SlideShare ist ein Scribd-Unternehmen logo
1 von 88
SNS COLLEGE OF ENGINEERING
An Autonomous Institutions
Accredited by NBA – AICTE and Accredited by NAAC – UGC with ‘A’ & ‘A+’Grade
Approved by AICTE, New Delhi & Affiliated to Anna University, Chennai
DEPARTMENT OF CIVIL ENGINEERING
COURSE NAME:
CE8701 - ESTIMATION, COSTING AND VALUATION ENGINEERING
IV YEAR / VII SEMESTER
Unit II: RATE ANALYSIS AND COSTING
Topic 1 : Analysis of Rates
12/4/2020
UNIT II - RATE ANALYSIS AND COSTING
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
Standard Data – Observed Data – Schedule of rates – Market rates –
Standard Data for Man Hours and Machineries for common civil works –
Rate Analysis for all Building works, canals, and Roads– Cost Estimates
(additional practice in class room using Computer softwares) - (Analysis of
rates for the item of work asked, the data regarding labour, rates of material
and rates of labour to be given in the Examination Question Paper)
2/88
12/4/2020
Analysis of Rates
.
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
Data
Method of determining the rate per unit of particular item of
work in a structure.
Including Quantities of materials required, cost of materials at
site, Labour required and labourer charge, lump sum if required.
The cost per unit of an item of work is called data.
Analysis of rates
 Quantities of items are calculated by detailed estimation.
Classification of Data
1. Standard data
2. Main data
3. Sub data
4. Observed data
5. Sundries and Lump sum provision.
3/88
12/4/2020
Analysis of Rates
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
1. Standard data
SOR 2019-2020.pdf
2. Main data
 Major item of works.
 Total cost of a particular item of work involving many sub works or
sub data
3.Sub data
 In main data some of the certain minor items (Sub data) are not
given directly.
 In this case the cost of minor works are prepared as sub data.
4/88
12/4/2020
Analysis of Rates
.
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
3.Sub data
Example:
Plastering with C.M (1:5) 12mm thick – 10 m2
a) Cement mortar 1:5 – 0.14 m3
b) Mason I class – 1.1 Nos
c) Mazdoor I class – 0.5 Nos
d) Mazdoor II class – 1.1 NoS
e) Lump sum / Sundries – L.S
5/88
12/4/2020
Analysis of Rates
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
Abstract of estimation cost table
6/88
12/4/2020
Analysis of Rates
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
Problem 1
Prepare the data for
1.Cement mortar
a) Cement Mortar 1:2 – 1 m3
b) Cement Mortar 1:3 – 1 m3
c) Cement Mortar 1:4 – 1 m3
d) Cement Mortar 1:5 – 1 m3
e) Cement Mortar 1:6 – 1 m3
2. Lime mortar and
a) Lime Mortar 1:1.5 – 1 m3
Sand cost at site - 1 m3
Lime – 0.67 m3
Mixing charge - 1 m3
7/88
12/4/2020
Analysis of Rates
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
b) Lime Mortar 1:2 – 1 m3
Sand cost at site - 1 m3
Lime – 0.50 m3
Mixing charge - 1 m3
3. Surkhi mortar.
a) Surkhi Mortar 1:0.5:1.5 – 1 m3
Lime- 0.5 m3
Surkhi – 0.25 m3
Sand – 0.75 m3
Grinding charges - 1 m3
b) Surkhi Mortar 1:0.5:1 – 1 m3
Lime- 0.67 m3
Surkhi – 0.33 m3
Sand – 0.67 m3 and Grinding charges - 1 m3
8/88
12/4/2020
Analysis of Rates
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
3. Surkhi mortar.
c) Surkhi Mortar 1:1:0.5 – 1 m3
Lime- 0.4 m3
Surkhi – 0.5 m3
Sand – 0.6 m3
Grinding charges - 1 m3
Cost of labour
1. Mixing cement mortar charges – 50/ m3
2. Grinding lime mortar charges – 100/ m3
9/88
12/4/2020
Analysis of Rates
.
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
Cost of materials and labour at site
Surkhi Mortar = Rs.580/ m3
Material Unit Cost (Rs) Lead (Km)
Rate for
lead/Km
(Rs)
Handling
charge (Rs)
Cement 1 bag 450 12 5 6
Lime 1 m3 1272 8 6 20
Sand 1 m3 1590 20 6 30
10/88
12/4/2020
Analysis of Rates
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
Solution
Lead statement for cost of material at site:
Surkhi Mortar = 580/ m3
Materia
l
Unit
Cost
(Rs)
1
Lead
(Km)
2
Rate for
lead/Km (Rs)
3
Handling
charge
(Rs)
4
Total (1+
(2x3) +4)
Cement 1 bag 450 12 5 6 516
Lime 1 m3 1272 8 6 20 1340
Sand 1 m3 1590 20 6 30 1740
11/88
12/4/2020
Analysis of Rates
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
1.Cement mortar
a) Cement Mortar 1:2 – 1 m3
1 m3 Sand cost at site 1740 1 m3 1740.00
720 kg
(1440/2)
Cement 516 50 kg 7430.40
1 m3 Mixing charge 50 1 m3 50.000
Rate for 1 m3 9220.40
12/88
12/4/2020
Analysis of Rates
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
1.Cement mortar
b) Cement Mortar 1:3 – 1 m3
1 m3 Sand cost at site 1740 1 m3 1740.00
480 kg
(1440/3)
Cement 516 50 kg 4953.60
1 m3 Mixing charge 50 1 m3 50.000
Rate for 1 m3 6743.60
13/88
12/4/2020
Analysis of Rates
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
1.Cement mortar
c) Cement Mortar 1:4 – 1 m3
1 m3 Sand cost at site 1740 1 m3 1740.00
360 kg
(1440/4)
Cement 516 50 kg 3715.20
1 m3 Mixing charge 50 1 m3 50.000
Rate for 1 m3 5505.20
14/88
12/4/2020
Analysis of Rates
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
1.Cement mortar
d) Cement Mortar 1:5 – 1 m3
1 m3 Sand cost at site 1740 1 m3 1740.00
288 kg
(1440/5)
Cement 516 50 kg 2972.16
1 m3 Mixing charge 50 1 m3 50.000
Rate for 1 m3 4762.16
15/88
12/4/2020
Analysis of Rates
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
1.Cement mortar
e) Cement Mortar 1:6 – 1 m3
1 m3 Sand cost at site 1740 1 m3 1740.00
240 kg
(1440/6)
Cement 516 50 kg 2476.80
1 m3 Mixing charge 50 1 m3 50.000
Rate for 1 m3 4266.80
16/88
12/4/2020
Analysis of Rates
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
2.Lime mortar
a) Lime Mortar 1:1.5 – 1 m3
1 m3 Sand cost at site 1740 1 m3 1740.00
0.67 m3 Lime 1340 1 m3 897.80
1 m3 Mixing charge 50 1 m3 50.00
Rate for 1 m3 2687.80
17/88
12/4/2020
Analysis of Rates
.
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
2.Lime mortar
b) Lime Mortar 1:2 – 1 m3
1 m3 Sand cost at site 1740 1 m3 1740.00
0.5 m3 Lime 1340 1 m3 670.00
1 m3 Mixing charge 50 1 m3 50.00
Rate for 1 m3 2460.00
18/88
12/4/2020
Analysis of Rates
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
3. Surkhi mortar.
a) Surkhi Mortar 1:0.5:1.5 – 1 m3
0.5 m3 Lime 1340 1 m3 670.00
0.25 m3 Surkhi 580 1 m3 145.00
0.75 m3 Sand 1740 1 m3 1305.00
1 m3 Grinding Charge 100 1 m3 100
Rate for 1 m3 2220.00
19/88
12/4/2020
Analysis of Rates
.
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
3. Surkhi mortar.
b) Surkhi Mortar 1:0.5:1 – 1 m3
0.67 m3 Lime 1340 1 m3 897.80
0.33 m3 Surkhi 580 1 m3 191.40
0.67 m3 Sand 1740 1 m3 1165.8
1 m3 Grinding Charge 100 1 m3 100
Rate for 1 m3 2355.00
20/88
12/4/2020
Analysis of Rates
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
3. Surkhi mortar.
c) Surkhi Mortar 1:1:0.5 – 1 m3
0.4 m3 Lime 1340 1 m3 536.00
0.5 m3 Surkhi 580 1 m3 290.00
0.6 m3 Sand 1740 1 m3 1044
1 m3 Grinding Charge 100 1 m3 100
Rate for 1 m3 1970.00
21/88
12/4/2020 SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
Happy Learning
22/88
12/4/2020
Analysis of Rates
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
Problem 2
Prepare the data for concrete broken stone using 40mm size in CM 1:4 -10
m3.
Material and labour required
a) Cement Mortar 1:4 - 1 m3
Sand cost at site - 1 m3
Cement – 360 kg
Mixing charges - 1 m3
b) Plain cement concrete in cement mortar 1:4:10 using 40mm size hard
broken stone -10 m3
Broken stone 40mm size cost at site - 9.5 m3
Cement mortar 1:4 as per worked sub data – 3.8 m3
Mason II Class -1.8 Nos
Mazdoor category I – 17.7 Nos.
Mazdoor category II – 14.1 Nos 23/88
12/4/2020
Analysis of Rates
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
Cost of Labour
Mixing charger for CM – Rs 50 / m3
Mason II class - Rs 900 / day
Mazdoor category I – 700 /day
Mazdoor category II – 500 / day
Cost of materials and labour at site
Material Unit
Cost
(Rs)
Lead
(Km)
Rate for
lead/Km
(Rs)
Handling
charge (Rs)
Cement 1 bag 450 12 5 6
Sand 1 m3 1590 20 6 30
Broken stone
40mm size
1 m3 710 20 7 35
24/88
12/4/2020
Analysis of Rates
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
Solution
Lead statement for cost of material at site:
Material Unit
Cost
(Rs)
1
Lead
(Km)
2
Rate for
lead/Km
(Rs)
3
Handling
charge
(Rs)
4
Total (1+
(2x3) +4)
Cement 1 bag 450 12 5 6 516
Sand 1 m3 1590 20 6 30 1740
Broken stone
40mm size
1 m3 710 20 7 35 885
25/88
12/4/2020
Analysis of Rates
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
Sub data
Cement mortar 1:4
1 m3 Sand cost at site 1740 1 m3 1740.00
360 kg
(1440/4)
Cement 516 50 kg 3715.20
1 m3 Mixing charge 50 1 m3 50.000
Rate for 1 m3 5505.20
26/88
12/4/2020
Analysis of Rates
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
Main data
Plain cement concrete in cement mortar 1:4:10 using 40mm size hard
broken stone -10 m3
Rate for 10 m3 = Rs.50387.260/-
9.5 m3 Broken stone 40mm size cost at site 885 1m3 8407.50
3.8 m3 Cement mortar 1:4 as per worked sub
data
5505.2 1m3 20919.76
1.8 Nos Mason II Class 900 Day 1620.00
17.7 Nos Mazdoor category I 700 Day 12390.00
14.1 Nos Maxdoor category II 500 Day 7050.00
Rate for 10 m3 50387.260
27/88
12/4/2020
Analysis of Rates
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
Problem 3
Prepare the data for flooring with cc 1:4:8 using 20mm size broken
stone 100mm thick and plastered over with CM 1:3, 15mm thick – 10
m2
Material and labour required
a) Cement Mortar 1:4 - 1 m3
Sand cost at site - 1 m3
Cement – 360 kg
Mixing charges - 1 m3
b) Cement Mortar 1:3 - 1 m3
Sand cost at site - 1 m3
Cement – 480 kg
Mixing charges - 1 m3
28/88
12/4/2020
Analysis of Rates
.
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
c) Cement concrete 1:4:8, 20mm size broken stone - 10 m3
Broken stone 20mm size - 9 m3
Cement Mortar 1:4 – 4.5 m3
Mason II class– 1.8 nos
Mazdoor category I – 17.7 nos
Mazdoor category II– 14.1 nos
d) Plastering with Cement mortar 1:3, 15mm thick - 10 m2
Cement Mortar 1:3 – 0.14 m3
Mason I class– 1.1 nos
Mazdoor category I – 0.5 nos
Mazdoor category II– 1.1 nos
29/88
12/4/2020
Analysis of Rates
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
e) Flooring with cement concrete 1:4:8 - 10 m2
Concrete broken stone in cement mortar 1:4 – 1 m3
Plastering with cement mortar 1:3, 15mm thick – 10 m2
Cost of material and labour at site in rupees
Cement - 10320 / tonne
Sand - 1740 / m3 (5000/unit in store)
Stone 20mm - 885 / m3 (2500/unit store)
Mason I class - 950 / Day
Mason II class - 900 / Day
Mazdoor class I - 700 / Day
Mazdoor class II- 500 / Day
Mixing charge - 50 / m3
30/88
12/4/2020
Analysis of Rates
.
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
Solution
Sub data 1 - Cement mortar 1:4 - 1 m3
1 m3 Sand cost at site 1740 1 m3 1740.00
360 kg
(1440/4)
Cement 10320 1000 kg 3715.20
1 m3 Mixing charge 50 1 m3 50.000
Rate for 1 m3 5505.20
31/88
12/4/2020
Analysis of Rates
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
Sub data 2 - Cement mortar 1:3 - 1 m3
1 m3 Sand cost at site 1740 1 m3 1740.00
480 kg
(1440/3)
Cement 10320 1000 kg 4953.60
1 m3 Mixing charge 50 1 m3 50.000
Rate for 1 m3 6743.60
32/88
12/4/2020
Analysis of Rates
.
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
Sub data 3 - Plastering with Cement mortar 1:3, 15mm thick - 10 m2
0.14 m3 Cement mortar 1:3 6743.60 m3 944.104
1.1 nos Mason I class 950 Day 1045
0.5 nos Mazdoor category I 700 Day 350
1.1 nos Mazdoor caterory II 500 Day 550
Rate for 10 m2 2889.10
33/88
12/4/2020
Analysis of Rates
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
Sub data 4 - Cement concrete 1:4:8, 20mm size broken stone - 10 m3
9.0 m3 Broken stone 20mm 885 m3 7965
4.5 m3 Cement mortar 1:4 5505.2 m3 24773.4
1.8 nos Mason II Class 900 Day 1620
17.7 nos Mazdoor category I 700 Day 12390
14.1 nos Mazdoor category II 500 Day 7050
Rate for 10 m3 53798.40
34/88
12/4/2020
Analysis of Rates
.
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
