Welcome 
Investigation of Basement Flooding and 
Stormwater Runoff Quality Control 
Study Areas 24, 25, 26 and 27 
(Yonge Street & Sheppard Avenue Area) 
Public Information Centre #2 
View displays and discuss the study with project staff 
Feel free to ask questions and fill out a comment sheet
Purpose of Tonight’s Meeting 
• Provide background on the study. 
• Present the findings of the study. 
• Present the recommended solutions for Study Areas 
24, 25, 26 and 27. 
• Receive your comments. 
• Outline the next steps in the study. 
• We want to hear from you! Your input is very 
important.
Purpose of Our Study 
• Examine existing stormwater drainage 
and sanitary sewer systems and identify 
the causes of basement flooding and/or 
surface flooding (severe ponding on 
streets during extreme storms). 
• Assess control measures to improve the 
quality of stormwater surface runoff as per 
the City’s Wet Weather Flow Master Plan. 
• Make recommendations to: 
 Reduce the risk of future flooding; 
and, 
 Improve the quality of stormwater 
runoff before it is discharged to the 
West Don River and/or its tributaries.
Study Area 24 
• Study Area 24 has been subject to 
pockets of basement and surface 
flooding incidents during major storms 
in May 2000, August 2005, and 
May/July 2013. 
• Three (3) storm sewer outfalls 
discharge stormwater runoff to 
tributaries of Don River West Branch. 
#24-1 
#24-2 
Outfall #24-1 Outfall #24-2 
#24-3
Study Area 25 
• Study Area 25 has been subject to 
pockets of basement and surface flooding 
incidents during major storms, including 
storms in May 2000, August 2005, and 
May/July 2013. 
• Eight (8) storm sewer outfalls discharge 
stormwater runoff to tributaries of Don 
River West Branch. 
#25-1 
#25-2 
#25-4 #25-3 
#25-6 
#25-8 
#25-7 
Outfall #25-1 
Outfall #25-2 
Outfall #25-3 
Outfall #25-4 
Outfall #25-5 
Outfall #25-6 
Outfall #25-7 
Outfall #25-8 
#25-5
Study Area 26 
• Study Area 26 has been 
subject to pockets of 
basement and surface 
flooding incidents during 
major storms, including 
storms in May 2000, 
August 2005, and May/July 
2013. 
• Seven (7) storm sewer 
outfalls discharge 
stormwater runoff to 
tributaries of Don River 
West Branch. 
#26-1 
#26-2 
#26-3 
#26-5 #26-6 
#26-7 
#26-8 
#26-9 
Outfall #26-1 Outfall #26-2 
Outfall #26-7
Study Area 27 
• Study Area 27 has been 
subject to pockets of 
basement and surface 
flooding incidents during 
major storms, including 
storms in May 2000, August 
2005, and May/July 2013. 
• Thirteen (13) storm sewer 
outfalls discharge 
stormwater runoff to 
tributaries of Don River East 
Branch. 
#27-1 
#27-2 
#27-3 
#27-4 
#27-6 #27-7 
#27-5 
#27-9 
#27-8 
#27-10 
#27-11 
#27-12 
Outfall #27-1 
Outfall #27-2 
Outfall #27-3 
Outfall #27-4 
Outfall #27-5 Outfall #27-6 
#27-13 
Outfall #27-7 
Outfall #27-11 
Outfall #27-8 Outfall #27-9 Outfall #27-10
Municipal Class 
Environmental Assessment (EA) 
Process 
• The City of Toronto must follow the Municipal Class 
Environmental Assessment (EA) process to meet the 
requirements of Ontario’s EA Act for all infrastructure projects. 
• The EA Act requires the “protection, conservation and wise 
management of the environment” while undergoing 
infrastructure enhancements. 
• The EA process is also an opportunity for the public and 
agencies to provide input throughout the project.
The Steps Involved in Our Study 
Many steps are involved in the study before solutions can be recommended. This work 
includes: 
• Collect and review background data on land use, population, soil conditions, sanitary sewer and 
storm drainage systems, topography and overland drainage patterns, flooding history, and operation/ 
maintenance records; 
• Conduct field surveys to inventory the number of roof leaders disconnected, survey catchbasins, 
identify low lying areas, and conduct an inventory of storm outfalls; 
• Develop computer models to: 
– analyse the causes of flooding and to predict flows under various storm events; and, 
– assess the impacts of stormwater runoff on water quality in Don River; 
• Develop and receive feedback on alternatives to address the issue of flooding in each of the study 
areas and improve stormwater runoff water quality before it is discharged to Don River (1st Public 
Information Centre held on September 26, 2013); 
• Gather input from the community and review agencies and undertake further assessment and 
refinement of alternatives; 
• Identify and assess alternatives and present recommended solutions 
( 2nd Public Information Centre); and, 
• Gather input from the community and review agencies and finalize the EA study based on input 
received. 
We Are Here
Our Basement Flooding Findings 
Under normal rainfall events, the storm and sanitary 
sewer systems operate as designed. However, 
during extreme storms, the following takes place: 
Storm System: 
• Stormwater flow exceeds the storm sewer capacity and overloads the 
system. 
• Significant stromwater remains on the surface and significant flows on 
roads and creeks. Surface water may enter basements through 
basement doors, window sills, and reverse-slope driveways. 
• At low lying areas with no overland flow 
outlet, water accumulates (ponds) on 
the surface and enters the sanitary 
sewer system through manhole covers, 
contributing to excess inflow. 
• Shallow sewers.
Our Basement Flooding Findings 
Low Points in the Area 
Overland Flow Paths
Our Basement Flooding Findings 
Sanitary System: 
• During heavy rainfall events, the ground becomes extremely wet, 
water enters the sanitary system through cracks or broken pipes, 
cracked maintenance hole walls and loose pipe joints underground, 
contributing to backup of the sanitary sewers. 
• Water entering the basement from the surface via basement doors, 
window sills, and reverse-sloped driveways, and through floor drains. 
• Downspouts and weeping tiles connected to the sanitary sewer 
system. 
• Illegal or unknown cross-connections between the sanitary and storm 
sewer systems. 
• Oil/grease dumped into sanitary sewers causing 
blockages.
Causes of Basement Flooding
Storm Drainage System 
• Storm sewers (minor system) convey up to 1 in 2 year storms. 
• Streets (major system) convey major storms that exceed the storm sewer 
capacity. 
• Temporary ponding on streets is expected during major rain storms. 
Design Standards: 
• Water level in the sanitary sewer is below basement elevation. 
• Street flow depth should not exceed the street right-of-way limits.
Our Stormwater Runoff 
Quality Findings 
• Urbanization has not only increased surface runoff and decreased 
infiltration into the ground but also increased the potential for the transport 
of pollutants via surface runoff from streets, parking lots and other hard 
surfaces. 
• Stormwater runoff often contains grit, oil/grease, heavy metals (zinc, lead, 
etc.), bacteria, nitrates/sulfates, salt and other pollutants. 
• Pollutants in the stormwater runoff adversely impact the water quality of 
