Optimum Utilization and Managing
The Supply of Bulk Nitrogen Contract
Maintenance Team East Kuwait-II
Operations Group East Kuwait
2
BACK GROUND
CSO
Current Nitrogen Requisition Workflow
Authorized Site Person
Contractor Trip Tickets after the Delivery
Contractor
Controlling Team
3
WAYFORWARD

PROPOSAL: IMPLEMENTATION OF eBEAMS WORKFLOW IN NITROGEN REQUEST
MANAGING EXPENSES
BENEFITS



ENHANCE TRACKING
OPTIMUM UTILIZATION OF CONTRACT VALUE
TIMELY INVOICING AND AVOID BACK LOG
4
BREIF PROPOSAL
Bulk N2 Service Request
CSO, WCA & CRP
Applications
Link SR & SO Application
Existing eBEAMS Applications
New eBEAMS Module have to be Created
Contractor
eBEAMS will auto-generate SR
& eMail to the Contractor
eBEAMS will auto-generate CRP FIN 70
Report & eMail to the Contractor
(User Team’s Platform for the N2 Request)
(Controlling Team’s Invoicing Platform)
5
BULK N2 SERVICE REQUEST
CREATION / APPROVAL & CLOSURE WORKFLOWS
(BY USER TEAMS)
6
Related Request
Lead / Approver
Requester
Stop
Requesting Lead
Approval
Contractor
N2 Service
Request
Close
Process to
Approval
Approve
Approve
Reject
Reject
eMAIL
Notification
BULK N2 SERVICE REQUEST (PROPOSED eBEAMS WORKFLOW)
System
Verification
No
Yes
Request Initiation Processes – By the Requester
Status: WAPPR
MANDATORY FIELDS
1. Summary
2. Location / Unit
3. Requester Phone & eMail ID
4. Requesting Lead
5. Requesting Team Leader
6. Requesting Team
7. Controlling Team
8. Requisition Line Items
(a). Item
- TRLR Contractor @ 2000 – 2400 PSIg
- TRLR KOC @ 2000 – 2400 PSIg
- Filling Cyls 480 Cu. FT @ 3500 PSI
- Filling Cyls 240 Cu. FT @ 2100 PSI
- Testing of N2 Gas Samples
(b). Qty.
(c). Required Date & Time
(d). Work Type (Mandatory only for Item ‘TRLR
Contractor @ 2000 – 2400 PSIg’)
- Shutdown Job
- Welding Job
- Others
(e) End Date & Time (Mandatory only for
Item ‘TRLR Contractor @ 2000 – 2400 PSIg’)
If the Work Type is ‘Welding Job’
By default System will allot 24 Hrs. as
Required Duration.
7
Related Request
Lead / Approver
Requester
Stop
Requesting Lead
Approval
Contractor
N2 Service
Request
Status: WAPPR
Close
Process to
Approval
Approve
Approve
Reject
Reject
eMAIL
Notification
System
Verification
No
Yes
Request Approval Processes – By Requesting Lead (Sec. Head / Snr. Engr.)
eMAIL Notification to
Requester
Any Active Duplicated
Request exists for same
Unit on same date
eBEAMS Notification to Requester,
Lead / Approver & Controlling Team
CC eMAIL Notification to
Requester
Lead Should be either
Sec. Head / Snr. Engr
BULK N2 SERVICE REQUEST (PROPOSED eBEAMS WORKFLOW)
8
Related Request
Lead / Approver
Requester
Stop
Requesting Lead
Approval
Contractor
N2 Service
Request
Status: WAPPR
Close
Process to
Approval
Approve
Approve
Reject
Reject
eMAIL
Notification
System
Verification
No
Yes
Request Approval Processes – For Duplicated Requests
eMAIL Notification to
Requester & Lead
Any Active Duplicated
Request exists for same
Unit on same date
eBEAMS Notification to Requester,
Lead / Approver & Controlling Team
CC eMAIL Notification to
Requester
‘Related Request Lead /
Approver’ is the Person Who
Approved the 1st Request (Active
duplicated Request).
BULK N2 SERVICE REQUEST (PROPOSED eBEAMS WORKFLOW)
9
Requesting
TL Approval
Requester
Requesting Lead
Approval
Contractor
N2 Service
Request (Revision)
Cancel
Extend
Approve
Extension
Approve Cancellation
Reject
Extension
Reject Cancellation
eMAIL
Notification
Status: APPR
Stop
Complete
Status: COMP
Controlling Team
eBEAMS
Notification
Revise
Reject Revision
Approve Revision
Request Approved & Notified to the Contractor – Awaiting Closure Processes from the Requester.
System Alerts:
(Only for Item ‘TRLR Contractor @ 2000 – 2400 PSIg’)
 12Hrs Before the Service expiry;
An Auto-generated System eMail to
Requester.
If the Request is Open
 7 Days after Service Completion;
An Auto-generated System eMail to
Requester & Requesting Sec. Head
/ Snr. Engr.
 30 Days after Service Completion;
An Auto-generated System eMail to
Requesting Sec. Head / Snr. Engr &
Requesting TL.
BULK N2 SERVICE REQUEST (PROPOSED eBEAMS WORKFLOW)
10
Requesting
TL Approval
Requester
Requesting Lead
Approval
Contractor
N2 Service Request
(Revision)
Cancel
Approve Cancellation
Reject Cancellation
eMAIL
Notification
Stop
Complete
Status: COMP
Controlling Team
eBEAMS
Notification
Trip
Note
Approve
Extension
Revise
Reject Revision
Approve Revision
Extend
Reject
Extension
Status: APPR
Request Completion Processes
Mandatory Fields
1. Actual Service Completion
2. Actual Utilization (SCF)
(Mandatory only for Item ‘TRLR
Contractor @ 2000 – 2400 PSIg’)
3. Actual Truck Relocation
(Mandatory only for Item ‘TRLR
Contractor @ 2000 – 2400 PSIg’)
BULK N2 SERVICE REQUEST (PROPOSED eBEAMS WORKFLOW)
11
Requesting
TL Approval
Requester
Requesting Lead
Approval
Contractor
N2 Service Request
(Revision)
Cancel
Approve Cancellation
Reject Cancellation
eMAIL
Notification
Stop
Complete
Controlling Team
eBEAMS
Notification
Status: WCAN
Approve
Extension
Revise
Reject Revision
