Rate analysis and costing - Estimation, Costing and Valuation Engineering
1. SNS COLLEGE OF ENGINEERING
An Autonomous Institutions
Accredited by NBA – AICTE and Accredited by NAAC – UGC with ‘A’ & ‘A+’Grade
Approved by AICTE, New Delhi & Affiliated to Anna University, Chennai
DEPARTMENT OF CIVIL ENGINEERING
COURSE NAME:
CE8701 - ESTIMATION, COSTING AND VALUATION ENGINEERING
IV YEAR / VII SEMESTER
Unit II: RATE ANALYSIS AND COSTING
Topic 1 : Analysis of Rates
2. 12/4/2020
UNIT II - RATE ANALYSIS AND COSTING
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
Standard Data – Observed Data – Schedule of rates – Market rates –
Standard Data for Man Hours and Machineries for common civil works –
Rate Analysis for all Building works, canals, and Roads– Cost Estimates
(additional practice in class room using Computer softwares) - (Analysis of
rates for the item of work asked, the data regarding labour, rates of material
and rates of labour to be given in the Examination Question Paper)
2/88
3. 12/4/2020
Analysis of Rates
.
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
Data
Method of determining the rate per unit of particular item of
work in a structure.
Including Quantities of materials required, cost of materials at
site, Labour required and labourer charge, lump sum if required.
The cost per unit of an item of work is called data.
Analysis of rates
Quantities of items are calculated by detailed estimation.
Classification of Data
1. Standard data
2. Main data
3. Sub data
4. Observed data
5. Sundries and Lump sum provision.
3/88
4. 12/4/2020
Analysis of Rates
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
1. Standard data
SOR 2019-2020.pdf
2. Main data
Major item of works.
Total cost of a particular item of work involving many sub works or
sub data
3.Sub data
In main data some of the certain minor items (Sub data) are not
given directly.
In this case the cost of minor works are prepared as sub data.
4/88
5. 12/4/2020
Analysis of Rates
.
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
3.Sub data
Example:
Plastering with C.M (1:5) 12mm thick – 10 m2
a) Cement mortar 1:5 – 0.14 m3
b) Mason I class – 1.1 Nos
c) Mazdoor I class – 0.5 Nos
d) Mazdoor II class – 1.1 NoS
e) Lump sum / Sundries – L.S
5/88
23. 12/4/2020
Analysis of Rates
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
Problem 2
Prepare the data for concrete broken stone using 40mm size in CM 1:4 -10
m3.
Material and labour required
a) Cement Mortar 1:4 - 1 m3
Sand cost at site - 1 m3
Cement – 360 kg
Mixing charges - 1 m3
b) Plain cement concrete in cement mortar 1:4:10 using 40mm size hard
broken stone -10 m3
Broken stone 40mm size cost at site - 9.5 m3
Cement mortar 1:4 as per worked sub data – 3.8 m3
Mason II Class -1.8 Nos
Mazdoor category I – 17.7 Nos.
Mazdoor category II – 14.1 Nos 23/88
24. 12/4/2020
Analysis of Rates
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
Cost of Labour
Mixing charger for CM – Rs 50 / m3
Mason II class - Rs 900 / day
Mazdoor category I – 700 /day
Mazdoor category II – 500 / day
Cost of materials and labour at site
Material Unit
Cost
(Rs)
Lead
(Km)
Rate for
lead/Km
(Rs)
Handling
charge (Rs)
Cement 1 bag 450 12 5 6
Sand 1 m3 1590 20 6 30
Broken stone
40mm size
1 m3 710 20 7 35
24/88
25. 12/4/2020
Analysis of Rates
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
Solution
Lead statement for cost of material at site:
Material Unit
Cost
(Rs)
1
Lead
(Km)
2
Rate for
lead/Km
(Rs)
3
Handling
charge
(Rs)
4
Total (1+
(2x3) +4)
Cement 1 bag 450 12 5 6 516
Sand 1 m3 1590 20 6 30 1740
Broken stone
40mm size
1 m3 710 20 7 35 885
25/88
26. 12/4/2020
Analysis of Rates
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
Sub data
Cement mortar 1:4
1 m3 Sand cost at site 1740 1 m3 1740.00
360 kg
(1440/4)
Cement 516 50 kg 3715.20
1 m3 Mixing charge 50 1 m3 50.000
Rate for 1 m3 5505.20
26/88
27. 12/4/2020
Analysis of Rates
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
Main data
Plain cement concrete in cement mortar 1:4:10 using 40mm size hard
broken stone -10 m3
Rate for 10 m3 = Rs.50387.260/-
9.5 m3 Broken stone 40mm size cost at site 885 1m3 8407.50
3.8 m3 Cement mortar 1:4 as per worked sub
data
5505.2 1m3 20919.76
1.8 Nos Mason II Class 900 Day 1620.00
17.7 Nos Mazdoor category I 700 Day 12390.00
14.1 Nos Maxdoor category II 500 Day 7050.00
Rate for 10 m3 50387.260
27/88
28. 12/4/2020
Analysis of Rates
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
Problem 3
Prepare the data for flooring with cc 1:4:8 using 20mm size broken
stone 100mm thick and plastered over with CM 1:3, 15mm thick – 10
m2
Material and labour required
a) Cement Mortar 1:4 - 1 m3
Sand cost at site - 1 m3
Cement – 360 kg
Mixing charges - 1 m3
b) Cement Mortar 1:3 - 1 m3
Sand cost at site - 1 m3
Cement – 480 kg
Mixing charges - 1 m3
28/88
29. 12/4/2020
Analysis of Rates
.
