Monthly Progress Report 
DAMAC Heights at Dubai Marina 
Report No.7 - September 2014 
Submitted to 
DAMAC Gulf Properties Co. LLC 
P.O.BOX 2195, Dubai 
United Arab Emirates
Monthly Progress Report - September 2014 
Prepared for 
Damac Properties Co. LLC 
P.O.Box 2195, Dubai 
United Arab Emirates 
Prepared by 
AECOM Middle East Limited 
ايست ليمتد ϝ وم ميد Ϝ اي 
PO Box 51028, Dubai 
United Arab Emirates 
www.aecom.com 
30.Sep.14 
© AECOM 2014 
The information contained in this document produced by AECOM Middle 
East Limited is solely for the use of the Client identified on the cover sheet 
for the purpose for which it has been prepared and AECOM Middle East 
Limited undertakes no duty to or accepts any responsibility to any third party 
who may rely upon this document. 
All rights reserved. No section or element of this document may be removed from this document, reproduced, electronically stored or transmitted in any form without the 
written permission of AECOM Middle East Limited. 
Quality Information 
Document 
Monthly Progress Report - September 2014 
Ref Date 16.Okt.14 
Prepared by Sameh Kandil Reviewed by 
Revision History 
Fuad Hasan/Tareq Al Emam 
Authorised 
Name/Position Signature 
Project Director 
Revision Revision Date Details 
0 16.Okt.14
2 
Table of Contents 
Monthly Progress Report No. 7 - September 2014 
Project Description 4 
Tower Statistics 4 
Project Stakeholders 4 
Executive Summary 5 
Key Accomplishments 6 
Key Focus Issues 7 
Area of Concerns 8 
Contract Summary 10 
Milestones 11 
Upcoming Activities - 30 Day Look Ahead 13 
Dashboard Reports 16 
Schedule Progress 17 
Negative Float Contour 21 
Progress Photographs 23 
Health, Safety and Environment 29 
Engineering 31 
Quality Assurance and Control 33 
Commercial Status 35 
Risk Management 37 
Core Values into Practice 38 
AECOM Core Values 39 
Core Values into Practice 40 
Appendices 42 
Appendix 1: Schedule Update (Target Completion Programme-Rev3) 
Appendix 2: Structure Delay 
Appendix 3: Core Walls and Slabs Cycles 
Appendix 4: MEP Progress Data Sheets 
Appendix 5: Finishes Progress Data Sheets 
Appendix 6: External Facade Progress Data Sheets 
Appendix 7: Lifts Progress Data Sheets 
Appendix 8: Garbage Chute Progress Data Sheets 
Appendix 9: Long Lead Items Log 
Appendix 10: Provisional Sum Nomination Log 
Appendix 11: Building Permit Status 
Appendix 12: Technical Review Log 
Appendix 13: Outstanding RFIs 
Appendix 14: Outstanding Shop Drawings 
Appendix 15: Outstanding Material Submittal 
Appendix 16: Outstanding Subcontractors' Prequalification 
Appendix 17: Outstanding Method Statement 
Appendix 18: Non-Conformance Report 
Appendix 19: Actions Log 
Appendix 20: AECOM's Organization Chart
3 
Monthly Progress Report No. 7 - September 2014 
Project 
Description
4 
Project Description 
Tower's Statistics 
DAMAC Heights Tower located at plot No.A3A,392-569 at Dubai Marina and comprises of the following criteria; 
141,542 m2 
3,464 m2 
72,899 m2 
522.67 m2 
335 m 
6 
5 
79 
3 
1 
Dates Projection 
Date of Commencement 19.Jun.11 
Original Project Duration 1096 
Original Completion Date 18.Jun.14 
Forecast Project Duration 2012 
Project Forecast Completion 20.Dez.16 
2 Bedroom 258 
3 Bedroom 86 
4 Bedroom 9 
5 Bedroom 2 
Shops 
Project Stakeholders 
Monthly Progress Report No. 7 - September 2014 
Designation 
1 
Main Contractor 
Supervision Consultant 
MEP Sub-Contractor 
Facade Sub-Contractor 
Building Built Up Area 
Plot Area 
Apartments Built Up Area 
Commercial Built Up Area 
Stakeholders Names 
Ramboll Middle East Limited 
ARABTEC Construction L.L.C 
AECOM Middle East Limited 
REMCO Co. L.L.C 
Elevators Sub-Contractor 
Master Developer 
Local Authorities 
DAMAC Gulf Properties Co. L.L.C 
Toshiba Elevator Middle East L.L.C 
Aluminum & Light Industries Co. (ALICO) Ltd 
Emaar Properties PJSC 
Dubai Municipality 
Client 
Consultant 
BMU Sub-Contractor 
Danway L.L.C 
Fit Out Sub-Contractor JC Maclean International 
Dubai Civil Defense 
DEWA 
Dubai Civil Aviation 
Etisalat 
Number of Flats 
Number of Parking Slot 
Number of Shops 
Total Tower Height 
Top Roof 
Mechanical Floors 
Floors 
30,62,85,86,8 
7,88 
Area/Height Calculations 
Height of Tower 
Floors Count 
Basement&Ground Floors 
Podium Floors 
Typical Floors 
Mechanical Floors 
Apartment Types 
Rooms/Slot Count 
Parking Slots 649 
1 Bedroom 282 
637 
649 
1 
5 
335
5 
Monthly Progress Report No. 7 - September 2014 
Executive 
Summary
6 
Executive Summary 
Monthly Progress Report No. 7 - September 2014 
• DuriŶg the ŵoŶth of Septeŵďer ϮϬϭϰ the projeĐt aĐtiǀities are progressiŶg. The ǁorks for the superstruĐture 
activities are continuing although the overall delays to the project remains. The core walls cycles as well as the slab 
cycles both of which are averaging (6) days. 
• EdžĐaǀatioŶ ǁork has stopped due to a seepage eǀeŶt that oĐĐurred oŶ ϭϳ Septeŵďer, that Đaused floodiŶg iŶ the 
area of section DD. 
• The MEP ϭst aŶd ϮŶd high leǀel serǀiĐes, MEP risers aŶd proǀisioŶ for floor aŶd ǁall serǀiĐes are oŶgoiŶg. The 
progress has improved and the delays will be mitigated by the end of October 2014. 
• The fiŶishes ǁorks iŶĐludes; ďloĐk, plaster, paiŶt aŶd ĐeiliŶg are oŶgoiŶg. 
• The Lift ǁorks has started iŶ the loǁ zoŶe, ŵed zoŶe aŶd high zoŶe. 
• FaĐade ǁorks; StiĐk ĐurtaiŶ ǁall at ďalĐoŶies ĐoŶtiŶues ďLJ ALICO iŶ Ϯϯ floors ĐoŶĐurreŶtlLJ, hoǁeǀer, the uŶitized 
curtain wall system is delayed. Also the glass panels test is still behind schedule. 
• Post-TeŶsioŶiŶg paĐkage froŵ leǀel ϲϰ till leǀel ϴϰ ǁas reǀieǁed ďLJ the ϯrd partLJ aŶd returŶed ďaĐk ǁith 
comments to ATC during the month. 
• DEWA desigŶ paĐkage is oŶ hold aǁaitiŶg the reĐeipt of NOC reŶeǁal froŵ EMAAR. 
• ATC ǁas iŶstruĐted to proĐeed ǁith proĐuriŶg the Bus Bars aŶd LV PaŶels. 
• SH&E reŵaiŶs a foĐus area of iŵproǀeŵeŶt, hoǁeǀer, the projeĐt ĐoŶtiŶues ǁithout LTI. 
• The keLJ risk to the projeĐt reŵaiŶs the laĐk of reǀised IFC doĐuŵeŶts for all leǀels that is peŶdiŶg froŵ the desigŶ 
consultant and will impact the authority packages for approval. Moreover, there is a risk of seepage from the 
existing diaphragm walls. Focus also should be given to finalize all the pending nominations to avoid any potential 
delays. 
Key Accomplishments Key Focus Issues 
Construction Progress Construction Progress 
• There is potential delays in the structure at Level 62 (Mechanical floor) 
as ATC from the Engineer point of view will not be able to achieve the 
planned cycle (8 days) because the width of two wing walls will increase 
and thus the slip form will require reconfiguration. Also the double height 
(5300 mm) will require 2 pours to reach the full height. 
• The structure completion date was slipped 6 calendar days and ATC 
has to mitigate such delays in the forthcoming floors. 
• A solution has to be proposed for the diaphragm wall in order to 
continue the work in Zone B. 
• REMCO has to increase the allocated labors and supervisors. Also ATC 
has to increase its MEP supervisors in order to follow up and expedite 
REMCO progress. 
• REMCO has to provide the partial and full clearance to commence the 
plaster and ceiling work on time. Also the electrical risers work has to be 
improved. 
• Paint (primer & stucco) and ceiling progress to be imporved by ATC. 
• ALCIO has to improve the curtain wall installation. 
• Clearance for sequencing of work to be done to avoid NCRs and 
stoppage of progress. 
• ATC to expidite the progress of Substation's finsihes and MEP works. 
Schedule Progress 
• ATC has to detail the external facade and lift work packages in order to enable 
the Engineer to monitor and control these packages. 
• The Engineer is insisting on adding sufficient details for MEP works in the 
program in order to be able to monitor the MEP package. 
• The overall delays till end of September 2014 is 182 days due to the delay in 
nomination of facade light package, however, the Engineer is of the view that 
the facade light nomination will not affect the project completion date, as the 
light fixtures will be installed before the project completion, which means there is 
sufficient time for procurement and engineering. 
Structure 
•The Slabs were poured up to level 36 and core walls were poured 
up to level 38. The stairs were poured till level 28. 
• The average cycles are 6 days for core walls and slabs. 
• The work in zone B was suspended due to the seepage event. 
However, secant piles breaking is going on in section BB 
progressing 81% complete. 
MEP 
• MEP High Level works are progressing in levels B5,B4,B3,B2 and 
6 till 31. 
• MEP concealed works are progressing from level 6 till 24. 
• MEP risers- HAVC are progressing from level 6 till 22. 
• MEP risers- Fire Fighting are progressing from level 6 till 18. 
• MEP risers- Plumbing are progressing from level 6 till 31. 
• MEP risers- Electrical are progressing from level 6 till 19. 
• MEP ceiling clearance are progressing from level 6 till 9. 
Finishes 
• Block work is progressing from level 6 till 29. 
• Doors sub frames and plaster works are progressing from level 6 
till 22. 
• Paint work is progressing from level 6 till 14 and false ceiling 
started in level 6. 
External Facade 
• ALICO started the installation of Stick frame curtain wall for 
balconies from level 6 till 28. Also the brackets for Unitized system 
and balcony balustrade started from level 6 to 8. 
Lifts 
• Toshiba started the preliminary works and separator steel beams 
in the low, med and high zones. 
Garbage Chute 
• Garbage Chute mock up was done at level 6.
7 
Monthly Progress Report No. 7 - September 2014 
Key Accomplishments Key Focus Issues 
Schedule Progress 
Health, Safety and Environment 
Engineering 
• PT shop drawings for levels (64-84) are under ATC review in order 
to resubmit it again to the 3rd Party for approval. 
• The LV shop drawings are ready for submission to DEWA, 
however, DEWA asked for design NOC's renewal before going 
further with drawings submission for review. 
• ATC continues preparing the shop drawings for false ceiling. 
• AECOM is preparing a proposal to have a permanent solution to 
the diaphragm wall. 
• ATC is preparing the fabrication drawings for the secondary steel 
structure of level 5. 
• A proposal for balcony rain water risers was submitted to Damac. 
• Approval has been obtained for FF and FA of level 5 from Civil 
defense and DM. 
• AECOM is working to provide Zone B's de-strutting sequencing. 
• Material submittal for intercom system, MV switch gear, generator 
and laminated Glass for Balcony Partition were approved. 
• DAMAC advised that the decision is to proceed with stone 
cladding and a sample sent to ATC. 
• An instruction was given to ATC to proceed with procuring the Bus 
bars and LV Panels. 
• The purchase order issued for Corridors tile. 
Quality Assurance and Control 
• 98 NCRs were issued to date and 85 of them are closed. 
• 8 NCRs were issued during this month. 
Commercial Status 
• The flooding delay events are still under review by 3rd party. No 
action is possible on ATC's claims until such time as the EOT 
decision is reached. 
• Variations submission, assessment and approval continues. 
• AECOM asked ATC to submit the PI insurances. 
• Payment Certificate (IPC) for August 2014 is under review. 
Procurement 
• RME has to release the Steam and Sauna package. 
• DAMAC has to finalize the nomination of façade light. 
• DAMAC to re-nominate the sanitary wares package. 
• ALICO to provide the factory production progress report showing the status of 
fabrication and the expected delivery dates. 
• ALICO to expedite the delivery of Cladding Panels and Unitized Curtain Wall 
System. 
• REMCO has to issue the purchase order of the Bus bars and LV Panels. 
Quality Assurance and Control 
• ATC has to improve the quality of concrete works. 
• ATC has to give the structural clearance before the commencement of 
MEP works. 
• ATC to improve quality of submittals to avoid ,multiple re-submission. 
Procurement 
Commercial Status 
• Final concluded report of flooding events has to be issued by DAMAC in order 
to enable Arabtec to issue a revised clause 14 that will reflect the new 
completion date. 
• Processing of agreed variations. 
• Processing of contractor IPCs in line with the contractual time frame. 
• ATC issued the Target Completion Programme - Rev 3 and it is 
under the Engineer's review. The comments will be issued to 
Arabtec by 2nd week of October 2014. 
Health, Safety and Environment 
• More work has to be done regarding the overhead protection. 
• House keeping needs improvement by ATC. 
• Excavation at sections B-B and D-D is a high risk activity. 
• Water Seepage at section DD and BB has to be monitored closely. 
• ineffective pest control in the project site offices. 
• Emergency escape route from level 27 to level 30 is inadequate. 
• More work has to be done to control the dust of Garbage Chute. 
•10 site observation were closed during the month of September 
2014 and 2 notices were issued. 
• Number of first aid cases in September 2014 was (2) and (3) 
cases were recorded for near misses and (0) cases for LTI. 
• 308 orientation for new hires and 195 tool box talk were done 
during September 2014. 
Engineering 
• PT drawings for levels (64-84) has to be resubmitted by ATC for review. 
• Ramboll to provide updated drawings considering the missing electrical points 
for level 43 and above. 
• ATC to issue fabrication drawings for secondary steel structure for P5. 
• AECOM to prepare a proposal to have a permanent solution to the diaphragm 
wall. 
• AECOM to propose the sequencing of de-strutting for Zone B. 
• Ramboll to update the RCP plans considering the existing MEP provisions and 
the bulkhead dimensions for levels 6 till 38. 
• Arch and MEP design drawings (IFC) for Fendi floors from Level 43 to Roof 
has to be finalized. 
• ATC/ALICO to advice about the slab edge clashes with the façade various 
upper levels. 
• Pool designer's full design package to be issued in order to allow DAMAC to 
proceed with the nomination. 
• Emaar NOC has to be obtained in order to enable the submission of LV 
drawings to DEWA. The Renewal of design NOC can't be obtained without 
Emaar NOC.
8 
Area of Concerns 
Area of Concern & Impact if Action not made 
1 
2 
3 
4 
5 
6 
7 
8 
9 
10 
Lack of proposal for a permanent solution to the diphragm wall: 
Impact: Prolongation for the work suspension in Zone B. 
Lack of MEP's IFC revised drawings from Ramboll from level 43 
and above: 
Impact: Delay in relevant shop drawings and thus delays to obtain 
DEWA approval for the shop drawings /schedule of loads and 
delays in procuring LV panels and Bus bars. 
Lack of Façade and Lifts detailed activities in the target 
completion schedule: 
Impact: Prevents AECOM from identifying the Façade and Lifts 
critical activities for the project delivery. Also prevents AECOM 
from closely monitoring the progress at site. 
Monthly Progress Report No. 7 - September 2014 
Required Date 
10.Okt.14 
15.Okt.14 DAMAC/Ramboll 
30.Okt.14 Arabtec 
30.Okt.14 
Lack of manpower for MEP work: 
Impact: REMCO will not be able to give ATC the MEP clearance to 
start the block and plaster works on time as per TCP-rev 3. 01.Okt.14 
Absence of an independent inspection agency for post tension 
installation: 
Impact: The quality of PT works may be affected. Currently ATC is 
not in compliance with the specifications and payment deductions 
will be applied in response. 
30.Okt.14 
Delay in submitting fabrication drawings and shop drawings for 
the secondry steel structure at level P5: 
Impact: Installation of Unitized Curtain Wall will be delayed. 
Delay in the installation of façade glass panels (Stick&Unitized): 
Impact: Potential delays to the suspended ceiling installation. 
01.Okt.14 
8 days Core Wall cycle will not be achieved in level 62 : 
Impact: Potential delays to structure completion date as the 
structure is on the critical bath. 
Responsible Impact 
AECOM/DAMAC 
15.Okt.14 
Arabtec 
ATC/ALICO 
C 
C 
C 
C 
Arabtec C 
ATC/REMCO 
Arabtec 
Lack of de-strutting sequencing in Zone B : 
Impact: Potential delays to the excavation work. 10.Okt.14 AECOM 
Delay in finishes and electrical works inside the substation: 
Impact: Potential delays for handing over the substation to DEWA 
and delay for the permenent power application. 01.Okt.14 ATC 
C 
C 
M 
M 
M
9 
Area of Concerns 
Monthly Progress Report No. 7 - September 2014 
Area of Concern & Impact if Action not made Required Date Responsible Impact 
11 
Critical Manageable 
Lack of instruction to proceed with ordering the marble for Lift 
Lobby: 
Impact: Possibility of installation delays. 
15.Okt.14 DAMAC 
M 
C M
10 
Contract Summary 
Performance Indicators Measure This Month Last Month 
CV EV - AC 
EAC Variance EAC - CP 
Near Misses 3 
* Note: 1) The Cost and Procurement sections will be frozen till 
approving the Target Completion Programme. 
2) SPI and SV improved due to the issuing of TCP-Rev 03. 
Approved 
Claims 
Approved PS 
0 2 26,116,726 
No. of Near Misses 
Schedule Progress % 
Total 
Commitments 
479,041,833 
Variation Status 
Variation Approved 
35 
Financial Status (AED) 
Approved 
Variations 
Upward Trend Downward Trend No Change 
Residual PS Pending 
Effective 
Contract Value 
Gross Certified Physical % 
AED % AED % AED % AED % 
119.845 23.6% 115.38 22.7% 75.44487 14.84% 63.693 12.5% 
Complete 
Variations 
AC - Actual Cost; CPI - Cost Performance Index; CP - Contract Price; CV - Cost Variance; EAC - Estimate At Completion; EV - Earned Value; 
NCR - Non-Conformance Report; PV - Planned Value; RFI - Request For Information; SPI - Schedule Performance Index; SV - Schedule Variance 
79 
* Note: The percentage value is the current amount divided by the Contract Price 
of AED 508,301,847. 
Monthly Progress Report No. 7 - September 2014 
22.46% 
Payment Status (AED m) 
9 9 26 
0.85 
-56.5 
-157 
Area 
Time 
SPI EV / PV 
SV 
Float (MS01) 
0.89 
-44.8 
-182 
EV - PV (AED m) 
Days Float 
Remaining 
CPI EV / AC 
NCR Close Out Issued/Closed 
98/85 92/77 
RFI 
Submittals 
% Closed 88% 
86% 
90% 
88% 
Cost 
Quality 
Health and 
Safety 
Engineering 
244,747,598 
Variation Under DAMAC 
Assessment 
Variation Under 
ATC Assessment 
Total 
Procurement Major Items 
Variation Rejected 
2 
% Closed 
Gross and Net certified figures exclude Advance Payments. 
Estimate at 
Completion 
8,177,509 5 18,378,571 
Net Certified Perviously Certified Paid to Date 
37,437,524 1,899,214
11 
Control Milestones 
Days 
Monthly Progress Report No. 7 - September 2014 
Milestones TCP-Rev 3 Current Forecast Current Float 
Remaining 
Clause 14 
Program 
592 18-Jun-14 
226 08.Aug.13 
159 06.Mär.13 
90% 
34% 
5% 
Nomination of PS Items (not yet nominated) 
Days 
> 5 days 
0 to 5 days 
< 0 days 
Upward 
Trend 
Downward 
Trend 
Milestones TCP - Rev 3 Current Forecast Current Float 
Remaining 
Clause 14 
Program 
-218 2-Feb-12 10 
-41 3-Jun-12 80 
51 21-Nov-12 
35 4-Mar-13 80 
44 80 
-27 17-Apr-13 80 
90% 
34% 
5% 
30.Sep 
Permits/NOCs Status Summary 
Actual 
Issue Date 
23-Jan-11 
14.Nov.13 
25.Nov.13 
10.Jul.14 
171 
SC Nomination for Fit 
Out (Fendi Flat) 
SC Nomination for 
Sauna,Jacuzzi 
13-Nov-14 13-Nov-14 
3-Sep-14 1-Oct-14 
Revised 
Appoval 
Required 
- 30.00 
3.00 
50.00 
Variance 
since Aug 14 
(30.00) 
RME/AECOM 
FIC Location Approval RME/AECOM 
Dubai Municipality 
Fence NOC RME 
SC Nomination for Fit 
Out (Life Style) 
4-Nov-14 4-Nov-14 116 0.00 
SC Nomination for 
Landscaping Works 
20-Nov-14 Nominated 
SC Nomination for 
Swimming Pool Works 
20-Aug-14 1-Oct-14 69 (30.00) 
20 
Ground water Discharge 08.Mai.14 
Drainage Design NOC 
and Drawings Approval 
ATC 
22-Jul-11 
Authority NOC/Permit 
Anticipated 
Issue Date 
Expiry Date 
Days 
Remaining 
Responsible 
0 to 5 days 
< 0 days 
Upward 
Trend 
Downward 
Trend 
No Change 
Note: Days remaining from 30 Sep 2014 to Planned Dates of TCP. 
Variance 
since Aug 14 
MS03 -Producing Wild 
Air (till 30th Floor) 
8-Mar-15 5-May-15 -50 
MS02 -Completion of 
Structure 
14-May-15 20-May-15 -4 
MS01 - Project 
Completion 
14-May-16 20-Dec-16 -182 
0.00 
0.00 
SC Nomination for 
Façade Lighting 
24-Feb-14 1-Oct-14 -178 
No Change 
Note: 
1) Days remaining from 30 Sep 2014 to Planned Dates of TCP. 
2) Variance since Aug-14: the difference between Current forecast of Sep 
vs. forecast of Aug. 
> 5 days
12 
Permits/NOCs Status Summary 
Actual 
Issue Date 
Anticipated 
Issue Date 
NOC/Permit Responsible 
09.Jun.13 
05.Mai.13 
25-Mar-13 
Monthly Progress Report No. 7 - September 2014 
Note: Days remaining from 30 Sep 2014 to Anticipated Date > 60 days 
90% 
34% 
5% 
PerforŵaŶce MeasureŵeŶt – DefiŶitioŶs 
30 to < 60 days 
DEWA - Electrical 
Electrical Load Design 
NOC 
04.Mai.15 RME/AECOM 
Revised 
Appoval 
Required 
LV Design Drawing 
Approval 
Revised 
Appoval 
Required 
RME/AECOM 
Substation / Trench 
Design Approval 
RME/AECOM 
Planned Value (PV) 
Planned value of physical works to be accomplished. 
Actual Cost (AC) 
Actual cost of works physically accomplished. 
Earned Value (EV) 
Budgeted cost of works physically accomplished. 
Schedule Performance Index (SPI) = EV / PV 
SPI represents the current efficiency of progress. 
A SPI >1.0 denotes you are accomplishing more than planned. 
A SPI <1.0 denotes you are accomplishing less than planned 
< 30 days 
Schedule Variance (SV) = EV –PV 
SV represents the difference between what you have 
accomplished and what you planned to accomplish. 
A positive (+) Schedule Variance denotes you are 
ahead of schedule. 
A negative (-) Schedule Variance denotes you are 
behind schedule. 
DEWA - Water 
Water Design NOC 24-Mar-15 RME/AECOM 
RME/AECOM 
Water Supply Design 
Drawing Approval 
Revised 
Appoval 
Required 
Authority 
Days 
Remaining 
Expiry Date 
Revised 
Appoval 
Required 
Dubai Civil Defense Design Drawing Approval 
Revised 
Appoval 
Required 
RME/AECOM
13 
Upcoming Activities - 30 Days Look Ahead 
C 
14 
Monthly Progress Report No. 7 - September 2014 
Activity Type Start Finish Activity 
Slab L37 - Completion 
Slab L38 - Completion 
Slab L39 - Completion 
Slab L40 - Completion 
08.Okt.14 
12.Okt.14 
16.Okt.14 
28.Okt.14 Slab L41 - Completion 
Slab L42 - Completion 
Core Wall L41 - Completion 
Core Wall L42 - Completion 
Core Wall L43 - Completion 
Block Work Completion-L18 
08.Okt.14 
18.Okt.14 
23.Okt.14 
29.Okt.14 
5-Oct-14 
17-Oct-14 
29-Oct-14 
2-Oct-14 
16-Oct-14 
24-Oct-14 
Block Work Completion-L27 
Block Work Completion-L28 
Block Work Completion-L29 
Block Work Completion-L30 
Block Work Completion-L31 
Plaster Work Completion-L20 
Plaster Work Completion-L22 
Plaster Work Completion-L23 
24-Oct-14 Plaster Work Completion-L24 
Plaster Work Completion-L25 
3-Oct-14 
10-Oct-14 
29-Oct-14 
Plaster Work Completion-L21 
21.Okt.14 
03.Nov.14 
Core Wall L39 - Completion 
13.Okt.14 Core Wall L40 - Completion 
Construction 
31-Oct-14 
2-Oct-14 
2-Oct-14 
2-Oct-14 
3-Oct-14 
Paint Work Completion-L6 
Paint Work Completion-L7 
Paint Work Completion-L8 
Paint Work Completion-L9 
6-Oct-14 Paint Work Completion-L10 
9-Oct-14 Paint Work Completion-L11 
13-Oct-14 Paint Work Completion-L12 
17-Oct-14 
27-Oct-14 Paint Work Completion-L15 
Monthly Progress Report No. 7 - September 2014 
9-Oct-14 
Paint Work Completion-L13 
21-Oct-14 Paint Work Completion-L14 
C 
C 
C 
C 
C 
C 
C 
C 
C 
C
Upcoming Activities - 30 Days Look Ahead 
Activity Type Start Finish Activity 
MEP H/L Completion - L29 
C 
C 
C 
C 
ALICO, Toshiba and JC Maclean detailed work schedules will 
be submitted to the Engineer. 
Continue reviewing ATC's new shop drawings submittals. 
30-Oct-14 
31-Oct-14 Finalize the open/overdue shop drawings submittals. 
PT drawings for levels (64-84) will be resubmitted 
again by ATC for 3rd party review. 
Ramboll to provide updated drawings considering the 
25-Oct-14 missing electrical points for level 43 and above. 
Fabrication drawings to be submitted by ATC for the 
Engineer review. 
AECOM to propose the sequencing of de-strutting for 
Zone B. 
DAMAC/AECOM will conclude a solution to the 
diaphragm wall. 
Finalize the open/overdue material submittals. 
1-Oct-14 31-Oct-14 
15-Oct-14 
15-Oct-14 
15-Oct-14 
15-Oct-14 
1-Oct-14 31-Oct-14 
Procurement 21-Oct-14 Unitized curtain wall will be delivered to site. 
Quality 
1-Oct-14 LPO will be issued for Corridor Tiles. 
1-Oct-14 31-Oct-14 ATC will keep closing the outstanding NCRs. 
1-Oct-14 31-Oct-14 
Quality Technical Meeting will be held on weekly basis to 
monitor the quality. 
1-Oct-14 
20-Oct-14 LPO for secondary steel strucutre will be issued. 
1-Oct-14 
20-Oct-14 RME has to release the Steam and Sauna Package. 
Construction 
23.Okt.14 
MEP H/L Completion - L31 
MEP H/L Completion - L32 
11.Okt.14 
20.Okt.14 
27.Okt.14 
MEP H/L Completion - L30 
Schedule 
15-Oct-14 
Electrical design NOC will be issued. 
Engineering 
31-Oct-14 
15-Oct-14 DAMAC will finalize the nomination of Façade Light. 
Re-nomination for the sanitary wares packages by 
DAMAC. 
15-Oct-14 
Continue reviewing ATC's new material submittals. 
C 
C 
C 
C 
C 
C 
C
15 
Upcoming Activities - 30 Days Look Ahead 
DAMAC will continue float tenders and receiving 
quotations for the provisional sum items. 
Critical Path Activity 
1-Oct-14 31-Oct-14 
10-Oct-14 Payment Certificate (IPC) for August 2014 will be issued. 
Commercial 
31-Oct-14 Finalize the list of pending variations submitted by ATC. 
1-Oct-14 
Monthly Progress Report No. 7 - September 2014 
Activity Type Start Finish Activity 
C
16 
Monthly Progress Report No. 7 - September 2014 
Dashboard 
R 
Report
17 
Schedule Progress 
Control Milestones 
Clause 14 
Program 
Current 
Forecast 
Monthly Progress Report No. 7 - September 2014 
-220 
18-Jun-14 20-Dec-16 -182 - 3 0.00 
14-May-15 
-6 
8-Aug-13 20-May-15 -4 3.00 
-58 
6-Mar-13 5-May-15 -50 5 0.00 
26-Aug-13 6-Aug-15 -14 7 9.00 
26-Nov-13 2-Jan-16 -46 1 0.00 
-35 
11-Dec-12 9-Jul-15 -28 - 4 7.00 
5-Jan-13 29-Nov-14 -5 - 8.00 
18-Sep-12 30-Oct-14 -57 4 .00 
23-Mar-14 7-Mar-16 0 - 6.00 
28-Mar-13 7-Oct-15 -28 - 3 6.00 
Upward Trend Downward Trend 
90% 
34% 
5% 
Milestone 
60- Days look Ahead Critical Activities 
TCP - Rev 3 
No Change 
Current 
Forecast 
02.Okt.14 -6 - 6.00 
08.Okt.14 -4 - 3.00 
13.Okt.14 -3 - 3.00 
18.Okt.14 -3 - 3.00 
23-Oct-14 -5 - 5.00 
29.Okt.14 -5 - 4.00 
04.Nov.14 -5 - 6.00 
09.Nov.14 -4 - 5.00 
15.Nov.14 -4 - 6.00 
22-Feb-16 
31-Aug-15 
2) Variance since Aug-14: the difference between Current forecast in Sep 
vs. forecast in Aug. 
Activity 
Slab L37 - Completion 
Slab L38 - Completion 
Slab L39 - Completion 
Slab L41 - Completion 
Slab L42 - Completion 
Slab L43 - Completion 
Slab L44 - Completion 
Slab L45 - Completion 
Total 
Variance 
8-Mar-15 
21-Jul-15 
8-Nov-15 
4-Jun-15 
24-Nov-14 
9-Sep-14 
MS01 - Project Completion 
MS02-Completion of Structure 
MS03 - Producing Wild Air (till 
30th Floor) 
MS04 - Producing Wild Air (31- 
62th Floor) 
MS05 - Producing Wild Air 
(above 62th Floor) 
MS06 - Completion of P5 Slab at 
Zone B 
MS07 - Completion of Block 
Work till Level 36th 
MS08 - Completion of Façade 
Works (level 6 till level 10) 
TCP - Rev 3 Current Float 
-5 
-51 
Variance 
since Aug 14 
Variance 
since Aug 14 
08.Okt.14 
> 5 days 
0 to 5 days 
< 0 days 
28.Okt.14 
03.Nov.14 
09.Nov.14 
13.Nov.14 
19.Nov.14 
-55 
-14 
-37 
12.Okt.14 
-16 
14-May-16 
MS09 - Completion of Lift Works 
MS10 - Commencement of 
Swimming Pool Works 
Note: 1) Total Variance: the difference between TCP and Current Forecast. 
Slab L40 - Completion 21.Okt.14 
Total 
Variance 
16.Okt.14
18 
60- Days look Ahead Critical Activities 
TCP - Rev 3 
Monthly Progress Report No. 7 - September 2014 
25.Nov.14 
30.Nov.14 
20-Nov-14 -5 - 6.00 
25.Nov.14 -5 - 6.00 
30.Nov.14 -6 - 6.00 
01.Okt.14 -7 - 9.00 
08.Okt.14 -5 - 6.00 
13.Okt.14 -5 - 6.00 
19.Okt.14 -4 - 8.00 
23.Okt.14 -6 - 9.00 
29.Okt.14 -5 - 7.00 
03.Nov.14 -5 - 6.00 
09.Nov.14 -4 - 8.00 
15.Nov.14 -4 - 9.00 
19.Nov.14 -5 - 8.00 
24.Nov.14 -5 - 7.00 
29.Nov.14 -5 - 8.00 
Activity 
Slab L46 - Completion 
Slab L47 - Completion 
Slab L48 - Completion 
Core Wall L39 - Completion 
Core Wall L40 - Completion 
Core Wall L41 - Completion 
Core Wall L42 - Completion 
Core Wall L43 - Completion 
Core Wall L46 - Completion 
Core Wall L47 - Completion 
Core Wall L48 - Completion 
Core Wall L49 - Completion 
06.Dez.14 
08.Okt.14 
13.Okt.14 
18.Okt.14 
23.Okt.14 