Approve Revision
Extend
Reject
Extension
Request Cancellation Processes
eMAIL Notification to
Requester
Mandatory Fields
1. Cancellation Justification
System Check
Should be 24Hrs before
Scheduled Delivery
eBEAMS Notification to Requester,
Lead / Approver & Controlling Team
CC eMAIL Notification to
Requester
BULK N2 SERVICE REQUEST (PROPOSED eBEAMS WORKFLOW)
12
Requesting
TL Approval
Requester
Requesting Lead
Approval
Contractor
N2 Service Request
(Revision)
Cancel
Approve Cancellation
Reject Cancellation
eMAIL
Notification
Stop
Complete
Controlling Team
eBEAMS
Notification
Approve
Extension
Revise
Reject Revision
Approve Revision
Extend
Reject
Extension
Status: WREV
Request Revision Processes (Only for Item ‘TRLR Contractor @ 2000 – 2400 PSIg’)
eMAIL Notification to
Requester
Mandatory Fields
1. Revised Date & time
2. Revision Justification
System Check
Should be 24Hrs before
Scheduled Completion
eBEAMS Notification to Requester,
Lead / Approver & Controlling Team
CC eMAIL Notification to
Requester
BULK N2 SERVICE REQUEST (PROPOSED eBEAMS WORKFLOW)
13
Requesting
TL Approval
Requester
Requesting Lead
Approval
Contractor
N2 Service Request
(Revision)
Cancel
Approve Cancellation
Reject Cancellation
eMAIL
Notification
Status: WEXT
Stop
Complete
Controlling Team
eBEAMS
Notification
Approve
Extension
Revise
Reject Revision
Approve Revision
Extend
Reject
Extension
Request Extension Processes (Only for Item ‘TRLR Contractor @ 2000 – 2400 PSIg’)
eMAIL Notification to
Requester & Lead
Mandatory Fields
1. Extended Date & time
2. Extension Justification
System Check
Should be 12Hrs before
Scheduled Completion
eBEAMS Notification to Requester,
Lead / Approver & Controlling Team
CC eMAIL Notification to
Requester
BULK N2 SERVICE REQUEST (PROPOSED eBEAMS WORKFLOW)
14
Note:
1. All the Communications, Justifications and Remarks Shall be Communicated thru. Log Window; by creating Logs during the Workflow.
2. Selecting ‘Urgent’ will allow the User to add back-dated N2 Requests and Generate Service Orders (System will allow to add back dated Required & Actual Service Completion dates).
* Controlling Team (Person Group):
Responsibility
Urgent ?
* Request Number:
* Location / Unit: Reported Date:
Site:
Status:
Related Requests:
Requested By:
* Phone:
* Requesting Team:
* eMail ID:
Name: * Requesting Lead:
* Requesting TL: * Name:
* Name:
Attachments
* Summary:
List Request Log
Contract Number Contractor Name:
Line Item Qty.
Work
Type
Required
Date
End Date
Revised End
Date
Revision
Justification:
Extended End
Date
Extension
Justification
Cancellation
Justification
Relocation
Requirement
Actual Service
Completion
Actual Utilization
(SCF)
Actual Truck
Relocation
Requisition Line Item
BULK N2 SERVICE REQUEST (PROPOSED eBEAMS MODULE / WINDOW)
15
AUTO-GENERATED eBEAMS SR# TO THE CONTRACTOR
Auto-Generated eBEAMS Service Request Should Have Following Minimum Information's
 Service Request Number
 Location / unit
 Item
 Qty.
 Required / Start Date & Time
 End Date & Time (Only for Item ‘TRLR Contractor @ 2000 – 2400 PSIg’)
 Requesting Team Name
 Requester KOC ID & Name
 Requester Mail ID & Phone Number
 Revision Details, If any
 Cancellation Details, If any
16
BULK N2 SERVICE ORDER
CREATION & APPROVAL WORKFLOWS
(BY CONTROLLING TEAM)
17
Requesting
TL Approval
Requester
Requesting Lead
Approval
Contractor
N2 Service Request
(Revision)
Cancel
Approve Cancellation
Reject Cancellation
eMAIL
Notification
Stop
Complete
Status: COMP
Controlling Team
eBEAMS
Notification
Trip
Note
Approve
Extension
Revise
Reject Revision
Approve Revision
Extend
Reject
Extension
Status: APPR
Service Order Creation Process
Mandatory Fields
1. Actual Service
Completion
2. Actual Utilization
(SCF)
(Mandatory only for Item
‘TRLR Contractor @ 2000 –
2400 PSIg’)
3. Actual Truck
Relocation
(Mandatory only for Item
‘TRLR Contractor @ 2000 –
2400 PSIg’)
BULK N2 SERVICE ORDER (PROPOSED eBEAMS WORKFLOW)
Creation of Service
Order from SR#
By Controlling Team (Material Section)
1. System will allow the
Controlling team to Create SO,
Only after the SR Completion
from the User teams.
2. System will automatically copy
all the required fields from SR
to SO during the SO Creation
Processes (SR to SO link have to
create)
18 Service Order Creation & Associated Workflow Processes
BULK N2 SERVICE ORDER (PROPOSED eBEAMS WORKFLOW)
Creation of Service
Order from SR#
SO Review &
Approval
SO Review &
Approval
Create WCA
Auto
WCA
Create CRP
Review & Approval
Review & Approval
Review & Approval
Review & Approval
Review & Approval
Review & Approval
N
Y
By Controlling Team
(Material Section)
By Controlling Team
Snr. Engr.
By Controlling Team
TL
By Controlling Team
Snr. Engr.
By Controlling Team
TL
By Controlling Team
Accountant
By Controlling Team
Snr. Engr.
By Controlling Team
TL
By Controlling Team
Accountant
By Controlling Team
(Material Section)
Contractor
CRP FIN 70
Report System Auto-Generation
CC eMAIL Notification to
Requester
eMAIL
Notification
www.kockw.com
Thank You