the receiving watercourse, which affects fisheries, wildlife, recreational 
uses, visual aesthetics, etc.
Evaluation of Options 
The following criteria were used in evaluating each of the 
options and selecting the recommended solutions: 
Natural Environment 
• Potential impact on terrestrial systems 
(vegetation, trees, wildlife) 
• Potential impact on aquatic systems, 
aquatic life and vegetation 
• Potential impact on soils, groundwater 
and surface water 
• Potential impact on stream erosion 
Social and Cultural Environment 
• Potential to impact the community (i.e. 
community disruption - visibility, noise, 
traffic impacts, etc.) 
• Potential to impact land use compatibility 
(parks/open spaces, recreational uses) 
• Potential to impact archaeological and/or 
natural heritage sites 
Technical 
• Effectiveness of control measure in 
eliminating basement flooding and/or 
improving the quality of the stormwater 
runoff 
• Feasibility of control measure 
(available space, accessibility, 
construction requirements) 
• Flooding impacts on upstream, 
downstream and surrounding areas 
Economic 
• Capital cost 
• Operating/maintenance cost
Recommended Solutions – Source Control 
Options recommended in the study areas include: 
Downspout 
Sealing Maintenance 
Disconnection 
Hole Covers 
in Low Lying Areas 
‘Pick Holes’, plugged 
with rubber insert 
Surface Flow Path 
Diversion 
Additional source control options recommended: 
• Catch basin inlet control 
• Increasing the number of catch basins 
• Repairing sewer systems to reduce 
Inflow/Infiltration (I/I) based on CCTV inspections 
Source control measures 
help to reduce the risk of 
basement flooding, and 
also contribute to 
improving stormwater 
runoff quality.
Recommended Solutions – Source Control 
Catch basin Inlet Control Devices 
• Control the amount of water that 
enters the storm sewer system during 
a storm event. 
• Allow excess stormwater to remain in 
catch basins or temporarily on the 
street until the storm subsides. 
• Helps prevent overloading of the 
storm sewer and sewer backups. 
• Device is installed inside the catch 
basin. It is not visible on the surface. 
• Minimal effort and time to install.
Recommended Solutions – Conveyance Control 
Options recommended for implementation in the study areas 
to help reduce the risk of basement flooding 
Replacement of existing storm 
Existing storm and/or sanitary 
sewers with inadequate 
capacities to convey the required 
flows are replaced with larger 
pipes. 
Existing sewer pipes remain in 
place and another sewer pipe is 
installed in parallel to provide 
additional flow capacity. 
and/or sanitary sewers 
Adding new sewers (Twinning)
Recommended Solutions – Conveyance Control 
Option recommended for implementation in the study areas 
to help reduce the risk of basement flooding 
Oversized Storage 
Temporary storage of flows will 
be provided by underground 
oversized pipes commonly 
referred to as ‘superpipes’. 
Once there is adequate flow 
capacity in the respective sewer 
systems, the flows from these 
storage facilities will be 
gradually released.
Recommended Solutions – Conveyance Control 
Option recommended for implementation in the study 
areas to improve stormwater runoff quality 
• Bioretention units are plant and soil based, low 
impact treatment and infiltration systems. The 
units work to filter pollutants and slow down 
stormwater runoff. 
• The bioretention units consist of: 
• A soil mixture that allows easy percolation of 
water to the granular base. 
• A granular base consisting of clear washed 
stones in a fabric wrap. 
• Vegetation, trees and shrubs. 
• Can be applied in the street right-of-way (upstream 
of catch basins) in 30% of Study Areas 24, 25, 26 
and 27. 
• Units on average would be designed to capture 
and treat 70m3/hectare which translates into runoff 
from approximately 15 mm of rain. 
• The units will be landscaped to blend into existing 
surroundings; and there will be future consultation 
with the community to confirm the locations of 
bioretention units. 
Bioretention Units
Recommended Solutions – Conveyance Control 
Option recommended for implementation in the study 
areas to improve stormwater runoff quality 
Oil/Grit Separator 
An oil/grit separator is an 
underground structure connected 
to the storm sewer to improve 
stormwater quality by removing 
contaminants from the 
stormwater such as grease, oil, 
mud, sand and trash.
Recommended Solution for Area 24 
Flood Control Measures 
HOUNSLOW AVE 
% 
% 
% 
% 
% 
% 
% 
% 
% % 
% 
% 
% 
% 
% 
% 
% 
%% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
%% 
% % 
% 
% 
% % 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% % % 
% 
% 
% 
% 
% 
% 
%% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% % 
% % 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
%% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% % 
% % % 
% % 
% % 
% % 
% 
% 
% 
% 
% % 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% % 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% % 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% % 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
ELLERSLIE AVE 
FIN CH AVE W 
BATHURST ST 
CHURCHILL AVE 
¹ 
¹ 
0 200 400 m 
Legend 
Sanitary Sewer Manhole 
% Sanitary Sewer 
Storm Sewer Manhole 
% Storm Sewer 
Catchment Area 24 
Building 
Lot 
Sanitary Sewer Remediation 
Sanitary Oversized Sewer 
Storm Sewer Remediation 
Storm Sewer Upgrade 
West Don River
Recommended Solution for Area 25 
Flood Control Measures 
% 
% 
% 
% 
% 
% 
% 
BOGERT AVE 
% 
% % % 
%% 
% 
% 
% 
% 
% 
% 
% 
% % 
% 
% 
% % 
% 
% 
% 
% 
% 
% 
% 
% 
% % 
% 
% 
% 
% 
% 
% 
% 
% 
% % 
% % 
% % % 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% % 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% % 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% % 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% %% 
% 
% 
% 
% % 
% 
% 
% 
% 
%% 
% % 
% 
% 
% % 
% % 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% % 
% 
% % 
% 
% 
% 
%% 
% 
% 
% 
% 
% 
% % 
% 
% 
% 
% 
% 
%% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
%% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% % 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% % 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
%% 
% 
% 
%% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
%% 
% 
% 
% 
% 
% 
% % 
% 
% 
% 
% % 
% 
% 
% % 
% 
% 
% 
% 
% 
% 
% 
% % 
% 
% 
% 
% 
% % 
% 
% 
% % 
SENLAC RD 
JOHNSTON AVE 
CAMERON AVE 
BETTY ANN DR 
STUART AVE 
¹ 
Legend 
Sanitary Sewer Manhole 
% Sanitary Sewer 
Storm Sewer Manhole 
% Storm Sewer 
Catchment Area 25 
Building 
Lot 
Sanitary Sewer Remediation 
Sanitary Sewer Upgrade 
Storm Sewer Remediation 
Storm Sewer Upgrade 
¹ 
0 200 400 m 
West Don River
Recommended Solution for Area 26 
Flood Control Measures 
% 
% 
% 
% 
% 
% 
% 
% 
HENDON AVE 
% 
% 
% 
% 
%% 
% 
% 
% 
% 
% % 
% 
% % 
% 
% 
% 
% 
% 
%% 
%% 
% 
% 
% 