13.Nov.14 
19.Nov.14 
Core Wall L50 - Completion 04.Dez.14 
3-Oct-14 
Block Work Completion-L18 05.Aug.14 -59 - 3 0.00 
Block Work Completion-L27 28.Sep.14 5-Oct-14 
-7 - 7.00 
Block Work Completion-L28 07.Okt.14 10-Oct-14 
-3 - 6.00 
Block Work Completion-L29 14.Okt.14 17-Oct-14 
-3 - 7.00 
Block Work Completion-L30 26.Okt.14 29-Oct-14 
-3 - 1 3.00 
Block Work Completion-L31 26.Okt.14 29-Oct-14 
-3 - 7.00 
Block Work Completion-L32 30.Okt.14 2-Nov-14 
-3 - 5.00 
Block Work Completion-L33 04.Nov.14 9-Nov-14 
-5 - 6.00 
Block Work Completion-L34 11.Nov.14 16-Nov-14 
-5 - 7.00 
Block Work Completion-L35 18.Nov.14 23-Nov-14 
-5 - 8.00 
Block Work Completion-L36 24.Nov.14 29-Nov-14 
-5 - 8.00 
Plaster Work Completion-L20 06.Sep.14 2-Oct-14 
-26 - 6.00 
Plaster Work Completion-L21 11.Sep.14 9-Oct-14 
-28 - 7.00 
Plaster Work Completion-L22 17.Sep.14 16-Oct-14 
-29 - 8.00 
Plaster Work Completion-L23 22.Sep.14 24-Oct-14 
-32 - 1 0.00 
Plaster Work Completion-L24 28.Sep.14 -26 - 4.00 
Plaster Work Completion-L25 06.Okt.14 -25 - 5.00 
Plaster Work Completion-L26 13.Okt.14 -19 - 2.00 
Plaster Work Completion-L27 21.Okt.14 -16 - 1.00 
Plaster Work Completion-L28 29.Okt.14 11-Nov-14 
-13 - 1.00 
Plaster Work Completion-L29 05.Nov.14 16-Nov-14 
-11 - 4.00 
Plaster Work Completion-L30 16.Nov.14 22-Nov-14 
-6 - 2.00 
Total 
Variance 
Current 
Forecast 
29.Okt.14 
Core Wall L44 - Completion 03.Nov.14 
Core Wall L45 - Completion 08.Nov.14 
Variance 
since Aug 14 
24.Nov.14 
29.Nov.14 
24-Oct-14 
31-Oct-14 
1-Nov-14 
6-Nov-14
19 
60- Days look Ahead Critical Activities 
TCP - Rev 3 
Monthly Progress Report No. 7 - September 2014 
Current 
Forecast 
30-Nov-14 
Plaster Work Completion-L31 16.Nov.14 -14 - 5.00 
Paint Work Completion-L6 12.Jul.14 -82 - 2 6.00 
Paint Work Completion-L7 19.Jul.14 2-Oct-14 
-75 - 2 0.00 
Paint Work Completion-L8 23.Jul.14 2-Oct-14 
-71 - 1 5.00 
Paint Work Completion-L9 30.Jul.14 3-Oct-14 
-65 - 1 6.00 
Paint Work Completion-L10 04.Aug.14 6-Oct-14 
-63 - 1 7.00 
Paint Work Completion-L11 09.Aug.14 -61 - 1 7.00 
Paint Work Completion-L12 13.Aug.14 -61 - 1 7.00 
Paint Work Completion-L13 18.Aug.14 -60 - 1 7.00 
Paint Work Completion-L14 23.Aug.14 -59 - 1 9.00 
Paint Work Completion-L15 27.Aug.14 -61 - 1 9.00 
Paint Work Completion-L16 01.Sep.14 -62 - 1 9.00 
Paint Work Completion-L17 08.Sep.14 -61 - 1 9.00 
Paint Work Completion-L18 15.Sep.14 -60 - 1 9.00 
Paint Work Completion-L19 21.Sep.14 21-Nov-14 
-61 - 2 0.00 
Paint Work Completion-L20 25.Sep.14 27-Nov-14 
-63 - 2 0.00 
Paint Work Completion-L21 01.Okt.14 6-Dec-14 
-66 - 2 3.00 
MEP H/L Completion - L29 07.Okt.14 11.Okt.14 
-4 8.00 
MEP H/L Completion - L30 11.Okt.14 23.Okt.14 
-12 1.00 
MEP H/L Completion - L31 14.Okt.14 20.Okt.14 
-6 7.00 
MEP H/L Completion - L32 20.Okt.14 27.Okt.14 
-7 6.00 
MEP H/L Completion - L33 28.Okt.14 03.Nov.14 
-6 6.00 
MEP H/L Completion - L34 04.Nov.14 10.Nov.14 
-6 6.00 
MEP H/L Completion - L35 11.Nov.14 17.Nov.14 
-6 6.00 
MEP H/L Completion - L36 17.Nov.14 23.Nov.14 
-6 6.00 
MEP H/L Completion - L37 23.Nov.14 29.Nov.14 
-6 7.00 
90% 
34% 
5% 
Variance 
since Aug 14 
Activity 
2-Oct-14 
9-Oct-14 
13-Oct-14 
17-Oct-14 
21-Oct-14 
27-Oct-14 
2-Nov-14 
8-Nov-14 
14-Nov-14 
Total 
Variance 
Upward Trend Downward Trend No Change 
> 5 days 
0 to 5 days 
< 0 days
20 
Physical % Complete 
30 
25 
20 
15 
10 
5 
* Note: Physical % Complete based on TCP - Rev 3. 
Nomination of PS Items 
Clause 14 
Program 
TCP - Rev 3 Current Float 
Var. since 
Aug 14 
7-May-15 
10-Aug-13 7-May-15 51 - 
1-Oct-14 
2-Feb-12 24-Feb-14 -178 - 30.00 
1-Oct-14 
3-Jun-12 20-Aug-14 69 - 30.00 
21-Nov-12 20-Nov-14 
15-Jan-13 18-Apr-13 Nominated 
4-Mar-13 4-Nov-14 116 - 
13-Nov-14 20 - 
17-Apr-13 3-Sep-14 171 - 
90% 
34% 
5% 
SC Nomination for 
Fit Out (Life Style) 
SC Nomination for 
Fit Out (Fendi Flat) 
SC Nomination for 
Sauna,Jacuzzi 
Critical Path (TCP-Rev 3) 
Work Packages 2013 2014 2015 2016 
Planned Actual 
Impact on MS02 
0.89 
Schedule Performance 
Index (SPI) 
SC Nomination for 
Fit Out (Entrance) 
SC Nomination for 
Façade Lighting 
SC Nomination for 
Swimming Pool 
No Change 
Milestone 
Nominated 
Downward Trend 
> 5 days 
0 to 5 days 
Monthly Progress Report No. 7 - September 2014 
Progress % Complete 
Days Remaining until 
MS02 
4-Nov-14 
Impact on MS01 
Concrete Skeleton 
Fit Out after Wild Air 
Façade Glazing 
Lifts 
Testing/Commissioning 
Current 
Forecast 
< 0 days 
13-Nov-14 
1-Oct-14 
Upward Trend 
SC Nomination for 
Landscaping Works 
SC Nomination for 
Roof Steel Works 
Snagging 
9.09 
9.62 10.57 
11.53 12.48 
15.29 
18.4 
22.35 25.15 
7.4 
9.62 10.21 10.81 11.4 
13.62 
16.04 
18.95 
22.46 
0 
Planned % Actual % 
- 182 
- 4 
22.5 
226
21 
Negative Float Contour 
Dominant Causes for Project Delays 
-10 
Monthly Progress Report No. 7 - September 2014 
Critical Paths Analysis 
Paths Package Activities 
Path 3 (Curtain Wall) Path 1 Façade Light 
Nomination, Procurement, 
Engineering, Installation. 
Path 4 (MEP Long Lead Items (Mechanical)) 
-20 
Path 1 (Façade Light) 
Path 2 ( Bus Bars and LV Panels) 
-40 
-144 
-182 
* Note: The shown analysis was run based on TCP-Rev 03, however, this version isn't approved so the shown analysis is only a tentative 
one. 
Path 3 Curtain Wall 
Installation of 7 elements for 
external façade (unitized system, 
stick system, doors, balcony 
partitions, cladding, balustrade and 
louvers. 
Float 
- 182.00 
- 51.00 
Path 4 
MEP Long Lead 
Items (Mechanical) 
CW pumps submission/approval, 
procurement/installation, producing 
wild air, fit out works by JC 
Maclean. 
- 50.00 
Path 2 
-144 days 
Path 1 
-182 days 
Path 3 
-51 days 
Path 4 
-50 days 
-182 THIS MONTH 
DELAYS IDENTIFIED 
Path 2 
Bus Bars and LV 
Panels 
Procurement/installation of Bus 
Bars and LV Panels. 
- 144.00 
Analysis run on 30-September-14
22 
Risk Analysis 
Risk Analysis on Critical Paths 
Monthly Progress Report No. 7 - September 2014 
• Risk: Delay of -182 days 
• Driver: Late of Nomination of Façade Light 
• Mitigation: 
• The Engineer is of the view that the facade light 
nomination will not affect the project completion 
date, as the light fixtures will be installed before 
the project completion, which means there is 
enough time for procurement and engineering. 
• However, it is recommended that the client to 
expedite the nomination to avoid any risk to 
coordinate procurement with other parties. 
• Risk: Delay of -144 days 
• Driver: Procurement of Bus Bars and LV 
Panels 
• Mitigation: 
• An instruction issued by DAMAC to ATC to 
proceed with procuring the Bus Bars and LV 
Panels. The LPO will be issued during the month 
of October 2014. 
• On the other hand DAMAC/AECOM are working 
to get the NOC from Emaar in order to seek the 
design NOC from DEWA. 
Analysis run on 30-September-14 
• Risk: Delay of -51 days 
• Driver: Delay in Curtain Wall Installation 
• Mitigation: 
• The design of secondry steel structure was done 
by ALICO. 
• ATC to submit the fabrication drawings to the 
engineer for approval. 
• Unitized panels will be delivered to site by 21- 
Oct-14. 
• Risk: Delay of -50 days 
• Driver: Chilled Water Pumps 
• Mitigation: 
• On the basis that the chilled water pumps will 
contribute in producing wild air so that the delay 
in submission the material submittal affected the 
delivery date to site and thus affected the 
commencement of wild air operation. However, 
the pumps are approved and the purchase order 
will be issued during August 2014. 
• The Engineer is of the view that the wild air is a 
vague issue so that Arabtec has been instructed 
many time in the weekly progress meetings to 
plan the wild air operation to allow the fit out 
work start and submit a proposal for review, 
however, ATC stated that the term ''wild air'' is 
not in the contract. 
Path 1 
Path 2 
Path 3 
Path 4 
Path 1 Path2 Path3 Path 4 
200 
180 
160 
140 
120 
100 
80 
60 
40 
20 
0 
Paths 182 144 51 50 
Delays 
Critical Paths
23 
Slabs Planned Pouring Actual Pouring Progress Variance 
23rd floor 02.Jul.14 4-Jul-14 100% - 2 .00 
24th floor 10.Jul.14 10-Jul-14 100% - 1 .00 
25th floor 19.Jul.14 17-Jul-14 100% 1 .00 
26th floor 26.Jul.14 23-Jul-14 100% - 1 .00 
27th floor 03.Aug.14 1-Aug-14 100% 1 .00 
28th floor 09.Aug.14 9-Aug-14 100% - 
29th floor 16.Aug.14 14-Aug-14 100% - 
30th floor 23.Aug.14 22-Aug-14 100% - 1 .00 
31st floor 31.Aug.14 31-Aug-14 100% - 
32nd floor 06.Sep.14 7-Sep-14 100% - 1 .00 
33rd floor 11.Sep.14 12-Sep-14 100% - 
34th floor 16.Sep.14 18-Sep-14 100% - 1 .00 
35th floor 21.Sep.14 24-Sep-14 100% - 1 .00 
36th floor 27.Sep.14 30-Sep-14 100% - 3 .00 
Progress Photographs 
Structure Progress - Level 36 
Zone B - Section DD; Seepage Area 
Monthly Progress Report No. 7 - September 2014 
57.12% 
5.69% 
17.50% 
9.42% 
12.38% 
%Pld %Act 
0.00% 
0.00% 
3.42% 
56.34% 
3.38% 
16.04% 
20.63% 
2.10% 
0.38% 
DAMAC Heights 
Tower
24 
Core Walls Planned Pouring Actual Pouring Progress Variance 
23rd floor 21.Jun.14 15-Jun-14 100% - 
24th floor 30.Jun.14 19-Jun-14 100% 2 .00 
25th floor 06.Jul.14 26-Jun-14 100% 2 .00 
26th floor 13.Jul.14 3-Jul-14 100% - 1 .00 
27th floor 20.Jul.14 14-Jul-14 100% - 1 .00 
28th floor 27.Jul.14 21-Jul-14 100% - 1 .00 
29th floor 04.Aug.14 27-Jul-14 100% 1 .00 
30th floor 11.Aug.14 13-Aug-14 100% 2 .00 
31st floor 18.Aug.14 17-Aug-14 100% 7 .00 
32nd floor 23.Aug.14 24-Aug-14 100% - 1 .00 
33rd floor 28.Aug.14 28-Aug-14 100% 6 .00 
34th floor 03.Sep.14 3-Sep-14 100% - 3 .00 
35th floor 08.Sep.14 14-Sep-14 100% - 2 .00 
36th floor 16.Sep.14 17-Sep-14 100% - 6 .00 
37th floor 22.Sep.14 25-Sep-14 100% - 3 .00 
38th floor 27.Sep.14 29-Sep-14 100% - 1 .00 
Progress Photographs 
Dry Area: False Ceiling Suspension System @ Level 6 
Corridor: False Ceiling Boards @ Level 6 
Monthly Progress Report No. 7 - September 2014 
57.12% 
5.69% 
17.50% 
9.42% 
12.38% 
%Pld %Act 
0.00% 
0.00% 
3.42% 
56.34% 
3.38% 
16.04% 
20.63% 
2.10% 
0.38% 
DAMAC Heights 
Tower
25 
HVAC HL Works Planned Finish Actual Finish Progress Variance 
24th floor 30.Aug.14 91% 
25th floor 06.Sep.14 90% 
26th floor 13.Sep.14 90% 
27th floor 21.Sep.14 84% 
28th floor 28.Sep.14 69% 
29th floor 07.Okt.14 52% 
FF HL Works Planned Finish Actual Finish Progress Variance 
24th floor 30.Aug.14 99% 
25th floor 06.Sep.14 98% 
26th floor 13.Sep.14 96% 
27th floor 21.Sep.14 96% 
28th floor 28.Sep.14 88% 
29th floor 07.Okt.14 78% 
Progress Photographs 
Wet Area: Wall Tiles and Water Proofing @ Level 6 
Painting (Primer & Putty) @ Level 13 
Monthly Progress Report No. 7 - September 2014 
57.12% 
5.69% 
17.50% 
9.42% 
12.38% 
%Pld %Act 
0.00% 
0.00% 
3.42% 
56.34% 
3.38% 
16.04% 
20.63% 
2.10% 
0.38% 
DAMAC Heights 
Tower
26 
Progress Photographs Monthly Progress Report No. 7 - September 2014 
Plumbing HL Work Planned Finish Actual Finish Progress Variance 
24th floor 30.Aug.14 95% 
25th floor 06.Sep.14 95% 
26th floor 13.Sep.14 95% 
27th floor 21.Sep.14 95% 
28th floor 28.Sep.14 95% 
29th floor 07.Okt.14 49% 
Electrical HL Work Planned Finish Actual Finish Progress Variance 
24th floor 30.Aug.14 94% 
25th floor 06.Sep.14 80% 
26th floor 13.Sep.14 94% 
27th floor 21.Sep.14 90% 
28th floor 28.Sep.14 90% 
29th floor 07.Okt.14 84% 
MEP High Level Service @ Level 27 
Foundation for Equipment @ Level 30 
57.12% 
5.69% 
17.50% 
9.42% 
12.38% 
%Pld %Act 
0.00% 
0.00% 
3.42% 
56.34% 
3.38% 
16.04% 
20.63% 
2.10% 
0.38% 
DAMAC Heights 
Tower
27 
Monthly Progress Report No. 7 - September 2014 Progress Photographs 
Blocks Planned Finish Actual Finish Progress Variance 
17th floor 27-Jul-14 95% 
18th floor 5-Aug-14 50% 
19th floor 10-Aug-14 95% 
20th floor 16-Aug-14 95% 
21st floor 20-Aug-14 95% 
22nd floor 27-Aug-14 95% 
23rd floor 1-Sep-14 95% 
24th floor 7-Sep-14 95% 
25th floor 13-Sep-14 95% 
26th floor 20-Sep-14 95% 
27th floor 28-Sep-14 70% 
28th floor 7-Oct-14 15% 
29th floor 14-Oct-14 5% 
Substation - Trenches and Block Wall 
Stick Curtain Wall - Aluminium Cladding 
57.12% 
5.69% 
17.50% 
9.42% 
12.38% 
%Pld %Act 
0.00% 
0.00% 
3.42% 
56.34% 
3.38% 
16.04% 
20.63% 
2.10% 
0.38% 
DAMAC Heights 
Tower
28 
Concealed MEP Planned Finish Actual Finish Progress Variance 
19th floor 21-Aug-14 98% 
20th floor 27-Aug-14 99% 
21st floor 02.Sep.14 96% 
22nd floor 08.Sep.14 96% 
23rd floor 13.Sep.14 90% 
24th floor 18.Sep.14 59% 
Plaster Planned Finish Actual Finish Progress Variance 
17th floor 19-Aug-14 95% 
18th floor 26-Aug-14 2% 
19th floor 1-Sep-14 95% 
20th floor 6-Sep-14 70% 
21st floor 11-Sep-14 13% 
22nd floor 17-Sep-14 5% 
Progress Photographs 
Stick Curtain Wall - Galss Panels 
Brackets Installation for Balcony Balustrade 
Monthly Progress Report No. 7 - September 2014 
57.12% 
5.69% 
17.50% 
9.42% 
12.38% 
%Pld %Act 
0.00% 
0.00% 
3.42% 
56.34% 
3.38% 
16.04% 
20.63% 
2.10% 
0.38% 
DAMAC Heights 
Tower
29 
Health, Safety & Environment 
HSE Statistics 
Total Hours 
Worked 
Work Force 
(Average) 
Monthly Progress Report No. 7 - September 2014 
Fatalities Lost Time Injury 
First 
Aid 
Cases 
Near 
Misses 
381,010 1465 0 0 2 3 
4,292,339 1402 0 4 182 15 
4,673,349 0 0 4 184 18 
* Note: 
HSE Site Inspections 
Site Observations 
Notices (Improvement & 
Stop Works) 
Issues Closed Open Issued Closed Open 
Safety 
Audits 
(Average) 
5 - 14 10 4 2 1 2 
128 - 174 172 2 22 21 1 
133 - 188 182 6 24 22 2 
HSE Training & Seminars 
Orientation 
for New Hires 
308 
4,440 
4,748 
Significant Incidents 
1 
2 
3 
4 
5 
6 
Critical Manageable 
Severe Negligible 
This Month 
19 
No. of Training Tool Box Talks Safety Training 
Safety Meetings 
Description/Comments Risk Rate 
Joint 
Inspections 
Recordable 
Injuries 
0 
19 
Previous Months 
Total Project 
This Month 
Previous Months 
Total Project 
4 
66 
70 
Current Month 
Previous Months 
Total Project 
195 
1346 
1541 
5 
60 
65 
Water seepage in section DD and a subsequent soil settlement along section BB and DD. 
C 
S 
M 
N 
C
30 
May Statistics 
0 
(0) 
0 
(4) 
0 
(19) 
2 
(184) 
14 
(188) 
LTI & Lost Work Days 
Monthly Progress Report No. 7 - September 2014 
Fatalities 
LTI 
Total Hours Worked this 
Month 
Total Hours Worked Previous 
Months 
Total Hours Worked For the 
Project 
Work Force Average 
Notices Issued this Month 
Current Month 
(Cumulative Contract) 
Recordable Injuries 
First Aid Cases 
Site Observations 
Eye Injuries 
0 (22) 
Back Injuries 
0 (4) 
Face Injuries 
0 (9) 
Trunk Front Injuries 
0 (4) 
Hand Injuries 
1 (62) 
Head Injuries 
0 (4) 
Arm Injuries 
1 (28) 
Leg Injuries 
1 (35) 
Ankle/Foot Injuries 
0 (14) 
3.5 
3 
2.5 
2 
1.5 
1 
0.5 
0 
Lost Time Injury (LTI) 
Lost Work Days (LWD) 
381,010 
4,292,339 
4,673,349 
1465 
2
31 
Engineering 
NOCs Status Summary 
Actual 
Issue Date 
17.Sep.13 
GSM NOC RME/AECOM 
19.Jun.14 - 
23.Jän.11 
14.Nov.13 
25.Nov.13 
10.Jul.14 
09.Jun.13 
27.Mai.14 
06.Jul.14 
05.Mai.13 
25-Mar-13 
27-Dec-11 
25-Jun-12 
9-Sep-13 
90% 
# 34% 30 to < 60 days 
5% 
RME 
> 60 days 
< 30 days 
Note: Days remaining from 30 Sep 2014 to Anticipated Date 
Expiry Date 
Days 
Remaining 
Responsible 
Dubai Civil Aviation 
26.Mai.15 RME/AECOM 
RME/AECOM 
DEWA - Electrical 
Electrical Load 
Design NOC 
04.Mai.15 RME/AECOM 
LV Design Drawing 
Approval 
Revised 
Approval is 
required 
RME/AECOM 
Substation / Trench 
Design Approval 
Revised 
Approval is 
required 
RME/AECOM 
Authority 
Etisalat Design NOC 
& Drawings Approval 
Monthly Progress Report No. 7 - September 2014 
NOC/Permit 
Anticipated 
Issue Date 
Height NOC 
Warning Light NOC 
Revised 
Approval is 
required 
Final NOC after 
final design 
approval. 
Water Supply Design 
Drawing Approval 
Revised 
Approval is 
required 
RME/AECOM 
Revised 
Approval is 
required 
Revised 
Approval is 
required 
16.Sep.15 RME/AECOM 
Etisalat 
RME 
ATC 
RME/AECOM 
RME/AECOM 
Revised 
Approval is 
required 
Dubai Municipality 
Fence NOC 22.Jul.11 
Ground water 
Discharge 
08.Mai.14 
Drainage Design NOC 
and Drawings 
Approval 
FIC Location Approval 
Dubai Civil Defense 
Design Drawing 
Approval 
RME/AECOM 
DEWA - Water 
Water Design NOC 24-Mar-15 RME/AECOM 
EMAAR 
Water Seepage 
Remedial Works 
RME 
Dewatering 
Conditional NOC 
24-Dec-12 RME 
Drainage NOC 9-Dec-13
32 
Critical Authorities Issues 
Authority Action 
Subject 
NOCs & 
Dwgs. 
NOC 
DEWA, DM and Civil Defence 
Revised approvals are required due 
to the architectural changes. 
Engineering Submittal Status Report 
Planned Date Current Forecast 
1 2 3 4 5 6 
17 3 12 - 1 0 1 
1266 58 1055 6 73 66 8 
72 37 28 1 5 1 0 
209 39 128 0 17 22 3 
3- Revise& Resubmit 5- Under Review 
4- Rejected 6- Review not required 
* Note: Only 2014 submittals have been considered. 
Submitted Open Closed 
367 35 332 
209 39 170 
72 7 65 
90% 
81% 
90% 
19 89% 
1266 145 1121 
17 1 16 
1931 227 1704 
Monthly Progress Report No. 7 - September 2014 
EMAAR 30.Okt.14 
1- Approved 
2- Approved as Noted 
Request for 
Information 
Materials 
Method Statement 
Prequalification 
Approval 
* Note: Only 2014 submittals have been considered. 
94% 
0 
5 
0 
Review Category 
Submittals Closed 
% RFIs Closed 
Document Submittal 
Prequalification 
Approval 
NOC has to be given by Emaar in 
order to seek the design NOC from 
DEWA. 
Submitted 
0 
Total 88% 
Number of Submittals 
Submittals Open 
Shop Drawings 
Method Statements 
Materials 
Document Submittal Overdue % Closed 
Shop Drawings 
88% 
12% 
Submittals Closed 
Submittals Open 
1931 
1704 
227 
90%
33 
Quality Assurance & Control 
Non-Conformance Reports (NCR) 
Category 1: Per Work Package 
Monthly Progress Report No. 7 - September 2014 
September NCRs Total NCRs 
Issued Closed Open Issued 
Close 
d 
Open Issued Closed Open 
8 7 1 0 0 0 8 7 1 
68 57 11 3 6 2 71 63 8 
3 2 1 1 1 1 4 3 1 
11 11 0 4 1 3 15 12 3 
0 0 0 0 0 0 0 0 0 
0 0 0 0 0 0 0 0 0 
90 77 13 8 8 6 98 85 13 
General 
Architectural 
MEP 
Lifts 
Category 2: Per Root Causes 
September NCRs Total NCRs 
Issued Closed Open Issued 
Close 
d 
Open Issued Closed Open 
5,16,44,45,56,62, 
64,73,86. 
9 8 1 0 1 0 9 9 0 
6,8,11,12,14,15,21,22,2 
3,24,26,27,29, 
32,38,39,43,51,53,54,8 
0,81,98. 
22 22 0 1 1 0 23 23 0 
9,28,99,102,104. 2 1 1 3 0 3 5 1 4 
34,49,50,66. 4 4 0 0 0 0 4 4 0 
1,37,40,69,82. 5 5 0 0 0 0 5 5 0 
10,13,17,18,19,20,25,3 
0,31,33,35,41,46,47,48, 
52,55,57,58,59,60,65,6 
8,70,71,72,74,75,76,77, 
78,79,83,84,85,88,89,9 
0,91,94,96,100,101. 
40 30 10 3 5 3 43 35 8 
2,3,7,42,61,63,67,87,95 
. 
8 7 1 1 1 0 9 8 1 
90 77 13 8 8 6 98 85 13 
Use of Unapproved Drawings/Materials 
Deviation from Specifications 
Not Following Manufacturer's Instructions 
Deviation from the Safety Requirements 
Not working as per Method Statement 
Bad Workmanship 
Others 
Total 
Use of Unapproved 
Drawings/Material 
Total 
Work Area 
Previous NCRs 
Others 
NCR ID 
Deviation from Specifications 
Not Following Manufacturer's 
Instructions 
Deviation from the Safety 
Requirements 
Not working as per Method 
Statement 
Bad Workmanship 
Previous NCRs 
Work Area 
Structural 
External Façade 
9 
23 
5 
4 
5 
43 
9 
A 
B 
C 
D 
E 
F 
G
34 
Key Quality Improvement Measures 
Implemented in the Month 
• CurreŶtlLJ ATC keeps suďŵittiŶg the ĐoŶĐrete test results iŶ tiŵelLJ ŵaŶŶer 
as was instructed by AECOM. 
• AECOM iŶstruĐted ATC to suďŵit the struĐtural ĐlearaŶĐe ďefore the 
commencement of MEP work. 
• AECOM is going to hold Quality Technical Meetings on weekly basis to 
monitor the quality. 
Audits 
Internal External 
Quality Trending 
Monthly Progress Report No. 7 - September 2014 
NCR Closed % 
NCR Opened % 
Total NCRs Raised 
NCRs Closed 
NCRs Opened 
8 NON-CONFORMANCE 
IDENTIFIED THIS 
MONTH 
Quality Improvement Measures 
3 
9 
4 
6 
3 3 
13 
9 
6 
5 
13 
8 
14 
12 
10 
8 
6 
4 
2 
0 
NCR Raised 
87% 
13% 
98 
85 
13
35 
Commercial Status 
Cost Summary (AED) 
Monthly Progress Report No. 7 - September 2014 
244,747,598 8,177,509 - 226,116,726 479,041,833 37,437,524 1,899,214 
20,000,000 7,738,272 - - 27,738,272 - 
297,020 389,706 686,726 515,808 
GHU 1,676,655 
1,595,000 81,655 - - 1,676,655 - - 
Payment Status (AED) 
AED % AED % AED % AED 
119,845,391 23.58% 115,383,973 22.7% 75,444,872 14.8% 63,693,496 
21,989,206 79.3% 21,989,206 79.3% 21,436,431 77.3% 21,792,331 
686,726 100.0% 618,053 90.0% 418,956 61.0% 618,053 
1,403,119 83.7% 1,262,807 75.3% 1,355,221 80.8% 1,320,372 
516479357.2 
27738271.57 
686726.1 
* Note: The percentage value is the current amount divided by the Contract Price 
ATC IPC# 39 (Aug-14) was considered for this report. 
ATC 
RMB 
IGS 
GHU 
Variation Status 1676655 
Variation 
Approved 
Cumulative Current Month 
Variation 
Rejected 
Variation 
DAMAC 
Assessment 
Variation 
ATC 
Assessment 
Variation 
Approved 
Variation 
Rejected 
Variation 
DAMAC 
Assessment 
35 9 9 26 0 0 0 
Variation Value (AED) 
Variation 
Approved 
Variation 
Rejected 
Variation 
DAMAC 
Assessment 
Variation 
ATC 
Assessment 
Variation 
Approved 
Variation 
Rejected 
Variation 
DAMAC 
Assessment 
8,177,509 6,801,791 1,679,024 220,190 
Key Commercial Issues 
1 
2 
Monthly Progress Report No. 7 - September 2014 36 
All Gross/Net Certified and Paid to Date Values excluded Advance Payments. 
Item Management Strategy 
Extension of Time Claims 
EOT flooding claims are under review by 3rd party, anticipated closure in 
October 2014. 
ATC's Pending Variations Variations submission, assessment and approval continues. 
Variation ATC 
Assessment 
ATC 0 
Cumulative Current Month 
Variation ATC 
Assessment 
ATC 
12.53% 
78.56% 
95.29% 
81.63% 
Effective 
Contract 
Value 
Approved 
Variations 
Approved 
Claims 
Approved PS 
Total 
Commitments 
Residual 
PS 
Pending 
Variations 
Estimate at 
Completion 
ATC 518,378,571 
RMB 27,738,272 
IGS 1,202,534 
Paid to Date 
% 
Gross Certified Net Certified Previously Certified
Cash Flow (AED,000) 
1,300 
1,200 
1,100 
1,000 
900 
800 
700 
600 
500 
400 
300 
200 
100 
Notice of Delays Under Review 
Ref 
. 
Date Received 
Delayed nomination of Elevators 
Delayed nomination of MEP 
Delayed nomination of Glazing 
1 19-Feb-12 
2 19-Feb-12 
3 19-Feb-12 
4 Delayed nomination of BMU 
19-Feb-12 
5 Delayed nomination of Façade Light 
19-Feb-12 
6 Delayed nomination of Sanitary Fittings 
19-Feb-12 
7 Delayed nomination of Home Automation 
19-Feb-12 
8 19-Feb-12 
9 19-Feb-12 
10 19-Feb-12 
11 2-Apr-12 
12 2-Apr-12 
13 6-May-13 
14 6-May-13 
15 6-May-13 
16 6-May-13 
17 6-May-13 
18 6-May-13 
19 6-May-13 
20 6-May-13 
21 18-Aug-13 
22 12-Feb-14 
23 5-Mar-14 
23.58 
12.53 
Delayed nomination of Kitchen Cabinet 
Delayed nomination of Shower Enclosure ATC Total Variations 
Delayed nomination of Timber Doors/Ironmongery Approved 
Delayed nomination of Vanity Counter 
Delayed nomination of Swimming Pool 
Delayed nomination of Toilet Access. 
Delayed nomination of Light Fittings 
Delayed nomination of Roof Features Equipment 
Delayed nomination of Fit out for Entrance 
* Note: Only SC's nominations delays have mentioned. 
Ref 
. 
35 
ATC Total Variations 
Rejected 
Delayed nomination of Wardrobe, Vanaties 
Delayed nomination of Mirrors 
Delayed nomination of Landscape 
Delayed nomination of Fit out for HC 
Delayed nomination of Supply Porcelain/Ceramic Tiles 
Item Date Received 
No Claims closed to date - 
ATC Total Variations 
Delayed nomination of Fit out for Saunna,Steam and Pending 
Delayed nomination of Fit out for Signage/Lockers 
Claims Closed 
ATC Gross % Certified 
* Note: Cash flow will be produced after agreeing the target completion program. 
Item ATC Paid % to Date 
35 
9 
0 
Monthly Planned 
Monthly Actual 
Cum. Planned 
Cum. Actual
37 
Risk Management 
Top 7 Risks 
RS_04 
Risk Event Cause Risk Response 
Delays in possessing 
DEWA approval for LV 
shop drawings and delays 
in procuring LV Panels and 
Bus Bars 
Re-design of secondary 
steel structure to support 
the façade 
Changes to the mechanical 
floors arrangement and 
absence of the design for 
P5. 
Monthly Progress Report No. 7 - September 2014 
ALICO designed the secondary steel 
structure. ATC to expidite submission 
of fabrication drawings for approval in 
order to place the material order. 
DAMAC/R 
ME 
ATC 
Risk ID Rating 
Risk 
Owner 
DAMAC/ 
AECOM 
RS_01 
RS_02 
Late of issuing MEP IFC 
drawings. 
RME to issue the final MEP IFC 
drawings. Also the renewal of DEWA 
design NOC to be done. On the other 
hand an instruction to proceed with 
procurment was issued by DAMAC. 
Flooding in Zone B 
Seepage through openings 
in the existing diaphragm 
walls. 
Seepage occurred during September 
2014 and AECOM will provide a 
proposal for a permanent soluation to 
the diaphragm wall. 
ATC/ 
REMCO 
RS_03 
Delays in pouring the slab 
of level 62 
8 days estimated cycle will 
not be achieved as the 
core wall will need for 2 
weeks at least. 
AECOM highlighted this issue to ATC in 
the weekly progress meeting, 
however, no mitigation provided. 
ATC 
RS_05 
Delays In MEP high level 
installations, Concealed 
Work and Risers Work 
Delays from REMCO in 
high level works 
installation due to 
insufficient of manpower. 
REMCO to increase the allocated 
manpower in order to work 
concurrently in 5 levels. 
RS_07 BMU Functionality 
DAMAC 
ALICO 
RS_06 
Delays in nomination of 
the PS items 
DAMAC's tenders 
floating/awarding process 
delayed. 
DAMAC has to expedite the PS items' 
procuring process in order to avoid 
delaying the site works. Notably 
façade light package. 
There is no coordination 
between the BMU and 
Façade Designs. 
Alico is doing the technical study. 
Risk Rating Breakdown 
5 
4 
3 
2 
1 
0 
Critical Severe Manageable Negligible 
Critical 
Severe 
Manageable 
Negligible
38 
Core Values 
into Practice 
R 
Monthly Progress Report No. 7 - September 2014
39 
AECOM Core Values 
'To enhance and sustain the world’s built, natural and social environments'' 
Monthly Progress Report No. 7 - September 2014 
Growth 
We recognize that our financial growth is the fairly earned result of living up to these 
principles. 
We earn and advance our reputation by delivering superior value on every project that we 
undertake. 
Our industry leadership depends on making project solutions more exciting, 
sustainable and cost-effective. 
We move with speed and dexterity to adapt and adjust to emerging client and project 
requirements. 
9 Core Values 
We succeed by doing things the right way, with respect to ethics, laws, standards of 
quality, and each other. 
Employees 
Our product is our people — our knowledge, skills, passion and diversity. Our success 
begins with valuing our people and fostering their development. 
We succeed by making our clients successful. We embrace our clients’ challenges 
and opportunities and work for their success. 
Whether in an office or on a construction site, keeping our people safe is our most 
important measure of success. 
Clients 
Excellence 
Innovation 
Safety 
Integrity 
Agility 
File :- Printed On :- 16.10.2014 at 10:38
40 
Core Values into Practice 
AECOM Solutions 
Time Cost 
1 
AECOM advice to allow the 
building tower to proceed 
beyond Level 15 in absence 
of Zone B Raft being 
completed. 
15 weeks + delays EOT Costs 
High 
AECOM reviewed the 
Structure and concluded 
that there was no impact 
on the design to allow the 
tower structure to 
proceed without Zone B. 
CS-Site based 
Structural 
B+P-Structural 
Implemented 
by AECOM and 
closed impact 
negated. 
No: It is Design Related. 
Design decision required 
from Ramboll- however 
design consultant did not 
provide an adequate 
response. 
INT, 
CLN, 
EX, AG, 
SA 
2 
Soil Improvement outside 
the plot to stabilize extent 
monitoring and supervision 
and the need to decide 
when to commence 
excavation. 
Continued delay 
to Zone B 
construction 
added to the 
current claim by 
ATC for flood 
event including 
suspension of all 
work. 
EOT Costs+ 
Damages + 
Insurance 
claims+suspension 
of work costs. 
High 
AECOM reviewed the 
Client proposed solution 
and methodology and 
devised an 
implementation plan in 
coordination with AECOM 
Geotechnical department 
to minimize the risk on the 
area and provided an 
implementation plan with 
monitoring and 
contingency measures to 
allow for commencement 
of excavation work. 
CS-Site based 
Civil/ Structural 
TRN-Geotechnical 
Implemented 
by AECOM 
ongoing 
No: AECOM Scope covers 
supervision services and 
monitoring only. 
AECOM provided advice 
and recommendations to 
the implementation of the 
solution proposed by the 
client without any liability 
for the success or failure 
of the solution proposed. 
 