Main data - Flooring with cc1:4:8 using 20mm size broken stone
100mm thick and plastered over with CM 1:3, 15mm thick – 10 m2
Result - Rate for 10 m2 = Rs.8268.940/-
1 m3 Concrete broken stone in
CM 1:4
53798.40 10 m3 5379.84
10 m2 Plastering with CM (1:3)
15mm thick
2889.10 10 m2 2889.10
Rate for 10 m2 8268.940
35/88
12/4/2020
Analysis of Rates
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
Problem 4
Prepare the data for Mosaic tiled flooring using hydraulic pressed
mosaic tiles of 200x200x20mm size with CM 1:4, 20mm thick and
pointing with colour cement including polishing – 1 m2
Material and labour required
a) Cement Mortar 1:4 - 1 m3
Sand cost at site - 1 m3
Cement - 360 kg
Mixing charges - 1 m3
b) Mosaic tiled flooring, pointing and polishing - 10 m2
Mosaic tile 200x200x20mm – 250 nos.
Cement mortar 1:4 – 0.21 m3
Colour cement - 22kg
36/88
12/4/2020
Analysis of Rates
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
b) Mosaic tiled flooring, pointing and polishing - 10 m2
Mason I class - 1.1 nos.
Mason II Class - 2.7 nos
Mazdoor category I - 2.7 nos
Mazdoor category II - 5.4 nos
Polisher - 1.1 nos
Cost of material and labour at site in rupees
Cement - 516 / bag
Sand - 1740 / m3 (5000/unit in store)
Colour cement - 450 / bag
Mosaic tiles - 4500 / 100 nos
Mason I class - 950 / Day
37/88
12/4/2020
Analysis of Rates
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
Cost of material and labour at site in rupees
Mason II class - 900 / Day
Polisher - 800 / Day
Mazdoor class I - 700 / Day
Mazdoor class II- 500 / Day
Mixing charge - 50 / m3
Solution
Sub data 1 - Cement mortar 1:4 - 1 m3
1 m3 Sand cost at site 1740 1 m3 1740.00
360 kg Cement 10320 1000 kg 3715.20
1 m3 Mixing charge 50 1 m3 50.000
Rate for 1 m3 5505.20
38/88
12/4/2020
Analysis of Rates
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
Main data : Mosaic tiled flooring using hydraulic pressed mosaic tiles
of 200x200x20mm size with CM 1:4, 20mm thick and pointing with
colour cement including polishing – 1 m2
250 nos Mosaic tiles 4500 100 nos 11250
0.21 m3 CM 1:4 5505.2 1 m3 1156.092
22 kg Colour cement 450 Bag 198
1.1 nos Mason I class 950 Day 1045
2.7 nos Mason II class 900 Day 2430
2.7 nos Mazdoor I class 700 Day 1890
5.4 nos Mazdoor II class 500 Day 2700
1.1 nos Polisher 800 Day 880
Rate for 10 m2 21549.092
39/88
12/4/2020
Analysis of Rates
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
Rate of 10 m2 = Rs.21549.092/-
Rate of 1 m2 = 21549.092/10 = Rs.2154.909.
Result :
Rate of 1 m2 = Rs.2154.909.
Brick work calculation.
A) Brickwork in foundation
Rate will varying at based on the depth.
Ex – 1.5m to 4.5m, 4.5m to 9m
B) Brickwork in super structure
Rate will varying based on the height
Ex: Up to 4.5m and above 4.5m at every 1m height.
40/88
12/4/2020
Analysis of Rates
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
Problem 4
Prepare the data for brick work in foundation in cement mortar 1:5
mix using first class bricks– 1 m3
Material and labour required.
a) Cement Mortar 1:5 - 1 m3
Sand cost at site - 1 m3
Cement - 288 kg
Mixing charges - 1 m3
b) Brickwork in foundation using I class brick works in CM 1:5 - 10 m3
Bricks – 19 x 9 x 9 cm - 5000 nos
Cement mortar 1:5 - 2.2 m3
Mason I class - 3.5 nos.
41/88
12/4/2020
Analysis of Rates
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
b) Brickwork in foundation using I class brick works in CM 1:5 - 10 m3
Mason II Class - 10.6 nos
Mazdoor category I - 7.1 nos
Mazdoor category II - 21.2 nos
Cost of material and labour at site in rupees
Cement - 516 / bag
Sand - 1740 / m3 (5000/unit in store)
Bricks I class - 8 / no
Mason I class - 950 / Day
Mason II class - 900 / Day
Mazdoor class I - 700 / Day
Mazdoor class II- 500 / Day
Mixing charge - 50 / m3
42/88
12/4/2020
Analysis of Rates
.
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
Solution:
Sub data 1 - Cement mortar 1:5 - 1 m3
1 m3 Sand cost at site 1740 1 m3 1740.00
288 kg
(1440/5)
Cement 516 50 kg 2972.16
1 m3 Mixing charge 50 1 m3 50.000
Rate for 1 m3 4762.16
43/88
12/4/2020
Analysis of Rates
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
Main data: Brickwork in foundation using I class brick works in CM
1:5 - 10 m3
Result : Rate for 1 m3 = Rs.7891.17/-
5000 nos Bricks 19x9x9 cm 8 No 40000
2.2 m3 CM 1:5 4762.16 m3 10476.75
3.5 nos Mason I class 950 Day 3325
10.6 nos Mason II class 900 Day 9540
7.1 nos Mazdoor I category 700 Day 4970
21.2 nos Mazdoor II category 500 Day 10600
Rate for 10 m3 78911.75
44/88
12/4/2020
Analysis of Rates
.
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
Problem 5 (Tutorial problem)
Prepare the data for brick work in super structure using first class
brick in cement mortar 1:5 – 1 m3
Material and labour required.
a) Brickwork with CM 1:5 - 10 m3
Bricks – - 5000 nos
Cement mortar 1:5 - 1.4 m3
Mason I class - 7.0 nos.
Mason II class - 8.1 nos.
Mazdoor I class - 8.1 nos.
Mazdoor II class - 8.4 nos.
45/88
12/4/2020
Analysis of Rates
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
b)Cost of material and labour at site in rupees
Cement - 516 / bag
Sand - 1740 / m3 (5000/unit in store)
Bricks I class - 8 / no
Mason I class - 950 / Day
Mason II class - 900 / Day
Mazdoor class I - 700 / Day
Mazdoor class II- 500 / Day
Mixing charge - 50 / m3
46/88
12/4/2020
Analysis of Rates
.
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
Problem 6 (Tutorial problem)
Prepare the data for brick work in partition using second class brick
in cement mortar 1:3 – 1 m3
Material and labour required.
a) Cement Mortar 1:3 - 1 m3
Sand cost at site - 1 m3
Cement - 480 kg
Mixing charges - 1 m3
b) Brickwork with CM 1:3 - 10 m3
Bricks II class - 7500 nos
Cement mortar 1:3 - 2.7 m3
Mason I class - 3.5 nos.
47/88
12/4/2020
Analysis of Rates
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
b) Brickwork with CM 1:3 - 10 m3
Mason II class - 7.1 nos.
Mazdoor I class - 7.1 nos.
Mazdoor II class - 14.1 nos.
Cost of material and labour at site in rupees
Cement - 516 / bag
Sand - 1740 / m3 (5000/unit in store)
Bricks I class - 8 / no
Mason I class - 950 / Day
Mason II class - 900 / Day
Mazdoor class I - 700 / Day
Mazdoor class II- 500 / Day
Mixing charge - 50 / m3
48/88
12/4/2020
Analysis of Rates
.
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
Problem 7 (Tutorial problem)
Prepare the data for coursed rubble masonry second sort in cement
mortar 1:5 – 1 m3
Material and labour required.
a) Cement Mortar 1:5 - 1 m3
Sand cost at site - 1 m3
Cement - 288 kg
Mixing charges - 1 m3
b) Coursed rubble masonry second sort in CM 1:5- 10 m3
Course rubble stone - 6 m3
Rough stone - 5 m3
Cement mortar 1:5 - 3.2 m3
49/88
12/4/2020
Analysis of Rates
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
b) Coursed rubble masonry second sort in CM 1:5- 10 m3
Mason I class - 7.1 nos.
Mason II class - 17.6 nos.
Mazdoor II class - 14.1 nos.
Cost of material and labour at site in rupees
Cement - 516 / bag
Sand - 1740 / m3 (5000/unit in store)
Course rubbled stone - 915 / m3
Rough stone - 975 / m3
Mason I class - 950 / Day
Mason II class - 900 / Day
Mazdoor class II - 500 / Day
Mixing charge - 50 / m3
50/88
12/4/2020
Analysis of Rates
.
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
Problem 8
Prepare the data for weathering course with broken brick in pure
slaked lime over RCC roof slab - 10 m3
Material and labour required.
a) Weathering course with 20mm broken brick - 10 m3
Broken brick 20mm size - 12.8 m3
Slaked lime - 5 m3
Mason I class - 1.8 nos
Mazdoor I class - 17.7 nos
Mazdoor II class - 14.1 nos
51/88
12/4/2020
Analysis of Rates
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
b) Cost of the materials and labours at site
Broken brick 20mm size - 750/ m3
Slaked lime - 1100/ m3
Mason I class - 920/ Day
Mazdoor I class - 700 / Day
Mazdoor II class - 500 / Day
52/88
12/4/2020
Analysis of Rates
.
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
Solution
Main data : Weathering course with 20mm broken brick - 10 m3
Result : Rate for 10 m3 = Rs.36250/-
12.8m3 Broken Bricks 20mm 750 1m3 9600
5m3 Slaked lime 1100 1 m3 5500
1.8 nos Mason I class 950 Day 1710
17.7 nos Mazdoor I category 700 Day 12390
14.1 nos Mazdoor II category 500 Day 7050
Rate for 10 m3 36250
53/88
12/4/2020
Analysis of Rates
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
Problem 9
Prepare the data for RCC roof slab of size 4 x 3 x 0.1 m of mix 1:2:4
using 20mm hard broken stone with reinforcement at 80kg/m3 of
concrete including cutting, bending , tying and centering curing etc. –
1 m3
Material and labour required
a) Cement concrete 1:2:4 using 20mm hard broken stone - 10 m3
Broken stone - 9 m3
Cement - 3240 kg
Sand - 4.5 m3
Mason I class - 3.5 nos
Mazdoor I grade - 21.2 nos.
Mazdoor II grade - 35.8 nos
54/88
12/4/2020
Analysis of Rates
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
b) RCC roof 4 x3 x0.12m with reinforcement 80kg/ m3 of concrete
including cutting, bending, tying etc., - 1 m3
Cement concrete 1:2:4 - 1 m3
Steel - 80kg/ m3
Binding wire - 1 % of steel required
Cutting, bending and tying - as steel required
Centering - as required + 20 % extra for sides.
c) Cost of material and labour at site in rupees
Cement - 516 / bag
Sand - 1740 / m3 (5000/unit in store)
Broken brick 20mm size - 750/ m3
Steel - 55000/ tonne
Binding wire - 150 / kg
55/88
12/4/2020
Analysis of Rates
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
c) Cost of material and labour at site in rupees
Mason I class - 950 / day
Mason II class - 900 / day
Mazdoor I grade - 700 / day
Mazdoor II grade - 500 / day
Cutting, bending and tying – 50 / kg
Centering charge - 300 / m2
Solution
Centering Area = (L x B ) + 20 % for sides or L (B+2D)
= ( 4x 3) + (20/100) x (4x3)
= 14.4 m2
56/88
12/4/2020
Analysis of Rates
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
Sub data: CC 1:2:4 using 20mm hard broken stone – 10 m3
9 m3 Broken Bricks 20mm 750 1m3 6750
4.5m3 Sand 1740 1 m3 7830
3240 kg Cement 516 Bag 33436.8
3.5 nos Mason I class 950 Day 3325
21.2 nos Mazdoor I category 700 Day 14840
35.8 nos Mazdoor II category 500 Day 17900
Rate for 10 m3 84081.8
57/88
12/4/2020
Analysis of Rates
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
Main data: RCC roof 4 x3 x0.12m with reinforcement 80kg/ m3 of
concrete including cutting, bending, tying etc., - 1 m3
Result : Rate for 1 m3 = Rs. 21248.18/-
1 m3 CC 1:2:4 84081.8 10m3 8408.18
80kg Steel 55000 tonne 4400.00
0.8 kg Binding wire (1% of steel) 150 kg 120.00
80kg Cutting, Bending & tying 50 kg 4000.00
14.4 m2 Centering 300 1 m2 4320.00
Rate for 1 m3 21248.18
58/88
12/4/2020
Analysis of Rates
.
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
Problem 10
Prepare the data for RCC beam of size 300 x 450mm with 1:2:4 mix
using 20mm hard broken stone with reinforcement of 150kg/m3
including centering, shuttering, etc. – 1 m3
Material and labour required
a) Cement concrete 1:2:4 using 20mm hard broken stone - 10 m3
Broken stone - 9 m3
Cement - 2.25 m3
Sand - 4.5 m3
Mason I class - 3.5 nos
Mazdoor I grade - 21.2 nos.
Mazdoor II grade - 35.3 nos
59/88
12/4/2020
Analysis of Rates
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
b) RCC beam of size 300 x 450mm with 1:2:4 mix using 20mm hard
broken stone with reinforcement of 150kg/m3 including centering,
shuttering, etc. – 1 m3
Cement concrete 1:2:4 - 1 m3
Steel - 150 kg/ m3
Binding wire - 1 % of steel required
Cutting, bending and tying - as steel required
Centering - as required
c) Cost of material and labour at site in rupees
Cement - 516 / bag
Sand - 1740 / m3 (5000/unit in store)
Broken brick 20mm size - 750/ m3
Steel - 55000/ tonne
60/88
12/4/2020
Analysis of Rates
.
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
