Forney ridge brief overview and chimney tops intro 2012 grs

Friends of Great Smoky Mountains National Park
Friends of Great Smoky Mountains National ParkFriends of Great Smoky Mountains National Park
National Park Service
Great Smoky Mountains National Park                         U.S. Department of the Interior



          Trails Forever – Chimney Tops Trail Rehabilitation 2012




                     Trail rehabilitation will begin in May 2012
                       and is scheduled for multiple phases
National Park Service
Great Smoky Mountains National Park                           U.S. Department of the Interior



          Trails Forever – Chimney Tops Trail Rehabilitation 2012




             Trail rehabilitation will be completed that enhances the visitors
                         experience while protecting the resource
National Park Service
Great Smoky Mountains National Park                            U.S. Department of the Interior



          Trails Forever – Chimney Tops Trail Rehabilitation 2012




                Trail rehabilitation will be achieved utilizing sustainable
                          construction methods and materials
National Park Service
Great Smoky Mountains National Park                       U.S. Department of the Interior



    Trails Forever – Chimney Tops Trail Rehabilitation - Beginning 2012




                               May the fun begin!!!!!
                   Existing eroded, braided, 12 foot wide “trail”
National Park Service
Great Smoky Mountains National Park               U.S. Department of the Interior



    Trails Forever – Chimney Tops Trail Rehabilitation - Beginning 2012
National Park Service
Great Smoky Mountains National Park               U.S. Department of the Interior



    Trails Forever – Chimney Tops Trail Rehabilitation - Beginning 2012




                                                                       Chimney Tops Trail
                                                                          Phase One
National Park Service
Great Smoky Mountains National Park            U.S. Department of the Interior



      Trails Forever – Chimney Tops Trail Rehabilitation 2012

 The resources required to accomplish Phase One:
National Park Service
Great Smoky Mountains National Park                               U.S. Department of the Interior



        Trails Forever – Chimney Tops Trail Rehabilitation 2012

 The resources required to accomplish Phase One:

 •   The Trails Forever Park crew with five members for 13PP’s.
National Park Service
Great Smoky Mountains National Park                               U.S. Department of the Interior



        Trails Forever – Chimney Tops Trail Rehabilitation 2012

 The resources required to accomplish Phase One:

 •   The Trails Forever Park crew with five members for 13PP’s.

 •   Four members of the ND trail crew for 1pp to install a new handrail system on the first
     bridge crossing the West Prong of the Little Pigeon River.
National Park Service
Great Smoky Mountains National Park                               U.S. Department of the Interior



        Trails Forever – Chimney Tops Trail Rehabilitation 2012

 The resources required to accomplish Phase One:

 •   The Trails Forever Park crew with five members for 13PP’s.

 •   Four members of the ND trail crew for 1pp to install a new handrail system on the first
     bridge crossing the West Prong of the Little Pigeon River.

 •   PLC funded youth crew (type and time frame yet to be determined due to uncertain
     funding).
National Park Service
Great Smoky Mountains National Park                               U.S. Department of the Interior



        Trails Forever – Chimney Tops Trail Rehabilitation 2012

 The resources required to accomplish Phase One:

 •   The Trails Forever Park crew with five members for 13PP’s.

 •   Four members of the ND trail crew for 1pp to install a new handrail system on the first
     bridge crossing the West Prong of the Little Pigeon River.

 •   PLC funded youth crew (type and time frame yet to be determined due to uncertain
     funding).

