RAJEEV INSTITUTE OF TECHNOLOGY
HASSAN
Department of Civil Engineering
TECHNICAL SEMINAR
on
“CASE STUDY ON SIGNATURE BRIDGE”
Under the guidance of
Mrs. RASHMI A S
Assistant Professor
Presented by:
TEJAS D A
4RA16CV107
1
2
CONTENTS
1. INTRODUCTION
2. COMPONENTS OF SIGNATURE BRIDGE
3. ASSESMENTS AND ERRECTION
4. CONCLUSION
3
Introduction
Signature bridge:
• The Signature Bridge is a cantilever spar cable-stayed bridge. It
spans the Yamuna river at Wazirabad section, connecting Wazirabad
to East Delhi.
• It is India's first asymmetrical cable-stayed bridge.
• The pylon of the Signature bridge is the tallest structure in Delhi
and is double the height of Qutb Minar with its 154-metre high
viewing box, which acts as selfie points for visitors. It shortens the
travel time between north and northeast Delhi.
• This bridge is self-anchored bridge in which cables are anchored at
the deck level. Main advantage of this self-anchored bridge is that it
allow transmission of forces from backstays to deck with rendering
the deck self-equilibrated in the longitudinal direction.
4
Signature bridge
Areal view of Signature bridge
Detail of the bridge
• Structural Design Firm: Schlaich Bergermann Partner
• Contractor: Joint Venture Gammon India[6][13] and Tensa India
Construtora Cidade
• Main span: 251 m
• Height of pylon: 165 m above ground
• Total length of infrastructure project: 6 km (approx.)
• Lanes: 2 x 4
• Deck surface: 25,000 m2
• Total length of bridge: 675 m (incl. 100 m west extension)
• Side spans: 36 m
• Structural steel pylon: 5800 tonne
• Structural steel deck: 7400 tonne
• Open foundation: 6 nos.
• Closed foundation: 16 nos.
5
Components of signature bridge
6
Detail of components
Foundation:
The final structure concluded for 23 foundation Out of which 16 wells of 8-9
m diameter sunk up to the level 500 mm above the highest rock level with
sixteen 1.20 m diameter piles inserted through the walls of the well embedded
up to 6m into rock on each wells, a combined tie beam of 4.5 m deep and 42 m
x 17.5 m sizes on top of the well connecting the wells, piles and piers
constructed on top of the same.
7
Bearings:
There are 20 free spherical bearings, two large fixed bearings under
pylon legs of the capacity of 17,000t, two numbers of longitudinally
guided spherical bearings at the location of expansion joimts to
enable reversible momvement of 270mm and rock bearing under
backstay anchor foundation, which can tranfere the tensile faorce of
6,380t within main cable stay system. The two inclined pillars merge
at half height of the pylon. Above that point, the backstay cables and
the inclined cables lead into the pylon.
.
Deck:
Two carriage way, typically 14m wide and separated by a concrete crash barriers as
well as two lateral emergency pathways, from the deck of the bridge that total 35.2m in
width. Each of the carriage way accommodates four traffic lanes. The deck is formed of
outer I-shaped longitudinal main girders at 4.5m intervals. A third central nain girder is
placed to distribute heavy truck loads onto the several cross girders. All structural steel
is grade S355. Shop welding and site splices with high strength friction grip bolts will
be used. The deck is transversally supported on both ends of the bridge and at the
pylon. The only longitudinal movement of the deck at its western end is 250mm
approximately.
Cables:
The deck is supported by two cable planes. The cables are directly anchored to
the webs of the outer main girders at 13.5 meter distances with their dead end,
and are stressed with in the stressing chamber at the top of the pylon. The
cables will be made up of bundles of parallel 0.6'' strands grsde 1770.
depending on the location the number of strands per cable varies from 55 to
123 no. at the main span end is 127no. for each of the backstays. corrosion
protection will be international practice i.e., with hot dip galvanized wires and
individually coated strands that are covered by an PEpipe. In the backstay area
the lower part of the cables will be covered with steel tubes for fire protection.
10
Fabrication
• Construction of the super structure involved fabrication and erection of about
14,500Mt of structural steel for permanent structure. The pylon with its harp shaped
