Drop-In Event
February 28, 2017
Gardiner Expressway York/Bay/Yonge Ramps
2013 Study Objectives
• Originally constructed from 1958 to
1964, the ramps need to address
today’s demands and uses
• Long-term plans for the waterfront aim
to remove barriers and reconnect the
City with Lake Ontario
• Waterfront streets are to be remade
as “places” with high quality amenities
for pedestrians and cyclists
• Improving conditions for the
increasing volume of pedestrians,
cyclists and vehicles requires a
reworking of the road network
Existing Conditions: York/Bay/Yonge Ramps
Study Outcome:
Replacing the York/Bay/Yonge Ramps
The Environmental Assessment Study (2013) recommended:
• Removing the long elevated ramp to Bay Street and loop
ramp at York Street
• Installing a new shorter exit ramp to Harbour Street ending
at Lower Simcoe Street
• Widening Harbour Street from 3 to 4 lanes from Lower
Simcoe to Bay Street
• Adding streetscaping elements (pavers, trees) along
Harbour Street
• Replacing the York ramp loop with redesigned park space
Recommended Improvements
Study Outcome: New Lower Simcoe Ramp
Simcoe Street
Bay Street
Queens Quay
York Street
Key Benefits
A new ramp to Lower Simcoe Street & Improvements to
Harbour Street will:
• Continue to accommodate high volumes of traffic flow between the
Gardiner Expressway, the downtown core and the waterfront
• Create an enhanced public realm for the increasing number of
pedestrians and cyclists living and working in, or visiting the area
• Improve public safety by including well-signalized, well-lit intersections
and better signage for all users
• Create park space (within the existing York Street off-ramp site) to help
enhance the waterfront area
Improvements help support all modes of travel
Existing York/Yonge/Bay Ramps
(Looking west @ Lower Simcoe Street)
Main expressway structure
YBY Exit ramp structure
Future Lower Simcoe Ramp
(Looking west @ Lower Simcoe Street)
Existing York Street Intersection
(Looking south-east towards the lake)
Existing York Street Intersection
- 3 lanes travelling east to Harbour Street
- York St. exit ramp bisects park space
- no sidewalk access on east side of York St
- traffic median at south-east strands pedestrian traffic
Future York Street Intersection
(Looking south-east towards the lake)
+ new northbound turn lane
+ added lane on Harbour S
+ improved pedestrian connections
+ redesigned park space
+ added through traffic lane
+ improved multi-use trail
Future York Street Intersection
Existing Bay Street Ramp
(adjacent to Harbour Street)
Future Harbour Street
(Looking west from Bay Street)
+ improved multi-use trail
+ added lane on Harbour Street
+ improved sidewalks
+ added trees
Future Harbour Street
(Looking east towards Bay Street)
Construction Phase 1: Preparatory Work
July 2016 to December 2016
• Foundation and substructure of
new ramp at Lower Simcoe
started
• Underground infrastructure
relocated (fibre optic cables,
sewers, etc…)
• No closures occurred; only
temporary lane restrictions
during off-peak hours on
eastbound Lake Shore Blvd.
• Multi-use trail closed from Rees
Street to Lower Simcoe Street
Construction Phase 2:
Demolition of Existing Ramps & Construction of
New Lower Simcoe Ramp and Harbour Street
April 2017 to January 2018
Tasks Jan Feb Mar Apr May June July Aug Sept Oct-
Jan
Complete foundation and substructure
for new ramp at Lower Simcoe Street
Install new catch basins and stormwater
leads on Harbour St
Demolish existing YBY off ramp
Relocate Hydro vault and install new
Hydro transformer
Construct new Lower Simcoe ramp
Install automated de-icing system on
ramp
Widen Harbour Street to 4 lanes along
with streetscape improvements
Work Details
Work Hours:
• 7:00 am to 7:00 pm, Monday to Saturday
• Periods of 24/7 and overnight work may be used to help
minimize traffic congestion and shorten overall project duration
Noise:
• Demolition work & concrete removal will be loud and disruptive
at times
• Work may take place around the clock in some instances, but
the noisiest work will cease by 11:00 p.m.
Dust:
• Contractor must control dust
• Work surfaces to be wetted down to avoid spreading dust
Traffic Management
York/Bay/Yonge Ramp will be CLOSED
starting Monday, April 17 to January 2018
• Motorists will still have full access to downtown by exiting the
EB Gardiner Expressway at:
- Jameson Avenue
- Spadina Avenue
- Jarvis Street
• EB off ramp at Spadina will be adjusted to allow for movement
onto EB Lake Shore Boulevard (NB/Left turn at Spadina will
remain)
• Traffic signal times will be adjusted to reduce congestion
• Full access to all westbound Gardiner ramps from Lake Shore
Blvd West will be maintained
Spadina Avenue Off Ramp at Lake Shore Blvd
Motorists exiting the Gardiner Expressway at
Spadina Avenue will be able to access Lake
Shore Boulevard to travel eastbound.
A locked gate along the ramp exit will be
opened to allow motorists to move onto Lake
Shore Boulevard.
Bollards will be placed on Lake Shore Blvd
ahead of the locked gate to provide a lane of
traffic for motorists to move into.
Spadina Ave Off-Ramp Eastbound
During Demolition: April to July
• EB on-ramp at Rees Street will be:
- closed during off-peak hours (9:30 a.m. to 3:30 p.m.)
- open during peak hours to allow demolition during the day
and reduce overnight work
• Intersections along Harbour Street at Lower Simcoe, York &
Bay Streets will be closed for select weekends to safely
remove the overhead spans of the York/Bay/Yonge ramps
(dates to be confirmed)
Throughout Construction: April to January
• EB Lake Shore Boulevard/Harbour Street will be reduced to
two lanes from Lower Simcoe Street to Bay Street
• Motorists can use parallel east/west streets south of Queen St
Traffic Management
Notification & Access for Vehicle Traffic
• Portable Variable Message signs will be placed
along EB Lake Shore Blvd and EB Gardiner
Expressway
• Orange and black advance traffic advisory signage
will be placed at key locations
• Road closures and restrictions will be managed in
coordination with local events
• Laneways and driveways that serve businesses
will remain accessible for deliveries or service
• Access for emergency vehicles will be
maintained at all times
• Changeable Message signage on the DVP, Gardiner and Lake Shore Blvd
will advise motorists of the ramp closure starting March 1st
Pedestrian and Cyclist Access
• Sidewalks to remain open on:
• Lower Simcoe and York Streets for north/south travel
• North side of Harbour Street
• Multi-use trail alongside Lake Shore Blvd
will remain closed during Phase 2
• Cyclists to use detour from Martin
Goodman Trail at Rees St to Queens Quay
Raising Awareness
• Construction Notice Update #1 issued via Canada
Post to approx. 55,000 properties and emailed to all
stakeholders
• Email updates to be provided throughout construction
Sign-up up at toronto.ca/simcoe-ramp
• Road closures to be promoted through Media
Releases, Twitter and Email Updates
• A Construction Liaison Committee will be formed with
local property groups to address concerns during
construction
Help us spread the word - include information on your
websites and email your audience

