SlideShare a Scribd company logo
1 of 27
GENCO HOLDING COMPANY
March 29, 2013
Key Areas
A. Summary
B. GENCO-1: Jamshoro Thermal Power Plant
C. GENCO-2: Guddu Thermal Power Plant
D. GENCO-3: Muzaffargarh Thermal Power Plant
Key Agenda
2Generation Holding Company
Generation Holding Company 3
GHC Summary
INSTALLED CAPACITY
1. GENCO-1 Jamshoro
1. TPS Jamshoro 850 MW
2. GTPS Kotri 174 MW
2. GENCO-2 Guddu
1. TPS Guddu 1,655 MW
3. GENCO-3 Muzaffargarh
1. TPS Muzaffargarh 1,350 MW
2. NGPS Piran Ghaib 195 MW
3. GTPS Faisalabad 244 MW
4. SPS Faisalabad 132 MW
4. GENCO-4 Lakhra
1. Lakhra FBC Power Plant 150 MW
Total GENCOs Installed Capacity 4,750 MW
Generation Holding Company 4
Rehabilitation Program
Major Power Plant in Operations
1. Jamshoro Power Plant (GENCO-1)
2. Guddu Power Plant (GENCO-2)
3. Muzaffargarh Power Plant (GENCO-3)
Generation Holding Company 5
POWER STATION
OPERATING CAPACITY
MW
CAPACITY BEFORE
REHABILITATION
AFTER
REHABILITATION
CAPACITY GAIN
TPS Jamshoro - JPCL 225 710 485
TPS Guddu - CPGCL 980 1475 495
TPS Muzaffargarh - NPGCL 650 1175 525
TOTAL 1855 3360 1505
GHC Summary
Rehabilitation – December 2013
USAID ASSISTANCE PROGRAM
 Under the Empower Pakistan-Energy policy program, USAID
extended its cooperation to recapture the lost capacity of power
units and optimize their performance through rehabilitation and
maintenance of core power plants of GENCOs.
 The performance of units of Thermal Power Station Jamshoro, Unit
No 5,7&8 of TPS Guddu and units of Thermal Power Station
Muzaffargarh was assessed by the USAID Team of experts and a
gain of 315 MW was estimated through an assistance of 51.621
Million US$ which was later increased to 54.231 Million US$
(19.329, 19.124&15.778 MUS$ for GENCO I, II & III respectively)
through a Project Implementation Letter (PIL) signed between the
GENCOS & USAID in April 2012.
 To execute this activity, Fixed Amount Reimbursement Agreement
(FARA) was signed among the generation companies and the USAID
in May 2010.
Generation Holding Company 6
USAID ASSESSED BENEFITS
Expected Benefits
TPS Jamshoro
Unit 1-4
TPS Guddu
Unit 5,7&8
TPS
Muzaffargarh
Unit 1-6
Heat rate (%) 4 3.59 2
Additional energy
Mkwh/year
530 237-272 930
Fuel savings Million
US$/year
11.4 3 17
Availability (%) 4-5 3-4 3-4
Expected Gain MW 95 55 165
Finances Million US$ 19.329 19.124 15.778
SUMMARY LATEST STATUS FARA / PIL (USAID) OF GENCOS
AS ON MARCH 18, 2013
COMPANY
(GENCO)
Amount allocated
under USAID (PIL)
Million US$
Reimbursed to
GENCOS Million US$
Claim submitted for
Reimbursement to
USAID Million US$
Balance Amount
allocated under
USAID (PIL) Million
US$
JPCL (GENCO-I) 19.329
14.893
(77.04%)
1.070
(5.54%)
3.366
(17.41%)
CPGCL (GENCO-II) 19.124
15.513
(81.12%)
-
3.611
(18.88%)
NPGCL (GENCO-III) 15.778
9.795
(62.08%)
2.573
(16.31%)
3.410
(21.61%)
TOTAL 54.231 40.201 3.643 10.387
Generation Holding Company 8
JAMSHORO POWER COMPANY LIMITED (GENCO-I)
PRESENT STATUS
 Procurement process for the purchase of spare parts as per
FARA/PIL has been started and 14.893 MUS$ (77.04%) of total
amount has been reimbursed & claims for 1.070 MUS$ (5.54%) of
the total amount have been lodged with USAID for reimbursement.
 Under rehabilitation of boiler equipment, replacement of Air Pre-
Heater Elements, final super heater tube elements, all burner guns
and some of the sootblowers of Unit No. 1 has been done so far
and the remaining work will be done after the receipt of material at
site. The capacity has been increased from 125 MW to 200 MW at
this Unit.
 HP Heaters & Economizer tubes at Unit No.2,3&4 have been
replaced and the work has been completed successfully. The
capacity has been increased from 100 to 510 MW at these units
(Unit 2, 3&4).
 Completion date of the project is March 31,2014.
Generation Holding Company 9
CENTRALPOWER GENERATION COMPANY LIMITED (GENCO-II)
PRESENT STATUS
• Purchase & Service Orders on April 10 & April 20, 2012
have been placed on to General Electric (GEII - OEM) for
the rehabilitation/up-rating work respectively.
• After opening of L/C (October 30, 2012), USAID was
persuaded and the funds have been delivered to SBP nostro
account amounting Million USD 15.513 (81.12%).
• M/s GE is ready to ship the parts (spares) of
uprate/upgrade of ST-5, Gt-07 and GT-08.
• The schedule of the shutdown of units will be after
reaching the last consignment at site (Guddu), tentative
w.e.f. April, 2013.
• Expected completion date of the project is August, 2013.
Generation Holding Company 10
NORTHERN POWER GENERATION COMPANY LIMITED (GENCO-III)
PRESENT STATUS
 So far 9.795 Million US$ (62.08%) of the allocated
funds have been reimbursed & claims for 2.573 MUS$
(16.31%) of the total amount have been lodged with
USAID for reimbursement.
 Rehabilitation of Unit No.1, 2&3 of TPS Muzaffargarh
has been completed and attained a gain of 220 MW
against the assessed capacity of 70 MW which is due
to further deration of units.
 Replacement of Economizer tubes & Air Preheater
Elements of Unit No. 6 is in progress after that the
same will be replaced at Unit No.5.
 Completion date of the project is June 30, 2013.
Generation Holding Company 11
Generation Holding Company 12
Rehabilitation Program
Jamshoro Power Plant (GENCO-1)
Generation Holding Company 13
GENERATION