body , leaning backwards, would be the most unstable structure during construction
stage.
• Pylon is complex structure having inclination in all directions. It is made up of
irregular pannels wleded out of varying steel plates of different grades. To
thoroughly understand the complexities of the structure , dimensional weights of
the elements to be fabricated, transported and erected, a true-to-scale digital model
of the bridge was prepared in Tekla.
• Some of the major challenges involved as using plat thickness ranging from 2.5 to
250mm including Z quality steel and drilling almost 8,50,000 holes for HSFG bolts
ranging from 12mm to 36mm in plates upto 120mm thick.
• To ensure fabrication accuracy many test were carried out like Dye penetration test,
ultrasonic test etc.
11
• Two methods for drilling of holes were specially devised. Pre-drilled holes on web
plate of the connection during panel fabrication and post-drilling for other holes
which are marked and drilled with template after fit-up, welding, rectification and
milling of segments.
• All the compression joints were designed to transfer load through bearing contact
surface along with the splice connection.
• The pylon included three parts; steel segments, main body , pylon head segments.
• Steel leg was divided into 11 large segments, main body was divided into 5 large
segments, front cable pylon was divide into 5 large segments.
• The fabrication of pylon included base fabrication, leg fabrication, main body
fabrication band back body segments fabrication.
• Fabrication and erection of segments were divided into 3 parts: panelling
fabrication, shop assembly and trial assembly bon site into large blocks for erection,
erection and bolt connection on site.
12
Erection
• The pylon is composed of two legs,box girders, inclined backwards and inward and
connected at a level of 63m by a main body that is vertical shaft with variable cross
section which hosts the top anchorages for the stay cables. The legs have
rectangular box girder with a constant width of 2.50m and height varying from 7.20
to 9.60m.
• The pylon was divided into segment with weights varying from 40t to 250t. The
joints between the segments were flanged bolted joints with machined flnages.
• After working out several alternative, it was proposed to erect pylon using 1,250t
crawler crane, while the pylon would be supported with a specially designed
temporary struts until the system is stable after installation of permanent cables.
Segments weighting more than 40t to 250t were required to be erected.
• Pre-cast deck panels were erected over girders using the Goliath gantry for deck
erection towards the river side .
• For correct positioning, with double inclination, of pylon segments was achieved by
a specially designed turn table.
13
• Structural geometry was checked at installation of every element and daily survey
procedure started at the beginning of stay caboe stressing.
• While monitoring the effect of construction lodings, element loadings and cable
stressing on deformation of pylon and decks, the following correction factors of the
environmental effects had to be applied. The pylon position changed rapidly during
the day, with movements around 20mm in the longitudinal and vertical direction
and upto 40mm in transverse direction.
• Stay cable consists of 19 pairs of cables with varying number of stands minimum
being 55 to maximun 127 of 15.70 mm dia with GUTS of 1,770Mpa.
• Stay cable strands preparation consists of pulling out the strand from coil drum,
laying on the bench , uncoating, cutting and marking for identification.
• Strands in the cables were tensioned using iso-elongation method. This method
utilise Moni strand jack attached with a load cell, hydraulic pump, dynamometer for
calibration of pump-jack system.
• A topographic survey of the bridge during each stressing phase was provided. After
reaching 80% of the stressing force in each phase, new elongation to be applied to
the strand had to be provided considering the actual load registered and the data
collected from the topographic survey.
14
Inference
It symbolises the standard for iconism in India.
3-dimensionally varying pylons being attempted
first time and over comes many other complex
issues by proper construction engineering.
15
16
THANK
YOU

