September 2013
1
Contents
1. Pre- Commissioning
2. Preservation of pipeline
3. Commissioning Activities
2
Commissioning Procedures
These Procedures covers the following:
 Pre-commissioning, which covers all activities and approvals necessary to allow purging with gas and
pressurizing to normal operating pressure to commence.
 Pipeline preservation, in case gas-initiation of the pipeline is performed later than six months after
the installations are completed the pipeline is preserved.
 Commissioning of dry pipelines. The criteria for being considered a dry pipeline are as follows:
• Dew point temperature must be < - 20° C measured at atmospheric pressure.
• Over-pressure following sealing of the lines must be at least I barg.
• The acceptable minimum standard during the whole period of preservation is a dew
point temperature of - I0° C.
 Commissioning of wet pipelines. Wet pipelines are considered those that are not met the previous
criteria·
3
1.1 PRE-COMMISSIONING ACTIVITIES
On substantial completion of construction activities, Contractor mobilizes its commissioning team to
initiate pre-commissioning activities in a phased manner.
The objective of pre-commissioning is to ensure that the pipeline as well all the facilities have been
completed according to the Project Specifications and that commissioning and operation will take
place safely and effectively.
Also during the pre-commissioning should be verified that all the relevant data with the
commissioning of the pipeline has been received and that the commissioning procedure is
presented and discussed with all personnel involved.
Another important aspect which has to be verified during this procedure is that all the necessary
drawings, technical information, and O & M manuals have been received and that the operating
plan has been existing .
Pre-commissioning may therefore be defined as all the checks that are to be completed prior to
commissioning being permitted to commence.
4
The pre-commissioning phase includes three main types of field activities:
a) Systematic conformity checks, carried out on each item of equipment or component, such as
pressure gauges, cables, etc., to verify visually the condition of the equipment, the quality of the
installation, the compliance with project drawings and specifications, manufacturer's
instructions, safety rules, codes, standards and good engineering practices. These checks will
confirm the following:
• All pipe assemblies and weldings have been completed.
• All pipeline pressure and leak tests have been completed and relevant certified test
documents have been received (weld radiographs, hydrostatic test documents etc)
• Electrical and control installations have been completed and are functioning.
5
• Cathodic protection systems have been completed and are functioning.
• Security fences have been installed around all above ground high pressure pipeline facilities.
• Emergency vehicle access is provided to all pipe line facilities (land valve stations, MIR-stations,
Scraper Stations.
• Right-of-way restoration has been completed according to specifications and landowner
agreements and all environmental concerns have been addressed.
b) Equipment static/de-energized tests, to ensure the quality of a number of critical components.
This "cold" testing concerns all disciplines, e.g. calibration of instruments, machinery
alignments, setting of safety valves, pressure testing of piping, cable continuities, etc.
c) Dewatering and drying of the pipeline and the vessels has been completed in accordance with
specifications and approved procedures.
6
As soon as practical, the Pre-commissioning team shall acquire a complete set of drawings and data
as listed below:
1. As built drawings and technical information regarding:
• Pipeline sections between line valve stations : pipe logs showing the location, size, wall
thickness, and pipe grade
• Line Valve stations: schematic showing venting and valving arrangements, as well as
technical data regarding material, fittings, valves, etc.
• M/R Stations: schematics showing venting arrangements, customer interconnections for gas
service and by-pass technical data regarding material, fittings, valves, etc.
• Scraper Stations: schematics showing piping arrangement as well as technical data regarding
material, fittings, valves, etc.
• Cathodic protection facilities: including type and description of rectifiers, number and type of
sacrificial anodes, measuring posts, insulating couplings, type of pipeline external and internal
coating
7
2. Route Maps which indicate among the others the pipeline routing, the depth of pipeline, the
access routes to valve stations, M/R Stations , Scraper Stations, cathodic protection rectifiers
and measuring posts have been received.
3. 3. Vendor-supplied equipment design specifications, installation drawings, operation and
maintenance manuals.
4. 3. All QC documentation relating to the construction testing i.e. hydro test packs, cable
checklists etc. as well as emergency procedures and operating plans.
Pre-commissioning work described herein will require all necessary tools, test instruments, water,
air and electric power etc to be made available to the Pre-commissioning team. Also spare parts and
repair materials as well as that all the necessary tools and work equipment as pipe locators, gas
detection equipment etc should be available.
Each craftsman such as pipe fitter, millwright, mechanic, instrument technician, or electrician, who
is assisting the Pre-commissioning team, shall have his normal tools available.
8
All necessary tags, warning tapes, barricade tapes and safety supplies shall be made available at the
site. The following signs are posted at strategic locations before proceeding with the appropriate
Pre-commissioning activities:
Tags:
 No smoking
 Danger, high voltage
 Do not enter beyond this point
9
Finally, the following safety supplies are made available to all staff involved in the pre-commissioning
activities.
 Ear Protection
 Safety Glasses
 Hard Hats
 First Aid Kit
 Face Shield
 Chemical Gloves
 Safety Goggles
 Padlocks with Multi-Lock Clips
 Safety Boots
 Boiler suits/overalls
10
For the purpose of pre-commissioning, the facilities will be subdivided suitably into a few systems.
The pre-commissioning checks of each piece of equipment are to be as complete and as
comprehensive as possible to ensure that the equipment are installed as specified and will operate as
designed. Proper pre-commissioning will ensure that the facilities can be made operable with the
least number of problems. To achieve this,
(1) The Pre-commissioning Team shall become familiar with all data and information.
(2) The Pre-commissioning Team shall start all pre-commissioning checks as early as possible
during the construction activities to ensure that the final installation of all equipment is as designed
and specified.
11
All personnel involved in the pre-commissioning and commissioning activities have to be
educated with regard to the following:
• Access routes to line valve stations, MfR stations, and scraper stations.
• Vehicle and equipment use and capabilities.
• The overall commissioning plan and the co-ordination and procedures to be utilized.
• The job responsibilities of each individual and his part in the overall plan.
• Determination of gas volumes required for purging and loading.
• Sequence of valve sections to be purged and loaded
• Details of purging and loading procedures. Details .of emergency and operating plans and
responses to any problems or difficulties that may be encountered.
• The effects and precautions necessary when working with high pressure natural gas.
• Use and capabilities of telecommunication and mobile telecommunications systems.
Also it has to be verified that involved personnel have been trained and qualified for operating
the pipeline.
12
The following guidelines summarize all activities to be completed during the pre-commissioning
phase of the project.
1. Testing and adequate flushing of all piping systems.
2. Removal of all blinds or spool pieces used during hydrostatic testing.
3. Proper positioning of spectacle blinds.
4. Witness or calibrate, and test all instruments in accordance with the Pre-commissioning
procedures, and record all calibrations and test data on the checklists provided for each