GENCO – 1 Jamshoro Power Plant (1/3)
Unit Make DOC Fuel
Installed
capacity
Current
capacity
Design
Efficiency
Current
Efficiency
Unit 1 Japan 1990 RFO 250 MW 200 MW 36.63 % 30.60 %
Unit 2 China 1989 RFO/Gas 200 MW 170 MW 33.89 % 25.20 %
Unit 3 China 1990 RFO/Gas 200 MW 170 MW 33.89 % 25.20 %
Unit 4 China 1991 RFO/Gas 200 MW 170 MW 33.89 % 25.20 %
Total 850 MW 710 MW
Current Status
Generation Holding Company 14
GENERATION
GENCO – 1 Jamshoro Power Plant (2/3)
Unit
Installed
capacity
2007 IDC
NEPRA
Current
capacity
Design
Efficiency
2007 IDC
NEPRA
Current
Efficiency
Unit 1 250 MW 205 MW 125 MW 36.63 % 32.00 % 30.60 %
Unit 2 200 MW 165 MW 170 MW 33.89 % 27.80 % 25.20 %
Unit 3 200 MW 165 MW 170 MW 33.89 % 27.80 % 25.20 %
Unit 4 200 MW 165 MW 170 MW 33.89 % 27.80 % 25.20 %
Total 850 MW 700 MW 710 MW
This is the problem: The differential between tariff and actual generation.
CAPACITY GAIN AFTER REHABILITATION
Unit No.
Capacity Before
Rehabilitation
MW
Capacity After
Rehabilitation
MW
Capacity Gain By
March 2013
MW
Thermal Efficiency %
Before After Gain
1 125 200 75 33.95 35.88 5.70
2
100
170 70 28.47 32.37 13.70
3 170 170 28.47 32.37 13.70
4 170 170 28.47 32.37 13.70
Total 225 710 485 29.84 33.25 11.70
THERMAL POWER STATION JAMSHORO
PARAWISE REPLY OF NEPRA’s QUERRIES JPCL (GENCO-I)
a. Fuel flow meters have already been installed at units of Power Complex Jamshoro.
b. No Gas Chromatograph is installed at TPS Jamshoro. However, the case has been initiated
for the procurement and installation of the Choromatograph and successful bidder has
been recommended for approval by the competent Authority and will be installed soon.
c. Heat rate and initial dependability test of each generating block will be carried out after
calibration of fuel (Gas, Oil) flow meters. The case for calibration of fuel flow meters is
under process with USAID.
d. Gas supply agreement has already been signed with SSGCL on 10Apr 1995, whereas Fuel
oil supply agreement with PSO will be initiated shortly.
e. Power Purchase Agreement with the NTDC has already been signed on 26 November,
2010.
f. Tender for all GENCOs was invited by General Manager (Thermal) office but only a single
bidder participated without furnishing the earnest money and the case couldn’t be
matured. Keeping in view the Ministry of Water and Power (MoW&P) directions for hiring
of independent engineer, USAID was contacted for provision of assistance in this case. The
same will now be conducted by the independent engineer M/s PES as is appointed by the
USAID. Consent of NEPRA has also been taken on the issue.
g. After conducting the heat rate and initial dependable capacity modification in generation
license will be applied and thereafter power purchase agreement will be signed with NTDC.
Generation Holding Company 16
Generation Holding Company 17
Rehabilitation Program
Guddu Power Plant (GENCO-2)
Generation Holding Company 18
GENERATION
GENCO – 2 Guddu Power Plant
Unit Tech. Units DOC Fuel
Installed
capacity
Current
capacity
Block 1 CCGT 11 - 13 1992 - 1994 Gas 415 MW 230 MW
Block 2 CCGT 5 - 10 1985 - 1988 Gas 600 MW 370 MW
Block 3 ST 3 - 4 1980 & 1985 Gas/RFO 420 MW 270 MW
Block 4 ST 1 - 2 1974 Gas 220 MW 110 MW
Total 1,655 MW 980 MW
Current Status: 13 Units
900-920 MW is available at Gas as a fuel.
Generation Holding Company 19
GENERATION
GENCO – 2 Guddu Power Plant
Block
Designed
%
NEPRA
%
Present
%
Expected
%
Current
Capacity
Expected
Capacity
Block-I
(GT-11, 12 & ST-13)
48.20 40.00 36.32 40.00 230 385
Block-II
(ST-5, GT-7 & GT-8)
44.36 36.00 32.69 36.00 370 570
Block-III
(ST-3 and 4)
37.55 30.00 27.24 28.44 270 340
Block-IV
(ST-1&2)
37.50 28.00 25.43 27.33 110 180
980 MW 1475 MW
Post major Outages & Rehabilitation: An expected gain of 495 MW
CAPACITY GAIN AFTER REHABILITATION
Unit No.
Capacity Before
Rehabilitation
MW
Capacity After
Rehabilitation
MW
Capacity Gain By
March 2013
MW
Thermal Efficiency %
Block No Before After Gain
1 60 90 30
IV 23.05 23.05 00
2 50 90 40
3 140 170 30
III 27.26 28.44 4.15
4 130 170 40
5 0 80 80
II
32.71 36.00 9.137 0 100 100
8 80 100 20
6 75 75 00
37.58 37.77 0.509 105 105 00
10 110 110 00
11 80 130 50
I 36.34 40.15 9.5012 80 130 50
13 70 125 55
Total 980 1475 495
THERMAL POWER STATION GUDDU
Note:
1. For modification of Unit No. 1 & 2 by the Russian company, the L/C has been established for carrying out Gas firing
improvement.
2. At present Unit No. 5 is under Shutdown for want of repair of generator rotor at GE works Saudi Arabia. Rotor has reached at Port
at Karachi. The Unit will come back on bar in April, 2013 & take load 35-40 MW.
3. Unit No. 7 is under shutdown for want of new Torque Converter from M/s Voith Germany and is expected to be back on bar by
June 2013 & 90 MW load will be available on this Unit and Total gain at this block will be 125 MW ( ST 5 35 MW + GT 7 90
MW).
4. For Uprate/Upgrade of GE Units 5, 7 & 8, Purchase & Service Order has been placed on M/s GE USA. The job will be completed in
8-10 weeks as per schedule. 5. LOI in favour of M/s MAPNA Iran has been issued to carry out the overhauling job of the Siemens
Units 11, 12 & 13. Service order yet to be issued. The job will be carried out one by one on each Unit in 105 days starting from
mid April, 2013 .
PARAWISE REPLY OF NEPRA’s QUERRIES CPGCL (GENCO-II)