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
c) Cement concrete 1:4:8, 20mm size broken stone - 10 m3
Broken stone 20mm size - 9 m3
Cement Mortar 1:4 – 4.5 m3
Mason II class– 1.8 nos
Mazdoor category I – 17.7 nos
Mazdoor category II– 14.1 nos
d) Plastering with Cement mortar 1:3, 15mm thick - 10 m2
Cement Mortar 1:3 – 0.14 m3
Mason I class– 1.1 nos
Mazdoor category I – 0.5 nos
Mazdoor category II– 1.1 nos
29/88
30. 12/4/2020
Analysis of Rates
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
e) Flooring with cement concrete 1:4:8 - 10 m2
Concrete broken stone in cement mortar 1:4 – 1 m3
Plastering with cement mortar 1:3, 15mm thick – 10 m2
Cost of material and labour at site in rupees
Cement - 10320 / tonne
Sand - 1740 / m3 (5000/unit in store)
Stone 20mm - 885 / m3 (2500/unit store)
Mason I class - 950 / Day
Mason II class - 900 / Day
Mazdoor class I - 700 / Day
Mazdoor class II- 500 / Day
Mixing charge - 50 / m3
30/88
31. 12/4/2020
Analysis of Rates
.
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
Solution
Sub data 1 - Cement mortar 1:4 - 1 m3
1 m3 Sand cost at site 1740 1 m3 1740.00
360 kg
(1440/4)
Cement 10320 1000 kg 3715.20
1 m3 Mixing charge 50 1 m3 50.000
Rate for 1 m3 5505.20
31/88
32. 12/4/2020
Analysis of Rates
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
Sub data 2 - Cement mortar 1:3 - 1 m3
1 m3 Sand cost at site 1740 1 m3 1740.00
480 kg
(1440/3)
Cement 10320 1000 kg 4953.60
1 m3 Mixing charge 50 1 m3 50.000
Rate for 1 m3 6743.60
32/88
33. 12/4/2020
Analysis of Rates
.
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
Sub data 3 - Plastering with Cement mortar 1:3, 15mm thick - 10 m2
0.14 m3 Cement mortar 1:3 6743.60 m3 944.104
1.1 nos Mason I class 950 Day 1045
0.5 nos Mazdoor category I 700 Day 350
1.1 nos Mazdoor caterory II 500 Day 550
Rate for 10 m2 2889.10
33/88
34. 12/4/2020
Analysis of Rates
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
Sub data 4 - Cement concrete 1:4:8, 20mm size broken stone - 10 m3
9.0 m3 Broken stone 20mm 885 m3 7965
4.5 m3 Cement mortar 1:4 5505.2 m3 24773.4
1.8 nos Mason II Class 900 Day 1620
17.7 nos Mazdoor category I 700 Day 12390
14.1 nos Mazdoor category II 500 Day 7050
Rate for 10 m3 53798.40
34/88
35. 12/4/2020
Analysis of Rates
.
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
Main data - Flooring with cc1:4:8 using 20mm size broken stone
100mm thick and plastered over with CM 1:3, 15mm thick – 10 m2
Result - Rate for 10 m2 = Rs.8268.940/-
1 m3 Concrete broken stone in
CM 1:4
53798.40 10 m3 5379.84
10 m2 Plastering with CM (1:3)
15mm thick
2889.10 10 m2 2889.10
Rate for 10 m2 8268.940
35/88
36. 12/4/2020
Analysis of Rates
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
Problem 4
Prepare the data for Mosaic tiled flooring using hydraulic pressed
mosaic tiles of 200x200x20mm size with CM 1:4, 20mm thick and
pointing with colour cement including polishing – 1 m2
Material and labour required
a) Cement Mortar 1:4 - 1 m3
Sand cost at site - 1 m3
Cement - 360 kg
Mixing charges - 1 m3
b) Mosaic tiled flooring, pointing and polishing - 10 m2
Mosaic tile 200x200x20mm – 250 nos.