c) Cost of material and labour at site in rupees
Binding wire - 150 / kg
Mason I class - 950 / day
Mason II class - 900 / day
Mazdoor I grade - 700 / day
Mazdoor II grade - 500 / day
Cutting, bending and tying – 50 / kg
Centering charge - 300 / m2
Solution
Centering Area = L (B+2D)
Volume = L x B x D , L = 1 m3 / (0.3 x 0.45) = 7.41m.
Centering Area = L (B+2D) = 7.41 (0.3+2x0.45) = 8.832 m2
61/88
12/4/2020
Analysis of Rates
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
Sub data: CC 1:2:4 using 20mm hard broken stone – 10 m3
9 m3 Broken Bricks 20mm 750 1m3 6750
4.5m3 Sand 1740 1 m3 7830
(2.25 x 1440)
3240 kg
Cement 516 Bag 33436.8
3.5 nos Mason I class 950 Day 3325
21.2 nos Mazdoor I category 700 Day 14840
35.3 nos Mazdoor II category 500 Day 17650
Rate for 10 m3 83831.8
62/88
12/4/2020
Analysis of Rates
.
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
Main data: RCC beam of size 300 x 450mm with 1:2:4 mix using
20mm hard broken stone with reinforcement of 150kg/m3 including
centering, shuttering, etc. – 1 m3
Result : Rate for 1 m3 = Rs. 27007.78/-
1 m3 CC 1:2:4 83831.8 10m3 8383.18
150 kg Steel 55000 tonne 8250.00
1.5 kg Binding wire (1% of steel) 150 kg 225.00
150kg Cutting, Bending & tying 50 kg 7500.00
8.832 m2 Centering 300 1 m2 2649.60
Rate for 1 m3 27007.78
63/88
12/4/2020
Analysis of Rates
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
Problem 11 (Tutorial problem)
Prepare the data for RCC column of size 300x300mm with mix of 1:2:4
using 20mm hard broken stone with reinforcement of 160 kg/m3
including centering, shuttering, curing, etc. – 1 m run.
Material and labour required
a) Cement concrete 1:2:4 using 20mm hard broken stone - 10 m3
Broken stone - 9 m3
Cement - 2.25 m3
Sand - 4.5 m3
Mason I class - 3.5 nos
Mazdoor I grade - 21.2 nos.
Mazdoor II grade - 35.3 nos
64/88
12/4/2020
Analysis of Rates
.
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
b) RCC 1:2:4 mix column – 1mrun.
Cement concrete 1:2:4 - 0.09 m3 (0.3 x 0.3 x 1)
Steel - 14.56 kg (0.091 m3 x 160 kg/ m3)
Binding wire - 1 % of steel required
Cutting, bending and tying - as steel required
Centering - as required
c) Cost of material and labour at site in rupees
Cement - 516 / bag
Sand - 1740 / m3 (5000/unit in store)
Broken brick 20mm size - 750/ m3
Steel - 55000/ tonne
65/88
12/4/2020
Analysis of Rates
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
c) Cost of material and labour at site in rupees
Binding wire - 150 / kg
Mason I class - 950 / day
Mason II class - 900 / day
Mazdoor I grade - 700 / day
Mazdoor II grade - 500 / day
Cutting, bending and tying – 50 / kg
Centering charge - 300 / m2
Solution
Centering Area for 1m run = (0.3 x 4 ) x 1
= 1.2m2
66/88
12/4/2020
Analysis of Rates
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
Problem 12
Prepare the data for the following items of plastering over brick
masonry in cement mortar of given mix.
a) Plastering with CM 1:3 - 12mm thick – 10 m2
b) Plastering with CM 1:3 - 20mm thick – 10 m2
c) Plastering with CM 1:5 - 12mm thick – 10 m2
d) Plastering with CM 1:5 - 15mm thick – 10 m2
e) Plastering with CM 1:5 - 20mm thick – 10 m2
Material and labour required
a) Plastering with CM 1:3 - 12mm thick – 10 m2
Cement mortar 1:3 - 0.14 m3 , Mason I class -1.1 nos
Mazdoor category I - 0.5 nos and Mazdoor category II- 1.1 nos
67/88
12/4/2020
Analysis of Rates
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
b) Plastering with CM 1:3 - 20mm thick – 10 m2
Cement mortar 1:3 - 0.22 m3
Mason I class -2.2 nos
Mazdoor category I - 0.5 nos
Mazdoor category II - 3.2 nos
c) Plastering with CM 1:5 - 12mm thick – 10 m2
Cement mortar 1:5 - 0.14 m3
Mason I class -1.1 nos
Mazdoor category I - 0.5 nos
Mazdoor category II - 1.1 nos
d) Plastering with CM 1:5 - 15mm thick – 10 m2
Cement mortar 1:5 - 0.17 m3
Mason I class -1.51 nos
Mazdoor category I - 0.5 nos & Mazdoor category II- 1.89 nos
68/88
12/4/2020
Analysis of Rates
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
e) Plastering with CM 1:5 - 20mm thick – 10 m2
Cement mortar 1:5 - 0.22 m3
Mason I class -2.2 nos
Mazdoor category I - 0.5 nos
Mazdoor category II - 3.2 nos
Cost of materials and Labours at site
Cement - 516 / bag
Sand - 1740 / m3
Mixing charger for CM - Rs 50 / m3
Mason I class - Rs 950/ day
Mason II class - Rs 900 / day
Mazdoor category I - 700 /day
Mazdoor category II - 500 / day
69/88
12/4/2020
Analysis of Rates
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
Sub data 1 : Cement Mortar 1:3 – 1 m3
1 m3 Sand cost at site 1740 1 m3 1740.00
480 kg
(1440/3)
Cement 516 50 kg 4953.60
1 m3 Mixing charge 50 1 m3 50.000
Rate for 1 m3 6743.60
70/88
12/4/2020
Analysis of Rates
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
Sub data 1 : Cement Mortar 1:5 – 1 m3
1 m3 Sand cost at site 1740 1 m3 1740.00
288 kg
(1440/5)
Cement 516 50 kg 2972.16
1 m3 Mixing charge 50 1 m3 50.000
Rate for 1 m3 4762.16
71/88
12/4/2020
Analysis of Rates
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
Main data : a) Plastering with CM 1:3 - 12mm thick – 10 m2
Result for 10 m2 = Rs.2889.104/-
0.14 m3 Cement mortar 1:3 6743.6 1 m3 944.104
1.1 nos Mason I class 950 Day 1045.00
0.5 nos Mazdoor category I 700 Day 350
1.1 nos Mazdoor category II 500 Day 550
Rate for 10 m2 2889.104
72/88
12/4/2020
Analysis of Rates
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
Main data : b) Plastering with CM 1:3 - 20 mm thick – 10 m2
Result for 10 m2 = Rs.5523.592/-
0.22 m3 Cement mortar 1:3 6743.6 1 m3 1483.592
2.2 nos Mason I class 950 Day 2090.00
0.5 nos Mazdoor category I 700 Day 350
3.2 nos Mazdoor category II 500 Day 1600
Rate for 10 m2 5523.592
73/88
12/4/2020
Analysis of Rates
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
Main data : c) Plastering with CM 1:5 - 12mm thick – 10 m2
Result for 10 m2 = Rs.2611.702/-
0.14 m3 Cement mortar 1:5 4762.16 1 m3 666.702
1.1 nos Mason I class 950 Day 1045.00
0.5 nos Mazdoor category I 700 Day 350
1.1 nos Mazdoor category II 500 Day 550
Rate for 10 m2 2611.702
74/88
12/4/2020
Analysis of Rates
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
Main data : d) Plastering with CM 1:5 - 15 mm thick – 10 m2
Result for 10 m2 = Rs.3539.067/-
0.17 m3 Cement mortar 1:3 4762.16 1 m3 809.567
1.51 nos Mason I class 950 Day 1434.50
0.5 nos Mazdoor category I 700 Day 350
1.89 nos Mazdoor category II 500 Day 945
Rate for 10 m2 3539.067
75/88
12/4/2020
Analysis of Rates
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
Main data : e) Plastering with CM 1:5 - 20mm thick – 10 m2
Result for 10 m2 = Rs.5087.67/-
0.22 m3 Cement mortar 1:5 4762.16 1 m3 1047.67
2.2 nos Mason I class 950 Day 2090.00
0.5 nos Mazdoor category I 700 Day 350
3.2 nos Mazdoor category II 500 Day 1600
Rate for 10 m2 5087.67
76/88
12/4/2020
Analysis of Rates
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
Problem 13
Prepare the data for painting new iron work one cost using ready
mixed enamel paint over red oxide priming cost – 10 m2
Material and labour required
a) Painting priming coat on new iron work – 10 m2
Ready mixed red oxide paint - 1.33litres
Painter I class - 0.7 nos
Sundries including brushes, soaps, putty etc.- L.S
b) Painting new iron work one coat using ready mixed enamel paint –
10 m2
Synthetic enamel paint - 1.33litres
Painter I class - 0.7 nos
Sundries including brushes, soaps, putty etc.- L.S
77/88
12/4/2020
Analysis of Rates
.
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
c) Painting new iron work one coat using ready mixed enamel paint
over red oxide priming coat – 10 m2
Red oxide priming coat - 10 m2
Painting one coat using ready mixed enamel paint - 10 m2
Cost of materials and labour
Priming coat : Ready mixed red oxide paint - Rs.150/litre
Painting coat : Synthetic enamel paint - Rs.250/Litre
Painter I class - 800/Day
Sundries for brushes, soaps, putty etc,
a) Priming coat - Rs.150
b) Painting coat - Rs.200
78/88
12/4/2020
Analysis of Rates
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
Sub data 1: Painting priming coat on new iron work – 10 m2
1.33
Litres
Ready mixed red oxide paint 150 litre 199.50
0.7 Nos Painter I class 800 Day 560.00
L.S
Sundries for brushes, soaps,
putty, etc.
150 L.S 150.00
Rate for 10 m2 909.500
79/88
12/4/2020
Analysis of Rates
.
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
Sub data 2: Painting new iron work one coat using ready mixed
enamel paint – 10 m
1.33
Litres
Synthetic enamel paint 250 litre 332.50
0.7 Nos Painter I class 800 Day 560.00
L.S
Sundries for brushes, soaps,
putty, etc.
200 L.S 200.00
Rate for 10 m2 1092.50
80/88
12/4/2020
Analysis of Rates
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
Main data: Painting new iron work one coat using ready mixed enamel
paint over red oxide priming coat – 10 m2
Result : Rate for 10 m2 = Rs.2002/-
10 m2 Red oxide priming coat 909.50 10 m2 909.500
10 m2 Painting one coat using
ready mixed enamel paint
1092.50 10 m2 1092.500
Rate for 10 m2 2002.00
81/88
12/4/2020
Analysis of Rates
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
Problem 14 - White / colour washing over plastered surfaces
i) Prepare the data for white washing one coat on plastered surface -
10 m2 .
ii) Prepare the data for white washing two coat on plastered surface -
10 m2 .
iii) Prepare the data for colour washing one coat on plastered surface
- 10 m2 .
Material and labour required
a) White washing 1 coat with best lime on plastered surface – 10 m2
Shell lime (finely screened) - 0.05m3
Gum - LS
Painter II class -1.1nos
82/88
12/4/2020
Analysis of Rates
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
a) White washing 1 coat with best lime on plastered surface – 10 m2
Mazdoor category I - 0.3 nos
Mazdoor category II - 1.9Nos
Sundries including brushes,etc - L.S
b) White washing 2 coat with best lime on plastered surface – 10 m2
Shell lime (finely screened) - 0.07m3
Gum - LS
Painter II class -1.6nos
Mazdoor category I - 0.5 nos
Mazdoor category II - 2.7Nos
Sundries including brushes,etc - L.S
83/88
12/4/2020
Analysis of Rates
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
c) Colour washing 2 coats on plastered surface – 10 m2
White washing two coats as per worked previous data - 10 m2
Add 50 % of above rate - 10 m2
Cost of material and labour at site
Shell lime - 1500/ m3
Gum - 50 / 100m2
Sundries including brushes, etc - Rs.50
Painter II Class - 750 / Day
Mazdoor category I - 700 / Day
Mazdoor category II - 500 / Day
84/88
12/4/2020
Analysis of Rates
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
Main data: White washing 1 coat with best lime on plastered surface –
10 m2
Result : Rate for 10 m2 = Rs.2160/-
0.05 m3 Shell lime 1500 m3 75.00
L.S Gum 50 100m2 50.00
1.1nos Painter II class 750 Day 825.00
0.3 nos Mazdoor category I 700 Day 210.00
1.9 nos Mazdoor category II 500 Day 950.00
L.S
Sundries including
brushes.etc.
50 L.S 50.00
Rate for 10 m2 2160.00
85/88
12/4/2020
Analysis of Rates
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
Main data: White washing 2 coat with best lime on plastered surface –
10 m2
Result : Rate for 10 m2 = Rs.3105/-
0.07 m3 Shell lime 1500 m3 105.00
L.S Gum 50 100m2 50.00
1.6 nos Painter II class 750 Day 1200.00
0.5 nos Mazdoor category I 700 Day 350
2.7 nos Mazdoor category II 500 Day 1350.00
L.S
Sundries including
brushes.etc.
50 L.S 50.00
Rate for 10 m2 3105.00
86/88
12/4/2020
Analysis of Rates
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
Main data: Colour washing 1 coat as per white washing 2 coats + 50%
of the above rate– 10 m2
Result : Rate for 10 m2 = Rs.4657.50/-
10m2 White washing two coats as
per worked previous data
3105 10m2 3105.00
10m2 Add 50 % of above rate 1552.5 10m2 1552.50
Rate for 10 m2 4657.50
87/88
Thank You
HAPPY LEARNING