a. Fuel flow meters have already been installed on steam units and gas turbines of Power Complex
Guddu.
b. The tender invited fifth time for the procurement of gas chromatograph that was opened on 19-
02-2013 and is in evaluation process. The same will be installed / commissioned in next 4-6
months. The previously called tenders could not be matured due to bid did not received.
c. Heat rate and initial dependability test of each generating block will be carried out after
calibration of fuel (Gas, Oil) flow meters. The case for calibration of fuel flow meters is under
process with USAID.
d. Fuel Supply Agreement (FSA) with supplier (PSO) and Gas Supply Agreement with Pakistan
Petroleum Limited (PPL) and Sui Northern Gas Pipeline Limited (SNGPL) are in process.
e. Draft Power Purchase Agreement between NTDC and CPGCL has been submitted to NTDC on 05-
10-2012. Articles 1 to 7 of the Agreement have been discussed and remaining articles will be
discussed on 14-03-2013 as meeting date conveyed by the NTDC.
f. Tender for all GENCOs was invited by General Manager (Thermal) office but only a single bidder
participated without furnishing the earnest money and the case couldn’t be matured. Keeping in
view the Ministry of Water and Power (MoW&P) directions for hiring of independent engineer,
USAID was contacted for provision of assistance in this case. The same will now be conducted by
the independent engineer M/s PES as is appointed by the USAID. Consent of NEPRA has also
been taken on the issue. .
g. After conducting the heat rate and initial dependable capacity modification in generation license
will be applied and thereafter power purchase agreement will be signed with NTDC.
Generation Holding Company 21
Generation Holding Company 22
Rehabilitation Program
Muzaffargarh Power Plant (GENCO-3)
Generation Holding Company 23
GENERATION
GENCO – 3 Muzaffargarh Power Plant (1/5)
Unit Make DOC Fuel
Installed
capacity
Current
capacity
Unit 1 Russia 1993 RFO/Gas 210 90
Unit 2 Russia 1994 RFO/Gas 210 160
Unit 3 Russia 1995 RFO/Gas 210 160
Unit 4 China 1997 RFO/Gas 320 160
Unit 5 China 1995 RFO/Gas 210 100
Unit 6 China 1995 RFO/Gas 210 80
Total 1370 MW 750 MW
Current Status
Generation Holding Company 24
GENERATION
GENCO – 3 Muzaffargarh Power Plant (2/5)
Block
Designed
%
NEPRA
%
Present
%
Expected
%
Current
Capacity
Expected
Capacity
Unit 1 36.77 33.00 30.41 32.41 90 165
Unit 2 36.77 33.00 31.97 32.66 160 170
Unit 3 36.77 33.00 31.26 32.12 160 170
Unit 4 36.70 33.00 28.80 34.02 160 210
Unit 5 31.65 29.00 24.55 26.60 100 140
Unit 6 31.65 29.00 25.01 26.55 80 120
750 MW 975 MW
Post major Outages & Rehabilitation
CAPACITY GAIN AFTER REHABILITATION
Unit No.
Capacity Before
Rehabilitation
MW
Capacity After
Rehabilitation
MW
Capacity Gain By
March 2013
MW
Thermal Efficiency %
Before After Gain
1 90 185 80 30.41 32.41 6.57
2 110 185 70 31.97 32.66 2.15
3 110 185 70 31.26 32.12 2.75
4 160 280 100 28.80 34.02 18.12
5 100 170 70 24.55 26.60 8.35
6 80 170 90 25.01 26.55 6.15
Total 650 1175 525 28.66 30.72 7.18
THERMAL POWER STATION MUZAFFARGARH
PARAWISE REPLY OF NEPRA’s QUERRIES NPGCL (GENCO-III)
Generation Holding Company 26
a. Fuel flow meters have already been installed at units of Power Complex Muzaffargarh.
b. No chromatograph meter is installed at TPS Muzaffargarh. Calorimeter is installed by Sui
Northern Gas Pipelines Limited (SNGPL) at their gas Station TPS Muzaffargarh. The monthly
calibration of the Calorimeter is carried out by the joint metering Committee of SNGPL and TPS
Muzaffargarh. Procurement case for chromatograph meter is in process.
c. Heat rate and initial dependability test of each generating block will be carried out after
calibration of fuel (Gas, Oil) flow meters. The case for calibration of fuel flow meters is under
process with USAID.
d. Fuel Oil Supply agreement has been signed between NPGCL and Pakistan State Oil Company
Limited (PSO) on dated 16.09.2009. Request of Gas Supply Agreement between NPGCL (GENCO-
III) and SNGPL has been made several times. SNGPL rejected the request for GSA of even 10
MMCFD with TPS Muzaffargarh due to their system constraints. GSA already exists between
WAPDA and SNGPL to supply 25 MMCFD gas to Gas Turbine Power Station Faisalabad, however,
GSA is not being implemented on part of SNGPL.
e. Power Purchase Agreement was signed in 1999 but expired. The restated PPA is in the process of
finalization and Draft PPA is in the process of finalization with CPPA. The finalization of PPA will be
after Heat Rate/CDC test.
f. Tender for all GENCOs was invited by General Manager (Thermal) office but only a single bidder
participated without furnishing the earnest money and the case couldn’t be matured. Keeping in
view the Ministry of Water and Power (MoW&P) directions for hiring of independent engineer,
USAID was contacted for provision of assistance in this case. The same will now be conducted by
the independent engineer M/s PES as is appointed by the USAID. Consent of NEPRA has also
been taken on the issue.
g. After conducting the heat rate and initial dependable capacity modification in generation license
will be applied and thereafter power purchase agreement will be signed with NTDC.
Generation Holding Company 27
Genco Holding Company Limited
THANKS