 •   Volunteers recruited to work alongside Trails Forever Park crew.
National Park Service
Great Smoky Mountains National Park          U.S. Department of the Interior



      Trails Forever – Chimney Tops Trail Rehabilitation 2012

 Trail closure request
National Park Service
Great Smoky Mountains National Park                               U.S. Department of the Interior



        Trails Forever – Chimney Tops Trail Rehabilitation 2012

 Trail closure request

 We are requesting that the trail be closed to all public use during the four day work week from
 Monday at 7am through Thursday at 5:30pm and re-opened to public use Thursday afternoon
 through Sunday evening. The following are the factors that have led to this closure
 recommendation:
National Park Service
Great Smoky Mountains National Park                               U.S. Department of the Interior



        Trails Forever – Chimney Tops Trail Rehabilitation 2012

 Trail closure request

 We are requesting that the trail be closed to all public use during the four day work week from
 Monday at 7am through Thursday at 5:30pm and re-opened to public use Thursday afternoon
 through Sunday evening. The following are the factors that have led to this closure
 recommendation:

 •   The trail has a unique high volume user traffic pattern.
National Park Service
Great Smoky Mountains National Park                                U.S. Department of the Interior



        Trails Forever – Chimney Tops Trail Rehabilitation 2012

 Trail closure request

 We are requesting that the trail be closed to all public use during the four day work week from
 Monday at 7am through Thursday at 5:30pm and re-opened to public use Thursday afternoon
 through Sunday evening. The following are the factors that have led to this closure
 recommendation:

 •   The trail has a unique high volume user traffic pattern.
 •   The trail serves only as a day use trail with no impacts to overnight users.
National Park Service
Great Smoky Mountains National Park                                 U.S. Department of the Interior



        Trails Forever – Chimney Tops Trail Rehabilitation 2012

 Trail closure request

 We are requesting that the trail be closed to all public use during the four day work week from
 Monday at 7am through Thursday at 5:30pm and re-opened to public use Thursday afternoon
 through Sunday evening. The following are the factors that have led to this closure
 recommendation:

 •   The trail has a unique high volume user traffic pattern.
 •   The trail serves only as a day use trail with no impacts to overnight users.
 •   The trail does not serve as a connector to high use trails and/or trail loop hiking
     opportunities.
National Park Service
Great Smoky Mountains National Park                                 U.S. Department of the Interior



        Trails Forever – Chimney Tops Trail Rehabilitation 2012

 Trail closure request

 We are requesting that the trail be closed to all public use during the four day work week from
 Monday at 7am through Thursday at 5:30pm and re-opened to public use Thursday afternoon
 through Sunday evening. The following are the factors that have led to this closure
 recommendation:

 •   The trail has a unique high volume user traffic pattern.
 •   The trail serves only as a day use trail with no impacts to overnight users.
 •   The trail does not serve as a connector to high use trails and/or trail loop hiking
     opportunities.
 •   The trail is located in very steep, narrow gorge type topography with very dense vegetative
     growth, that for long stretches follows the creek.
National Park Service
Great Smoky Mountains National Park                                 U.S. Department of the Interior



        Trails Forever – Chimney Tops Trail Rehabilitation 2012

 Trail closure request

 We are requesting that the trail be closed to all public use during the four day work week from
 Monday at 7am through Thursday at 5:30pm and re-opened to public use Thursday afternoon
 through Sunday evening. The following are the factors that have led to this closure
 recommendation:

 •   The trail has a unique high volume user traffic pattern.
 •   The trail serves only as a day use trail with no impacts to overnight users.
 •   The trail does not serve as a connector to high use trails and/or trail loop hiking
     opportunities.
 •   The trail is located in very steep, narrow gorge type topography with very dense vegetative
     growth, that for long stretches follows the creek.
 •   Visitor and employee safety are our highest Park goals and are “the only job that MUST get
     completed” C. Daniels-GRSM Safety Officer
National Park Service
Great Smoky Mountains National Park                                     U.S. Department of the Interior



        Trails Forever – Chimney Tops Trail Rehabilitation 2012

 Trail closure request

 We are requesting that the trail be closed to all public use during the four day work week from
 Monday at 7am through Thursday at 5:30pm and re-opened to public use Thursday afternoon
 through Sunday evening. The following are the factors that have led to this closure
 recommendation:

 •   The trail has a unique high volume user traffic pattern.
 •   The trail serves only as a day use trail with no impacts to overnight users.
 •   The trail does not serve as a connector to high use trails and/or trail loop hiking
     opportunities.
 •   The trail is located in very steep, narrow gorge type topography with very dense vegetative
     growth, that for long stretches follows the creek.
 •   Visitor and employee safety are our highest Park goals and are “the only job that MUST get
     completed” C. Daniels-GRSM Safety Officer
 •   If the trail is closed there are still over 800 miles of fantastic trails for visitors to explore and
     enjoy.
National Park Service
Great Smoky Mountains National Park                      U.S. Department of the Interior



      Trails Forever – Chimney Tops Trail Rehabilitation 2012




                 Examples of challenges to crew and visitor safety
National Park Service
Great Smoky Mountains National Park           U.S. Department of the Interior



      Trails Forever – Chimney Tops Trail Rehabilitation 2012

 Proposed Trail Closure Implementation Plan
National Park Service
Great Smoky Mountains National Park                             U.S. Department of the Interior



        Trails Forever – Chimney Tops Trail Rehabilitation 2012

 Proposed Trail Closure Implementation Plan

 •   The Chimney Tops trail would be officially closed to all users each work week from 7AM
     Monday through 5:30PM Thursday. This closure will start Monday, April 30 th last through
     Thursday, October 18th.
National Park Service
Great Smoky Mountains National Park                               U.S. Department of the Interior



        Trails Forever – Chimney Tops Trail Rehabilitation 2012

 Proposed Trail Closure Implementation Plan

 •   The Chimney Tops trail would be officially closed to all users each work week from 7AM
     Monday through 5:30PM Thursday. This closure will start Monday, April 30 th last through
     Thursday, October 18th.

 •   Informational signs would be posted at all trailheads and junctions that have any potential
     to access Chimney Tops Trail.
National Park Service
Great Smoky Mountains National Park                            U.S. Department of the Interior



        Trails Forever – Chimney Tops Trail Rehabilitation 2012

 Proposed Trail Closure Implementation Plan

 The following trails and locations would require posting:

 Chimney Tops Trail               Trailhead and Jct. with Road Prong Trail
 Road Prong Trail                 Trailhead and Jct. with Chimney Tops Trail
 Sugarland Mt. Trail              Both Clingmans Dome RD. and Little River RD. Trailheads
 Husky Gap Trail                  Trailhead at Newfound Gap RD.
 Little River Trail               Trailhead
 Cucumber Gap Trail               Trailhead
 Goshen Prong Trail               Jct. with AT

 All Kiosks and self-permit stations Park wide
National Park Service
Great Smoky Mountains National Park                            U.S. Department of the Interior



        Trails Forever – Chimney Tops Trail Rehabilitation 2012

 Proposed Trail Closure Implementation Plan

 •   Public announcements would be made ahead of the closure to all local media outlets
     internal and external to the Park.
National Park Service
Great Smoky Mountains National Park                             U.S. Department of the Interior



        Trails Forever – Chimney Tops Trail Rehabilitation 2012

 Proposed Trail Closure Implementation Plan

 •   Public announcements would be made ahead of the closure to all local media outlets
     internal and external to the Park.

 •   Park staff would be advised of the closure and may be advised to suggest alternative hikes
     like the Forney Ridge Trail.
National Park Service
Great Smoky Mountains National Park                             U.S. Department of the Interior



        Trails Forever – Chimney Tops Trail Rehabilitation 2012

 Proposed Trail Closure Implementation Plan

 •   Public announcements would be made ahead of the closure to all local media outlets
     internal and external to the Park.

 •   Park staff would be advised of the closure and may be advised to suggest alternative hikes
     like the Forney Ridge Trail.

 •   Portable VMS notification needs to be located at the Chimney Tops Parking lot explaining
     trail closure.
National Park Service
Great Smoky Mountains National Park                                 U.S. Department of the Interior



        Trails Forever – Chimney Tops Trail Rehabilitation 2012

 Proposed Trail Closure Implementation Plan

 •   Public announcements would be made ahead of the closure to all local media outlets
     internal and external to the Park.