More Related Content

What's hot

Emery village pic #1 boards v4 (reduced)
Emery village pic #1 boards v4 (reduced)Emery village pic #1 boards v4 (reduced)
Emery village pic #1 boards v4 (reduced)knelischer
 
Mount Dennis Station Open House
Mount Dennis Station Open HouseMount Dennis Station Open House
Mount Dennis Station Open HouseCrosstown TO
 
Reimagining yonge_street__pic_3_display_panels
Reimagining yonge_street__pic_3_display_panelsReimagining yonge_street__pic_3_display_panels
Reimagining yonge_street__pic_3_display_panelsknelischer
 
Remove jcfo booklet
Remove jcfo bookletRemove jcfo booklet
Remove jcfo bookletGardinerEast
 
Remove jcfo boards
Remove jcfo boardsRemove jcfo boards
Remove jcfo boardsGardinerEast
 
Gardiner East EA Public Forum 3 (Feb062014) - panels
Gardiner East EA Public Forum 3 (Feb062014) - panelsGardiner East EA Public Forum 3 (Feb062014) - panels
Gardiner East EA Public Forum 3 (Feb062014) - panelsGardinerEast
 
Former Kodak Lands Update - November 19, 2015
Former Kodak Lands Update - November 19, 2015Former Kodak Lands Update - November 19, 2015
Former Kodak Lands Update - November 19, 2015Crosstown TO
 
Kennedy Station Design Update Meeting Presentation
Kennedy Station Design Update Meeting PresentationKennedy Station Design Update Meeting Presentation
Kennedy Station Design Update Meeting PresentationCrosstown TO
 
John Street Open House Display Boards
John Street Open House Display BoardsJohn Street Open House Display Boards
John Street Open House Display Boardsknelischer
 
URBAN PLANNING AND URBAN DESIGN PORTFOLIO
URBAN PLANNING AND URBAN DESIGN PORTFOLIOURBAN PLANNING AND URBAN DESIGN PORTFOLIO
URBAN PLANNING AND URBAN DESIGN PORTFOLIOezra esdras
 
تحليلي شارع الجمهورية : طرابلس- ليبيا وشارع كامبريدج -كندا - اعداد ايمان الشحومي
تحليلي شارع الجمهورية : طرابلس- ليبيا وشارع كامبريدج -كندا - اعداد ايمان الشحوميتحليلي شارع الجمهورية : طرابلس- ليبيا وشارع كامبريدج -كندا - اعداد ايمان الشحومي
تحليلي شارع الجمهورية : طرابلس- ليبيا وشارع كامبريدج -كندا - اعداد ايمان الشحوميImén Chhoumi
 
Cedarvale station open house for website final2
Cedarvale station open house for website final2Cedarvale station open house for website final2
Cedarvale station open house for website final2Crosstown TO
 
Mount Dennis Mobility Hub Update and Station Design Review
Mount Dennis Mobility Hub Update and Station Design ReviewMount Dennis Mobility Hub Update and Station Design Review
Mount Dennis Mobility Hub Update and Station Design ReviewCrosstown TO
 
Avenue station open house
Avenue station open house Avenue station open house
Avenue station open house Crosstown TO
 
Steeles Bridge EA PIC#2 powerpoint 04_01_2017
Steeles Bridge  EA PIC#2 powerpoint 04_01_2017Steeles Bridge  EA PIC#2 powerpoint 04_01_2017
Steeles Bridge EA PIC#2 powerpoint 04_01_2017Paul B. Martin
 

What's hot (19)

Emery village pic #1 boards v4 (reduced)
Emery village pic #1 boards v4 (reduced)Emery village pic #1 boards v4 (reduced)
Emery village pic #1 boards v4 (reduced)
 
Lawrence Park PIC 3 slides
Lawrence Park PIC 3 slidesLawrence Park PIC 3 slides
Lawrence Park PIC 3 slides
 
Mount Dennis Station Open House
Mount Dennis Station Open HouseMount Dennis Station Open House
Mount Dennis Station Open House
 
Reimagining yonge_street__pic_3_display_panels
Reimagining yonge_street__pic_3_display_panelsReimagining yonge_street__pic_3_display_panels
Reimagining yonge_street__pic_3_display_panels
 
Remove jcfo booklet
Remove jcfo bookletRemove jcfo booklet
Remove jcfo booklet
 
Remove jcfo boards
Remove jcfo boardsRemove jcfo boards
Remove jcfo boards
 
Gardiner East EA Public Forum 3 (Feb062014) - panels
Gardiner East EA Public Forum 3 (Feb062014) - panelsGardiner East EA Public Forum 3 (Feb062014) - panels
Gardiner East EA Public Forum 3 (Feb062014) - panels
 