More Related Content

What's hot

New base 1053 special 20 july 2017 energy news ilovepdf-compressed
New base 1053 special 20 july 2017 energy news ilovepdf-compressedNew base 1053 special 20 july 2017 energy news ilovepdf-compressed
New base 1053 special 20 july 2017 energy news ilovepdf-compressedKhaled Al Awadi
 
India presentation 2
India presentation 2India presentation 2
India presentation 2UKTI2014
 
16 MW PRAN Power Stations
16 MW PRAN Power Stations16 MW PRAN Power Stations
16 MW PRAN Power StationsSalim Bhuiyan
 
Energy Analysis of Nigeria
Energy Analysis of NigeriaEnergy Analysis of Nigeria
Energy Analysis of NigeriaSatya Sahoo
 
Introduction of taiwan offshore wind business jimmy huang
Introduction of taiwan offshore wind business jimmy huangIntroduction of taiwan offshore wind business jimmy huang
Introduction of taiwan offshore wind business jimmy huangJimmy Huang
 
A summer training report on NTPC
A summer training report on NTPCA summer training report on NTPC
A summer training report on NTPCRanjeet1501
 
New base special 25 february 2014
New base special  25 february 2014New base special  25 february 2014
New base special 25 february 2014Khaled Al Awadi
 
Project management in thermal power plants
Project management in thermal power plantsProject management in thermal power plants
Project management in thermal power plantsPrashant Alekar
 
Industrial training report of NTPC
Industrial training report of NTPC Industrial training report of NTPC
Industrial training report of NTPC Shivam Singh
 
Status of hydro power in india 23.03.10
Status of hydro power in india 23.03.10Status of hydro power in india 23.03.10
Status of hydro power in india 23.03.10Ines Kkumar
 
Solar Energy Assessment Report for 100 kWp of Bengaluru, Karnataka created by...
Solar Energy Assessment Report for 100 kWp of Bengaluru, Karnataka created by...Solar Energy Assessment Report for 100 kWp of Bengaluru, Karnataka created by...
Solar Energy Assessment Report for 100 kWp of Bengaluru, Karnataka created by...Sayanti Sanyal
 
IRJET- Using Thermoelectric Generators to Utilize Heat Generated in Disc Brakes
IRJET- Using Thermoelectric Generators to Utilize Heat Generated in Disc BrakesIRJET- Using Thermoelectric Generators to Utilize Heat Generated in Disc Brakes
IRJET- Using Thermoelectric Generators to Utilize Heat Generated in Disc BrakesIRJET Journal
 
Summer traininig-report ntpc anta content
Summer traininig-report ntpc anta contentSummer traininig-report ntpc anta content
Summer traininig-report ntpc anta contentnishant pareek
 
Presentazione di Gruppo Veronagest
Presentazione di Gruppo VeronagestPresentazione di Gruppo Veronagest
Presentazione di Gruppo VeronagestVeronagest
 
M.Sc thesis Presentation
M.Sc thesis PresentationM.Sc thesis Presentation
M.Sc thesis Presentationubongsimon
 
Ntpc information
Ntpc informationNtpc information
Ntpc informationNTPC
 

What's hot (20)