More Related Content

What's hot

Civil Engineering Internship Presentation-Anis Rahman Khokan
Civil Engineering Internship Presentation-Anis Rahman KhokanCivil Engineering Internship Presentation-Anis Rahman Khokan
Civil Engineering Internship Presentation-Anis Rahman KhokanAnis Rahman Khokan
 
TRAINING REPORT ON COSTRUCTION OF FLYOVER FROM MITHAPUR TO CHIRIYATAND (BIHAR)
TRAINING REPORT ON  COSTRUCTION OF FLYOVER FROM  MITHAPUR TO CHIRIYATAND (BIHAR)TRAINING REPORT ON  COSTRUCTION OF FLYOVER FROM  MITHAPUR TO CHIRIYATAND (BIHAR)
TRAINING REPORT ON COSTRUCTION OF FLYOVER FROM MITHAPUR TO CHIRIYATAND (BIHAR)vishal prakash
 
Industrial project report ppt CIVIL ENGINEERING
Industrial project report ppt CIVIL ENGINEERINGIndustrial project report ppt CIVIL ENGINEERING
Industrial project report ppt CIVIL ENGINEERINGJAPJEETSINGH13
 
HIGH FLOOD LEVEL BRIDGE CONSTRUCTION
HIGH FLOOD LEVEL BRIDGE CONSTRUCTIONHIGH FLOOD LEVEL BRIDGE CONSTRUCTION
HIGH FLOOD LEVEL BRIDGE CONSTRUCTIONTEJPRAKASH KUMAWAT
 
A project report on flyover internship bihar rajya pul nirman nigam limited p...
A project report on flyover internship bihar rajya pul nirman nigam limited p...A project report on flyover internship bihar rajya pul nirman nigam limited p...
A project report on flyover internship bihar rajya pul nirman nigam limited p...Prashant Shaurabh
 
Presentation on construction of cable stay bridge - a modern technique for su...
Presentation on construction of cable stay bridge - a modern technique for su...Presentation on construction of cable stay bridge - a modern technique for su...
Presentation on construction of cable stay bridge - a modern technique for su...Rajesh Prasad
 
cellular lightweight concrete ppt
cellular lightweight concrete pptcellular lightweight concrete ppt
cellular lightweight concrete pptShubhamKumar687939
 
Concrete Road
Concrete RoadConcrete Road
Concrete RoadKp Ahm
 
Site visit road constraction
Site visit road constraction Site visit road constraction
Site visit road constraction Samitha Dilshan
 
Prefabrication​ structure ppt
Prefabrication​ structure pptPrefabrication​ structure ppt
Prefabrication​ structure pptAbhishekM45
 
Fly ash and silica fume concrete mix design
Fly ash and silica fume concrete mix design Fly ash and silica fume concrete mix design
Fly ash and silica fume concrete mix design Saiduluthota
 
Design of multistorey building
Design of multistorey buildingDesign of multistorey building
Design of multistorey buildingSivaji Djpk
 
Pre stressed concrete Bridge
Pre stressed concrete BridgePre stressed concrete Bridge
Pre stressed concrete BridgeShubham Das
 
Schedule of Rates
Schedule of RatesSchedule of Rates
Schedule of RatesRaj Shah
 
signature bridge short presentation
signature bridge short presentationsignature bridge short presentation
signature bridge short presentationPravin Gaurav
 

What's hot (20)

Civil Engineering Internship Presentation-Anis Rahman Khokan
Civil Engineering Internship Presentation-Anis Rahman KhokanCivil Engineering Internship Presentation-Anis Rahman Khokan
Civil Engineering Internship Presentation-Anis Rahman Khokan
 
Bituminous Road
 Bituminous Road Bituminous Road
Bituminous Road
 
TRAINING REPORT ON COSTRUCTION OF FLYOVER FROM MITHAPUR TO CHIRIYATAND (BIHAR)
TRAINING REPORT ON  COSTRUCTION OF FLYOVER FROM  MITHAPUR TO CHIRIYATAND (BIHAR)TRAINING REPORT ON  COSTRUCTION OF FLYOVER FROM  MITHAPUR TO CHIRIYATAND (BIHAR)
TRAINING REPORT ON COSTRUCTION OF FLYOVER FROM MITHAPUR TO CHIRIYATAND (BIHAR)
 
Industrial project report ppt CIVIL ENGINEERING
Industrial project report ppt CIVIL ENGINEERINGIndustrial project report ppt CIVIL ENGINEERING
Industrial project report ppt CIVIL ENGINEERING
 
HIGH FLOOD LEVEL BRIDGE CONSTRUCTION
HIGH FLOOD LEVEL BRIDGE CONSTRUCTIONHIGH FLOOD LEVEL BRIDGE CONSTRUCTION
HIGH FLOOD LEVEL BRIDGE CONSTRUCTION
 
A project report on flyover internship bihar rajya pul nirman nigam limited p...
A project report on flyover internship bihar rajya pul nirman nigam limited p...A project report on flyover internship bihar rajya pul nirman nigam limited p...
A project report on flyover internship bihar rajya pul nirman nigam limited p...
 