Weitere ähnliche Inhalte

Was ist angesagt?

Analysis of rates for labour and material
Analysis of rates for labour and materialAnalysis of rates for labour and material
Analysis of rates for labour and materialALI HYDER GADHI
 
Rate analysis road work in Estimation & Rate Analyisis
Rate analysis road work in Estimation & Rate AnalyisisRate analysis road work in Estimation & Rate Analyisis
Rate analysis road work in Estimation & Rate AnalyisisJaptyesh Singh
 
Valuation - Estimation, Costing and Valuation Engineering
Valuation - Estimation, Costing and Valuation EngineeringValuation - Estimation, Costing and Valuation Engineering
Valuation - Estimation, Costing and Valuation EngineeringShanmugasundaram N
 
Mode of measurement, rules for deduction of plastering & brickwork
Mode of measurement, rules for deduction of plastering & brickworkMode of measurement, rules for deduction of plastering & brickwork
Mode of measurement, rules for deduction of plastering & brickworkAshwiniChaudhari13
 
Supplementary cementitious materials origin from agricultural wastes new
Supplementary cementitious materials origin from agricultural wastes newSupplementary cementitious materials origin from agricultural wastes new
Supplementary cementitious materials origin from agricultural wastes newSaibas S
 
Durability of concrete
Durability of concreteDurability of concrete
Durability of concreteRajesh Prasad
 
Durability and Permeability of Concrete
Durability  and Permeability of ConcreteDurability  and Permeability of Concrete
Durability and Permeability of ConcreteGAURAV. H .TANDON
 
5#rate analysis problems
5#rate analysis   problems5#rate analysis   problems
5#rate analysis problemsLIJI A
 
Quality control of concrete
Quality control of concreteQuality control of concrete
Quality control of concreteGaurang Kakadiya
 
Contracts - Estimation, Costing and Valuation Engineering
Contracts - Estimation, Costing and Valuation EngineeringContracts - Estimation, Costing and Valuation Engineering
Contracts - Estimation, Costing and Valuation EngineeringShanmugasundaram N
 
Lec 9 center line method
Lec 9 center line methodLec 9 center line method
Lec 9 center line methodmalang1214
 
Types of estimate - Estimation, Costing and Valuation Engineering
Types of estimate - Estimation, Costing and Valuation EngineeringTypes of estimate - Estimation, Costing and Valuation Engineering
Types of estimate - Estimation, Costing and Valuation EngineeringShanmugasundaram N
 
Estimating part 1
Estimating part 1Estimating part 1
Estimating part 1ArunRavi43
 

Was ist angesagt? (20)

Analysis of rates for labour and material
Analysis of rates for labour and materialAnalysis of rates for labour and material
Analysis of rates for labour and material
 
Rate analysis road work in Estimation & Rate Analyisis
Rate analysis road work in Estimation & Rate AnalyisisRate analysis road work in Estimation & Rate Analyisis
Rate analysis road work in Estimation & Rate Analyisis
 
Types of estimates
Types of estimatesTypes of estimates
Types of estimates
 
Valuation - Estimation, Costing and Valuation Engineering
Valuation - Estimation, Costing and Valuation EngineeringValuation - Estimation, Costing and Valuation Engineering
Valuation - Estimation, Costing and Valuation Engineering
 
Concrete Mix Design
Concrete Mix DesignConcrete Mix Design
Concrete Mix Design
 
Rate analysis
Rate analysisRate analysis
Rate analysis
 
Mode of measurement, rules for deduction of plastering & brickwork
Mode of measurement, rules for deduction of plastering & brickworkMode of measurement, rules for deduction of plastering & brickwork
Mode of measurement, rules for deduction of plastering & brickwork
 
Supplementary cementitious materials origin from agricultural wastes new
Supplementary cementitious materials origin from agricultural wastes newSupplementary cementitious materials origin from agricultural wastes new
Supplementary cementitious materials origin from agricultural wastes new
 
Durability of concrete
Durability of concreteDurability of concrete
Durability of concrete
 
Durability and Permeability of Concrete
Durability  and Permeability of ConcreteDurability  and Permeability of Concrete
Durability and Permeability of Concrete
 
Approximate estimate
Approximate estimateApproximate estimate
Approximate estimate
 
Approximate estimate
Approximate estimateApproximate estimate
Approximate estimate
 
5#rate analysis problems
5#rate analysis   problems5#rate analysis   problems
5#rate analysis problems
 
Quality control of concrete
Quality control of concreteQuality control of concrete
Quality control of concrete
 
Contracts - Estimation, Costing and Valuation Engineering
Contracts - Estimation, Costing and Valuation EngineeringContracts - Estimation, Costing and Valuation Engineering
Contracts - Estimation, Costing and Valuation Engineering
 
Contracts
ContractsContracts
Contracts
 
Estimating & Costing - I
Estimating & Costing - IEstimating & Costing - I
Estimating & Costing - I
 
Lec 9 center line method
Lec 9 center line methodLec 9 center line method
Lec 9 center line method
 
Types of estimate - Estimation, Costing and Valuation Engineering
Types of estimate - Estimation, Costing and Valuation EngineeringTypes of estimate - Estimation, Costing and Valuation Engineering
Types of estimate - Estimation, Costing and Valuation Engineering
 
Estimating part 1
Estimating part 1Estimating part 1
Estimating part 1
 

Ähnlich wie Rate analysis and costing - Estimation, Costing and Valuation Engineering

IRJET-Mix Proportion of Materials in Pervious Concrete
IRJET-Mix Proportion of Materials in Pervious ConcreteIRJET-Mix Proportion of Materials in Pervious Concrete
IRJET-Mix Proportion of Materials in Pervious ConcreteIRJET Journal
 
USE OF MERAUKE FINE AGGREGATE AND DIGOEL BOVEN COARSE AGGREGATE ON CONCRETE C...
USE OF MERAUKE FINE AGGREGATE AND DIGOEL BOVEN COARSE AGGREGATE ON CONCRETE C...USE OF MERAUKE FINE AGGREGATE AND DIGOEL BOVEN COARSE AGGREGATE ON CONCRETE C...
USE OF MERAUKE FINE AGGREGATE AND DIGOEL BOVEN COARSE AGGREGATE ON CONCRETE C...IAEME Publication
 
IRJET- Utilization of STP By–Product as a Raw Material in Concrete
IRJET- Utilization of STP By–Product as a Raw Material in ConcreteIRJET- Utilization of STP By–Product as a Raw Material in Concrete
IRJET- Utilization of STP By–Product as a Raw Material in ConcreteIRJET Journal
 
Utilisation of RAP (Reclaimed Asphalt Pavement) Material Obtained By Milling ...
Utilisation of RAP (Reclaimed Asphalt Pavement) Material Obtained By Milling ...Utilisation of RAP (Reclaimed Asphalt Pavement) Material Obtained By Milling ...
Utilisation of RAP (Reclaimed Asphalt Pavement) Material Obtained By Milling ...IJERA Editor
 
Partial Replacement of Sand by Quarry Dust in Construction of Box Culvert
Partial Replacement of Sand by Quarry Dust in Construction of Box CulvertPartial Replacement of Sand by Quarry Dust in Construction of Box Culvert
Partial Replacement of Sand by Quarry Dust in Construction of Box CulvertIRJET Journal
 
“Experimental Investigation of Green Concrete Paver Block by Partial Replacem...
“Experimental Investigation of Green Concrete Paver Block by Partial Replacem...“Experimental Investigation of Green Concrete Paver Block by Partial Replacem...
“Experimental Investigation of Green Concrete Paver Block by Partial Replacem...IRJET Journal
 
IRJET- Application of Rubber Properties in Clay Bricks
IRJET- Application of Rubber Properties in Clay BricksIRJET- Application of Rubber Properties in Clay Bricks
IRJET- Application of Rubber Properties in Clay BricksIRJET Journal
 
IRJET- Effect of Manufactured Sand on Mechanical Properties of Concrete
IRJET-  	  Effect of Manufactured Sand on Mechanical Properties of ConcreteIRJET-  	  Effect of Manufactured Sand on Mechanical Properties of Concrete
IRJET- Effect of Manufactured Sand on Mechanical Properties of ConcreteIRJET Journal
 
A Study on Cement Stabilized Conventional Waste and Marginal Material for Pav...
A Study on Cement Stabilized Conventional Waste and Marginal Material for Pav...A Study on Cement Stabilized Conventional Waste and Marginal Material for Pav...
A Study on Cement Stabilized Conventional Waste and Marginal Material for Pav...IRJET Journal
 
Fundamentals of Estimating and Costing
 Fundamentals of Estimating and Costing Fundamentals of Estimating and Costing
Fundamentals of Estimating and CostingGanesh Tatikonda
 
chapter1-210122051628.pdf
chapter1-210122051628.pdfchapter1-210122051628.pdf
chapter1-210122051628.pdfDeepak37004
 
IRJET - The Use of Waste Plastic in the Manufacture of Bricks
IRJET - The Use of Waste Plastic in the Manufacture of BricksIRJET - The Use of Waste Plastic in the Manufacture of Bricks
IRJET - The Use of Waste Plastic in the Manufacture of BricksIRJET Journal
 
IRJET- Mix Design Steps for Self-Compacting Concrete
IRJET- Mix Design Steps for Self-Compacting ConcreteIRJET- Mix Design Steps for Self-Compacting Concrete
IRJET- Mix Design Steps for Self-Compacting ConcreteIRJET Journal
 

Ähnlich wie Rate analysis and costing - Estimation, Costing and Valuation Engineering (20)

Bhadanis CONCRETE WORK ESTIMATION GUIDE
Bhadanis CONCRETE WORK ESTIMATION GUIDE Bhadanis CONCRETE WORK ESTIMATION GUIDE
Bhadanis CONCRETE WORK ESTIMATION GUIDE
 
ROAD WORK ESTIMATION GUIDE MATERIAL BHADANIS
ROAD WORK ESTIMATION GUIDE MATERIAL BHADANISROAD WORK ESTIMATION GUIDE MATERIAL BHADANIS
ROAD WORK ESTIMATION GUIDE MATERIAL BHADANIS
 
BHADANIS - PLASTER WORK ESTIMATION GUIDE
BHADANIS - PLASTER WORK ESTIMATION GUIDE BHADANIS - PLASTER WORK ESTIMATION GUIDE
BHADANIS - PLASTER WORK ESTIMATION GUIDE
 
BHADANIS - BRICK WORK ESTIMATION GUIDE CIVIL WORKS CONSTRUCTION ESTIMATION
BHADANIS - BRICK WORK ESTIMATION GUIDE CIVIL WORKS CONSTRUCTION ESTIMATIONBHADANIS - BRICK WORK ESTIMATION GUIDE CIVIL WORKS CONSTRUCTION ESTIMATION
BHADANIS - BRICK WORK ESTIMATION GUIDE CIVIL WORKS CONSTRUCTION ESTIMATION
 
BHADANIS Construction Material Estimation Guide
BHADANIS Construction Material Estimation GuideBHADANIS Construction Material Estimation Guide
BHADANIS Construction Material Estimation Guide
 
Bhadanis RCC WORK ESTIMATION GUIDE PCC WORK ESTIMATION
Bhadanis RCC WORK ESTIMATION GUIDE PCC WORK ESTIMATIONBhadanis RCC WORK ESTIMATION GUIDE PCC WORK ESTIMATION
Bhadanis RCC WORK ESTIMATION GUIDE PCC WORK ESTIMATION
 
IRJET-Mix Proportion of Materials in Pervious Concrete
IRJET-Mix Proportion of Materials in Pervious ConcreteIRJET-Mix Proportion of Materials in Pervious Concrete
IRJET-Mix Proportion of Materials in Pervious Concrete
 
USE OF MERAUKE FINE AGGREGATE AND DIGOEL BOVEN COARSE AGGREGATE ON CONCRETE C...
USE OF MERAUKE FINE AGGREGATE AND DIGOEL BOVEN COARSE AGGREGATE ON CONCRETE C...USE OF MERAUKE FINE AGGREGATE AND DIGOEL BOVEN COARSE AGGREGATE ON CONCRETE C...
USE OF MERAUKE FINE AGGREGATE AND DIGOEL BOVEN COARSE AGGREGATE ON CONCRETE C...
 
IRJET- Utilization of STP By–Product as a Raw Material in Concrete
IRJET- Utilization of STP By–Product as a Raw Material in ConcreteIRJET- Utilization of STP By–Product as a Raw Material in Concrete
IRJET- Utilization of STP By–Product as a Raw Material in Concrete
 
Nagpur csr
Nagpur csrNagpur csr
Nagpur csr
 
Utilisation of RAP (Reclaimed Asphalt Pavement) Material Obtained By Milling ...
Utilisation of RAP (Reclaimed Asphalt Pavement) Material Obtained By Milling ...Utilisation of RAP (Reclaimed Asphalt Pavement) Material Obtained By Milling ...
Utilisation of RAP (Reclaimed Asphalt Pavement) Material Obtained By Milling ...
 
Partial Replacement of Sand by Quarry Dust in Construction of Box Culvert
Partial Replacement of Sand by Quarry Dust in Construction of Box CulvertPartial Replacement of Sand by Quarry Dust in Construction of Box Culvert
Partial Replacement of Sand by Quarry Dust in Construction of Box Culvert
 
“Experimental Investigation of Green Concrete Paver Block by Partial Replacem...
“Experimental Investigation of Green Concrete Paver Block by Partial Replacem...“Experimental Investigation of Green Concrete Paver Block by Partial Replacem...
“Experimental Investigation of Green Concrete Paver Block by Partial Replacem...
 
IRJET- Application of Rubber Properties in Clay Bricks
IRJET- Application of Rubber Properties in Clay BricksIRJET- Application of Rubber Properties in Clay Bricks
IRJET- Application of Rubber Properties in Clay Bricks
 
IRJET- Effect of Manufactured Sand on Mechanical Properties of Concrete
IRJET-  	  Effect of Manufactured Sand on Mechanical Properties of ConcreteIRJET-  	  Effect of Manufactured Sand on Mechanical Properties of Concrete
IRJET- Effect of Manufactured Sand on Mechanical Properties of Concrete
 
A Study on Cement Stabilized Conventional Waste and Marginal Material for Pav...
A Study on Cement Stabilized Conventional Waste and Marginal Material for Pav...A Study on Cement Stabilized Conventional Waste and Marginal Material for Pav...
A Study on Cement Stabilized Conventional Waste and Marginal Material for Pav...
 