% 
% 
% 
% 
% % 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% % 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% % 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
%% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% % 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
%% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
%% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
%% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
%% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
%% 
% 
% 
% 
% % 
% 
% 
% 
% 
% 
%% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
%% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% % 
% 
% 
% 
% 
% 
%% 
% 
% 
% 
% 
%% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
%% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
%% 
% 
% 
% 
%% 
% 
% 
%% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
%% 
% 
% 
% 
% 
% 
% 
%% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% % 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
%% 
%% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% % 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
%% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
%% 
% 
% 
% 
%% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
%% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
%% 
% 
% 
% 
% 
% 
% 
% 
% 
%% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% % 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
%% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
%% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
YONGE ST 
FINCH AVE W 
BEECROFT RD 
DUDLEY AVE 
KENNETH AVE 
WILLOWDALE AVE 
SHEPPARD AVE E 
HOUNSLOW AVE 
CHURCHILL AVE 
BYNG AVE 
CHARLTON BLVD 
ELLERSLIE AVE 
AVONDALE AVE 
DREWRY AVE 
LURGAN DR 
ANNDALE DR 
BURNETT AVE 
DORIS AVE 
ELMHURST AVE 
ANCONA ST 
West Don River 
¹ 
Legend 
Sanitary Sewer Manhole 
% Sanitary Sewer 
Storm Sewer Manhole 
% Storm Sewer 
Catchment Area 26 
Building 
Lot 
Sanitary Sewer Remediation 
Sanitary Sewer Upgrade 
New Sanitary Sewer Diversion 
Storm Sewer Remediation 
Storm Sewer Upgrade 
New Storm Sewer Diversion 
0 200 400 600 m
Recommended Solution for Area 27 
Flood Control Measures 
% 
% 
% 
% 
% 
% 
% 
%% 
% 
% % 
%% 
HOLMES AVE 
% 
% 
% 
% 
% 
%% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% % 
% 
% 
% 
% 
% 
% 
%%% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% %% 
% 
% 
% 
% % 
%% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% % 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% % 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
%% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% % 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% % 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
%% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% % 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% % 
% 
% 
% 
% 
% 
% 
% 
% 
%% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
%% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% % 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% % 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% % 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% % 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% % 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% % 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
%% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% % 
BURBANK DR 
OLIVE AVE 
WILFRED AVE 
BAYVIEW AVE 
MCKEE AVE 
CITATION DR 
ESTELLE AVE 
HIGHWAY 401 X E 
BYNG AVE 
HIGHWAY 401 X W 
HILLCREST AVE 
HOLLYWOOD AVE 
HAWKSBURY DR 
DUNVIEW AVE 
HI MOUNT DR 
BUNTY LANE 
REAN DR 
SPRING GARDEN AVE 
DORIS AVE 
NORTON AVE 
DUDLEY AVE 
Legend 
Sanitary Sewer Manhole 
% Sanitary Sewer 
Storm Sewer Manhole 
% Storm Sewer 
Catchment Area 27 
Building 
Lot 
Sanitary Sewer Remediation 
Sanitary Sewer Upgrade 
Sanitary Oversized Sewer 
Storm Sewer Remediation 
Storm Sewer Upgrade 
¹ 
East Don River 
0 200 400 600 m
Recommended Solution for Area 24 
Stormwater Quality Improvement 
Measures 
Source Control 
Measures 
Residential 
 Roof downspout 
disconnection 
 Rain barrel 
 Additional trees 
& bushes 
 Pervious driveway 
 Lot re-grading 
to grass area 
Industrial/Commercial 
/Institutional 
 Flat roof top restrictors 
 Catchbasin restrictors 
in parking lots 
 Additional trees 
& bushes 
Conveyance Control 
Measures 
Residential 
 Filtration/Bioretention 
in street right-of-way 
Industrial/Commercial 
/Institutional 
 Filtration/Bioretention 
in street right-of-way 
 Oil/Grit Separators 
HOUNSLOW AVE 
% 
% 
% 
% 
% 
% % 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
%% % 
% 
% 
% % 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% % % 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
%% 
% % 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
%% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% % 
% % % 
$1 
ELLERSLIE AVE 
FINCH AVE W 
BATHURST ST 
CHURCHILL AVE 
¹ 
¹ 
0 200 400 m 
Legend 
Storm Sewer Manhole 
Storm Sewer Outfall 
% Storm Sewer 
River 
Roadway 
$1 Oil / Grit Separator 
Bioretention Unit in the Street R.O.W. 
Catchment Area 24 
West Don River
Recommended Solution for Area 25 
Stormwater Quality Improvement 
Measures 
Source Control 
Measures 
Residential 
 Roof downspout 
disconnection 
 Rain barrel 
 Additional trees 
& bushes 
 Pervious driveway 
 Lot re-grading 
to grass area 
Industrial/Commercial 
/Institutional 
 Flat roof top restrictors 
 Catchbasin restrictors 
in parking lots 
 Additional trees 
& bushes 
Conveyance Control 
Measures 
Residential 
 Filtration/Bioretention 
in street right-of-way 
Industrial/Commercial 
/Institutional 
 Filtration/Bioretention 
in street right-of-way 
 Oil/Grit Separators 
% 
% 
% 
% 
% 
% 
BOGERT AVE 
% 
% % % 
%% 
% 
% 
% 
% 
% 
% 
% 
% % 
% 
% 
% % 
% 
% 
% 
% 
% 
% 
% 
% 
% % 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% % 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% % 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% % 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% % 
% 
% 
% 
% 
% % 
% 
% 
% 
% 
% 
% 
% % 
% 
% 
% % 
% % 
% 
% 
% 
% 
%% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
$1 
SENLAC RD 
JOHNSTON AVE 
CAMERON AVE 
BETTY ANN DR 
STUART AVE 
¹ 
Legend 
Storm Sewer Manhole 
Storm Sewer Outfall 
% Storm Sewer 
Roadway 
River 
$1 Oil / Grit Separator 
Bioretention Unit in the Street R.O.W. 
Catchment Area 25 
¹ 
West Don River 
0 200 400 m
Recommended Solution for Area 26 
Stormwater Quality Improvement Measures 
Source Control Measures 
Residential 
 Roof downspout disconnection 
 Rain barrel 
 Additional trees & bushes 
 Pervious driveway 
 Lot re-grading to grass area 
Commercial/Institutional 
 Flat roof top restrictors 
 Catchbasin restrictors in parking lots 
 Additional trees & bushes 
Conveyance Control 
Measures 
Residential 
 Filtration/Bioretention 
in street right-of-way 
Commercial/Institutional 
 Filtration/Bioretention 
in street right-of-way 