More Related Content

Similar to Optimum Utilization and Managing The Supply of Bulk Nitrogen Contract - Revised.pptx

Cenelca Ii Drm Presentation
Cenelca Ii Drm PresentationCenelca Ii Drm Presentation
Cenelca Ii Drm Presentation
Wilson Contreras
 
State of Nevada RFP Legacy Modernization
State of Nevada RFP Legacy ModernizationState of Nevada RFP Legacy Modernization
State of Nevada RFP Legacy Modernization
Alexander Doré
 
JATIN RELAN (11BEC0532) TRAINING PPT
JATIN RELAN (11BEC0532) TRAINING PPTJATIN RELAN (11BEC0532) TRAINING PPT
JATIN RELAN (11BEC0532) TRAINING PPT
JATIN RELAN
 
Protecting Multi-Interfaced Mobile Web Services using Agreements
Protecting Multi-Interfaced Mobile Web Services using Agreements Protecting Multi-Interfaced Mobile Web Services using Agreements
Protecting Multi-Interfaced Mobile Web Services using Agreements
Dr. Fahad Aijaz
 

Similar to Optimum Utilization and Managing The Supply of Bulk Nitrogen Contract - Revised.pptx (20)

Quality Assurance Procedures fro MCAP.ppt
Quality Assurance Procedures fro MCAP.pptQuality Assurance Procedures fro MCAP.ppt
Quality Assurance Procedures fro MCAP.ppt
 
HandyMan(SRS Final Presentation)
HandyMan(SRS Final Presentation)HandyMan(SRS Final Presentation)
HandyMan(SRS Final Presentation)
 
Trading Partner Migrations
Trading Partner MigrationsTrading Partner Migrations
Trading Partner Migrations
 
WebXpress Cash Management Solution
WebXpress Cash Management SolutionWebXpress Cash Management Solution
WebXpress Cash Management Solution
 