Fundamentals of Estimating and Costing
 Fundamentals of Estimating and Costing Fundamentals of Estimating and Costing
Fundamentals of Estimating and Costing
 
chapter1-210122051628.pdf
chapter1-210122051628.pdfchapter1-210122051628.pdf
chapter1-210122051628.pdf
 
IRJET - The Use of Waste Plastic in the Manufacture of Bricks
IRJET - The Use of Waste Plastic in the Manufacture of BricksIRJET - The Use of Waste Plastic in the Manufacture of Bricks
IRJET - The Use of Waste Plastic in the Manufacture of Bricks
 
IRJET- Mix Design Steps for Self-Compacting Concrete
IRJET- Mix Design Steps for Self-Compacting ConcreteIRJET- Mix Design Steps for Self-Compacting Concrete
IRJET- Mix Design Steps for Self-Compacting Concrete
 

Mehr von Shanmugasundaram N

Response of structures to earthquake - Structural dynamics and Earthquake Eng...
Response of structures to earthquake - Structural dynamics and Earthquake Eng...Response of structures to earthquake - Structural dynamics and Earthquake Eng...
Response of structures to earthquake - Structural dynamics and Earthquake Eng...Shanmugasundaram N
 
Elements of seismology - Structural dynamics and Earthquake Engineering (SD&EE)
Elements of seismology - Structural dynamics and Earthquake Engineering (SD&EE)Elements of seismology - Structural dynamics and Earthquake Engineering (SD&EE)
Elements of seismology - Structural dynamics and Earthquake Engineering (SD&EE)Shanmugasundaram N
 
Lessons learned from past earthquake - Structural dynamics and Earthquake Eng...
Lessons learned from past earthquake - Structural dynamics and Earthquake Eng...Lessons learned from past earthquake - Structural dynamics and Earthquake Eng...
Lessons learned from past earthquake - Structural dynamics and Earthquake Eng...Shanmugasundaram N
 
Techniques for repair and protection methods II- Repair and rehabilitation of...
Techniques for repair and protection methods II- Repair and rehabilitation of...Techniques for repair and protection methods II- Repair and rehabilitation of...
Techniques for repair and protection methods II- Repair and rehabilitation of...Shanmugasundaram N
 
Techniques for repair and protection methods - Repair and rehabilitation of s...
Techniques for repair and protection methods - Repair and rehabilitation of s...Techniques for repair and protection methods - Repair and rehabilitation of s...
Techniques for repair and protection methods - Repair and rehabilitation of s...Shanmugasundaram N
 
Strength and durability of concrete - Repair and rehabilitation of structures...
Strength and durability of concrete - Repair and rehabilitation of structures...Strength and durability of concrete - Repair and rehabilitation of structures...
Strength and durability of concrete - Repair and rehabilitation of structures...Shanmugasundaram N
 
Special concretes- Repair and rehabilitation of structures(RRS) - Concrete Te...
Special concretes- Repair and rehabilitation of structures(RRS) - Concrete Te...Special concretes- Repair and rehabilitation of structures(RRS) - Concrete Te...
Special concretes- Repair and rehabilitation of structures(RRS) - Concrete Te...Shanmugasundaram N
 
Repair, rehabilitation and retrofitting of structures - RRS
Repair, rehabilitation and retrofitting of structures - RRSRepair, rehabilitation and retrofitting of structures - RRS
Repair, rehabilitation and retrofitting of structures - RRSShanmugasundaram N
 
Maintenance and repair strategies - Repair and rehabilitation of structures(RRS)
Maintenance and repair strategies - Repair and rehabilitation of structures(RRS)Maintenance and repair strategies - Repair and rehabilitation of structures(RRS)
Maintenance and repair strategies - Repair and rehabilitation of structures(RRS)Shanmugasundaram N
 
Moment distribution method - Structural Analysis
Moment distribution method  - Structural AnalysisMoment distribution method  - Structural Analysis
Moment distribution method - Structural AnalysisShanmugasundaram N
 
Portal frames with sway - - Structural Analysis
Portal frames with sway -  - Structural AnalysisPortal frames with sway -  - Structural Analysis
Portal frames with sway - - Structural AnalysisShanmugasundaram N
 
Basics of sdm and equations - - Structural Analysis
Basics of sdm and equations -  - Structural AnalysisBasics of sdm and equations -  - Structural Analysis
Basics of sdm and equations - - Structural AnalysisShanmugasundaram N
 
Determination of static and kinematic indeterminacies - Structural Analysis
Determination of static and kinematic indeterminacies - Structural AnalysisDetermination of static and kinematic indeterminacies - Structural Analysis
Determination of static and kinematic indeterminacies - Structural AnalysisShanmugasundaram N
 
Philosophy, purpose of estimation, load bearing and framed structure - Estima...
Philosophy, purpose of estimation, load bearing and framed structure - Estima...Philosophy, purpose of estimation, load bearing and framed structure - Estima...
Philosophy, purpose of estimation, load bearing and framed structure - Estima...Shanmugasundaram N
 
Methods of estimation - Estimation, Costing and Valuation Engineering
Methods of estimation - Estimation, Costing and Valuation EngineeringMethods of estimation - Estimation, Costing and Valuation Engineering
Methods of estimation - Estimation, Costing and Valuation EngineeringShanmugasundaram N
 

Mehr von Shanmugasundaram N (20)

Types of arches
Types of arches   Types of arches
Types of arches
 
Total station survey
Total station surveyTotal station survey
Total station survey
 
Gps survey
Gps surveyGps survey
Gps survey
 
Control surveying
Control surveyingControl surveying
Control surveying
 
Response of structures to earthquake - Structural dynamics and Earthquake Eng...
Response of structures to earthquake - Structural dynamics and Earthquake Eng...Response of structures to earthquake - Structural dynamics and Earthquake Eng...
Response of structures to earthquake - Structural dynamics and Earthquake Eng...
 
Elements of seismology - Structural dynamics and Earthquake Engineering (SD&EE)
Elements of seismology - Structural dynamics and Earthquake Engineering (SD&EE)Elements of seismology - Structural dynamics and Earthquake Engineering (SD&EE)
Elements of seismology - Structural dynamics and Earthquake Engineering (SD&EE)
 
Lessons learned from past earthquake - Structural dynamics and Earthquake Eng...
Lessons learned from past earthquake - Structural dynamics and Earthquake Eng...Lessons learned from past earthquake - Structural dynamics and Earthquake Eng...
Lessons learned from past earthquake - Structural dynamics and Earthquake Eng...
 
Techniques for repair and protection methods II- Repair and rehabilitation of...
Techniques for repair and protection methods II- Repair and rehabilitation of...Techniques for repair and protection methods II- Repair and rehabilitation of...
Techniques for repair and protection methods II- Repair and rehabilitation of...
 
Techniques for repair and protection methods - Repair and rehabilitation of s...
Techniques for repair and protection methods - Repair and rehabilitation of s...Techniques for repair and protection methods - Repair and rehabilitation of s...
Techniques for repair and protection methods - Repair and rehabilitation of s...
 
Strength and durability of concrete - Repair and rehabilitation of structures...
Strength and durability of concrete - Repair and rehabilitation of structures...Strength and durability of concrete - Repair and rehabilitation of structures...
Strength and durability of concrete - Repair and rehabilitation of structures...
 
Special concretes- Repair and rehabilitation of structures(RRS) - Concrete Te...
Special concretes- Repair and rehabilitation of structures(RRS) - Concrete Te...Special concretes- Repair and rehabilitation of structures(RRS) - Concrete Te...
Special concretes- Repair and rehabilitation of structures(RRS) - Concrete Te...
 
Repair, rehabilitation and retrofitting of structures - RRS
Repair, rehabilitation and retrofitting of structures - RRSRepair, rehabilitation and retrofitting of structures - RRS
Repair, rehabilitation and retrofitting of structures - RRS
 
Maintenance and repair strategies - Repair and rehabilitation of structures(RRS)
Maintenance and repair strategies - Repair and rehabilitation of structures(RRS)Maintenance and repair strategies - Repair and rehabilitation of structures(RRS)
Maintenance and repair strategies - Repair and rehabilitation of structures(RRS)
 
Moment distribution method - Structural Analysis
Moment distribution method  - Structural AnalysisMoment distribution method  - Structural Analysis
Moment distribution method - Structural Analysis
 
Portal frames with sway - - Structural Analysis
Portal frames with sway -  - Structural AnalysisPortal frames with sway -  - Structural Analysis
Portal frames with sway - - Structural Analysis
 
Basics of sdm and equations - - Structural Analysis
Basics of sdm and equations -  - Structural AnalysisBasics of sdm and equations -  - Structural Analysis
Basics of sdm and equations - - Structural Analysis
 
Determination of static and kinematic indeterminacies - Structural Analysis
Determination of static and kinematic indeterminacies - Structural AnalysisDetermination of static and kinematic indeterminacies - Structural Analysis
Determination of static and kinematic indeterminacies - Structural Analysis
 
Basics of structural analysis
Basics of structural analysisBasics of structural analysis
Basics of structural analysis
 
Philosophy, purpose of estimation, load bearing and framed structure - Estima...
Philosophy, purpose of estimation, load bearing and framed structure - Estima...Philosophy, purpose of estimation, load bearing and framed structure - Estima...
Philosophy, purpose of estimation, load bearing and framed structure - Estima...
 
Methods of estimation - Estimation, Costing and Valuation Engineering
Methods of estimation - Estimation, Costing and Valuation EngineeringMethods of estimation - Estimation, Costing and Valuation Engineering
Methods of estimation - Estimation, Costing and Valuation Engineering
 

Kürzlich hochgeladen

Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
11. Properties of Liquid Fuels in Energy Engineering.pdf
11. Properties of Liquid Fuels in Energy Engineering.pdf11. Properties of Liquid Fuels in Energy Engineering.pdf
11. Properties of Liquid Fuels in Energy Engineering.pdfHafizMudaserAhmad
 
Crystal Structure analysis and detailed information pptx
Crystal Structure analysis and detailed information pptxCrystal Structure analysis and detailed information pptx
Crystal Structure analysis and detailed information pptxachiever3003
 
Correctly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleCorrectly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleAlluxio, Inc.
 
BSNL Internship Training presentation.pptx
BSNL Internship Training presentation.pptxBSNL Internship Training presentation.pptx
BSNL Internship Training presentation.pptxNiranjanYadav41
 
Industrial Safety Unit-IV workplace health and safety.ppt
Industrial Safety Unit-IV workplace health and safety.pptIndustrial Safety Unit-IV workplace health and safety.ppt
Industrial Safety Unit-IV workplace health and safety.pptNarmatha D
 
Virtual memory management in Operating System
Virtual memory management in Operating SystemVirtual memory management in Operating System
Virtual memory management in Operating SystemRashmi Bhat
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfCCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfAsst.prof M.Gokilavani
 
Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...121011101441
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...asadnawaz62
 
Autonomous emergency braking system (aeb) ppt.ppt
Autonomous emergency braking system (aeb) ppt.pptAutonomous emergency braking system (aeb) ppt.ppt
Autonomous emergency braking system (aeb) ppt.pptbibisarnayak0
 
Configuration of IoT devices - Systems managament
Configuration of IoT devices - Systems managamentConfiguration of IoT devices - Systems managament
Configuration of IoT devices - Systems managamentBharaniDharan195623
 
Energy Awareness training ppt for manufacturing process.pptx
Energy Awareness training ppt for manufacturing process.pptxEnergy Awareness training ppt for manufacturing process.pptx
Energy Awareness training ppt for manufacturing process.pptxsiddharthjain2303
 
Work Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvWork Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvLewisJB
 
Indian Dairy Industry Present Status and.ppt
Indian Dairy Industry Present Status and.pptIndian Dairy Industry Present Status and.ppt
Indian Dairy Industry Present Status and.pptMadan Karki
 
System Simulation and Modelling with types and Event Scheduling
System Simulation and Modelling with types and Event SchedulingSystem Simulation and Modelling with types and Event Scheduling
System Simulation and Modelling with types and Event SchedulingBootNeck1
 

Kürzlich hochgeladen (20)

Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
11. Properties of Liquid Fuels in Energy Engineering.pdf
11. Properties of Liquid Fuels in Energy Engineering.pdf11. Properties of Liquid Fuels in Energy Engineering.pdf
11. Properties of Liquid Fuels in Energy Engineering.pdf
 
Crystal Structure analysis and detailed information pptx
Crystal Structure analysis and detailed information pptxCrystal Structure analysis and detailed information pptx
Crystal Structure analysis and detailed information pptx
 
Design and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdfDesign and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdf
 
Designing pile caps according to ACI 318-19.pptx
Designing pile caps according to ACI 318-19.pptxDesigning pile caps according to ACI 318-19.pptx
Designing pile caps according to ACI 318-19.pptx
 
Correctly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleCorrectly Loading Incremental Data at Scale
Correctly Loading Incremental Data at Scale
 
BSNL Internship Training presentation.pptx
BSNL Internship Training presentation.pptxBSNL Internship Training presentation.pptx
BSNL Internship Training presentation.pptx
 
Industrial Safety Unit-IV workplace health and safety.ppt
Industrial Safety Unit-IV workplace health and safety.pptIndustrial Safety Unit-IV workplace health and safety.ppt
Industrial Safety Unit-IV workplace health and safety.ppt
 
Virtual memory management in Operating System
Virtual memory management in Operating SystemVirtual memory management in Operating System
Virtual memory management in Operating System
 
POWER SYSTEMS-1 Complete notes examples
POWER SYSTEMS-1 Complete notes  examplesPOWER SYSTEMS-1 Complete notes  examples
POWER SYSTEMS-1 Complete notes examples
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfCCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
 
Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...
 