 •   Park staff would be advised of the closure and may be advised to suggest alternative hikes
     like the Forney Ridge Trail.

 •   Portable VMS notification needs to be located at the Chimney Tops Parking lot explaining
     trail closure.

 •   Trail access will be closed with barricades yet parking lot will still be open to gain access to
     closure information, alternative hiking opportunities, and Trails Forever program
     information.
1 von 28

Más contenido relacionado

Último(20)

SIMPLE PRESENT TENSE_new.pptxSIMPLE PRESENT TENSE_new.pptx
SIMPLE PRESENT TENSE_new.pptx
nisrinamadani2146 views
Plastic waste.pdfPlastic waste.pdf
Plastic waste.pdf
alqaseedae81 views
Industry4wrd.pptxIndustry4wrd.pptx
Industry4wrd.pptx
BC Chew153 views
CWP_23995_2013_17_11_2023_FINAL_ORDER.pdfCWP_23995_2013_17_11_2023_FINAL_ORDER.pdf
CWP_23995_2013_17_11_2023_FINAL_ORDER.pdf
SukhwinderSingh895865467 views
STERILITY TEST.pptxSTERILITY TEST.pptx
STERILITY TEST.pptx
Anupkumar Sharma102 views
Narration  ppt.pptxNarration  ppt.pptx
Narration ppt.pptx
Tariq KHAN62 views
NS3 Unit 2 Life processes of animals.pptxNS3 Unit 2 Life processes of animals.pptx
NS3 Unit 2 Life processes of animals.pptx
manuelaromero201389 views
231112 (WR) v1  ChatGPT OEB 2023.pdf231112 (WR) v1  ChatGPT OEB 2023.pdf
231112 (WR) v1 ChatGPT OEB 2023.pdf
WilfredRubens.com100 views
Class 10 English  lesson plansClass 10 English  lesson plans
Class 10 English lesson plans
Tariq KHAN172 views
Material del tarjetero LEES Travesías.docxMaterial del tarjetero LEES Travesías.docx
Material del tarjetero LEES Travesías.docx
Norberto Millán Muñoz57 views
ANATOMY AND PHYSIOLOGY UNIT 1 { PART-1}ANATOMY AND PHYSIOLOGY UNIT 1 { PART-1}
ANATOMY AND PHYSIOLOGY UNIT 1 { PART-1}
DR .PALLAVI PATHANIA156 views
Chemistry of sex hormones.pptxChemistry of sex hormones.pptx
Chemistry of sex hormones.pptx
RAJ K. MAURYA97 views
discussion post.pdfdiscussion post.pdf
discussion post.pdf
jessemercerail70 views
Education and Diversity.pptxEducation and Diversity.pptx
Education and Diversity.pptx
DrHafizKosar56 views
Gopal Chakraborty Memorial Quiz 2.0 Prelims.pptxGopal Chakraborty Memorial Quiz 2.0 Prelims.pptx
Gopal Chakraborty Memorial Quiz 2.0 Prelims.pptx
Debapriya Chakraborty221 views

Destacado(20)

How to have difficult conversations How to have difficult conversations
How to have difficult conversations
Rajiv Jayarajah, MAppComm, ACC3.9K views
Introduction to Data ScienceIntroduction to Data Science
Introduction to Data Science
Christy Abraham Joy82.1K views
ChatGPT webinar slidesChatGPT webinar slides
ChatGPT webinar slides
Alireza Esmikhani30.2K views
More than Just Lines on a Map: Best Practices for U.S Bike RoutesMore than Just Lines on a Map: Best Practices for U.S Bike Routes
More than Just Lines on a Map: Best Practices for U.S Bike Routes
Project for Public Spaces & National Center for Biking and Walking6.9K views
Barbie - Brand Strategy PresentationBarbie - Brand Strategy Presentation
Barbie - Brand Strategy Presentation
Erica Santiago25.1K views
9 Tips for a Work-free Vacation9 Tips for a Work-free Vacation
9 Tips for a Work-free Vacation
Weekdone.com7.1K views
I Rock Therefore I Am. 20 Legendary Quotes from PrinceI Rock Therefore I Am. 20 Legendary Quotes from Prince
I Rock Therefore I Am. 20 Legendary Quotes from Prince
Empowered Presentations142.8K views
How to Map Your FutureHow to Map Your Future
How to Map Your Future
SlideShop.com275.1K views