RFQ -WELDING
RFQ -WELDING RFQ -WELDING
RFQ -WELDING
 
CBEC - GST - Registration Approval process
CBEC - GST - Registration Approval processCBEC - GST - Registration Approval process
CBEC - GST - Registration Approval process
 
Cenelca Ii Drm Presentation
Cenelca Ii Drm PresentationCenelca Ii Drm Presentation
Cenelca Ii Drm Presentation
 
State of Nevada RFP Legacy Modernization
State of Nevada RFP Legacy ModernizationState of Nevada RFP Legacy Modernization
State of Nevada RFP Legacy Modernization
 
ssss11220146195 (1)
ssss11220146195 (1)ssss11220146195 (1)
ssss11220146195 (1)
 
JATIN RELAN (11BEC0532) TRAINING PPT
JATIN RELAN (11BEC0532) TRAINING PPTJATIN RELAN (11BEC0532) TRAINING PPT
JATIN RELAN (11BEC0532) TRAINING PPT
 
Customer Loan Origination System - Part 2 (Web)
Customer Loan Origination System - Part 2 (Web)Customer Loan Origination System - Part 2 (Web)
Customer Loan Origination System - Part 2 (Web)
 
Procurement of Services using Oracle EBS
Procurement of Services using Oracle EBSProcurement of Services using Oracle EBS
Procurement of Services using Oracle EBS
 
Cbec - GST - Registration Application cancellation by tax payer and tax official
Cbec - GST - Registration Application cancellation by tax payer and tax officialCbec - GST - Registration Application cancellation by tax payer and tax official
Cbec - GST - Registration Application cancellation by tax payer and tax official
 
PROCUREMENT.pptx
PROCUREMENT.pptxPROCUREMENT.pptx
PROCUREMENT.pptx
 
Frontline services
Frontline services Frontline services
Frontline services
 
Protecting Multi-Interfaced Mobile Web Services using Agreements
Protecting Multi-Interfaced Mobile Web Services using Agreements Protecting Multi-Interfaced Mobile Web Services using Agreements
Protecting Multi-Interfaced Mobile Web Services using Agreements
 
Mechanical Engineering Seminar 2017_2
Mechanical Engineering Seminar 2017_2Mechanical Engineering Seminar 2017_2
Mechanical Engineering Seminar 2017_2
 
M Imran
M ImranM Imran
M Imran
 
Inforln.com ERP LN 10.4 Using the New Claim Features
Inforln.com ERP LN 10.4 Using the New Claim FeaturesInforln.com ERP LN 10.4 Using the New Claim Features
Inforln.com ERP LN 10.4 Using the New Claim Features
 
IFA system in MES and diffucultiess.pptx
IFA system in MES and diffucultiess.pptxIFA system in MES and diffucultiess.pptx
IFA system in MES and diffucultiess.pptx
 

Recently uploaded

%+27788225528 love spells in Atlanta Psychic Readings, Attraction spells,Brin...
%+27788225528 love spells in Atlanta Psychic Readings, Attraction spells,Brin...%+27788225528 love spells in Atlanta Psychic Readings, Attraction spells,Brin...
%+27788225528 love spells in Atlanta Psychic Readings, Attraction spells,Brin...
masabamasaba
 
Love witchcraft +27768521739 Binding love spell in Sandy Springs, GA |psychic...
Love witchcraft +27768521739 Binding love spell in Sandy Springs, GA |psychic...Love witchcraft +27768521739 Binding love spell in Sandy Springs, GA |psychic...
Love witchcraft +27768521739 Binding love spell in Sandy Springs, GA |psychic...
chiefasafspells
 
Large-scale Logging Made Easy: Meetup at Deutsche Bank 2024
Large-scale Logging Made Easy: Meetup at Deutsche Bank 2024Large-scale Logging Made Easy: Meetup at Deutsche Bank 2024
Large-scale Logging Made Easy: Meetup at Deutsche Bank 2024
VictoriaMetrics
 
%+27788225528 love spells in Colorado Springs Psychic Readings, Attraction sp...
%+27788225528 love spells in Colorado Springs Psychic Readings, Attraction sp...%+27788225528 love spells in Colorado Springs Psychic Readings, Attraction sp...
%+27788225528 love spells in Colorado Springs Psychic Readings, Attraction sp...
masabamasaba
 
%+27788225528 love spells in Toronto Psychic Readings, Attraction spells,Brin...
%+27788225528 love spells in Toronto Psychic Readings, Attraction spells,Brin...%+27788225528 love spells in Toronto Psychic Readings, Attraction spells,Brin...
%+27788225528 love spells in Toronto Psychic Readings, Attraction spells,Brin...
masabamasaba
 