Autonomous emergency braking system (aeb) ppt.ppt
Autonomous emergency braking system (aeb) ppt.pptAutonomous emergency braking system (aeb) ppt.ppt
Autonomous emergency braking system (aeb) ppt.ppt
 
Configuration of IoT devices - Systems managament
Configuration of IoT devices - Systems managamentConfiguration of IoT devices - Systems managament
Configuration of IoT devices - Systems managament
 
Energy Awareness training ppt for manufacturing process.pptx
Energy Awareness training ppt for manufacturing process.pptxEnergy Awareness training ppt for manufacturing process.pptx
Energy Awareness training ppt for manufacturing process.pptx
 
Work Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvWork Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvv
 
Indian Dairy Industry Present Status and.ppt
Indian Dairy Industry Present Status and.pptIndian Dairy Industry Present Status and.ppt
Indian Dairy Industry Present Status and.ppt
 
System Simulation and Modelling with types and Event Scheduling
System Simulation and Modelling with types and Event SchedulingSystem Simulation and Modelling with types and Event Scheduling
System Simulation and Modelling with types and Event Scheduling
 

Rate analysis and costing - Estimation, Costing and Valuation Engineering

  • 1. SNS COLLEGE OF ENGINEERING An Autonomous Institutions Accredited by NBA – AICTE and Accredited by NAAC – UGC with ‘A’ & ‘A+’Grade Approved by AICTE, New Delhi & Affiliated to Anna University, Chennai DEPARTMENT OF CIVIL ENGINEERING COURSE NAME: CE8701 - ESTIMATION, COSTING AND VALUATION ENGINEERING IV YEAR / VII SEMESTER Unit II: RATE ANALYSIS AND COSTING Topic 1 : Analysis of Rates
  • 2. 12/4/2020 UNIT II - RATE ANALYSIS AND COSTING SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil Standard Data – Observed Data – Schedule of rates – Market rates – Standard Data for Man Hours and Machineries for common civil works – Rate Analysis for all Building works, canals, and Roads– Cost Estimates (additional practice in class room using Computer softwares) - (Analysis of rates for the item of work asked, the data regarding labour, rates of material and rates of labour to be given in the Examination Question Paper) 2/88
  • 3. 12/4/2020 Analysis of Rates . SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil Data Method of determining the rate per unit of particular item of work in a structure. Including Quantities of materials required, cost of materials at site, Labour required and labourer charge, lump sum if required. The cost per unit of an item of work is called data. Analysis of rates  Quantities of items are calculated by detailed estimation. Classification of Data 1. Standard data 2. Main data 3. Sub data 4. Observed data 5. Sundries and Lump sum provision. 3/88
  • 4. 12/4/2020 Analysis of Rates SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil 1. Standard data SOR 2019-2020.pdf 2. Main data  Major item of works.  Total cost of a particular item of work involving many sub works or sub data 3.Sub data  In main data some of the certain minor items (Sub data) are not given directly.  In this case the cost of minor works are prepared as sub data. 4/88
  • 5. 12/4/2020 Analysis of Rates . SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil 3.Sub data Example: Plastering with C.M (1:5) 12mm thick – 10 m2 a) Cement mortar 1:5 – 0.14 m3 b) Mason I class – 1.1 Nos c) Mazdoor I class – 0.5 Nos d) Mazdoor II class – 1.1 NoS e) Lump sum / Sundries – L.S 5/88
  • 6. 12/4/2020 Analysis of Rates SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil Abstract of estimation cost table 6/88
  • 7. 12/4/2020 Analysis of Rates SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil Problem 1 Prepare the data for 1.Cement mortar a) Cement Mortar 1:2 – 1 m3 b) Cement Mortar 1:3 – 1 m3 c) Cement Mortar 1:4 – 1 m3 d) Cement Mortar 1:5 – 1 m3 e) Cement Mortar 1:6 – 1 m3 2. Lime mortar and a) Lime Mortar 1:1.5 – 1 m3 Sand cost at site - 1 m3 Lime – 0.67 m3 Mixing charge - 1 m3 7/88
  • 8. 12/4/2020 Analysis of Rates SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil b) Lime Mortar 1:2 – 1 m3 Sand cost at site - 1 m3 Lime – 0.50 m3 Mixing charge - 1 m3 3. Surkhi mortar. a) Surkhi Mortar 1:0.5:1.5 – 1 m3 Lime- 0.5 m3 Surkhi – 0.25 m3 Sand – 0.75 m3 Grinding charges - 1 m3 b) Surkhi Mortar 1:0.5:1 – 1 m3 Lime- 0.67 m3 Surkhi – 0.33 m3 Sand – 0.67 m3 and Grinding charges - 1 m3 8/88
  • 9. 12/4/2020 Analysis of Rates SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil 3. Surkhi mortar. c) Surkhi Mortar 1:1:0.5 – 1 m3 Lime- 0.4 m3 Surkhi – 0.5 m3 Sand – 0.6 m3 Grinding charges - 1 m3 Cost of labour 1. Mixing cement mortar charges – 50/ m3 2. Grinding lime mortar charges – 100/ m3 9/88
  • 10. 12/4/2020 Analysis of Rates . SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil Cost of materials and labour at site Surkhi Mortar = Rs.580/ m3 Material Unit Cost (Rs) Lead (Km) Rate for lead/Km (Rs) Handling charge (Rs) Cement 1 bag 450 12 5 6 Lime 1 m3 1272 8 6 20 Sand 1 m3 1590 20 6 30 10/88
  • 11. 12/4/2020 Analysis of Rates SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil Solution Lead statement for cost of material at site: Surkhi Mortar = 580/ m3 Materia l Unit Cost (Rs) 1 Lead (Km) 2 Rate for lead/Km (Rs) 3 Handling charge (Rs) 4 Total (1+ (2x3) +4) Cement 1 bag 450 12 5 6 516 Lime 1 m3 1272 8 6 20 1340 Sand 1 m3 1590 20 6 30 1740 11/88
  • 12. 12/4/2020 Analysis of Rates SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil 1.Cement mortar a) Cement Mortar 1:2 – 1 m3 1 m3 Sand cost at site 1740 1 m3 1740.00 720 kg (1440/2) Cement 516 50 kg 7430.40 1 m3 Mixing charge 50 1 m3 50.000 Rate for 1 m3 9220.40 12/88
  • 13. 12/4/2020 Analysis of Rates SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil 1.Cement mortar b) Cement Mortar 1:3 – 1 m3 1 m3 Sand cost at site 1740 1 m3 1740.00 480 kg (1440/3) Cement 516 50 kg 4953.60 1 m3 Mixing charge 50 1 m3 50.000 Rate for 1 m3 6743.60 13/88
  • 14. 12/4/2020 Analysis of Rates SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil 1.Cement mortar c) Cement Mortar 1:4 – 1 m3 1 m3 Sand cost at site 1740 1 m3 1740.00 360 kg (1440/4) Cement 516 50 kg 3715.20 1 m3 Mixing charge 50 1 m3 50.000 Rate for 1 m3 5505.20 14/88
  • 15. 12/4/2020 Analysis of Rates SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil 1.Cement mortar d) Cement Mortar 1:5 – 1 m3 1 m3 Sand cost at site 1740 1 m3 1740.00 288 kg (1440/5) Cement 516 50 kg 2972.16 1 m3 Mixing charge 50 1 m3 50.000 Rate for 1 m3 4762.16 15/88
  • 16. 12/4/2020 Analysis of Rates SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil 1.Cement mortar e) Cement Mortar 1:6 – 1 m3 1 m3 Sand cost at site 1740 1 m3 1740.00 240 kg (1440/6) Cement 516 50 kg 2476.80 1 m3 Mixing charge 50 1 m3 50.000 Rate for 1 m3 4266.80 16/88
  • 17. 12/4/2020 Analysis of Rates SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil 2.Lime mortar a) Lime Mortar 1:1.5 – 1 m3 1 m3 Sand cost at site 1740 1 m3 1740.00 0.67 m3 Lime 1340 1 m3 897.80 1 m3 Mixing charge 50 1 m3 50.00 Rate for 1 m3 2687.80 17/88
  • 18. 12/4/2020 Analysis of Rates . SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil 2.Lime mortar b) Lime Mortar 1:2 – 1 m3 1 m3 Sand cost at site 1740 1 m3 1740.00 0.5 m3 Lime 1340 1 m3 670.00 1 m3 Mixing charge 50 1 m3 50.00 Rate for 1 m3 2460.00 18/88
  • 19. 12/4/2020 Analysis of Rates SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil 3. Surkhi mortar. a) Surkhi Mortar 1:0.5:1.5 – 1 m3 0.5 m3 Lime 1340 1 m3 670.00 0.25 m3 Surkhi 580 1 m3 145.00 0.75 m3 Sand 1740 1 m3 1305.00 1 m3 Grinding Charge 100 1 m3 100 Rate for 1 m3 2220.00 19/88
  • 20. 12/4/2020 Analysis of Rates . SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil 3. Surkhi mortar. b) Surkhi Mortar 1:0.5:1 – 1 m3 0.67 m3 Lime 1340 1 m3 897.80 0.33 m3 Surkhi 580 1 m3 191.40 0.67 m3 Sand 1740 1 m3 1165.8 1 m3 Grinding Charge 100 1 m3 100 Rate for 1 m3 2355.00 20/88
  • 21. 12/4/2020 Analysis of Rates SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil 3. Surkhi mortar. c) Surkhi Mortar 1:1:0.5 – 1 m3 0.4 m3 Lime 1340 1 m3 536.00 0.5 m3 Surkhi 580 1 m3 290.00 0.6 m3 Sand 1740 1 m3 1044 1 m3 Grinding Charge 100 1 m3 100 Rate for 1 m3 1970.00 21/88
  • 22. 12/4/2020 SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil Happy Learning 22/88
  • 23. 12/4/2020 Analysis of Rates SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil Problem 2 Prepare the data for concrete broken stone using 40mm size in CM 1:4 -10 m3. Material and labour required a) Cement Mortar 1:4 - 1 m3 Sand cost at site - 1 m3 Cement – 360 kg Mixing charges - 1 m3 b) Plain cement concrete in cement mortar 1:4:10 using 40mm size hard broken stone -10 m3 Broken stone 40mm size cost at site - 9.5 m3 Cement mortar 1:4 as per worked sub data – 3.8 m3 Mason II Class -1.8 Nos Mazdoor category I – 17.7 Nos. Mazdoor category II – 14.1 Nos 23/88
  • 24. 12/4/2020 Analysis of Rates SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil Cost of Labour Mixing charger for CM – Rs 50 / m3 Mason II class - Rs 900 / day Mazdoor category I – 700 /day Mazdoor category II – 500 / day Cost of materials and labour at site Material Unit Cost (Rs) Lead (Km) Rate for lead/Km (Rs) Handling charge (Rs) Cement 1 bag 450 12 5 6 Sand 1 m3 1590 20 6 30 Broken stone 40mm size 1 m3 710 20 7 35 24/88
  • 25. 12/4/2020 Analysis of Rates SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil Solution Lead statement for cost of material at site: Material Unit Cost (Rs) 1 Lead (Km) 2 Rate for lead/Km (Rs) 3 Handling charge (Rs) 4 Total (1+ (2x3) +4) Cement 1 bag 450 12 5 6 516 Sand 1 m3 1590 20 6 30 1740 Broken stone 40mm size 1 m3 710 20 7 35 885 25/88
  • 26. 12/4/2020 Analysis of Rates SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil Sub data Cement mortar 1:4 1 m3 Sand cost at site 1740 1 m3 1740.00 360 kg (1440/4) Cement 516 50 kg 3715.20 1 m3 Mixing charge 50 1 m3 50.000 Rate for 1 m3 5505.20 26/88
  • 27. 12/4/2020 Analysis of Rates SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil Main data Plain cement concrete in cement mortar 1:4:10 using 40mm size hard broken stone -10 m3 Rate for 10 m3 = Rs.50387.260/- 9.5 m3 Broken stone 40mm size cost at site 885 1m3 8407.50 3.8 m3 Cement mortar 1:4 as per worked sub data 5505.2 1m3 20919.76 1.8 Nos Mason II Class 900 Day 1620.00 17.7 Nos Mazdoor category I 700 Day 12390.00 14.1 Nos Maxdoor category II 500 Day 7050.00 Rate for 10 m3 50387.260 27/88
  • 28. 12/4/2020 Analysis of Rates SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil Problem 3 Prepare the data for flooring with cc 1:4:8 using 20mm size broken stone 100mm thick and plastered over with CM 1:3, 15mm thick – 10 m2 Material and labour required a) Cement Mortar 1:4 - 1 m3 Sand cost at site - 1 m3 Cement – 360 kg Mixing charges - 1 m3 b) Cement Mortar 1:3 - 1 m3 Sand cost at site - 1 m3 Cement – 480 kg Mixing charges - 1 m3 28/88
  • 29. 12/4/2020 Analysis of Rates . SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil c) Cement concrete 1:4:8, 20mm size broken stone - 10 m3 Broken stone 20mm size - 9 m3 Cement Mortar 1:4 – 4.5 m3 Mason II class– 1.8 nos Mazdoor category I – 17.7 nos Mazdoor category II– 14.1 nos d) Plastering with Cement mortar 1:3, 15mm thick - 10 m2 Cement Mortar 1:3 – 0.14 m3 Mason I class– 1.1 nos Mazdoor category I – 0.5 nos Mazdoor category II– 1.1 nos 29/88
  • 30. 12/4/2020 Analysis of Rates SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil e) Flooring with cement concrete 1:4:8 - 10 m2 Concrete broken stone in cement mortar 1:4 – 1 m3 Plastering with cement mortar 1:3, 15mm thick – 10 m2 Cost of material and labour at site in rupees Cement - 10320 / tonne Sand - 1740 / m3 (5000/unit in store) Stone 20mm - 885 / m3 (2500/unit store) Mason I class - 950 / Day Mason II class - 900 / Day Mazdoor class I - 700 / Day Mazdoor class II- 500 / Day Mixing charge - 50 / m3 30/88
  • 31. 12/4/2020 Analysis of Rates . SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil Solution Sub data 1 - Cement mortar 1:4 - 1 m3 1 m3 Sand cost at site 1740 1 m3 1740.00 360 kg (1440/4) Cement 10320 1000 kg 3715.20 1 m3 Mixing charge 50 1 m3 50.000 Rate for 1 m3 5505.20 31/88
  • 32. 12/4/2020 Analysis of Rates SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil Sub data 2 - Cement mortar 1:3 - 1 m3 1 m3 Sand cost at site 1740 1 m3 1740.00 480 kg (1440/3) Cement 10320 1000 kg 4953.60 1 m3 Mixing charge 50 1 m3 50.000 Rate for 1 m3 6743.60 32/88