Cement mortar 1:4 – 0.21 m3
Colour cement - 22kg
36/88
37. 12/4/2020
Analysis of Rates
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
b) Mosaic tiled flooring, pointing and polishing - 10 m2
Mason I class - 1.1 nos.
Mason II Class - 2.7 nos
Mazdoor category I - 2.7 nos
Mazdoor category II - 5.4 nos
Polisher - 1.1 nos
Cost of material and labour at site in rupees
Cement - 516 / bag
Sand - 1740 / m3 (5000/unit in store)
Colour cement - 450 / bag
Mosaic tiles - 4500 / 100 nos
Mason I class - 950 / Day
37/88
38. 12/4/2020
Analysis of Rates
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
Cost of material and labour at site in rupees
Mason II class - 900 / Day
Polisher - 800 / Day
Mazdoor class I - 700 / Day
Mazdoor class II- 500 / Day
Mixing charge - 50 / m3
Solution
Sub data 1 - Cement mortar 1:4 - 1 m3
1 m3 Sand cost at site 1740 1 m3 1740.00
360 kg Cement 10320 1000 kg 3715.20
1 m3 Mixing charge 50 1 m3 50.000
Rate for 1 m3 5505.20
38/88
39. 12/4/2020
Analysis of Rates
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
Main data : Mosaic tiled flooring using hydraulic pressed mosaic tiles
of 200x200x20mm size with CM 1:4, 20mm thick and pointing with
colour cement including polishing – 1 m2
250 nos Mosaic tiles 4500 100 nos 11250
0.21 m3 CM 1:4 5505.2 1 m3 1156.092
22 kg Colour cement 450 Bag 198
1.1 nos Mason I class 950 Day 1045
2.7 nos Mason II class 900 Day 2430
2.7 nos Mazdoor I class 700 Day 1890
5.4 nos Mazdoor II class 500 Day 2700
1.1 nos Polisher 800 Day 880
Rate for 10 m2 21549.092
39/88
40. 12/4/2020
Analysis of Rates
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
Rate of 10 m2 = Rs.21549.092/-
Rate of 1 m2 = 21549.092/10 = Rs.2154.909.
Result :
Rate of 1 m2 = Rs.2154.909.
Brick work calculation.
A) Brickwork in foundation
Rate will varying at based on the depth.
Ex – 1.5m to 4.5m, 4.5m to 9m
B) Brickwork in super structure
Rate will varying based on the height
Ex: Up to 4.5m and above 4.5m at every 1m height.
40/88
41. 12/4/2020
Analysis of Rates
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
Problem 4
Prepare the data for brick work in foundation in cement mortar 1:5
mix using first class bricks– 1 m3
Material and labour required.
a) Cement Mortar 1:5 - 1 m3
Sand cost at site - 1 m3
Cement - 288 kg
Mixing charges - 1 m3
b) Brickwork in foundation using I class brick works in CM 1:5 - 10 m3
Bricks – 19 x 9 x 9 cm - 5000 nos
Cement mortar 1:5 - 2.2 m3
Mason I class - 3.5 nos.
41/88
42. 12/4/2020
Analysis of Rates
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
b) Brickwork in foundation using I class brick works in CM 1:5 - 10 m3
Mason II Class - 10.6 nos
Mazdoor category I - 7.1 nos
Mazdoor category II - 21.2 nos
Cost of material and labour at site in rupees
Cement - 516 / bag
Sand - 1740 / m3 (5000/unit in store)
Bricks I class - 8 / no
Mason I class - 950 / Day
Mason II class - 900 / Day
Mazdoor class I - 700 / Day
Mazdoor class II- 500 / Day
Mixing charge - 50 / m3
42/88
43. 12/4/2020
Analysis of Rates
.
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
Solution:
Sub data 1 - Cement mortar 1:5 - 1 m3
1 m3 Sand cost at site 1740 1 m3 1740.00
288 kg
(1440/5)
Cement 516 50 kg 2972.16
1 m3 Mixing charge 50 1 m3 50.000
Rate for 1 m3 4762.16
43/88
44. 12/4/2020
Analysis of Rates
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
Main data: Brickwork in foundation using I class brick works in CM
1:5 - 10 m3
Result : Rate for 1 m3 = Rs.7891.17/-
5000 nos Bricks 19x9x9 cm 8 No 40000
2.2 m3 CM 1:5 4762.16 m3 10476.75
3.5 nos Mason I class 950 Day 3325
10.6 nos Mason II class 900 Day 9540
7.1 nos Mazdoor I category 700 Day 4970
21.2 nos Mazdoor II category 500 Day 10600
Rate for 10 m3 78911.75
44/88
45. 12/4/2020
Analysis of Rates
.
