tower crane risk assessment templates9 lifting operations with tower crane risk assessment templates
9 lifting operations with tower crane risk assessment templatesDwarika Bhushan Sharma
 
Safety management for construction machines & equipments
 Safety management for construction machines & equipments Safety management for construction machines & equipments
Safety management for construction machines & equipmentsSelva Prakash
 
4 cofferdams (temporary works) risk assessment templates
4 cofferdams (temporary works) risk assessment templates4 cofferdams (temporary works) risk assessment templates
4 cofferdams (temporary works) risk assessment templatesDwarika Bhushan Sharma
 
3 emergency management risk assessment templates
3 emergency management risk assessment templates3 emergency management risk assessment templates
3 emergency management risk assessment templatesDwarika Bhushan Sharma
 
Demolition of building
Demolition of buildingDemolition of building
Demolition of buildingAnimesh1714013
 
10 use of mobile concrete pump risk assessment templates
10 use of mobile concrete pump risk assessment templates10 use of mobile concrete pump risk assessment templates
10 use of mobile concrete pump risk assessment templatesDwarika Bhushan Sharma
 
Construction safety lecture-3
Construction safety  lecture-3Construction safety  lecture-3
Construction safety lecture-3Saleem Malik
 
SAFETY REQUIREMENTS FOR FORMWORK STRUCTURES
SAFETY REQUIREMENTS FOR FORMWORK STRUCTURESSAFETY REQUIREMENTS FOR FORMWORK STRUCTURES
SAFETY REQUIREMENTS FOR FORMWORK STRUCTURESHASNIZAM BIN MD SAAD
 
7 Falsework (Temporary Works) Risk Assessment Templates.docx
7 Falsework (Temporary Works) Risk Assessment Templates.docx7 Falsework (Temporary Works) Risk Assessment Templates.docx
7 Falsework (Temporary Works) Risk Assessment Templates.docxDwarika Bhushan Sharma
 
Demolition Safety 2015
Demolition Safety 2015Demolition Safety 2015
Demolition Safety 2015John Newquist
 
Health and Safety in Construction PPT
Health and Safety in Construction  PPTHealth and Safety in Construction  PPT
Health and Safety in Construction PPTLuke D'Arcy
 
Safety in various construction operations –
Safety in various construction operations –Safety in various construction operations –
Safety in various construction operations –Nayana 54321
 
SCAFFOLDING Safety Training
SCAFFOLDING Safety TrainingSCAFFOLDING Safety Training
SCAFFOLDING Safety TrainingWilliam York
 
12 construction safety
12 construction safety12 construction safety
12 construction safetyazak80
 
14 use of plant graders and road rollers risk assessment templates
14 use of plant  graders and road rollers risk assessment templates14 use of plant  graders and road rollers risk assessment templates
14 use of plant graders and road rollers risk assessment templatesDwarika Bhushan Sharma
 

What's hot (20)

Lifting plan
Lifting planLifting plan
Lifting plan
 
9 lifting operations with tower crane risk assessment templates
9 lifting operations with tower crane risk assessment templates9 lifting operations with tower crane risk assessment templates
9 lifting operations with tower crane risk assessment templates
 
CRANE SAFETY HANDBOOK
CRANE SAFETY HANDBOOK CRANE SAFETY HANDBOOK
CRANE SAFETY HANDBOOK
 
Safety management for construction machines & equipments
 Safety management for construction machines & equipments Safety management for construction machines & equipments
Safety management for construction machines & equipments
 
Scaffolding safety at construction site
Scaffolding safety at construction siteScaffolding safety at construction site
Scaffolding safety at construction site
 
4 cofferdams (temporary works) risk assessment templates
4 cofferdams (temporary works) risk assessment templates4 cofferdams (temporary works) risk assessment templates
4 cofferdams (temporary works) risk assessment templates
 
Construction Safety Training
Construction Safety TrainingConstruction Safety Training
Construction Safety Training
 
3 emergency management risk assessment templates
3 emergency management risk assessment templates3 emergency management risk assessment templates
3 emergency management risk assessment templates
 
Demolition of building
Demolition of buildingDemolition of building
Demolition of building
 
