Diese Präsentation wurde erfolgreich gemeldet.
Die SlideShare-Präsentation wird heruntergeladen. ×

Watershed planning in texas ling

Anzeige
Anzeige
Anzeige
Anzeige
Anzeige
Anzeige
Anzeige
Anzeige
Anzeige
Anzeige
Anzeige
Anzeige
Wird geladen in …3
×

Hier ansehen

1 von 12 Anzeige

Weitere Verwandte Inhalte

Ähnlich wie Watershed planning in texas ling (20)

Weitere von Soil and Water Conservation Society (20)

Anzeige

Aktuellste (20)

Watershed planning in texas ling

  1. 1. Ward Ling Texas A&M AgriLife Extension July 25, 2016 WATERSHED PLANNING IN TEXAS: LESSONS LEARNED
  2. 2. AGRILIFE’S WPP EXPERIENCE  Plum Creek WPP – 2009  Geronimo Creek WPP - 2012  Mill Creek WPP – 2016  All received EPA acceptance
  3. 3. PLUM CREEK WPP PROCESS  Pre-emptive Work  Met with local media, County Extension Agents  Identified potential steering committee members  Watershed characterization and set up model  Data collection  WPP Development  public meetings and sought input on development  presented chapters multiple times, presented complete draft plan twice at the end of period  1 ½ year delay to achieve EPA acceptance  Some implementation started during the long interim period between development and acceptance  EPA accepted in June 2009
  4. 4. PLUM CREEK WPP PROCESS  Pre-emptive work – 5 months  WPP development – 25 months  Some implementation started before EPA acceptance  EPA review – 17 months Time = 3.8 yrs Pre-emptive Development EPA Review
  5. 5. GERONIMO CREEK WPP PROCESS  Pre-emptive work  Met with local media, County Extension Agents  Identified potential steering committee members  Watershed characterization and set up model  Data collection (drought started)  WPP Development  Used report model from Plum WPP  presented draft sections to public as developed  Delays – Was put on hold by funding entity over modeling issues  EPA approval September 2012
  6. 6. GERONIMO CREEK WPP PROCESS  Pre-emptive work – 4 months  Development – 16 months  Delays – 16 months  EPA review – 2 weeks Time = 3 yrs Pre-emptive Development Delay EPA Review
  7. 7. MILL CREEK PROCESS  Pre-emptive Work  Met with local media, County Extension Agents  Identified potential steering committee members  Watershed characterization and set up model  Data collection  WPP Development  Public meetings and sought input on development  Ran model and presented outputs  Submitted sections to public as developed  EPA approval delay– took longer due to internal restructuring
  8. 8. MILL CREEK WPP PROCESS  Pre-emptive work – 4 months  Development – 6 months  EPA review – 8 months Time = 1.5 yrs Pre-emptive WPP Development EPA Review
  9. 9. THINGS TO DO  Preemptive work  Set up the model—have it ready—easy to understand  Meet with potential Steering Committee members  Have a document template ready  Value your stakeholders  Communicate with them  Value them - Name them in press releases, websites, and keep them informed  Engage approving agencies starting at day 1
  10. 10. THINGS TO AVOID  Long development phase— no re-running the model or recalibration, please…  Time lags between development and implementation  Long approval or acceptance process  These can all lead to:  Turnover of elected officials and city management  Stakeholder “fatigue”
  11. 11. SUGGESTED POLICY CHANGES  Match Flexibility - allow steering committee member time to count towards match  Refreshments – allowance for meetings—“if you feed them, they will come…”  Travel funds – increase funding to allow federal and state personnel to attend stakeholder meetings  Reduce “us and them” feelings by stakeholders  Would help to keep them engaged in the development and reviewing the document as it is developed
  12. 12. QUESTIONS? Ward Ling Texas A&M AgriLife Extension College Station, Texas wling@tamu.edu

×