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
Problem 5 (Tutorial problem)
Prepare the data for brick work in super structure using first class
brick in cement mortar 1:5 – 1 m3
Material and labour required.
a) Brickwork with CM 1:5 - 10 m3
Bricks – - 5000 nos
Cement mortar 1:5 - 1.4 m3
Mason I class - 7.0 nos.
Mason II class - 8.1 nos.
Mazdoor I class - 8.1 nos.
Mazdoor II class - 8.4 nos.
45/88
46. 12/4/2020
Analysis of Rates
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
b)Cost of material and labour at site in rupees
Cement - 516 / bag
Sand - 1740 / m3 (5000/unit in store)
Bricks I class - 8 / no
Mason I class - 950 / Day
Mason II class - 900 / Day
Mazdoor class I - 700 / Day
Mazdoor class II- 500 / Day
Mixing charge - 50 / m3
46/88
47. 12/4/2020
Analysis of Rates
.
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
Problem 6 (Tutorial problem)
Prepare the data for brick work in partition using second class brick
in cement mortar 1:3 – 1 m3
Material and labour required.
a) Cement Mortar 1:3 - 1 m3
Sand cost at site - 1 m3
Cement - 480 kg
Mixing charges - 1 m3
b) Brickwork with CM 1:3 - 10 m3
Bricks II class - 7500 nos
Cement mortar 1:3 - 2.7 m3
Mason I class - 3.5 nos.
47/88
48. 12/4/2020
Analysis of Rates
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
b) Brickwork with CM 1:3 - 10 m3
Mason II class - 7.1 nos.
Mazdoor I class - 7.1 nos.
Mazdoor II class - 14.1 nos.
Cost of material and labour at site in rupees
Cement - 516 / bag
Sand - 1740 / m3 (5000/unit in store)
Bricks I class - 8 / no
Mason I class - 950 / Day
Mason II class - 900 / Day
Mazdoor class I - 700 / Day
Mazdoor class II- 500 / Day
Mixing charge - 50 / m3
48/88
49. 12/4/2020
Analysis of Rates
.
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
Problem 7 (Tutorial problem)
Prepare the data for coursed rubble masonry second sort in cement
mortar 1:5 – 1 m3
Material and labour required.
a) Cement Mortar 1:5 - 1 m3
Sand cost at site - 1 m3
Cement - 288 kg
Mixing charges - 1 m3
b) Coursed rubble masonry second sort in CM 1:5- 10 m3
Course rubble stone - 6 m3
Rough stone - 5 m3
Cement mortar 1:5 - 3.2 m3
49/88
50. 12/4/2020
Analysis of Rates
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
b) Coursed rubble masonry second sort in CM 1:5- 10 m3
Mason I class - 7.1 nos.
Mason II class - 17.6 nos.
Mazdoor II class - 14.1 nos.
Cost of material and labour at site in rupees
Cement - 516 / bag
Sand - 1740 / m3 (5000/unit in store)
Course rubbled stone - 915 / m3
Rough stone - 975 / m3
Mason I class - 950 / Day
Mason II class - 900 / Day
Mazdoor class II - 500 / Day
Mixing charge - 50 / m3
50/88
51. 12/4/2020
Analysis of Rates
.
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
Problem 8
Prepare the data for weathering course with broken brick in pure
slaked lime over RCC roof slab - 10 m3
Material and labour required.
a) Weathering course with 20mm broken brick - 10 m3
Broken brick 20mm size - 12.8 m3
Slaked lime - 5 m3
Mason I class - 1.8 nos
Mazdoor I class - 17.7 nos
Mazdoor II class - 14.1 nos
51/88
52. 12/4/2020
Analysis of Rates
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
b) Cost of the materials and labours at site
Broken brick 20mm size - 750/ m3
Slaked lime - 1100/ m3
Mason I class - 920/ Day
Mazdoor I class - 700 / Day
Mazdoor II class - 500 / Day
52/88
53. 12/4/2020
Analysis of Rates
.