INT, 
CLN, 
EX, AG, 
SA 
AECOM Values Legend 
Monthly Progress Report No. 7 - September 2014 
Sr. Description 
Impacted if not addressed 
Risk AECOM Solution 
AECOM 
Discipline 
involved 
Status Included in Scope 
AECOM 
Values 
INT: Integrity CLN: Client GR: Growth EX: Excellence INN: Innovation AG: Agility EMP: Employees SA: Safety 
9 Core Values 
File :- Printed On :- 16.10.2014 at 10:38
41 
Core Values into Practice 
AECOM Solutions 
Time Cost 
3 
Sub Contractor for Post-tensioned 
slab design 
highlighting punching shear 
overstress in various 
columns from levels 26 and 
above. 
Delay to the 
casting of the 
slabs. 
Increased cost of 
adding 
reinforcement 
and concrete as 
drop caps and 
shear 
reinforcement at 
the identified 
columns. 
Medium 
AECOM site structural 
team reviewed the 
calculations and advised 
that the sub contractor 
was not applying the loads 
correctly thereby 
eliminating the added 
measures. 
CS-Site Structural Implemented 
by AECOM and 
closed negating 
the impact 
Monthly Progress Report No. 7 - September 2014 
No: It is Design Related. 
Design decision required 
from Ramboll- however 
design consultant did not 
provide adequate 
response, AECOM 
provided the guidance 
through on site workshop 
and obtained Design 
Consultant, 3rd party and 
Employer consensus 
resulting in the sub 
contractor revising his 
comments. 
 