Former Kodak Lands Update - November 19, 2015
Former Kodak Lands Update - November 19, 2015Former Kodak Lands Update - November 19, 2015
Former Kodak Lands Update - November 19, 2015
 
Kennedy Station Design Update Meeting Presentation
Kennedy Station Design Update Meeting PresentationKennedy Station Design Update Meeting Presentation
Kennedy Station Design Update Meeting Presentation
 
John Street Open House Display Boards
John Street Open House Display BoardsJohn Street Open House Display Boards
John Street Open House Display Boards
 
URBAN PLANNING AND URBAN DESIGN PORTFOLIO
URBAN PLANNING AND URBAN DESIGN PORTFOLIOURBAN PLANNING AND URBAN DESIGN PORTFOLIO
URBAN PLANNING AND URBAN DESIGN PORTFOLIO
 
تحليلي شارع الجمهورية : طرابلس- ليبيا وشارع كامبريدج -كندا - اعداد ايمان الشحومي
تحليلي شارع الجمهورية : طرابلس- ليبيا وشارع كامبريدج -كندا - اعداد ايمان الشحوميتحليلي شارع الجمهورية : طرابلس- ليبيا وشارع كامبريدج -كندا - اعداد ايمان الشحومي
تحليلي شارع الجمهورية : طرابلس- ليبيا وشارع كامبريدج -كندا - اعداد ايمان الشحومي
 
Beaufort-Sector1-Charrette-FinalPresentation
Beaufort-Sector1-Charrette-FinalPresentationBeaufort-Sector1-Charrette-FinalPresentation
Beaufort-Sector1-Charrette-FinalPresentation
 
Cedarvale station open house for website final2
Cedarvale station open house for website final2Cedarvale station open house for website final2
Cedarvale station open house for website final2
 
Mount Dennis Mobility Hub Update and Station Design Review
Mount Dennis Mobility Hub Update and Station Design ReviewMount Dennis Mobility Hub Update and Station Design Review
Mount Dennis Mobility Hub Update and Station Design Review
 
Sectors 2 & 3 Charrette Closing Presentation
Sectors 2 & 3 Charrette Closing PresentationSectors 2 & 3 Charrette Closing Presentation
Sectors 2 & 3 Charrette Closing Presentation
 
The Highline
 The Highline The Highline
The Highline
 
Avenue station open house
Avenue station open house Avenue station open house
Avenue station open house
 
Steeles Bridge EA PIC#2 powerpoint 04_01_2017
Steeles Bridge  EA PIC#2 powerpoint 04_01_2017Steeles Bridge  EA PIC#2 powerpoint 04_01_2017
Steeles Bridge EA PIC#2 powerpoint 04_01_2017
 

Similar to FG Gardiner New Simcoe Ramp - display boards

Brentcliffe-Victoria Park Construction Liaison Committee (CLC) Meeting - May ...
Brentcliffe-Victoria Park Construction Liaison Committee (CLC) Meeting - May ...Brentcliffe-Victoria Park Construction Liaison Committee (CLC) Meeting - May ...
Brentcliffe-Victoria Park Construction Liaison Committee (CLC) Meeting - May ...Crosstown TO
 
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)Crosstown TO
 
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) MeetingBrentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) MeetingCrosstown TO
 
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)Crosstown TO
 
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)Crosstown TO
 
Fairbank & Oakwood Stations Construction Liaison Committee - Feb 2018
Fairbank & Oakwood Stations Construction Liaison Committee - Feb 2018Fairbank & Oakwood Stations Construction Liaison Committee - Feb 2018
Fairbank & Oakwood Stations Construction Liaison Committee - Feb 2018Crosstown TO
 
Pharmacy to Kennedy Construction Liaison Committee Meeting
Pharmacy to Kennedy Construction Liaison Committee MeetingPharmacy to Kennedy Construction Liaison Committee Meeting
Pharmacy to Kennedy Construction Liaison Committee MeetingCrosstown TO
 
Leaside - Laird Construction Liaison Committee Meeting - March 2018
Leaside - Laird Construction Liaison Committee Meeting - March 2018Leaside - Laird Construction Liaison Committee Meeting - March 2018
Leaside - Laird Construction Liaison Committee Meeting - March 2018Crosstown TO
 
Jan. 21, 2015 City Council Presentation 2015 Capital Improvement Projects
Jan. 21, 2015 City Council Presentation 2015 Capital Improvement Projects Jan. 21, 2015 City Council Presentation 2015 Capital Improvement Projects
Jan. 21, 2015 City Council Presentation 2015 Capital Improvement Projects City of Corona
 
Pharmacy to Kennedy Construction Liaison Committee Meeting - May 2020, 2020
Pharmacy to Kennedy Construction Liaison Committee Meeting - May 2020, 2020Pharmacy to Kennedy Construction Liaison Committee Meeting - May 2020, 2020
Pharmacy to Kennedy Construction Liaison Committee Meeting - May 2020, 2020Crosstown TO
 
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee MeetingBrentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee MeetingCrosstown TO
 
Leaside open house sep 2014 slides
Leaside open house sep 2014   slidesLeaside open house sep 2014   slides
Leaside open house sep 2014 slidesCrosstown TO
 
Leaside open house sep 2014 Slides
Leaside open house sep 2014 SlidesLeaside open house sep 2014 Slides
Leaside open house sep 2014 SlidesCrosstown TO
 
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee MeetingBrentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee MeetingCrosstown TO
 
Chaplin & Avenue CLC - Construction Update - February 7, 2018
Chaplin & Avenue CLC - Construction Update - February 7, 2018Chaplin & Avenue CLC - Construction Update - February 7, 2018
Chaplin & Avenue CLC - Construction Update - February 7, 2018Brittany Maxwell
 