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
Solution
Main data : Weathering course with 20mm broken brick - 10 m3
Result : Rate for 10 m3 = Rs.36250/-
12.8m3 Broken Bricks 20mm 750 1m3 9600
5m3 Slaked lime 1100 1 m3 5500
1.8 nos Mason I class 950 Day 1710
17.7 nos Mazdoor I category 700 Day 12390
14.1 nos Mazdoor II category 500 Day 7050
Rate for 10 m3 36250
53/88
54. 12/4/2020
Analysis of Rates
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
Problem 9
Prepare the data for RCC roof slab of size 4 x 3 x 0.1 m of mix 1:2:4
using 20mm hard broken stone with reinforcement at 80kg/m3 of
concrete including cutting, bending , tying and centering curing etc. –
1 m3
Material and labour required
a) Cement concrete 1:2:4 using 20mm hard broken stone - 10 m3
Broken stone - 9 m3
Cement - 3240 kg
Sand - 4.5 m3
Mason I class - 3.5 nos
Mazdoor I grade - 21.2 nos.
Mazdoor II grade - 35.8 nos
54/88
55. 12/4/2020
Analysis of Rates
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
b) RCC roof 4 x3 x0.12m with reinforcement 80kg/ m3 of concrete
including cutting, bending, tying etc., - 1 m3
Cement concrete 1:2:4 - 1 m3
Steel - 80kg/ m3
Binding wire - 1 % of steel required
Cutting, bending and tying - as steel required
Centering - as required + 20 % extra for sides.
c) Cost of material and labour at site in rupees
Cement - 516 / bag
Sand - 1740 / m3 (5000/unit in store)
Broken brick 20mm size - 750/ m3
Steel - 55000/ tonne
Binding wire - 150 / kg
55/88
56. 12/4/2020
Analysis of Rates
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
c) Cost of material and labour at site in rupees
Mason I class - 950 / day
Mason II class - 900 / day
Mazdoor I grade - 700 / day
Mazdoor II grade - 500 / day
Cutting, bending and tying – 50 / kg
Centering charge - 300 / m2
Solution
Centering Area = (L x B ) + 20 % for sides or L (B+2D)
= ( 4x 3) + (20/100) x (4x3)
= 14.4 m2
56/88
57. 12/4/2020
Analysis of Rates
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
Sub data: CC 1:2:4 using 20mm hard broken stone – 10 m3
9 m3 Broken Bricks 20mm 750 1m3 6750
4.5m3 Sand 1740 1 m3 7830
3240 kg Cement 516 Bag 33436.8
3.5 nos Mason I class 950 Day 3325
21.2 nos Mazdoor I category 700 Day 14840
35.8 nos Mazdoor II category 500 Day 17900
Rate for 10 m3 84081.8
57/88
58. 12/4/2020
Analysis of Rates
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
Main data: RCC roof 4 x3 x0.12m with reinforcement 80kg/ m3 of
concrete including cutting, bending, tying etc., - 1 m3
Result : Rate for 1 m3 = Rs. 21248.18/-
1 m3 CC 1:2:4 84081.8 10m3 8408.18
80kg Steel 55000 tonne 4400.00
0.8 kg Binding wire (1% of steel) 150 kg 120.00
80kg Cutting, Bending & tying 50 kg 4000.00
14.4 m2 Centering 300 1 m2 4320.00
Rate for 1 m3 21248.18
58/88
59. 12/4/2020
Analysis of Rates
.
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
Problem 10
Prepare the data for RCC beam of size 300 x 450mm with 1:2:4 mix
using 20mm hard broken stone with reinforcement of 150kg/m3
including centering, shuttering, etc. – 1 m3
Material and labour required
a) Cement concrete 1:2:4 using 20mm hard broken stone - 10 m3
Broken stone - 9 m3
Cement - 2.25 m3
Sand - 4.5 m3
Mason I class - 3.5 nos
Mazdoor I grade - 21.2 nos.
Mazdoor II grade - 35.3 nos
59/88
60. 12/4/2020
Analysis of Rates
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
b) RCC beam of size 300 x 450mm with 1:2:4 mix using 20mm hard
broken stone with reinforcement of 150kg/m3 including centering,
shuttering, etc. – 1 m3
Cement concrete 1:2:4 - 1 m3
Steel - 150 kg/ m3
Binding wire - 1 % of steel required
Cutting, bending and tying - as steel required
Centering - as required
c) Cost of material and labour at site in rupees
Cement - 516 / bag
Sand - 1740 / m3 (5000/unit in store)
Broken brick 20mm size - 750/ m3
Steel - 55000/ tonne
60/88
61. 12/4/2020
Analysis of Rates
.
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
c) Cost of material and labour at site in rupees
Binding wire - 150 / kg
Mason I class - 950 / day
Mason II class - 900 / day
Mazdoor I grade - 700 / day
Mazdoor II grade - 500 / day
Cutting, bending and tying – 50 / kg
Centering charge - 300 / m2
Solution
Centering Area = L (B+2D)
Volume = L x B x D , L = 1 m3 / (0.3 x 0.45) = 7.41m.