Abortion Pill Prices Boksburg [(+27832195400*)] 🏥 Women's Abortion Clinic in ...
Abortion Pill Prices Boksburg [(+27832195400*)] 🏥 Women's Abortion Clinic in ...Abortion Pill Prices Boksburg [(+27832195400*)] 🏥 Women's Abortion Clinic in ...
Abortion Pill Prices Boksburg [(+27832195400*)] 🏥 Women's Abortion Clinic in ...
Medical / Health Care (+971588192166) Mifepristone and Misoprostol tablets 200mg
 
%+27788225528 love spells in Knoxville Psychic Readings, Attraction spells,Br...
%+27788225528 love spells in Knoxville Psychic Readings, Attraction spells,Br...%+27788225528 love spells in Knoxville Psychic Readings, Attraction spells,Br...
%+27788225528 love spells in Knoxville Psychic Readings, Attraction spells,Br...
masabamasaba
 

Recently uploaded (20)

%in Soweto+277-882-255-28 abortion pills for sale in soweto
%in Soweto+277-882-255-28 abortion pills for sale in soweto%in Soweto+277-882-255-28 abortion pills for sale in soweto
%in Soweto+277-882-255-28 abortion pills for sale in soweto
 
BUS PASS MANGEMENT SYSTEM USING PHP.pptx
BUS PASS MANGEMENT SYSTEM USING PHP.pptxBUS PASS MANGEMENT SYSTEM USING PHP.pptx
BUS PASS MANGEMENT SYSTEM USING PHP.pptx
 
%+27788225528 love spells in Atlanta Psychic Readings, Attraction spells,Brin...
%+27788225528 love spells in Atlanta Psychic Readings, Attraction spells,Brin...%+27788225528 love spells in Atlanta Psychic Readings, Attraction spells,Brin...
%+27788225528 love spells in Atlanta Psychic Readings, Attraction spells,Brin...
 
WSO2CON 2024 - Freedom First—Unleashing Developer Potential with Open Source
WSO2CON 2024 - Freedom First—Unleashing Developer Potential with Open SourceWSO2CON 2024 - Freedom First—Unleashing Developer Potential with Open Source
WSO2CON 2024 - Freedom First—Unleashing Developer Potential with Open Source
 
%in ivory park+277-882-255-28 abortion pills for sale in ivory park
%in ivory park+277-882-255-28 abortion pills for sale in ivory park %in ivory park+277-882-255-28 abortion pills for sale in ivory park
%in ivory park+277-882-255-28 abortion pills for sale in ivory park
 
%in tembisa+277-882-255-28 abortion pills for sale in tembisa
%in tembisa+277-882-255-28 abortion pills for sale in tembisa%in tembisa+277-882-255-28 abortion pills for sale in tembisa
%in tembisa+277-882-255-28 abortion pills for sale in tembisa
 
What Goes Wrong with Language Definitions and How to Improve the Situation
What Goes Wrong with Language Definitions and How to Improve the SituationWhat Goes Wrong with Language Definitions and How to Improve the Situation
What Goes Wrong with Language Definitions and How to Improve the Situation
 
Love witchcraft +27768521739 Binding love spell in Sandy Springs, GA |psychic...
Love witchcraft +27768521739 Binding love spell in Sandy Springs, GA |psychic...Love witchcraft +27768521739 Binding love spell in Sandy Springs, GA |psychic...
Love witchcraft +27768521739 Binding love spell in Sandy Springs, GA |psychic...
 
Large-scale Logging Made Easy: Meetup at Deutsche Bank 2024
Large-scale Logging Made Easy: Meetup at Deutsche Bank 2024Large-scale Logging Made Easy: Meetup at Deutsche Bank 2024
Large-scale Logging Made Easy: Meetup at Deutsche Bank 2024
 
%+27788225528 love spells in Colorado Springs Psychic Readings, Attraction sp...
%+27788225528 love spells in Colorado Springs Psychic Readings, Attraction sp...%+27788225528 love spells in Colorado Springs Psychic Readings, Attraction sp...
%+27788225528 love spells in Colorado Springs Psychic Readings, Attraction sp...
 
Devoxx UK 2024 - Going serverless with Quarkus, GraalVM native images and AWS...
Devoxx UK 2024 - Going serverless with Quarkus, GraalVM native images and AWS...Devoxx UK 2024 - Going serverless with Quarkus, GraalVM native images and AWS...
Devoxx UK 2024 - Going serverless with Quarkus, GraalVM native images and AWS...
 
WSO2CON 2024 - Navigating API Complexity: REST, GraphQL, gRPC, Websocket, Web...
WSO2CON 2024 - Navigating API Complexity: REST, GraphQL, gRPC, Websocket, Web...WSO2CON 2024 - Navigating API Complexity: REST, GraphQL, gRPC, Websocket, Web...
WSO2CON 2024 - Navigating API Complexity: REST, GraphQL, gRPC, Websocket, Web...
 