 Oil/Grit Separators 
% 
% 
% 
% 
% 
% 
% 
HENDON AVE 
% 
% 
% 
% 
% 
% 
% 
% % 
% 
% 
% % 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% % 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% % 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% % 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
%% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
%% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
%% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
%% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
%% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
%% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
%% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
%% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
%% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
%% 
% 
%% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
%% 
% 
% 
% 
% 
% 
%% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
%% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
%% 
% 
% 
% 
%% 
% 
% 
%% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
%% 
% 
% 
% 
% 
% 
% 
% 
%% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
%% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
$1 
$1 
$1 
$1 
$1 
$1 
$1 
$1 
YONGE ST 
FINCH AVE W 
BEECROFT RD 
DUDLEY AVE 
KENNETH AVE 
WILLOWDALE AVE 
SHEPPARD AVE E 
HOUNSLOW AVE 
CHURCHILL AVE 
BYNG AVE 
CHARLTON BLVD 
ELLERSLIE AVE 
AVONDALE AVE 
DREWRY AVE 
LURGAN DR 
ANN DALE DR 
BURNETT AVE 
DORIS AVE 
ELMHURST AVE 
ANCONA ST 
¹ 
Legend 
Storm Sewer Manhole 
Storm Sewer Outfall 
% Storm Sewer 
Roadway 
River 
$1 Oil / Grit Separator 
Bioretention Unit in the Street R.O.W. 
Catchment Area 26 
West Don River 
0 200 400 600 m
Recommended Solution for Area 27 
Stormwater Quality Improvement Measures 
Source Control Measures 
Residential 
 Roof downspout disconnection 
 Rain barrel 
 Additional trees & bushes 
 Pervious driveway 
 Lot re-grading to grass area 
Commercial/Institutional 
 Flat roof top restrictors 
 Catchbasin restrictors in parking lots 
 Additional trees & bushes 
Conveyance Control 
Measures 
Residential 
 Filtration/Bioretention 
in street right-of-way 
Commercial/Institutional 
 Filtration/Bioretention 
in street right-of-way 
 Oil/Grit Separators 
% 
% 
% 
% 
% 
% 
% 
%% 
% 
HOLMES AVE 
% 
% 
% 
% 
% 
%% 
% 
% 
%% 
% 
% 
%% 
% 
% 
% 
% 
% 
% 
% 
% % 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
%% 
% 
% %% 
% 
% 
% 
% % 
%% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
BURBANK DR 
% 
% 
% 
% 
% 
% 
% 
% % 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% % 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
%%% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% % 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% % 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% % 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% % 
% 
% 
% 
% 
% 
% 
% 
%% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% 
% % 
% 
% 
% 
% 
% 
% 
% 
% 
% 
%% 
% 
% 
% 
$1 
$1 
OLIVE AVE 
WILFRED AVE 
BAYVIEW AVE 
MCKEE AVE 
CITATION DR 
ESTELLE AVE 
HIGHWAY 401 X E 
BYNG AVE 
HIGHWAY 401 X W 
HILLCREST AVE 
HOLLYWOOD AVE 
HAWKSBURY DR 
DUNVIEW AVE 
HI MOUNT DR 
BUNTY LANE 
REAN DR 
SPRING GARDEN AVE 
DORIS AVE 
NORTON AVE 
DUDLEY AVE 
Legend 
Manhole 
Storm Sewer Outfall 
% Storm Sewer 
Roadway 
River 
$1 Oil / Grit Separator 
Bioretention Unit in the Street R.O.W. 
Catchment Area 27 
¹ 
East Don River 
0 200 400 600 m 
% 
$1
Next Steps 
• After tonight’s meeting, we will gather your comments. 
• We will review the feedback and finalize the recommended solutions. 
• The Project File will be prepared and made available for 30-day public 
review in early 2015. 
• The City will implement the recommended solutions pending completion of 
the Environmental Assessment, future regulatory and budgetary approvals, 
and coordination with other planned infrastructure projects in these areas. 
For more information on this study, or to provide your comments or to be added 
to the study mailing list, please contact: 
Josie Franch, Public Consultation Unit 
55 John Street, Metro Hall, 19th Floor 
Toronto, ON M5V 3C6 
E-mail: jfranch@toronto.ca 
Phone: 416-338-2859 
Tty: 416-338-0889 
Fax: 416-392-2974 
Website: www.toronto.ca/involved/projects
Homeowner Measures to Control 
Flooding 
Backwater Valve 
on Sanitary Lateral Disconnect foundation drain 
from storm / sanitary sewer 
and connect to sump pump
Steps You Can Take to 
Reduce Flooding Risks 
• Regularly clear eavestroughs and 
downspouts of debris 
• Check for and repair leaks or cracks in 
walls, floors, windows and your home’s 
foundations 
• Do not pour grease down your drains 
• Avoid household water use during heavy 
rainfall 
• If you have window wells, consider using 
window well covers to prevent water from 
entering your home 
• Ensure the ground is sloping away from 
your home's foundation and does not 
impact neighbouring properties
Steps You Can Take to 
Reduce Flooding Risks 
• Talk to a City-licensed and qualified plumber to discuss 
options such as: 
• Installation of a backwater valve on your home’s 
• sanitary and/or storm sewer connection 
• Installation of a sump pump and disconnection of your 
home’s foundation drains (weeping tiles) from the City’s 
sewer system 
• Consider installing a battery backup on your sump pump, in 
case of a power outage 
• Ensure periodic maintenance of the above devices 
• Install soft-surface landscaping (e.g., sodded areas, 
porous paving, etc.) 
• Clear roadside sewer grates (catch basins) of debris and 
leaves, if safe to do so.
Basement Flooding Protection 
Subsidy Program 
To assist homeowners, the City 
offers owners of single-family, duplex 
and triplex residential homes, a 
financial subsidy of up to $3,400 per 
property, to install flood protection 
devices including: 
• Backwater valve (max $1,250), 
• Sump pump (max $1,750), and 
• Disconnection of a home’s foundation 
drains (weeping tile) from the sewer system 
(max $400).
Downspout Disconnection 
• The City has a bylaw making downspout 
disconnection mandatory, where feasible. 
• The bylaw came into effect on December 
3, 2013 for properties in basement flooding 
areas and will come into effect on 
December 3, 2016 for properties outside 
basement flooding and combined sewer 
service area. 
• If disconnection is not technically feasible 
or would create a hazardous condition, 
owners can apply to the City for an 
exemption. 
Benefits of disconnecting your 
downspout: 
• Helps reduce the amount of stormwater 
that is sent into the sewer system 
• Less stormwater in the system will help 
prevent wastewater from backing up into 
basements 
• Leads to lower energy costs at wastewater 
treatment facilities – producing fewer 
greenhouse gas emissions 
• Helps to replenish and protect the 
groundwater table and reduces and delays 
stormwater runoff—helping to prevent flash 
flooding in rivers and streams