INT, 
CLN, 
EX, AG, 
SA 
4 
AECOM Values Legend 
Included in Scope 
AECOM 
Values 
INT: Integrity CLN: Client GR: Growth EX: Excellence INN: Innovation AG: Agility EMP: Employees SA: Safety 
9 Core Values 
Sr. Description 
Impacted if not addressed 
Risk AECOM Solution 
AECOM 
Discipline 
involved 
Status 
File :- Printed On :- 16.10.2014 at 10:38
42 
Appendices 
R 
Monthly Progress Report No. 7 - September 2014
QATAR 
ACCOUNT 
MANAGEMENT 
PROGRAM 
Damac Heights 
Appendix 1 
Schedule Update
Activity ID Activity Name Original 
Duration 
DAMAC Gulf Properties L.L.C 
DAMAC Heights at Dubai Marina 
Planned Start Planned Finish Actual/Forecast 
Start 
Actual/Forecast 
Finish 
Total 
Float 
Planned % 
Complete 
Actual % 
Complete 
SPI 
2014 2015 
Total 2012.00 24-Feb-14 14-May-16 05-Jun-11 A 20-Dec-16 -220.00 25.15% 22.46% 0.89 
DAMAC HEIGHTS-Target Completion Programme- Rev 3.1 2012.00 24-Feb-14 14-May-16 05-Jun-11 A 20-Dec-16 -220.00 25.15% 22.46% 0.89 
GENERAL 2012.00 24-Feb-14 14-May-16 05-Jun-11 A 20-Dec-16 -220.00 100% 0% 0.00 
KEY DATES 1700.00 15-Nov-14 14-May-16 05-Jun-11 A 20-Dec-16 -182.00 0% 0% 0.00 
DHKMSGN220 IFC Drawing 0.00 05-Jun-11 A 100% 100% 0.00 
DHKMSGN200 Commencement Date 0.00 19-Jun-11 A 100% 100% 0.00 
DHKMSGN210 Site Possession 0.00 19-Jun-11 A 100% 100% 0.00 
DHKMSGN250 DM Approval on enabling Work Completion 0.00 02-Oct-12 A 100% 100% 0.00 
DHKMSGN260 Approval test results on Enabling Work items 0.00 02-Oct-12 A 100% 100% 0.00 
DHKMSGN240 Dewatering System Handing Over 0.00 22-Oct-12 A 100% 100% 0.00 
DHKMSGN230 Building Permit 0.00 27-Mar-13 A 100% 100% 0.00 
DHKMSGN470 Design Nocs 0.00 18-Apr-13 A 100% 100% 0.00 
DHKMSGN410 Tower Raft Pour 0.00 17-May-13 A 100% 100% 0.00 
DHKMSGN420 Overall Foundation Completion 0.00 15-Nov-14 21-Dec-14 -28.00 0% 0% 0.00 
DHKMSGN430 Basement/Podium Completion of Structure up to GF 0.00 19-Feb-15 26-Mar-15 -28.00 0% 0% 0.00 
DHKMSGN400 Partial Power On (Up to Lvl.30) 0.00 19-Feb-15 19-Apr-15 -50.00 0% 0% 0.00 
DHKMSGN500 Wild Air On (Up to Lvl..29) 0.00 08-Mar-15 05-May-15 -50.00 0% 0% 0.00 
DHKMSGN450 Podium Completion of Structure up to Lv. P5 0.00 04-Jun-15 09-Jul-15 -1.00 0% 0% 0.00 
DHKMSGN402 Partial Power On (Lvl.31-61) 0.00 14-Jun-15 20-Jul-15 -14.00 0% 0% 0.00 
DHKMSGN502 Wild Air On (Lvl.31-61) 0.00 21-Jul-15 06-Aug-15 -14.00 0% 0% 0.00 
DHKMSGN452 Completion of Structure 0.00 12-Aug-15 17-Aug-15 7.00 0% 0% 0.00 
DHKMSGN440 Completion of Facade Cladding Up to Lvl.85 0.00 15-Aug-15 18-Oct-15 -10.00 0% 0% 0.00 
DHKMSGN462 Wild Air On (Level 62 above) 0.00 08-Nov-15 02-Jan-16 -46.00 0% 0% 0.00 
DHKMSGN442 Completion of Facade Cladding Up to top 0.00 12-Nov-15 13-Jan-16 -5.00 0% 0% 0.00 
DHKMSGN460 Permanent Power On (Overall) 0.00 08-Dec-15 25-May-16 -144.00 0% 0% 0.00 
DHKMSGN990 Project Completion 0.00 14-May-16 20-Dec-16 -182.00 0% 0% 0.00 
EMPLOYER KEY DATES 1756.00 07-Sep-14 19-Feb-16 15-Oct-12 A 30-Jun-16 -77.00 0% 0% 0.00 
ISSUANCE OF VALID NOCs (BY OTHERS) 0.00 24-Feb-14 16-Mar-14 30-Sep-14 30-Sep-14 25.00 0% 0% 0.00 
AUTHORITIES APPROVALS 1069.00 24-Feb-14 08-Mar-16 05-May-13 A 25-May-16 -63.00 100% 0% 0.00 
DEWA POWER ON 1069.00 24-Feb-14 08-Mar-16 05-May-13 A 25-May-16 -63.00 100% 0% 0.00 
SUB-STATION WORKS 1069.00 16-Mar-14 08-Dec-15 05-May-13 A 25-May-16 -169.00 100% 0% 0.00 
LOAD SCHEDULE 100.00 18-Mar-14 24-Jul-14 18-Mar-14 A 19-Jan-15 -175.00 0% 0% 0.00 
DHDWALS010 Prepare Shop Drawings 10.00 18-Mar-14 29-Mar-14 18-Mar-14 A 02-Oct-14 -145.00 100% 99% 0.00 
DHDWALS020 Prepare Load Schedules 10.00 26-Mar-14 06-Apr-14 05-Apr-14 A 13-Oct-14 -145.00 100% 99% 0.00 
DHDWALS090 Engineer's Review 14.00 07-Apr-14 20-Apr-14 20-May-14 A 14-Oct-14 -175.00 100% 99% 0.00 
DHDWALS030 Submit Load Schedules to DEWA REV 00 5.00 20-Apr-14 26-Apr-14 15-Oct-14 20-Oct-14 -145.00 100% 0% 0.00 
DHDWALS040 DEWA : Return Load Schedules with comments REV00 21.00 27-Apr-14 25-May-14 21-Oct-14 18-Nov-14 -122.00 100% 0% 0.00 
DHDWALS050 Resubmit Load Schedules REV 01 5.00 26-May-14 30-May-14 19-Nov-14 23-Nov-14 -174.00 100% 0% 0.00 
DHDWALS060 DEWA : Return Load Schedules with comments REV01 21.00 31-May-14 20-Jun-14 24-Nov-14 14-Dec-14 -174.00 100% 0% 0.00 
DHDWALS070 Resubmit Load Schedules REV 02 5.00 21-Jun-14 25-Jun-14 15-Dec-14 20-Dec-14 -143.00 100% 0% 0.00 
DHDWALS080 DEWA: Approve Load Schd. REV02 & Issue Const. NOC 21.00 26-Jun-14 24-Jul-14 21-Dec-14 19-Jan-15 -121.00 100% 0% 0.00 
SUB-STATION WORKS 667.00 16-Mar-14 02-Feb-15 05-May-13 A 20-Apr-15 -62.00 100% 0% 0.00 
DHDWASS110 Prepare Substation Trench Layout Shop Drg 45.00 16-Mar-14 16-Mar-14 05-May-13 A 21-Jun-13 A 100% 100% 0.00 
DHDWASS120 Submit SS Trench Layout Shop Drg to DEWA 4.00 16-Mar-14 16-Mar-14 22-Jun-13 A 27-Jun-13 A 100% 100% 0.00 
DHDWASS130 DEWA: Return Substation Layout Drg With Comments 12.00 16-Mar-14 16-Mar-14 28-Jun-13 A 09-Jul-13 A 100% 100% 0.00 
DHDWASS140 Incorporate DEWA Comments in Shop Drgs 12.00 16-Mar-14 16-Mar-14 10-Jul-13 A 22-Jul-13 A 100% 100% 0.00 
DHDWASS150 Resubmit SS Trench Layout Shop Drg to DEWA 6.00 16-Mar-14 16-Mar-14 23-Jul-13 A 30-Jul-13 A 100% 100% 0.00 
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 
Overall Foundation Completion 
Basement/Podium Completion of Structure up to GF 
Partial Power On (Up to Lvl.30) 
Wild Air On (Up to Lvl..29) 
Podium Completion of Structure up to Lv. P5 
Partial Power On (Lvl.31-61) 
Wild Air On (Lvl.31-61) 
Completion of Structure 
Completion of Facade Cladding Up Prepare Shop Drawings 
Prepare Load Schedules 
Engineer's Review 
Submit Load Schedules to DEWA REV 00 
DEWA : Return Load Schedules with comments REV00 
Resubmit Load Schedules REV 01 
DEWA : Return Load Schedules with comments REV01 
Resubmit Load Schedules REV 02 
DEWA: Approve Load Schd. REV02 & Issue Const. NOC 
DEWA: Return Substation Layout Drg With Comments 
Resubmit SS Trench Layout Shop Drg to DEWA 
Data Date : 30-Sep-14 
Page : 1 of 58 
Printed On : 16-Oct-14 
Baseline 
Actual Work 
Remaining Work 
Critical Remaining Work 
Baseline Milestone 
Curernt Milestone 
Project Progress Update as of 30-Sep-2014 
Taregt Completion Programme - Rev 03 
Date Revision Chec... Appr... 
20-Aug-14 Target Completion Programme - Rev 03 (Baseline) 
30-Sep-14 Schedule Update - September-14 (Update) SK
Activity ID Activity Name Original 
Duration 
Planned Start Planned Finish Actual/Forecast 
Start 
Actual/Forecast 
Finish 
Total 
Float 
Planned % 
Complete 
Actual % 
Complete 
SPI 
2014 2015 
DHDWASS160 DEWA : Approve SS Trench Layout Shop Drawings 21.00 16-Mar-14 16-Mar-14 31-Jul-13 A 27-Aug-13 A 100% 100% 0.00 
DHDWASS170 Complete Substations Trench Works 60.00 01-Jun-14 15-Jun-14 21-Sep-13 A 22-Jun-14 A 100% 100% 0.00 
DHDWASS010 Access to Substation 0.00 16-Jun-14 02-Sep-14 A 100% 100% 0.00 
DHDWASS020 Fix Cable Trays 6.00 05-Aug-14 11-Aug-14 22-Oct-14 29-Oct-14 -52.00 100% 0% 0.00 
DHDWASS030 Fix Electrical Conduits 6.00 12-Aug-14 18-Aug-14 30-Oct-14 05-Nov-14 -52.00 100% 0% 0.00 
DHDWASS040 Power & Lighting Wiring 6.00 19-Aug-14 25-Aug-14 06-Nov-14 12-Nov-14 -52.00 100% 0% 0.00 
DHDWASS050 Install & Terminate DB's 6.00 26-Aug-14 01-Sep-14 13-Nov-14 19-Nov-14 -52.00 100% 0% 0.00 
DHDWASS060 Install Wiring Devices 6.00 02-Sep-14 08-Sep-14 20-Nov-14 26-Nov-14 -52.00 100% 0% 0.00 
DHDWASS070 Install Light Fittings 6.00 02-Sep-14 08-Sep-14 20-Nov-14 26-Nov-14 -48.00 100% 0% 0.00 
DHDWASS080 Install Emergency Lights 6.00 02-Sep-14 08-Sep-14 20-Nov-14 26-Nov-14 -48.00 100% 0% 0.00 
DHDWASS090 Install Fire Alarm 5.00 03-Sep-14 08-Sep-14 22-Nov-14 26-Nov-14 -48.00 100% 0% 0.00 
DHDWASS100 Substation Works Completion 0.00 22-Sep-14 11-Dec-14 -52.00 100% 0% 0.00 
DHDWASS180 Substation Ready for Inspection 0.00 22-Sep-14 11-Dec-14 -52.00 100% 0% 0.00 
DHDWASS190 Consultant : Inspect Substation 3.00 23-Sep-14 25-Sep-14 13-Dec-14 15-Dec-14 -52.00 100% 0% 0.00 
DHDWASS200 Consultant : Submit Inspection check list to DEWA 6.00 27-Sep-14 02-Oct-14 16-Dec-14 22-Dec-14 -52.00 66.67% 0% 0.00 
DHDWASS210 DEWA : Inspect Substation 20.00 05-Oct-14 02-Nov-14 23-Dec-14 20-Jan-15 -44.00 0% 0% 0.00 
DHDWASS220 Address DEWA Comments 20.00 03-Nov-14 25-Nov-14 21-Jan-15 12-Feb-15 -53.00 0% 0% 0.00 
DHDWASS230 Consultant : Reinspect Substation 12.00 26-Nov-14 10-Dec-14 14-Feb-15 26-Feb-15 -53.00 0% 0% 0.00 
DHDWASS240 Consultant : Resubmit Inspection request to DEWA 20.00 11-Dec-14 04-Jan-15 28-Feb-15 22-Mar-15 -53.00 0% 0% 0.00 
DHDWASS250 DEWA : Reinspect & Approve Substation 20.00 05-Jan-15 01-Feb-15 23-Mar-15 19-Apr-15 -44.00 0% 0% 0.00 
DHDWASS260 Substation Ready for HT Cable / Transformer Work 0.00 02-Feb-15 20-Apr-15 -53.00 0% 0% 0.00 
LV ROOM WORKS 603.00 21-Oct-14 08-Dec-15 01-Oct-14 25-May-16 -169.00 0% 0% 0.00 
DHDWALV000 Access to LV Room 0.00 21-Oct-14 01-Oct-14 131.00 0% 0% 0.00 
DHDWALV010 Cable Ladder & Tray Fixing 26.00 21-Oct-14 20-Nov-14 01-Oct-14 03-Nov-14 131.00 0% 0% 0.00 
DHDWALV020 Earthing Strips laying 20.00 05-Nov-14 27-Nov-14 18-Oct-14 10-Nov-14 139.00 0% 0% 0.00 
DHDWALV030 Cable lying & Terminations 26.00 22-Nov-14 22-Dec-14 04-Nov-14 04-Dec-14 139.00 0% 0% 0.00 
DHDWALV040 Panel Installation 45.00 03-Jan-15 23-Feb-15 08-Mar-15 28-Apr-15 61.00 0% 0% 0.00 
DHDWALV050 Panel Earthing termination 15.00 24-Feb-15 12-Mar-15 29-Apr-15 17-May-15 61.00 0% 0% 0.00 
DHDWALV060 Install MDB & Termination 30.00 19-Mar-15 22-Apr-15 22-Sep-15 29-Oct-15 -46.00 0% 0% 0.00 
DHDWALV170 Install Chequered Plates 12.00 23-Apr-15 04-May-15 30-Oct-15 10-Nov-15 -43.00 0% 0% 0.00 
DHDWALV070 Install Wiring Devices 12.00 23-Apr-15 06-May-15 31-Oct-15 12-Nov-15 -46.00 0% 0% 0.00 
DHDWALV080 Install Light Fittings 12.00 07-May-15 21-May-15 14-Nov-15 26-Nov-15 -46.00 0% 0% 0.00 
DHDWALV090 Install FM 200 System 12.00 23-May-15 04-Jun-15 28-Nov-15 12-Dec-15 -46.00 0% 0% 0.00 
DHDWALV100 Install Fire Alarm Devices 12.00 06-Jun-15 18-Jun-15 13-Dec-15 26-Dec-15 -46.00 0% 0% 0.00 
DHDWALV110 Complete All MEP Installation in Building 0.00 01-Nov-15 26-Dec-15 -46.00 0% 0% 0.00 
DHDWALV120 Submit Inspection request to DEWA 12.00 02-Nov-15 15-Nov-15 27-Dec-15 09-Jan-16 -46.00 0% 0% 0.00 
DHDWALV130 DEWA : Inspect Installation 3.00 16-Nov-15 18-Nov-15 10-Jan-16 12-Jan-16 -38.00 0% 0% 0.00 
DHDWALV140 Address Comments of DEWA 6.00 19-Nov-15 25-Nov-15 08-May-16 14-May-16 -144.00 0% 0% 0.00 
DHDWALV150 Resubmit Inspection Request to DEWA 3.00 26-Nov-15 29-Nov-15 15-May-16 17-May-16 -144.00 0% 0% 0.00 
DHDWALV160 DEWA : Inspect & Approve Installations 6.00 30-Nov-15 08-Dec-15 18-May-16 25-May-16 -121.00 0% 0% 0.00 
PERMANENT POWER APPLICATION 115.00 02-Feb-15 26-May-15 20-Apr-15 12-Aug-15 -63.00 0% 0% 0.00 
DHDWAPA000 Application Registration 60.00 02-Feb-15 12-Apr-15 20-Apr-15 29-Jun-15 -53.00 0% 0% 0.00 
DHDWAPA010 DEWA : Estimate amount for permit power 26.00 14-Apr-15 19-May-15 01-Jul-15 05-Aug-15 -45.00 0% 0% 0.00 
DHDWAPA020 Client : Pay Estimate amount to DEWA 0.00 26-May-15 12-Aug-15 -45.00 0% 0% 0.00 
HIGH TENSION WORKS 222.00 20-Jun-15 08-Dec-15 05-Sep-15 25-May-16 -144.00 0% 0% 0.00 
DHDWAHT000 DEWA : HT Cable Work & Transformer Procurement & Installat1io3n0.00 20-Jun-15 23-Nov-15 05-Sep-15 07-Feb-16 -52.00 0% 0% 0.00 
DHDWAHT010 Permanent Power on 0.00 08-Dec-15 25-May-16 -144.00 0% 0% 0.00 
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 
DEWA : Approve SS Trench Layout Shop Drawings 
Complete Substations Trench Works 
Access to Substation 
Fix Cable Trays 
Fix Electrical Conduits 
Power & Lighting Wiring 
Install & Terminate DB's 
Install Wiring Devices 
Install Light Fittings 
Install Emergency Lights 
Install Fire Alarm 
Substation Works Completion 
Substation Ready for Inspection 
Consultant : Inspect Substation 
Consultant : Submit Inspection check list to DEWA 
DEWA : Inspect Substation 
Address DEWA Comments 
Consultant : Reinspect Substation 
Consultant : Resubmit Inspection request to DEWA 
DEWA : Reinspect & Approve Substation 
Substation Ready for HT Cable / Transformer Work 
Access to LV Room 
Cable Ladder & Tray Fixing 
Earthing Strips laying 
Cable lying & Terminations 
Panel Installation 
Panel Earthing termination 
Install MDB & Termination 
Install Chequered Plates 
Install Wiring Devices 
Install Light Fittings 
Install FM 200 System 
Application Registration 
DEWA : Estimate amount for permit power 
Client : Pay Estimate amount to DEWA 
DAMAC Gulf Properties L.L.C 
DAMAC Heights at Dubai Marina 
Data Date : 30-Sep-14 
Page : 2 of 58 
Printed On : 16-Oct-14 
Baseline 
Actual Work 
Remaining Work 
Critical Remaining Work 
Baseline Milestone 
Curernt Milestone 
Project Progress Update as of 30-Sep-2014 
Taregt Completion Programme - Rev 03 
Date Revision Chec... Appr... 
20-Aug-14 Target Completion Programme - Rev 03 (Baseline) 
30-Sep-14 Schedule Update - September-14 (Update) SK
Activity ID Activity Name Original 
Duration 
Planned Start Planned Finish Actual/Forecast 
Start 
Actual/Forecast 
Finish 
Total 
Float 
Planned % 
Complete 
Actual % 
Complete 
SPI 
2014 2015 
DEWA WATER 567.00 03-Mar-14 08-Mar-16 26-Jan-14 A 12-Apr-16 -20.00 0% 0% 0.00 
DUBAI CIVIL DEFENCE 104.00 27-Feb-14 06-Jul-14 24-Feb-14 A 24-Feb-14 A 0% 0% 0.00 
CIVIL AVIATION 223.00 29-Oct-14 04-Jun-15 24-Feb-14 A 24-Feb-14 A 0% 0% 0.00 
ETISALAT/ DU 383.00 03-Mar-14 14-Jul-15 24-Feb-14 A 11-Oct-15 66.00 0% 0% 0.00 
DM DRAINAGE 567.00 24-Feb-14 08-Mar-16 24-Feb-14 A 12-Apr-16 -20.00 0% 0% 0.00 
CONSTRUCTION EQUIPMENTS 1570.00 24-Feb-14 14-Nov-15 11-May-13 A 13-Jan-16 -60.00 0% 0% 0.00 
ENGINEERING & PROCUREMENT 1843.00 24-Feb-14 07-Dec-15 19-Jun-11 A 02-Feb-16 128.00 0% 0% 0.00 
PROVISIONAL SUMS 658.00 24-Feb-14 01-Oct-15 13-Aug-13 A 01-Oct-15 132.00 0% 0% 0.00 
MEP LONG LEAD ITEMS 319.00 19-Mar-14 22-Jul-15 14-Jan-14 A 05-Oct-15 -29.00 0% 0% 0.00 
Electrical 307.00 10-Jun-14 05-Apr-15 05-Mar-14 A 05-Oct-15 -46.00 0% 0% 0.00 
Bus Bar 127.00 10-Jul-14 14-Jan-15 05-Mar-14 A 17-Jun-15 -128.00 0% 0% 0.00 
A3260 Material Submittal 14.00 10-Jul-14 26-Jul-14 05-Mar-14 A 16-Apr-14 A 100% 100% 0.00 
A3270 Material Approval 14.00 27-Jul-14 13-Aug-14 06-Mar-14 A 06-May-14 A 100% 100% 0.00 
A3280 Issue of PO to Supplier 7.00 14-Aug-14 21-Aug-14 20-Jan-15 27-Jan-15 -128.00 100% 0% 0.00 
A3290 Manufacturing /Procurement and Delivery of the Material 120.00 23-Aug-14 14-Jan-15 28-Jan-15 17-Jun-15 -128.00 28.33% 0% 0.00 
Wiring Accessories 227.00 28-Oct-14 05-Apr-15 16-Apr-14 A 08-Feb-15 52.00 0% 0% 0.00 
A3220 Material Submittal 14.00 28-Oct-14 12-Nov-14 16-Apr-14 A 18-May-14 A 0% 100% 0.00 
A3230 Material Approval 14.00 13-Nov-14 29-Nov-14 17-Apr-14 A 02-Jun-14 A 0% 100% 0.00 
A3240 Issue of PO to Supplier 7.00 30-Nov-14 08-Dec-14 01-Oct-14 11-Oct-14 52.00 0% 0% 0.00 
A3250 Manufacturing /Procurement and Delivery of the Material 100.00 09-Dec-14 05-Apr-15 12-Oct-14 08-Feb-15 52.00 0% 0% 0.00 
LV Panels & Switchgear 127.00 10-Jun-14 14-Dec-14 18-Mar-14 A 03-Mar-15 104.00 0% 0% 0.00 
A3300 Material Submittal 14.00 10-Jun-14 25-Jun-14 18-Mar-14 A 01-May-14 A 100% 100% 0.00 
A3310 Material Approval 14.00 26-Jun-14 12-Jul-14 19-Mar-14 A 15-May-14 A 100% 100% 0.00 
A3320 Issue of PO to Supplier 7.00 13-Jul-14 20-Jul-14 01-Oct-14 11-Oct-14 104.00 100% 0% 0.00 
A3330 Manufacturing /Procurement and Delivery of the Material 120.00 21-Jul-14 14-Dec-14 12-Oct-14 03-Mar-15 104.00 50% 0% 0.00 
Generator 193.00 15-Jul-14 30-Mar-15 24-Aug-14 A 05-Oct-15 -46.00 0% 0% 0.00 
A3340 Material Submittal 14.00 15-Jul-14 02-Aug-14 24-Aug-14 A 19-Feb-15 -46.00 100% 78.57% 0.00 
A3350 Material Approval 14.00 03-Aug-14 18-Aug-14 25-Aug-14 A 23-Feb-15 -46.00 100% 78.57% 0.00 
A3360 Issue of PO to Supplier 7.00 19-Aug-14 26-Aug-14 24-Feb-15 03-Mar-15 -46.00 100% 0% 0.00 
A3370 Manufacturing /Procurement and Delivery of the Material 180.00 27-Aug-14 30-Mar-15 04-Mar-15 05-Oct-15 -46.00 16.67% 0% 0.00 
ELV 227.00 19-Mar-14 28-Apr-15 16-Feb-14 A 03-Mar-15 151.00 0% 0% 0.00 
BMS 227.00 28-Oct-14 28-Apr-15 08-Jun-14 A 03-Mar-15 151.00 0% 0% 0.00 
A3420 Material Submittal 14.00 28-Oct-14 12-Nov-14 08-Jun-14 A 20-Aug-14 A 0% 100% 0.00 
A3430 Material Approval 14.00 13-Nov-14 29-Nov-14 09-Jun-14 A 31-Aug-14 A 0% 100% 0.00 
A3440 Issue of PO to Supplier 7.00 30-Nov-14 08-Dec-14 01-Oct-14 11-Oct-14 151.00 0% 0% 0.00 
A3450 Manufacturing /Procurement and Delivery of the Material 120.00 09-Dec-14 28-Apr-15 12-Oct-14 03-Mar-15 151.00 0% 0% 0.00 
FA System Panels 157.00 19-Mar-14 27-Oct-14 16-Feb-14 A 27-Oct-14 20.00 0% 0% 0.00 
A3380 Material Submittal 14.00 19-Mar-14 03-Apr-14 16-Feb-14 A 20-May-14 A 100% 100% 0.00 
A3390 Material Approval 14.00 05-Apr-14 20-Apr-14 17-Feb-14 A 04-Jun-14 A 100% 100% 0.00 
A3400 Issue of PO to Supplier 7.00 21-Apr-14 28-Apr-14 05-Jun-14 A 23-Jun-14 A 100% 100% 0.00 
A3410 Manufacturing /Procurement and Delivery of the Material 150.00 29-Apr-14 27-Oct-14 24-Jun-14 A 27-Oct-14 20.00 86.67% 0% 0.00 
HVAC 284.00 26-Mar-14 22-Jul-15 02-Feb-14 A 19-Apr-15 96.00 0% 0% 0.00 
FAHU 167.00 23-Apr-14 14-Dec-14 03-Mar-14 A 15-Dec-14 5.00 0% 0% 0.00 
A3500 Material Submittal 14.00 23-Apr-14 08-May-14 03-Mar-14 A 20-May-14 A 100% 100% 0.00 
A3510 Material Approval 14.00 10-May-14 25-May-14 04-Mar-14 A 10-Jun-14 A 100% 100% 0.00 
A3520 Issue of PO to Supplier 7.00 26-May-14 03-Jun-14 11-Jun-14 A 22-Jun-14 A 100% 100% 0.00 
A3530 Manufacturing /Procurement and Delivery of the Material 160.00 04-Jun-14 14-Dec-14 23-Jun-14 A 15-Dec-14 5.00 62.5% 61.88% 0.00 
FCU 125.00 26-Mar-14 21-Aug-14 09-Feb-14 A 21-Aug-14 A 0% 0% 0.00 
A3820 Material Submittal 14.00 26-Mar-14 10-Apr-14 09-Feb-14 A 03-Jul-14 A 100% 100% 0.00 
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 
Material Submittal 
Material Approval 
Issue of PO to Supplier 
Manufacturing /Procurement and Delivery of the Material 
Material Submittal 
Material Approval 
Issue of PO to Supplier 
Manufacturing /Procurement and Delivery of the Material 
Material Submittal 
Material Approval 
Issue of PO to Supplier 
Manufacturing /Procurement and Delivery of the Material 
Material Submittal 
Material Approval 
Issue of PO to Supplier 
Manufacturing /Procurement and Delivery Material Submittal 
Material Approval 
Issue of PO to Supplier 
Manufacturing /Procurement and Delivery of the Material 
Material Submittal 
Material Approval 
Issue of PO to Supplier 
Manufacturing /Procurement and Delivery of the Material 
Material Submittal 
Material Approval 
Issue of PO to Supplier 
Manufacturing /Procurement and Delivery of the Material 
Material Submittal 
DAMAC Gulf Properties L.L.C 
DAMAC Heights at Dubai Marina 
Data Date : 30-Sep-14 
Page : 3 of 58 
Printed On : 16-Oct-14 
Baseline 
Actual Work 
Remaining Work 
Critical Remaining Work 
Baseline Milestone 
Curernt Milestone 
Project Progress Update as of 30-Sep-2014 
Taregt Completion Programme - Rev 03 
Date Revision Chec... Appr... 
20-Aug-14 Target Completion Programme - Rev 03 (Baseline) 
30-Sep-14 Schedule Update - September-14 (Update) SK
Activity ID Activity Name Original 
Duration 
Planned Start Planned Finish Actual/Forecast 
Start 
Actual/Forecast 
Finish 
Total 
Float 
Planned % 
Complete 
Actual % 
Complete 
SPI 
2014 2015 
A3830 Material Approval 14.00 12-Apr-14 27-Apr-14 10-Feb-14 A 23-Jul-14 A 100% 100% 0.00 
A3840 Issue of PO to Supplier 7.00 28-Apr-14 05-May-14 24-Jul-14 A 31-Jul-14 A 100% 100% 0.00 
A3850 Manufacturing /Procurement and Delivery of the Material 90.00 06-May-14 21-Aug-14 01-Aug-14 A 21-Aug-14 A 100% 100% 0.00 
Fans ( Pressurisation , Parking Extract Etc ) 195.00 29-May-14 19-Jan-15 10-Mar-14 A 09-Dec-14 34.00 0% 0% 0.00 
A3460 Material Submittal 14.00 29-May-14 14-Jun-14 10-Mar-14 A 09-Jun-14 A 100% 100% 0.00 
A3470 Material Approval 14.00 15-Jun-14 30-Jun-14 11-Mar-14 A 01-Jul-14 A 100% 100% 0.00 
A3480 Issue of PO to Supplier 7.00 01-Jul-14 08-Jul-14 02-Jul-14 A 22-Jul-14 A 100% 100% 0.00 
A3490 Manufacturing /Procurement and Delivery of the Material 160.00 09-Jul-14 19-Jan-15 23-Jul-14 A 09-Dec-14 34.00 43.75% 65% 0.00 
Chilled Water Pumps 195.00 29-May-14 19-Jan-15 05-Mar-14 A 18-Mar-15 -50.00 0% 0% 0.00 
A3540 Material Submittal 14.00 29-May-14 14-Jun-14 05-Mar-14 A 03-Jul-14 A 100% 100% 0.00 
A3550 Material Approval 14.00 15-Jun-14 30-Jun-14 06-Mar-14 A 19-Jul-14 A 100% 100% 0.00 
A3560 Issue of PO to Supplier 7.00 01-Jul-14 08-Jul-14 20-Jul-14 A 24-Aug-14 A 100% 100% 0.00 
A3570 Manufacturing /Procurement and Delivery of the Material 160.00 09-Jul-14 19-Jan-15 25-Aug-14 A 18-Mar-15 -50.00 43.75% 12.5% 0.00 
Cooling Tower 257.00 03-Dec-14 22-Jul-15 25-May-14 A 19-Apr-15 96.00 0% 0% 0.00 
A3580 Material Submittal 14.00 03-Dec-14 18-Dec-14 25-May-14 A 12-Aug-14 A 0% 100% 0.00 
A3590 Material Approval 14.00 20-Dec-14 05-Jan-15 26-May-14 A 13-Aug-14 A 0% 100% 0.00 
A3600 Issue of PO to Supplier 7.00 06-Jan-15 13-Jan-15 01-Oct-14 11-Oct-14 96.00 0% 0% 0.00 
A3610 Manufacturing /Procurement and Delivery of the Material 160.00 14-Jan-15 22-Jul-15 12-Oct-14 19-Apr-15 96.00 0% 0% 0.00 
Chiller 215.00 22-May-14 05-Feb-15 08-Mar-14 A 15-Mar-15 4.00 0% 0% 0.00 
A3620 Material Submittal 14.00 22-May-14 08-Jun-14 08-Mar-14 A 09-Jun-14 A 100% 100% 0.00 
A3630 Material Approval 14.00 09-Jun-14 24-Jun-14 09-Mar-14 A 19-Jun-14 A 100% 100% 0.00 
A3640 Issue of PO to Supplier 7.00 25-Jun-14 02-Jul-14 21-Jun-14 A 22-Jun-14 A 100% 100% 0.00 
A3650 Manufacturing /Procurement and Delivery of the Material 180.00 03-Jul-14 05-Feb-15 24-Jun-14 A 15-Mar-15 4.00 41.67% 23.89% 0.00 
Heat Exchanger 195.00 30-Apr-14 21-Dec-14 02-Feb-14 A 19-Nov-14 36.00 0% 0% 0.00 
A3660 Material Submittal 14.00 30-Apr-14 15-May-14 02-Feb-14 A 13-May-14 A 100% 100% 0.00 
A3670 Material Approval 14.00 17-May-14 02-Jun-14 03-Feb-14 A 01-Jun-14 A 100% 100% 0.00 
A3680 Issue of PO to Supplier 7.00 03-Jun-14 10-Jun-14 02-Jun-14 A 22-Jul-14 A 100% 100% 0.00 
A3690 Manufacturing /Procurement and Delivery of the Material 160.00 11-Jun-14 21-Dec-14 23-Jul-14 A 19-Nov-14 36.00 58.75% 75% 0.00 
Fire Fighting 215.00 22-May-14 03-Jun-15 01-May-14 A 15-Jun-15 45.00 0% 0% 0.00 
Fire Pumps 187.00 22-May-14 05-Feb-15 01-May-14 A 12-May-15 -43.00 0% 0% 0.00 
A3700 Material Submittal 14.00 22-May-14 08-Jun-14 01-May-14 A 18-May-14 A 100% 100% 0.00 
A3710 Material Approval 14.00 09-Jun-14 24-Jun-14 19-May-14 A 05-Jun-14 A 100% 100% 0.00 
A3720 Issue of PO to Supplier 7.00 25-Jun-14 02-Jul-14 01-Oct-14 11-Oct-14 -43.00 100% 0% 0.00 
A3730 Manufacturing /Procurement and Delivery of the Material 180.00 03-Jul-14 05-Feb-15 12-Oct-14 12-May-15 -43.00 41.67% 0% 0.00 
FM200 215.00 20-Sep-14 03-Jun-15 01-Oct-14 15-Jun-15 45.00 0% 0% 0.00 
A4020 Material Submittal 14.00 20-Sep-14 07-Oct-14 01-Oct-14 19-Oct-14 45.00 71.43% 0% 0.00 
A4030 Material Approval 14.00 08-Oct-14 23-Oct-14 20-Oct-14 05-Nov-14 45.00 0% 0% 0.00 
A4040 Issue of PO to Supplier 7.00 26-Oct-14 02-Nov-14 06-Nov-14 13-Nov-14 45.00 0% 0% 0.00 
A4050 Manufacturing /Procurement and Delivery of the Material 180.00 03-Nov-14 03-Jun-15 15-Nov-14 15-Jun-15 45.00 0% 0% 0.00 
Plumbing 319.00 14-Sep-14 18-Mar-15 14-Jan-14 A 03-Mar-15 96.00 0% 0% 0.00 
Sump Pump 192.00 14-Sep-14 18-Mar-15 29-Jun-14 A 03-Mar-15 96.00 0% 0% 0.00 
A3780 Material Submittal 14.00 14-Sep-14 29-Sep-14 29-Jun-14 A 04-Aug-14 A 100% 100% 0.00 
A3790 Material Approval 14.00 30-Sep-14 18-Oct-14 30-Jun-14 A 14-Aug-14 A 7.14% 100% 0.00 
A3800 Issue of PO to Supplier 7.00 19-Oct-14 27-Oct-14 01-Oct-14 11-Oct-14 96.00 0% 0% 0.00 
A3810 Manufacturing /Procurement and Delivery of the Material 120.00 28-Oct-14 18-Mar-15 12-Oct-14 03-Mar-15 96.00 0% 0% 0.00 
Water Heat er 155.00 14-Sep-14 18-Mar-15 14-Jan-14 A 31-May-14 A 0% 0% 0.00 
A3860 Material Submittal 14.00 14-Sep-14 29-Sep-14 14-Jan-14 A 16-Apr-14 A 100% 100% 0.00 
A3880 Issue of PO to Supplier 7.00 19-Oct-14 27-Oct-14 04-May-14 A 14-May-14 A 0% 100% 0.00 
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 
Material Approval 
Issue of PO to Supplier 
Manufacturing /Procurement and Delivery of the Material 
Material Submittal 
Material Approval 
Issue of PO to Supplier 
Manufacturing /Procurement and Delivery of the Material 
Material Submittal 
Material Approval 
Issue of PO to Supplier 
Manufacturing /Procurement and Delivery of the Material 
Material Submittal 
Material Approval 
Issue of PO to Supplier 
Manufacturing /Procurement and Delivery of the Material 
Material Submittal 
Material Approval 
Issue of PO to Supplier 
Manufacturing /Procurement and Delivery of the Material 
Material Submittal 
Material Approval 
Issue of PO to Supplier 
Manufacturing /Procurement and Delivery of the Material 
Material Submittal 
Material Approval 
Issue of PO to Supplier 
Manufacturing /Procurement and Delivery of the Material 
Material Submittal 
Material Approval 
Issue of PO to Supplier 
Manufacturing /Procurement and Delivery of the Material 
Material Submittal 
Material Approval 
Issue of PO to Supplier 
Manufacturing /Procurement and Delivery of the Material 
Material Submittal 
Issue of PO to Supplier 
DAMAC Gulf Properties L.L.C 
DAMAC Heights at Dubai Marina 
Data Date : 30-Sep-14 
Page : 4 of 58 
Printed On : 16-Oct-14 
Baseline 
Actual Work 
Remaining Work 
Critical Remaining Work 
Baseline Milestone 
Curernt Milestone 
Project Progress Update as of 30-Sep-2014 
Taregt Completion Programme - Rev 03 
Date Revision Chec... Appr... 
20-Aug-14 Target Completion Programme - Rev 03 (Baseline) 
30-Sep-14 Schedule Update - September-14 (Update) SK
Activity ID Activity Name Original 
Duration 
Planned Start Planned Finish Actual/Forecast 
Start 
Actual/Forecast 
Finish 
Total 
Float 
Planned % 
Complete 
Actual % 
Complete 
SPI 
2014 2015 
A3870 Material Approval 14.00 30-Sep-14 18-Oct-14 15-May-14 A 20-May-14 A 7.14% 100% 0.00 
A3890 Manufacturing /Procurement and Delivery of the Material 120.00 28-Oct-14 18-Mar-15 21-May-14 A 31-May-14 A 0% 100% 0.00 
Booster Pump 192.00 14-Sep-14 18-Mar-15 03-Jun-14 A 03-Mar-15 96.00 0% 0% 0.00 
A3900 Material Submittal 14.00 14-Sep-14 29-Sep-14 03-Jun-14 A 29-Jun-14 A 100% 100% 0.00 
A3910 Material Approval 14.00 30-Sep-14 18-Oct-14 04-Jun-14 A 08-Jul-14 A 7.14% 100% 0.00 
A3920 Issue of PO to Supplier 7.00 19-Oct-14 27-Oct-14 01-Oct-14 11-Oct-14 96.00 0% 0% 0.00 
A3930 Manufacturing /Procurement and Delivery of the Material 120.00 28-Oct-14 18-Mar-15 12-Oct-14 03-Mar-15 96.00 0% 0% 0.00 
Transfer Pump 192.00 14-Sep-14 18-Mar-15 03-Jun-14 A 03-Mar-15 96.00 0% 0% 0.00 
A3940 Material Submittal 14.00 14-Sep-14 29-Sep-14 03-Jun-14 A 29-Jun-14 A 100% 100% 0.00 
A3950 Material Approval 14.00 30-Sep-14 18-Oct-14 04-Jun-14 A 08-Jul-14 A 7.14% 100% 0.00 
A3960 Issue of PO to Supplier 7.00 19-Oct-14 27-Oct-14 01-Oct-14 11-Oct-14 96.00 0% 0% 0.00 
A3970 Manufacturing /Procurement and Delivery of the Material 120.00 28-Oct-14 18-Mar-15 12-Oct-14 03-Mar-15 96.00 0% 0% 0.00 
Sewage Pump 192.00 14-Sep-14 18-Mar-15 29-Jun-14 A 03-Mar-15 96.00 0% 0% 0.00 
A3980 Material Submittal 14.00 14-Sep-14 29-Sep-14 29-Jun-14 A 04-Aug-14 A 100% 100% 0.00 
A3990 Material Approval 14.00 30-Sep-14 18-Oct-14 30-Jun-14 A 14-Aug-14 A 7.14% 100% 0.00 
A4000 Issue of PO to Supplier 7.00 19-Oct-14 27-Oct-14 01-Oct-14 11-Oct-14 96.00 0% 0% 0.00 
A4010 Manufacturing /Procurement and Delivery of the Material 120.00 28-Oct-14 18-Mar-15 12-Oct-14 03-Mar-15 96.00 0% 0% 0.00 
DOMESTIC SUBCONTRACTORS 1589.00 24-Feb-14 22-Mar-15 19-Jun-11 A 24-Oct-15 186.00 0% 0% 0.00 
Prime Cost 363.00 01-Apr-14 28-Sep-15 24-Feb-14 A 28-Sep-15 65.00 0% 0% 0.00 
SUB-STRUCTURE 938.00 24-Feb-14 24-Feb-14 22-Jun-11 A 20-Sep-13 A 0% 0% 0.00 
SUPER STRUCTURE 1633.00 24-Feb-14 13-Jul-15 11-Apr-13 A 02-Feb-16 A 0% 0% 0.00 
MEP 1835.00 24-Feb-14 07-Dec-15 24-Feb-14 A 24-Feb-14 A 0% 0% 0.00 
CONSTRUCTION 1603.00 24-Feb-14 30-Apr-16 26-Jun-11 A 27-Aug-16 -88.00 25.09% 22.48% 0.90 
STRUCTURAL , ARCHITECTURAL , MEP 1530.00 24-Feb-14 30-Apr-16 26-Jun-11 A 31-May-16 -15.00 29.36% 28.06% 0.96 
FOUNDATION WORKS 1363.00 24-Feb-14 11-Oct-15 26-Jun-11 A 16-Nov-15 -4.00 75.13% 71.94% 0.96 
BASEMENT & PODIUM 1455.00 24-Feb-14 30-Apr-16 31-May-13 A 23-May-16 -8.00 48.62% 48.59% 1.00 
TOWER 696.00 24-Feb-14 06-Apr-16 10-Feb-14 A 31-May-16 -45.00 24.04% 22.56% 0.94 
LEVELS 06 - 29 577.00 24-Feb-14 14-Nov-15 10-Feb-14 A 12-Jan-16 -50.00 68.5% 64.97% 0.95 
LEVEL 06 468.00 24-Feb-14 21-May-15 10-Feb-14 A 02-Sep-15 -72.00 76.72% 72.35% 0.94 
STRUCTURAL - LEVEL 6 20.00 24-Feb-14 16-Mar-14 10-Feb-14 A 09-Mar-14 A 100% 100% 1.00 
DHCWA07100 Core Wal - Level 06 6.00 24-Feb-14 24-Feb-14 15-Feb-14 A 20-Feb-14 A 100% 100% 1.00 
DHSLA06100 Construction of Horizontals - L06 4.00 10-Mar-14 11-Mar-14 10-Feb-14 A 04-Mar-14 A 100% 100% 1.00 
DHCWA07110 Construction of Verticals - L06 3.00 13-Mar-14 16-Mar-14 06-Mar-14 A 09-Mar-14 A 100% 100% 1.00 
STAIRCASES 4.00 25-May-14 29-May-14 08-May-14 A 18-May-14 A 0% 0% 0.00 
DHSLA06102 Stair # 2 4.00 25-May-14 29-May-14 08-May-14 A 13-May-14 A 100% 100% 0.00 
DHSLA06104 Stair # 1 4.00 25-May-14 29-May-14 13-May-14 A 18-May-14 A 100% 100% 0.00 
FINISHES - LEVEL 06 246.00 12-Apr-14 21-May-15 24-Feb-14 A 14-Jul-15 -31.00 40.01% 18.14% 0.45 
Dry area 230.00 06-May-14 02-May-15 28-Apr-14 A 25-Jun-15 -43.00 30.8% 15.86% 0.51 
DHFSH06100 Block Work in Dry Area 6.00 06-May-14 12-May-14 28-Apr-14 A 19-May-14 A 100% 100% 1.00 
DHFSH06120 Marking,Cutting & Chasing - Dry Area 4.00 13-May-14 17-May-14 15-May-14 A 03-Jun-14 A 100% 100% 1.00 
DHFSH06130 Sub frame Fixing/Plaster Preparation - Dry Area 4.00 08-Jun-14 12-Jun-14 21-May-14 A 07-Jun-14 A 100% 100% 1.00 
DHFSH06160 Plaster in Dry Area 8.00 12-Jun-14 22-Jun-14 25-May-14 A 18-Jun-14 A 100% 100% 1.00 
DHFSH06190 Dry Area Floor Screed 7.00 22-Jun-14 30-Jun-14 01-Sep-14 A 01-Sep-14 A 100% 100% 0.00 
DHFSH06230 Dry Area Painting - Primer 4.00 30-Jun-14 05-Jul-14 01-Sep-14 A 01-Oct-14 -8.00 100% 80% 0.00 
DHFSH06260 Dry Area Painting - Stucco 6.00 05-Jul-14 12-Jul-14 06-Sep-14 A 06-Oct-14 48.00 100% 60% 0.00 
DHFSH06290 Dry Area False Ceiling Suspension 6.00 23-Aug-14 30-Aug-14 02-Sep-14 A 09-Oct-14 -8.00 100% 15% 0.15 
DHFSH06350 Dry Area False Ceiling Tiling / Boarding 5.00 17-Sep-14 23-Sep-14 14-Oct-14 19-Oct-14 37.00 100% 0% 0.00 
DHFSH06400 Dry Area Painting - 1st Coat 5.00 23-Sep-14 29-Sep-14 20-Oct-14 26-Oct-14 37.00 100% 0% 0.00 
DHFSH06450 Dry Area Flooring 5.00 12-Oct-14 18-Oct-14 02-Nov-14 06-Nov-14 32.00 0% 0% 0.00 
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 
Material Approval 
Manufacturing /Procurement and Delivery of the Material 
Material Submittal 
Material Approval 
Issue of PO to Supplier 
Manufacturing /Procurement and Delivery of the Material 
Material Submittal 
Material Approval 
Issue of PO to Supplier 
Manufacturing /Procurement and Delivery of the Material 
Material Submittal 
Material Approval 
Issue of PO to Supplier 
Manufacturing /Procurement and Delivery of the Material 
Construction of Horizontals - L06 
Construction of Verticals - L06 
Stair # 2 
Stair # 1 
Block Work in Dry Area 
Marking,Cutting & Chasing - Dry Area 
Sub frame Fixing/Plaster Preparation - Dry Area 
Plaster in Dry Area 
Dry Area Floor Screed 
Dry Area Painting - Primer 
Dry Area Painting - Stucco 
Dry Area False Ceiling Suspension 
Dry Area False Ceiling Tiling / Boarding 
Dry Area Painting - 1st Coat 
Dry Area Flooring 
DAMAC Gulf Properties L.L.C 
DAMAC Heights at Dubai Marina 
Data Date : 30-Sep-14 
Page : 5 of 58 
Printed On : 16-Oct-14 
Baseline 
Actual Work 
Remaining Work 
Critical Remaining Work 
Baseline Milestone 
Curernt Milestone 
Project Progress Update as of 30-Sep-2014 
Taregt Completion Programme - Rev 03 
Date Revision Chec... Appr... 
20-Aug-14 Target Completion Programme - Rev 03 (Baseline) 
30-Sep-14 Schedule Update - September-14 (Update) SK
Activity ID Activity Name Original 
Duration 
Planned Start Planned Finish Actual/Forecast 
Start 
Actual/Forecast 
Finish 
Total 
Float 
Planned % 
Complete 
Actual % 
Complete 
SPI 
2014 2015 
DHFSH06430 Installation of Timber Doors & Ironmongery 5.00 22-Mar-15 26-Mar-15 20-May-15 25-May-15 -50.00 0% 0% 0.00 
DHFSH06802 Installation of Wardrobe 12.00 22-Mar-15 04-Apr-15 20-May-15 02-Jun-15 -50.00 0% 0% 0.00 
DHFSH06500 Paint Final Coat 6.00 26-Apr-15 02-May-15 20-Jun-15 25-Jun-15 -43.00 0% 0% 0.00 
Wet area 204.00 13-May-14 04-Apr-15 24-Feb-14 A 02-Jun-15 -45.00 43.27% 24.17% 0.56 
DHFSH06220 Wet Area Floor Screed 4.00 29-Sep-14 06-Oct-14 24-Feb-14 A 24-Feb-14 A 28.13% 100% 0.00 
DHFSH06110 Block Work in Wet Area 6.00 13-May-14 19-May-14 28-Apr-14 A 19-May-14 A 100% 100% 0.00 
DHFSH06140 Marking,Cutting & Chasing - Wet Area 4.00 20-May-14 24-May-14 15-May-14 A 03-Jun-14 A 100% 100% 1.00 
DHFSH06150 Sub frame Fixing/Plaster Preparation - Wet Area 4.00 08-Jun-14 12-Jun-14 21-May-14 A 07-Jun-14 A 100% 100% 1.00 
DHFSH06170 Plaster in Wet Area 4.00 12-Jun-14 17-Jun-14 25-May-14 A 18-Jun-14 A 100% 100% 1.00 
DHFSH06180 Wet Area Wall Tiling 6.00 23-Aug-14 30-Aug-14 02-Sep-14 A 02-Oct-14 -23.00 100% 60% 0.60 
DHFSH06300 Wet Area False Ceiling Suspension 5.00 01-Sep-14 07-Sep-14 11-Oct-14 15-Oct-14 7.00 100% 0% 0.00 
DHFSH06370 Wet Area False Ceiling Tiling/Boarding 6.00 17-Sep-14 24-Sep-14 14-Oct-14 20-Oct-14 15.00 100% 0% 0.00 
DHFSH06210 Wet Area Waterproofing 4.00 24-Sep-14 29-Sep-14 16-Sep-14 A 26-Oct-14 15.00 100% 10% 0.10 
DHFSH06250 Wet Area Floor Tiling 5.00 06-Oct-14 12-Oct-14 27-Oct-14 01-Nov-14 15.00 0% 0% 0.00 
DHFSH06460 Cabinet Carcass 5.00 18-Oct-14 22-Oct-14 02-Nov-14 06-Nov-14 15.00 0% 0% 0.00 
DHFSH06420 Installation of Shower Enclosure 4.00 28-Mar-15 31-Mar-15 26-May-15 30-May-15 -42.00 0% 0% 0.00 
DHFSH06390 Installation of Vanity Counters & Tops 5.00 28-Mar-15 01-Apr-15 26-May-15 31-May-15 -50.00 0% 0% 0.00 
DHFSH06800 Installation of Kitchen Cabinet 12.00 22-Mar-15 04-Apr-15 20-May-15 02-Jun-15 -50.00 0% 0% 0.00 
Corridor/ Lift Lobby 44.00 30-Jun-14 10-Mar-15 01-Sep-14 A 24-Nov-14 89.00 66.67% 0% 0.00 
DHFSH06240 Corridor/Lift Lobby Floor Screed 4.00 30-Jun-14 05-Jul-14 01-Sep-14 A 01-Sep-14 A 100% 100% 0.00 
DHFSH06270 Lift Lobby Painting - Primer & Stucco 6.00 05-Jul-14 12-Jul-14 01-Sep-14 A 02-Oct-14 13.00 100% 75% 0.00 
DHFSH06310 Lift Lobby False Ceiling Suspension 6.00 03-Sep-14 10-Sep-14 13-Oct-14 19-Oct-14 7.00 100% 0% 0.00 
DHFSH06360 Lift Lobby False Ceiling Tiling / Boarding 5.00 17-Sep-14 23-Sep-14 20-Oct-14 26-Oct-14 93.00 100% 0% 0.00 
DHFSH06410 Lift Lobby Painting - 1st Coat 6.00 23-Sep-14 30-Sep-14 27-Oct-14 02-Nov-14 93.00 100% 0% 0.00 
DHFSH06470 Lift Lobby Flooring 6.00 18-Oct-14 26-Oct-14 08-Nov-14 13-Nov-14 89.00 0% 0% 0.00 
DHFSH06490 Utility Rooms- Epoxy Flooring 6.00 26-Oct-14 02-Nov-14 15-Nov-14 20-Nov-14 89.00 0% 0% 0.00 
DHFSH06440 Installation of Steel Doors & Windows 3.00 08-Mar-15 10-Mar-15 22-Nov-14 24-Nov-14 89.00 0% 0% 0.00 
Staircase 51.00 22-Jun-14 18-Mar-15 01-Oct-14 03-Dec-14 91.00 45.08% 0% 0.00 
DHFSH06200 Staircase Plastering 4.00 22-Jun-14 26-Jun-14 01-Oct-14 07-Oct-14 27.00 100% 0% 0.00 
DHFSH06280 Staircase Painting - Primer & Stucco 6.00 12-Jul-14 19-Jul-14 08-Oct-14 14-Oct-14 119.00 100% 0% 0.00 
DHFSH06320 Staircase Handrail Fixing 3.00 04-Dec-14 08-Dec-14 15-Oct-14 18-Oct-14 119.00 0% 0% 0.00 
DHFSH06330 Staircase Painting 1st Coat 3.00 08-Dec-14 11-Dec-14 27-Oct-14 29-Oct-14 113.00 0% 0% 0.00 
DHFSH06340 Staircase Final Painting 5.00 11-Mar-15 16-Mar-15 25-Nov-14 30-Nov-14 91.00 0% 0% 0.00 
DHFSH06380 Staircase Epoxy Flooring 2.00 17-Mar-15 18-Mar-15 01-Dec-14 03-Dec-14 91.00 0% 0% 0.00 
General 246.00 12-Apr-14 21-May-15 03-Apr-14 A 14-Jul-15 -43.00 0% 0% 0.00 
DHSTR06000 Access from Structure 0.00 12-Apr-14 03-Apr-14 A 100% 100% 0.00 
DHFSH06510 Snagging & De-Snagging 16.00 03-May-15 21-May-15 27-Jun-15 14-Jul-15 -43.00 0% 0% 0.00 
Show Flats 1 & 2 116.00 12-Jul-14 29-Nov-14 01-Oct-14 18-Feb-15 93.00 0% 0% 0.00 
DHFSH06511 Finishes & MEP Works - Flat 1 (Workmanship) 116.00 12-Jul-14 29-Nov-14 01-Oct-14 18-Feb-15 93.00 58.62% 0% 0.00 
DHFSH06512 Finishes & MEP Works - Flat 2 (Workmanship) 116.00 12-Jul-14 29-Nov-14 01-Oct-14 18-Feb-15 93.00 58.62% 0% 0.00 
MEP - LEVEL 06 465.00 08-Mar-14 25-Apr-15 10-Feb-14 A 02-Sep-15 -106.00 70.98% 70.98% 1.00 
DHMEP06000 Embeded Conduits & Boxex - Concrete Works 4.00 08-Mar-14 11-Mar-14 10-Feb-14 A 04-Mar-14 A 100% 100% 0.00 
DHMEP06100 H/L Chilled Water Piping,Drainage,Water ,Fire fighting Piping ,Du1c8t.i0n0g, C15a-bAlipnrg-1 ,4 Wiring et0c5-May-14 03-Apr-14 A 29-Apr-14 A 100% 100% 1.00 
DHMEP06130 Cable Trays & Cable Trunking 6.00 13-May-14 19-May-14 03-Apr-14 A 29-Apr-14 A 100% 100% 0.00 
DHMEP06160 Pressure Testing of Pipes 12.00 23-Aug-14 04-Sep-14 28-Apr-14 A 17-May-14 A 100% 100% 0.00 
DHMEP06120 Embeded Condiuts,Boxes ,Sleeves and Pix Pipes in Walls 6.00 25-May-14 01-Jun-14 20-May-14 A 05-Jun-14 A 100% 100% 1.00 
DHMEP06110 MEP Works in Risers& Clearance 5.00 12-Jul-14 16-Jul-14 05-Apr-14 A 01-Oct-14 -33.00 100% 78% 0.00 
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 
Installation of Timber Doors & Ironmongery 
Installation of Wardrobe 
Paint Final Coat 
Wet Area Floor Screed 
Block Work in Wet Area 
Marking,Cutting & Chasing - Wet Area 
Sub frame Fixing/Plaster Preparation - Wet Area 
Plaster in Wet Area 
Wet Area Wall Tiling 
Wet Area False Ceiling Suspension 
Wet Area False Ceiling Tiling/Boarding 
Wet Area Waterproofing 
Wet Area Floor Tiling 
Cabinet Carcass 
Installation of Shower Enclosure 
Installation of Vanity Counters & Tops 
Installation of Kitchen Cabinet 
Corridor/Lift Lobby Floor Screed 
Lift Lobby Painting - Primer & Stucco 
Lift Lobby False Ceiling Suspension 
Lift Lobby False Ceiling Tiling / Boarding 
Lift Lobby Painting - 1st Coat 
Lift Lobby Flooring 
Utility Rooms- Epoxy Flooring 
Installation of Steel Doors & Windows 
Staircase Plastering 
Staircase Painting - Primer & Stucco 
Staircase Handrail Fixing 
Staircase Painting 1st Coat 
Staircase Final Painting 
Staircase Epoxy Flooring 
Access from Structure 
Snagging & De-Snagging 
Finishes & MEP Works - Flat 1 (Workmanship) 
Finishes & MEP Works - Flat 2 (Workmanship) 
Embeded Conduits & Boxex - Concrete Works 
H/L Chilled Water Piping,Drainage,Water ,Fire fighting Piping ,Ducting, Cabling , Wiring etc 
Cable Trays & Cable Trunking 
Pressure Testing of Pipes 
Embeded Condiuts,Boxes ,Sleeves and Pix Pipes in Walls 
MEP Works in Risers& Clearance 
DAMAC Gulf Properties L.L.C 
DAMAC Heights at Dubai Marina 
Data Date : 30-Sep-14 
Page : 6 of 58 
Printed On : 16-Oct-14 
Baseline 
Actual Work 
Remaining Work 
Critical Remaining Work 
Baseline Milestone 
Curernt Milestone 
Project Progress Update as of 30-Sep-2014 
Taregt Completion Programme - Rev 03 
Date Revision Chec... Appr... 
20-Aug-14 Target Completion Programme - Rev 03 (Baseline) 
30-Sep-14 Schedule Update - September-14 (Update) SK
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues
Monthly Progress Report Highlights Key Issues