Presentation on construction of cable stay bridge - a modern technique for su...
Presentation on construction of cable stay bridge - a modern technique for su...Presentation on construction of cable stay bridge - a modern technique for su...
Presentation on construction of cable stay bridge - a modern technique for su...
 
cellular lightweight concrete ppt
cellular lightweight concrete pptcellular lightweight concrete ppt
cellular lightweight concrete ppt
 
Signature bridge ppt2
Signature bridge ppt2Signature bridge ppt2
Signature bridge ppt2
 
Concrete Road
Concrete RoadConcrete Road
Concrete Road
 
Site visit road constraction
Site visit road constraction Site visit road constraction
Site visit road constraction
 
Mix design-ppt
Mix design-pptMix design-ppt
Mix design-ppt
 
Prefabrication​ structure ppt
Prefabrication​ structure pptPrefabrication​ structure ppt
Prefabrication​ structure ppt
 
Fly ash and silica fume concrete mix design
Fly ash and silica fume concrete mix design Fly ash and silica fume concrete mix design
Fly ash and silica fume concrete mix design
 
Design of multistorey building
Design of multistorey buildingDesign of multistorey building
Design of multistorey building
 
Self curing concrete
Self curing concreteSelf curing concrete
Self curing concrete
 
Classification of bridges
Classification of bridgesClassification of bridges
Classification of bridges
 
Pre stressed concrete Bridge
Pre stressed concrete BridgePre stressed concrete Bridge
Pre stressed concrete Bridge
 
Schedule of Rates
Schedule of RatesSchedule of Rates
Schedule of Rates
 
signature bridge short presentation
signature bridge short presentationsignature bridge short presentation
signature bridge short presentation
 

Similar to Case study on signature bridge ppt (1)

Millau via duct presentation full analysis
Millau via duct presentation full analysisMillau via duct presentation full analysis
Millau via duct presentation full analysisMohammad Ali
 
Bandra Worli sea link
Bandra Worli sea linkBandra Worli sea link
Bandra Worli sea linkKAVYA H
 
Calculation note suez canal cable stayed bridge
Calculation note suez canal cable stayed bridgeCalculation note suez canal cable stayed bridge
Calculation note suez canal cable stayed bridgeMohammed Abdelkawy
 
Calculation Note Final
Calculation Note FinalCalculation Note Final
Calculation Note FinalMohamed Elfike
 
Nhpc training report civil engineerimg_bit_mesra_ISHANT GAUTAM
Nhpc training report civil engineerimg_bit_mesra_ISHANT GAUTAMNhpc training report civil engineerimg_bit_mesra_ISHANT GAUTAM
Nhpc training report civil engineerimg_bit_mesra_ISHANT GAUTAMIshant Gautam.
 
stress ribbon bridge.pptx
stress ribbon bridge.pptxstress ribbon bridge.pptx
stress ribbon bridge.pptxSauravShahane
 
Experimental study of precast portal frame
Experimental study of precast portal frameExperimental study of precast portal frame
Experimental study of precast portal frameSatish Kambaliya
 
BALANCED CANTILEVER BRIDGE
BALANCED CANTILEVER BRIDGEBALANCED CANTILEVER BRIDGE
BALANCED CANTILEVER BRIDGEsrinivas cnu
 
well foundation of six lane new ganga bridge near kacchi dargah in district P...
well foundation of six lane new ganga bridge near kacchi dargah in district P...well foundation of six lane new ganga bridge near kacchi dargah in district P...
well foundation of six lane new ganga bridge near kacchi dargah in district P...Arman Hashmi
 