Jw workshop
Jw workshopJw workshop
Jw workshop
 
New base 1053 special 20 july 2017 energy news ilovepdf-compressed
New base 1053 special 20 july 2017 energy news ilovepdf-compressedNew base 1053 special 20 july 2017 energy news ilovepdf-compressed
New base 1053 special 20 july 2017 energy news ilovepdf-compressed
 
India presentation 2
India presentation 2India presentation 2
India presentation 2
 
16 MW PRAN Power Stations
16 MW PRAN Power Stations16 MW PRAN Power Stations
16 MW PRAN Power Stations
 
Energy Analysis of Nigeria
Energy Analysis of NigeriaEnergy Analysis of Nigeria
Energy Analysis of Nigeria
 
Introduction of taiwan offshore wind business jimmy huang
Introduction of taiwan offshore wind business jimmy huangIntroduction of taiwan offshore wind business jimmy huang
Introduction of taiwan offshore wind business jimmy huang
 
A summer training report on NTPC
A summer training report on NTPCA summer training report on NTPC
A summer training report on NTPC
 
New base special 25 february 2014
New base special  25 february 2014New base special  25 february 2014
New base special 25 february 2014
 
PIC O&M Experience
PIC O&M ExperiencePIC O&M Experience
PIC O&M Experience
 
Project management in thermal power plants
Project management in thermal power plantsProject management in thermal power plants
Project management in thermal power plants
 
Summer training report on
Summer training report onSummer training report on
Summer training report on
 
Industrial training report of NTPC
Industrial training report of NTPC Industrial training report of NTPC
Industrial training report of NTPC
 
Go Solar
Go SolarGo Solar
Go Solar
 
Status of hydro power in india 23.03.10
Status of hydro power in india 23.03.10Status of hydro power in india 23.03.10
Status of hydro power in india 23.03.10
 
Solar Energy Assessment Report for 100 kWp of Bengaluru, Karnataka created by...
Solar Energy Assessment Report for 100 kWp of Bengaluru, Karnataka created by...Solar Energy Assessment Report for 100 kWp of Bengaluru, Karnataka created by...
Solar Energy Assessment Report for 100 kWp of Bengaluru, Karnataka created by...
 
IRJET- Using Thermoelectric Generators to Utilize Heat Generated in Disc Brakes
IRJET- Using Thermoelectric Generators to Utilize Heat Generated in Disc BrakesIRJET- Using Thermoelectric Generators to Utilize Heat Generated in Disc Brakes
IRJET- Using Thermoelectric Generators to Utilize Heat Generated in Disc Brakes
 
Summer traininig-report ntpc anta content
Summer traininig-report ntpc anta contentSummer traininig-report ntpc anta content
Summer traininig-report ntpc anta content
 
Presentazione di Gruppo Veronagest
Presentazione di Gruppo VeronagestPresentazione di Gruppo Veronagest
Presentazione di Gruppo Veronagest
 
M.Sc thesis Presentation
M.Sc thesis PresentationM.Sc thesis Presentation
M.Sc thesis Presentation
 
Ntpc information
Ntpc informationNtpc information
Ntpc information
 

Viewers also liked

Power plant tarrif Stratagies
Power plant tarrif StratagiesPower plant tarrif Stratagies
Power plant tarrif StratagiesIftikhar Ahmed
 
Gencos Rehabilitation 27.03.2013
Gencos Rehabilitation 27.03.2013Gencos Rehabilitation 27.03.2013
Gencos Rehabilitation 27.03.2013SULTAN ZAFAR
 
Project Description
Project Description Project Description
Project Description Ahmed Afzal
 
Power sector of pakistan
Power sector of pakistanPower sector of pakistan
Power sector of pakistanUSMAN TARIQ
 
Pakistan power sector overview issues and recommendations
Pakistan power sector overview issues and recommendations Pakistan power sector overview issues and recommendations
Pakistan power sector overview issues and recommendations abrar younas
 
Analysis of Power Generation Plant at Pakistan Steel Mills
Analysis of Power Generation Plant at Pakistan Steel MillsAnalysis of Power Generation Plant at Pakistan Steel Mills
Analysis of Power Generation Plant at Pakistan Steel MillsDanial Sohail
 
Presentation By N.A. Zuberi
Presentation By N.A. ZuberiPresentation By N.A. Zuberi
Presentation By N.A. ZuberiIEEEP Karachi
 
Energy crises in pakistan butt presentation
Energy crises in pakistan butt presentationEnergy crises in pakistan butt presentation
Energy crises in pakistan butt presentationgoodamazing
 
Power system in pakistan
Power system in pakistan Power system in pakistan
Power system in pakistan rana622987
 
Power Generation In Pakistan
Power Generation In PakistanPower Generation In Pakistan
Power Generation In PakistanImad Baig
 
Power Sector in Pakistan - 2017
Power Sector in Pakistan - 2017Power Sector in Pakistan - 2017
Power Sector in Pakistan - 2017Salman Haider
 

Viewers also liked (11)

Power plant tarrif Stratagies
Power plant tarrif StratagiesPower plant tarrif Stratagies
Power plant tarrif Stratagies
 
Gencos Rehabilitation 27.03.2013
Gencos Rehabilitation 27.03.2013Gencos Rehabilitation 27.03.2013
Gencos Rehabilitation 27.03.2013
 
Project Description
Project Description Project Description
Project Description
 
Power sector of pakistan
Power sector of pakistanPower sector of pakistan
Power sector of pakistan
 
Pakistan power sector overview issues and recommendations
Pakistan power sector overview issues and recommendations Pakistan power sector overview issues and recommendations
Pakistan power sector overview issues and recommendations
 