10 use of mobile concrete pump risk assessment templates
10 use of mobile concrete pump risk assessment templates10 use of mobile concrete pump risk assessment templates
10 use of mobile concrete pump risk assessment templates
 
Construction safety lecture-3
Construction safety  lecture-3Construction safety  lecture-3
Construction safety lecture-3
 
Safety in Construction
Safety in ConstructionSafety in Construction
Safety in Construction
 
SAFETY REQUIREMENTS FOR FORMWORK STRUCTURES
SAFETY REQUIREMENTS FOR FORMWORK STRUCTURESSAFETY REQUIREMENTS FOR FORMWORK STRUCTURES
SAFETY REQUIREMENTS FOR FORMWORK STRUCTURES
 
7 Falsework (Temporary Works) Risk Assessment Templates.docx
7 Falsework (Temporary Works) Risk Assessment Templates.docx7 Falsework (Temporary Works) Risk Assessment Templates.docx
7 Falsework (Temporary Works) Risk Assessment Templates.docx
 
Demolition Safety 2015
Demolition Safety 2015Demolition Safety 2015
Demolition Safety 2015
 
Health and Safety in Construction PPT
Health and Safety in Construction  PPTHealth and Safety in Construction  PPT
Health and Safety in Construction PPT
 
Safety in various construction operations –
Safety in various construction operations –Safety in various construction operations –
Safety in various construction operations –
 
SCAFFOLDING Safety Training
SCAFFOLDING Safety TrainingSCAFFOLDING Safety Training
SCAFFOLDING Safety Training
 
12 construction safety
12 construction safety12 construction safety
12 construction safety
 
14 use of plant graders and road rollers risk assessment templates
14 use of plant  graders and road rollers risk assessment templates14 use of plant  graders and road rollers risk assessment templates
14 use of plant graders and road rollers risk assessment templates
 

Similar to Demolition Hazards and Controls

demolition of building
demolition of buildingdemolition of building
demolition of buildingtushar garg
 
Construction Safety Training_Session 07_Construction Demolition, Hazards and ...
Construction Safety Training_Session 07_Construction Demolition, Hazards and ...Construction Safety Training_Session 07_Construction Demolition, Hazards and ...
Construction Safety Training_Session 07_Construction Demolition, Hazards and ...Muizz Anibire
 
civil DEMOLITION OF BUILDING ppt.pdf
civil DEMOLITION OF BUILDING ppt.pdfcivil DEMOLITION OF BUILDING ppt.pdf
civil DEMOLITION OF BUILDING ppt.pdfpramodKumarsahani1
 
Techniques for Demolition of Structure
Techniques for Demolition of StructureTechniques for Demolition of Structure
Techniques for Demolition of StructureDinaker Dixit
 
Demolition of building and its precautionary measures as per IS code
Demolition of building and its precautionary measures as per IS codeDemolition of building and its precautionary measures as per IS code
Demolition of building and its precautionary measures as per IS codejaimin1702
 
BUILDING DEMOLITION
BUILDING DEMOLITIONBUILDING DEMOLITION
BUILDING DEMOLITIONseminarppts
 
25 Demolition of existing concrete structures Risk Assessment Templates.docx
25 Demolition of existing concrete structures Risk Assessment Templates.docx25 Demolition of existing concrete structures Risk Assessment Templates.docx
25 Demolition of existing concrete structures Risk Assessment Templates.docxDwarika Bhushan Sharma
 
demolition-of-building-7436-hPNbxid.pptx
demolition-of-building-7436-hPNbxid.pptxdemolition-of-building-7436-hPNbxid.pptx
demolition-of-building-7436-hPNbxid.pptxJade165645
 
Demolition of Structures.
Demolition of Structures.Demolition of Structures.
Demolition of Structures.Chintan Varia
 
Building Service Chapter 4
Building Service Chapter 4Building Service Chapter 4
Building Service Chapter 4Izam Lukman
 