instrument and instrument loop.
5. Verify that lubricants, oils, coolants, etc., required for all equipment are on the job site and in
good condition (i.e. not contaminated).
6. Ensure that fire extinguishers are in place.
7. Check all electrical closures.
8. Ensure that all escape routes are clear of obstacles.
13
9. Ensure that all eyewash stations are operational.
10. Wear personal safety equipment.
11. Clear area from unauthorized personnel.
12. Be aware of the wind direction.
13. Be aware of the designated meeting area location.
14. Ensure that fire detection equipment is operational.
14
General
Preservation of a pipeline is carried out to maintain the pre commissioning condition, which the
installations are in until commissioning comes into force.
2.1 Preservation with dry air
If the initial gas filling of the pipelines is carried out later than six months after the installation-
works are completed preservation of the pipelines takes place according to the dry air method. The
main criteria for a dry pipeline are as follows:
 Dewpoint temperature must be ≤ -20°C measured at atmospheric pressure.
 Overpressure after sealing of the pipelines must be at least one barg.
 The acceptable minimum norm during the entire preserva tion-period is a measured dewpoint
temperature of ≤ -10 °C (measured at atmospheric pressure and at an overpressure of one barg).
15
The dewpoint temperature and the pressure is measured and registered within the preservation
period with stated intervals since the pipeline-contractor as well as a neutral third party is
involved.
2.2 Preservation with nitrogen (N2)
If it is decided to preserve the pipeline by the use of nitrogen the criteria are as follows:
 Purge with nitrogen until achieving 100% N2
 The overpressure after sealing must be at least 2 barg.
Measurements of the pressure at stated intervals during the preservation period is required.
16
3.1 Commissioning of dry pipelines
3.1.1 General
Commissioning includes the following activities:
The supervision and execution of the Commissioning activities are to be carried out by DESFA’s
personnel who are suitably trained and qualified for this task.
Commissioning check· list is to be strictly adhered to during execution of the commissioning.
Commissioning is to take place in coordination with Gas Control Center. No valves are to be opened
without prior approval from Gas Control Center.
17
Purging of a section of pipeline is to be considered as complete when 100 % gas is measured 3
times at the exhaust point with two independent gas measuring instruments.
When commissioning a new section of pipeline, or possibly a modified section of pipeline (e.g.
in case of repair or construction activity) notification is to be carried out by means of form 2.2.b.
 Purging, loading, and placing into service may be carried out only after presentation of the
notification of placing into service.
 The person responsible for observation of the commissioning policy is DESFA’s District
Manager, or alternately, a deputy named by him.
The criteria for being considered a dry pipeline are as described here above, and if those criteria
are not fulfilled then the pipeline is considered as wet.
Sections of the pipeline which have been constructed, as well as sections of the pipeline on which
repairs have been carried out, contain air or a mixture of gas and air. These pipelines or sections
of pipelines must be placed into service in a safe, economical and environmentally responsible
manner.
18
The following description and points to be observed ensure a trouble-free process for commissioning
of dry pipelines.
 Prepare the scope and the technique for commissioning and complying with Gas Control
requirements
 Establish the purge direction
 Determine whether inert gas is required and eventually required volume
 Calculate the purge time
 Determine which will be the inlet throttle valve and exhaust valve and carry out a function
test of these valves
 Establish the purge velocity. This velocity is usually between 5 m/sec in the main pipeline if no
inert gas is used or 7-10 m/sec if inert gas is used
19
 Check all facilities which have a relation to the commissioning according to the safety check
list which is herewith
 Ensure that capable and adequate personnel is assigned
 Ensure satisfactory performance of vehicles, equipment, and instruments
 Ensure effective and reliable communications between the inlet point, the exhaust point,
and Gas Control Center
 Advise Gas Control Center of commencement of purging, loading, and placing into service
 Ensure with the Gas Control Center for the availability of the required quantities of gas
 In case of use of inert gas, the adequate volume will be determined from the cross sectional
area of the pipe. An inert gas plug approx. 300 m in length is recommended as it may be
difficult to maintain a purge velocity of 3 - 7 rn/s. The supervisor in charge of commissioning
will determine if inert gas is to be used
20
3.1.2 Commissioning procedure
 The procedure begins with the injection of gas , or inert gas if it is decided, into the inlet throttle
valve which is opened slowly, while measuring the velocity at the outlet throttle valve
 Then should regulate the purge velocity (usually approx. 10 rn/sec in the main
 pipeline - 90 m/sec from vent stack) following always the be given by a per son at the vent stack
 Commence timing of the purge only after regulation of the purge velocity has been achieved
 Close to the expiration of the purge time, the gas concentration is to be measured by means of
two independent gas measuring instruments
 After verification of measurements of 100 % Vol gas at least 3 times then first the throttling
valves of the exit and then the valves of the insert point are to be closed in that order
 All vented gas quantities are to be reported for the calculation of the vented gas
21
 Two pressure gauges and one pressure recorder are installed at the start and end of the pipeline
section to be loaded (one additional pressure gauge is to be kept in reserve in case of
malfunction). The range of the scales of the gauges and recorders must be at least equal to the
maximum possible loading pressure
 The pipeline is loaded in stages so that the pressure in the pipeline rises to 5 - 10 bar during
the first hour
 The second hour the throttle inner valve is opened further so that the pressure rises to 10 - 20
bar
 Finally the inlet throttle valve is opened further so that final loading pressure is reached after
three hours
 Depending on the quantity of gas supply available for loading the pipeline, lower pressure
increments are to be selected in accordance with Gas Control Center
22
 After each hour a· leak test of susceptible points on the pipeline (e.g. tie-in welds, flange
connections, etc.) is to be carried out using a foam producing liquid. If any leaks are found
permanent repairs are to be carried out in accordance with specifications before proceeding
with the loading operation
 Leaks from fittings should be tightened in accordance to vendors instructions
 Loading time for the pipeline or section of pipeline will generally be determined by the gas
volumes available and the configuration at the inlet and throttle valve
 After the pipeline has been loaded (pressure equalization) it will be connected to the pipeline
system
 For further commissioning of pipeline downstream Section the above procedure is repeated
23
3.2 Commissioning of wet pipelines
In the case of wet pipeline and before purging with natural gas it is necessary to dry the pipeline.
The cause of this is that under certain pressure and temperature conditions, gas hydrates will form
when hygroscopic water (i.e. water remaining after de-watering) comes into contact with gas. The
range of pressure and temperature, within which natural gas hydrates form, lies above 0o C
(water dew point) and 6 bar. A decomposition of gas hydrates occurs by an increase in temperature
or reduction in pressure.
Based on present experience the following dehydration procedures are generally accepted:
• Drying with dry air
• Absorption of residual water by alcohol
• Drying of residual water by vacuum
After the drying of the pipeline the procedure for the commissioning of dry pipeline is followed.
24