Forney ridge brief overview and chimney tops intro 2012 grs

  • 1. National Park Service Great Smoky Mountains National Park U.S. Department of the Interior Trails Forever – Chimney Tops Trail Rehabilitation 2012 Trail rehabilitation will begin in May 2012 and is scheduled for multiple phases
  • 2. National Park Service Great Smoky Mountains National Park U.S. Department of the Interior Trails Forever – Chimney Tops Trail Rehabilitation 2012 Trail rehabilitation will be completed that enhances the visitors experience while protecting the resource
  • 3. National Park Service Great Smoky Mountains National Park U.S. Department of the Interior Trails Forever – Chimney Tops Trail Rehabilitation 2012 Trail rehabilitation will be achieved utilizing sustainable construction methods and materials
  • 4. National Park Service Great Smoky Mountains National Park U.S. Department of the Interior Trails Forever – Chimney Tops Trail Rehabilitation - Beginning 2012 May the fun begin!!!!! Existing eroded, braided, 12 foot wide “trail”
  • 5. National Park Service Great Smoky Mountains National Park U.S. Department of the Interior Trails Forever – Chimney Tops Trail Rehabilitation - Beginning 2012
  • 6. National Park Service Great Smoky Mountains National Park U.S. Department of the Interior Trails Forever – Chimney Tops Trail Rehabilitation - Beginning 2012 Chimney Tops Trail Phase One
  • 7. National Park Service Great Smoky Mountains National Park U.S. Department of the Interior Trails Forever – Chimney Tops Trail Rehabilitation 2012 The resources required to accomplish Phase One:
  • 8. National Park Service Great Smoky Mountains National Park U.S. Department of the Interior Trails Forever – Chimney Tops Trail Rehabilitation 2012 The resources required to accomplish Phase One: • The Trails Forever Park crew with five members for 13PP’s.
  • 9. National Park Service Great Smoky Mountains National Park U.S. Department of the Interior Trails Forever – Chimney Tops Trail Rehabilitation 2012 The resources required to accomplish Phase One: • The Trails Forever Park crew with five members for 13PP’s. • Four members of the ND trail crew for 1pp to install a new handrail system on the first bridge crossing the West Prong of the Little Pigeon River.
  • 10. National Park Service Great Smoky Mountains National Park U.S. Department of the Interior Trails Forever – Chimney Tops Trail Rehabilitation 2012 The resources required to accomplish Phase One: • The Trails Forever Park crew with five members for 13PP’s. • Four members of the ND trail crew for 1pp to install a new handrail system on the first bridge crossing the West Prong of the Little Pigeon River. • PLC funded youth crew (type and time frame yet to be determined due to uncertain funding).
  • 11. National Park Service Great Smoky Mountains National Park U.S. Department of the Interior Trails Forever – Chimney Tops Trail Rehabilitation 2012 The resources required to accomplish Phase One: • The Trails Forever Park crew with five members for 13PP’s. • Four members of the ND trail crew for 1pp to install a new handrail system on the first bridge crossing the West Prong of the Little Pigeon River. • PLC funded youth crew (type and time frame yet to be determined due to uncertain funding). • Volunteers recruited to work alongside Trails Forever Park crew.
  • 12. National Park Service Great Smoky Mountains National Park U.S. Department of the Interior Trails Forever – Chimney Tops Trail Rehabilitation 2012 Trail closure request
  • 13. National Park Service Great Smoky Mountains National Park U.S. Department of the Interior Trails Forever – Chimney Tops Trail Rehabilitation 2012 Trail closure request We are requesting that the trail be closed to all public use during the four day work week from Monday at 7am through Thursday at 5:30pm and re-opened to public use Thursday afternoon through Sunday evening. The following are the factors that have led to this closure recommendation:
  • 14. National Park Service Great Smoky Mountains National Park U.S. Department of the Interior Trails Forever – Chimney Tops Trail Rehabilitation 2012 Trail closure request We are requesting that the trail be closed to all public use during the four day work week from Monday at 7am through Thursday at 5:30pm and re-opened to public use Thursday afternoon through Sunday evening. The following are the factors that have led to this closure recommendation: • The trail has a unique high volume user traffic pattern.
  • 15. National Park Service Great Smoky Mountains National Park U.S. Department of the Interior Trails Forever – Chimney Tops Trail Rehabilitation 2012 Trail closure request We are requesting that the trail be closed to all public use during the four day work week from Monday at 7am through Thursday at 5:30pm and re-opened to public use Thursday afternoon through Sunday evening. The following are the factors that have led to this closure recommendation: • The trail has a unique high volume user traffic pattern. • The trail serves only as a day use trail with no impacts to overnight users.
  • 16. National Park Service Great Smoky Mountains National Park U.S. Department of the Interior Trails Forever – Chimney Tops Trail Rehabilitation 2012 Trail closure request We are requesting that the trail be closed to all public use during the four day work week from Monday at 7am through Thursday at 5:30pm and re-opened to public use Thursday afternoon through Sunday evening. The following are the factors that have led to this closure recommendation: • The trail has a unique high volume user traffic pattern. • The trail serves only as a day use trail with no impacts to overnight users. • The trail does not serve as a connector to high use trails and/or trail loop hiking opportunities.
  • 17. National Park Service Great Smoky Mountains National Park U.S. Department of the Interior Trails Forever – Chimney Tops Trail Rehabilitation 2012 Trail closure request We are requesting that the trail be closed to all public use during the four day work week from Monday at 7am through Thursday at 5:30pm and re-opened to public use Thursday afternoon through Sunday evening. The following are the factors that have led to this closure recommendation: • The trail has a unique high volume user traffic pattern. • The trail serves only as a day use trail with no impacts to overnight users. • The trail does not serve as a connector to high use trails and/or trail loop hiking opportunities. • The trail is located in very steep, narrow gorge type topography with very dense vegetative growth, that for long stretches follows the creek.
  • 18. National Park Service Great Smoky Mountains National Park U.S. Department of the Interior Trails Forever – Chimney Tops Trail Rehabilitation 2012 Trail closure request We are requesting that the trail be closed to all public use during the four day work week from Monday at 7am through Thursday at 5:30pm and re-opened to public use Thursday afternoon through Sunday evening. The following are the factors that have led to this closure recommendation: • The trail has a unique high volume user traffic pattern. • The trail serves only as a day use trail with no impacts to overnight users. • The trail does not serve as a connector to high use trails and/or trail loop hiking opportunities. • The trail is located in very steep, narrow gorge type topography with very dense vegetative growth, that for long stretches follows the creek. • Visitor and employee safety are our highest Park goals and are “the only job that MUST get completed” C. Daniels-GRSM Safety Officer
  • 19. National Park Service Great Smoky Mountains National Park U.S. Department of the Interior Trails Forever – Chimney Tops Trail Rehabilitation 2012 Trail closure request We are requesting that the trail be closed to all public use during the four day work week from Monday at 7am through Thursday at 5:30pm and re-opened to public use Thursday afternoon through Sunday evening. The following are the factors that have led to this closure recommendation: • The trail has a unique high volume user traffic pattern. • The trail serves only as a day use trail with no impacts to overnight users. • The trail does not serve as a connector to high use trails and/or trail loop hiking opportunities. • The trail is located in very steep, narrow gorge type topography with very dense vegetative growth, that for long stretches follows the creek. • Visitor and employee safety are our highest Park goals and are “the only job that MUST get completed” C. Daniels-GRSM Safety Officer • If the trail is closed there are still over 800 miles of fantastic trails for visitors to explore and enjoy.