Weitere ähnliche Inhalte

Was ist angesagt?

Contract payment and variation
Contract payment and variationContract payment and variation
Contract payment and variationVj NiroSh
 
Construction phases
Construction phasesConstruction phases
Construction phasesMeesum Zaidi
 
Current Construction Projects, City of Chicago, August 21, 2008
Current Construction Projects, City of Chicago, August 21, 2008Current Construction Projects, City of Chicago, August 21, 2008
Current Construction Projects, City of Chicago, August 21, 2008Daniel X. O'Neil
 
edwin cv for QA-QC Manager
edwin cv for QA-QC Manageredwin cv for QA-QC Manager
edwin cv for QA-QC ManagerEdwin Aguinaldo
 
Construction project management
Construction project managementConstruction project management
Construction project managementsaif hasan
 
Promo_Epc project rule of credit and progress measurement
Promo_Epc project rule of credit and progress measurement Promo_Epc project rule of credit and progress measurement
Promo_Epc project rule of credit and progress measurement ignitetribes
 
Defects in construction
Defects in constructionDefects in construction
Defects in constructionShivangi Saini
 
FIDIC-Relevant to Time Management
FIDIC-Relevant to Time ManagementFIDIC-Relevant to Time Management
FIDIC-Relevant to Time ManagementASHISH KUMAR SINGH
 
Construction process
Construction processConstruction process
Construction processMazen Al-Qadi
 
How to Choose a Project Delivery Method
How to Choose a Project Delivery MethodHow to Choose a Project Delivery Method
How to Choose a Project Delivery MethodPMA Consultants
 
Building Construction 1: project 1
Building Construction 1: project 1Building Construction 1: project 1
Building Construction 1: project 1Nabeel Joomun
 
Time Impact Analysis
Time Impact AnalysisTime Impact Analysis
Time Impact AnalysisChris Carson
 
Construction quality management plan (Construction Productivity Analysis)
Construction quality management plan (Construction Productivity Analysis)Construction quality management plan (Construction Productivity Analysis)
Construction quality management plan (Construction Productivity Analysis)Jayson Narito
 
VERTEX Construction Delays and Forensic Schedule Analyses
VERTEX Construction Delays and Forensic Schedule AnalysesVERTEX Construction Delays and Forensic Schedule Analyses
VERTEX Construction Delays and Forensic Schedule AnalysesThe Vertex Companies, LLC
 
Types of resources in civil engineering field
Types of resources in civil engineering fieldTypes of resources in civil engineering field
Types of resources in civil engineering fieldswetha110
 
Project Charter Summery
Project Charter SummeryProject Charter Summery
Project Charter SummeryDerek Cooksey
 
Curriculum vitae of civil engineer for construction manager or Sr. project en...
Curriculum vitae of civil engineer for construction manager or Sr. project en...Curriculum vitae of civil engineer for construction manager or Sr. project en...
Curriculum vitae of civil engineer for construction manager or Sr. project en...Amir Mohammed
 
Conditions of CPWD contract in INDIA
Conditions of CPWD contract in INDIAConditions of CPWD contract in INDIA
Conditions of CPWD contract in INDIAAvinash Kumar Gupta
 

Was ist angesagt? (20)

Contract payment and variation
Contract payment and variationContract payment and variation
Contract payment and variation
 
Construction phases
Construction phasesConstruction phases
Construction phases
 
Current Construction Projects, City of Chicago, August 21, 2008
Current Construction Projects, City of Chicago, August 21, 2008Current Construction Projects, City of Chicago, August 21, 2008
Current Construction Projects, City of Chicago, August 21, 2008
 
edwin cv for QA-QC Manager
edwin cv for QA-QC Manageredwin cv for QA-QC Manager
edwin cv for QA-QC Manager
 
Construction project management
Construction project managementConstruction project management
Construction project management
 
Promo_Epc project rule of credit and progress measurement
Promo_Epc project rule of credit and progress measurement Promo_Epc project rule of credit and progress measurement
Promo_Epc project rule of credit and progress measurement
 
Defects in construction
Defects in constructionDefects in construction
Defects in construction
 
FIDIC-Relevant to Time Management
FIDIC-Relevant to Time ManagementFIDIC-Relevant to Time Management
FIDIC-Relevant to Time Management
 
Project Schedule Management
Project Schedule ManagementProject Schedule Management
Project Schedule Management
 
Construction process
Construction processConstruction process
Construction process
 
How to Choose a Project Delivery Method
How to Choose a Project Delivery MethodHow to Choose a Project Delivery Method
How to Choose a Project Delivery Method
 
Building Construction 1: project 1
Building Construction 1: project 1Building Construction 1: project 1
Building Construction 1: project 1
 
Time Impact Analysis
Time Impact AnalysisTime Impact Analysis
Time Impact Analysis
 
Construction quality management plan (Construction Productivity Analysis)
Construction quality management plan (Construction Productivity Analysis)Construction quality management plan (Construction Productivity Analysis)
Construction quality management plan (Construction Productivity Analysis)
 
VERTEX Construction Delays and Forensic Schedule Analyses
VERTEX Construction Delays and Forensic Schedule AnalysesVERTEX Construction Delays and Forensic Schedule Analyses
VERTEX Construction Delays and Forensic Schedule Analyses
 
Site possession
Site possessionSite possession
Site possession
 
Types of resources in civil engineering field
Types of resources in civil engineering fieldTypes of resources in civil engineering field
Types of resources in civil engineering field
 
Project Charter Summery
Project Charter SummeryProject Charter Summery
Project Charter Summery
 
Curriculum vitae of civil engineer for construction manager or Sr. project en...
Curriculum vitae of civil engineer for construction manager or Sr. project en...Curriculum vitae of civil engineer for construction manager or Sr. project en...
Curriculum vitae of civil engineer for construction manager or Sr. project en...
 
Conditions of CPWD contract in INDIA
Conditions of CPWD contract in INDIAConditions of CPWD contract in INDIA
Conditions of CPWD contract in INDIA
 

Ähnlich wie Monthly Progress Report Highlights Key Issues

Ähnlich wie Monthly Progress Report Highlights Key Issues (20)

DAMAC Heights Project
DAMAC Heights ProjectDAMAC Heights Project
DAMAC Heights Project
 
Anas Khalifa's CV_JAN.-2017
Anas Khalifa's CV_JAN.-2017Anas Khalifa's CV_JAN.-2017
Anas Khalifa's CV_JAN.-2017
 
Anas Khalifa's CV_JAN.-2017
Anas Khalifa's CV_JAN.-2017Anas Khalifa's CV_JAN.-2017
Anas Khalifa's CV_JAN.-2017
 
Final TEAM SLIDE PRESENTATION (1)
Final TEAM  SLIDE PRESENTATION (1)Final TEAM  SLIDE PRESENTATION (1)
Final TEAM SLIDE PRESENTATION (1)
 
Mitigtion Plan Presentation
Mitigtion Plan PresentationMitigtion Plan Presentation
Mitigtion Plan Presentation
 
HASSAN ALI CV1
HASSAN ALI CV1HASSAN ALI CV1
HASSAN ALI CV1
 
Project Controls planning & Scheduling Engineer-Portfolio
Project Controls planning & Scheduling Engineer-PortfolioProject Controls planning & Scheduling Engineer-Portfolio
Project Controls planning & Scheduling Engineer-Portfolio
 
SABER CV
SABER CVSABER CV
SABER CV
 
CV
CVCV
CV
 
AH15019
AH15019AH15019
AH15019
 
Antara Dashboard-002.pptx
Antara Dashboard-002.pptxAntara Dashboard-002.pptx
Antara Dashboard-002.pptx
 
Naveed Asif C.V Updated
Naveed Asif C.V UpdatedNaveed Asif C.V Updated
Naveed Asif C.V Updated
 
Topside
TopsideTopside
Topside
 
Jasim_CV_-_2016_W_MEP
Jasim_CV_-_2016_W_MEPJasim_CV_-_2016_W_MEP
Jasim_CV_-_2016_W_MEP
 
Wael El Ahmadi 2016 - Sr. Construction Engineer - Mechanical -Cv
Wael El Ahmadi 2016 - Sr. Construction Engineer - Mechanical -CvWael El Ahmadi 2016 - Sr. Construction Engineer - Mechanical -Cv
Wael El Ahmadi 2016 - Sr. Construction Engineer - Mechanical -Cv
 
Eng. Ayman Mitkees Cv.
Eng. Ayman Mitkees Cv.Eng. Ayman Mitkees Cv.
Eng. Ayman Mitkees Cv.
 
A.youssef_c.v.2014.doc-2(3)
A.youssef_c.v.2014.doc-2(3)A.youssef_c.v.2014.doc-2(3)
A.youssef_c.v.2014.doc-2(3)
 
Ramy Emad C.V Project Engineer
Ramy Emad C.V Project EngineerRamy Emad C.V Project Engineer
Ramy Emad C.V Project Engineer
 
Amjad survey inspector
Amjad survey inspectorAmjad survey inspector
Amjad survey inspector
 
CV_Tarun Kumar Behera
CV_Tarun Kumar BeheraCV_Tarun Kumar Behera
CV_Tarun Kumar Behera
 

Mehr von Sam Kendall, MSc, BSc Civil Eng., PMP®, MIEAust

Mehr von Sam Kendall, MSc, BSc Civil Eng., PMP®, MIEAust (20)

Kandil Mohammed Ibrahim_Sameh_Dissertation
Kandil Mohammed Ibrahim_Sameh_DissertationKandil Mohammed Ibrahim_Sameh_Dissertation
Kandil Mohammed Ibrahim_Sameh_Dissertation
 
Summary Progress Of Facade Works
Summary Progress Of Facade WorksSummary Progress Of Facade Works
Summary Progress Of Facade Works
 
Summary Progress Of Concrete Works
Summary Progress Of Concrete WorksSummary Progress Of Concrete Works
Summary Progress Of Concrete Works
 
Progress Of Ceiling Per Floors
Progress Of Ceiling Per FloorsProgress Of Ceiling Per Floors
Progress Of Ceiling Per Floors
 
N1
N1N1
N1
 
Progress Of Slab
Progress Of SlabProgress Of Slab
Progress Of Slab
 
Overall Progress S-Curve For Ceiling
Overall Progress S-Curve For CeilingOverall Progress S-Curve For Ceiling
Overall Progress S-Curve For Ceiling
 
Overall Progress S-Curve For Facades
Overall Progress S-Curve For FacadesOverall Progress S-Curve For Facades
Overall Progress S-Curve For Facades
 
Overall Progress S-Curve For Elevators
Overall Progress S-Curve For ElevatorsOverall Progress S-Curve For Elevators
Overall Progress S-Curve For Elevators
 
Overall Progres S-Curve For Concrete Works
Overall Progres S-Curve For Concrete WorksOverall Progres S-Curve For Concrete Works
Overall Progres S-Curve For Concrete Works
 
Window Analysis @ 30-June-2012
Window Analysis @ 30-June-2012Window Analysis @ 30-June-2012
Window Analysis @ 30-June-2012
 
01. P269 - Project Implementation Programme - Rev 00
01. P269 - Project Implementation Programme -  Rev 0001. P269 - Project Implementation Programme -  Rev 00
01. P269 - Project Implementation Programme - Rev 00
 
13. Overall S-Curve
13. Overall S-Curve13. Overall S-Curve
13. Overall S-Curve
 
10. Overall Implementation Programme
10. Overall Implementation Programme10. Overall Implementation Programme
10. Overall Implementation Programme
 
Building-Structure Planning Model
Building-Structure Planning ModelBuilding-Structure Planning Model
Building-Structure Planning Model
 
AWI20202 commercial
AWI20202 commercialAWI20202 commercial
AWI20202 commercial
 
Rihan Height Project Execution Plan-Rev00
Rihan Height Project Execution Plan-Rev00Rihan Height Project Execution Plan-Rev00
Rihan Height Project Execution Plan-Rev00
 
Monthly Progress Report No.13 - September 2011
Monthly Progress Report No.13 - September 2011Monthly Progress Report No.13 - September 2011
Monthly Progress Report No.13 - September 2011
 
Final Submission EOT 1
Final Submission EOT 1Final Submission EOT 1
Final Submission EOT 1
 