WSO2CON2024 - It's time to go Platformless
WSO2CON2024 - It's time to go PlatformlessWSO2CON2024 - It's time to go Platformless
WSO2CON2024 - It's time to go Platformless
 
WSO2CON 2024 Slides - Open Source to SaaS
WSO2CON 2024 Slides - Open Source to SaaSWSO2CON 2024 Slides - Open Source to SaaS
WSO2CON 2024 Slides - Open Source to SaaS
 
WSO2Con2024 - GitOps in Action: Navigating Application Deployment in the Plat...
WSO2Con2024 - GitOps in Action: Navigating Application Deployment in the Plat...WSO2Con2024 - GitOps in Action: Navigating Application Deployment in the Plat...
WSO2Con2024 - GitOps in Action: Navigating Application Deployment in the Plat...
 
%+27788225528 love spells in Toronto Psychic Readings, Attraction spells,Brin...
%+27788225528 love spells in Toronto Psychic Readings, Attraction spells,Brin...%+27788225528 love spells in Toronto Psychic Readings, Attraction spells,Brin...
%+27788225528 love spells in Toronto Psychic Readings, Attraction spells,Brin...
 
Abortion Pill Prices Boksburg [(+27832195400*)] 🏥 Women's Abortion Clinic in ...
Abortion Pill Prices Boksburg [(+27832195400*)] 🏥 Women's Abortion Clinic in ...Abortion Pill Prices Boksburg [(+27832195400*)] 🏥 Women's Abortion Clinic in ...
Abortion Pill Prices Boksburg [(+27832195400*)] 🏥 Women's Abortion Clinic in ...
 
%+27788225528 love spells in Knoxville Psychic Readings, Attraction spells,Br...
%+27788225528 love spells in Knoxville Psychic Readings, Attraction spells,Br...%+27788225528 love spells in Knoxville Psychic Readings, Attraction spells,Br...
%+27788225528 love spells in Knoxville Psychic Readings, Attraction spells,Br...
 
WSO2CON 2024 Slides - Unlocking Value with AI
WSO2CON 2024 Slides - Unlocking Value with AIWSO2CON 2024 Slides - Unlocking Value with AI
WSO2CON 2024 Slides - Unlocking Value with AI
 
WSO2CON 2024 - API Management Usage at La Poste and Its Impact on Business an...
WSO2CON 2024 - API Management Usage at La Poste and Its Impact on Business an...WSO2CON 2024 - API Management Usage at La Poste and Its Impact on Business an...
WSO2CON 2024 - API Management Usage at La Poste and Its Impact on Business an...
 

Optimum Utilization and Managing The Supply of Bulk Nitrogen Contract - Revised.pptx