  • 20. National Park Service Great Smoky Mountains National Park U.S. Department of the Interior Trails Forever – Chimney Tops Trail Rehabilitation 2012 Examples of challenges to crew and visitor safety
  • 21. National Park Service Great Smoky Mountains National Park U.S. Department of the Interior Trails Forever – Chimney Tops Trail Rehabilitation 2012 Proposed Trail Closure Implementation Plan
  • 22. National Park Service Great Smoky Mountains National Park U.S. Department of the Interior Trails Forever – Chimney Tops Trail Rehabilitation 2012 Proposed Trail Closure Implementation Plan • The Chimney Tops trail would be officially closed to all users each work week from 7AM Monday through 5:30PM Thursday. This closure will start Monday, April 30 th last through Thursday, October 18th.
  • 23. National Park Service Great Smoky Mountains National Park U.S. Department of the Interior Trails Forever – Chimney Tops Trail Rehabilitation 2012 Proposed Trail Closure Implementation Plan • The Chimney Tops trail would be officially closed to all users each work week from 7AM Monday through 5:30PM Thursday. This closure will start Monday, April 30 th last through Thursday, October 18th. • Informational signs would be posted at all trailheads and junctions that have any potential to access Chimney Tops Trail.
  • 24. National Park Service Great Smoky Mountains National Park U.S. Department of the Interior Trails Forever – Chimney Tops Trail Rehabilitation 2012 Proposed Trail Closure Implementation Plan The following trails and locations would require posting: Chimney Tops Trail Trailhead and Jct. with Road Prong Trail Road Prong Trail Trailhead and Jct. with Chimney Tops Trail Sugarland Mt. Trail Both Clingmans Dome RD. and Little River RD. Trailheads Husky Gap Trail Trailhead at Newfound Gap RD. Little River Trail Trailhead Cucumber Gap Trail Trailhead Goshen Prong Trail Jct. with AT All Kiosks and self-permit stations Park wide
  • 25. National Park Service Great Smoky Mountains National Park U.S. Department of the Interior Trails Forever – Chimney Tops Trail Rehabilitation 2012 Proposed Trail Closure Implementation Plan • Public announcements would be made ahead of the closure to all local media outlets internal and external to the Park.
  • 26. National Park Service Great Smoky Mountains National Park U.S. Department of the Interior Trails Forever – Chimney Tops Trail Rehabilitation 2012 Proposed Trail Closure Implementation Plan • Public announcements would be made ahead of the closure to all local media outlets internal and external to the Park. • Park staff would be advised of the closure and may be advised to suggest alternative hikes like the Forney Ridge Trail.
  • 27. National Park Service Great Smoky Mountains National Park U.S. Department of the Interior Trails Forever – Chimney Tops Trail Rehabilitation 2012 Proposed Trail Closure Implementation Plan • Public announcements would be made ahead of the closure to all local media outlets internal and external to the Park. • Park staff would be advised of the closure and may be advised to suggest alternative hikes like the Forney Ridge Trail. • Portable VMS notification needs to be located at the Chimney Tops Parking lot explaining trail closure.
  • 28. National Park Service Great Smoky Mountains National Park U.S. Department of the Interior Trails Forever – Chimney Tops Trail Rehabilitation 2012 Proposed Trail Closure Implementation Plan • Public announcements would be made ahead of the closure to all local media outlets internal and external to the Park. • Park staff would be advised of the closure and may be advised to suggest alternative hikes like the Forney Ridge Trail. • Portable VMS notification needs to be located at the Chimney Tops Parking lot explaining trail closure. • Trail access will be closed with barricades yet parking lot will still be open to gain access to closure information, alternative hiking opportunities, and Trails Forever program information.