Busan geoje fixed link
Busan   geoje fixed linkBusan   geoje fixed link
Busan geoje fixed linkVicky Matwan
 
Cable anchoring and grouting for cable tensioning
Cable anchoring and grouting for cable tensioningCable anchoring and grouting for cable tensioning
Cable anchoring and grouting for cable tensioningChinnuNinan
 
Chenab Bridge.pdf
Chenab Bridge.pdfChenab Bridge.pdf
Chenab Bridge.pdfPpt Creater
 
Dhruvin kurilpa bridge
Dhruvin kurilpa bridgeDhruvin kurilpa bridge
Dhruvin kurilpa bridgeDhruv Seth
 

Similar to Case study on signature bridge ppt (1) (20)

Millau via duct presentation full analysis
Millau via duct presentation full analysisMillau via duct presentation full analysis
Millau via duct presentation full analysis
 
THE CONSTRUCTION PROCEDURE AND ADVANTAGE OF THE RAIL CABLE-LIFTING CONSTRUCTI...
THE CONSTRUCTION PROCEDURE AND ADVANTAGE OF THE RAIL CABLE-LIFTING CONSTRUCTI...THE CONSTRUCTION PROCEDURE AND ADVANTAGE OF THE RAIL CABLE-LIFTING CONSTRUCTI...
THE CONSTRUCTION PROCEDURE AND ADVANTAGE OF THE RAIL CABLE-LIFTING CONSTRUCTI...
 
the millau viaduct
the millau viaductthe millau viaduct
the millau viaduct
 
Millau viaduct
Millau viaductMillau viaduct
Millau viaduct
 
Bandra Worli sea link
Bandra Worli sea linkBandra Worli sea link
Bandra Worli sea link
 
Calculation note suez canal cable stayed bridge
Calculation note suez canal cable stayed bridgeCalculation note suez canal cable stayed bridge
Calculation note suez canal cable stayed bridge
 
Calculation Note Final
Calculation Note FinalCalculation Note Final
Calculation Note Final
 
Nhpc training report civil engineerimg_bit_mesra_ISHANT GAUTAM
Nhpc training report civil engineerimg_bit_mesra_ISHANT GAUTAMNhpc training report civil engineerimg_bit_mesra_ISHANT GAUTAM
Nhpc training report civil engineerimg_bit_mesra_ISHANT GAUTAM
 
stress ribbon bridge.pptx
stress ribbon bridge.pptxstress ribbon bridge.pptx
stress ribbon bridge.pptx
 
Cable stayed bridge
Cable stayed bridgeCable stayed bridge
Cable stayed bridge
 
Segmental bridge construction
Segmental bridge constructionSegmental bridge construction
Segmental bridge construction
 
Experimental study of precast portal frame
Experimental study of precast portal frameExperimental study of precast portal frame
Experimental study of precast portal frame
 
BALANCED CANTILEVER BRIDGE
BALANCED CANTILEVER BRIDGEBALANCED CANTILEVER BRIDGE
BALANCED CANTILEVER BRIDGE
 
Bridge-SIT-01.pptx
Bridge-SIT-01.pptxBridge-SIT-01.pptx
Bridge-SIT-01.pptx
 
well foundation of six lane new ganga bridge near kacchi dargah in district P...
well foundation of six lane new ganga bridge near kacchi dargah in district P...well foundation of six lane new ganga bridge near kacchi dargah in district P...
well foundation of six lane new ganga bridge near kacchi dargah in district P...
 
Busan geoje fixed link
Busan   geoje fixed linkBusan   geoje fixed link
Busan geoje fixed link
 
Cable anchoring and grouting for cable tensioning
Cable anchoring and grouting for cable tensioningCable anchoring and grouting for cable tensioning
Cable anchoring and grouting for cable tensioning
 
Bandra worli sealink pdf
Bandra worli sealink pdfBandra worli sealink pdf
Bandra worli sealink pdf
 
Chenab Bridge.pdf
Chenab Bridge.pdfChenab Bridge.pdf
Chenab Bridge.pdf
 
Dhruvin kurilpa bridge
Dhruvin kurilpa bridgeDhruvin kurilpa bridge
Dhruvin kurilpa bridge
 