Centering Area = L (B+2D) = 7.41 (0.3+2x0.45) = 8.832 m2
61/88
62. 12/4/2020
Analysis of Rates
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
Sub data: CC 1:2:4 using 20mm hard broken stone – 10 m3
9 m3 Broken Bricks 20mm 750 1m3 6750
4.5m3 Sand 1740 1 m3 7830
(2.25 x 1440)
3240 kg
Cement 516 Bag 33436.8
3.5 nos Mason I class 950 Day 3325
21.2 nos Mazdoor I category 700 Day 14840
35.3 nos Mazdoor II category 500 Day 17650
Rate for 10 m3 83831.8
62/88
63. 12/4/2020
Analysis of Rates
.
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
Main data: RCC beam of size 300 x 450mm with 1:2:4 mix using
20mm hard broken stone with reinforcement of 150kg/m3 including
centering, shuttering, etc. – 1 m3
Result : Rate for 1 m3 = Rs. 27007.78/-
1 m3 CC 1:2:4 83831.8 10m3 8383.18
150 kg Steel 55000 tonne 8250.00
1.5 kg Binding wire (1% of steel) 150 kg 225.00
150kg Cutting, Bending & tying 50 kg 7500.00
8.832 m2 Centering 300 1 m2 2649.60
Rate for 1 m3 27007.78
63/88
64. 12/4/2020
Analysis of Rates
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
Problem 11 (Tutorial problem)
Prepare the data for RCC column of size 300x300mm with mix of 1:2:4
using 20mm hard broken stone with reinforcement of 160 kg/m3
including centering, shuttering, curing, etc. – 1 m run.
Material and labour required
a) Cement concrete 1:2:4 using 20mm hard broken stone - 10 m3
Broken stone - 9 m3
Cement - 2.25 m3
Sand - 4.5 m3
Mason I class - 3.5 nos
Mazdoor I grade - 21.2 nos.
Mazdoor II grade - 35.3 nos
64/88
65. 12/4/2020
Analysis of Rates
.
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
b) RCC 1:2:4 mix column – 1mrun.
Cement concrete 1:2:4 - 0.09 m3 (0.3 x 0.3 x 1)
Steel - 14.56 kg (0.091 m3 x 160 kg/ m3)
Binding wire - 1 % of steel required
Cutting, bending and tying - as steel required
Centering - as required
c) Cost of material and labour at site in rupees
Cement - 516 / bag
Sand - 1740 / m3 (5000/unit in store)
Broken brick 20mm size - 750/ m3
Steel - 55000/ tonne
65/88
66. 12/4/2020
Analysis of Rates
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
c) Cost of material and labour at site in rupees
Binding wire - 150 / kg
Mason I class - 950 / day
Mason II class - 900 / day
Mazdoor I grade - 700 / day
Mazdoor II grade - 500 / day
Cutting, bending and tying – 50 / kg
Centering charge - 300 / m2
Solution
Centering Area for 1m run = (0.3 x 4 ) x 1
= 1.2m2
66/88
67. 12/4/2020
Analysis of Rates
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
Problem 12
Prepare the data for the following items of plastering over brick
masonry in cement mortar of given mix.