OSHA demolition
OSHA demolitionOSHA demolition
OSHA demolitionHni Amiera
 
SAFETY IN USE OF CONSTRUCTION MACHINARY AND EQUIPMENT.pptx
SAFETY IN USE OF CONSTRUCTION MACHINARY AND EQUIPMENT.pptxSAFETY IN USE OF CONSTRUCTION MACHINARY AND EQUIPMENT.pptx
SAFETY IN USE OF CONSTRUCTION MACHINARY AND EQUIPMENT.pptxShyam Sundar Roy
 
Demolition of a building
Demolition of a buildingDemolition of a building
Demolition of a buildingAbhishekKadve
 
Demolishing of concrete structures
Demolishing of concrete structuresDemolishing of concrete structures
Demolishing of concrete structuresTsegaye Arega
 

Similar to Demolition Hazards and Controls (20)

demolition of building
demolition of buildingdemolition of building
demolition of building
 
Construction Safety Training_Session 07_Construction Demolition, Hazards and ...
Construction Safety Training_Session 07_Construction Demolition, Hazards and ...Construction Safety Training_Session 07_Construction Demolition, Hazards and ...
Construction Safety Training_Session 07_Construction Demolition, Hazards and ...
 
BCT Mod 4 demolition of structure (Updated)
BCT Mod 4 demolition of structure (Updated)BCT Mod 4 demolition of structure (Updated)
BCT Mod 4 demolition of structure (Updated)
 
Demolition pptx
Demolition pptxDemolition pptx
Demolition pptx
 
civil DEMOLITION OF BUILDING ppt.pdf
civil DEMOLITION OF BUILDING ppt.pdfcivil DEMOLITION OF BUILDING ppt.pdf
civil DEMOLITION OF BUILDING ppt.pdf
 
Techniques for Demolition of Structure
Techniques for Demolition of StructureTechniques for Demolition of Structure
Techniques for Demolition of Structure
 
Demolition of building and its precautionary measures as per IS code
Demolition of building and its precautionary measures as per IS codeDemolition of building and its precautionary measures as per IS code
Demolition of building and its precautionary measures as per IS code
 
BUILDING DEMOLITION
BUILDING DEMOLITIONBUILDING DEMOLITION
BUILDING DEMOLITION
 
25 Demolition of existing concrete structures Risk Assessment Templates.docx
25 Demolition of existing concrete structures Risk Assessment Templates.docx25 Demolition of existing concrete structures Risk Assessment Templates.docx
25 Demolition of existing concrete structures Risk Assessment Templates.docx
 
Techniques behind demolition of structures
Techniques behind demolition of structuresTechniques behind demolition of structures
Techniques behind demolition of structures
 
demolition-of-building-7436-hPNbxid.pptx
demolition-of-building-7436-hPNbxid.pptxdemolition-of-building-7436-hPNbxid.pptx
demolition-of-building-7436-hPNbxid.pptx
 
Demolition of Structures.
Demolition of Structures.Demolition of Structures.
Demolition of Structures.
 
Bs bab 4
Bs bab 4Bs bab 4
Bs bab 4
 
Building Service Chapter 4
Building Service Chapter 4Building Service Chapter 4
Building Service Chapter 4
 
OSHA demolition
OSHA demolitionOSHA demolition
OSHA demolition
 
BCT Mod 4 demolition of structure
BCT Mod 4 demolition of structureBCT Mod 4 demolition of structure
BCT Mod 4 demolition of structure
 
SAFETY IN USE OF CONSTRUCTION MACHINARY AND EQUIPMENT.pptx
SAFETY IN USE OF CONSTRUCTION MACHINARY AND EQUIPMENT.pptxSAFETY IN USE OF CONSTRUCTION MACHINARY AND EQUIPMENT.pptx
SAFETY IN USE OF CONSTRUCTION MACHINARY AND EQUIPMENT.pptx
 
Dempolition notes Part 1.pdf
Dempolition notes Part 1.pdfDempolition notes Part 1.pdf
Dempolition notes Part 1.pdf
 
Demolition of a building
Demolition of a buildingDemolition of a building
Demolition of a building
 
Demolishing of concrete structures
Demolishing of concrete structuresDemolishing of concrete structures
Demolishing of concrete structures
 

Recently uploaded

Block diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.pptBlock diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.pptNANDHAKUMARA10
 
A Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna MunicipalityA Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna MunicipalityMorshed Ahmed Rahath
 