Weitere ähnliche Inhalte

Mehr von Toronto Public Consultation Unit

Waterfront Sanitary Servicing Master Plan Update (Oct. 30 PIE).
Waterfront Sanitary Servicing Master Plan Update (Oct. 30 PIE). Waterfront Sanitary Servicing Master Plan Update (Oct. 30 PIE).
Waterfront Sanitary Servicing Master Plan Update (Oct. 30 PIE). Toronto Public Consultation Unit
 
King-Liberty Pedestrian / Cycling Bridge Project Update - Slides
King-Liberty Pedestrian / Cycling Bridge Project Update - Slides King-Liberty Pedestrian / Cycling Bridge Project Update - Slides
King-Liberty Pedestrian / Cycling Bridge Project Update - Slides Toronto Public Consultation Unit
 
Six Points Interchange Reconfiguration public event display panels, May 11, 2017
Six Points Interchange Reconfiguration public event display panels, May 11, 2017Six Points Interchange Reconfiguration public event display panels, May 11, 2017
Six Points Interchange Reconfiguration public event display panels, May 11, 2017Toronto Public Consultation Unit
 
College Street Promenade BIA Streetscaping Update Public Meeting Feb 28 final
College Street Promenade BIA Streetscaping Update Public Meeting Feb 28  finalCollege Street Promenade BIA Streetscaping Update Public Meeting Feb 28  final
College Street Promenade BIA Streetscaping Update Public Meeting Feb 28 finalToronto Public Consultation Unit
 
King-Liberty Pedestrian / Cycling Bridge (Dec. 8 2016 Information Panels)
King-Liberty Pedestrian / Cycling Bridge (Dec. 8 2016 Information Panels)King-Liberty Pedestrian / Cycling Bridge (Dec. 8 2016 Information Panels)
King-Liberty Pedestrian / Cycling Bridge (Dec. 8 2016 Information Panels)Toronto Public Consultation Unit
 

Mehr von Toronto Public Consultation Unit (20)

Waterfront Sanitary Servicing Master Plan Update (Oct. 30 PIE).
Waterfront Sanitary Servicing Master Plan Update (Oct. 30 PIE). Waterfront Sanitary Servicing Master Plan Update (Oct. 30 PIE).
Waterfront Sanitary Servicing Master Plan Update (Oct. 30 PIE).
 
SmartTrack Public Meeting Presentation
SmartTrack Public Meeting PresentationSmartTrack Public Meeting Presentation
SmartTrack Public Meeting Presentation
 
Waterfront Transit Reset Phase 2 Display Panels
Waterfront Transit Reset Phase 2 Display PanelsWaterfront Transit Reset Phase 2 Display Panels
Waterfront Transit Reset Phase 2 Display Panels
 
Waterfront Transit Reset Public Meeting Presentation
Waterfront Transit Reset Public Meeting Presentation Waterfront Transit Reset Public Meeting Presentation
Waterfront Transit Reset Public Meeting Presentation
 
King-Liberty Pedestrian / Cycling Bridge Project Update - Slides
King-Liberty Pedestrian / Cycling Bridge Project Update - Slides King-Liberty Pedestrian / Cycling Bridge Project Update - Slides
King-Liberty Pedestrian / Cycling Bridge Project Update - Slides
 
Sewer Outfall Project
Sewer Outfall ProjectSewer Outfall Project
Sewer Outfall Project
 
General information
General informationGeneral information
General information
 
Disinfection System
Disinfection SystemDisinfection System
Disinfection System
 
2017 Sediment Basin construction updated information
2017 Sediment Basin construction updated information 2017 Sediment Basin construction updated information
2017 Sediment Basin construction updated information
 
Scarborough Subway TPAP Boards
Scarborough Subway TPAP Boards Scarborough Subway TPAP Boards
Scarborough Subway TPAP Boards
 
2017 05-18 Etobicoke Creek Nort Trail panels final
2017 05-18 Etobicoke Creek Nort Trail panels final2017 05-18 Etobicoke Creek Nort Trail panels final
2017 05-18 Etobicoke Creek Nort Trail panels final
 
King Street Phase 2 Slide Deck
King Street Phase 2 Slide Deck King Street Phase 2 Slide Deck
King Street Phase 2 Slide Deck
 
Scarborough Subway TPAP PIC
Scarborough Subway TPAP PICScarborough Subway TPAP PIC
Scarborough Subway TPAP PIC
 
Six Points Interchange Reconfiguration public event display panels, May 11, 2017
Six Points Interchange Reconfiguration public event display panels, May 11, 2017Six Points Interchange Reconfiguration public event display panels, May 11, 2017
Six Points Interchange Reconfiguration public event display panels, May 11, 2017
 
Downsview Area Long Term Water Servicing
Downsview Area Long Term Water Servicing Downsview Area Long Term Water Servicing
Downsview Area Long Term Water Servicing
 
FG Gardiner New Simcoe Ramp - display boards
FG Gardiner   New Simcoe Ramp - display boardsFG Gardiner   New Simcoe Ramp - display boards
FG Gardiner New Simcoe Ramp - display boards
 
College Street Promenade BIA Streetscaping Update Public Meeting Feb 28 final
College Street Promenade BIA Streetscaping Update Public Meeting Feb 28  finalCollege Street Promenade BIA Streetscaping Update Public Meeting Feb 28  final
College Street Promenade BIA Streetscaping Update Public Meeting Feb 28 final
 
Swc public consultation_pres_170307_final
Swc public consultation_pres_170307_finalSwc public consultation_pres_170307_final
Swc public consultation_pres_170307_final
 
King Street Pilot Public Meeting
King Street Pilot Public MeetingKing Street Pilot Public Meeting
King Street Pilot Public Meeting
 
King-Liberty Pedestrian / Cycling Bridge (Dec. 8 2016 Information Panels)
King-Liberty Pedestrian / Cycling Bridge (Dec. 8 2016 Information Panels)King-Liberty Pedestrian / Cycling Bridge (Dec. 8 2016 Information Panels)
King-Liberty Pedestrian / Cycling Bridge (Dec. 8 2016 Information Panels)
 