Weitere ähnliche Inhalte

Was ist angesagt?

PetroSync - Pre-Commissioning, Commissioning and Start-Up
PetroSync - Pre-Commissioning, Commissioning and Start-UpPetroSync - Pre-Commissioning, Commissioning and Start-Up
PetroSync - Pre-Commissioning, Commissioning and Start-UpPetroSync
 
Study 5: Pre-commissioning Safety Review
Study 5: Pre-commissioning Safety ReviewStudy 5: Pre-commissioning Safety Review
Study 5: Pre-commissioning Safety ReviewGerard B. Hawkins
 
Piping Hydrostatic Test / Hydrotesting
Piping Hydrostatic Test / HydrotestingPiping Hydrostatic Test / Hydrotesting
Piping Hydrostatic Test / HydrotestingAbhijeet Nagle
 
AIR COMPRESSOR CHECKLIST Form # HSEQ - ACL Rev 2.docx
AIR COMPRESSOR CHECKLIST Form # HSEQ - ACL Rev 2.docxAIR COMPRESSOR CHECKLIST Form # HSEQ - ACL Rev 2.docx
AIR COMPRESSOR CHECKLIST Form # HSEQ - ACL Rev 2.docxDwarika Bhushan Sharma
 
Hazardous Area Classification
Hazardous Area ClassificationHazardous Area Classification
Hazardous Area Classificationdebuddit
 
Hydrotest REPORT FOR 4'' 158m Line.
Hydrotest REPORT FOR 4'' 158m Line.Hydrotest REPORT FOR 4'' 158m Line.
Hydrotest REPORT FOR 4'' 158m Line.Emeka Ngwobia
 
Work Permit System
Work Permit SystemWork Permit System
Work Permit SystemGagan Tanwar
 
PIPING & INSTRUMENTATION DIAGRAM.pdf
PIPING & INSTRUMENTATION DIAGRAM.pdfPIPING & INSTRUMENTATION DIAGRAM.pdf
PIPING & INSTRUMENTATION DIAGRAM.pdfMassinissaHamel
 
Piping Training course-How to be an Expert in Pipe & Fittings for Oil & Gas c...
Piping Training course-How to be an Expert in Pipe & Fittings for Oil & Gas c...Piping Training course-How to be an Expert in Pipe & Fittings for Oil & Gas c...
Piping Training course-How to be an Expert in Pipe & Fittings for Oil & Gas c...Varun Patel
 
PORTABLE TOOLS CHECKLIST Form # HSEQ - PTC Rev 2 -.docx
PORTABLE TOOLS CHECKLIST Form # HSEQ - PTC  Rev 2 -.docxPORTABLE TOOLS CHECKLIST Form # HSEQ - PTC  Rev 2 -.docx
PORTABLE TOOLS CHECKLIST Form # HSEQ - PTC Rev 2 -.docxDwarika Bhushan Sharma
 
Pressure Safety Valve Sizing - API 520/521/526
Pressure Safety Valve Sizing - API 520/521/526Pressure Safety Valve Sizing - API 520/521/526
Pressure Safety Valve Sizing - API 520/521/526Vijay Sarathy
 
what is process piping
what is process pipingwhat is process piping
what is process pipingVarun Patel
 
Heat exchanger types and hydro testing
Heat exchanger types and hydro testingHeat exchanger types and hydro testing
Heat exchanger types and hydro testingwaqarahmed445
 

Was ist angesagt? (20)

PetroSync - Pre-Commissioning, Commissioning and Start-Up
PetroSync - Pre-Commissioning, Commissioning and Start-UpPetroSync - Pre-Commissioning, Commissioning and Start-Up
PetroSync - Pre-Commissioning, Commissioning and Start-Up
 
Study 5: Pre-commissioning Safety Review
Study 5: Pre-commissioning Safety ReviewStudy 5: Pre-commissioning Safety Review
Study 5: Pre-commissioning Safety Review
 
Piping Hydrostatic Test / Hydrotesting
Piping Hydrostatic Test / HydrotestingPiping Hydrostatic Test / Hydrotesting
Piping Hydrostatic Test / Hydrotesting
 
AIR COMPRESSOR CHECKLIST Form # HSEQ - ACL Rev 2.docx
AIR COMPRESSOR CHECKLIST Form # HSEQ - ACL Rev 2.docxAIR COMPRESSOR CHECKLIST Form # HSEQ - ACL Rev 2.docx
AIR COMPRESSOR CHECKLIST Form # HSEQ - ACL Rev 2.docx
 
Weekly air compressor check list
Weekly air compressor check listWeekly air compressor check list
Weekly air compressor check list
 
Weekly welding machine checklist
Weekly welding machine checklistWeekly welding machine checklist
Weekly welding machine checklist
 
Hazardous Area Classification
Hazardous Area ClassificationHazardous Area Classification
Hazardous Area Classification
 
Hydrotest REPORT FOR 4'' 158m Line.
Hydrotest REPORT FOR 4'' 158m Line.Hydrotest REPORT FOR 4'' 158m Line.
Hydrotest REPORT FOR 4'' 158m Line.
 
Work Permit System
Work Permit SystemWork Permit System
Work Permit System
 
PIPING & INSTRUMENTATION DIAGRAM.pdf
PIPING & INSTRUMENTATION DIAGRAM.pdfPIPING & INSTRUMENTATION DIAGRAM.pdf
PIPING & INSTRUMENTATION DIAGRAM.pdf
 
Piping Training course-How to be an Expert in Pipe & Fittings for Oil & Gas c...
Piping Training course-How to be an Expert in Pipe & Fittings for Oil & Gas c...Piping Training course-How to be an Expert in Pipe & Fittings for Oil & Gas c...
Piping Training course-How to be an Expert in Pipe & Fittings for Oil & Gas c...
 