2016EF22_0 solar project report rooftop projects
2016EF22_0 solar project report rooftop projects2016EF22_0 solar project report rooftop projects
2016EF22_0 solar project report rooftop projectssmsksolar
 
chapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineeringchapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineeringmulugeta48
 
Hostel management system project report..pdf
Hostel management system project report..pdfHostel management system project report..pdf
Hostel management system project report..pdfKamal Acharya
 
22-prompt engineering noted slide shown.pdf
22-prompt engineering noted slide shown.pdf22-prompt engineering noted slide shown.pdf
22-prompt engineering noted slide shown.pdf203318pmpc
 
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...SUHANI PANDEY
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756dollysharma2066
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapRishantSharmaFr
 
Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...
Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...
Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...soginsider
 
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance Bookingroncy bisnoi
 
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Bookingdharasingh5698
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayEpec Engineered Technologies
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...roncy bisnoi
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . pptDineshKumar4165
 
Unit 2- Effective stress & Permeability.pdf
Unit 2- Effective stress & Permeability.pdfUnit 2- Effective stress & Permeability.pdf
Unit 2- Effective stress & Permeability.pdfRagavanV2
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXssuser89054b
 
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoor
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoorTop Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoor
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoordharasingh5698
 

Recently uploaded (20)

Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
 
Block diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.pptBlock diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.ppt
 
A Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna MunicipalityA Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna Municipality
 
2016EF22_0 solar project report rooftop projects
2016EF22_0 solar project report rooftop projects2016EF22_0 solar project report rooftop projects
2016EF22_0 solar project report rooftop projects
 
chapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineeringchapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineering
 
Hostel management system project report..pdf
Hostel management system project report..pdfHostel management system project report..pdf
Hostel management system project report..pdf
 
22-prompt engineering noted slide shown.pdf
22-prompt engineering noted slide shown.pdf22-prompt engineering noted slide shown.pdf
22-prompt engineering noted slide shown.pdf
 
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leap
 
Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...
Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...
Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...
 
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
 
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power Play
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . ppt
 
Unit 2- Effective stress & Permeability.pdf
Unit 2- Effective stress & Permeability.pdfUnit 2- Effective stress & Permeability.pdf
Unit 2- Effective stress & Permeability.pdf
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
 
Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024
 
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoor
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoorTop Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoor
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoor
 