a) Plastering with CM 1:3 - 12mm thick – 10 m2
b) Plastering with CM 1:3 - 20mm thick – 10 m2
c) Plastering with CM 1:5 - 12mm thick – 10 m2
d) Plastering with CM 1:5 - 15mm thick – 10 m2
e) Plastering with CM 1:5 - 20mm thick – 10 m2
Material and labour required
a) Plastering with CM 1:3 - 12mm thick – 10 m2
Cement mortar 1:3 - 0.14 m3 , Mason I class -1.1 nos
Mazdoor category I - 0.5 nos and Mazdoor category II- 1.1 nos
67/88
68. 12/4/2020
Analysis of Rates
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
b) Plastering with CM 1:3 - 20mm thick – 10 m2
Cement mortar 1:3 - 0.22 m3
Mason I class -2.2 nos
Mazdoor category I - 0.5 nos
Mazdoor category II - 3.2 nos
c) Plastering with CM 1:5 - 12mm thick – 10 m2
Cement mortar 1:5 - 0.14 m3
Mason I class -1.1 nos
Mazdoor category I - 0.5 nos
Mazdoor category II - 1.1 nos
d) Plastering with CM 1:5 - 15mm thick – 10 m2
Cement mortar 1:5 - 0.17 m3
Mason I class -1.51 nos
Mazdoor category I - 0.5 nos & Mazdoor category II- 1.89 nos
68/88
69. 12/4/2020
Analysis of Rates
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
e) Plastering with CM 1:5 - 20mm thick – 10 m2
Cement mortar 1:5 - 0.22 m3
Mason I class -2.2 nos
Mazdoor category I - 0.5 nos
Mazdoor category II - 3.2 nos
Cost of materials and Labours at site
Cement - 516 / bag
Sand - 1740 / m3
Mixing charger for CM - Rs 50 / m3
Mason I class - Rs 950/ day
Mason II class - Rs 900 / day
Mazdoor category I - 700 /day
Mazdoor category II - 500 / day
69/88
70. 12/4/2020
Analysis of Rates
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
Sub data 1 : Cement Mortar 1:3 – 1 m3
1 m3 Sand cost at site 1740 1 m3 1740.00
480 kg
(1440/3)
Cement 516 50 kg 4953.60
1 m3 Mixing charge 50 1 m3 50.000
Rate for 1 m3 6743.60
70/88
71. 12/4/2020
Analysis of Rates
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
Sub data 1 : Cement Mortar 1:5 – 1 m3
1 m3 Sand cost at site 1740 1 m3 1740.00
288 kg
(1440/5)
Cement 516 50 kg 2972.16
1 m3 Mixing charge 50 1 m3 50.000
Rate for 1 m3 4762.16
71/88
72. 12/4/2020
Analysis of Rates
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
Main data : a) Plastering with CM 1:3 - 12mm thick – 10 m2
Result for 10 m2 = Rs.2889.104/-
0.14 m3 Cement mortar 1:3 6743.6 1 m3 944.104
1.1 nos Mason I class 950 Day 1045.00
0.5 nos Mazdoor category I 700 Day 350
1.1 nos Mazdoor category II 500 Day 550
Rate for 10 m2 2889.104
72/88
73. 12/4/2020
Analysis of Rates
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
Main data : b) Plastering with CM 1:3 - 20 mm thick – 10 m2
Result for 10 m2 = Rs.5523.592/-
0.22 m3 Cement mortar 1:3 6743.6 1 m3 1483.592
2.2 nos Mason I class 950 Day 2090.00
0.5 nos Mazdoor category I 700 Day 350
3.2 nos Mazdoor category II 500 Day 1600
Rate for 10 m2 5523.592
73/88
74. 12/4/2020
Analysis of Rates
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
Main data : c) Plastering with CM 1:5 - 12mm thick – 10 m2
Result for 10 m2 = Rs.2611.702/-
0.14 m3 Cement mortar 1:5 4762.16 1 m3 666.702
1.1 nos Mason I class 950 Day 1045.00
0.5 nos Mazdoor category I 700 Day 350
1.1 nos Mazdoor category II 500 Day 550
Rate for 10 m2 2611.702
74/88
75. 12/4/2020
Analysis of Rates
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
Main data : d) Plastering with CM 1:5 - 15 mm thick – 10 m2
Result for 10 m2 = Rs.3539.067/-
0.17 m3 Cement mortar 1:3 4762.16 1 m3 809.567
1.51 nos Mason I class 950 Day 1434.50
0.5 nos Mazdoor category I 700 Day 350
1.89 nos Mazdoor category II 500 Day 945
Rate for 10 m2 3539.067
75/88
76. 12/4/2020
Analysis of Rates
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
Main data : e) Plastering with CM 1:5 - 20mm thick – 10 m2
Result for 10 m2 = Rs.5087.67/-
0.22 m3 Cement mortar 1:5 4762.16 1 m3 1047.67
2.2 nos Mason I class 950 Day 2090.00
0.5 nos Mazdoor category I 700 Day 350
3.2 nos Mazdoor category II 500 Day 1600
Rate for 10 m2 5087.67
76/88
77. 12/4/2020
Analysis of Rates
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
Problem 13
Prepare the data for painting new iron work one cost using ready
mixed enamel paint over red oxide priming cost – 10 m2
Material and labour required
a) Painting priming coat on new iron work – 10 m2
Ready mixed red oxide paint - 1.33litres
Painter I class - 0.7 nos
Sundries including brushes, soaps, putty etc.- L.S
b) Painting new iron work one coat using ready mixed enamel paint –
10 m2
Synthetic enamel paint - 1.33litres
Painter I class - 0.7 nos
Sundries including brushes, soaps, putty etc.- L.S
77/88
78. 12/4/2020
Analysis of Rates
.