Analysis of Power Generation Plant at Pakistan Steel Mills
Analysis of Power Generation Plant at Pakistan Steel MillsAnalysis of Power Generation Plant at Pakistan Steel Mills
Analysis of Power Generation Plant at Pakistan Steel Mills
 
Presentation By N.A. Zuberi
Presentation By N.A. ZuberiPresentation By N.A. Zuberi
Presentation By N.A. Zuberi
 
Energy crises in pakistan butt presentation
Energy crises in pakistan butt presentationEnergy crises in pakistan butt presentation
Energy crises in pakistan butt presentation
 
Power system in pakistan
Power system in pakistan Power system in pakistan
Power system in pakistan
 
Power Generation In Pakistan
Power Generation In PakistanPower Generation In Pakistan
Power Generation In Pakistan
 
Power Sector in Pakistan - 2017
Power Sector in Pakistan - 2017Power Sector in Pakistan - 2017
Power Sector in Pakistan - 2017
 

Similar to Gencos rehabilitation 27.03.2013

Dalmia Cement Ariyalur_240314_114438.pdf
Dalmia Cement Ariyalur_240314_114438.pdfDalmia Cement Ariyalur_240314_114438.pdf
Dalmia Cement Ariyalur_240314_114438.pdfBlentBulut5
 
Gasoducto Sur Peruano en Calgary
Gasoducto Sur Peruano en CalgaryGasoducto Sur Peruano en Calgary
Gasoducto Sur Peruano en CalgaryErnesto Linares
 
Erg infrastructure day 2019
Erg infrastructure day 2019Erg infrastructure day 2019
Erg infrastructure day 2019ERG S.p.A.
 
Power industries and solar pv power plant in pakistan
Power industries and solar pv power plant in pakistanPower industries and solar pv power plant in pakistan
Power industries and solar pv power plant in pakistanIBRAR AHMAD
 
New and renewable energy policy and investment in thailand 05-jun-13
New and renewable energy policy and investment in thailand 05-jun-13New and renewable energy policy and investment in thailand 05-jun-13
New and renewable energy policy and investment in thailand 05-jun-13Peerasak C.
 
A summer traning report on ntpc
A summer traning report on ntpcA summer traning report on ntpc
A summer traning report on ntpcRanjeet1501
 
Transmission Summit West 2013
Transmission Summit West 2013Transmission Summit West 2013
Transmission Summit West 2013ScottMadden, Inc.
 
Green Energy From Heat - Themo Electric Generation (TEG)
Green Energy From Heat  - Themo Electric Generation (TEG)Green Energy From Heat  - Themo Electric Generation (TEG)
Green Energy From Heat - Themo Electric Generation (TEG)jamietpe
 
B4 - Maibarara Geothermal Inc., Philippines: Geothermal Start-Up in a Deregul...
B4 - Maibarara Geothermal Inc., Philippines: Geothermal Start-Up in a Deregul...B4 - Maibarara Geothermal Inc., Philippines: Geothermal Start-Up in a Deregul...
B4 - Maibarara Geothermal Inc., Philippines: Geothermal Start-Up in a Deregul...Iceland Geothermal
 
Ntpc KAHALGAON REPORT FILE
Ntpc KAHALGAON REPORT FILENtpc KAHALGAON REPORT FILE
Ntpc KAHALGAON REPORT FILERanjan kumar
 
Design and analysis of an external rotor internal-stator doubly fed induction...
Design and analysis of an external rotor internal-stator doubly fed induction...Design and analysis of an external rotor internal-stator doubly fed induction...
Design and analysis of an external rotor internal-stator doubly fed induction...Mellah Hacene
 
Projectproposalon10mwsolarpvpowerplant 160312085340 (2)
Projectproposalon10mwsolarpvpowerplant 160312085340 (2)Projectproposalon10mwsolarpvpowerplant 160312085340 (2)
Projectproposalon10mwsolarpvpowerplant 160312085340 (2)Muzaffar Ahmad
 
Project Proposal on 10 MW Solar PV Power Plant
Project Proposal on 10 MW Solar PV Power PlantProject Proposal on 10 MW Solar PV Power Plant
Project Proposal on 10 MW Solar PV Power PlantVignesh Sekar
 
RCREEE-enerMENA_pgesco profile-rcree
RCREEE-enerMENA_pgesco profile-rcreeRCREEE-enerMENA_pgesco profile-rcree
RCREEE-enerMENA_pgesco profile-rcreeRCREEE
 
Eng apresentação de resultados v.final
Eng apresentação de resultados v.finalEng apresentação de resultados v.final
Eng apresentação de resultados v.finalersa_ri
 
Earnings release 3 q14_final
Earnings release 3 q14_finalEarnings release 3 q14_final
Earnings release 3 q14_finalCPFL RI
 

Similar to Gencos rehabilitation 27.03.2013 (20)

Dalmia Cement Ariyalur_240314_114438.pdf
Dalmia Cement Ariyalur_240314_114438.pdfDalmia Cement Ariyalur_240314_114438.pdf
Dalmia Cement Ariyalur_240314_114438.pdf
 
Report ntpc auraiya
Report ntpc auraiyaReport ntpc auraiya
Report ntpc auraiya
 
Gasoducto Sur Peruano en Calgary
Gasoducto Sur Peruano en CalgaryGasoducto Sur Peruano en Calgary
Gasoducto Sur Peruano en Calgary
 