Demolition Hazards and Controls

  • 1. Group Members Bilal Bhati Muhammad Abbas Usman Tahir Demolition - Hazards and Controls
  • 2. CONTENTS Introduction What is demolition????? Why demolition???? Methods of demolition Steps before demolition Demolition sequence Hazards in demolition work Persons at risk Safety measures Risk control 2
  • 3. WHAT IS DEMOLITION?????  Demolition means dismantling, razing, destroying or wrecking any building or structure or any part by pre-planned and controlled methods.  Demolition is the tearing-down of building and other structures Introduction 3
  • 6. WHY DEMOLITION????  The structures which have already passed their design life need to be reconstruct, for safety and operational requirements.  The old structures need to be demolished for replacement by new structures. 6
  • 7. Methods of Demolition 1. Demolition By Hand 2. Ball And Crane 3. Demolition By Machines 4. Demolition By Hydraulic Rushers 5. Demolition By Explosives 6. Robotic Machines 7
  • 8. 1-Demolition By Hand Demolition is done manually by labor using hammers 8
  • 9. 2-DEMOLITION BY WRECKING BALL  The wrecking ball application consists of a crane equipped with a steel ball.  The deconstruction of the building is by the impact energy of the steel ball suspended from the crawler crane. 9
  • 10. 3-DEMOLITION BY MACHINES  The sequence of demolition by machine is typically the same as the top down manual method, except that most of the demolition is done by mechanical plant. 10
  • 13. 4-DEMOLITION BY HYDRAULIC RUSHERS  The crusher attachment breaks the concrete and the reinforcement by the hydraulic thrust through the long boom arm system.  The hydraulic crusher can be operated from the ground outside the building. This method is also suitable for dangerous buildings, silos and other industrial facilities. 13
  • 16. Columns are fully loaded with explosives 16
  • 17.
  • 18. Pre-blast Considerations  The design may include pre-weakening of the structure, the strategy in placement of the explosives and time delay so that the building will collapse in a safe manner.  Pre-weakening of the structure may include cutting out a portion of the shear walls and other structural elements.  A test blast may be conducted to verify the strength of the structural member and to fine tune the explosive design. 18
  • 21. ADVANCED TECHNIQUES USING ROBOTIC MACHINES  There is a different, specialized approach to every demolition project.  Robotic machines meet these unique challenges.  We have large high reach equipment that has the capability to reach some very high and awkward areas.  Smaller Robotic demolisher machines to get into those tight spots and if a project has some tricky or confined spaces we have robotic equipment on hand to get the job done. 21
  • 24. Factors Affecting Selection of Demolition Method  Type of structure o Size of structure o Available time o Location of structure o Limitation of noise, dust and vibrations o Skills person o Safety o Availability of equipment o Behavior of structure 24
  • 25. Demolition Sequence  All cantilevers structures shall demolished first.  Before demolishing roof , all water tanks and lift rooms shall be demolished first.  Demolition of floor slab shall begin at mid span and proceed towards the supporting beams.  The order of demolition of floor beams shall be as follows  Cantilever beam  Secondary beam  Primary beam  Non load bearing walls and partition walls shall be removed prior to demolition process.  Columns and load bearing walls shall be demolished after removal of beams on top. 25
  • 26. Steps before demolition 1. Surveying 2. Removal of hazardous materials 3. Preparation of plan 4. Hazard Identification 5. Safety measures 26
  • 27. 1-Survey for demolition  For demolition of a building ,detailed survey and assessment of a building is necessary. 1. Building survey Drawing records Material survey Hazardous materials Photographs of a building to be demolished Surrounding buildings Building height, distance from nearby buildings Type of building 27
  • 28. Structural survey Drawing records Special structure Behaviour of structure Structural support system Degree of deterioration 28
  • 29. Asbestos Containing Material  In the case when asbestos containing material are discovered, specialist contractor shall be employed to remove such asbestos containing material. Asbestos Material 2-Removal of hazardous materials: 29
  • 30.  Based on demolition surveys, a demolition plan is prepared . This plan is produced with the application for approval to the local authority.  This plan include  Plan showing the location of a building to be demolished.  Building height, structural system  Proposed sequence of demolition steps  Details of equipments used. 3-Preparation of plan 30
  • 31. 3-Preparation of plan  Extent of damage to the building  Existing structures and facilities in the vicinity  Layout plan  Proposed method of demolition  Safety measures 31
  • 32. Hazards in Demolation Work  Falls from height or on the same level.  Falling debris.  Premature collapse of the structure being demolished.  Dust and fumes.  The silting up of drainage systems by dust.  The problems arising from spilt fuel oils.  Manual handling.  Presence of asbestos and other hazardous substances. 32
  • 33. Hazards in Demolation Work  Noise and vibration from heavy plant and equipment  Electric shock  Pires and explosions from the use of flammable and  Explosive substances  Smoke from burning waste timber  Pneumatic drills and power tools  the existence of services, such as electricity, gas and water  Collision with heavy plant  Plant and vehicles overturning. 33