PORTABLE TOOLS CHECKLIST Form # HSEQ - PTC Rev 2 -.docx
PORTABLE TOOLS CHECKLIST Form # HSEQ - PTC  Rev 2 -.docxPORTABLE TOOLS CHECKLIST Form # HSEQ - PTC  Rev 2 -.docx
PORTABLE TOOLS CHECKLIST Form # HSEQ - PTC Rev 2 -.docx
 
PPT ON PERMIT TO WORK, by Ekemezie E
PPT ON PERMIT TO WORK, by Ekemezie EPPT ON PERMIT TO WORK, by Ekemezie E
PPT ON PERMIT TO WORK, by Ekemezie E
 
Pressure Safety Valve Sizing - API 520/521/526
Pressure Safety Valve Sizing - API 520/521/526Pressure Safety Valve Sizing - API 520/521/526
Pressure Safety Valve Sizing - API 520/521/526
 
what is process piping
what is process pipingwhat is process piping
what is process piping
 
Piping interview
Piping interviewPiping interview
Piping interview
 
Heat exchanger types and hydro testing
Heat exchanger types and hydro testingHeat exchanger types and hydro testing
Heat exchanger types and hydro testing
 
Engineering & Design of Pipe Supports
Engineering & Design of Pipe SupportsEngineering & Design of Pipe Supports
Engineering & Design of Pipe Supports
 
Cold Work Permit
Cold Work PermitCold Work Permit
Cold Work Permit
 
Nitrogen purging
Nitrogen  purgingNitrogen  purging
Nitrogen purging
 

Ähnlich wie Precommisioning and commissioning updated

Episode 34 : Project Execution Part (5)
Episode 34 :  Project Execution Part (5)Episode 34 :  Project Execution Part (5)
Episode 34 : Project Execution Part (5)SAJJAD KHUDHUR ABBAS
 
2 cm-ms-bld-012 - roof fan & natural ventilator
2   cm-ms-bld-012 - roof fan & natural ventilator2   cm-ms-bld-012 - roof fan & natural ventilator
2 cm-ms-bld-012 - roof fan & natural ventilatorMinh Bui Si
 
Boiler recommissioning procedure after capital overhaul
Boiler recommissioning procedure after capital overhaul Boiler recommissioning procedure after capital overhaul
Boiler recommissioning procedure after capital overhaul Manohar Tatwawadi
 
Trailblazers (Power) Install Substation Switchgear
Trailblazers (Power) Install Substation SwitchgearTrailblazers (Power) Install Substation Switchgear
Trailblazers (Power) Install Substation SwitchgearMarty Stevenson
 
Trailblazers (Power) Install Substation Circuit Breakers
Trailblazers (Power) Install Substation Circuit BreakersTrailblazers (Power) Install Substation Circuit Breakers
Trailblazers (Power) Install Substation Circuit BreakersMarty Stevenson
 
Fulham Reach Block G Risk Review Presentation For review
Fulham Reach Block G Risk Review Presentation For reviewFulham Reach Block G Risk Review Presentation For review
Fulham Reach Block G Risk Review Presentation For reviewMark Platten
 
110921 commissioning of offshore installations
110921 commissioning of offshore installations110921 commissioning of offshore installations
110921 commissioning of offshore installationslaithu2908
 
Commissioning Technician
Commissioning TechnicianCommissioning Technician
Commissioning Technicianudipta dey
 
61131730 transmission-line-case-study
61131730 transmission-line-case-study61131730 transmission-line-case-study
61131730 transmission-line-case-studyhomeworkping4
 
Lifting steam drum 72 ton by winch
Lifting steam drum 72 ton by winchLifting steam drum 72 ton by winch
Lifting steam drum 72 ton by winchHaGun Gunawan
 
Piping supervisor Cv.mohamad anwar malik
Piping supervisor Cv.mohamad anwar malikPiping supervisor Cv.mohamad anwar malik
Piping supervisor Cv.mohamad anwar malikMOHAMAD ANWAR MALIK
 

Ähnlich wie Precommisioning and commissioning updated (20)

Episode 34 : Project Execution Part (5)
Episode 34 :  Project Execution Part (5)Episode 34 :  Project Execution Part (5)
Episode 34 : Project Execution Part (5)
 
Episode 22 : PROJECT EXECUTION
Episode 22 : PROJECT EXECUTION Episode 22 : PROJECT EXECUTION
Episode 22 : PROJECT EXECUTION
 
Plant start up
Plant start upPlant start up
Plant start up
 
my_cv_WP
my_cv_WPmy_cv_WP
my_cv_WP
 
2 cm-ms-bld-012 - roof fan & natural ventilator
2   cm-ms-bld-012 - roof fan & natural ventilator2   cm-ms-bld-012 - roof fan & natural ventilator
2 cm-ms-bld-012 - roof fan & natural ventilator
 
1 80 fineshed
1 80 fineshed1 80 fineshed
1 80 fineshed
 
Safety plan
Safety planSafety plan
Safety plan
 
Boiler recommissioning procedure after capital overhaul
Boiler recommissioning procedure after capital overhaul Boiler recommissioning procedure after capital overhaul
Boiler recommissioning procedure after capital overhaul
 
Steam Blow out
Steam Blow outSteam Blow out
Steam Blow out
 
078 switchgear install 1.0
078 switchgear install 1.0078 switchgear install 1.0
078 switchgear install 1.0
 
Trailblazers (Power) Install Substation Switchgear
Trailblazers (Power) Install Substation SwitchgearTrailblazers (Power) Install Substation Switchgear
Trailblazers (Power) Install Substation Switchgear
 
Trailblazers (Power) Install Substation Circuit Breakers
Trailblazers (Power) Install Substation Circuit BreakersTrailblazers (Power) Install Substation Circuit Breakers
Trailblazers (Power) Install Substation Circuit Breakers
 
076 circuit breaker install 1.0
076 circuit breaker install 1.0076 circuit breaker install 1.0
076 circuit breaker install 1.0
 
Fulham Reach Block G Risk Review Presentation For review
Fulham Reach Block G Risk Review Presentation For reviewFulham Reach Block G Risk Review Presentation For review
Fulham Reach Block G Risk Review Presentation For review
 
110921 commissioning of offshore installations
110921 commissioning of offshore installations110921 commissioning of offshore installations
110921 commissioning of offshore installations
 
Commissioning Technician
Commissioning TechnicianCommissioning Technician
Commissioning Technician
 
61131730 transmission-line-case-study
61131730 transmission-line-case-study61131730 transmission-line-case-study
61131730 transmission-line-case-study
 
Lifting steam drum 72 ton by winch
Lifting steam drum 72 ton by winchLifting steam drum 72 ton by winch
Lifting steam drum 72 ton by winch
 
C.V
C.VC.V
C.V
 
Piping supervisor Cv.mohamad anwar malik
Piping supervisor Cv.mohamad anwar malikPiping supervisor Cv.mohamad anwar malik
Piping supervisor Cv.mohamad anwar malik
 

Mehr von Personal Secret

Noise PPT Slide with AGNICE CONTRACTING DUBAI
Noise PPT Slide with AGNICE CONTRACTING  DUBAINoise PPT Slide with AGNICE CONTRACTING  DUBAI
Noise PPT Slide with AGNICE CONTRACTING DUBAIPersonal Secret
 