Cash Flow Portfolio
Cash Flow PortfolioCash Flow Portfolio
Cash Flow Portfolio
 

Monthly Progress Report Highlights Key Issues

  • 1. Monthly Progress Report DAMAC Heights at Dubai Marina Report No.7 - September 2014 Submitted to DAMAC Gulf Properties Co. LLC P.O.BOX 2195, Dubai United Arab Emirates
  • 2. Monthly Progress Report - September 2014 Prepared for Damac Properties Co. LLC P.O.Box 2195, Dubai United Arab Emirates Prepared by AECOM Middle East Limited ايست ليمتد ϝ وم ميد Ϝ اي PO Box 51028, Dubai United Arab Emirates www.aecom.com 30.Sep.14 © AECOM 2014 The information contained in this document produced by AECOM Middle East Limited is solely for the use of the Client identified on the cover sheet for the purpose for which it has been prepared and AECOM Middle East Limited undertakes no duty to or accepts any responsibility to any third party who may rely upon this document. All rights reserved. No section or element of this document may be removed from this document, reproduced, electronically stored or transmitted in any form without the written permission of AECOM Middle East Limited. Quality Information Document Monthly Progress Report - September 2014 Ref Date 16.Okt.14 Prepared by Sameh Kandil Reviewed by Revision History Fuad Hasan/Tareq Al Emam Authorised Name/Position Signature Project Director Revision Revision Date Details 0 16.Okt.14
  • 3. 2 Table of Contents Monthly Progress Report No. 7 - September 2014 Project Description 4 Tower Statistics 4 Project Stakeholders 4 Executive Summary 5 Key Accomplishments 6 Key Focus Issues 7 Area of Concerns 8 Contract Summary 10 Milestones 11 Upcoming Activities - 30 Day Look Ahead 13 Dashboard Reports 16 Schedule Progress 17 Negative Float Contour 21 Progress Photographs 23 Health, Safety and Environment 29 Engineering 31 Quality Assurance and Control 33 Commercial Status 35 Risk Management 37 Core Values into Practice 38 AECOM Core Values 39 Core Values into Practice 40 Appendices 42 Appendix 1: Schedule Update (Target Completion Programme-Rev3) Appendix 2: Structure Delay Appendix 3: Core Walls and Slabs Cycles Appendix 4: MEP Progress Data Sheets Appendix 5: Finishes Progress Data Sheets Appendix 6: External Facade Progress Data Sheets Appendix 7: Lifts Progress Data Sheets Appendix 8: Garbage Chute Progress Data Sheets Appendix 9: Long Lead Items Log Appendix 10: Provisional Sum Nomination Log Appendix 11: Building Permit Status Appendix 12: Technical Review Log Appendix 13: Outstanding RFIs Appendix 14: Outstanding Shop Drawings Appendix 15: Outstanding Material Submittal Appendix 16: Outstanding Subcontractors' Prequalification Appendix 17: Outstanding Method Statement Appendix 18: Non-Conformance Report Appendix 19: Actions Log Appendix 20: AECOM's Organization Chart
  • 4. 3 Monthly Progress Report No. 7 - September 2014 Project Description
  • 5. 4 Project Description Tower's Statistics DAMAC Heights Tower located at plot No.A3A,392-569 at Dubai Marina and comprises of the following criteria; 141,542 m2 3,464 m2 72,899 m2 522.67 m2 335 m 6 5 79 3 1 Dates Projection Date of Commencement 19.Jun.11 Original Project Duration 1096 Original Completion Date 18.Jun.14 Forecast Project Duration 2012 Project Forecast Completion 20.Dez.16 2 Bedroom 258 3 Bedroom 86 4 Bedroom 9 5 Bedroom 2 Shops Project Stakeholders Monthly Progress Report No. 7 - September 2014 Designation 1 Main Contractor Supervision Consultant MEP Sub-Contractor Facade Sub-Contractor Building Built Up Area Plot Area Apartments Built Up Area Commercial Built Up Area Stakeholders Names Ramboll Middle East Limited ARABTEC Construction L.L.C AECOM Middle East Limited REMCO Co. L.L.C Elevators Sub-Contractor Master Developer Local Authorities DAMAC Gulf Properties Co. L.L.C Toshiba Elevator Middle East L.L.C Aluminum & Light Industries Co. (ALICO) Ltd Emaar Properties PJSC Dubai Municipality Client Consultant BMU Sub-Contractor Danway L.L.C Fit Out Sub-Contractor JC Maclean International Dubai Civil Defense DEWA Dubai Civil Aviation Etisalat Number of Flats Number of Parking Slot Number of Shops Total Tower Height Top Roof Mechanical Floors Floors 30,62,85,86,8 7,88 Area/Height Calculations Height of Tower Floors Count Basement&Ground Floors Podium Floors Typical Floors Mechanical Floors Apartment Types Rooms/Slot Count Parking Slots 649 1 Bedroom 282 637 649 1 5 335
  • 6. 5 Monthly Progress Report No. 7 - September 2014 Executive Summary
  • 7. 6 Executive Summary Monthly Progress Report No. 7 - September 2014 • DuriŶg the ŵoŶth of Septeŵďer ϮϬϭϰ the projeĐt aĐtiǀities are progressiŶg. The ǁorks for the superstruĐture activities are continuing although the overall delays to the project remains. The core walls cycles as well as the slab cycles both of which are averaging (6) days. • EdžĐaǀatioŶ ǁork has stopped due to a seepage eǀeŶt that oĐĐurred oŶ ϭϳ Septeŵďer, that Đaused floodiŶg iŶ the area of section DD. • The MEP ϭst aŶd ϮŶd high leǀel serǀiĐes, MEP risers aŶd proǀisioŶ for floor aŶd ǁall serǀiĐes are oŶgoiŶg. The progress has improved and the delays will be mitigated by the end of October 2014. • The fiŶishes ǁorks iŶĐludes; ďloĐk, plaster, paiŶt aŶd ĐeiliŶg are oŶgoiŶg. • The Lift ǁorks has started iŶ the loǁ zoŶe, ŵed zoŶe aŶd high zoŶe. • FaĐade ǁorks; StiĐk ĐurtaiŶ ǁall at ďalĐoŶies ĐoŶtiŶues ďLJ ALICO iŶ Ϯϯ floors ĐoŶĐurreŶtlLJ, hoǁeǀer, the uŶitized curtain wall system is delayed. Also the glass panels test is still behind schedule. • Post-TeŶsioŶiŶg paĐkage froŵ leǀel ϲϰ till leǀel ϴϰ ǁas reǀieǁed ďLJ the ϯrd partLJ aŶd returŶed ďaĐk ǁith comments to ATC during the month. • DEWA desigŶ paĐkage is oŶ hold aǁaitiŶg the reĐeipt of NOC reŶeǁal froŵ EMAAR. • ATC ǁas iŶstruĐted to proĐeed ǁith proĐuriŶg the Bus Bars aŶd LV PaŶels. • SH&E reŵaiŶs a foĐus area of iŵproǀeŵeŶt, hoǁeǀer, the projeĐt ĐoŶtiŶues ǁithout LTI. • The keLJ risk to the projeĐt reŵaiŶs the laĐk of reǀised IFC doĐuŵeŶts for all leǀels that is peŶdiŶg froŵ the desigŶ consultant and will impact the authority packages for approval. Moreover, there is a risk of seepage from the existing diaphragm walls. Focus also should be given to finalize all the pending nominations to avoid any potential delays. Key Accomplishments Key Focus Issues Construction Progress Construction Progress • There is potential delays in the structure at Level 62 (Mechanical floor) as ATC from the Engineer point of view will not be able to achieve the planned cycle (8 days) because the width of two wing walls will increase and thus the slip form will require reconfiguration. Also the double height (5300 mm) will require 2 pours to reach the full height. • The structure completion date was slipped 6 calendar days and ATC has to mitigate such delays in the forthcoming floors. • A solution has to be proposed for the diaphragm wall in order to continue the work in Zone B. • REMCO has to increase the allocated labors and supervisors. Also ATC has to increase its MEP supervisors in order to follow up and expedite REMCO progress. • REMCO has to provide the partial and full clearance to commence the plaster and ceiling work on time. Also the electrical risers work has to be improved. • Paint (primer & stucco) and ceiling progress to be imporved by ATC. • ALCIO has to improve the curtain wall installation. • Clearance for sequencing of work to be done to avoid NCRs and stoppage of progress. • ATC to expidite the progress of Substation's finsihes and MEP works. Schedule Progress • ATC has to detail the external facade and lift work packages in order to enable the Engineer to monitor and control these packages. • The Engineer is insisting on adding sufficient details for MEP works in the program in order to be able to monitor the MEP package. • The overall delays till end of September 2014 is 182 days due to the delay in nomination of facade light package, however, the Engineer is of the view that the facade light nomination will not affect the project completion date, as the light fixtures will be installed before the project completion, which means there is sufficient time for procurement and engineering. Structure •The Slabs were poured up to level 36 and core walls were poured up to level 38. The stairs were poured till level 28. • The average cycles are 6 days for core walls and slabs. • The work in zone B was suspended due to the seepage event. However, secant piles breaking is going on in section BB progressing 81% complete. MEP • MEP High Level works are progressing in levels B5,B4,B3,B2 and 6 till 31. • MEP concealed works are progressing from level 6 till 24. • MEP risers- HAVC are progressing from level 6 till 22. • MEP risers- Fire Fighting are progressing from level 6 till 18. • MEP risers- Plumbing are progressing from level 6 till 31. • MEP risers- Electrical are progressing from level 6 till 19. • MEP ceiling clearance are progressing from level 6 till 9. Finishes • Block work is progressing from level 6 till 29. • Doors sub frames and plaster works are progressing from level 6 till 22. • Paint work is progressing from level 6 till 14 and false ceiling started in level 6. External Facade • ALICO started the installation of Stick frame curtain wall for balconies from level 6 till 28. Also the brackets for Unitized system and balcony balustrade started from level 6 to 8. Lifts • Toshiba started the preliminary works and separator steel beams in the low, med and high zones. Garbage Chute • Garbage Chute mock up was done at level 6.
  • 8. 7 Monthly Progress Report No. 7 - September 2014 Key Accomplishments Key Focus Issues Schedule Progress Health, Safety and Environment Engineering • PT shop drawings for levels (64-84) are under ATC review in order to resubmit it again to the 3rd Party for approval. • The LV shop drawings are ready for submission to DEWA, however, DEWA asked for design NOC's renewal before going further with drawings submission for review. • ATC continues preparing the shop drawings for false ceiling. • AECOM is preparing a proposal to have a permanent solution to the diaphragm wall. • ATC is preparing the fabrication drawings for the secondary steel structure of level 5. • A proposal for balcony rain water risers was submitted to Damac. • Approval has been obtained for FF and FA of level 5 from Civil defense and DM. • AECOM is working to provide Zone B's de-strutting sequencing. • Material submittal for intercom system, MV switch gear, generator and laminated Glass for Balcony Partition were approved. • DAMAC advised that the decision is to proceed with stone cladding and a sample sent to ATC. • An instruction was given to ATC to proceed with procuring the Bus bars and LV Panels. • The purchase order issued for Corridors tile. Quality Assurance and Control • 98 NCRs were issued to date and 85 of them are closed. • 8 NCRs were issued during this month. Commercial Status • The flooding delay events are still under review by 3rd party. No action is possible on ATC's claims until such time as the EOT decision is reached. • Variations submission, assessment and approval continues. • AECOM asked ATC to submit the PI insurances. • Payment Certificate (IPC) for August 2014 is under review. Procurement • RME has to release the Steam and Sauna package. • DAMAC has to finalize the nomination of façade light. • DAMAC to re-nominate the sanitary wares package. • ALICO to provide the factory production progress report showing the status of fabrication and the expected delivery dates. • ALICO to expedite the delivery of Cladding Panels and Unitized Curtain Wall System. • REMCO has to issue the purchase order of the Bus bars and LV Panels. Quality Assurance and Control • ATC has to improve the quality of concrete works. • ATC has to give the structural clearance before the commencement of MEP works. • ATC to improve quality of submittals to avoid ,multiple re-submission. Procurement Commercial Status • Final concluded report of flooding events has to be issued by DAMAC in order to enable Arabtec to issue a revised clause 14 that will reflect the new completion date. • Processing of agreed variations. • Processing of contractor IPCs in line with the contractual time frame. • ATC issued the Target Completion Programme - Rev 3 and it is under the Engineer's review. The comments will be issued to Arabtec by 2nd week of October 2014. Health, Safety and Environment • More work has to be done regarding the overhead protection. • House keeping needs improvement by ATC. • Excavation at sections B-B and D-D is a high risk activity. • Water Seepage at section DD and BB has to be monitored closely. • ineffective pest control in the project site offices. • Emergency escape route from level 27 to level 30 is inadequate. • More work has to be done to control the dust of Garbage Chute. •10 site observation were closed during the month of September 2014 and 2 notices were issued. • Number of first aid cases in September 2014 was (2) and (3) cases were recorded for near misses and (0) cases for LTI. • 308 orientation for new hires and 195 tool box talk were done during September 2014. Engineering • PT drawings for levels (64-84) has to be resubmitted by ATC for review. • Ramboll to provide updated drawings considering the missing electrical points for level 43 and above. • ATC to issue fabrication drawings for secondary steel structure for P5. • AECOM to prepare a proposal to have a permanent solution to the diaphragm wall. • AECOM to propose the sequencing of de-strutting for Zone B. • Ramboll to update the RCP plans considering the existing MEP provisions and the bulkhead dimensions for levels 6 till 38. • Arch and MEP design drawings (IFC) for Fendi floors from Level 43 to Roof has to be finalized. • ATC/ALICO to advice about the slab edge clashes with the façade various upper levels. • Pool designer's full design package to be issued in order to allow DAMAC to proceed with the nomination. • Emaar NOC has to be obtained in order to enable the submission of LV drawings to DEWA. The Renewal of design NOC can't be obtained without Emaar NOC.
  • 9. 8 Area of Concerns Area of Concern & Impact if Action not made 1 2 3 4 5 6 7 8 9 10 Lack of proposal for a permanent solution to the diphragm wall: Impact: Prolongation for the work suspension in Zone B. Lack of MEP's IFC revised drawings from Ramboll from level 43 and above: Impact: Delay in relevant shop drawings and thus delays to obtain DEWA approval for the shop drawings /schedule of loads and delays in procuring LV panels and Bus bars. Lack of Façade and Lifts detailed activities in the target completion schedule: Impact: Prevents AECOM from identifying the Façade and Lifts critical activities for the project delivery. Also prevents AECOM from closely monitoring the progress at site. Monthly Progress Report No. 7 - September 2014 Required Date 10.Okt.14 15.Okt.14 DAMAC/Ramboll 30.Okt.14 Arabtec 30.Okt.14 Lack of manpower for MEP work: Impact: REMCO will not be able to give ATC the MEP clearance to start the block and plaster works on time as per TCP-rev 3. 01.Okt.14 Absence of an independent inspection agency for post tension installation: Impact: The quality of PT works may be affected. Currently ATC is not in compliance with the specifications and payment deductions will be applied in response. 30.Okt.14 Delay in submitting fabrication drawings and shop drawings for the secondry steel structure at level P5: Impact: Installation of Unitized Curtain Wall will be delayed. Delay in the installation of façade glass panels (Stick&Unitized): Impact: Potential delays to the suspended ceiling installation. 01.Okt.14 8 days Core Wall cycle will not be achieved in level 62 : Impact: Potential delays to structure completion date as the structure is on the critical bath. Responsible Impact AECOM/DAMAC 15.Okt.14 Arabtec ATC/ALICO C C C C Arabtec C ATC/REMCO Arabtec Lack of de-strutting sequencing in Zone B : Impact: Potential delays to the excavation work. 10.Okt.14 AECOM Delay in finishes and electrical works inside the substation: Impact: Potential delays for handing over the substation to DEWA and delay for the permenent power application. 01.Okt.14 ATC C C M M M
  • 10. 9 Area of Concerns Monthly Progress Report No. 7 - September 2014 Area of Concern & Impact if Action not made Required Date Responsible Impact 11 Critical Manageable Lack of instruction to proceed with ordering the marble for Lift Lobby: Impact: Possibility of installation delays. 15.Okt.14 DAMAC M C M
  • 11. 10 Contract Summary Performance Indicators Measure This Month Last Month CV EV - AC EAC Variance EAC - CP Near Misses 3 * Note: 1) The Cost and Procurement sections will be frozen till approving the Target Completion Programme. 2) SPI and SV improved due to the issuing of TCP-Rev 03. Approved Claims Approved PS 0 2 26,116,726 No. of Near Misses Schedule Progress % Total Commitments 479,041,833 Variation Status Variation Approved 35 Financial Status (AED) Approved Variations Upward Trend Downward Trend No Change Residual PS Pending Effective Contract Value Gross Certified Physical % AED % AED % AED % AED % 119.845 23.6% 115.38 22.7% 75.44487 14.84% 63.693 12.5% Complete Variations AC - Actual Cost; CPI - Cost Performance Index; CP - Contract Price; CV - Cost Variance; EAC - Estimate At Completion; EV - Earned Value; NCR - Non-Conformance Report; PV - Planned Value; RFI - Request For Information; SPI - Schedule Performance Index; SV - Schedule Variance 79 * Note: The percentage value is the current amount divided by the Contract Price of AED 508,301,847. Monthly Progress Report No. 7 - September 2014 22.46% Payment Status (AED m) 9 9 26 0.85 -56.5 -157 Area Time SPI EV / PV SV Float (MS01) 0.89 -44.8 -182 EV - PV (AED m) Days Float Remaining CPI EV / AC NCR Close Out Issued/Closed 98/85 92/77 RFI Submittals % Closed 88% 86% 90% 88% Cost Quality Health and Safety Engineering 244,747,598 Variation Under DAMAC Assessment Variation Under ATC Assessment Total Procurement Major Items Variation Rejected 2 % Closed Gross and Net certified figures exclude Advance Payments. Estimate at Completion 8,177,509 5 18,378,571 Net Certified Perviously Certified Paid to Date 37,437,524 1,899,214
  • 12. 11 Control Milestones Days Monthly Progress Report No. 7 - September 2014 Milestones TCP-Rev 3 Current Forecast Current Float Remaining Clause 14 Program 592 18-Jun-14 226 08.Aug.13 159 06.Mär.13 90% 34% 5% Nomination of PS Items (not yet nominated) Days > 5 days 0 to 5 days < 0 days Upward Trend Downward Trend Milestones TCP - Rev 3 Current Forecast Current Float Remaining Clause 14 Program -218 2-Feb-12 10 -41 3-Jun-12 80 51 21-Nov-12 35 4-Mar-13 80 44 80 -27 17-Apr-13 80 90% 34% 5% 30.Sep Permits/NOCs Status Summary Actual Issue Date 23-Jan-11 14.Nov.13 25.Nov.13 10.Jul.14 171 SC Nomination for Fit Out (Fendi Flat) SC Nomination for Sauna,Jacuzzi 13-Nov-14 13-Nov-14 3-Sep-14 1-Oct-14 Revised Appoval Required - 30.00 3.00 50.00 Variance since Aug 14 (30.00) RME/AECOM FIC Location Approval RME/AECOM Dubai Municipality Fence NOC RME SC Nomination for Fit Out (Life Style) 4-Nov-14 4-Nov-14 116 0.00 SC Nomination for Landscaping Works 20-Nov-14 Nominated SC Nomination for Swimming Pool Works 20-Aug-14 1-Oct-14 69 (30.00) 20 Ground water Discharge 08.Mai.14 Drainage Design NOC and Drawings Approval ATC 22-Jul-11 Authority NOC/Permit Anticipated Issue Date Expiry Date Days Remaining Responsible 0 to 5 days < 0 days Upward Trend Downward Trend No Change Note: Days remaining from 30 Sep 2014 to Planned Dates of TCP. Variance since Aug 14 MS03 -Producing Wild Air (till 30th Floor) 8-Mar-15 5-May-15 -50 MS02 -Completion of Structure 14-May-15 20-May-15 -4 MS01 - Project Completion 14-May-16 20-Dec-16 -182 0.00 0.00 SC Nomination for Façade Lighting 24-Feb-14 1-Oct-14 -178 No Change Note: 1) Days remaining from 30 Sep 2014 to Planned Dates of TCP. 2) Variance since Aug-14: the difference between Current forecast of Sep vs. forecast of Aug. > 5 days
  • 13. 12 Permits/NOCs Status Summary Actual Issue Date Anticipated Issue Date NOC/Permit Responsible 09.Jun.13 05.Mai.13 25-Mar-13 Monthly Progress Report No. 7 - September 2014 Note: Days remaining from 30 Sep 2014 to Anticipated Date > 60 days 90% 34% 5% PerforŵaŶce MeasureŵeŶt – DefiŶitioŶs 30 to < 60 days DEWA - Electrical Electrical Load Design NOC 04.Mai.15 RME/AECOM Revised Appoval Required LV Design Drawing Approval Revised Appoval Required RME/AECOM Substation / Trench Design Approval RME/AECOM Planned Value (PV) Planned value of physical works to be accomplished. Actual Cost (AC) Actual cost of works physically accomplished. Earned Value (EV) Budgeted cost of works physically accomplished. Schedule Performance Index (SPI) = EV / PV SPI represents the current efficiency of progress. A SPI >1.0 denotes you are accomplishing more than planned. A SPI <1.0 denotes you are accomplishing less than planned < 30 days Schedule Variance (SV) = EV –PV SV represents the difference between what you have accomplished and what you planned to accomplish. A positive (+) Schedule Variance denotes you are ahead of schedule. A negative (-) Schedule Variance denotes you are behind schedule. DEWA - Water Water Design NOC 24-Mar-15 RME/AECOM RME/AECOM Water Supply Design Drawing Approval Revised Appoval Required Authority Days Remaining Expiry Date Revised Appoval Required Dubai Civil Defense Design Drawing Approval Revised Appoval Required RME/AECOM
  • 14. 13 Upcoming Activities - 30 Days Look Ahead C 14 Monthly Progress Report No. 7 - September 2014 Activity Type Start Finish Activity Slab L37 - Completion Slab L38 - Completion Slab L39 - Completion Slab L40 - Completion 08.Okt.14 12.Okt.14 16.Okt.14 28.Okt.14 Slab L41 - Completion Slab L42 - Completion Core Wall L41 - Completion Core Wall L42 - Completion Core Wall L43 - Completion Block Work Completion-L18 08.Okt.14 18.Okt.14 23.Okt.14 29.Okt.14 5-Oct-14 17-Oct-14 29-Oct-14 2-Oct-14 16-Oct-14 24-Oct-14 Block Work Completion-L27 Block Work Completion-L28 Block Work Completion-L29 Block Work Completion-L30 Block Work Completion-L31 Plaster Work Completion-L20 Plaster Work Completion-L22 Plaster Work Completion-L23 24-Oct-14 Plaster Work Completion-L24 Plaster Work Completion-L25 3-Oct-14 10-Oct-14 29-Oct-14 Plaster Work Completion-L21 21.Okt.14 03.Nov.14 Core Wall L39 - Completion 13.Okt.14 Core Wall L40 - Completion Construction 31-Oct-14 2-Oct-14 2-Oct-14 2-Oct-14 3-Oct-14 Paint Work Completion-L6 Paint Work Completion-L7 Paint Work Completion-L8 Paint Work Completion-L9 6-Oct-14 Paint Work Completion-L10 9-Oct-14 Paint Work Completion-L11 13-Oct-14 Paint Work Completion-L12 17-Oct-14 27-Oct-14 Paint Work Completion-L15 Monthly Progress Report No. 7 - September 2014 9-Oct-14 Paint Work Completion-L13 21-Oct-14 Paint Work Completion-L14 C C C C C C C C C C
  • 15. Upcoming Activities - 30 Days Look Ahead Activity Type Start Finish Activity MEP H/L Completion - L29 C C C C ALICO, Toshiba and JC Maclean detailed work schedules will be submitted to the Engineer. Continue reviewing ATC's new shop drawings submittals. 30-Oct-14 31-Oct-14 Finalize the open/overdue shop drawings submittals. PT drawings for levels (64-84) will be resubmitted again by ATC for 3rd party review. Ramboll to provide updated drawings considering the 25-Oct-14 missing electrical points for level 43 and above. Fabrication drawings to be submitted by ATC for the Engineer review. AECOM to propose the sequencing of de-strutting for Zone B. DAMAC/AECOM will conclude a solution to the diaphragm wall. Finalize the open/overdue material submittals. 1-Oct-14 31-Oct-14 15-Oct-14 15-Oct-14 15-Oct-14 15-Oct-14 1-Oct-14 31-Oct-14 Procurement 21-Oct-14 Unitized curtain wall will be delivered to site. Quality 1-Oct-14 LPO will be issued for Corridor Tiles. 1-Oct-14 31-Oct-14 ATC will keep closing the outstanding NCRs. 1-Oct-14 31-Oct-14 Quality Technical Meeting will be held on weekly basis to monitor the quality. 1-Oct-14 20-Oct-14 LPO for secondary steel strucutre will be issued. 1-Oct-14 20-Oct-14 RME has to release the Steam and Sauna Package. Construction 23.Okt.14 MEP H/L Completion - L31 MEP H/L Completion - L32 11.Okt.14 20.Okt.14 27.Okt.14 MEP H/L Completion - L30 Schedule 15-Oct-14 Electrical design NOC will be issued. Engineering 31-Oct-14 15-Oct-14 DAMAC will finalize the nomination of Façade Light. Re-nomination for the sanitary wares packages by DAMAC. 15-Oct-14 Continue reviewing ATC's new material submittals. C C C C C C C
  • 16. 15 Upcoming Activities - 30 Days Look Ahead DAMAC will continue float tenders and receiving quotations for the provisional sum items. Critical Path Activity 1-Oct-14 31-Oct-14 10-Oct-14 Payment Certificate (IPC) for August 2014 will be issued. Commercial 31-Oct-14 Finalize the list of pending variations submitted by ATC. 1-Oct-14 Monthly Progress Report No. 7 - September 2014 Activity Type Start Finish Activity C
  • 17. 16 Monthly Progress Report No. 7 - September 2014 Dashboard R Report
  • 18. 17 Schedule Progress Control Milestones Clause 14 Program Current Forecast Monthly Progress Report No. 7 - September 2014 -220 18-Jun-14 20-Dec-16 -182 - 3 0.00 14-May-15 -6 8-Aug-13 20-May-15 -4 3.00 -58 6-Mar-13 5-May-15 -50 5 0.00 26-Aug-13 6-Aug-15 -14 7 9.00 26-Nov-13 2-Jan-16 -46 1 0.00 -35 11-Dec-12 9-Jul-15 -28 - 4 7.00 5-Jan-13 29-Nov-14 -5 - 8.00 18-Sep-12 30-Oct-14 -57 4 .00 23-Mar-14 7-Mar-16 0 - 6.00 28-Mar-13 7-Oct-15 -28 - 3 6.00 Upward Trend Downward Trend 90% 34% 5% Milestone 60- Days look Ahead Critical Activities TCP - Rev 3 No Change Current Forecast 02.Okt.14 -6 - 6.00 08.Okt.14 -4 - 3.00 13.Okt.14 -3 - 3.00 18.Okt.14 -3 - 3.00 23-Oct-14 -5 - 5.00 29.Okt.14 -5 - 4.00 04.Nov.14 -5 - 6.00 09.Nov.14 -4 - 5.00 15.Nov.14 -4 - 6.00 22-Feb-16 31-Aug-15 2) Variance since Aug-14: the difference between Current forecast in Sep vs. forecast in Aug. Activity Slab L37 - Completion Slab L38 - Completion Slab L39 - Completion Slab L41 - Completion Slab L42 - Completion Slab L43 - Completion Slab L44 - Completion Slab L45 - Completion Total Variance 8-Mar-15 21-Jul-15 8-Nov-15 4-Jun-15 24-Nov-14 9-Sep-14 MS01 - Project Completion MS02-Completion of Structure MS03 - Producing Wild Air (till 30th Floor) MS04 - Producing Wild Air (31- 62th Floor) MS05 - Producing Wild Air (above 62th Floor) MS06 - Completion of P5 Slab at Zone B MS07 - Completion of Block Work till Level 36th MS08 - Completion of Façade Works (level 6 till level 10) TCP - Rev 3 Current Float -5 -51 Variance since Aug 14 Variance since Aug 14 08.Okt.14 > 5 days 0 to 5 days < 0 days 28.Okt.14 03.Nov.14 09.Nov.14 13.Nov.14 19.Nov.14 -55 -14 -37 12.Okt.14 -16 14-May-16 MS09 - Completion of Lift Works MS10 - Commencement of Swimming Pool Works Note: 1) Total Variance: the difference between TCP and Current Forecast. Slab L40 - Completion 21.Okt.14 Total Variance 16.Okt.14
  • 19. 18 60- Days look Ahead Critical Activities TCP - Rev 3 Monthly Progress Report No. 7 - September 2014 25.Nov.14 30.Nov.14 20-Nov-14 -5 - 6.00 25.Nov.14 -5 - 6.00 30.Nov.14 -6 - 6.00 01.Okt.14 -7 - 9.00 08.Okt.14 -5 - 6.00 13.Okt.14 -5 - 6.00 19.Okt.14 -4 - 8.00 23.Okt.14 -6 - 9.00 29.Okt.14 -5 - 7.00 03.Nov.14 -5 - 6.00 09.Nov.14 -4 - 8.00 15.Nov.14 -4 - 9.00 19.Nov.14 -5 - 8.00 24.Nov.14 -5 - 7.00 29.Nov.14 -5 - 8.00 Activity Slab L46 - Completion Slab L47 - Completion Slab L48 - Completion Core Wall L39 - Completion Core Wall L40 - Completion Core Wall L41 - Completion Core Wall L42 - Completion Core Wall L43 - Completion Core Wall L46 - Completion Core Wall L47 - Completion Core Wall L48 - Completion Core Wall L49 - Completion 06.Dez.14 08.Okt.14 13.Okt.14 18.Okt.14 23.Okt.14 13.Nov.14 19.Nov.14 Core Wall L50 - Completion 04.Dez.14 3-Oct-14 Block Work Completion-L18 05.Aug.14 -59 - 3 0.00 Block Work Completion-L27 28.Sep.14 5-Oct-14 -7 - 7.00 Block Work Completion-L28 07.Okt.14 10-Oct-14 -3 - 6.00 Block Work Completion-L29 14.Okt.14 17-Oct-14 -3 - 7.00 Block Work Completion-L30 26.Okt.14 29-Oct-14 -3 - 1 3.00 Block Work Completion-L31 26.Okt.14 29-Oct-14 -3 - 7.00 Block Work Completion-L32 30.Okt.14 2-Nov-14 -3 - 5.00 Block Work Completion-L33 04.Nov.14 9-Nov-14 -5 - 6.00 Block Work Completion-L34 11.Nov.14 16-Nov-14 -5 - 7.00 Block Work Completion-L35 18.Nov.14 23-Nov-14 -5 - 8.00 Block Work Completion-L36 24.Nov.14 29-Nov-14 -5 - 8.00 Plaster Work Completion-L20 06.Sep.14 2-Oct-14 -26 - 6.00 Plaster Work Completion-L21 11.Sep.14 9-Oct-14 -28 - 7.00 Plaster Work Completion-L22 17.Sep.14 16-Oct-14 -29 - 8.00 Plaster Work Completion-L23 22.Sep.14 24-Oct-14 -32 - 1 0.00 Plaster Work Completion-L24 28.Sep.14 -26 - 4.00 Plaster Work Completion-L25 06.Okt.14 -25 - 5.00 Plaster Work Completion-L26 13.Okt.14 -19 - 2.00 Plaster Work Completion-L27 21.Okt.14 -16 - 1.00 Plaster Work Completion-L28 29.Okt.14 11-Nov-14 -13 - 1.00 Plaster Work Completion-L29 05.Nov.14 16-Nov-14 -11 - 4.00 Plaster Work Completion-L30 16.Nov.14 22-Nov-14 -6 - 2.00 Total Variance Current Forecast 29.Okt.14 Core Wall L44 - Completion 03.Nov.14 Core Wall L45 - Completion 08.Nov.14 Variance since Aug 14 24.Nov.14 29.Nov.14 24-Oct-14 31-Oct-14 1-Nov-14 6-Nov-14
  • 20. 19 60- Days look Ahead Critical Activities TCP - Rev 3 Monthly Progress Report No. 7 - September 2014 Current Forecast 30-Nov-14 Plaster Work Completion-L31 16.Nov.14 -14 - 5.00 Paint Work Completion-L6 12.Jul.14 -82 - 2 6.00 Paint Work Completion-L7 19.Jul.14 2-Oct-14 -75 - 2 0.00 Paint Work Completion-L8 23.Jul.14 2-Oct-14 -71 - 1 5.00 Paint Work Completion-L9 30.Jul.14 3-Oct-14 -65 - 1 6.00 Paint Work Completion-L10 04.Aug.14 6-Oct-14 -63 - 1 7.00 Paint Work Completion-L11 09.Aug.14 -61 - 1 7.00 Paint Work Completion-L12 13.Aug.14 -61 - 1 7.00 Paint Work Completion-L13 18.Aug.14 -60 - 1 7.00 Paint Work Completion-L14 23.Aug.14 -59 - 1 9.00 Paint Work Completion-L15 27.Aug.14 -61 - 1 9.00 Paint Work Completion-L16 01.Sep.14 -62 - 1 9.00 Paint Work Completion-L17 08.Sep.14 -61 - 1 9.00 Paint Work Completion-L18 15.Sep.14 -60 - 1 9.00 Paint Work Completion-L19 21.Sep.14 21-Nov-14 -61 - 2 0.00 Paint Work Completion-L20 25.Sep.14 27-Nov-14 -63 - 2 0.00 Paint Work Completion-L21 01.Okt.14 6-Dec-14 -66 - 2 3.00 MEP H/L Completion - L29 07.Okt.14 11.Okt.14 -4 8.00 MEP H/L Completion - L30 11.Okt.14 23.Okt.14 -12 1.00 MEP H/L Completion - L31 14.Okt.14 20.Okt.14 -6 7.00 MEP H/L Completion - L32 20.Okt.14 27.Okt.14 -7 6.00 MEP H/L Completion - L33 28.Okt.14 03.Nov.14 -6 6.00 MEP H/L Completion - L34 04.Nov.14 10.Nov.14 -6 6.00 MEP H/L Completion - L35 11.Nov.14 17.Nov.14 -6 6.00 MEP H/L Completion - L36 17.Nov.14 23.Nov.14 -6 6.00 MEP H/L Completion - L37 23.Nov.14 29.Nov.14 -6 7.00 90% 34% 5% Variance since Aug 14 Activity 2-Oct-14 9-Oct-14 13-Oct-14 17-Oct-14 21-Oct-14 27-Oct-14 2-Nov-14 8-Nov-14 14-Nov-14 Total Variance Upward Trend Downward Trend No Change > 5 days 0 to 5 days < 0 days