  • 34. Hazards in Demolation Work Hazard of falling from Height 34
  • 35. Hazards in Demolation Work Falling Hazards 35
  • 37. Hazards in Demolation Work Dust Hazard 37
  • 38. Hazards in Demolation Work Asbestos Dust Hazard is there 38
  • 39. Persons at Risk •Site workers involve in demolition 39
  • 44. Training and Communication:  Demolition workers, including plant or equipment operators, shall go through proper job safety training and be informed of the potential hazards by attending training sessions as well as on-the-job training. Safety measures/Controls 44
  • 45. Safety Measures Equipment Maintenance:  All equipment shall be tested and examined before use. They shall be properly stored and maintained. The equipment shall be inspected daily and results of the inspection shall be recorded accordingly. 45
  • 46. Electrical Safety  A properly connected power source from a local electric utility supplier or a mobile electricity generator shall be utilized in demolition sites. Safety Measures 46
  • 47. Fire:  All flammable goods shall be removed from site unless they are necessary for the works involved. Any remaining flammable goods shall be stored in proper storage facilities. Safety Measures 47
  • 48. Vibration:  Demolition work will cause vibration to neighboring buildings or structures to various extent, depending on the method of demolition, which should be controlled by suitable monitoring. The most serious vibration is caused by implosion. Safety Measures 48
  • 49. Safety Measures Air Pollution:  Concrete breaking, handling of debris and hauling process are main sources of dust from building demolition. Dust mitigation measures, such as water spray, shall be adopted to minimise dust emissions. Burning of waste shall not be allowed.  Diesel fumes generated by mechanical plant or equipment shall be controlled. 49
  • 51. NOISE  Noise pollution arising from the demolition works due the use of powered mechanical equipment such as pneumatic breakers, excavators and generators, loading and transportation of debris, etc. affects the workers, and the sensitive receivers in the vicinity of the demolition site. 51
  • 52. Noise Pollution Use of ear plug/ear defender for avoiding noise pollution 52
  • 53. DEBRIS AND WASTE HANDLING 53
  • 54. PROTECTIVE SCREENS  Protective screen covers shall be placed, where necessary, to prevent flying pieces from injuring the fellow workmen. 54
  • 55. Personel Protective Equipments Protection of worker with PPE is very important.PPE s come in the last as safety measures. 55
  • 56. Personel Protective Equipments Use of hard hat gloves safety shoes glasses jacket ear plug must be compulsory 56
  • 57. Safety Signs Safety signs must be thear to aware the Persons at work and public 57
  • 58. Table of Hazardous activites Pesrsons at Risk and Control Measures Activity:- What is Hazard? Harm:- Who or What? Safety Measure/ What are you doing? Public Entering Site Injuries To Persons Site Must be Securely Fenced off and Locked at the end of working day. Signage Warning of Danger Gas/Elec Explosion/Fire/Shoks Services To Be disconnected and Confirmed to be disconnected by Liacensed Person. Working at height/ Fall From Height Injury To Persons Use of Scaffolding , Use of Fall arrest System. 58
  • 59. Table of Hazardous activites Pesrsons at Risk and Control Measures Activity:- What is Hazard? Harm:- Who or What? Safety Measure/ What are you doing? Road users and Padestrians During movement of lorries Injury To Persons Use of Banks man at all times warning signs and Physical Barriears General site Hazards like dust and cuts. Injury To Persons Use of PPE,s at all times. Dust suppression system Planned,Full site Coverage of water mist when required. Manual Handeling Injury To Persons All Times to be checked before manual lifting. Slips/Trips Injury To Persons Good House Keeping/Remove All Trip Hazards 59
  • 60. Table of Hazardous activites Pesrsons at Risk and Control Measures Activity:- What is Hazard? Harm:- Who or What? Safety Measure/ What are you doing? Falling Massonary uncontrolled Collapse Site Opperative, Possible Public Whilst Carrying out the soft strip state of the contract the structural stability will be assessed. If any part of the building is deemed at risk then All persons are to be evacuated and mechanical means use to remove and make safe any required area of the building 60
  • 61. Conclusion  Demolition is the most dangerous/hazardous activity as compare to the other civil activities.  Demolition must be wellplanned to avoid fatalities and injuries  Development in techniques allows rapid demolition with no harm to the environment. 61
  • 62. Conclusion  It can be concluded that demolishing/imploding the building structure will prove very useful, economical and quickest for reconstruction.  Leads to a safe and controlled demolition for the occupants and neighbourhood. 62
  • 63. References  http://www.implosionworld.com/history.html  www.wikipedia.com  http://archsd.gov.hk/media/11640/demolition_e2004.pdf  http://wiki.iricen.gov.in/doku/lib/exe/fetch.php?media=m %E0%A4%BEr%E0%A5%8Dc_march_2013:achuta_ra o.pdf  http://www.concreteconstruction.net/Images/Demolition %20of%20Concrete%20Structures_tcm45-341335.pdf  https://www.cdc.gov/niosh/topics/noisecontrol/  https://www.pinterest.com/pin/854065516804139130/ 63