Work at Height & Scaffolding Awareness 22.06.2021
Work at Height  & Scaffolding  Awareness 22.06.2021Work at Height  & Scaffolding  Awareness 22.06.2021
Work at Height & Scaffolding Awareness 22.06.2021Personal Secret
 
Ramadan Health & Safety Precautions
Ramadan Health & Safety PrecautionsRamadan Health & Safety Precautions
Ramadan Health & Safety PrecautionsPersonal Secret
 
Confined space entry ppt slide
Confined space entry ppt slideConfined space entry ppt slide
Confined space entry ppt slidePersonal Secret
 
First aid training good ppt
First aid training good pptFirst aid training good ppt
First aid training good pptPersonal Secret
 
Petrol area loading . unloading ppt
Petrol area loading . unloading  pptPetrol area loading . unloading  ppt
Petrol area loading . unloading pptPersonal Secret
 
Process safety ADNOC STANDARD
Process safety ADNOC STANDARDProcess safety ADNOC STANDARD
Process safety ADNOC STANDARDPersonal Secret
 
7 adco engr appreciation by william sir
7  adco engr appreciation by william sir7  adco engr appreciation by william sir
7 adco engr appreciation by william sirPersonal Secret
 

Mehr von Personal Secret (14)

CHEMICAL SAFETY NEW.pdf
CHEMICAL SAFETY NEW.pdfCHEMICAL SAFETY NEW.pdf
CHEMICAL SAFETY NEW.pdf
 
FIRE ALARM SYSTEM.pdf
FIRE ALARM SYSTEM.pdfFIRE ALARM SYSTEM.pdf
FIRE ALARM SYSTEM.pdf
 
Noise PPT Slide with AGNICE CONTRACTING DUBAI
Noise PPT Slide with AGNICE CONTRACTING  DUBAINoise PPT Slide with AGNICE CONTRACTING  DUBAI
Noise PPT Slide with AGNICE CONTRACTING DUBAI
 
Work at Height & Scaffolding Awareness 22.06.2021
Work at Height  & Scaffolding  Awareness 22.06.2021Work at Height  & Scaffolding  Awareness 22.06.2021
Work at Height & Scaffolding Awareness 22.06.2021
 
Gas Tester Training
Gas Tester TrainingGas Tester Training
Gas Tester Training
 
Ramadan Health & Safety Precautions
Ramadan Health & Safety PrecautionsRamadan Health & Safety Precautions
Ramadan Health & Safety Precautions
 
Confined space entry ppt slide
Confined space entry ppt slideConfined space entry ppt slide
Confined space entry ppt slide
 
Housekeeping PowerPoint
Housekeeping PowerPointHousekeeping PowerPoint
Housekeeping PowerPoint
 
First aid training good ppt
First aid training good pptFirst aid training good ppt
First aid training good ppt
 
Petrol area loading . unloading ppt
Petrol area loading . unloading  pptPetrol area loading . unloading  ppt
Petrol area loading . unloading ppt
 
Zones
ZonesZones
Zones
 
Process safety ADNOC STANDARD
Process safety ADNOC STANDARDProcess safety ADNOC STANDARD
Process safety ADNOC STANDARD
 
Banks man awareness
Banks man awarenessBanks man awareness
Banks man awareness
 
7 adco engr appreciation by william sir
7  adco engr appreciation by william sir7  adco engr appreciation by william sir
7 adco engr appreciation by william sir
 

Kürzlich hochgeladen

CCXG global forum, April 2024, Luca Lo Re
CCXG global forum, April 2024,  Luca Lo ReCCXG global forum, April 2024,  Luca Lo Re
CCXG global forum, April 2024, Luca Lo ReOECD Environment
 
CCXG global forum, April 2024, Adriana Bonilla
CCXG global forum, April 2024,  Adriana BonillaCCXG global forum, April 2024,  Adriana Bonilla
CCXG global forum, April 2024, Adriana BonillaOECD Environment
 
CCXG global forum, April 2024, Brian Motherway and Paolo Frankl
CCXG global forum, April 2024,  Brian Motherway and Paolo FranklCCXG global forum, April 2024,  Brian Motherway and Paolo Frankl
CCXG global forum, April 2024, Brian Motherway and Paolo FranklOECD Environment
 
CCXG global forum, April 2024, Marta Torres-Gunfaus
CCXG global forum, April 2024,  Marta Torres-GunfausCCXG global forum, April 2024,  Marta Torres-Gunfaus
CCXG global forum, April 2024, Marta Torres-GunfausOECD Environment
 
DETAILED LESSON FINAL DEMO TEACHING.docx
DETAILED LESSON FINAL DEMO TEACHING.docxDETAILED LESSON FINAL DEMO TEACHING.docx
DETAILED LESSON FINAL DEMO TEACHING.docxImilyAcma
 
Little Green Ranger ESG Sustainability Report
Little Green Ranger ESG Sustainability ReportLittle Green Ranger ESG Sustainability Report
Little Green Ranger ESG Sustainability ReportKennethOng48
 
CCXG global forum, April 2025, Key takeaways
CCXG global forum, April 2025, Key takeawaysCCXG global forum, April 2025, Key takeaways
CCXG global forum, April 2025, Key takeawaysOECD Environment
 
CCXG global forum, April 2024, Sirini Jeudy-Hugo
CCXG global forum, April 2024,  Sirini Jeudy-HugoCCXG global forum, April 2024,  Sirini Jeudy-Hugo
CCXG global forum, April 2024, Sirini Jeudy-HugoOECD Environment
 
CCXG global forum, April 2024, MJ Mace
CCXG global forum, April 2024,   MJ MaceCCXG global forum, April 2024,   MJ Mace
CCXG global forum, April 2024, MJ MaceOECD Environment
 
CCXG global forum, April 2024, Jo Tyndall
CCXG global forum, April 2024,  Jo TyndallCCXG global forum, April 2024,  Jo Tyndall
CCXG global forum, April 2024, Jo TyndallOECD Environment
 
CCXG global forum, April 2024, Geert Fremout
CCXG global forum, April 2024,  Geert FremoutCCXG global forum, April 2024,  Geert Fremout
CCXG global forum, April 2024, Geert FremoutOECD Environment
 
CCXG global forum, April 2024, Thomas Spencer
CCXG global forum, April 2024,  Thomas SpencerCCXG global forum, April 2024,  Thomas Spencer
CCXG global forum, April 2024, Thomas SpencerOECD Environment
 
SBSTTA 26 Biosafety AI’s. A policy perspective. Jens Warrie.
SBSTTA 26 Biosafety AI’s. A policy perspective. Jens Warrie.SBSTTA 26 Biosafety AI’s. A policy perspective. Jens Warrie.
SBSTTA 26 Biosafety AI’s. A policy perspective. Jens Warrie.pensoftservices
 