  • 33. 12/4/2020 Analysis of Rates . SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil Sub data 3 - Plastering with Cement mortar 1:3, 15mm thick - 10 m2 0.14 m3 Cement mortar 1:3 6743.60 m3 944.104 1.1 nos Mason I class 950 Day 1045 0.5 nos Mazdoor category I 700 Day 350 1.1 nos Mazdoor caterory II 500 Day 550 Rate for 10 m2 2889.10 33/88
  • 34. 12/4/2020 Analysis of Rates SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil Sub data 4 - Cement concrete 1:4:8, 20mm size broken stone - 10 m3 9.0 m3 Broken stone 20mm 885 m3 7965 4.5 m3 Cement mortar 1:4 5505.2 m3 24773.4 1.8 nos Mason II Class 900 Day 1620 17.7 nos Mazdoor category I 700 Day 12390 14.1 nos Mazdoor category II 500 Day 7050 Rate for 10 m3 53798.40 34/88
  • 35. 12/4/2020 Analysis of Rates . SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil Main data - Flooring with cc1:4:8 using 20mm size broken stone 100mm thick and plastered over with CM 1:3, 15mm thick – 10 m2 Result - Rate for 10 m2 = Rs.8268.940/- 1 m3 Concrete broken stone in CM 1:4 53798.40 10 m3 5379.84 10 m2 Plastering with CM (1:3) 15mm thick 2889.10 10 m2 2889.10 Rate for 10 m2 8268.940 35/88
  • 36. 12/4/2020 Analysis of Rates SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil Problem 4 Prepare the data for Mosaic tiled flooring using hydraulic pressed mosaic tiles of 200x200x20mm size with CM 1:4, 20mm thick and pointing with colour cement including polishing – 1 m2 Material and labour required a) Cement Mortar 1:4 - 1 m3 Sand cost at site - 1 m3 Cement - 360 kg Mixing charges - 1 m3 b) Mosaic tiled flooring, pointing and polishing - 10 m2 Mosaic tile 200x200x20mm – 250 nos. Cement mortar 1:4 – 0.21 m3 Colour cement - 22kg 36/88
  • 37. 12/4/2020 Analysis of Rates SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil b) Mosaic tiled flooring, pointing and polishing - 10 m2 Mason I class - 1.1 nos. Mason II Class - 2.7 nos Mazdoor category I - 2.7 nos Mazdoor category II - 5.4 nos Polisher - 1.1 nos Cost of material and labour at site in rupees Cement - 516 / bag Sand - 1740 / m3 (5000/unit in store) Colour cement - 450 / bag Mosaic tiles - 4500 / 100 nos Mason I class - 950 / Day 37/88
  • 38. 12/4/2020 Analysis of Rates SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil Cost of material and labour at site in rupees Mason II class - 900 / Day Polisher - 800 / Day Mazdoor class I - 700 / Day Mazdoor class II- 500 / Day Mixing charge - 50 / m3 Solution Sub data 1 - Cement mortar 1:4 - 1 m3 1 m3 Sand cost at site 1740 1 m3 1740.00 360 kg Cement 10320 1000 kg 3715.20 1 m3 Mixing charge 50 1 m3 50.000 Rate for 1 m3 5505.20 38/88
  • 39. 12/4/2020 Analysis of Rates SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil Main data : Mosaic tiled flooring using hydraulic pressed mosaic tiles of 200x200x20mm size with CM 1:4, 20mm thick and pointing with colour cement including polishing – 1 m2 250 nos Mosaic tiles 4500 100 nos 11250 0.21 m3 CM 1:4 5505.2 1 m3 1156.092 22 kg Colour cement 450 Bag 198 1.1 nos Mason I class 950 Day 1045 2.7 nos Mason II class 900 Day 2430 2.7 nos Mazdoor I class 700 Day 1890 5.4 nos Mazdoor II class 500 Day 2700 1.1 nos Polisher 800 Day 880 Rate for 10 m2 21549.092 39/88
  • 40. 12/4/2020 Analysis of Rates SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil Rate of 10 m2 = Rs.21549.092/- Rate of 1 m2 = 21549.092/10 = Rs.2154.909. Result : Rate of 1 m2 = Rs.2154.909. Brick work calculation. A) Brickwork in foundation Rate will varying at based on the depth. Ex – 1.5m to 4.5m, 4.5m to 9m B) Brickwork in super structure Rate will varying based on the height Ex: Up to 4.5m and above 4.5m at every 1m height. 40/88
  • 41. 12/4/2020 Analysis of Rates SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil Problem 4 Prepare the data for brick work in foundation in cement mortar 1:5 mix using first class bricks– 1 m3 Material and labour required. a) Cement Mortar 1:5 - 1 m3 Sand cost at site - 1 m3 Cement - 288 kg Mixing charges - 1 m3 b) Brickwork in foundation using I class brick works in CM 1:5 - 10 m3 Bricks – 19 x 9 x 9 cm - 5000 nos Cement mortar 1:5 - 2.2 m3 Mason I class - 3.5 nos. 41/88
  • 42. 12/4/2020 Analysis of Rates SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil b) Brickwork in foundation using I class brick works in CM 1:5 - 10 m3 Mason II Class - 10.6 nos Mazdoor category I - 7.1 nos Mazdoor category II - 21.2 nos Cost of material and labour at site in rupees Cement - 516 / bag Sand - 1740 / m3 (5000/unit in store) Bricks I class - 8 / no Mason I class - 950 / Day Mason II class - 900 / Day Mazdoor class I - 700 / Day Mazdoor class II- 500 / Day Mixing charge - 50 / m3 42/88
  • 43. 12/4/2020 Analysis of Rates . SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil Solution: Sub data 1 - Cement mortar 1:5 - 1 m3 1 m3 Sand cost at site 1740 1 m3 1740.00 288 kg (1440/5) Cement 516 50 kg 2972.16 1 m3 Mixing charge 50 1 m3 50.000 Rate for 1 m3 4762.16 43/88
  • 44. 12/4/2020 Analysis of Rates SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil Main data: Brickwork in foundation using I class brick works in CM 1:5 - 10 m3 Result : Rate for 1 m3 = Rs.7891.17/- 5000 nos Bricks 19x9x9 cm 8 No 40000 2.2 m3 CM 1:5 4762.16 m3 10476.75 3.5 nos Mason I class 950 Day 3325 10.6 nos Mason II class 900 Day 9540 7.1 nos Mazdoor I category 700 Day 4970 21.2 nos Mazdoor II category 500 Day 10600 Rate for 10 m3 78911.75 44/88
  • 45. 12/4/2020 Analysis of Rates . SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil Problem 5 (Tutorial problem) Prepare the data for brick work in super structure using first class brick in cement mortar 1:5 – 1 m3 Material and labour required. a) Brickwork with CM 1:5 - 10 m3 Bricks – - 5000 nos Cement mortar 1:5 - 1.4 m3 Mason I class - 7.0 nos. Mason II class - 8.1 nos. Mazdoor I class - 8.1 nos. Mazdoor II class - 8.4 nos. 45/88
  • 46. 12/4/2020 Analysis of Rates SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil b)Cost of material and labour at site in rupees Cement - 516 / bag Sand - 1740 / m3 (5000/unit in store) Bricks I class - 8 / no Mason I class - 950 / Day Mason II class - 900 / Day Mazdoor class I - 700 / Day Mazdoor class II- 500 / Day Mixing charge - 50 / m3 46/88
  • 47. 12/4/2020 Analysis of Rates . SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil Problem 6 (Tutorial problem) Prepare the data for brick work in partition using second class brick in cement mortar 1:3 – 1 m3 Material and labour required. a) Cement Mortar 1:3 - 1 m3 Sand cost at site - 1 m3 Cement - 480 kg Mixing charges - 1 m3 b) Brickwork with CM 1:3 - 10 m3 Bricks II class - 7500 nos Cement mortar 1:3 - 2.7 m3 Mason I class - 3.5 nos. 47/88
  • 48. 12/4/2020 Analysis of Rates SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil b) Brickwork with CM 1:3 - 10 m3 Mason II class - 7.1 nos. Mazdoor I class - 7.1 nos. Mazdoor II class - 14.1 nos. Cost of material and labour at site in rupees Cement - 516 / bag Sand - 1740 / m3 (5000/unit in store) Bricks I class - 8 / no Mason I class - 950 / Day Mason II class - 900 / Day Mazdoor class I - 700 / Day Mazdoor class II- 500 / Day Mixing charge - 50 / m3 48/88
  • 49. 12/4/2020 Analysis of Rates . SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil Problem 7 (Tutorial problem) Prepare the data for coursed rubble masonry second sort in cement mortar 1:5 – 1 m3 Material and labour required. a) Cement Mortar 1:5 - 1 m3 Sand cost at site - 1 m3 Cement - 288 kg Mixing charges - 1 m3 b) Coursed rubble masonry second sort in CM 1:5- 10 m3 Course rubble stone - 6 m3 Rough stone - 5 m3 Cement mortar 1:5 - 3.2 m3 49/88
  • 50. 12/4/2020 Analysis of Rates SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil b) Coursed rubble masonry second sort in CM 1:5- 10 m3 Mason I class - 7.1 nos. Mason II class - 17.6 nos. Mazdoor II class - 14.1 nos. Cost of material and labour at site in rupees Cement - 516 / bag Sand - 1740 / m3 (5000/unit in store) Course rubbled stone - 915 / m3 Rough stone - 975 / m3 Mason I class - 950 / Day Mason II class - 900 / Day Mazdoor class II - 500 / Day Mixing charge - 50 / m3 50/88
  • 51. 12/4/2020 Analysis of Rates . SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil Problem 8 Prepare the data for weathering course with broken brick in pure slaked lime over RCC roof slab - 10 m3 Material and labour required. a) Weathering course with 20mm broken brick - 10 m3 Broken brick 20mm size - 12.8 m3 Slaked lime - 5 m3 Mason I class - 1.8 nos Mazdoor I class - 17.7 nos Mazdoor II class - 14.1 nos 51/88
  • 52. 12/4/2020 Analysis of Rates SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil b) Cost of the materials and labours at site Broken brick 20mm size - 750/ m3 Slaked lime - 1100/ m3 Mason I class - 920/ Day Mazdoor I class - 700 / Day Mazdoor II class - 500 / Day 52/88
  • 53. 12/4/2020 Analysis of Rates . SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil Solution Main data : Weathering course with 20mm broken brick - 10 m3 Result : Rate for 10 m3 = Rs.36250/- 12.8m3 Broken Bricks 20mm 750 1m3 9600 5m3 Slaked lime 1100 1 m3 5500 1.8 nos Mason I class 950 Day 1710 17.7 nos Mazdoor I category 700 Day 12390 14.1 nos Mazdoor II category 500 Day 7050 Rate for 10 m3 36250 53/88
  • 54. 12/4/2020 Analysis of Rates SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil Problem 9 Prepare the data for RCC roof slab of size 4 x 3 x 0.1 m of mix 1:2:4 using 20mm hard broken stone with reinforcement at 80kg/m3 of concrete including cutting, bending , tying and centering curing etc. – 1 m3 Material and labour required a) Cement concrete 1:2:4 using 20mm hard broken stone - 10 m3 Broken stone - 9 m3 Cement - 3240 kg Sand - 4.5 m3 Mason I class - 3.5 nos Mazdoor I grade - 21.2 nos. Mazdoor II grade - 35.8 nos 54/88
  • 55. 12/4/2020 Analysis of Rates SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil b) RCC roof 4 x3 x0.12m with reinforcement 80kg/ m3 of concrete including cutting, bending, tying etc., - 1 m3 Cement concrete 1:2:4 - 1 m3 Steel - 80kg/ m3 Binding wire - 1 % of steel required Cutting, bending and tying - as steel required Centering - as required + 20 % extra for sides. c) Cost of material and labour at site in rupees Cement - 516 / bag Sand - 1740 / m3 (5000/unit in store) Broken brick 20mm size - 750/ m3 Steel - 55000/ tonne Binding wire - 150 / kg 55/88
  • 56. 12/4/2020 Analysis of Rates SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil c) Cost of material and labour at site in rupees Mason I class - 950 / day Mason II class - 900 / day Mazdoor I grade - 700 / day Mazdoor II grade - 500 / day Cutting, bending and tying – 50 / kg Centering charge - 300 / m2 Solution Centering Area = (L x B ) + 20 % for sides or L (B+2D) = ( 4x 3) + (20/100) x (4x3) = 14.4 m2 56/88
  • 57. 12/4/2020 Analysis of Rates SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil Sub data: CC 1:2:4 using 20mm hard broken stone – 10 m3 9 m3 Broken Bricks 20mm 750 1m3 6750 4.5m3 Sand 1740 1 m3 7830 3240 kg Cement 516 Bag 33436.8 3.5 nos Mason I class 950 Day 3325 21.2 nos Mazdoor I category 700 Day 14840 35.8 nos Mazdoor II category 500 Day 17900 Rate for 10 m3 84081.8 57/88
  • 58. 12/4/2020 Analysis of Rates SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil Main data: RCC roof 4 x3 x0.12m with reinforcement 80kg/ m3 of concrete including cutting, bending, tying etc., - 1 m3 Result : Rate for 1 m3 = Rs. 21248.18/- 1 m3 CC 1:2:4 84081.8 10m3 8408.18 80kg Steel 55000 tonne 4400.00 0.8 kg Binding wire (1% of steel) 150 kg 120.00 80kg Cutting, Bending & tying 50 kg 4000.00 14.4 m2 Centering 300 1 m2 4320.00 Rate for 1 m3 21248.18 58/88
  • 59. 12/4/2020 Analysis of Rates . SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil Problem 10 Prepare the data for RCC beam of size 300 x 450mm with 1:2:4 mix using 20mm hard broken stone with reinforcement of 150kg/m3 including centering, shuttering, etc. – 1 m3 Material and labour required a) Cement concrete 1:2:4 using 20mm hard broken stone - 10 m3 Broken stone - 9 m3 Cement - 2.25 m3 Sand - 4.5 m3 Mason I class - 3.5 nos Mazdoor I grade - 21.2 nos. Mazdoor II grade - 35.3 nos 59/88