More from varun km

accelerated bridge construction(ABC)
accelerated bridge construction(ABC)accelerated bridge construction(ABC)
accelerated bridge construction(ABC)varun km
 
smart village report
smart village reportsmart village report
smart village reportvarun km
 
3 d printed building technology report
 3 d printed building technology report 3 d printed building technology report
3 d printed building technology reportvarun km
 
Accelerated Bridge Construction( ABC)
Accelerated Bridge  Construction( ABC)Accelerated Bridge  Construction( ABC)
Accelerated Bridge Construction( ABC)varun km
 
POLYETHYLENE CONCRETE
POLYETHYLENE CONCRETEPOLYETHYLENE CONCRETE
POLYETHYLENE CONCRETEvarun km
 
3d printed building technology
3d printed building technology3d printed building technology
3d printed building technologyvarun km
 

More from varun km (6)

accelerated bridge construction(ABC)
accelerated bridge construction(ABC)accelerated bridge construction(ABC)
accelerated bridge construction(ABC)
 
smart village report
smart village reportsmart village report
smart village report
 
3 d printed building technology report
 3 d printed building technology report 3 d printed building technology report
3 d printed building technology report
 
Accelerated Bridge Construction( ABC)
Accelerated Bridge  Construction( ABC)Accelerated Bridge  Construction( ABC)
Accelerated Bridge Construction( ABC)
 
POLYETHYLENE CONCRETE
POLYETHYLENE CONCRETEPOLYETHYLENE CONCRETE
POLYETHYLENE CONCRETE
 
3d printed building technology
3d printed building technology3d printed building technology
3d printed building technology
 

Recently uploaded

notes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptnotes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptMsecMca
 
Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...
Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...
Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...soginsider
 
Minimum and Maximum Modes of microprocessor 8086
Minimum and Maximum Modes of microprocessor 8086Minimum and Maximum Modes of microprocessor 8086
Minimum and Maximum Modes of microprocessor 8086anil_gaur
 
Engineering Drawing focus on projection of planes
Engineering Drawing focus on projection of planesEngineering Drawing focus on projection of planes
Engineering Drawing focus on projection of planesRAJNEESHKUMAR341697
 
+97470301568>> buy weed in qatar,buy thc oil qatar,buy weed and vape oil in d...
+97470301568>> buy weed in qatar,buy thc oil qatar,buy weed and vape oil in d...+97470301568>> buy weed in qatar,buy thc oil qatar,buy weed and vape oil in d...
+97470301568>> buy weed in qatar,buy thc oil qatar,buy weed and vape oil in d...Health
 
Introduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaIntroduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaOmar Fathy
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfJiananWang21
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VDineshKumar4165
 
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills KuwaitKuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwaitjaanualu31
 
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKARHAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKARKOUSTAV SARKAR
 
Air Compressor reciprocating single stage
Air Compressor reciprocating single stageAir Compressor reciprocating single stage
Air Compressor reciprocating single stageAbc194748
 
DC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationDC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationBhangaleSonal
 
AIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech studentsAIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech studentsvanyagupta248
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapRishantSharmaFr
 
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptxS1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptxSCMS School of Architecture
 
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Arindam Chakraborty, Ph.D., P.E. (CA, TX)
 
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptxA CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptxmaisarahman1
 

Recently uploaded (20)

notes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptnotes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.ppt
 
Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...
Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...
Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...
 
Minimum and Maximum Modes of microprocessor 8086
Minimum and Maximum Modes of microprocessor 8086Minimum and Maximum Modes of microprocessor 8086
Minimum and Maximum Modes of microprocessor 8086
 
Engineering Drawing focus on projection of planes
Engineering Drawing focus on projection of planesEngineering Drawing focus on projection of planes
Engineering Drawing focus on projection of planes
 
+97470301568>> buy weed in qatar,buy thc oil qatar,buy weed and vape oil in d...
+97470301568>> buy weed in qatar,buy thc oil qatar,buy weed and vape oil in d...+97470301568>> buy weed in qatar,buy thc oil qatar,buy weed and vape oil in d...
+97470301568>> buy weed in qatar,buy thc oil qatar,buy weed and vape oil in d...
 
Introduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaIntroduction to Serverless with AWS Lambda
Introduction to Serverless with AWS Lambda
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdf
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - V
 
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills KuwaitKuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
 
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced LoadsFEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
 
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKARHAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
 
Air Compressor reciprocating single stage
Air Compressor reciprocating single stageAir Compressor reciprocating single stage
Air Compressor reciprocating single stage
 
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
 
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
 
DC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationDC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equation
 
AIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech studentsAIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech students
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leap
 
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptxS1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
 
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
 
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptxA CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
 

Case study on signature bridge ppt (1)

  • 1. RAJEEV INSTITUTE OF TECHNOLOGY HASSAN Department of Civil Engineering TECHNICAL SEMINAR on “CASE STUDY ON SIGNATURE BRIDGE” Under the guidance of Mrs. RASHMI A S Assistant Professor Presented by: TEJAS D A 4RA16CV107 1
  • 2. 2 CONTENTS 1. INTRODUCTION 2. COMPONENTS OF SIGNATURE BRIDGE 3. ASSESMENTS AND ERRECTION 4. CONCLUSION
  • 3. 3 Introduction Signature bridge: • The Signature Bridge is a cantilever spar cable-stayed bridge. It spans the Yamuna river at Wazirabad section, connecting Wazirabad to East Delhi. • It is India's first asymmetrical cable-stayed bridge. • The pylon of the Signature bridge is the tallest structure in Delhi and is double the height of Qutb Minar with its 154-metre high viewing box, which acts as selfie points for visitors. It shortens the travel time between north and northeast Delhi. • This bridge is self-anchored bridge in which cables are anchored at the deck level. Main advantage of this self-anchored bridge is that it allow transmission of forces from backstays to deck with rendering the deck self-equilibrated in the longitudinal direction.
  • 4. 4 Signature bridge Areal view of Signature bridge
  • 5. Detail of the bridge • Structural Design Firm: Schlaich Bergermann Partner • Contractor: Joint Venture Gammon India[6][13] and Tensa India Construtora Cidade • Main span: 251 m • Height of pylon: 165 m above ground • Total length of infrastructure project: 6 km (approx.) • Lanes: 2 x 4 • Deck surface: 25,000 m2 • Total length of bridge: 675 m (incl. 100 m west extension) • Side spans: 36 m • Structural steel pylon: 5800 tonne • Structural steel deck: 7400 tonne • Open foundation: 6 nos. • Closed foundation: 16 nos. 5
  • 7. Detail of components Foundation: The final structure concluded for 23 foundation Out of which 16 wells of 8-9 m diameter sunk up to the level 500 mm above the highest rock level with sixteen 1.20 m diameter piles inserted through the walls of the well embedded up to 6m into rock on each wells, a combined tie beam of 4.5 m deep and 42 m x 17.5 m sizes on top of the well connecting the wells, piles and piers constructed on top of the same. 7
  • 8. Bearings: There are 20 free spherical bearings, two large fixed bearings under pylon legs of the capacity of 17,000t, two numbers of longitudinally guided spherical bearings at the location of expansion joimts to enable reversible momvement of 270mm and rock bearing under backstay anchor foundation, which can tranfere the tensile faorce of 6,380t within main cable stay system. The two inclined pillars merge at half height of the pylon. Above that point, the backstay cables and the inclined cables lead into the pylon.
  • 9. . Deck: Two carriage way, typically 14m wide and separated by a concrete crash barriers as well as two lateral emergency pathways, from the deck of the bridge that total 35.2m in width. Each of the carriage way accommodates four traffic lanes. The deck is formed of outer I-shaped longitudinal main girders at 4.5m intervals. A third central nain girder is placed to distribute heavy truck loads onto the several cross girders. All structural steel is grade S355. Shop welding and site splices with high strength friction grip bolts will be used. The deck is transversally supported on both ends of the bridge and at the pylon. The only longitudinal movement of the deck at its western end is 250mm approximately.