Get inspired by SYMBA Project: promoting Industrial Symbiosis
Get inspired by SYMBA Project: promoting Industrial SymbiosisGet inspired by SYMBA Project: promoting Industrial Symbiosis
Get inspired by SYMBA Project: promoting Industrial Symbiosissymbaprojecteu
 
Biodiversity and Health. Prof. Richard Kock.
Biodiversity and Health. Prof. Richard Kock.Biodiversity and Health. Prof. Richard Kock.
Biodiversity and Health. Prof. Richard Kock.pensoftservices
 
CCXG global forum, April 2024, Nino Tkhilava
CCXG global forum, April 2024,  Nino TkhilavaCCXG global forum, April 2024,  Nino Tkhilava
CCXG global forum, April 2024, Nino TkhilavaOECD Environment
 
Planning and Designing Green buildings-.issues, options and strategies
Planning and Designing Green buildings-.issues, options and strategiesPlanning and Designing Green buildings-.issues, options and strategies
Planning and Designing Green buildings-.issues, options and strategiesJIT KUMAR GUPTA
 
CCXG global forum, April 2024, Julio Cordano
CCXG global forum, April 2024,  Julio CordanoCCXG global forum, April 2024,  Julio Cordano
CCXG global forum, April 2024, Julio CordanoOECD Environment
 
CCXG global forum, April 2024, Watcharin Boonyarit
CCXG global forum, April 2024,  Watcharin BoonyaritCCXG global forum, April 2024,  Watcharin Boonyarit
CCXG global forum, April 2024, Watcharin BoonyaritOECD Environment
 
CCXG global forum, April 2024, Annett Möhner
CCXG global forum, April 2024,  Annett MöhnerCCXG global forum, April 2024,  Annett Möhner
CCXG global forum, April 2024, Annett MöhnerOECD Environment
 

Kürzlich hochgeladen (20)

CCXG global forum, April 2024, Luca Lo Re
CCXG global forum, April 2024,  Luca Lo ReCCXG global forum, April 2024,  Luca Lo Re
CCXG global forum, April 2024, Luca Lo Re
 
CCXG global forum, April 2024, Adriana Bonilla
CCXG global forum, April 2024,  Adriana BonillaCCXG global forum, April 2024,  Adriana Bonilla
CCXG global forum, April 2024, Adriana Bonilla
 
CCXG global forum, April 2024, Brian Motherway and Paolo Frankl
CCXG global forum, April 2024,  Brian Motherway and Paolo FranklCCXG global forum, April 2024,  Brian Motherway and Paolo Frankl
CCXG global forum, April 2024, Brian Motherway and Paolo Frankl
 
CCXG global forum, April 2024, Marta Torres-Gunfaus
CCXG global forum, April 2024,  Marta Torres-GunfausCCXG global forum, April 2024,  Marta Torres-Gunfaus
CCXG global forum, April 2024, Marta Torres-Gunfaus
 
DETAILED LESSON FINAL DEMO TEACHING.docx
DETAILED LESSON FINAL DEMO TEACHING.docxDETAILED LESSON FINAL DEMO TEACHING.docx
DETAILED LESSON FINAL DEMO TEACHING.docx
 
Little Green Ranger ESG Sustainability Report
Little Green Ranger ESG Sustainability ReportLittle Green Ranger ESG Sustainability Report
Little Green Ranger ESG Sustainability Report
 
CCXG global forum, April 2025, Key takeaways
CCXG global forum, April 2025, Key takeawaysCCXG global forum, April 2025, Key takeaways
CCXG global forum, April 2025, Key takeaways
 
CCXG global forum, April 2024, Sirini Jeudy-Hugo
CCXG global forum, April 2024,  Sirini Jeudy-HugoCCXG global forum, April 2024,  Sirini Jeudy-Hugo
CCXG global forum, April 2024, Sirini Jeudy-Hugo
 
CCXG global forum, April 2024, MJ Mace
CCXG global forum, April 2024,   MJ MaceCCXG global forum, April 2024,   MJ Mace
CCXG global forum, April 2024, MJ Mace
 
CCXG global forum, April 2024, Jo Tyndall
CCXG global forum, April 2024,  Jo TyndallCCXG global forum, April 2024,  Jo Tyndall
CCXG global forum, April 2024, Jo Tyndall
 
CCXG global forum, April 2024, Geert Fremout
CCXG global forum, April 2024,  Geert FremoutCCXG global forum, April 2024,  Geert Fremout
CCXG global forum, April 2024, Geert Fremout
 
CCXG global forum, April 2024, Thomas Spencer
CCXG global forum, April 2024,  Thomas SpencerCCXG global forum, April 2024,  Thomas Spencer
CCXG global forum, April 2024, Thomas Spencer
 
SBSTTA 26 Biosafety AI’s. A policy perspective. Jens Warrie.
SBSTTA 26 Biosafety AI’s. A policy perspective. Jens Warrie.SBSTTA 26 Biosafety AI’s. A policy perspective. Jens Warrie.
SBSTTA 26 Biosafety AI’s. A policy perspective. Jens Warrie.
 
Get inspired by SYMBA Project: promoting Industrial Symbiosis
Get inspired by SYMBA Project: promoting Industrial SymbiosisGet inspired by SYMBA Project: promoting Industrial Symbiosis
Get inspired by SYMBA Project: promoting Industrial Symbiosis
 
Biodiversity and Health. Prof. Richard Kock.
Biodiversity and Health. Prof. Richard Kock.Biodiversity and Health. Prof. Richard Kock.
Biodiversity and Health. Prof. Richard Kock.
 
CCXG global forum, April 2024, Nino Tkhilava
CCXG global forum, April 2024,  Nino TkhilavaCCXG global forum, April 2024,  Nino Tkhilava
CCXG global forum, April 2024, Nino Tkhilava
 
Planning and Designing Green buildings-.issues, options and strategies
Planning and Designing Green buildings-.issues, options and strategiesPlanning and Designing Green buildings-.issues, options and strategies
Planning and Designing Green buildings-.issues, options and strategies
 
CCXG global forum, April 2024, Julio Cordano
CCXG global forum, April 2024,  Julio CordanoCCXG global forum, April 2024,  Julio Cordano
CCXG global forum, April 2024, Julio Cordano
 
CCXG global forum, April 2024, Watcharin Boonyarit
CCXG global forum, April 2024,  Watcharin BoonyaritCCXG global forum, April 2024,  Watcharin Boonyarit
CCXG global forum, April 2024, Watcharin Boonyarit
 
CCXG global forum, April 2024, Annett Möhner
CCXG global forum, April 2024,  Annett MöhnerCCXG global forum, April 2024,  Annett Möhner
CCXG global forum, April 2024, Annett Möhner
 