Pic#2 areas 24,25,26,27 sept 24-final

  • 1. Welcome Investigation of Basement Flooding and Stormwater Runoff Quality Control Study Areas 24, 25, 26 and 27 (Yonge Street & Sheppard Avenue Area) Public Information Centre #2 View displays and discuss the study with project staff Feel free to ask questions and fill out a comment sheet
  • 2. Purpose of Tonight’s Meeting • Provide background on the study. • Present the findings of the study. • Present the recommended solutions for Study Areas 24, 25, 26 and 27. • Receive your comments. • Outline the next steps in the study. • We want to hear from you! Your input is very important.
  • 3. Purpose of Our Study • Examine existing stormwater drainage and sanitary sewer systems and identify the causes of basement flooding and/or surface flooding (severe ponding on streets during extreme storms). • Assess control measures to improve the quality of stormwater surface runoff as per the City’s Wet Weather Flow Master Plan. • Make recommendations to:  Reduce the risk of future flooding; and,  Improve the quality of stormwater runoff before it is discharged to the West Don River and/or its tributaries.
  • 4. Study Area 24 • Study Area 24 has been subject to pockets of basement and surface flooding incidents during major storms in May 2000, August 2005, and May/July 2013. • Three (3) storm sewer outfalls discharge stormwater runoff to tributaries of Don River West Branch. #24-1 #24-2 Outfall #24-1 Outfall #24-2 #24-3
  • 5. Study Area 25 • Study Area 25 has been subject to pockets of basement and surface flooding incidents during major storms, including storms in May 2000, August 2005, and May/July 2013. • Eight (8) storm sewer outfalls discharge stormwater runoff to tributaries of Don River West Branch. #25-1 #25-2 #25-4 #25-3 #25-6 #25-8 #25-7 Outfall #25-1 Outfall #25-2 Outfall #25-3 Outfall #25-4 Outfall #25-5 Outfall #25-6 Outfall #25-7 Outfall #25-8 #25-5
  • 6. Study Area 26 • Study Area 26 has been subject to pockets of basement and surface flooding incidents during major storms, including storms in May 2000, August 2005, and May/July 2013. • Seven (7) storm sewer outfalls discharge stormwater runoff to tributaries of Don River West Branch. #26-1 #26-2 #26-3 #26-5 #26-6 #26-7 #26-8 #26-9 Outfall #26-1 Outfall #26-2 Outfall #26-7
  • 7. Study Area 27 • Study Area 27 has been subject to pockets of basement and surface flooding incidents during major storms, including storms in May 2000, August 2005, and May/July 2013. • Thirteen (13) storm sewer outfalls discharge stormwater runoff to tributaries of Don River East Branch. #27-1 #27-2 #27-3 #27-4 #27-6 #27-7 #27-5 #27-9 #27-8 #27-10 #27-11 #27-12 Outfall #27-1 Outfall #27-2 Outfall #27-3 Outfall #27-4 Outfall #27-5 Outfall #27-6 #27-13 Outfall #27-7 Outfall #27-11 Outfall #27-8 Outfall #27-9 Outfall #27-10
  • 8. Municipal Class Environmental Assessment (EA) Process • The City of Toronto must follow the Municipal Class Environmental Assessment (EA) process to meet the requirements of Ontario’s EA Act for all infrastructure projects. • The EA Act requires the “protection, conservation and wise management of the environment” while undergoing infrastructure enhancements. • The EA process is also an opportunity for the public and agencies to provide input throughout the project.
  • 9. The Steps Involved in Our Study Many steps are involved in the study before solutions can be recommended. This work includes: • Collect and review background data on land use, population, soil conditions, sanitary sewer and storm drainage systems, topography and overland drainage patterns, flooding history, and operation/ maintenance records; • Conduct field surveys to inventory the number of roof leaders disconnected, survey catchbasins, identify low lying areas, and conduct an inventory of storm outfalls; • Develop computer models to: – analyse the causes of flooding and to predict flows under various storm events; and, – assess the impacts of stormwater runoff on water quality in Don River; • Develop and receive feedback on alternatives to address the issue of flooding in each of the study areas and improve stormwater runoff water quality before it is discharged to Don River (1st Public Information Centre held on September 26, 2013); • Gather input from the community and review agencies and undertake further assessment and refinement of alternatives; • Identify and assess alternatives and present recommended solutions ( 2nd Public Information Centre); and, • Gather input from the community and review agencies and finalize the EA study based on input received. We Are Here
  • 10. Our Basement Flooding Findings Under normal rainfall events, the storm and sanitary sewer systems operate as designed. However, during extreme storms, the following takes place: Storm System: • Stormwater flow exceeds the storm sewer capacity and overloads the system. • Significant stromwater remains on the surface and significant flows on roads and creeks. Surface water may enter basements through basement doors, window sills, and reverse-slope driveways. • At low lying areas with no overland flow outlet, water accumulates (ponds) on the surface and enters the sanitary sewer system through manhole covers, contributing to excess inflow. • Shallow sewers.
  • 11. Our Basement Flooding Findings Low Points in the Area Overland Flow Paths
  • 12. Our Basement Flooding Findings Sanitary System: • During heavy rainfall events, the ground becomes extremely wet, water enters the sanitary system through cracks or broken pipes, cracked maintenance hole walls and loose pipe joints underground, contributing to backup of the sanitary sewers. • Water entering the basement from the surface via basement doors, window sills, and reverse-sloped driveways, and through floor drains. • Downspouts and weeping tiles connected to the sanitary sewer system. • Illegal or unknown cross-connections between the sanitary and storm sewer systems. • Oil/grease dumped into sanitary sewers causing blockages.
  • 13. Causes of Basement Flooding
  • 14. Storm Drainage System • Storm sewers (minor system) convey up to 1 in 2 year storms. • Streets (major system) convey major storms that exceed the storm sewer capacity. • Temporary ponding on streets is expected during major rain storms. Design Standards: • Water level in the sanitary sewer is below basement elevation. • Street flow depth should not exceed the street right-of-way limits.
  • 15. Our Stormwater Runoff Quality Findings • Urbanization has not only increased surface runoff and decreased infiltration into the ground but also increased the potential for the transport of pollutants via surface runoff from streets, parking lots and other hard surfaces. • Stormwater runoff often contains grit, oil/grease, heavy metals (zinc, lead, etc.), bacteria, nitrates/sulfates, salt and other pollutants. • Pollutants in the stormwater runoff adversely impact the water quality of the receiving watercourse, which affects fisheries, wildlife, recreational uses, visual aesthetics, etc.
  • 16. Evaluation of Options The following criteria were used in evaluating each of the options and selecting the recommended solutions: Natural Environment • Potential impact on terrestrial systems (vegetation, trees, wildlife) • Potential impact on aquatic systems, aquatic life and vegetation • Potential impact on soils, groundwater and surface water • Potential impact on stream erosion Social and Cultural Environment • Potential to impact the community (i.e. community disruption - visibility, noise, traffic impacts, etc.) • Potential to impact land use compatibility (parks/open spaces, recreational uses) • Potential to impact archaeological and/or natural heritage sites Technical • Effectiveness of control measure in eliminating basement flooding and/or improving the quality of the stormwater runoff • Feasibility of control measure (available space, accessibility, construction requirements) • Flooding impacts on upstream, downstream and surrounding areas Economic • Capital cost • Operating/maintenance cost