Leaside/ Laird CLC Construction Update - January 2019
Leaside/ Laird CLC Construction Update - January 2019Leaside/ Laird CLC Construction Update - January 2019
Leaside/ Laird CLC Construction Update - January 2019Crosstown TO
 
Leaside & Laird Stations Construction Liaison Committee Meeting - Feb 2018
Leaside & Laird Stations Construction Liaison Committee Meeting - Feb 2018Leaside & Laird Stations Construction Liaison Committee Meeting - Feb 2018
Leaside & Laird Stations Construction Liaison Committee Meeting - Feb 2018Crosstown TO
 
Avenue & Chaplin CLC - Construction Update: July 8, 2020
Avenue & Chaplin CLC - Construction Update: July 8, 2020Avenue & Chaplin CLC - Construction Update: July 8, 2020
Avenue & Chaplin CLC - Construction Update: July 8, 2020Crosstown TO
 
Martin Goodman Trail West – Project Overview
Martin Goodman Trail West – Project OverviewMartin Goodman Trail West – Project Overview
Martin Goodman Trail West – Project OverviewWaterfrontTO
 

Similar to FG Gardiner New Simcoe Ramp - display boards (20)

Brentcliffe-Victoria Park Construction Liaison Committee (CLC) Meeting - May ...
Brentcliffe-Victoria Park Construction Liaison Committee (CLC) Meeting - May ...Brentcliffe-Victoria Park Construction Liaison Committee (CLC) Meeting - May ...
Brentcliffe-Victoria Park Construction Liaison Committee (CLC) Meeting - May ...
 
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
 
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) MeetingBrentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
 
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
 
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
 
Fairbank & Oakwood Stations Construction Liaison Committee - Feb 2018
Fairbank & Oakwood Stations Construction Liaison Committee - Feb 2018Fairbank & Oakwood Stations Construction Liaison Committee - Feb 2018
Fairbank & Oakwood Stations Construction Liaison Committee - Feb 2018
 
Pharmacy to Kennedy Construction Liaison Committee Meeting
Pharmacy to Kennedy Construction Liaison Committee MeetingPharmacy to Kennedy Construction Liaison Committee Meeting
Pharmacy to Kennedy Construction Liaison Committee Meeting
 
Leaside - Laird Construction Liaison Committee Meeting - March 2018
Leaside - Laird Construction Liaison Committee Meeting - March 2018Leaside - Laird Construction Liaison Committee Meeting - March 2018
Leaside - Laird Construction Liaison Committee Meeting - March 2018
 
Jan. 21, 2015 City Council Presentation 2015 Capital Improvement Projects
Jan. 21, 2015 City Council Presentation 2015 Capital Improvement Projects Jan. 21, 2015 City Council Presentation 2015 Capital Improvement Projects
Jan. 21, 2015 City Council Presentation 2015 Capital Improvement Projects
 
Display boards
Display boardsDisplay boards
Display boards
 
Pharmacy to Kennedy Construction Liaison Committee Meeting - May 2020, 2020
Pharmacy to Kennedy Construction Liaison Committee Meeting - May 2020, 2020Pharmacy to Kennedy Construction Liaison Committee Meeting - May 2020, 2020
Pharmacy to Kennedy Construction Liaison Committee Meeting - May 2020, 2020
 
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee MeetingBrentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
 
Leaside open house sep 2014 slides
Leaside open house sep 2014   slidesLeaside open house sep 2014   slides
Leaside open house sep 2014 slides
 
Leaside open house sep 2014 Slides
Leaside open house sep 2014 SlidesLeaside open house sep 2014 Slides
Leaside open house sep 2014 Slides
 
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee MeetingBrentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
 
Chaplin & Avenue CLC - Construction Update - February 7, 2018
Chaplin & Avenue CLC - Construction Update - February 7, 2018Chaplin & Avenue CLC - Construction Update - February 7, 2018
Chaplin & Avenue CLC - Construction Update - February 7, 2018
 
Leaside/ Laird CLC Construction Update - January 2019
Leaside/ Laird CLC Construction Update - January 2019Leaside/ Laird CLC Construction Update - January 2019
Leaside/ Laird CLC Construction Update - January 2019
 
Leaside & Laird Stations Construction Liaison Committee Meeting - Feb 2018
Leaside & Laird Stations Construction Liaison Committee Meeting - Feb 2018Leaside & Laird Stations Construction Liaison Committee Meeting - Feb 2018
Leaside & Laird Stations Construction Liaison Committee Meeting - Feb 2018
 
Avenue & Chaplin CLC - Construction Update: July 8, 2020
Avenue & Chaplin CLC - Construction Update: July 8, 2020Avenue & Chaplin CLC - Construction Update: July 8, 2020
Avenue & Chaplin CLC - Construction Update: July 8, 2020
 
Martin Goodman Trail West – Project Overview
Martin Goodman Trail West – Project OverviewMartin Goodman Trail West – Project Overview
Martin Goodman Trail West – Project Overview
 

More from Toronto Public Consultation Unit

Waterfront Sanitary Servicing Master Plan Update (Oct. 30 PIE).
Waterfront Sanitary Servicing Master Plan Update (Oct. 30 PIE). Waterfront Sanitary Servicing Master Plan Update (Oct. 30 PIE).
Waterfront Sanitary Servicing Master Plan Update (Oct. 30 PIE). Toronto Public Consultation Unit
 
Six Points Interchange Reconfiguration public event display panels, May 11, 2017
Six Points Interchange Reconfiguration public event display panels, May 11, 2017Six Points Interchange Reconfiguration public event display panels, May 11, 2017
Six Points Interchange Reconfiguration public event display panels, May 11, 2017Toronto Public Consultation Unit
 
College Street Promenade BIA Streetscaping Update Public Meeting Feb 28 final
College Street Promenade BIA Streetscaping Update Public Meeting Feb 28  finalCollege Street Promenade BIA Streetscaping Update Public Meeting Feb 28  final
College Street Promenade BIA Streetscaping Update Public Meeting Feb 28 finalToronto Public Consultation Unit
 