  • 10. Cables: The deck is supported by two cable planes. The cables are directly anchored to the webs of the outer main girders at 13.5 meter distances with their dead end, and are stressed with in the stressing chamber at the top of the pylon. The cables will be made up of bundles of parallel 0.6'' strands grsde 1770. depending on the location the number of strands per cable varies from 55 to 123 no. at the main span end is 127no. for each of the backstays. corrosion protection will be international practice i.e., with hot dip galvanized wires and individually coated strands that are covered by an PEpipe. In the backstay area the lower part of the cables will be covered with steel tubes for fire protection. 10
  • 11. Fabrication • Construction of the super structure involved fabrication and erection of about 14,500Mt of structural steel for permanent structure. The pylon with its harp shaped body , leaning backwards, would be the most unstable structure during construction stage. • Pylon is complex structure having inclination in all directions. It is made up of irregular pannels wleded out of varying steel plates of different grades. To thoroughly understand the complexities of the structure , dimensional weights of the elements to be fabricated, transported and erected, a true-to-scale digital model of the bridge was prepared in Tekla. • Some of the major challenges involved as using plat thickness ranging from 2.5 to 250mm including Z quality steel and drilling almost 8,50,000 holes for HSFG bolts ranging from 12mm to 36mm in plates upto 120mm thick. • To ensure fabrication accuracy many test were carried out like Dye penetration test, ultrasonic test etc. 11
  • 12. • Two methods for drilling of holes were specially devised. Pre-drilled holes on web plate of the connection during panel fabrication and post-drilling for other holes which are marked and drilled with template after fit-up, welding, rectification and milling of segments. • All the compression joints were designed to transfer load through bearing contact surface along with the splice connection. • The pylon included three parts; steel segments, main body , pylon head segments. • Steel leg was divided into 11 large segments, main body was divided into 5 large segments, front cable pylon was divide into 5 large segments. • The fabrication of pylon included base fabrication, leg fabrication, main body fabrication band back body segments fabrication. • Fabrication and erection of segments were divided into 3 parts: panelling fabrication, shop assembly and trial assembly bon site into large blocks for erection, erection and bolt connection on site. 12
  • 13. Erection • The pylon is composed of two legs,box girders, inclined backwards and inward and connected at a level of 63m by a main body that is vertical shaft with variable cross section which hosts the top anchorages for the stay cables. The legs have rectangular box girder with a constant width of 2.50m and height varying from 7.20 to 9.60m. • The pylon was divided into segment with weights varying from 40t to 250t. The joints between the segments were flanged bolted joints with machined flnages. • After working out several alternative, it was proposed to erect pylon using 1,250t crawler crane, while the pylon would be supported with a specially designed temporary struts until the system is stable after installation of permanent cables. Segments weighting more than 40t to 250t were required to be erected. • Pre-cast deck panels were erected over girders using the Goliath gantry for deck erection towards the river side . • For correct positioning, with double inclination, of pylon segments was achieved by a specially designed turn table. 13
  • 14. • Structural geometry was checked at installation of every element and daily survey procedure started at the beginning of stay caboe stressing. • While monitoring the effect of construction lodings, element loadings and cable stressing on deformation of pylon and decks, the following correction factors of the environmental effects had to be applied. The pylon position changed rapidly during the day, with movements around 20mm in the longitudinal and vertical direction and upto 40mm in transverse direction. • Stay cable consists of 19 pairs of cables with varying number of stands minimum being 55 to maximun 127 of 15.70 mm dia with GUTS of 1,770Mpa. • Stay cable strands preparation consists of pulling out the strand from coil drum, laying on the bench , uncoating, cutting and marking for identification. • Strands in the cables were tensioned using iso-elongation method. This method utilise Moni strand jack attached with a load cell, hydraulic pump, dynamometer for calibration of pump-jack system. • A topographic survey of the bridge during each stressing phase was provided. After reaching 80% of the stressing force in each phase, new elongation to be applied to the strand had to be provided considering the actual load registered and the data collected from the topographic survey. 14
  • 15. Inference It symbolises the standard for iconism in India. 3-dimensionally varying pylons being attempted first time and over comes many other complex issues by proper construction engineering. 15