  • 21. 20 Physical % Complete 30 25 20 15 10 5 * Note: Physical % Complete based on TCP - Rev 3. Nomination of PS Items Clause 14 Program TCP - Rev 3 Current Float Var. since Aug 14 7-May-15 10-Aug-13 7-May-15 51 - 1-Oct-14 2-Feb-12 24-Feb-14 -178 - 30.00 1-Oct-14 3-Jun-12 20-Aug-14 69 - 30.00 21-Nov-12 20-Nov-14 15-Jan-13 18-Apr-13 Nominated 4-Mar-13 4-Nov-14 116 - 13-Nov-14 20 - 17-Apr-13 3-Sep-14 171 - 90% 34% 5% SC Nomination for Fit Out (Life Style) SC Nomination for Fit Out (Fendi Flat) SC Nomination for Sauna,Jacuzzi Critical Path (TCP-Rev 3) Work Packages 2013 2014 2015 2016 Planned Actual Impact on MS02 0.89 Schedule Performance Index (SPI) SC Nomination for Fit Out (Entrance) SC Nomination for Façade Lighting SC Nomination for Swimming Pool No Change Milestone Nominated Downward Trend > 5 days 0 to 5 days Monthly Progress Report No. 7 - September 2014 Progress % Complete Days Remaining until MS02 4-Nov-14 Impact on MS01 Concrete Skeleton Fit Out after Wild Air Façade Glazing Lifts Testing/Commissioning Current Forecast < 0 days 13-Nov-14 1-Oct-14 Upward Trend SC Nomination for Landscaping Works SC Nomination for Roof Steel Works Snagging 9.09 9.62 10.57 11.53 12.48 15.29 18.4 22.35 25.15 7.4 9.62 10.21 10.81 11.4 13.62 16.04 18.95 22.46 0 Planned % Actual % - 182 - 4 22.5 226
  • 22. 21 Negative Float Contour Dominant Causes for Project Delays -10 Monthly Progress Report No. 7 - September 2014 Critical Paths Analysis Paths Package Activities Path 3 (Curtain Wall) Path 1 Façade Light Nomination, Procurement, Engineering, Installation. Path 4 (MEP Long Lead Items (Mechanical)) -20 Path 1 (Façade Light) Path 2 ( Bus Bars and LV Panels) -40 -144 -182 * Note: The shown analysis was run based on TCP-Rev 03, however, this version isn't approved so the shown analysis is only a tentative one. Path 3 Curtain Wall Installation of 7 elements for external façade (unitized system, stick system, doors, balcony partitions, cladding, balustrade and louvers. Float - 182.00 - 51.00 Path 4 MEP Long Lead Items (Mechanical) CW pumps submission/approval, procurement/installation, producing wild air, fit out works by JC Maclean. - 50.00 Path 2 -144 days Path 1 -182 days Path 3 -51 days Path 4 -50 days -182 THIS MONTH DELAYS IDENTIFIED Path 2 Bus Bars and LV Panels Procurement/installation of Bus Bars and LV Panels. - 144.00 Analysis run on 30-September-14
  • 23. 22 Risk Analysis Risk Analysis on Critical Paths Monthly Progress Report No. 7 - September 2014 • Risk: Delay of -182 days • Driver: Late of Nomination of Façade Light • Mitigation: • The Engineer is of the view that the facade light nomination will not affect the project completion date, as the light fixtures will be installed before the project completion, which means there is enough time for procurement and engineering. • However, it is recommended that the client to expedite the nomination to avoid any risk to coordinate procurement with other parties. • Risk: Delay of -144 days • Driver: Procurement of Bus Bars and LV Panels • Mitigation: • An instruction issued by DAMAC to ATC to proceed with procuring the Bus Bars and LV Panels. The LPO will be issued during the month of October 2014. • On the other hand DAMAC/AECOM are working to get the NOC from Emaar in order to seek the design NOC from DEWA. Analysis run on 30-September-14 • Risk: Delay of -51 days • Driver: Delay in Curtain Wall Installation • Mitigation: • The design of secondry steel structure was done by ALICO. • ATC to submit the fabrication drawings to the engineer for approval. • Unitized panels will be delivered to site by 21- Oct-14. • Risk: Delay of -50 days • Driver: Chilled Water Pumps • Mitigation: • On the basis that the chilled water pumps will contribute in producing wild air so that the delay in submission the material submittal affected the delivery date to site and thus affected the commencement of wild air operation. However, the pumps are approved and the purchase order will be issued during August 2014. • The Engineer is of the view that the wild air is a vague issue so that Arabtec has been instructed many time in the weekly progress meetings to plan the wild air operation to allow the fit out work start and submit a proposal for review, however, ATC stated that the term ''wild air'' is not in the contract. Path 1 Path 2 Path 3 Path 4 Path 1 Path2 Path3 Path 4 200 180 160 140 120 100 80 60 40 20 0 Paths 182 144 51 50 Delays Critical Paths
  • 24. 23 Slabs Planned Pouring Actual Pouring Progress Variance 23rd floor 02.Jul.14 4-Jul-14 100% - 2 .00 24th floor 10.Jul.14 10-Jul-14 100% - 1 .00 25th floor 19.Jul.14 17-Jul-14 100% 1 .00 26th floor 26.Jul.14 23-Jul-14 100% - 1 .00 27th floor 03.Aug.14 1-Aug-14 100% 1 .00 28th floor 09.Aug.14 9-Aug-14 100% - 29th floor 16.Aug.14 14-Aug-14 100% - 30th floor 23.Aug.14 22-Aug-14 100% - 1 .00 31st floor 31.Aug.14 31-Aug-14 100% - 32nd floor 06.Sep.14 7-Sep-14 100% - 1 .00 33rd floor 11.Sep.14 12-Sep-14 100% - 34th floor 16.Sep.14 18-Sep-14 100% - 1 .00 35th floor 21.Sep.14 24-Sep-14 100% - 1 .00 36th floor 27.Sep.14 30-Sep-14 100% - 3 .00 Progress Photographs Structure Progress - Level 36 Zone B - Section DD; Seepage Area Monthly Progress Report No. 7 - September 2014 57.12% 5.69% 17.50% 9.42% 12.38% %Pld %Act 0.00% 0.00% 3.42% 56.34% 3.38% 16.04% 20.63% 2.10% 0.38% DAMAC Heights Tower
  • 25. 24 Core Walls Planned Pouring Actual Pouring Progress Variance 23rd floor 21.Jun.14 15-Jun-14 100% - 24th floor 30.Jun.14 19-Jun-14 100% 2 .00 25th floor 06.Jul.14 26-Jun-14 100% 2 .00 26th floor 13.Jul.14 3-Jul-14 100% - 1 .00 27th floor 20.Jul.14 14-Jul-14 100% - 1 .00 28th floor 27.Jul.14 21-Jul-14 100% - 1 .00 29th floor 04.Aug.14 27-Jul-14 100% 1 .00 30th floor 11.Aug.14 13-Aug-14 100% 2 .00 31st floor 18.Aug.14 17-Aug-14 100% 7 .00 32nd floor 23.Aug.14 24-Aug-14 100% - 1 .00 33rd floor 28.Aug.14 28-Aug-14 100% 6 .00 34th floor 03.Sep.14 3-Sep-14 100% - 3 .00 35th floor 08.Sep.14 14-Sep-14 100% - 2 .00 36th floor 16.Sep.14 17-Sep-14 100% - 6 .00 37th floor 22.Sep.14 25-Sep-14 100% - 3 .00 38th floor 27.Sep.14 29-Sep-14 100% - 1 .00 Progress Photographs Dry Area: False Ceiling Suspension System @ Level 6 Corridor: False Ceiling Boards @ Level 6 Monthly Progress Report No. 7 - September 2014 57.12% 5.69% 17.50% 9.42% 12.38% %Pld %Act 0.00% 0.00% 3.42% 56.34% 3.38% 16.04% 20.63% 2.10% 0.38% DAMAC Heights Tower
  • 26. 25 HVAC HL Works Planned Finish Actual Finish Progress Variance 24th floor 30.Aug.14 91% 25th floor 06.Sep.14 90% 26th floor 13.Sep.14 90% 27th floor 21.Sep.14 84% 28th floor 28.Sep.14 69% 29th floor 07.Okt.14 52% FF HL Works Planned Finish Actual Finish Progress Variance 24th floor 30.Aug.14 99% 25th floor 06.Sep.14 98% 26th floor 13.Sep.14 96% 27th floor 21.Sep.14 96% 28th floor 28.Sep.14 88% 29th floor 07.Okt.14 78% Progress Photographs Wet Area: Wall Tiles and Water Proofing @ Level 6 Painting (Primer & Putty) @ Level 13 Monthly Progress Report No. 7 - September 2014 57.12% 5.69% 17.50% 9.42% 12.38% %Pld %Act 0.00% 0.00% 3.42% 56.34% 3.38% 16.04% 20.63% 2.10% 0.38% DAMAC Heights Tower
  • 27. 26 Progress Photographs Monthly Progress Report No. 7 - September 2014 Plumbing HL Work Planned Finish Actual Finish Progress Variance 24th floor 30.Aug.14 95% 25th floor 06.Sep.14 95% 26th floor 13.Sep.14 95% 27th floor 21.Sep.14 95% 28th floor 28.Sep.14 95% 29th floor 07.Okt.14 49% Electrical HL Work Planned Finish Actual Finish Progress Variance 24th floor 30.Aug.14 94% 25th floor 06.Sep.14 80% 26th floor 13.Sep.14 94% 27th floor 21.Sep.14 90% 28th floor 28.Sep.14 90% 29th floor 07.Okt.14 84% MEP High Level Service @ Level 27 Foundation for Equipment @ Level 30 57.12% 5.69% 17.50% 9.42% 12.38% %Pld %Act 0.00% 0.00% 3.42% 56.34% 3.38% 16.04% 20.63% 2.10% 0.38% DAMAC Heights Tower
  • 28. 27 Monthly Progress Report No. 7 - September 2014 Progress Photographs Blocks Planned Finish Actual Finish Progress Variance 17th floor 27-Jul-14 95% 18th floor 5-Aug-14 50% 19th floor 10-Aug-14 95% 20th floor 16-Aug-14 95% 21st floor 20-Aug-14 95% 22nd floor 27-Aug-14 95% 23rd floor 1-Sep-14 95% 24th floor 7-Sep-14 95% 25th floor 13-Sep-14 95% 26th floor 20-Sep-14 95% 27th floor 28-Sep-14 70% 28th floor 7-Oct-14 15% 29th floor 14-Oct-14 5% Substation - Trenches and Block Wall Stick Curtain Wall - Aluminium Cladding 57.12% 5.69% 17.50% 9.42% 12.38% %Pld %Act 0.00% 0.00% 3.42% 56.34% 3.38% 16.04% 20.63% 2.10% 0.38% DAMAC Heights Tower
  • 29. 28 Concealed MEP Planned Finish Actual Finish Progress Variance 19th floor 21-Aug-14 98% 20th floor 27-Aug-14 99% 21st floor 02.Sep.14 96% 22nd floor 08.Sep.14 96% 23rd floor 13.Sep.14 90% 24th floor 18.Sep.14 59% Plaster Planned Finish Actual Finish Progress Variance 17th floor 19-Aug-14 95% 18th floor 26-Aug-14 2% 19th floor 1-Sep-14 95% 20th floor 6-Sep-14 70% 21st floor 11-Sep-14 13% 22nd floor 17-Sep-14 5% Progress Photographs Stick Curtain Wall - Galss Panels Brackets Installation for Balcony Balustrade Monthly Progress Report No. 7 - September 2014 57.12% 5.69% 17.50% 9.42% 12.38% %Pld %Act 0.00% 0.00% 3.42% 56.34% 3.38% 16.04% 20.63% 2.10% 0.38% DAMAC Heights Tower
  • 30. 29 Health, Safety & Environment HSE Statistics Total Hours Worked Work Force (Average) Monthly Progress Report No. 7 - September 2014 Fatalities Lost Time Injury First Aid Cases Near Misses 381,010 1465 0 0 2 3 4,292,339 1402 0 4 182 15 4,673,349 0 0 4 184 18 * Note: HSE Site Inspections Site Observations Notices (Improvement & Stop Works) Issues Closed Open Issued Closed Open Safety Audits (Average) 5 - 14 10 4 2 1 2 128 - 174 172 2 22 21 1 133 - 188 182 6 24 22 2 HSE Training & Seminars Orientation for New Hires 308 4,440 4,748 Significant Incidents 1 2 3 4 5 6 Critical Manageable Severe Negligible This Month 19 No. of Training Tool Box Talks Safety Training Safety Meetings Description/Comments Risk Rate Joint Inspections Recordable Injuries 0 19 Previous Months Total Project This Month Previous Months Total Project 4 66 70 Current Month Previous Months Total Project 195 1346 1541 5 60 65 Water seepage in section DD and a subsequent soil settlement along section BB and DD. C S M N C
  • 31. 30 May Statistics 0 (0) 0 (4) 0 (19) 2 (184) 14 (188) LTI & Lost Work Days Monthly Progress Report No. 7 - September 2014 Fatalities LTI Total Hours Worked this Month Total Hours Worked Previous Months Total Hours Worked For the Project Work Force Average Notices Issued this Month Current Month (Cumulative Contract) Recordable Injuries First Aid Cases Site Observations Eye Injuries 0 (22) Back Injuries 0 (4) Face Injuries 0 (9) Trunk Front Injuries 0 (4) Hand Injuries 1 (62) Head Injuries 0 (4) Arm Injuries 1 (28) Leg Injuries 1 (35) Ankle/Foot Injuries 0 (14) 3.5 3 2.5 2 1.5 1 0.5 0 Lost Time Injury (LTI) Lost Work Days (LWD) 381,010 4,292,339 4,673,349 1465 2
  • 32. 31 Engineering NOCs Status Summary Actual Issue Date 17.Sep.13 GSM NOC RME/AECOM 19.Jun.14 - 23.Jän.11 14.Nov.13 25.Nov.13 10.Jul.14 09.Jun.13 27.Mai.14 06.Jul.14 05.Mai.13 25-Mar-13 27-Dec-11 25-Jun-12 9-Sep-13 90% # 34% 30 to < 60 days 5% RME > 60 days < 30 days Note: Days remaining from 30 Sep 2014 to Anticipated Date Expiry Date Days Remaining Responsible Dubai Civil Aviation 26.Mai.15 RME/AECOM RME/AECOM DEWA - Electrical Electrical Load Design NOC 04.Mai.15 RME/AECOM LV Design Drawing Approval Revised Approval is required RME/AECOM Substation / Trench Design Approval Revised Approval is required RME/AECOM Authority Etisalat Design NOC & Drawings Approval Monthly Progress Report No. 7 - September 2014 NOC/Permit Anticipated Issue Date Height NOC Warning Light NOC Revised Approval is required Final NOC after final design approval. Water Supply Design Drawing Approval Revised Approval is required RME/AECOM Revised Approval is required Revised Approval is required 16.Sep.15 RME/AECOM Etisalat RME ATC RME/AECOM RME/AECOM Revised Approval is required Dubai Municipality Fence NOC 22.Jul.11 Ground water Discharge 08.Mai.14 Drainage Design NOC and Drawings Approval FIC Location Approval Dubai Civil Defense Design Drawing Approval RME/AECOM DEWA - Water Water Design NOC 24-Mar-15 RME/AECOM EMAAR Water Seepage Remedial Works RME Dewatering Conditional NOC 24-Dec-12 RME Drainage NOC 9-Dec-13
  • 33. 32 Critical Authorities Issues Authority Action Subject NOCs & Dwgs. NOC DEWA, DM and Civil Defence Revised approvals are required due to the architectural changes. Engineering Submittal Status Report Planned Date Current Forecast 1 2 3 4 5 6 17 3 12 - 1 0 1 1266 58 1055 6 73 66 8 72 37 28 1 5 1 0 209 39 128 0 17 22 3 3- Revise& Resubmit 5- Under Review 4- Rejected 6- Review not required * Note: Only 2014 submittals have been considered. Submitted Open Closed 367 35 332 209 39 170 72 7 65 90% 81% 90% 19 89% 1266 145 1121 17 1 16 1931 227 1704 Monthly Progress Report No. 7 - September 2014 EMAAR 30.Okt.14 1- Approved 2- Approved as Noted Request for Information Materials Method Statement Prequalification Approval * Note: Only 2014 submittals have been considered. 94% 0 5 0 Review Category Submittals Closed % RFIs Closed Document Submittal Prequalification Approval NOC has to be given by Emaar in order to seek the design NOC from DEWA. Submitted 0 Total 88% Number of Submittals Submittals Open Shop Drawings Method Statements Materials Document Submittal Overdue % Closed Shop Drawings 88% 12% Submittals Closed Submittals Open 1931 1704 227 90%
  • 34. 33 Quality Assurance & Control Non-Conformance Reports (NCR) Category 1: Per Work Package Monthly Progress Report No. 7 - September 2014 September NCRs Total NCRs Issued Closed Open Issued Close d Open Issued Closed Open 8 7 1 0 0 0 8 7 1 68 57 11 3 6 2 71 63 8 3 2 1 1 1 1 4 3 1 11 11 0 4 1 3 15 12 3 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 90 77 13 8 8 6 98 85 13 General Architectural MEP Lifts Category 2: Per Root Causes September NCRs Total NCRs Issued Closed Open Issued Close d Open Issued Closed Open 5,16,44,45,56,62, 64,73,86. 9 8 1 0 1 0 9 9 0 6,8,11,12,14,15,21,22,2 3,24,26,27,29, 32,38,39,43,51,53,54,8 0,81,98. 22 22 0 1 1 0 23 23 0 9,28,99,102,104. 2 1 1 3 0 3 5 1 4 34,49,50,66. 4 4 0 0 0 0 4 4 0 1,37,40,69,82. 5 5 0 0 0 0 5 5 0 10,13,17,18,19,20,25,3 0,31,33,35,41,46,47,48, 52,55,57,58,59,60,65,6 8,70,71,72,74,75,76,77, 78,79,83,84,85,88,89,9 0,91,94,96,100,101. 40 30 10 3 5 3 43 35 8 2,3,7,42,61,63,67,87,95 . 8 7 1 1 1 0 9 8 1 90 77 13 8 8 6 98 85 13 Use of Unapproved Drawings/Materials Deviation from Specifications Not Following Manufacturer's Instructions Deviation from the Safety Requirements Not working as per Method Statement Bad Workmanship Others Total Use of Unapproved Drawings/Material Total Work Area Previous NCRs Others NCR ID Deviation from Specifications Not Following Manufacturer's Instructions Deviation from the Safety Requirements Not working as per Method Statement Bad Workmanship Previous NCRs Work Area Structural External Façade 9 23 5 4 5 43 9 A B C D E F G
  • 35. 34 Key Quality Improvement Measures Implemented in the Month • CurreŶtlLJ ATC keeps suďŵittiŶg the ĐoŶĐrete test results iŶ tiŵelLJ ŵaŶŶer as was instructed by AECOM. • AECOM iŶstruĐted ATC to suďŵit the struĐtural ĐlearaŶĐe ďefore the commencement of MEP work. • AECOM is going to hold Quality Technical Meetings on weekly basis to monitor the quality. Audits Internal External Quality Trending Monthly Progress Report No. 7 - September 2014 NCR Closed % NCR Opened % Total NCRs Raised NCRs Closed NCRs Opened 8 NON-CONFORMANCE IDENTIFIED THIS MONTH Quality Improvement Measures 3 9 4 6 3 3 13 9 6 5 13 8 14 12 10 8 6 4 2 0 NCR Raised 87% 13% 98 85 13
  • 36. 35 Commercial Status Cost Summary (AED) Monthly Progress Report No. 7 - September 2014 244,747,598 8,177,509 - 226,116,726 479,041,833 37,437,524 1,899,214 20,000,000 7,738,272 - - 27,738,272 - 297,020 389,706 686,726 515,808 GHU 1,676,655 1,595,000 81,655 - - 1,676,655 - - Payment Status (AED) AED % AED % AED % AED 119,845,391 23.58% 115,383,973 22.7% 75,444,872 14.8% 63,693,496 21,989,206 79.3% 21,989,206 79.3% 21,436,431 77.3% 21,792,331 686,726 100.0% 618,053 90.0% 418,956 61.0% 618,053 1,403,119 83.7% 1,262,807 75.3% 1,355,221 80.8% 1,320,372 516479357.2 27738271.57 686726.1 * Note: The percentage value is the current amount divided by the Contract Price ATC IPC# 39 (Aug-14) was considered for this report. ATC RMB IGS GHU Variation Status 1676655 Variation Approved Cumulative Current Month Variation Rejected Variation DAMAC Assessment Variation ATC Assessment Variation Approved Variation Rejected Variation DAMAC Assessment 35 9 9 26 0 0 0 Variation Value (AED) Variation Approved Variation Rejected Variation DAMAC Assessment Variation ATC Assessment Variation Approved Variation Rejected Variation DAMAC Assessment 8,177,509 6,801,791 1,679,024 220,190 Key Commercial Issues 1 2 Monthly Progress Report No. 7 - September 2014 36 All Gross/Net Certified and Paid to Date Values excluded Advance Payments. Item Management Strategy Extension of Time Claims EOT flooding claims are under review by 3rd party, anticipated closure in October 2014. ATC's Pending Variations Variations submission, assessment and approval continues. Variation ATC Assessment ATC 0 Cumulative Current Month Variation ATC Assessment ATC 12.53% 78.56% 95.29% 81.63% Effective Contract Value Approved Variations Approved Claims Approved PS Total Commitments Residual PS Pending Variations Estimate at Completion ATC 518,378,571 RMB 27,738,272 IGS 1,202,534 Paid to Date % Gross Certified Net Certified Previously Certified
  • 37. Cash Flow (AED,000) 1,300 1,200 1,100 1,000 900 800 700 600 500 400 300 200 100 Notice of Delays Under Review Ref . Date Received Delayed nomination of Elevators Delayed nomination of MEP Delayed nomination of Glazing 1 19-Feb-12 2 19-Feb-12 3 19-Feb-12 4 Delayed nomination of BMU 19-Feb-12 5 Delayed nomination of Façade Light 19-Feb-12 6 Delayed nomination of Sanitary Fittings 19-Feb-12 7 Delayed nomination of Home Automation 19-Feb-12 8 19-Feb-12 9 19-Feb-12 10 19-Feb-12 11 2-Apr-12 12 2-Apr-12 13 6-May-13 14 6-May-13 15 6-May-13 16 6-May-13 17 6-May-13 18 6-May-13 19 6-May-13 20 6-May-13 21 18-Aug-13 22 12-Feb-14 23 5-Mar-14 23.58 12.53 Delayed nomination of Kitchen Cabinet Delayed nomination of Shower Enclosure ATC Total Variations Delayed nomination of Timber Doors/Ironmongery Approved Delayed nomination of Vanity Counter Delayed nomination of Swimming Pool Delayed nomination of Toilet Access. Delayed nomination of Light Fittings Delayed nomination of Roof Features Equipment Delayed nomination of Fit out for Entrance * Note: Only SC's nominations delays have mentioned. Ref . 35 ATC Total Variations Rejected Delayed nomination of Wardrobe, Vanaties Delayed nomination of Mirrors Delayed nomination of Landscape Delayed nomination of Fit out for HC Delayed nomination of Supply Porcelain/Ceramic Tiles Item Date Received No Claims closed to date - ATC Total Variations Delayed nomination of Fit out for Saunna,Steam and Pending Delayed nomination of Fit out for Signage/Lockers Claims Closed ATC Gross % Certified * Note: Cash flow will be produced after agreeing the target completion program. Item ATC Paid % to Date 35 9 0 Monthly Planned Monthly Actual Cum. Planned Cum. Actual
  • 38. 37 Risk Management Top 7 Risks RS_04 Risk Event Cause Risk Response Delays in possessing DEWA approval for LV shop drawings and delays in procuring LV Panels and Bus Bars Re-design of secondary steel structure to support the façade Changes to the mechanical floors arrangement and absence of the design for P5. Monthly Progress Report No. 7 - September 2014 ALICO designed the secondary steel structure. ATC to expidite submission of fabrication drawings for approval in order to place the material order. DAMAC/R ME ATC Risk ID Rating Risk Owner DAMAC/ AECOM RS_01 RS_02 Late of issuing MEP IFC drawings. RME to issue the final MEP IFC drawings. Also the renewal of DEWA design NOC to be done. On the other hand an instruction to proceed with procurment was issued by DAMAC. Flooding in Zone B Seepage through openings in the existing diaphragm walls. Seepage occurred during September 2014 and AECOM will provide a proposal for a permanent soluation to the diaphragm wall. ATC/ REMCO RS_03 Delays in pouring the slab of level 62 8 days estimated cycle will not be achieved as the core wall will need for 2 weeks at least. AECOM highlighted this issue to ATC in the weekly progress meeting, however, no mitigation provided. ATC RS_05 Delays In MEP high level installations, Concealed Work and Risers Work Delays from REMCO in high level works installation due to insufficient of manpower. REMCO to increase the allocated manpower in order to work concurrently in 5 levels. RS_07 BMU Functionality DAMAC ALICO RS_06 Delays in nomination of the PS items DAMAC's tenders floating/awarding process delayed. DAMAC has to expedite the PS items' procuring process in order to avoid delaying the site works. Notably façade light package. There is no coordination between the BMU and Façade Designs. Alico is doing the technical study. Risk Rating Breakdown 5 4 3 2 1 0 Critical Severe Manageable Negligible Critical Severe Manageable Negligible
  • 39. 38 Core Values into Practice R Monthly Progress Report No. 7 - September 2014
  • 40. 39 AECOM Core Values 'To enhance and sustain the world’s built, natural and social environments'' Monthly Progress Report No. 7 - September 2014 Growth We recognize that our financial growth is the fairly earned result of living up to these principles. We earn and advance our reputation by delivering superior value on every project that we undertake. Our industry leadership depends on making project solutions more exciting, sustainable and cost-effective. We move with speed and dexterity to adapt and adjust to emerging client and project requirements. 9 Core Values We succeed by doing things the right way, with respect to ethics, laws, standards of quality, and each other. Employees Our product is our people — our knowledge, skills, passion and diversity. Our success begins with valuing our people and fostering their development. We succeed by making our clients successful. We embrace our clients’ challenges and opportunities and work for their success. Whether in an office or on a construction site, keeping our people safe is our most important measure of success. Clients Excellence Innovation Safety Integrity Agility File :- Printed On :- 16.10.2014 at 10:38
  • 41. 40 Core Values into Practice AECOM Solutions Time Cost 1 AECOM advice to allow the building tower to proceed beyond Level 15 in absence of Zone B Raft being completed. 15 weeks + delays EOT Costs High AECOM reviewed the Structure and concluded that there was no impact on the design to allow the tower structure to proceed without Zone B. CS-Site based Structural B+P-Structural Implemented by AECOM and closed impact negated. No: It is Design Related. Design decision required from Ramboll- however design consultant did not provide an adequate response. INT, CLN, EX, AG, SA 2 Soil Improvement outside the plot to stabilize extent monitoring and supervision and the need to decide when to commence excavation. Continued delay to Zone B construction added to the current claim by ATC for flood event including suspension of all work. EOT Costs+ Damages + Insurance claims+suspension of work costs. High AECOM reviewed the Client proposed solution and methodology and devised an implementation plan in coordination with AECOM Geotechnical department to minimize the risk on the area and provided an implementation plan with monitoring and contingency measures to allow for commencement of excavation work. CS-Site based Civil/ Structural TRN-Geotechnical Implemented by AECOM ongoing No: AECOM Scope covers supervision services and monitoring only. AECOM provided advice and recommendations to the implementation of the solution proposed by the client without any liability for the success or failure of the solution proposed. INT, CLN, EX, AG, SA AECOM Values Legend Monthly Progress Report No. 7 - September 2014 Sr. Description Impacted if not addressed Risk AECOM Solution AECOM Discipline involved Status Included in Scope AECOM Values INT: Integrity CLN: Client GR: Growth EX: Excellence INN: Innovation AG: Agility EMP: Employees SA: Safety 9 Core Values File :- Printed On :- 16.10.2014 at 10:38
  • 42. 41 Core Values into Practice AECOM Solutions Time Cost 3 Sub Contractor for Post-tensioned slab design highlighting punching shear overstress in various columns from levels 26 and above. Delay to the casting of the slabs. Increased cost of adding reinforcement and concrete as drop caps and shear reinforcement at the identified columns. Medium AECOM site structural team reviewed the calculations and advised that the sub contractor was not applying the loads correctly thereby eliminating the added measures. CS-Site Structural Implemented by AECOM and closed negating the impact Monthly Progress Report No. 7 - September 2014 No: It is Design Related. Design decision required from Ramboll- however design consultant did not provide adequate response, AECOM provided the guidance through on site workshop and obtained Design Consultant, 3rd party and Employer consensus resulting in the sub contractor revising his comments. INT, CLN, EX, AG, SA 4 AECOM Values Legend Included in Scope AECOM Values INT: Integrity CLN: Client GR: Growth EX: Excellence INN: Innovation AG: Agility EMP: Employees SA: Safety 9 Core Values Sr. Description Impacted if not addressed Risk AECOM Solution AECOM Discipline involved Status File :- Printed On :- 16.10.2014 at 10:38
  • 43. 42 Appendices R Monthly Progress Report No. 7 - September 2014
  • 44. QATAR ACCOUNT MANAGEMENT PROGRAM Damac Heights Appendix 1 Schedule Update
  • 45. Activity ID Activity Name Original Duration DAMAC Gulf Properties L.L.C DAMAC Heights at Dubai Marina Planned Start Planned Finish Actual/Forecast Start Actual/Forecast Finish Total Float Planned % Complete Actual % Complete SPI 2014 2015 Total 2012.00 24-Feb-14 14-May-16 05-Jun-11 A 20-Dec-16 -220.00 25.15% 22.46% 0.89 DAMAC HEIGHTS-Target Completion Programme- Rev 3.1 2012.00 24-Feb-14 14-May-16 05-Jun-11 A 20-Dec-16 -220.00 25.15% 22.46% 0.89 GENERAL 2012.00 24-Feb-14 14-May-16 05-Jun-11 A 20-Dec-16 -220.00 100% 0% 0.00 KEY DATES 1700.00 15-Nov-14 14-May-16 05-Jun-11 A 20-Dec-16 -182.00 0% 0% 0.00 DHKMSGN220 IFC Drawing 0.00 05-Jun-11 A 100% 100% 0.00 DHKMSGN200 Commencement Date 0.00 19-Jun-11 A 100% 100% 0.00 DHKMSGN210 Site Possession 0.00 19-Jun-11 A 100% 100% 0.00 DHKMSGN250 DM Approval on enabling Work Completion 0.00 02-Oct-12 A 100% 100% 0.00 DHKMSGN260 Approval test results on Enabling Work items 0.00 02-Oct-12 A 100% 100% 0.00 DHKMSGN240 Dewatering System Handing Over 0.00 22-Oct-12 A 100% 100% 0.00 DHKMSGN230 Building Permit 0.00 27-Mar-13 A 100% 100% 0.00 DHKMSGN470 Design Nocs 0.00 18-Apr-13 A 100% 100% 0.00 DHKMSGN410 Tower Raft Pour 0.00 17-May-13 A 100% 100% 0.00 DHKMSGN420 Overall Foundation Completion 0.00 15-Nov-14 21-Dec-14 -28.00 0% 0% 0.00 DHKMSGN430 Basement/Podium Completion of Structure up to GF 0.00 19-Feb-15 26-Mar-15 -28.00 0% 0% 0.00 DHKMSGN400 Partial Power On (Up to Lvl.30) 0.00 19-Feb-15 19-Apr-15 -50.00 0% 0% 0.00 DHKMSGN500 Wild Air On (Up to Lvl..29) 0.00 08-Mar-15 05-May-15 -50.00 0% 0% 0.00 DHKMSGN450 Podium Completion of Structure up to Lv. P5 0.00 04-Jun-15 09-Jul-15 -1.00 0% 0% 0.00 DHKMSGN402 Partial Power On (Lvl.31-61) 0.00 14-Jun-15 20-Jul-15 -14.00 0% 0% 0.00 DHKMSGN502 Wild Air On (Lvl.31-61) 0.00 21-Jul-15 06-Aug-15 -14.00 0% 0% 0.00 DHKMSGN452 Completion of Structure 0.00 12-Aug-15 17-Aug-15 7.00 0% 0% 0.00 DHKMSGN440 Completion of Facade Cladding Up to Lvl.85 0.00 15-Aug-15 18-Oct-15 -10.00 0% 0% 0.00 DHKMSGN462 Wild Air On (Level 62 above) 0.00 08-Nov-15 02-Jan-16 -46.00 0% 0% 0.00 DHKMSGN442 Completion of Facade Cladding Up to top 0.00 12-Nov-15 13-Jan-16 -5.00 0% 0% 0.00 DHKMSGN460 Permanent Power On (Overall) 0.00 08-Dec-15 25-May-16 -144.00 0% 0% 0.00 DHKMSGN990 Project Completion 0.00 14-May-16 20-Dec-16 -182.00 0% 0% 0.00 EMPLOYER KEY DATES 1756.00 07-Sep-14 19-Feb-16 15-Oct-12 A 30-Jun-16 -77.00 0% 0% 0.00 ISSUANCE OF VALID NOCs (BY OTHERS) 0.00 24-Feb-14 16-Mar-14 30-Sep-14 30-Sep-14 25.00 0% 0% 0.00 AUTHORITIES APPROVALS 1069.00 24-Feb-14 08-Mar-16 05-May-13 A 25-May-16 -63.00 100% 0% 0.00 DEWA POWER ON 1069.00 24-Feb-14 08-Mar-16 05-May-13 A 25-May-16 -63.00 100% 0% 0.00 SUB-STATION WORKS 1069.00 16-Mar-14 08-Dec-15 05-May-13 A 25-May-16 -169.00 100% 0% 0.00 LOAD SCHEDULE 100.00 18-Mar-14 24-Jul-14 18-Mar-14 A 19-Jan-15 -175.00 0% 0% 0.00 DHDWALS010 Prepare Shop Drawings 10.00 18-Mar-14 29-Mar-14 18-Mar-14 A 02-Oct-14 -145.00 100% 99% 0.00 DHDWALS020 Prepare Load Schedules 10.00 26-Mar-14 06-Apr-14 05-Apr-14 A 13-Oct-14 -145.00 100% 99% 0.00 DHDWALS090 Engineer's Review 14.00 07-Apr-14 20-Apr-14 20-May-14 A 14-Oct-14 -175.00 100% 99% 0.00 DHDWALS030 Submit Load Schedules to DEWA REV 00 5.00 20-Apr-14 26-Apr-14 15-Oct-14 20-Oct-14 -145.00 100% 0% 0.00 DHDWALS040 DEWA : Return Load Schedules with comments REV00 21.00 27-Apr-14 25-May-14 21-Oct-14 18-Nov-14 -122.00 100% 0% 0.00 DHDWALS050 Resubmit Load Schedules REV 01 5.00 26-May-14 30-May-14 19-Nov-14 23-Nov-14 -174.00 100% 0% 0.00 DHDWALS060 DEWA : Return Load Schedules with comments REV01 21.00 31-May-14 20-Jun-14 24-Nov-14 14-Dec-14 -174.00 100% 0% 0.00 DHDWALS070 Resubmit Load Schedules REV 02 5.00 21-Jun-14 25-Jun-14 15-Dec-14 20-Dec-14 -143.00 100% 0% 0.00 DHDWALS080 DEWA: Approve Load Schd. REV02 & Issue Const. NOC 21.00 26-Jun-14 24-Jul-14 21-Dec-14 19-Jan-15 -121.00 100% 0% 0.00 SUB-STATION WORKS 667.00 16-Mar-14 02-Feb-15 05-May-13 A 20-Apr-15 -62.00 100% 0% 0.00 DHDWASS110 Prepare Substation Trench Layout Shop Drg 45.00 16-Mar-14 16-Mar-14 05-May-13 A 21-Jun-13 A 100% 100% 0.00 DHDWASS120 Submit SS Trench Layout Shop Drg to DEWA 4.00 16-Mar-14 16-Mar-14 22-Jun-13 A 27-Jun-13 A 100% 100% 0.00 DHDWASS130 DEWA: Return Substation Layout Drg With Comments 12.00 16-Mar-14 16-Mar-14 28-Jun-13 A 09-Jul-13 A 100% 100% 0.00 DHDWASS140 Incorporate DEWA Comments in Shop Drgs 12.00 16-Mar-14 16-Mar-14 10-Jul-13 A 22-Jul-13 A 100% 100% 0.00 DHDWASS150 Resubmit SS Trench Layout Shop Drg to DEWA 6.00 16-Mar-14 16-Mar-14 23-Jul-13 A 30-Jul-13 A 100% 100% 0.00 Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Overall Foundation Completion Basement/Podium Completion of Structure up to GF Partial Power On (Up to Lvl.30) Wild Air On (Up to Lvl..29) Podium Completion of Structure up to Lv. P5 Partial Power On (Lvl.31-61) Wild Air On (Lvl.31-61) Completion of Structure Completion of Facade Cladding Up Prepare Shop Drawings Prepare Load Schedules Engineer's Review Submit Load Schedules to DEWA REV 00 DEWA : Return Load Schedules with comments REV00 Resubmit Load Schedules REV 01 DEWA : Return Load Schedules with comments REV01 Resubmit Load Schedules REV 02 DEWA: Approve Load Schd. REV02 & Issue Const. NOC DEWA: Return Substation Layout Drg With Comments Resubmit SS Trench Layout Shop Drg to DEWA Data Date : 30-Sep-14 Page : 1 of 58 Printed On : 16-Oct-14 Baseline Actual Work Remaining Work Critical Remaining Work Baseline Milestone Curernt Milestone Project Progress Update as of 30-Sep-2014 Taregt Completion Programme - Rev 03 Date Revision Chec... Appr... 20-Aug-14 Target Completion Programme - Rev 03 (Baseline) 30-Sep-14 Schedule Update - September-14 (Update) SK