Presentation - Park Lawn Lake Shore Transportation Master Plan Community Work...
Presentation - Park Lawn Lake Shore Transportation Master Plan Community Work...Presentation - Park Lawn Lake Shore Transportation Master Plan Community Work...
Presentation - Park Lawn Lake Shore Transportation Master Plan Community Work...Toronto Public Consultation Unit
 
Park Lawn Lake Shore Transportation Master Plan Community Workshop 1 Display ...
Park Lawn Lake Shore Transportation Master Plan Community Workshop 1 Display ...Park Lawn Lake Shore Transportation Master Plan Community Workshop 1 Display ...
Park Lawn Lake Shore Transportation Master Plan Community Workshop 1 Display ...Toronto Public Consultation Unit
 

More from Toronto Public Consultation Unit (20)

Waterfront Sanitary Servicing Master Plan Update (Oct. 30 PIE).
Waterfront Sanitary Servicing Master Plan Update (Oct. 30 PIE). Waterfront Sanitary Servicing Master Plan Update (Oct. 30 PIE).
Waterfront Sanitary Servicing Master Plan Update (Oct. 30 PIE).
 
SmartTrack Public Meeting Presentation
SmartTrack Public Meeting PresentationSmartTrack Public Meeting Presentation
SmartTrack Public Meeting Presentation
 
Waterfront Transit Reset Phase 2 Display Panels
Waterfront Transit Reset Phase 2 Display PanelsWaterfront Transit Reset Phase 2 Display Panels
Waterfront Transit Reset Phase 2 Display Panels
 
Waterfront Transit Reset Public Meeting Presentation
Waterfront Transit Reset Public Meeting Presentation Waterfront Transit Reset Public Meeting Presentation
Waterfront Transit Reset Public Meeting Presentation
 
Sewer Outfall Project
Sewer Outfall ProjectSewer Outfall Project
Sewer Outfall Project
 
General information
General informationGeneral information
General information
 
Disinfection System
Disinfection SystemDisinfection System
Disinfection System
 
2017 Sediment Basin construction updated information
2017 Sediment Basin construction updated information 2017 Sediment Basin construction updated information
2017 Sediment Basin construction updated information
 
Scarborough Subway TPAP Boards
Scarborough Subway TPAP Boards Scarborough Subway TPAP Boards
Scarborough Subway TPAP Boards
 
King Street Phase 2 Slide Deck
King Street Phase 2 Slide Deck King Street Phase 2 Slide Deck
King Street Phase 2 Slide Deck
 
Scarborough Subway TPAP PIC
Scarborough Subway TPAP PICScarborough Subway TPAP PIC
Scarborough Subway TPAP PIC
 
Six Points Interchange Reconfiguration public event display panels, May 11, 2017
Six Points Interchange Reconfiguration public event display panels, May 11, 2017Six Points Interchange Reconfiguration public event display panels, May 11, 2017
Six Points Interchange Reconfiguration public event display panels, May 11, 2017
 
Downsview Area Long Term Water Servicing
Downsview Area Long Term Water Servicing Downsview Area Long Term Water Servicing
Downsview Area Long Term Water Servicing
 
College Street Promenade BIA Streetscaping Update Public Meeting Feb 28 final
College Street Promenade BIA Streetscaping Update Public Meeting Feb 28  finalCollege Street Promenade BIA Streetscaping Update Public Meeting Feb 28  final
College Street Promenade BIA Streetscaping Update Public Meeting Feb 28 final
 
Swc public consultation_pres_170307_final
Swc public consultation_pres_170307_finalSwc public consultation_pres_170307_final
Swc public consultation_pres_170307_final
 
King Street Pilot Public Meeting
King Street Pilot Public MeetingKing Street Pilot Public Meeting
King Street Pilot Public Meeting
 
Presentation - Park Lawn Lake Shore Transportation Master Plan Community Work...
Presentation - Park Lawn Lake Shore Transportation Master Plan Community Work...Presentation - Park Lawn Lake Shore Transportation Master Plan Community Work...
Presentation - Park Lawn Lake Shore Transportation Master Plan Community Work...
 
Park Lawn Lake Shore Transportation Master Plan Community Workshop 1 Display ...
Park Lawn Lake Shore Transportation Master Plan Community Workshop 1 Display ...Park Lawn Lake Shore Transportation Master Plan Community Workshop 1 Display ...
Park Lawn Lake Shore Transportation Master Plan Community Workshop 1 Display ...
 
Downsview Water Service Improvement Study Boards
Downsview Water Service Improvement Study BoardsDownsview Water Service Improvement Study Boards
Downsview Water Service Improvement Study Boards
 
Downsview Water Service Improvement Study Maps
Downsview Water Service Improvement Study MapsDownsview Water Service Improvement Study Maps
Downsview Water Service Improvement Study Maps
 

Recently uploaded

Tuvalu Coastal Adaptation Project (TCAP)
Tuvalu Coastal Adaptation Project (TCAP)Tuvalu Coastal Adaptation Project (TCAP)
Tuvalu Coastal Adaptation Project (TCAP)NAP Global Network
 
The U.S. Budget and Economic Outlook (Presentation)
The U.S. Budget and Economic Outlook (Presentation)The U.S. Budget and Economic Outlook (Presentation)
The U.S. Budget and Economic Outlook (Presentation)Congressional Budget Office
 
World Press Freedom Day 2024; May 3rd - Poster
World Press Freedom Day 2024; May 3rd - PosterWorld Press Freedom Day 2024; May 3rd - Poster
World Press Freedom Day 2024; May 3rd - PosterChristina Parmionova
 