Precommisioning and commissioning updated

  • 2. Contents 1. Pre- Commissioning 2. Preservation of pipeline 3. Commissioning Activities 2
  • 3. Commissioning Procedures These Procedures covers the following:  Pre-commissioning, which covers all activities and approvals necessary to allow purging with gas and pressurizing to normal operating pressure to commence.  Pipeline preservation, in case gas-initiation of the pipeline is performed later than six months after the installations are completed the pipeline is preserved.  Commissioning of dry pipelines. The criteria for being considered a dry pipeline are as follows: • Dew point temperature must be < - 20° C measured at atmospheric pressure. • Over-pressure following sealing of the lines must be at least I barg. • The acceptable minimum standard during the whole period of preservation is a dew point temperature of - I0° C.  Commissioning of wet pipelines. Wet pipelines are considered those that are not met the previous criteria· 3
  • 4. 1.1 PRE-COMMISSIONING ACTIVITIES On substantial completion of construction activities, Contractor mobilizes its commissioning team to initiate pre-commissioning activities in a phased manner. The objective of pre-commissioning is to ensure that the pipeline as well all the facilities have been completed according to the Project Specifications and that commissioning and operation will take place safely and effectively. Also during the pre-commissioning should be verified that all the relevant data with the commissioning of the pipeline has been received and that the commissioning procedure is presented and discussed with all personnel involved. Another important aspect which has to be verified during this procedure is that all the necessary drawings, technical information, and O & M manuals have been received and that the operating plan has been existing . Pre-commissioning may therefore be defined as all the checks that are to be completed prior to commissioning being permitted to commence. 4
  • 5. The pre-commissioning phase includes three main types of field activities: a) Systematic conformity checks, carried out on each item of equipment or component, such as pressure gauges, cables, etc., to verify visually the condition of the equipment, the quality of the installation, the compliance with project drawings and specifications, manufacturer's instructions, safety rules, codes, standards and good engineering practices. These checks will confirm the following: • All pipe assemblies and weldings have been completed. • All pipeline pressure and leak tests have been completed and relevant certified test documents have been received (weld radiographs, hydrostatic test documents etc) • Electrical and control installations have been completed and are functioning. 5
  • 6. • Cathodic protection systems have been completed and are functioning. • Security fences have been installed around all above ground high pressure pipeline facilities. • Emergency vehicle access is provided to all pipe line facilities (land valve stations, MIR-stations, Scraper Stations. • Right-of-way restoration has been completed according to specifications and landowner agreements and all environmental concerns have been addressed. b) Equipment static/de-energized tests, to ensure the quality of a number of critical components. This "cold" testing concerns all disciplines, e.g. calibration of instruments, machinery alignments, setting of safety valves, pressure testing of piping, cable continuities, etc. c) Dewatering and drying of the pipeline and the vessels has been completed in accordance with specifications and approved procedures. 6
  • 7. As soon as practical, the Pre-commissioning team shall acquire a complete set of drawings and data as listed below: 1. As built drawings and technical information regarding: • Pipeline sections between line valve stations : pipe logs showing the location, size, wall thickness, and pipe grade • Line Valve stations: schematic showing venting and valving arrangements, as well as technical data regarding material, fittings, valves, etc. • M/R Stations: schematics showing venting arrangements, customer interconnections for gas service and by-pass technical data regarding material, fittings, valves, etc. • Scraper Stations: schematics showing piping arrangement as well as technical data regarding material, fittings, valves, etc. • Cathodic protection facilities: including type and description of rectifiers, number and type of sacrificial anodes, measuring posts, insulating couplings, type of pipeline external and internal coating 7
  • 8. 2. Route Maps which indicate among the others the pipeline routing, the depth of pipeline, the access routes to valve stations, M/R Stations , Scraper Stations, cathodic protection rectifiers and measuring posts have been received. 3. 3. Vendor-supplied equipment design specifications, installation drawings, operation and maintenance manuals. 4. 3. All QC documentation relating to the construction testing i.e. hydro test packs, cable checklists etc. as well as emergency procedures and operating plans. Pre-commissioning work described herein will require all necessary tools, test instruments, water, air and electric power etc to be made available to the Pre-commissioning team. Also spare parts and repair materials as well as that all the necessary tools and work equipment as pipe locators, gas detection equipment etc should be available. Each craftsman such as pipe fitter, millwright, mechanic, instrument technician, or electrician, who is assisting the Pre-commissioning team, shall have his normal tools available. 8
  • 9. All necessary tags, warning tapes, barricade tapes and safety supplies shall be made available at the site. The following signs are posted at strategic locations before proceeding with the appropriate Pre-commissioning activities: Tags:  No smoking  Danger, high voltage  Do not enter beyond this point 9
  • 10. Finally, the following safety supplies are made available to all staff involved in the pre-commissioning activities.  Ear Protection  Safety Glasses  Hard Hats  First Aid Kit  Face Shield  Chemical Gloves  Safety Goggles  Padlocks with Multi-Lock Clips  Safety Boots  Boiler suits/overalls 10
  • 11. For the purpose of pre-commissioning, the facilities will be subdivided suitably into a few systems. The pre-commissioning checks of each piece of equipment are to be as complete and as comprehensive as possible to ensure that the equipment are installed as specified and will operate as designed. Proper pre-commissioning will ensure that the facilities can be made operable with the least number of problems. To achieve this, (1) The Pre-commissioning Team shall become familiar with all data and information. (2) The Pre-commissioning Team shall start all pre-commissioning checks as early as possible during the construction activities to ensure that the final installation of all equipment is as designed and specified. 11
  • 12. All personnel involved in the pre-commissioning and commissioning activities have to be educated with regard to the following: • Access routes to line valve stations, MfR stations, and scraper stations. • Vehicle and equipment use and capabilities. • The overall commissioning plan and the co-ordination and procedures to be utilized. • The job responsibilities of each individual and his part in the overall plan. • Determination of gas volumes required for purging and loading. • Sequence of valve sections to be purged and loaded • Details of purging and loading procedures. Details .of emergency and operating plans and responses to any problems or difficulties that may be encountered. • The effects and precautions necessary when working with high pressure natural gas. • Use and capabilities of telecommunication and mobile telecommunications systems. Also it has to be verified that involved personnel have been trained and qualified for operating the pipeline. 12
  • 13. The following guidelines summarize all activities to be completed during the pre-commissioning phase of the project. 1. Testing and adequate flushing of all piping systems. 2. Removal of all blinds or spool pieces used during hydrostatic testing. 3. Proper positioning of spectacle blinds. 4. Witness or calibrate, and test all instruments in accordance with the Pre-commissioning procedures, and record all calibrations and test data on the checklists provided for each instrument and instrument loop. 5. Verify that lubricants, oils, coolants, etc., required for all equipment are on the job site and in good condition (i.e. not contaminated). 6. Ensure that fire extinguishers are in place. 7. Check all electrical closures. 8. Ensure that all escape routes are clear of obstacles. 13