  • 1. www.kockw.com Optimum Utilization and Managing The Supply of Bulk Nitrogen Contract Maintenance Team East Kuwait-II Operations Group East Kuwait
  • 2. 2 BACK GROUND CSO Current Nitrogen Requisition Workflow Authorized Site Person Contractor Trip Tickets after the Delivery Contractor Controlling Team
  • 3. 3 WAYFORWARD  PROPOSAL: IMPLEMENTATION OF eBEAMS WORKFLOW IN NITROGEN REQUEST MANAGING EXPENSES BENEFITS    ENHANCE TRACKING OPTIMUM UTILIZATION OF CONTRACT VALUE TIMELY INVOICING AND AVOID BACK LOG
  • 4. 4 BREIF PROPOSAL Bulk N2 Service Request CSO, WCA & CRP Applications Link SR & SO Application Existing eBEAMS Applications New eBEAMS Module have to be Created Contractor eBEAMS will auto-generate SR & eMail to the Contractor eBEAMS will auto-generate CRP FIN 70 Report & eMail to the Contractor (User Team’s Platform for the N2 Request) (Controlling Team’s Invoicing Platform)
  • 5. 5 BULK N2 SERVICE REQUEST CREATION / APPROVAL & CLOSURE WORKFLOWS (BY USER TEAMS)
  • 6. 6 Related Request Lead / Approver Requester Stop Requesting Lead Approval Contractor N2 Service Request Close Process to Approval Approve Approve Reject Reject eMAIL Notification BULK N2 SERVICE REQUEST (PROPOSED eBEAMS WORKFLOW) System Verification No Yes Request Initiation Processes – By the Requester Status: WAPPR MANDATORY FIELDS 1. Summary 2. Location / Unit 3. Requester Phone & eMail ID 4. Requesting Lead 5. Requesting Team Leader 6. Requesting Team 7. Controlling Team 8. Requisition Line Items (a). Item - TRLR Contractor @ 2000 – 2400 PSIg - TRLR KOC @ 2000 – 2400 PSIg - Filling Cyls 480 Cu. FT @ 3500 PSI - Filling Cyls 240 Cu. FT @ 2100 PSI - Testing of N2 Gas Samples (b). Qty. (c). Required Date & Time (d). Work Type (Mandatory only for Item ‘TRLR Contractor @ 2000 – 2400 PSIg’) - Shutdown Job - Welding Job - Others (e) End Date & Time (Mandatory only for Item ‘TRLR Contractor @ 2000 – 2400 PSIg’) If the Work Type is ‘Welding Job’ By default System will allot 24 Hrs. as Required Duration.
  • 7. 7 Related Request Lead / Approver Requester Stop Requesting Lead Approval Contractor N2 Service Request Status: WAPPR Close Process to Approval Approve Approve Reject Reject eMAIL Notification System Verification No Yes Request Approval Processes – By Requesting Lead (Sec. Head / Snr. Engr.) eMAIL Notification to Requester Any Active Duplicated Request exists for same Unit on same date eBEAMS Notification to Requester, Lead / Approver & Controlling Team CC eMAIL Notification to Requester Lead Should be either Sec. Head / Snr. Engr BULK N2 SERVICE REQUEST (PROPOSED eBEAMS WORKFLOW)
  • 8. 8 Related Request Lead / Approver Requester Stop Requesting Lead Approval Contractor N2 Service Request Status: WAPPR Close Process to Approval Approve Approve Reject Reject eMAIL Notification System Verification No Yes Request Approval Processes – For Duplicated Requests eMAIL Notification to Requester & Lead Any Active Duplicated Request exists for same Unit on same date eBEAMS Notification to Requester, Lead / Approver & Controlling Team CC eMAIL Notification to Requester ‘Related Request Lead / Approver’ is the Person Who Approved the 1st Request (Active duplicated Request). BULK N2 SERVICE REQUEST (PROPOSED eBEAMS WORKFLOW)
  • 9. 9 Requesting TL Approval Requester Requesting Lead Approval Contractor N2 Service Request (Revision) Cancel Extend Approve Extension Approve Cancellation Reject Extension Reject Cancellation eMAIL Notification Status: APPR Stop Complete Status: COMP Controlling Team eBEAMS Notification Revise Reject Revision Approve Revision Request Approved & Notified to the Contractor – Awaiting Closure Processes from the Requester. System Alerts: (Only for Item ‘TRLR Contractor @ 2000 – 2400 PSIg’)  12Hrs Before the Service expiry; An Auto-generated System eMail to Requester. If the Request is Open  7 Days after Service Completion; An Auto-generated System eMail to Requester & Requesting Sec. Head / Snr. Engr.  30 Days after Service Completion; An Auto-generated System eMail to Requesting Sec. Head / Snr. Engr & Requesting TL. BULK N2 SERVICE REQUEST (PROPOSED eBEAMS WORKFLOW)
  • 10. 10 Requesting TL Approval Requester Requesting Lead Approval Contractor N2 Service Request (Revision) Cancel Approve Cancellation Reject Cancellation eMAIL Notification Stop Complete Status: COMP Controlling Team eBEAMS Notification Trip Note Approve Extension Revise Reject Revision Approve Revision Extend Reject Extension Status: APPR Request Completion Processes Mandatory Fields 1. Actual Service Completion 2. Actual Utilization (SCF) (Mandatory only for Item ‘TRLR Contractor @ 2000 – 2400 PSIg’) 3. Actual Truck Relocation (Mandatory only for Item ‘TRLR Contractor @ 2000 – 2400 PSIg’) BULK N2 SERVICE REQUEST (PROPOSED eBEAMS WORKFLOW)