  • 46. Activity ID Activity Name Original Duration Planned Start Planned Finish Actual/Forecast Start Actual/Forecast Finish Total Float Planned % Complete Actual % Complete SPI 2014 2015 DHDWASS160 DEWA : Approve SS Trench Layout Shop Drawings 21.00 16-Mar-14 16-Mar-14 31-Jul-13 A 27-Aug-13 A 100% 100% 0.00 DHDWASS170 Complete Substations Trench Works 60.00 01-Jun-14 15-Jun-14 21-Sep-13 A 22-Jun-14 A 100% 100% 0.00 DHDWASS010 Access to Substation 0.00 16-Jun-14 02-Sep-14 A 100% 100% 0.00 DHDWASS020 Fix Cable Trays 6.00 05-Aug-14 11-Aug-14 22-Oct-14 29-Oct-14 -52.00 100% 0% 0.00 DHDWASS030 Fix Electrical Conduits 6.00 12-Aug-14 18-Aug-14 30-Oct-14 05-Nov-14 -52.00 100% 0% 0.00 DHDWASS040 Power & Lighting Wiring 6.00 19-Aug-14 25-Aug-14 06-Nov-14 12-Nov-14 -52.00 100% 0% 0.00 DHDWASS050 Install & Terminate DB's 6.00 26-Aug-14 01-Sep-14 13-Nov-14 19-Nov-14 -52.00 100% 0% 0.00 DHDWASS060 Install Wiring Devices 6.00 02-Sep-14 08-Sep-14 20-Nov-14 26-Nov-14 -52.00 100% 0% 0.00 DHDWASS070 Install Light Fittings 6.00 02-Sep-14 08-Sep-14 20-Nov-14 26-Nov-14 -48.00 100% 0% 0.00 DHDWASS080 Install Emergency Lights 6.00 02-Sep-14 08-Sep-14 20-Nov-14 26-Nov-14 -48.00 100% 0% 0.00 DHDWASS090 Install Fire Alarm 5.00 03-Sep-14 08-Sep-14 22-Nov-14 26-Nov-14 -48.00 100% 0% 0.00 DHDWASS100 Substation Works Completion 0.00 22-Sep-14 11-Dec-14 -52.00 100% 0% 0.00 DHDWASS180 Substation Ready for Inspection 0.00 22-Sep-14 11-Dec-14 -52.00 100% 0% 0.00 DHDWASS190 Consultant : Inspect Substation 3.00 23-Sep-14 25-Sep-14 13-Dec-14 15-Dec-14 -52.00 100% 0% 0.00 DHDWASS200 Consultant : Submit Inspection check list to DEWA 6.00 27-Sep-14 02-Oct-14 16-Dec-14 22-Dec-14 -52.00 66.67% 0% 0.00 DHDWASS210 DEWA : Inspect Substation 20.00 05-Oct-14 02-Nov-14 23-Dec-14 20-Jan-15 -44.00 0% 0% 0.00 DHDWASS220 Address DEWA Comments 20.00 03-Nov-14 25-Nov-14 21-Jan-15 12-Feb-15 -53.00 0% 0% 0.00 DHDWASS230 Consultant : Reinspect Substation 12.00 26-Nov-14 10-Dec-14 14-Feb-15 26-Feb-15 -53.00 0% 0% 0.00 DHDWASS240 Consultant : Resubmit Inspection request to DEWA 20.00 11-Dec-14 04-Jan-15 28-Feb-15 22-Mar-15 -53.00 0% 0% 0.00 DHDWASS250 DEWA : Reinspect & Approve Substation 20.00 05-Jan-15 01-Feb-15 23-Mar-15 19-Apr-15 -44.00 0% 0% 0.00 DHDWASS260 Substation Ready for HT Cable / Transformer Work 0.00 02-Feb-15 20-Apr-15 -53.00 0% 0% 0.00 LV ROOM WORKS 603.00 21-Oct-14 08-Dec-15 01-Oct-14 25-May-16 -169.00 0% 0% 0.00 DHDWALV000 Access to LV Room 0.00 21-Oct-14 01-Oct-14 131.00 0% 0% 0.00 DHDWALV010 Cable Ladder & Tray Fixing 26.00 21-Oct-14 20-Nov-14 01-Oct-14 03-Nov-14 131.00 0% 0% 0.00 DHDWALV020 Earthing Strips laying 20.00 05-Nov-14 27-Nov-14 18-Oct-14 10-Nov-14 139.00 0% 0% 0.00 DHDWALV030 Cable lying & Terminations 26.00 22-Nov-14 22-Dec-14 04-Nov-14 04-Dec-14 139.00 0% 0% 0.00 DHDWALV040 Panel Installation 45.00 03-Jan-15 23-Feb-15 08-Mar-15 28-Apr-15 61.00 0% 0% 0.00 DHDWALV050 Panel Earthing termination 15.00 24-Feb-15 12-Mar-15 29-Apr-15 17-May-15 61.00 0% 0% 0.00 DHDWALV060 Install MDB & Termination 30.00 19-Mar-15 22-Apr-15 22-Sep-15 29-Oct-15 -46.00 0% 0% 0.00 DHDWALV170 Install Chequered Plates 12.00 23-Apr-15 04-May-15 30-Oct-15 10-Nov-15 -43.00 0% 0% 0.00 DHDWALV070 Install Wiring Devices 12.00 23-Apr-15 06-May-15 31-Oct-15 12-Nov-15 -46.00 0% 0% 0.00 DHDWALV080 Install Light Fittings 12.00 07-May-15 21-May-15 14-Nov-15 26-Nov-15 -46.00 0% 0% 0.00 DHDWALV090 Install FM 200 System 12.00 23-May-15 04-Jun-15 28-Nov-15 12-Dec-15 -46.00 0% 0% 0.00 DHDWALV100 Install Fire Alarm Devices 12.00 06-Jun-15 18-Jun-15 13-Dec-15 26-Dec-15 -46.00 0% 0% 0.00 DHDWALV110 Complete All MEP Installation in Building 0.00 01-Nov-15 26-Dec-15 -46.00 0% 0% 0.00 DHDWALV120 Submit Inspection request to DEWA 12.00 02-Nov-15 15-Nov-15 27-Dec-15 09-Jan-16 -46.00 0% 0% 0.00 DHDWALV130 DEWA : Inspect Installation 3.00 16-Nov-15 18-Nov-15 10-Jan-16 12-Jan-16 -38.00 0% 0% 0.00 DHDWALV140 Address Comments of DEWA 6.00 19-Nov-15 25-Nov-15 08-May-16 14-May-16 -144.00 0% 0% 0.00 DHDWALV150 Resubmit Inspection Request to DEWA 3.00 26-Nov-15 29-Nov-15 15-May-16 17-May-16 -144.00 0% 0% 0.00 DHDWALV160 DEWA : Inspect & Approve Installations 6.00 30-Nov-15 08-Dec-15 18-May-16 25-May-16 -121.00 0% 0% 0.00 PERMANENT POWER APPLICATION 115.00 02-Feb-15 26-May-15 20-Apr-15 12-Aug-15 -63.00 0% 0% 0.00 DHDWAPA000 Application Registration 60.00 02-Feb-15 12-Apr-15 20-Apr-15 29-Jun-15 -53.00 0% 0% 0.00 DHDWAPA010 DEWA : Estimate amount for permit power 26.00 14-Apr-15 19-May-15 01-Jul-15 05-Aug-15 -45.00 0% 0% 0.00 DHDWAPA020 Client : Pay Estimate amount to DEWA 0.00 26-May-15 12-Aug-15 -45.00 0% 0% 0.00 HIGH TENSION WORKS 222.00 20-Jun-15 08-Dec-15 05-Sep-15 25-May-16 -144.00 0% 0% 0.00 DHDWAHT000 DEWA : HT Cable Work & Transformer Procurement & Installat1io3n0.00 20-Jun-15 23-Nov-15 05-Sep-15 07-Feb-16 -52.00 0% 0% 0.00 DHDWAHT010 Permanent Power on 0.00 08-Dec-15 25-May-16 -144.00 0% 0% 0.00 Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec DEWA : Approve SS Trench Layout Shop Drawings Complete Substations Trench Works Access to Substation Fix Cable Trays Fix Electrical Conduits Power & Lighting Wiring Install & Terminate DB's Install Wiring Devices Install Light Fittings Install Emergency Lights Install Fire Alarm Substation Works Completion Substation Ready for Inspection Consultant : Inspect Substation Consultant : Submit Inspection check list to DEWA DEWA : Inspect Substation Address DEWA Comments Consultant : Reinspect Substation Consultant : Resubmit Inspection request to DEWA DEWA : Reinspect & Approve Substation Substation Ready for HT Cable / Transformer Work Access to LV Room Cable Ladder & Tray Fixing Earthing Strips laying Cable lying & Terminations Panel Installation Panel Earthing termination Install MDB & Termination Install Chequered Plates Install Wiring Devices Install Light Fittings Install FM 200 System Application Registration DEWA : Estimate amount for permit power Client : Pay Estimate amount to DEWA DAMAC Gulf Properties L.L.C DAMAC Heights at Dubai Marina Data Date : 30-Sep-14 Page : 2 of 58 Printed On : 16-Oct-14 Baseline Actual Work Remaining Work Critical Remaining Work Baseline Milestone Curernt Milestone Project Progress Update as of 30-Sep-2014 Taregt Completion Programme - Rev 03 Date Revision Chec... Appr... 20-Aug-14 Target Completion Programme - Rev 03 (Baseline) 30-Sep-14 Schedule Update - September-14 (Update) SK
  • 47. Activity ID Activity Name Original Duration Planned Start Planned Finish Actual/Forecast Start Actual/Forecast Finish Total Float Planned % Complete Actual % Complete SPI 2014 2015 DEWA WATER 567.00 03-Mar-14 08-Mar-16 26-Jan-14 A 12-Apr-16 -20.00 0% 0% 0.00 DUBAI CIVIL DEFENCE 104.00 27-Feb-14 06-Jul-14 24-Feb-14 A 24-Feb-14 A 0% 0% 0.00 CIVIL AVIATION 223.00 29-Oct-14 04-Jun-15 24-Feb-14 A 24-Feb-14 A 0% 0% 0.00 ETISALAT/ DU 383.00 03-Mar-14 14-Jul-15 24-Feb-14 A 11-Oct-15 66.00 0% 0% 0.00 DM DRAINAGE 567.00 24-Feb-14 08-Mar-16 24-Feb-14 A 12-Apr-16 -20.00 0% 0% 0.00 CONSTRUCTION EQUIPMENTS 1570.00 24-Feb-14 14-Nov-15 11-May-13 A 13-Jan-16 -60.00 0% 0% 0.00 ENGINEERING & PROCUREMENT 1843.00 24-Feb-14 07-Dec-15 19-Jun-11 A 02-Feb-16 128.00 0% 0% 0.00 PROVISIONAL SUMS 658.00 24-Feb-14 01-Oct-15 13-Aug-13 A 01-Oct-15 132.00 0% 0% 0.00 MEP LONG LEAD ITEMS 319.00 19-Mar-14 22-Jul-15 14-Jan-14 A 05-Oct-15 -29.00 0% 0% 0.00 Electrical 307.00 10-Jun-14 05-Apr-15 05-Mar-14 A 05-Oct-15 -46.00 0% 0% 0.00 Bus Bar 127.00 10-Jul-14 14-Jan-15 05-Mar-14 A 17-Jun-15 -128.00 0% 0% 0.00 A3260 Material Submittal 14.00 10-Jul-14 26-Jul-14 05-Mar-14 A 16-Apr-14 A 100% 100% 0.00 A3270 Material Approval 14.00 27-Jul-14 13-Aug-14 06-Mar-14 A 06-May-14 A 100% 100% 0.00 A3280 Issue of PO to Supplier 7.00 14-Aug-14 21-Aug-14 20-Jan-15 27-Jan-15 -128.00 100% 0% 0.00 A3290 Manufacturing /Procurement and Delivery of the Material 120.00 23-Aug-14 14-Jan-15 28-Jan-15 17-Jun-15 -128.00 28.33% 0% 0.00 Wiring Accessories 227.00 28-Oct-14 05-Apr-15 16-Apr-14 A 08-Feb-15 52.00 0% 0% 0.00 A3220 Material Submittal 14.00 28-Oct-14 12-Nov-14 16-Apr-14 A 18-May-14 A 0% 100% 0.00 A3230 Material Approval 14.00 13-Nov-14 29-Nov-14 17-Apr-14 A 02-Jun-14 A 0% 100% 0.00 A3240 Issue of PO to Supplier 7.00 30-Nov-14 08-Dec-14 01-Oct-14 11-Oct-14 52.00 0% 0% 0.00 A3250 Manufacturing /Procurement and Delivery of the Material 100.00 09-Dec-14 05-Apr-15 12-Oct-14 08-Feb-15 52.00 0% 0% 0.00 LV Panels & Switchgear 127.00 10-Jun-14 14-Dec-14 18-Mar-14 A 03-Mar-15 104.00 0% 0% 0.00 A3300 Material Submittal 14.00 10-Jun-14 25-Jun-14 18-Mar-14 A 01-May-14 A 100% 100% 0.00 A3310 Material Approval 14.00 26-Jun-14 12-Jul-14 19-Mar-14 A 15-May-14 A 100% 100% 0.00 A3320 Issue of PO to Supplier 7.00 13-Jul-14 20-Jul-14 01-Oct-14 11-Oct-14 104.00 100% 0% 0.00 A3330 Manufacturing /Procurement and Delivery of the Material 120.00 21-Jul-14 14-Dec-14 12-Oct-14 03-Mar-15 104.00 50% 0% 0.00 Generator 193.00 15-Jul-14 30-Mar-15 24-Aug-14 A 05-Oct-15 -46.00 0% 0% 0.00 A3340 Material Submittal 14.00 15-Jul-14 02-Aug-14 24-Aug-14 A 19-Feb-15 -46.00 100% 78.57% 0.00 A3350 Material Approval 14.00 03-Aug-14 18-Aug-14 25-Aug-14 A 23-Feb-15 -46.00 100% 78.57% 0.00 A3360 Issue of PO to Supplier 7.00 19-Aug-14 26-Aug-14 24-Feb-15 03-Mar-15 -46.00 100% 0% 0.00 A3370 Manufacturing /Procurement and Delivery of the Material 180.00 27-Aug-14 30-Mar-15 04-Mar-15 05-Oct-15 -46.00 16.67% 0% 0.00 ELV 227.00 19-Mar-14 28-Apr-15 16-Feb-14 A 03-Mar-15 151.00 0% 0% 0.00 BMS 227.00 28-Oct-14 28-Apr-15 08-Jun-14 A 03-Mar-15 151.00 0% 0% 0.00 A3420 Material Submittal 14.00 28-Oct-14 12-Nov-14 08-Jun-14 A 20-Aug-14 A 0% 100% 0.00 A3430 Material Approval 14.00 13-Nov-14 29-Nov-14 09-Jun-14 A 31-Aug-14 A 0% 100% 0.00 A3440 Issue of PO to Supplier 7.00 30-Nov-14 08-Dec-14 01-Oct-14 11-Oct-14 151.00 0% 0% 0.00 A3450 Manufacturing /Procurement and Delivery of the Material 120.00 09-Dec-14 28-Apr-15 12-Oct-14 03-Mar-15 151.00 0% 0% 0.00 FA System Panels 157.00 19-Mar-14 27-Oct-14 16-Feb-14 A 27-Oct-14 20.00 0% 0% 0.00 A3380 Material Submittal 14.00 19-Mar-14 03-Apr-14 16-Feb-14 A 20-May-14 A 100% 100% 0.00 A3390 Material Approval 14.00 05-Apr-14 20-Apr-14 17-Feb-14 A 04-Jun-14 A 100% 100% 0.00 A3400 Issue of PO to Supplier 7.00 21-Apr-14 28-Apr-14 05-Jun-14 A 23-Jun-14 A 100% 100% 0.00 A3410 Manufacturing /Procurement and Delivery of the Material 150.00 29-Apr-14 27-Oct-14 24-Jun-14 A 27-Oct-14 20.00 86.67% 0% 0.00 HVAC 284.00 26-Mar-14 22-Jul-15 02-Feb-14 A 19-Apr-15 96.00 0% 0% 0.00 FAHU 167.00 23-Apr-14 14-Dec-14 03-Mar-14 A 15-Dec-14 5.00 0% 0% 0.00 A3500 Material Submittal 14.00 23-Apr-14 08-May-14 03-Mar-14 A 20-May-14 A 100% 100% 0.00 A3510 Material Approval 14.00 10-May-14 25-May-14 04-Mar-14 A 10-Jun-14 A 100% 100% 0.00 A3520 Issue of PO to Supplier 7.00 26-May-14 03-Jun-14 11-Jun-14 A 22-Jun-14 A 100% 100% 0.00 A3530 Manufacturing /Procurement and Delivery of the Material 160.00 04-Jun-14 14-Dec-14 23-Jun-14 A 15-Dec-14 5.00 62.5% 61.88% 0.00 FCU 125.00 26-Mar-14 21-Aug-14 09-Feb-14 A 21-Aug-14 A 0% 0% 0.00 A3820 Material Submittal 14.00 26-Mar-14 10-Apr-14 09-Feb-14 A 03-Jul-14 A 100% 100% 0.00 Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Material Submittal Material Approval Issue of PO to Supplier Manufacturing /Procurement and Delivery of the Material Material Submittal Material Approval Issue of PO to Supplier Manufacturing /Procurement and Delivery of the Material Material Submittal Material Approval Issue of PO to Supplier Manufacturing /Procurement and Delivery of the Material Material Submittal Material Approval Issue of PO to Supplier Manufacturing /Procurement and Delivery Material Submittal Material Approval Issue of PO to Supplier Manufacturing /Procurement and Delivery of the Material Material Submittal Material Approval Issue of PO to Supplier Manufacturing /Procurement and Delivery of the Material Material Submittal Material Approval Issue of PO to Supplier Manufacturing /Procurement and Delivery of the Material Material Submittal DAMAC Gulf Properties L.L.C DAMAC Heights at Dubai Marina Data Date : 30-Sep-14 Page : 3 of 58 Printed On : 16-Oct-14 Baseline Actual Work Remaining Work Critical Remaining Work Baseline Milestone Curernt Milestone Project Progress Update as of 30-Sep-2014 Taregt Completion Programme - Rev 03 Date Revision Chec... Appr... 20-Aug-14 Target Completion Programme - Rev 03 (Baseline) 30-Sep-14 Schedule Update - September-14 (Update) SK
  • 48. Activity ID Activity Name Original Duration Planned Start Planned Finish Actual/Forecast Start Actual/Forecast Finish Total Float Planned % Complete Actual % Complete SPI 2014 2015 A3830 Material Approval 14.00 12-Apr-14 27-Apr-14 10-Feb-14 A 23-Jul-14 A 100% 100% 0.00 A3840 Issue of PO to Supplier 7.00 28-Apr-14 05-May-14 24-Jul-14 A 31-Jul-14 A 100% 100% 0.00 A3850 Manufacturing /Procurement and Delivery of the Material 90.00 06-May-14 21-Aug-14 01-Aug-14 A 21-Aug-14 A 100% 100% 0.00 Fans ( Pressurisation , Parking Extract Etc ) 195.00 29-May-14 19-Jan-15 10-Mar-14 A 09-Dec-14 34.00 0% 0% 0.00 A3460 Material Submittal 14.00 29-May-14 14-Jun-14 10-Mar-14 A 09-Jun-14 A 100% 100% 0.00 A3470 Material Approval 14.00 15-Jun-14 30-Jun-14 11-Mar-14 A 01-Jul-14 A 100% 100% 0.00 A3480 Issue of PO to Supplier 7.00 01-Jul-14 08-Jul-14 02-Jul-14 A 22-Jul-14 A 100% 100% 0.00 A3490 Manufacturing /Procurement and Delivery of the Material 160.00 09-Jul-14 19-Jan-15 23-Jul-14 A 09-Dec-14 34.00 43.75% 65% 0.00 Chilled Water Pumps 195.00 29-May-14 19-Jan-15 05-Mar-14 A 18-Mar-15 -50.00 0% 0% 0.00 A3540 Material Submittal 14.00 29-May-14 14-Jun-14 05-Mar-14 A 03-Jul-14 A 100% 100% 0.00 A3550 Material Approval 14.00 15-Jun-14 30-Jun-14 06-Mar-14 A 19-Jul-14 A 100% 100% 0.00 A3560 Issue of PO to Supplier 7.00 01-Jul-14 08-Jul-14 20-Jul-14 A 24-Aug-14 A 100% 100% 0.00 A3570 Manufacturing /Procurement and Delivery of the Material 160.00 09-Jul-14 19-Jan-15 25-Aug-14 A 18-Mar-15 -50.00 43.75% 12.5% 0.00 Cooling Tower 257.00 03-Dec-14 22-Jul-15 25-May-14 A 19-Apr-15 96.00 0% 0% 0.00 A3580 Material Submittal 14.00 03-Dec-14 18-Dec-14 25-May-14 A 12-Aug-14 A 0% 100% 0.00 A3590 Material Approval 14.00 20-Dec-14 05-Jan-15 26-May-14 A 13-Aug-14 A 0% 100% 0.00 A3600 Issue of PO to Supplier 7.00 06-Jan-15 13-Jan-15 01-Oct-14 11-Oct-14 96.00 0% 0% 0.00 A3610 Manufacturing /Procurement and Delivery of the Material 160.00 14-Jan-15 22-Jul-15 12-Oct-14 19-Apr-15 96.00 0% 0% 0.00 Chiller 215.00 22-May-14 05-Feb-15 08-Mar-14 A 15-Mar-15 4.00 0% 0% 0.00 A3620 Material Submittal 14.00 22-May-14 08-Jun-14 08-Mar-14 A 09-Jun-14 A 100% 100% 0.00 A3630 Material Approval 14.00 09-Jun-14 24-Jun-14 09-Mar-14 A 19-Jun-14 A 100% 100% 0.00 A3640 Issue of PO to Supplier 7.00 25-Jun-14 02-Jul-14 21-Jun-14 A 22-Jun-14 A 100% 100% 0.00 A3650 Manufacturing /Procurement and Delivery of the Material 180.00 03-Jul-14 05-Feb-15 24-Jun-14 A 15-Mar-15 4.00 41.67% 23.89% 0.00 Heat Exchanger 195.00 30-Apr-14 21-Dec-14 02-Feb-14 A 19-Nov-14 36.00 0% 0% 0.00 A3660 Material Submittal 14.00 30-Apr-14 15-May-14 02-Feb-14 A 13-May-14 A 100% 100% 0.00 A3670 Material Approval 14.00 17-May-14 02-Jun-14 03-Feb-14 A 01-Jun-14 A 100% 100% 0.00 A3680 Issue of PO to Supplier 7.00 03-Jun-14 10-Jun-14 02-Jun-14 A 22-Jul-14 A 100% 100% 0.00 A3690 Manufacturing /Procurement and Delivery of the Material 160.00 11-Jun-14 21-Dec-14 23-Jul-14 A 19-Nov-14 36.00 58.75% 75% 0.00 Fire Fighting 215.00 22-May-14 03-Jun-15 01-May-14 A 15-Jun-15 45.00 0% 0% 0.00 Fire Pumps 187.00 22-May-14 05-Feb-15 01-May-14 A 12-May-15 -43.00 0% 0% 0.00 A3700 Material Submittal 14.00 22-May-14 08-Jun-14 01-May-14 A 18-May-14 A 100% 100% 0.00 A3710 Material Approval 14.00 09-Jun-14 24-Jun-14 19-May-14 A 05-Jun-14 A 100% 100% 0.00 A3720 Issue of PO to Supplier 7.00 25-Jun-14 02-Jul-14 01-Oct-14 11-Oct-14 -43.00 100% 0% 0.00 A3730 Manufacturing /Procurement and Delivery of the Material 180.00 03-Jul-14 05-Feb-15 12-Oct-14 12-May-15 -43.00 41.67% 0% 0.00 FM200 215.00 20-Sep-14 03-Jun-15 01-Oct-14 15-Jun-15 45.00 0% 0% 0.00 A4020 Material Submittal 14.00 20-Sep-14 07-Oct-14 01-Oct-14 19-Oct-14 45.00 71.43% 0% 0.00 A4030 Material Approval 14.00 08-Oct-14 23-Oct-14 20-Oct-14 05-Nov-14 45.00 0% 0% 0.00 A4040 Issue of PO to Supplier 7.00 26-Oct-14 02-Nov-14 06-Nov-14 13-Nov-14 45.00 0% 0% 0.00 A4050 Manufacturing /Procurement and Delivery of the Material 180.00 03-Nov-14 03-Jun-15 15-Nov-14 15-Jun-15 45.00 0% 0% 0.00 Plumbing 319.00 14-Sep-14 18-Mar-15 14-Jan-14 A 03-Mar-15 96.00 0% 0% 0.00 Sump Pump 192.00 14-Sep-14 18-Mar-15 29-Jun-14 A 03-Mar-15 96.00 0% 0% 0.00 A3780 Material Submittal 14.00 14-Sep-14 29-Sep-14 29-Jun-14 A 04-Aug-14 A 100% 100% 0.00 A3790 Material Approval 14.00 30-Sep-14 18-Oct-14 30-Jun-14 A 14-Aug-14 A 7.14% 100% 0.00 A3800 Issue of PO to Supplier 7.00 19-Oct-14 27-Oct-14 01-Oct-14 11-Oct-14 96.00 0% 0% 0.00 A3810 Manufacturing /Procurement and Delivery of the Material 120.00 28-Oct-14 18-Mar-15 12-Oct-14 03-Mar-15 96.00 0% 0% 0.00 Water Heat er 155.00 14-Sep-14 18-Mar-15 14-Jan-14 A 31-May-14 A 0% 0% 0.00 A3860 Material Submittal 14.00 14-Sep-14 29-Sep-14 14-Jan-14 A 16-Apr-14 A 100% 100% 0.00 A3880 Issue of PO to Supplier 7.00 19-Oct-14 27-Oct-14 04-May-14 A 14-May-14 A 0% 100% 0.00 Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Material Approval Issue of PO to Supplier Manufacturing /Procurement and Delivery of the Material Material Submittal Material Approval Issue of PO to Supplier Manufacturing /Procurement and Delivery of the Material Material Submittal Material Approval Issue of PO to Supplier Manufacturing /Procurement and Delivery of the Material Material Submittal Material Approval Issue of PO to Supplier Manufacturing /Procurement and Delivery of the Material Material Submittal Material Approval Issue of PO to Supplier Manufacturing /Procurement and Delivery of the Material Material Submittal Material Approval Issue of PO to Supplier Manufacturing /Procurement and Delivery of the Material Material Submittal Material Approval Issue of PO to Supplier Manufacturing /Procurement and Delivery of the Material Material Submittal Material Approval Issue of PO to Supplier Manufacturing /Procurement and Delivery of the Material Material Submittal Material Approval Issue of PO to Supplier Manufacturing /Procurement and Delivery of the Material Material Submittal Issue of PO to Supplier DAMAC Gulf Properties L.L.C DAMAC Heights at Dubai Marina Data Date : 30-Sep-14 Page : 4 of 58 Printed On : 16-Oct-14 Baseline Actual Work Remaining Work Critical Remaining Work Baseline Milestone Curernt Milestone Project Progress Update as of 30-Sep-2014 Taregt Completion Programme - Rev 03 Date Revision Chec... Appr... 20-Aug-14 Target Completion Programme - Rev 03 (Baseline) 30-Sep-14 Schedule Update - September-14 (Update) SK
  • 49. Activity ID Activity Name Original Duration Planned Start Planned Finish Actual/Forecast Start Actual/Forecast Finish Total Float Planned % Complete Actual % Complete SPI 2014 2015 A3870 Material Approval 14.00 30-Sep-14 18-Oct-14 15-May-14 A 20-May-14 A 7.14% 100% 0.00 A3890 Manufacturing /Procurement and Delivery of the Material 120.00 28-Oct-14 18-Mar-15 21-May-14 A 31-May-14 A 0% 100% 0.00 Booster Pump 192.00 14-Sep-14 18-Mar-15 03-Jun-14 A 03-Mar-15 96.00 0% 0% 0.00 A3900 Material Submittal 14.00 14-Sep-14 29-Sep-14 03-Jun-14 A 29-Jun-14 A 100% 100% 0.00 A3910 Material Approval 14.00 30-Sep-14 18-Oct-14 04-Jun-14 A 08-Jul-14 A 7.14% 100% 0.00 A3920 Issue of PO to Supplier 7.00 19-Oct-14 27-Oct-14 01-Oct-14 11-Oct-14 96.00 0% 0% 0.00 A3930 Manufacturing /Procurement and Delivery of the Material 120.00 28-Oct-14 18-Mar-15 12-Oct-14 03-Mar-15 96.00 0% 0% 0.00 Transfer Pump 192.00 14-Sep-14 18-Mar-15 03-Jun-14 A 03-Mar-15 96.00 0% 0% 0.00 A3940 Material Submittal 14.00 14-Sep-14 29-Sep-14 03-Jun-14 A 29-Jun-14 A 100% 100% 0.00 A3950 Material Approval 14.00 30-Sep-14 18-Oct-14 04-Jun-14 A 08-Jul-14 A 7.14% 100% 0.00 A3960 Issue of PO to Supplier 7.00 19-Oct-14 27-Oct-14 01-Oct-14 11-Oct-14 96.00 0% 0% 0.00 A3970 Manufacturing /Procurement and Delivery of the Material 120.00 28-Oct-14 18-Mar-15 12-Oct-14 03-Mar-15 96.00 0% 0% 0.00 Sewage Pump 192.00 14-Sep-14 18-Mar-15 29-Jun-14 A 03-Mar-15 96.00 0% 0% 0.00 A3980 Material Submittal 14.00 14-Sep-14 29-Sep-14 29-Jun-14 A 04-Aug-14 A 100% 100% 0.00 A3990 Material Approval 14.00 30-Sep-14 18-Oct-14 30-Jun-14 A 14-Aug-14 A 7.14% 100% 0.00 A4000 Issue of PO to Supplier 7.00 19-Oct-14 27-Oct-14 01-Oct-14 11-Oct-14 96.00 0% 0% 0.00 A4010 Manufacturing /Procurement and Delivery of the Material 120.00 28-Oct-14 18-Mar-15 12-Oct-14 03-Mar-15 96.00 0% 0% 0.00 DOMESTIC SUBCONTRACTORS 1589.00 24-Feb-14 22-Mar-15 19-Jun-11 A 24-Oct-15 186.00 0% 0% 0.00 Prime Cost 363.00 01-Apr-14 28-Sep-15 24-Feb-14 A 28-Sep-15 65.00 0% 0% 0.00 SUB-STRUCTURE 938.00 24-Feb-14 24-Feb-14 22-Jun-11 A 20-Sep-13 A 0% 0% 0.00 SUPER STRUCTURE 1633.00 24-Feb-14 13-Jul-15 11-Apr-13 A 02-Feb-16 A 0% 0% 0.00 MEP 1835.00 24-Feb-14 07-Dec-15 24-Feb-14 A 24-Feb-14 A 0% 0% 0.00 CONSTRUCTION 1603.00 24-Feb-14 30-Apr-16 26-Jun-11 A 27-Aug-16 -88.00 25.09% 22.48% 0.90 STRUCTURAL , ARCHITECTURAL , MEP 1530.00 24-Feb-14 30-Apr-16 26-Jun-11 A 31-May-16 -15.00 29.36% 28.06% 0.96 FOUNDATION WORKS 1363.00 24-Feb-14 11-Oct-15 26-Jun-11 A 16-Nov-15 -4.00 75.13% 71.94% 0.96 BASEMENT & PODIUM 1455.00 24-Feb-14 30-Apr-16 31-May-13 A 23-May-16 -8.00 48.62% 48.59% 1.00 TOWER 696.00 24-Feb-14 06-Apr-16 10-Feb-14 A 31-May-16 -45.00 24.04% 22.56% 0.94 LEVELS 06 - 29 577.00 24-Feb-14 14-Nov-15 10-Feb-14 A 12-Jan-16 -50.00 68.5% 64.97% 0.95 LEVEL 06 468.00 24-Feb-14 21-May-15 10-Feb-14 A 02-Sep-15 -72.00 76.72% 72.35% 0.94 STRUCTURAL - LEVEL 6 20.00 24-Feb-14 16-Mar-14 10-Feb-14 A 09-Mar-14 A 100% 100% 1.00 DHCWA07100 Core Wal - Level 06 6.00 24-Feb-14 24-Feb-14 15-Feb-14 A 20-Feb-14 A 100% 100% 1.00 DHSLA06100 Construction of Horizontals - L06 4.00 10-Mar-14 11-Mar-14 10-Feb-14 A 04-Mar-14 A 100% 100% 1.00 DHCWA07110 Construction of Verticals - L06 3.00 13-Mar-14 16-Mar-14 06-Mar-14 A 09-Mar-14 A 100% 100% 1.00 STAIRCASES 4.00 25-May-14 29-May-14 08-May-14 A 18-May-14 A 0% 0% 0.00 DHSLA06102 Stair # 2 4.00 25-May-14 29-May-14 08-May-14 A 13-May-14 A 100% 100% 0.00 DHSLA06104 Stair # 1 4.00 25-May-14 29-May-14 13-May-14 A 18-May-14 A 100% 100% 0.00 FINISHES - LEVEL 06 246.00 12-Apr-14 21-May-15 24-Feb-14 A 14-Jul-15 -31.00 40.01% 18.14% 0.45 Dry area 230.00 06-May-14 02-May-15 28-Apr-14 A 25-Jun-15 -43.00 30.8% 15.86% 0.51 DHFSH06100 Block Work in Dry Area 6.00 06-May-14 12-May-14 28-Apr-14 A 19-May-14 A 100% 100% 1.00 DHFSH06120 Marking,Cutting & Chasing - Dry Area 4.00 13-May-14 17-May-14 15-May-14 A 03-Jun-14 A 100% 100% 1.00 DHFSH06130 Sub frame Fixing/Plaster Preparation - Dry Area 4.00 08-Jun-14 12-Jun-14 21-May-14 A 07-Jun-14 A 100% 100% 1.00 DHFSH06160 Plaster in Dry Area 8.00 12-Jun-14 22-Jun-14 25-May-14 A 18-Jun-14 A 100% 100% 1.00 DHFSH06190 Dry Area Floor Screed 7.00 22-Jun-14 30-Jun-14 01-Sep-14 A 01-Sep-14 A 100% 100% 0.00 DHFSH06230 Dry Area Painting - Primer 4.00 30-Jun-14 05-Jul-14 01-Sep-14 A 01-Oct-14 -8.00 100% 80% 0.00 DHFSH06260 Dry Area Painting - Stucco 6.00 05-Jul-14 12-Jul-14 06-Sep-14 A 06-Oct-14 48.00 100% 60% 0.00 DHFSH06290 Dry Area False Ceiling Suspension 6.00 23-Aug-14 30-Aug-14 02-Sep-14 A 09-Oct-14 -8.00 100% 15% 0.15 DHFSH06350 Dry Area False Ceiling Tiling / Boarding 5.00 17-Sep-14 23-Sep-14 14-Oct-14 19-Oct-14 37.00 100% 0% 0.00 DHFSH06400 Dry Area Painting - 1st Coat 5.00 23-Sep-14 29-Sep-14 20-Oct-14 26-Oct-14 37.00 100% 0% 0.00 DHFSH06450 Dry Area Flooring 5.00 12-Oct-14 18-Oct-14 02-Nov-14 06-Nov-14 32.00 0% 0% 0.00 Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Material Approval Manufacturing /Procurement and Delivery of the Material Material Submittal Material Approval Issue of PO to Supplier Manufacturing /Procurement and Delivery of the Material Material Submittal Material Approval Issue of PO to Supplier Manufacturing /Procurement and Delivery of the Material Material Submittal Material Approval Issue of PO to Supplier Manufacturing /Procurement and Delivery of the Material Construction of Horizontals - L06 Construction of Verticals - L06 Stair # 2 Stair # 1 Block Work in Dry Area Marking,Cutting & Chasing - Dry Area Sub frame Fixing/Plaster Preparation - Dry Area Plaster in Dry Area Dry Area Floor Screed Dry Area Painting - Primer Dry Area Painting - Stucco Dry Area False Ceiling Suspension Dry Area False Ceiling Tiling / Boarding Dry Area Painting - 1st Coat Dry Area Flooring DAMAC Gulf Properties L.L.C DAMAC Heights at Dubai Marina Data Date : 30-Sep-14 Page : 5 of 58 Printed On : 16-Oct-14 Baseline Actual Work Remaining Work Critical Remaining Work Baseline Milestone Curernt Milestone Project Progress Update as of 30-Sep-2014 Taregt Completion Programme - Rev 03 Date Revision Chec... Appr... 20-Aug-14 Target Completion Programme - Rev 03 (Baseline) 30-Sep-14 Schedule Update - September-14 (Update) SK
  • 50. Activity ID Activity Name Original Duration Planned Start Planned Finish Actual/Forecast Start Actual/Forecast Finish Total Float Planned % Complete Actual % Complete SPI 2014 2015 DHFSH06430 Installation of Timber Doors & Ironmongery 5.00 22-Mar-15 26-Mar-15 20-May-15 25-May-15 -50.00 0% 0% 0.00 DHFSH06802 Installation of Wardrobe 12.00 22-Mar-15 04-Apr-15 20-May-15 02-Jun-15 -50.00 0% 0% 0.00 DHFSH06500 Paint Final Coat 6.00 26-Apr-15 02-May-15 20-Jun-15 25-Jun-15 -43.00 0% 0% 0.00 Wet area 204.00 13-May-14 04-Apr-15 24-Feb-14 A 02-Jun-15 -45.00 43.27% 24.17% 0.56 DHFSH06220 Wet Area Floor Screed 4.00 29-Sep-14 06-Oct-14 24-Feb-14 A 24-Feb-14 A 28.13% 100% 0.00 DHFSH06110 Block Work in Wet Area 6.00 13-May-14 19-May-14 28-Apr-14 A 19-May-14 A 100% 100% 0.00 DHFSH06140 Marking,Cutting & Chasing - Wet Area 4.00 20-May-14 24-May-14 15-May-14 A 03-Jun-14 A 100% 100% 1.00 DHFSH06150 Sub frame Fixing/Plaster Preparation - Wet Area 4.00 08-Jun-14 12-Jun-14 21-May-14 A 07-Jun-14 A 100% 100% 1.00 DHFSH06170 Plaster in Wet Area 4.00 12-Jun-14 17-Jun-14 25-May-14 A 18-Jun-14 A 100% 100% 1.00 DHFSH06180 Wet Area Wall Tiling 6.00 23-Aug-14 30-Aug-14 02-Sep-14 A 02-Oct-14 -23.00 100% 60% 0.60 DHFSH06300 Wet Area False Ceiling Suspension 5.00 01-Sep-14 07-Sep-14 11-Oct-14 15-Oct-14 7.00 100% 0% 0.00 DHFSH06370 Wet Area False Ceiling Tiling/Boarding 6.00 17-Sep-14 24-Sep-14 14-Oct-14 20-Oct-14 15.00 100% 0% 0.00 DHFSH06210 Wet Area Waterproofing 4.00 24-Sep-14 29-Sep-14 16-Sep-14 A 26-Oct-14 15.00 100% 10% 0.10 DHFSH06250 Wet Area Floor Tiling 5.00 06-Oct-14 12-Oct-14 27-Oct-14 01-Nov-14 15.00 0% 0% 0.00 DHFSH06460 Cabinet Carcass 5.00 18-Oct-14 22-Oct-14 02-Nov-14 06-Nov-14 15.00 0% 0% 0.00 DHFSH06420 Installation of Shower Enclosure 4.00 28-Mar-15 31-Mar-15 26-May-15 30-May-15 -42.00 0% 0% 0.00 DHFSH06390 Installation of Vanity Counters & Tops 5.00 28-Mar-15 01-Apr-15 26-May-15 31-May-15 -50.00 0% 0% 0.00 DHFSH06800 Installation of Kitchen Cabinet 12.00 22-Mar-15 04-Apr-15 20-May-15 02-Jun-15 -50.00 0% 0% 0.00 Corridor/ Lift Lobby 44.00 30-Jun-14 10-Mar-15 01-Sep-14 A 24-Nov-14 89.00 66.67% 0% 0.00 DHFSH06240 Corridor/Lift Lobby Floor Screed 4.00 30-Jun-14 05-Jul-14 01-Sep-14 A 01-Sep-14 A 100% 100% 0.00 DHFSH06270 Lift Lobby Painting - Primer & Stucco 6.00 05-Jul-14 12-Jul-14 01-Sep-14 A 02-Oct-14 13.00 100% 75% 0.00 DHFSH06310 Lift Lobby False Ceiling Suspension 6.00 03-Sep-14 10-Sep-14 13-Oct-14 19-Oct-14 7.00 100% 0% 0.00 DHFSH06360 Lift Lobby False Ceiling Tiling / Boarding 5.00 17-Sep-14 23-Sep-14 20-Oct-14 26-Oct-14 93.00 100% 0% 0.00 DHFSH06410 Lift Lobby Painting - 1st Coat 6.00 23-Sep-14 30-Sep-14 27-Oct-14 02-Nov-14 93.00 100% 0% 0.00 DHFSH06470 Lift Lobby Flooring 6.00 18-Oct-14 26-Oct-14 08-Nov-14 13-Nov-14 89.00 0% 0% 0.00 DHFSH06490 Utility Rooms- Epoxy Flooring 6.00 26-Oct-14 02-Nov-14 15-Nov-14 20-Nov-14 89.00 0% 0% 0.00 DHFSH06440 Installation of Steel Doors & Windows 3.00 08-Mar-15 10-Mar-15 22-Nov-14 24-Nov-14 89.00 0% 0% 0.00 Staircase 51.00 22-Jun-14 18-Mar-15 01-Oct-14 03-Dec-14 91.00 45.08% 0% 0.00 DHFSH06200 Staircase Plastering 4.00 22-Jun-14 26-Jun-14 01-Oct-14 07-Oct-14 27.00 100% 0% 0.00 DHFSH06280 Staircase Painting - Primer & Stucco 6.00 12-Jul-14 19-Jul-14 08-Oct-14 14-Oct-14 119.00 100% 0% 0.00 DHFSH06320 Staircase Handrail Fixing 3.00 04-Dec-14 08-Dec-14 15-Oct-14 18-Oct-14 119.00 0% 0% 0.00 DHFSH06330 Staircase Painting 1st Coat 3.00 08-Dec-14 11-Dec-14 27-Oct-14 29-Oct-14 113.00 0% 0% 0.00 DHFSH06340 Staircase Final Painting 5.00 11-Mar-15 16-Mar-15 25-Nov-14 30-Nov-14 91.00 0% 0% 0.00 DHFSH06380 Staircase Epoxy Flooring 2.00 17-Mar-15 18-Mar-15 01-Dec-14 03-Dec-14 91.00 0% 0% 0.00 General 246.00 12-Apr-14 21-May-15 03-Apr-14 A 14-Jul-15 -43.00 0% 0% 0.00 DHSTR06000 Access from Structure 0.00 12-Apr-14 03-Apr-14 A 100% 100% 0.00 DHFSH06510 Snagging & De-Snagging 16.00 03-May-15 21-May-15 27-Jun-15 14-Jul-15 -43.00 0% 0% 0.00 Show Flats 1 & 2 116.00 12-Jul-14 29-Nov-14 01-Oct-14 18-Feb-15 93.00 0% 0% 0.00 DHFSH06511 Finishes & MEP Works - Flat 1 (Workmanship) 116.00 12-Jul-14 29-Nov-14 01-Oct-14 18-Feb-15 93.00 58.62% 0% 0.00 DHFSH06512 Finishes & MEP Works - Flat 2 (Workmanship) 116.00 12-Jul-14 29-Nov-14 01-Oct-14 18-Feb-15 93.00 58.62% 0% 0.00 MEP - LEVEL 06 465.00 08-Mar-14 25-Apr-15 10-Feb-14 A 02-Sep-15 -106.00 70.98% 70.98% 1.00 DHMEP06000 Embeded Conduits & Boxex - Concrete Works 4.00 08-Mar-14 11-Mar-14 10-Feb-14 A 04-Mar-14 A 100% 100% 0.00 DHMEP06100 H/L Chilled Water Piping,Drainage,Water ,Fire fighting Piping ,Du1c8t.i0n0g, C15a-bAlipnrg-1 ,4 Wiring et0c5-May-14 03-Apr-14 A 29-Apr-14 A 100% 100% 1.00 DHMEP06130 Cable Trays & Cable Trunking 6.00 13-May-14 19-May-14 03-Apr-14 A 29-Apr-14 A 100% 100% 0.00 DHMEP06160 Pressure Testing of Pipes 12.00 23-Aug-14 04-Sep-14 28-Apr-14 A 17-May-14 A 100% 100% 0.00 DHMEP06120 Embeded Condiuts,Boxes ,Sleeves and Pix Pipes in Walls 6.00 25-May-14 01-Jun-14 20-May-14 A 05-Jun-14 A 100% 100% 1.00 DHMEP06110 MEP Works in Risers& Clearance 5.00 12-Jul-14 16-Jul-14 05-Apr-14 A 01-Oct-14 -33.00 100% 78% 0.00 Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Installation of Timber Doors & Ironmongery Installation of Wardrobe Paint Final Coat Wet Area Floor Screed Block Work in Wet Area Marking,Cutting & Chasing - Wet Area Sub frame Fixing/Plaster Preparation - Wet Area Plaster in Wet Area Wet Area Wall Tiling Wet Area False Ceiling Suspension Wet Area False Ceiling Tiling/Boarding Wet Area Waterproofing Wet Area Floor Tiling Cabinet Carcass Installation of Shower Enclosure Installation of Vanity Counters & Tops Installation of Kitchen Cabinet Corridor/Lift Lobby Floor Screed Lift Lobby Painting - Primer & Stucco Lift Lobby False Ceiling Suspension Lift Lobby False Ceiling Tiling / Boarding Lift Lobby Painting - 1st Coat Lift Lobby Flooring Utility Rooms- Epoxy Flooring Installation of Steel Doors & Windows Staircase Plastering Staircase Painting - Primer & Stucco Staircase Handrail Fixing Staircase Painting 1st Coat Staircase Final Painting Staircase Epoxy Flooring Access from Structure Snagging & De-Snagging Finishes & MEP Works - Flat 1 (Workmanship) Finishes & MEP Works - Flat 2 (Workmanship) Embeded Conduits & Boxex - Concrete Works H/L Chilled Water Piping,Drainage,Water ,Fire fighting Piping ,Ducting, Cabling , Wiring etc Cable Trays & Cable Trunking Pressure Testing of Pipes Embeded Condiuts,Boxes ,Sleeves and Pix Pipes in Walls MEP Works in Risers& Clearance DAMAC Gulf Properties L.L.C DAMAC Heights at Dubai Marina Data Date : 30-Sep-14 Page : 6 of 58 Printed On : 16-Oct-14 Baseline Actual Work Remaining Work Critical Remaining Work Baseline Milestone Curernt Milestone Project Progress Update as of 30-Sep-2014 Taregt Completion Programme - Rev 03 Date Revision Chec... Appr... 20-Aug-14 Target Completion Programme - Rev 03 (Baseline) 30-Sep-14 Schedule Update - September-14 (Update) SK