  • 17. Recommended Solutions – Source Control Options recommended in the study areas include: Downspout Sealing Maintenance Disconnection Hole Covers in Low Lying Areas ‘Pick Holes’, plugged with rubber insert Surface Flow Path Diversion Additional source control options recommended: • Catch basin inlet control • Increasing the number of catch basins • Repairing sewer systems to reduce Inflow/Infiltration (I/I) based on CCTV inspections Source control measures help to reduce the risk of basement flooding, and also contribute to improving stormwater runoff quality.
  • 18. Recommended Solutions – Source Control Catch basin Inlet Control Devices • Control the amount of water that enters the storm sewer system during a storm event. • Allow excess stormwater to remain in catch basins or temporarily on the street until the storm subsides. • Helps prevent overloading of the storm sewer and sewer backups. • Device is installed inside the catch basin. It is not visible on the surface. • Minimal effort and time to install.
  • 19. Recommended Solutions – Conveyance Control Options recommended for implementation in the study areas to help reduce the risk of basement flooding Replacement of existing storm Existing storm and/or sanitary sewers with inadequate capacities to convey the required flows are replaced with larger pipes. Existing sewer pipes remain in place and another sewer pipe is installed in parallel to provide additional flow capacity. and/or sanitary sewers Adding new sewers (Twinning)
  • 20. Recommended Solutions – Conveyance Control Option recommended for implementation in the study areas to help reduce the risk of basement flooding Oversized Storage Temporary storage of flows will be provided by underground oversized pipes commonly referred to as ‘superpipes’. Once there is adequate flow capacity in the respective sewer systems, the flows from these storage facilities will be gradually released.
  • 21. Recommended Solutions – Conveyance Control Option recommended for implementation in the study areas to improve stormwater runoff quality • Bioretention units are plant and soil based, low impact treatment and infiltration systems. The units work to filter pollutants and slow down stormwater runoff. • The bioretention units consist of: • A soil mixture that allows easy percolation of water to the granular base. • A granular base consisting of clear washed stones in a fabric wrap. • Vegetation, trees and shrubs. • Can be applied in the street right-of-way (upstream of catch basins) in 30% of Study Areas 24, 25, 26 and 27. • Units on average would be designed to capture and treat 70m3/hectare which translates into runoff from approximately 15 mm of rain. • The units will be landscaped to blend into existing surroundings; and there will be future consultation with the community to confirm the locations of bioretention units. Bioretention Units
  • 22. Recommended Solutions – Conveyance Control Option recommended for implementation in the study areas to improve stormwater runoff quality Oil/Grit Separator An oil/grit separator is an underground structure connected to the storm sewer to improve stormwater quality by removing contaminants from the stormwater such as grease, oil, mud, sand and trash.
  • 23. Recommended Solution for Area 24 Flood Control Measures HOUNSLOW AVE % % % % % % % % % % % % % % % % % %% % % % % % % % % % % % % % % % % % % % % % % %% % % % % % % % % % % % % % % % % % % % % % % % % % % % %% % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % %% % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % ELLERSLIE AVE FIN CH AVE W BATHURST ST CHURCHILL AVE ¹ ¹ 0 200 400 m Legend Sanitary Sewer Manhole % Sanitary Sewer Storm Sewer Manhole % Storm Sewer Catchment Area 24 Building Lot Sanitary Sewer Remediation Sanitary Oversized Sewer Storm Sewer Remediation Storm Sewer Upgrade West Don River
  • 24. Recommended Solution for Area 25 Flood Control Measures % % % % % % % BOGERT AVE % % % % %% % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % %% % % % % % % % % % %% % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % %% % % % % % % % % % % % % %% % % % % % % % % % % % %% % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % %% % % %% % % % % % % % % % % % % % % % % % % % % % %% % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % SENLAC RD JOHNSTON AVE CAMERON AVE BETTY ANN DR STUART AVE ¹ Legend Sanitary Sewer Manhole % Sanitary Sewer Storm Sewer Manhole % Storm Sewer Catchment Area 25 Building Lot Sanitary Sewer Remediation Sanitary Sewer Upgrade Storm Sewer Remediation Storm Sewer Upgrade ¹ 0 200 400 m West Don River
  • 25. Recommended Solution for Area 26 Flood Control Measures % % % % % % % % HENDON AVE % % % % %% % % % % % % % % % % % % % % %% %% % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % %% % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % %% % % % % % % % % % % % % % % % % % % % % % % %% % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % %% % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % %% % % % % % % % % % %% % % % % % % % % % % %% % % % % % % % % % % % % % % % % % %% % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % %% % % % % %% % % % % % % % % % % %% % % % % % % % % % % % %% % % % %% % % %% % % % % % % % % % % % % % % % % % % %% % % % % % % %% % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % %% %% % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % %% % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % %% % % % %% % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % %% % % % % % % % % % % % % % % % % % % % % % % % % % %% % % % % % % % % %% % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % %% % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % %% % % % % % % % % % % % YONGE ST FINCH AVE W BEECROFT RD DUDLEY AVE KENNETH AVE WILLOWDALE AVE SHEPPARD AVE E HOUNSLOW AVE CHURCHILL AVE BYNG AVE CHARLTON BLVD ELLERSLIE AVE AVONDALE AVE DREWRY AVE LURGAN DR ANNDALE DR BURNETT AVE DORIS AVE ELMHURST AVE ANCONA ST West Don River ¹ Legend Sanitary Sewer Manhole % Sanitary Sewer Storm Sewer Manhole % Storm Sewer Catchment Area 26 Building Lot Sanitary Sewer Remediation Sanitary Sewer Upgrade New Sanitary Sewer Diversion Storm Sewer Remediation Storm Sewer Upgrade New Storm Sewer Diversion 0 200 400 600 m
  • 26. Recommended Solution for Area 27 Flood Control Measures % % % % % % % %% % % % %% HOLMES AVE % % % % % %% % % % % % % % % % % % % % % % % % % % % %%% % % % % % % % % % % % % % %% % % % % % %% % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % %% % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % %% % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % %% % % % % % % % % % % % % % % % %% % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % %% % % % % % % % % % % % % % % BURBANK DR OLIVE AVE WILFRED AVE BAYVIEW AVE MCKEE AVE CITATION DR ESTELLE AVE HIGHWAY 401 X E BYNG AVE HIGHWAY 401 X W HILLCREST AVE HOLLYWOOD AVE HAWKSBURY DR DUNVIEW AVE HI MOUNT DR BUNTY LANE REAN DR SPRING GARDEN AVE DORIS AVE NORTON AVE DUDLEY AVE Legend Sanitary Sewer Manhole % Sanitary Sewer Storm Sewer Manhole % Storm Sewer Catchment Area 27 Building Lot Sanitary Sewer Remediation Sanitary Sewer Upgrade Sanitary Oversized Sewer Storm Sewer Remediation Storm Sewer Upgrade ¹ East Don River 0 200 400 600 m
  • 27. Recommended Solution for Area 24 Stormwater Quality Improvement Measures Source Control Measures Residential  Roof downspout disconnection  Rain barrel  Additional trees & bushes  Pervious driveway  Lot re-grading to grass area Industrial/Commercial /Institutional  Flat roof top restrictors  Catchbasin restrictors in parking lots  Additional trees & bushes Conveyance Control Measures Residential  Filtration/Bioretention in street right-of-way Industrial/Commercial /Institutional  Filtration/Bioretention in street right-of-way  Oil/Grit Separators HOUNSLOW AVE % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % %% % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % %% % % % % % % % % % % % % % % % %% % % % % % % % % % % % % % % % % % % % % % % % $1 ELLERSLIE AVE FINCH AVE W BATHURST ST CHURCHILL AVE ¹ ¹ 0 200 400 m Legend Storm Sewer Manhole Storm Sewer Outfall % Storm Sewer River Roadway $1 Oil / Grit Separator Bioretention Unit in the Street R.O.W. Catchment Area 24 West Don River
