2. Contents
— Power Energy in Russia
— IEC 61850 implementations
— IEC 61850 vendors
— IEC 61850 researches
— WG Meeting Host
2
3. Power Energy Sector in Russia
After the Reform
Infrastructure Sphere of Competition
Market Council Nuclear Power Stations
Federal Grid Company of RusHydro
Unified Energy System Wholesale Generation Companies
Holding of Interregional (6 companies)
Distribution Companies Territorial Generation Companies
System Operator (14 companies)
Other Generation Companies
Sales Companies
Repair and Maintenance Companies
Generation Company
of The Far East
3
4. Some Facts
Electric Energy Production in 2009 — 957.02·109 kW·h
Installed Power Generation Capacity — >156 GW
Total Transmission Substation Capacity — 310,000 MVA
Overall Transmission Line Distance — 120,000 km
Overall Distribution Line Distance — 2,000,000 km
4
5. Implementations of IEC 61850
in Russia
First First
Implementation: Implementation:
Substation 500 kV Substation 500 kV
“Alyuminievaya” “Alyuminievaya”
2006 2006
5
6. Implementations of IEC 61850
in Russia
All substations of
“The Moscow Ring
500 kV”
GOOSE (Copper Wire
Backup)
MMS
6
7. IEC 61850 Vendors in Russia
Protective Relaying
EKRA, Radius Automatika, Mehanotronica,
Dynamics, Bresler and more…
SCADA and Automation
RTSoft, ProSoft Systems, Novintech,
Energopromautomation and more…
Merging Units and Metering Equipment
Continuum +, Energoautomatika, UFD
7
8. IEC 61850 Researches
IEC 61850 Competence Centre of Moscow
Power Engineering University
MPEI
NettedAutomation
STRI
WG 10 TC 57 Members:
Alex Golovin
Aleksey Anoshin
8