  • 11. 11 Requesting TL Approval Requester Requesting Lead Approval Contractor N2 Service Request (Revision) Cancel Approve Cancellation Reject Cancellation eMAIL Notification Stop Complete Controlling Team eBEAMS Notification Status: WCAN Approve Extension Revise Reject Revision Approve Revision Extend Reject Extension Request Cancellation Processes eMAIL Notification to Requester Mandatory Fields 1. Cancellation Justification System Check Should be 24Hrs before Scheduled Delivery eBEAMS Notification to Requester, Lead / Approver & Controlling Team CC eMAIL Notification to Requester BULK N2 SERVICE REQUEST (PROPOSED eBEAMS WORKFLOW)
  • 12. 12 Requesting TL Approval Requester Requesting Lead Approval Contractor N2 Service Request (Revision) Cancel Approve Cancellation Reject Cancellation eMAIL Notification Stop Complete Controlling Team eBEAMS Notification Approve Extension Revise Reject Revision Approve Revision Extend Reject Extension Status: WREV Request Revision Processes (Only for Item ‘TRLR Contractor @ 2000 – 2400 PSIg’) eMAIL Notification to Requester Mandatory Fields 1. Revised Date & time 2. Revision Justification System Check Should be 24Hrs before Scheduled Completion eBEAMS Notification to Requester, Lead / Approver & Controlling Team CC eMAIL Notification to Requester BULK N2 SERVICE REQUEST (PROPOSED eBEAMS WORKFLOW)
  • 13. 13 Requesting TL Approval Requester Requesting Lead Approval Contractor N2 Service Request (Revision) Cancel Approve Cancellation Reject Cancellation eMAIL Notification Status: WEXT Stop Complete Controlling Team eBEAMS Notification Approve Extension Revise Reject Revision Approve Revision Extend Reject Extension Request Extension Processes (Only for Item ‘TRLR Contractor @ 2000 – 2400 PSIg’) eMAIL Notification to Requester & Lead Mandatory Fields 1. Extended Date & time 2. Extension Justification System Check Should be 12Hrs before Scheduled Completion eBEAMS Notification to Requester, Lead / Approver & Controlling Team CC eMAIL Notification to Requester BULK N2 SERVICE REQUEST (PROPOSED eBEAMS WORKFLOW)
  • 14. 14 Note: 1. All the Communications, Justifications and Remarks Shall be Communicated thru. Log Window; by creating Logs during the Workflow. 2. Selecting ‘Urgent’ will allow the User to add back-dated N2 Requests and Generate Service Orders (System will allow to add back dated Required & Actual Service Completion dates). * Controlling Team (Person Group): Responsibility Urgent ? * Request Number: * Location / Unit: Reported Date: Site: Status: Related Requests: Requested By: * Phone: * Requesting Team: * eMail ID: Name: * Requesting Lead: * Requesting TL: * Name: * Name: Attachments * Summary: List Request Log Contract Number Contractor Name: Line Item Qty. Work Type Required Date End Date Revised End Date Revision Justification: Extended End Date Extension Justification Cancellation Justification Relocation Requirement Actual Service Completion Actual Utilization (SCF) Actual Truck Relocation Requisition Line Item BULK N2 SERVICE REQUEST (PROPOSED eBEAMS MODULE / WINDOW)
  • 15. 15 AUTO-GENERATED eBEAMS SR# TO THE CONTRACTOR Auto-Generated eBEAMS Service Request Should Have Following Minimum Information's  Service Request Number  Location / unit  Item  Qty.  Required / Start Date & Time  End Date & Time (Only for Item ‘TRLR Contractor @ 2000 – 2400 PSIg’)  Requesting Team Name  Requester KOC ID & Name  Requester Mail ID & Phone Number  Revision Details, If any  Cancellation Details, If any
  • 16. 16 BULK N2 SERVICE ORDER CREATION & APPROVAL WORKFLOWS (BY CONTROLLING TEAM)
  • 17. 17 Requesting TL Approval Requester Requesting Lead Approval Contractor N2 Service Request (Revision) Cancel Approve Cancellation Reject Cancellation eMAIL Notification Stop Complete Status: COMP Controlling Team eBEAMS Notification Trip Note Approve Extension Revise Reject Revision Approve Revision Extend Reject Extension Status: APPR Service Order Creation Process Mandatory Fields 1. Actual Service Completion 2. Actual Utilization (SCF) (Mandatory only for Item ‘TRLR Contractor @ 2000 – 2400 PSIg’) 3. Actual Truck Relocation (Mandatory only for Item ‘TRLR Contractor @ 2000 – 2400 PSIg’) BULK N2 SERVICE ORDER (PROPOSED eBEAMS WORKFLOW) Creation of Service Order from SR# By Controlling Team (Material Section) 1. System will allow the Controlling team to Create SO, Only after the SR Completion from the User teams. 2. System will automatically copy all the required fields from SR to SO during the SO Creation Processes (SR to SO link have to create)
  • 18. 18 Service Order Creation & Associated Workflow Processes BULK N2 SERVICE ORDER (PROPOSED eBEAMS WORKFLOW) Creation of Service Order from SR# SO Review & Approval SO Review & Approval Create WCA Auto WCA Create CRP Review & Approval Review & Approval Review & Approval Review & Approval Review & Approval Review & Approval N Y By Controlling Team (Material Section) By Controlling Team Snr. Engr. By Controlling Team TL By Controlling Team Snr. Engr. By Controlling Team TL By Controlling Team Accountant By Controlling Team Snr. Engr. By Controlling Team TL By Controlling Team Accountant By Controlling Team (Material Section) Contractor CRP FIN 70 Report System Auto-Generation CC eMAIL Notification to Requester eMAIL Notification