  • 28. Recommended Solution for Area 25 Stormwater Quality Improvement Measures Source Control Measures Residential  Roof downspout disconnection  Rain barrel  Additional trees & bushes  Pervious driveway  Lot re-grading to grass area Industrial/Commercial /Institutional  Flat roof top restrictors  Catchbasin restrictors in parking lots  Additional trees & bushes Conveyance Control Measures Residential  Filtration/Bioretention in street right-of-way Industrial/Commercial /Institutional  Filtration/Bioretention in street right-of-way  Oil/Grit Separators % % % % % % BOGERT AVE % % % % %% % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % %% % % % % % % % % % % % $1 SENLAC RD JOHNSTON AVE CAMERON AVE BETTY ANN DR STUART AVE ¹ Legend Storm Sewer Manhole Storm Sewer Outfall % Storm Sewer Roadway River $1 Oil / Grit Separator Bioretention Unit in the Street R.O.W. Catchment Area 25 ¹ West Don River 0 200 400 m
  • 29. Recommended Solution for Area 26 Stormwater Quality Improvement Measures Source Control Measures Residential  Roof downspout disconnection  Rain barrel  Additional trees & bushes  Pervious driveway  Lot re-grading to grass area Commercial/Institutional  Flat roof top restrictors  Catchbasin restrictors in parking lots  Additional trees & bushes Conveyance Control Measures Residential  Filtration/Bioretention in street right-of-way Commercial/Institutional  Filtration/Bioretention in street right-of-way  Oil/Grit Separators % % % % % % % HENDON AVE % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % %% % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % %% % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % %% % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % %% % % % % % % % % % % % % % % % % % % % % %% % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % %% % % % % % % % % % %% % % % % % % % % % % %% % % % % % % % % % % % % % % % % % %% % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % %% % %% % % % % % % % % % % % % % % % % % % %% % % % % % %% % % % % % % % % % % % %% % % % % % % % % % % % %% % % % %% % % %% % % % % % % % % % % % % % % % % % % % % % %% % % % % % % % %% % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % %% % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % $1 $1 $1 $1 $1 $1 $1 $1 YONGE ST FINCH AVE W BEECROFT RD DUDLEY AVE KENNETH AVE WILLOWDALE AVE SHEPPARD AVE E HOUNSLOW AVE CHURCHILL AVE BYNG AVE CHARLTON BLVD ELLERSLIE AVE AVONDALE AVE DREWRY AVE LURGAN DR ANN DALE DR BURNETT AVE DORIS AVE ELMHURST AVE ANCONA ST ¹ Legend Storm Sewer Manhole Storm Sewer Outfall % Storm Sewer Roadway River $1 Oil / Grit Separator Bioretention Unit in the Street R.O.W. Catchment Area 26 West Don River 0 200 400 600 m
  • 30. Recommended Solution for Area 27 Stormwater Quality Improvement Measures Source Control Measures Residential  Roof downspout disconnection  Rain barrel  Additional trees & bushes  Pervious driveway  Lot re-grading to grass area Commercial/Institutional  Flat roof top restrictors  Catchbasin restrictors in parking lots  Additional trees & bushes Conveyance Control Measures Residential  Filtration/Bioretention in street right-of-way Commercial/Institutional  Filtration/Bioretention in street right-of-way  Oil/Grit Separators % % % % % % % %% % HOLMES AVE % % % % % %% % % %% % % %% % % % % % % % % % % % % % % % % % % % % % %% % % %% % % % % % %% % % % % % % % % % % % % % % % % % % % % % % % % % BURBANK DR % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % %%% % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % %% % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % % %% % % % $1 $1 OLIVE AVE WILFRED AVE BAYVIEW AVE MCKEE AVE CITATION DR ESTELLE AVE HIGHWAY 401 X E BYNG AVE HIGHWAY 401 X W HILLCREST AVE HOLLYWOOD AVE HAWKSBURY DR DUNVIEW AVE HI MOUNT DR BUNTY LANE REAN DR SPRING GARDEN AVE DORIS AVE NORTON AVE DUDLEY AVE Legend Manhole Storm Sewer Outfall % Storm Sewer Roadway River $1 Oil / Grit Separator Bioretention Unit in the Street R.O.W. Catchment Area 27 ¹ East Don River 0 200 400 600 m % $1
  • 31. Next Steps • After tonight’s meeting, we will gather your comments. • We will review the feedback and finalize the recommended solutions. • The Project File will be prepared and made available for 30-day public review in early 2015. • The City will implement the recommended solutions pending completion of the Environmental Assessment, future regulatory and budgetary approvals, and coordination with other planned infrastructure projects in these areas. For more information on this study, or to provide your comments or to be added to the study mailing list, please contact: Josie Franch, Public Consultation Unit 55 John Street, Metro Hall, 19th Floor Toronto, ON M5V 3C6 E-mail: jfranch@toronto.ca Phone: 416-338-2859 Tty: 416-338-0889 Fax: 416-392-2974 Website: www.toronto.ca/involved/projects
  • 32. Homeowner Measures to Control Flooding Backwater Valve on Sanitary Lateral Disconnect foundation drain from storm / sanitary sewer and connect to sump pump
  • 33. Steps You Can Take to Reduce Flooding Risks • Regularly clear eavestroughs and downspouts of debris • Check for and repair leaks or cracks in walls, floors, windows and your home’s foundations • Do not pour grease down your drains • Avoid household water use during heavy rainfall • If you have window wells, consider using window well covers to prevent water from entering your home • Ensure the ground is sloping away from your home's foundation and does not impact neighbouring properties
  • 34. Steps You Can Take to Reduce Flooding Risks • Talk to a City-licensed and qualified plumber to discuss options such as: • Installation of a backwater valve on your home’s • sanitary and/or storm sewer connection • Installation of a sump pump and disconnection of your home’s foundation drains (weeping tiles) from the City’s sewer system • Consider installing a battery backup on your sump pump, in case of a power outage • Ensure periodic maintenance of the above devices • Install soft-surface landscaping (e.g., sodded areas, porous paving, etc.) • Clear roadside sewer grates (catch basins) of debris and leaves, if safe to do so.
  • 35. Basement Flooding Protection Subsidy Program To assist homeowners, the City offers owners of single-family, duplex and triplex residential homes, a financial subsidy of up to $3,400 per property, to install flood protection devices including: • Backwater valve (max $1,250), • Sump pump (max $1,750), and • Disconnection of a home’s foundation drains (weeping tile) from the sewer system (max $400).
  • 36. Downspout Disconnection • The City has a bylaw making downspout disconnection mandatory, where feasible. • The bylaw came into effect on December 3, 2013 for properties in basement flooding areas and will come into effect on December 3, 2016 for properties outside basement flooding and combined sewer service area. • If disconnection is not technically feasible or would create a hazardous condition, owners can apply to the City for an exemption. Benefits of disconnecting your downspout: • Helps reduce the amount of stormwater that is sent into the sewer system • Less stormwater in the system will help prevent wastewater from backing up into basements • Leads to lower energy costs at wastewater treatment facilities – producing fewer greenhouse gas emissions • Helps to replenish and protect the groundwater table and reduces and delays stormwater runoff—helping to prevent flash flooding in rivers and streams