  • 14. 9. Ensure that all eyewash stations are operational. 10. Wear personal safety equipment. 11. Clear area from unauthorized personnel. 12. Be aware of the wind direction. 13. Be aware of the designated meeting area location. 14. Ensure that fire detection equipment is operational. 14
  • 15. General Preservation of a pipeline is carried out to maintain the pre commissioning condition, which the installations are in until commissioning comes into force. 2.1 Preservation with dry air If the initial gas filling of the pipelines is carried out later than six months after the installation- works are completed preservation of the pipelines takes place according to the dry air method. The main criteria for a dry pipeline are as follows:  Dewpoint temperature must be ≤ -20°C measured at atmospheric pressure.  Overpressure after sealing of the pipelines must be at least one barg.  The acceptable minimum norm during the entire preserva tion-period is a measured dewpoint temperature of ≤ -10 °C (measured at atmospheric pressure and at an overpressure of one barg). 15
  • 16. The dewpoint temperature and the pressure is measured and registered within the preservation period with stated intervals since the pipeline-contractor as well as a neutral third party is involved. 2.2 Preservation with nitrogen (N2) If it is decided to preserve the pipeline by the use of nitrogen the criteria are as follows:  Purge with nitrogen until achieving 100% N2  The overpressure after sealing must be at least 2 barg. Measurements of the pressure at stated intervals during the preservation period is required. 16
  • 17. 3.1 Commissioning of dry pipelines 3.1.1 General Commissioning includes the following activities: The supervision and execution of the Commissioning activities are to be carried out by DESFA’s personnel who are suitably trained and qualified for this task. Commissioning check· list is to be strictly adhered to during execution of the commissioning. Commissioning is to take place in coordination with Gas Control Center. No valves are to be opened without prior approval from Gas Control Center. 17
  • 18. Purging of a section of pipeline is to be considered as complete when 100 % gas is measured 3 times at the exhaust point with two independent gas measuring instruments. When commissioning a new section of pipeline, or possibly a modified section of pipeline (e.g. in case of repair or construction activity) notification is to be carried out by means of form 2.2.b.  Purging, loading, and placing into service may be carried out only after presentation of the notification of placing into service.  The person responsible for observation of the commissioning policy is DESFA’s District Manager, or alternately, a deputy named by him. The criteria for being considered a dry pipeline are as described here above, and if those criteria are not fulfilled then the pipeline is considered as wet. Sections of the pipeline which have been constructed, as well as sections of the pipeline on which repairs have been carried out, contain air or a mixture of gas and air. These pipelines or sections of pipelines must be placed into service in a safe, economical and environmentally responsible manner. 18
  • 19. The following description and points to be observed ensure a trouble-free process for commissioning of dry pipelines.  Prepare the scope and the technique for commissioning and complying with Gas Control requirements  Establish the purge direction  Determine whether inert gas is required and eventually required volume  Calculate the purge time  Determine which will be the inlet throttle valve and exhaust valve and carry out a function test of these valves  Establish the purge velocity. This velocity is usually between 5 m/sec in the main pipeline if no inert gas is used or 7-10 m/sec if inert gas is used 19
  • 20.  Check all facilities which have a relation to the commissioning according to the safety check list which is herewith  Ensure that capable and adequate personnel is assigned  Ensure satisfactory performance of vehicles, equipment, and instruments  Ensure effective and reliable communications between the inlet point, the exhaust point, and Gas Control Center  Advise Gas Control Center of commencement of purging, loading, and placing into service  Ensure with the Gas Control Center for the availability of the required quantities of gas  In case of use of inert gas, the adequate volume will be determined from the cross sectional area of the pipe. An inert gas plug approx. 300 m in length is recommended as it may be difficult to maintain a purge velocity of 3 - 7 rn/s. The supervisor in charge of commissioning will determine if inert gas is to be used 20
  • 21. 3.1.2 Commissioning procedure  The procedure begins with the injection of gas , or inert gas if it is decided, into the inlet throttle valve which is opened slowly, while measuring the velocity at the outlet throttle valve  Then should regulate the purge velocity (usually approx. 10 rn/sec in the main  pipeline - 90 m/sec from vent stack) following always the be given by a per son at the vent stack  Commence timing of the purge only after regulation of the purge velocity has been achieved  Close to the expiration of the purge time, the gas concentration is to be measured by means of two independent gas measuring instruments  After verification of measurements of 100 % Vol gas at least 3 times then first the throttling valves of the exit and then the valves of the insert point are to be closed in that order  All vented gas quantities are to be reported for the calculation of the vented gas 21
  • 22.  Two pressure gauges and one pressure recorder are installed at the start and end of the pipeline section to be loaded (one additional pressure gauge is to be kept in reserve in case of malfunction). The range of the scales of the gauges and recorders must be at least equal to the maximum possible loading pressure  The pipeline is loaded in stages so that the pressure in the pipeline rises to 5 - 10 bar during the first hour  The second hour the throttle inner valve is opened further so that the pressure rises to 10 - 20 bar  Finally the inlet throttle valve is opened further so that final loading pressure is reached after three hours  Depending on the quantity of gas supply available for loading the pipeline, lower pressure increments are to be selected in accordance with Gas Control Center 22
  • 23.  After each hour a· leak test of susceptible points on the pipeline (e.g. tie-in welds, flange connections, etc.) is to be carried out using a foam producing liquid. If any leaks are found permanent repairs are to be carried out in accordance with specifications before proceeding with the loading operation  Leaks from fittings should be tightened in accordance to vendors instructions  Loading time for the pipeline or section of pipeline will generally be determined by the gas volumes available and the configuration at the inlet and throttle valve  After the pipeline has been loaded (pressure equalization) it will be connected to the pipeline system  For further commissioning of pipeline downstream Section the above procedure is repeated 23
  • 24. 3.2 Commissioning of wet pipelines In the case of wet pipeline and before purging with natural gas it is necessary to dry the pipeline. The cause of this is that under certain pressure and temperature conditions, gas hydrates will form when hygroscopic water (i.e. water remaining after de-watering) comes into contact with gas. The range of pressure and temperature, within which natural gas hydrates form, lies above 0o C (water dew point) and 6 bar. A decomposition of gas hydrates occurs by an increase in temperature or reduction in pressure. Based on present experience the following dehydration procedures are generally accepted: • Drying with dry air • Absorption of residual water by alcohol • Drying of residual water by vacuum After the drying of the pipeline the procedure for the commissioning of dry pipeline is followed. 24