PPT BIJNOR COUNTING Counting of Votes on ETPBs (FOR SERVICE ELECTORS
PPT BIJNOR COUNTING Counting of Votes on ETPBs (FOR SERVICE ELECTORSPPT BIJNOR COUNTING Counting of Votes on ETPBs (FOR SERVICE ELECTORS
PPT BIJNOR COUNTING Counting of Votes on ETPBs (FOR SERVICE ELECTORSgovindsharma81649
 
Call On 6297143586 Viman Nagar Call Girls In All Pune 24/7 Provide Call With...
Call On 6297143586  Viman Nagar Call Girls In All Pune 24/7 Provide Call With...Call On 6297143586  Viman Nagar Call Girls In All Pune 24/7 Provide Call With...
Call On 6297143586 Viman Nagar Call Girls In All Pune 24/7 Provide Call With...tanu pandey
 
Item # 4 - 231 Encino Ave (Significance Only).pdf
Item # 4 - 231 Encino Ave (Significance Only).pdfItem # 4 - 231 Encino Ave (Significance Only).pdf
Item # 4 - 231 Encino Ave (Significance Only).pdfahcitycouncil
 
Top Rated Pune Call Girls Hadapsar ⟟ 6297143586 ⟟ Call Me For Genuine Sex Se...
Top Rated  Pune Call Girls Hadapsar ⟟ 6297143586 ⟟ Call Me For Genuine Sex Se...Top Rated  Pune Call Girls Hadapsar ⟟ 6297143586 ⟟ Call Me For Genuine Sex Se...
Top Rated Pune Call Girls Hadapsar ⟟ 6297143586 ⟟ Call Me For Genuine Sex Se...Call Girls in Nagpur High Profile
 
Incident Command System xxxxxxxxxxxxxxxxxxxxxxxxx
Incident Command System xxxxxxxxxxxxxxxxxxxxxxxxxIncident Command System xxxxxxxxxxxxxxxxxxxxxxxxx
Incident Command System xxxxxxxxxxxxxxxxxxxxxxxxxPeter Miles
 
Antisemitism Awareness Act: pénaliser la critique de l'Etat d'Israël
Antisemitism Awareness Act: pénaliser la critique de l'Etat d'IsraëlAntisemitism Awareness Act: pénaliser la critique de l'Etat d'Israël
Antisemitism Awareness Act: pénaliser la critique de l'Etat d'IsraëlEdouardHusson
 
Government e Marketplace GeM Presentation
Government e Marketplace GeM PresentationGovernment e Marketplace GeM Presentation
Government e Marketplace GeM Presentationgememarket11
 
Financing strategies for adaptation. Presentation for CANCC
Financing strategies for adaptation. Presentation for CANCCFinancing strategies for adaptation. Presentation for CANCC
Financing strategies for adaptation. Presentation for CANCCNAP Global Network
 
Booking open Available Pune Call Girls Shukrawar Peth 6297143586 Call Hot In...
Booking open Available Pune Call Girls Shukrawar Peth  6297143586 Call Hot In...Booking open Available Pune Call Girls Shukrawar Peth  6297143586 Call Hot In...
Booking open Available Pune Call Girls Shukrawar Peth 6297143586 Call Hot In...tanu pandey
 
A Press for the Planet: Journalism in the face of the Environmental Crisis
A Press for the Planet: Journalism in the face of the Environmental CrisisA Press for the Planet: Journalism in the face of the Environmental Crisis
A Press for the Planet: Journalism in the face of the Environmental CrisisChristina Parmionova
 
VIP Model Call Girls Narhe ( Pune ) Call ON 8005736733 Starting From 5K to 25...
VIP Model Call Girls Narhe ( Pune ) Call ON 8005736733 Starting From 5K to 25...VIP Model Call Girls Narhe ( Pune ) Call ON 8005736733 Starting From 5K to 25...
VIP Model Call Girls Narhe ( Pune ) Call ON 8005736733 Starting From 5K to 25...SUHANI PANDEY
 
Coastal Protection Measures in Hulhumale'
Coastal Protection Measures in Hulhumale'Coastal Protection Measures in Hulhumale'
Coastal Protection Measures in Hulhumale'NAP Global Network
 
Call Girls Chakan Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Chakan Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Chakan Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Chakan Call Me 7737669865 Budget Friendly No Advance Bookingroncy bisnoi
 
Scaling up coastal adaptation in Maldives through the NAP process
Scaling up coastal adaptation in Maldives through the NAP processScaling up coastal adaptation in Maldives through the NAP process
Scaling up coastal adaptation in Maldives through the NAP processNAP Global Network
 
Call Girls Sangamwadi Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Sangamwadi Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Sangamwadi Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Sangamwadi Call Me 7737669865 Budget Friendly No Advance Bookingroncy bisnoi
 

Recently uploaded (20)

Tuvalu Coastal Adaptation Project (TCAP)
Tuvalu Coastal Adaptation Project (TCAP)Tuvalu Coastal Adaptation Project (TCAP)
Tuvalu Coastal Adaptation Project (TCAP)
 
The U.S. Budget and Economic Outlook (Presentation)
The U.S. Budget and Economic Outlook (Presentation)The U.S. Budget and Economic Outlook (Presentation)
The U.S. Budget and Economic Outlook (Presentation)
 
(NEHA) Call Girls Nagpur Call Now 8250077686 Nagpur Escorts 24x7
(NEHA) Call Girls Nagpur Call Now 8250077686 Nagpur Escorts 24x7(NEHA) Call Girls Nagpur Call Now 8250077686 Nagpur Escorts 24x7
(NEHA) Call Girls Nagpur Call Now 8250077686 Nagpur Escorts 24x7
 
World Press Freedom Day 2024; May 3rd - Poster
World Press Freedom Day 2024; May 3rd - PosterWorld Press Freedom Day 2024; May 3rd - Poster
World Press Freedom Day 2024; May 3rd - Poster
 
PPT BIJNOR COUNTING Counting of Votes on ETPBs (FOR SERVICE ELECTORS
PPT BIJNOR COUNTING Counting of Votes on ETPBs (FOR SERVICE ELECTORSPPT BIJNOR COUNTING Counting of Votes on ETPBs (FOR SERVICE ELECTORS
PPT BIJNOR COUNTING Counting of Votes on ETPBs (FOR SERVICE ELECTORS
 
Call On 6297143586 Viman Nagar Call Girls In All Pune 24/7 Provide Call With...
Call On 6297143586  Viman Nagar Call Girls In All Pune 24/7 Provide Call With...Call On 6297143586  Viman Nagar Call Girls In All Pune 24/7 Provide Call With...
Call On 6297143586 Viman Nagar Call Girls In All Pune 24/7 Provide Call With...
 