  • 60. 12/4/2020 Analysis of Rates SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil b) RCC beam of size 300 x 450mm with 1:2:4 mix using 20mm hard broken stone with reinforcement of 150kg/m3 including centering, shuttering, etc. – 1 m3 Cement concrete 1:2:4 - 1 m3 Steel - 150 kg/ m3 Binding wire - 1 % of steel required Cutting, bending and tying - as steel required Centering - as required c) Cost of material and labour at site in rupees Cement - 516 / bag Sand - 1740 / m3 (5000/unit in store) Broken brick 20mm size - 750/ m3 Steel - 55000/ tonne 60/88
  • 61. 12/4/2020 Analysis of Rates . SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil c) Cost of material and labour at site in rupees Binding wire - 150 / kg Mason I class - 950 / day Mason II class - 900 / day Mazdoor I grade - 700 / day Mazdoor II grade - 500 / day Cutting, bending and tying – 50 / kg Centering charge - 300 / m2 Solution Centering Area = L (B+2D) Volume = L x B x D , L = 1 m3 / (0.3 x 0.45) = 7.41m. Centering Area = L (B+2D) = 7.41 (0.3+2x0.45) = 8.832 m2 61/88
  • 62. 12/4/2020 Analysis of Rates SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil Sub data: CC 1:2:4 using 20mm hard broken stone – 10 m3 9 m3 Broken Bricks 20mm 750 1m3 6750 4.5m3 Sand 1740 1 m3 7830 (2.25 x 1440) 3240 kg Cement 516 Bag 33436.8 3.5 nos Mason I class 950 Day 3325 21.2 nos Mazdoor I category 700 Day 14840 35.3 nos Mazdoor II category 500 Day 17650 Rate for 10 m3 83831.8 62/88
  • 63. 12/4/2020 Analysis of Rates . SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil Main data: RCC beam of size 300 x 450mm with 1:2:4 mix using 20mm hard broken stone with reinforcement of 150kg/m3 including centering, shuttering, etc. – 1 m3 Result : Rate for 1 m3 = Rs. 27007.78/- 1 m3 CC 1:2:4 83831.8 10m3 8383.18 150 kg Steel 55000 tonne 8250.00 1.5 kg Binding wire (1% of steel) 150 kg 225.00 150kg Cutting, Bending & tying 50 kg 7500.00 8.832 m2 Centering 300 1 m2 2649.60 Rate for 1 m3 27007.78 63/88
  • 64. 12/4/2020 Analysis of Rates SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil Problem 11 (Tutorial problem) Prepare the data for RCC column of size 300x300mm with mix of 1:2:4 using 20mm hard broken stone with reinforcement of 160 kg/m3 including centering, shuttering, curing, etc. – 1 m run. Material and labour required a) Cement concrete 1:2:4 using 20mm hard broken stone - 10 m3 Broken stone - 9 m3 Cement - 2.25 m3 Sand - 4.5 m3 Mason I class - 3.5 nos Mazdoor I grade - 21.2 nos. Mazdoor II grade - 35.3 nos 64/88
  • 65. 12/4/2020 Analysis of Rates . SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil b) RCC 1:2:4 mix column – 1mrun. Cement concrete 1:2:4 - 0.09 m3 (0.3 x 0.3 x 1) Steel - 14.56 kg (0.091 m3 x 160 kg/ m3) Binding wire - 1 % of steel required Cutting, bending and tying - as steel required Centering - as required c) Cost of material and labour at site in rupees Cement - 516 / bag Sand - 1740 / m3 (5000/unit in store) Broken brick 20mm size - 750/ m3 Steel - 55000/ tonne 65/88
  • 66. 12/4/2020 Analysis of Rates SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil c) Cost of material and labour at site in rupees Binding wire - 150 / kg Mason I class - 950 / day Mason II class - 900 / day Mazdoor I grade - 700 / day Mazdoor II grade - 500 / day Cutting, bending and tying – 50 / kg Centering charge - 300 / m2 Solution Centering Area for 1m run = (0.3 x 4 ) x 1 = 1.2m2 66/88
  • 67. 12/4/2020 Analysis of Rates SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil Problem 12 Prepare the data for the following items of plastering over brick masonry in cement mortar of given mix. a) Plastering with CM 1:3 - 12mm thick – 10 m2 b) Plastering with CM 1:3 - 20mm thick – 10 m2 c) Plastering with CM 1:5 - 12mm thick – 10 m2 d) Plastering with CM 1:5 - 15mm thick – 10 m2 e) Plastering with CM 1:5 - 20mm thick – 10 m2 Material and labour required a) Plastering with CM 1:3 - 12mm thick – 10 m2 Cement mortar 1:3 - 0.14 m3 , Mason I class -1.1 nos Mazdoor category I - 0.5 nos and Mazdoor category II- 1.1 nos 67/88
  • 68. 12/4/2020 Analysis of Rates SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil b) Plastering with CM 1:3 - 20mm thick – 10 m2 Cement mortar 1:3 - 0.22 m3 Mason I class -2.2 nos Mazdoor category I - 0.5 nos Mazdoor category II - 3.2 nos c) Plastering with CM 1:5 - 12mm thick – 10 m2 Cement mortar 1:5 - 0.14 m3 Mason I class -1.1 nos Mazdoor category I - 0.5 nos Mazdoor category II - 1.1 nos d) Plastering with CM 1:5 - 15mm thick – 10 m2 Cement mortar 1:5 - 0.17 m3 Mason I class -1.51 nos Mazdoor category I - 0.5 nos & Mazdoor category II- 1.89 nos 68/88
  • 69. 12/4/2020 Analysis of Rates SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil e) Plastering with CM 1:5 - 20mm thick – 10 m2 Cement mortar 1:5 - 0.22 m3 Mason I class -2.2 nos Mazdoor category I - 0.5 nos Mazdoor category II - 3.2 nos Cost of materials and Labours at site Cement - 516 / bag Sand - 1740 / m3 Mixing charger for CM - Rs 50 / m3 Mason I class - Rs 950/ day Mason II class - Rs 900 / day Mazdoor category I - 700 /day Mazdoor category II - 500 / day 69/88
  • 70. 12/4/2020 Analysis of Rates SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil Sub data 1 : Cement Mortar 1:3 – 1 m3 1 m3 Sand cost at site 1740 1 m3 1740.00 480 kg (1440/3) Cement 516 50 kg 4953.60 1 m3 Mixing charge 50 1 m3 50.000 Rate for 1 m3 6743.60 70/88
  • 71. 12/4/2020 Analysis of Rates SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil Sub data 1 : Cement Mortar 1:5 – 1 m3 1 m3 Sand cost at site 1740 1 m3 1740.00 288 kg (1440/5) Cement 516 50 kg 2972.16 1 m3 Mixing charge 50 1 m3 50.000 Rate for 1 m3 4762.16 71/88
  • 72. 12/4/2020 Analysis of Rates SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil Main data : a) Plastering with CM 1:3 - 12mm thick – 10 m2 Result for 10 m2 = Rs.2889.104/- 0.14 m3 Cement mortar 1:3 6743.6 1 m3 944.104 1.1 nos Mason I class 950 Day 1045.00 0.5 nos Mazdoor category I 700 Day 350 1.1 nos Mazdoor category II 500 Day 550 Rate for 10 m2 2889.104 72/88
  • 73. 12/4/2020 Analysis of Rates SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil Main data : b) Plastering with CM 1:3 - 20 mm thick – 10 m2 Result for 10 m2 = Rs.5523.592/- 0.22 m3 Cement mortar 1:3 6743.6 1 m3 1483.592 2.2 nos Mason I class 950 Day 2090.00 0.5 nos Mazdoor category I 700 Day 350 3.2 nos Mazdoor category II 500 Day 1600 Rate for 10 m2 5523.592 73/88
  • 74. 12/4/2020 Analysis of Rates SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil Main data : c) Plastering with CM 1:5 - 12mm thick – 10 m2 Result for 10 m2 = Rs.2611.702/- 0.14 m3 Cement mortar 1:5 4762.16 1 m3 666.702 1.1 nos Mason I class 950 Day 1045.00 0.5 nos Mazdoor category I 700 Day 350 1.1 nos Mazdoor category II 500 Day 550 Rate for 10 m2 2611.702 74/88
  • 75. 12/4/2020 Analysis of Rates SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil Main data : d) Plastering with CM 1:5 - 15 mm thick – 10 m2 Result for 10 m2 = Rs.3539.067/- 0.17 m3 Cement mortar 1:3 4762.16 1 m3 809.567 1.51 nos Mason I class 950 Day 1434.50 0.5 nos Mazdoor category I 700 Day 350 1.89 nos Mazdoor category II 500 Day 945 Rate for 10 m2 3539.067 75/88
  • 76. 12/4/2020 Analysis of Rates SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil Main data : e) Plastering with CM 1:5 - 20mm thick – 10 m2 Result for 10 m2 = Rs.5087.67/- 0.22 m3 Cement mortar 1:5 4762.16 1 m3 1047.67 2.2 nos Mason I class 950 Day 2090.00 0.5 nos Mazdoor category I 700 Day 350 3.2 nos Mazdoor category II 500 Day 1600 Rate for 10 m2 5087.67 76/88
  • 77. 12/4/2020 Analysis of Rates SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil Problem 13 Prepare the data for painting new iron work one cost using ready mixed enamel paint over red oxide priming cost – 10 m2 Material and labour required a) Painting priming coat on new iron work – 10 m2 Ready mixed red oxide paint - 1.33litres Painter I class - 0.7 nos Sundries including brushes, soaps, putty etc.- L.S b) Painting new iron work one coat using ready mixed enamel paint – 10 m2 Synthetic enamel paint - 1.33litres Painter I class - 0.7 nos Sundries including brushes, soaps, putty etc.- L.S 77/88
  • 78. 12/4/2020 Analysis of Rates . SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil c) Painting new iron work one coat using ready mixed enamel paint over red oxide priming coat – 10 m2 Red oxide priming coat - 10 m2 Painting one coat using ready mixed enamel paint - 10 m2 Cost of materials and labour Priming coat : Ready mixed red oxide paint - Rs.150/litre Painting coat : Synthetic enamel paint - Rs.250/Litre Painter I class - 800/Day Sundries for brushes, soaps, putty etc, a) Priming coat - Rs.150 b) Painting coat - Rs.200 78/88
  • 79. 12/4/2020 Analysis of Rates SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil Sub data 1: Painting priming coat on new iron work – 10 m2 1.33 Litres Ready mixed red oxide paint 150 litre 199.50 0.7 Nos Painter I class 800 Day 560.00 L.S Sundries for brushes, soaps, putty, etc. 150 L.S 150.00 Rate for 10 m2 909.500 79/88
  • 80. 12/4/2020 Analysis of Rates . SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil Sub data 2: Painting new iron work one coat using ready mixed enamel paint – 10 m 1.33 Litres Synthetic enamel paint 250 litre 332.50 0.7 Nos Painter I class 800 Day 560.00 L.S Sundries for brushes, soaps, putty, etc. 200 L.S 200.00 Rate for 10 m2 1092.50 80/88
  • 81. 12/4/2020 Analysis of Rates SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil Main data: Painting new iron work one coat using ready mixed enamel paint over red oxide priming coat – 10 m2 Result : Rate for 10 m2 = Rs.2002/- 10 m2 Red oxide priming coat 909.50 10 m2 909.500 10 m2 Painting one coat using ready mixed enamel paint 1092.50 10 m2 1092.500 Rate for 10 m2 2002.00 81/88
  • 82. 12/4/2020 Analysis of Rates SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil Problem 14 - White / colour washing over plastered surfaces i) Prepare the data for white washing one coat on plastered surface - 10 m2 . ii) Prepare the data for white washing two coat on plastered surface - 10 m2 . iii) Prepare the data for colour washing one coat on plastered surface - 10 m2 . Material and labour required a) White washing 1 coat with best lime on plastered surface – 10 m2 Shell lime (finely screened) - 0.05m3 Gum - LS Painter II class -1.1nos 82/88
  • 83. 12/4/2020 Analysis of Rates SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil a) White washing 1 coat with best lime on plastered surface – 10 m2 Mazdoor category I - 0.3 nos Mazdoor category II - 1.9Nos Sundries including brushes,etc - L.S b) White washing 2 coat with best lime on plastered surface – 10 m2 Shell lime (finely screened) - 0.07m3 Gum - LS Painter II class -1.6nos Mazdoor category I - 0.5 nos Mazdoor category II - 2.7Nos Sundries including brushes,etc - L.S 83/88
  • 84. 12/4/2020 Analysis of Rates SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil c) Colour washing 2 coats on plastered surface – 10 m2 White washing two coats as per worked previous data - 10 m2 Add 50 % of above rate - 10 m2 Cost of material and labour at site Shell lime - 1500/ m3 Gum - 50 / 100m2 Sundries including brushes, etc - Rs.50 Painter II Class - 750 / Day Mazdoor category I - 700 / Day Mazdoor category II - 500 / Day 84/88
  • 85. 12/4/2020 Analysis of Rates SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil Main data: White washing 1 coat with best lime on plastered surface – 10 m2 Result : Rate for 10 m2 = Rs.2160/- 0.05 m3 Shell lime 1500 m3 75.00 L.S Gum 50 100m2 50.00 1.1nos Painter II class 750 Day 825.00 0.3 nos Mazdoor category I 700 Day 210.00 1.9 nos Mazdoor category II 500 Day 950.00 L.S Sundries including brushes.etc. 50 L.S 50.00 Rate for 10 m2 2160.00 85/88
  • 86. 12/4/2020 Analysis of Rates SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil Main data: White washing 2 coat with best lime on plastered surface – 10 m2 Result : Rate for 10 m2 = Rs.3105/- 0.07 m3 Shell lime 1500 m3 105.00 L.S Gum 50 100m2 50.00 1.6 nos Painter II class 750 Day 1200.00 0.5 nos Mazdoor category I 700 Day 350 2.7 nos Mazdoor category II 500 Day 1350.00 L.S Sundries including brushes.etc. 50 L.S 50.00 Rate for 10 m2 3105.00 86/88
  • 87. 12/4/2020 Analysis of Rates SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil Main data: Colour washing 1 coat as per white washing 2 coats + 50% of the above rate– 10 m2 Result : Rate for 10 m2 = Rs.4657.50/- 10m2 White washing two coats as per worked previous data 3105 10m2 3105.00 10m2 Add 50 % of above rate 1552.5 10m2 1552.50 Rate for 10 m2 4657.50 87/88