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
c) Painting new iron work one coat using ready mixed enamel paint
over red oxide priming coat – 10 m2
Red oxide priming coat - 10 m2
Painting one coat using ready mixed enamel paint - 10 m2
Cost of materials and labour
Priming coat : Ready mixed red oxide paint - Rs.150/litre
Painting coat : Synthetic enamel paint - Rs.250/Litre
Painter I class - 800/Day
Sundries for brushes, soaps, putty etc,
a) Priming coat - Rs.150
b) Painting coat - Rs.200
78/88
79. 12/4/2020
Analysis of Rates
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
Sub data 1: Painting priming coat on new iron work – 10 m2
1.33
Litres
Ready mixed red oxide paint 150 litre 199.50
0.7 Nos Painter I class 800 Day 560.00
L.S
Sundries for brushes, soaps,
putty, etc.
150 L.S 150.00
Rate for 10 m2 909.500
79/88
80. 12/4/2020
Analysis of Rates
.
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
Sub data 2: Painting new iron work one coat using ready mixed
enamel paint – 10 m
1.33
Litres
Synthetic enamel paint 250 litre 332.50
0.7 Nos Painter I class 800 Day 560.00
L.S
Sundries for brushes, soaps,
putty, etc.
200 L.S 200.00
Rate for 10 m2 1092.50
80/88
81. 12/4/2020
Analysis of Rates
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
Main data: Painting new iron work one coat using ready mixed enamel
paint over red oxide priming coat – 10 m2
Result : Rate for 10 m2 = Rs.2002/-
10 m2 Red oxide priming coat 909.50 10 m2 909.500
10 m2 Painting one coat using
ready mixed enamel paint
1092.50 10 m2 1092.500
Rate for 10 m2 2002.00
81/88
82. 12/4/2020
Analysis of Rates
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
Problem 14 - White / colour washing over plastered surfaces
i) Prepare the data for white washing one coat on plastered surface -
10 m2 .
ii) Prepare the data for white washing two coat on plastered surface -
10 m2 .
iii) Prepare the data for colour washing one coat on plastered surface
- 10 m2 .
Material and labour required
a) White washing 1 coat with best lime on plastered surface – 10 m2
Shell lime (finely screened) - 0.05m3
Gum - LS
Painter II class -1.1nos
82/88
83. 12/4/2020
Analysis of Rates
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
a) White washing 1 coat with best lime on plastered surface – 10 m2
Mazdoor category I - 0.3 nos
Mazdoor category II - 1.9Nos
Sundries including brushes,etc - L.S
b) White washing 2 coat with best lime on plastered surface – 10 m2
Shell lime (finely screened) - 0.07m3
Gum - LS
Painter II class -1.6nos
Mazdoor category I - 0.5 nos
Mazdoor category II - 2.7Nos
Sundries including brushes,etc - L.S
83/88
84. 12/4/2020
Analysis of Rates
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
c) Colour washing 2 coats on plastered surface – 10 m2
White washing two coats as per worked previous data - 10 m2
Add 50 % of above rate - 10 m2
Cost of material and labour at site
Shell lime - 1500/ m3
Gum - 50 / 100m2
Sundries including brushes, etc - Rs.50
Painter II Class - 750 / Day
Mazdoor category I - 700 / Day
Mazdoor category II - 500 / Day
84/88
85. 12/4/2020
Analysis of Rates
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
Main data: White washing 1 coat with best lime on plastered surface –
10 m2
Result : Rate for 10 m2 = Rs.2160/-
0.05 m3 Shell lime 1500 m3 75.00
L.S Gum 50 100m2 50.00
1.1nos Painter II class 750 Day 825.00
0.3 nos Mazdoor category I 700 Day 210.00
1.9 nos Mazdoor category II 500 Day 950.00
L.S
Sundries including
brushes.etc.
50 L.S 50.00
Rate for 10 m2 2160.00
85/88
86. 12/4/2020
Analysis of Rates
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
Main data: White washing 2 coat with best lime on plastered surface –
10 m2
Result : Rate for 10 m2 = Rs.3105/-
0.07 m3 Shell lime 1500 m3 105.00
L.S Gum 50 100m2 50.00
1.6 nos Painter II class 750 Day 1200.00
0.5 nos Mazdoor category I 700 Day 350
2.7 nos Mazdoor category II 500 Day 1350.00
L.S
Sundries including
brushes.etc.
50 L.S 50.00
Rate for 10 m2 3105.00
86/88
87. 12/4/2020
Analysis of Rates
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
Main data: Colour washing 1 coat as per white washing 2 coats + 50%
of the above rate– 10 m2
Result : Rate for 10 m2 = Rs.4657.50/-
10m2 White washing two coats as
per worked previous data
3105 10m2 3105.00
10m2 Add 50 % of above rate 1552.5 10m2 1552.50
Rate for 10 m2 4657.50
87/88