Item # 4 - 231 Encino Ave (Significance Only).pdf
Item # 4 - 231 Encino Ave (Significance Only).pdfItem # 4 - 231 Encino Ave (Significance Only).pdf
Item # 4 - 231 Encino Ave (Significance Only).pdf
 
Top Rated Pune Call Girls Hadapsar ⟟ 6297143586 ⟟ Call Me For Genuine Sex Se...
Top Rated  Pune Call Girls Hadapsar ⟟ 6297143586 ⟟ Call Me For Genuine Sex Se...Top Rated  Pune Call Girls Hadapsar ⟟ 6297143586 ⟟ Call Me For Genuine Sex Se...
Top Rated Pune Call Girls Hadapsar ⟟ 6297143586 ⟟ Call Me For Genuine Sex Se...
 
Incident Command System xxxxxxxxxxxxxxxxxxxxxxxxx
Incident Command System xxxxxxxxxxxxxxxxxxxxxxxxxIncident Command System xxxxxxxxxxxxxxxxxxxxxxxxx
Incident Command System xxxxxxxxxxxxxxxxxxxxxxxxx
 
Antisemitism Awareness Act: pénaliser la critique de l'Etat d'Israël
Antisemitism Awareness Act: pénaliser la critique de l'Etat d'IsraëlAntisemitism Awareness Act: pénaliser la critique de l'Etat d'Israël
Antisemitism Awareness Act: pénaliser la critique de l'Etat d'Israël
 
Government e Marketplace GeM Presentation
Government e Marketplace GeM PresentationGovernment e Marketplace GeM Presentation
Government e Marketplace GeM Presentation
 
Russian🍌Dazzling Hottie Get☎️ 9053900678 ☎️call girl In Chandigarh By Chandig...
Russian🍌Dazzling Hottie Get☎️ 9053900678 ☎️call girl In Chandigarh By Chandig...Russian🍌Dazzling Hottie Get☎️ 9053900678 ☎️call girl In Chandigarh By Chandig...
Russian🍌Dazzling Hottie Get☎️ 9053900678 ☎️call girl In Chandigarh By Chandig...
 
Financing strategies for adaptation. Presentation for CANCC
Financing strategies for adaptation. Presentation for CANCCFinancing strategies for adaptation. Presentation for CANCC
Financing strategies for adaptation. Presentation for CANCC
 
Booking open Available Pune Call Girls Shukrawar Peth 6297143586 Call Hot In...
Booking open Available Pune Call Girls Shukrawar Peth  6297143586 Call Hot In...Booking open Available Pune Call Girls Shukrawar Peth  6297143586 Call Hot In...
Booking open Available Pune Call Girls Shukrawar Peth 6297143586 Call Hot In...
 
A Press for the Planet: Journalism in the face of the Environmental Crisis
A Press for the Planet: Journalism in the face of the Environmental CrisisA Press for the Planet: Journalism in the face of the Environmental Crisis
A Press for the Planet: Journalism in the face of the Environmental Crisis
 
VIP Model Call Girls Narhe ( Pune ) Call ON 8005736733 Starting From 5K to 25...
VIP Model Call Girls Narhe ( Pune ) Call ON 8005736733 Starting From 5K to 25...VIP Model Call Girls Narhe ( Pune ) Call ON 8005736733 Starting From 5K to 25...
VIP Model Call Girls Narhe ( Pune ) Call ON 8005736733 Starting From 5K to 25...
 
Coastal Protection Measures in Hulhumale'
Coastal Protection Measures in Hulhumale'Coastal Protection Measures in Hulhumale'
Coastal Protection Measures in Hulhumale'
 
Call Girls Chakan Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Chakan Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Chakan Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Chakan Call Me 7737669865 Budget Friendly No Advance Booking
 
Scaling up coastal adaptation in Maldives through the NAP process
Scaling up coastal adaptation in Maldives through the NAP processScaling up coastal adaptation in Maldives through the NAP process
Scaling up coastal adaptation in Maldives through the NAP process
 
Call Girls Sangamwadi Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Sangamwadi Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Sangamwadi Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Sangamwadi Call Me 7737669865 Budget Friendly No Advance Booking
 

FG Gardiner New Simcoe Ramp - display boards

  • 2. Gardiner Expressway York/Bay/Yonge Ramps 2013 Study Objectives • Originally constructed from 1958 to 1964, the ramps need to address today’s demands and uses • Long-term plans for the waterfront aim to remove barriers and reconnect the City with Lake Ontario • Waterfront streets are to be remade as “places” with high quality amenities for pedestrians and cyclists • Improving conditions for the increasing volume of pedestrians, cyclists and vehicles requires a reworking of the road network
  • 4. Study Outcome: Replacing the York/Bay/Yonge Ramps The Environmental Assessment Study (2013) recommended: • Removing the long elevated ramp to Bay Street and loop ramp at York Street • Installing a new shorter exit ramp to Harbour Street ending at Lower Simcoe Street • Widening Harbour Street from 3 to 4 lanes from Lower Simcoe to Bay Street • Adding streetscaping elements (pavers, trees) along Harbour Street • Replacing the York ramp loop with redesigned park space
  • 6. Study Outcome: New Lower Simcoe Ramp Simcoe Street Bay Street Queens Quay York Street
  • 7. Key Benefits A new ramp to Lower Simcoe Street & Improvements to Harbour Street will: • Continue to accommodate high volumes of traffic flow between the Gardiner Expressway, the downtown core and the waterfront • Create an enhanced public realm for the increasing number of pedestrians and cyclists living and working in, or visiting the area • Improve public safety by including well-signalized, well-lit intersections and better signage for all users • Create park space (within the existing York Street off-ramp site) to help enhance the waterfront area Improvements help support all modes of travel
  • 8. Existing York/Yonge/Bay Ramps (Looking west @ Lower Simcoe Street) Main expressway structure YBY Exit ramp structure
  • 9. Future Lower Simcoe Ramp (Looking west @ Lower Simcoe Street)
  • 10. Existing York Street Intersection (Looking south-east towards the lake)
  • 11. Existing York Street Intersection - 3 lanes travelling east to Harbour Street - York St. exit ramp bisects park space - no sidewalk access on east side of York St - traffic median at south-east strands pedestrian traffic
  • 12. Future York Street Intersection (Looking south-east towards the lake)
  • 13. + new northbound turn lane + added lane on Harbour S + improved pedestrian connections + redesigned park space + added through traffic lane + improved multi-use trail Future York Street Intersection
  • 14. Existing Bay Street Ramp (adjacent to Harbour Street)
  • 15. Future Harbour Street (Looking west from Bay Street) + improved multi-use trail + added lane on Harbour Street + improved sidewalks + added trees
  • 16. Future Harbour Street (Looking east towards Bay Street)
  • 17. Construction Phase 1: Preparatory Work July 2016 to December 2016 • Foundation and substructure of new ramp at Lower Simcoe started • Underground infrastructure relocated (fibre optic cables, sewers, etc…) • No closures occurred; only temporary lane restrictions during off-peak hours on eastbound Lake Shore Blvd. • Multi-use trail closed from Rees Street to Lower Simcoe Street
  • 18. Construction Phase 2: Demolition of Existing Ramps & Construction of New Lower Simcoe Ramp and Harbour Street April 2017 to January 2018 Tasks Jan Feb Mar Apr May June July Aug Sept Oct- Jan Complete foundation and substructure for new ramp at Lower Simcoe Street Install new catch basins and stormwater leads on Harbour St Demolish existing YBY off ramp Relocate Hydro vault and install new Hydro transformer Construct new Lower Simcoe ramp Install automated de-icing system on ramp Widen Harbour Street to 4 lanes along with streetscape improvements
  • 19. Work Details Work Hours: • 7:00 am to 7:00 pm, Monday to Saturday • Periods of 24/7 and overnight work may be used to help minimize traffic congestion and shorten overall project duration Noise: • Demolition work & concrete removal will be loud and disruptive at times • Work may take place around the clock in some instances, but the noisiest work will cease by 11:00 p.m. Dust: • Contractor must control dust • Work surfaces to be wetted down to avoid spreading dust
  • 20. Traffic Management York/Bay/Yonge Ramp will be CLOSED starting Monday, April 17 to January 2018 • Motorists will still have full access to downtown by exiting the EB Gardiner Expressway at: - Jameson Avenue - Spadina Avenue - Jarvis Street • EB off ramp at Spadina will be adjusted to allow for movement onto EB Lake Shore Boulevard (NB/Left turn at Spadina will remain) • Traffic signal times will be adjusted to reduce congestion • Full access to all westbound Gardiner ramps from Lake Shore Blvd West will be maintained
  • 21. Spadina Avenue Off Ramp at Lake Shore Blvd Motorists exiting the Gardiner Expressway at Spadina Avenue will be able to access Lake Shore Boulevard to travel eastbound. A locked gate along the ramp exit will be opened to allow motorists to move onto Lake Shore Boulevard. Bollards will be placed on Lake Shore Blvd ahead of the locked gate to provide a lane of traffic for motorists to move into. Spadina Ave Off-Ramp Eastbound
  • 22. During Demolition: April to July • EB on-ramp at Rees Street will be: - closed during off-peak hours (9:30 a.m. to 3:30 p.m.) - open during peak hours to allow demolition during the day and reduce overnight work • Intersections along Harbour Street at Lower Simcoe, York & Bay Streets will be closed for select weekends to safely remove the overhead spans of the York/Bay/Yonge ramps (dates to be confirmed) Throughout Construction: April to January • EB Lake Shore Boulevard/Harbour Street will be reduced to two lanes from Lower Simcoe Street to Bay Street • Motorists can use parallel east/west streets south of Queen St Traffic Management
  • 23. Notification & Access for Vehicle Traffic • Portable Variable Message signs will be placed along EB Lake Shore Blvd and EB Gardiner Expressway • Orange and black advance traffic advisory signage will be placed at key locations • Road closures and restrictions will be managed in coordination with local events • Laneways and driveways that serve businesses will remain accessible for deliveries or service • Access for emergency vehicles will be maintained at all times • Changeable Message signage on the DVP, Gardiner and Lake Shore Blvd will advise motorists of the ramp closure starting March 1st
  • 24. Pedestrian and Cyclist Access • Sidewalks to remain open on: • Lower Simcoe and York Streets for north/south travel • North side of Harbour Street • Multi-use trail alongside Lake Shore Blvd will remain closed during Phase 2 • Cyclists to use detour from Martin Goodman Trail at Rees St to Queens Quay
  • 25. Raising Awareness • Construction Notice Update #1 issued via Canada Post to approx. 55,000 properties and emailed to all stakeholders • Email updates to be provided throughout construction Sign-up up at toronto.ca/simcoe-ramp • Road closures to be promoted through Media Releases, Twitter and Email Updates • A Construction Liaison Committee will be formed with local property groups to address concerns during construction Help us spread the word - include information on your websites and email your audience