Erg infrastructure day 2019
Erg infrastructure day 2019Erg infrastructure day 2019
Erg infrastructure day 2019
 
Power industries and solar pv power plant in pakistan
Power industries and solar pv power plant in pakistanPower industries and solar pv power plant in pakistan
Power industries and solar pv power plant in pakistan
 
New and renewable energy policy and investment in thailand 05-jun-13
New and renewable energy policy and investment in thailand 05-jun-13New and renewable energy policy and investment in thailand 05-jun-13
New and renewable energy policy and investment in thailand 05-jun-13
 
QRM Q-2 2019.pptx
QRM Q-2 2019.pptxQRM Q-2 2019.pptx
QRM Q-2 2019.pptx
 
A summer traning report on ntpc
A summer traning report on ntpcA summer traning report on ntpc
A summer traning report on ntpc
 
Transmission Summit West 2013
Transmission Summit West 2013Transmission Summit West 2013
Transmission Summit West 2013
 
Green Energy From Heat - Themo Electric Generation (TEG)
Green Energy From Heat  - Themo Electric Generation (TEG)Green Energy From Heat  - Themo Electric Generation (TEG)
Green Energy From Heat - Themo Electric Generation (TEG)
 
Allen Report
Allen ReportAllen Report
Allen Report
 
B4 - Maibarara Geothermal Inc., Philippines: Geothermal Start-Up in a Deregul...
B4 - Maibarara Geothermal Inc., Philippines: Geothermal Start-Up in a Deregul...B4 - Maibarara Geothermal Inc., Philippines: Geothermal Start-Up in a Deregul...
B4 - Maibarara Geothermal Inc., Philippines: Geothermal Start-Up in a Deregul...
 
Ntpc KAHALGAON REPORT FILE
Ntpc KAHALGAON REPORT FILENtpc KAHALGAON REPORT FILE
Ntpc KAHALGAON REPORT FILE
 
Design and analysis of an external rotor internal-stator doubly fed induction...
Design and analysis of an external rotor internal-stator doubly fed induction...Design and analysis of an external rotor internal-stator doubly fed induction...
Design and analysis of an external rotor internal-stator doubly fed induction...
 
Sopitsuda thailandssolarfit
Sopitsuda thailandssolarfitSopitsuda thailandssolarfit
Sopitsuda thailandssolarfit
 
Projectproposalon10mwsolarpvpowerplant 160312085340 (2)
Projectproposalon10mwsolarpvpowerplant 160312085340 (2)Projectproposalon10mwsolarpvpowerplant 160312085340 (2)
Projectproposalon10mwsolarpvpowerplant 160312085340 (2)
 
Project Proposal on 10 MW Solar PV Power Plant
Project Proposal on 10 MW Solar PV Power PlantProject Proposal on 10 MW Solar PV Power Plant
Project Proposal on 10 MW Solar PV Power Plant
 
RCREEE-enerMENA_pgesco profile-rcree
RCREEE-enerMENA_pgesco profile-rcreeRCREEE-enerMENA_pgesco profile-rcree
RCREEE-enerMENA_pgesco profile-rcree
 
Eng apresentação de resultados v.final
Eng apresentação de resultados v.finalEng apresentação de resultados v.final
Eng apresentação de resultados v.final
 
Earnings release 3 q14_final
Earnings release 3 q14_finalEarnings release 3 q14_final
Earnings release 3 q14_final
 

Recently uploaded

Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...Call Girls in Nagpur High Profile
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)Suman Mia
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Call Girls in Nagpur High Profile
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 

Recently uploaded (20)

Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 

Gencos rehabilitation 27.03.2013

  • 2. Key Areas A. Summary B. GENCO-1: Jamshoro Thermal Power Plant C. GENCO-2: Guddu Thermal Power Plant D. GENCO-3: Muzaffargarh Thermal Power Plant Key Agenda 2Generation Holding Company
  • 3. Generation Holding Company 3 GHC Summary INSTALLED CAPACITY 1. GENCO-1 Jamshoro 1. TPS Jamshoro 850 MW 2. GTPS Kotri 174 MW 2. GENCO-2 Guddu 1. TPS Guddu 1,655 MW 3. GENCO-3 Muzaffargarh 1. TPS Muzaffargarh 1,350 MW 2. NGPS Piran Ghaib 195 MW 3. GTPS Faisalabad 244 MW 4. SPS Faisalabad 132 MW 4. GENCO-4 Lakhra 1. Lakhra FBC Power Plant 150 MW Total GENCOs Installed Capacity 4,750 MW
  • 4. Generation Holding Company 4 Rehabilitation Program Major Power Plant in Operations 1. Jamshoro Power Plant (GENCO-1) 2. Guddu Power Plant (GENCO-2) 3. Muzaffargarh Power Plant (GENCO-3)
  • 5. Generation Holding Company 5 POWER STATION OPERATING CAPACITY MW CAPACITY BEFORE REHABILITATION AFTER REHABILITATION CAPACITY GAIN TPS Jamshoro - JPCL 225 710 485 TPS Guddu - CPGCL 980 1475 495 TPS Muzaffargarh - NPGCL 650 1175 525 TOTAL 1855 3360 1505 GHC Summary Rehabilitation – December 2013
  • 6. USAID ASSISTANCE PROGRAM  Under the Empower Pakistan-Energy policy program, USAID extended its cooperation to recapture the lost capacity of power units and optimize their performance through rehabilitation and maintenance of core power plants of GENCOs.  The performance of units of Thermal Power Station Jamshoro, Unit No 5,7&8 of TPS Guddu and units of Thermal Power Station Muzaffargarh was assessed by the USAID Team of experts and a gain of 315 MW was estimated through an assistance of 51.621 Million US$ which was later increased to 54.231 Million US$ (19.329, 19.124&15.778 MUS$ for GENCO I, II & III respectively) through a Project Implementation Letter (PIL) signed between the GENCOS & USAID in April 2012.  To execute this activity, Fixed Amount Reimbursement Agreement (FARA) was signed among the generation companies and the USAID in May 2010. Generation Holding Company 6
  • 7. USAID ASSESSED BENEFITS Expected Benefits TPS Jamshoro Unit 1-4 TPS Guddu Unit 5,7&8 TPS Muzaffargarh Unit 1-6 Heat rate (%) 4 3.59 2 Additional energy Mkwh/year 530 237-272 930 Fuel savings Million US$/year 11.4 3 17 Availability (%) 4-5 3-4 3-4 Expected Gain MW 95 55 165 Finances Million US$ 19.329 19.124 15.778
  • 8. SUMMARY LATEST STATUS FARA / PIL (USAID) OF GENCOS AS ON MARCH 18, 2013 COMPANY (GENCO) Amount allocated under USAID (PIL) Million US$ Reimbursed to GENCOS Million US$ Claim submitted for Reimbursement to USAID Million US$ Balance Amount allocated under USAID (PIL) Million US$ JPCL (GENCO-I) 19.329 14.893 (77.04%) 1.070 (5.54%) 3.366 (17.41%) CPGCL (GENCO-II) 19.124 15.513 (81.12%) - 3.611 (18.88%) NPGCL (GENCO-III) 15.778 9.795 (62.08%) 2.573 (16.31%) 3.410 (21.61%) TOTAL 54.231 40.201 3.643 10.387 Generation Holding Company 8
  • 9. JAMSHORO POWER COMPANY LIMITED (GENCO-I) PRESENT STATUS  Procurement process for the purchase of spare parts as per FARA/PIL has been started and 14.893 MUS$ (77.04%) of total amount has been reimbursed & claims for 1.070 MUS$ (5.54%) of the total amount have been lodged with USAID for reimbursement.  Under rehabilitation of boiler equipment, replacement of Air Pre- Heater Elements, final super heater tube elements, all burner guns and some of the sootblowers of Unit No. 1 has been done so far and the remaining work will be done after the receipt of material at site. The capacity has been increased from 125 MW to 200 MW at this Unit.  HP Heaters & Economizer tubes at Unit No.2,3&4 have been replaced and the work has been completed successfully. The capacity has been increased from 100 to 510 MW at these units (Unit 2, 3&4).  Completion date of the project is March 31,2014. Generation Holding Company 9
  • 10. CENTRALPOWER GENERATION COMPANY LIMITED (GENCO-II) PRESENT STATUS • Purchase & Service Orders on April 10 & April 20, 2012 have been placed on to General Electric (GEII - OEM) for the rehabilitation/up-rating work respectively. • After opening of L/C (October 30, 2012), USAID was persuaded and the funds have been delivered to SBP nostro account amounting Million USD 15.513 (81.12%). • M/s GE is ready to ship the parts (spares) of uprate/upgrade of ST-5, Gt-07 and GT-08. • The schedule of the shutdown of units will be after reaching the last consignment at site (Guddu), tentative w.e.f. April, 2013. • Expected completion date of the project is August, 2013. Generation Holding Company 10
  • 11. NORTHERN POWER GENERATION COMPANY LIMITED (GENCO-III) PRESENT STATUS  So far 9.795 Million US$ (62.08%) of the allocated funds have been reimbursed & claims for 2.573 MUS$ (16.31%) of the total amount have been lodged with USAID for reimbursement.  Rehabilitation of Unit No.1, 2&3 of TPS Muzaffargarh has been completed and attained a gain of 220 MW against the assessed capacity of 70 MW which is due to further deration of units.  Replacement of Economizer tubes & Air Preheater Elements of Unit No. 6 is in progress after that the same will be replaced at Unit No.5.  Completion date of the project is June 30, 2013. Generation Holding Company 11
  • 12. Generation Holding Company 12 Rehabilitation Program Jamshoro Power Plant (GENCO-1)
  • 13. Generation Holding Company 13 GENERATION GENCO – 1 Jamshoro Power Plant (1/3) Unit Make DOC Fuel Installed capacity Current capacity Design Efficiency Current Efficiency Unit 1 Japan 1990 RFO 250 MW 200 MW 36.63 % 30.60 % Unit 2 China 1989 RFO/Gas 200 MW 170 MW 33.89 % 25.20 % Unit 3 China 1990 RFO/Gas 200 MW 170 MW 33.89 % 25.20 % Unit 4 China 1991 RFO/Gas 200 MW 170 MW 33.89 % 25.20 % Total 850 MW 710 MW Current Status
  • 14. Generation Holding Company 14 GENERATION GENCO – 1 Jamshoro Power Plant (2/3) Unit Installed capacity 2007 IDC NEPRA Current capacity Design Efficiency 2007 IDC NEPRA Current Efficiency Unit 1 250 MW 205 MW 125 MW 36.63 % 32.00 % 30.60 % Unit 2 200 MW 165 MW 170 MW 33.89 % 27.80 % 25.20 % Unit 3 200 MW 165 MW 170 MW 33.89 % 27.80 % 25.20 % Unit 4 200 MW 165 MW 170 MW 33.89 % 27.80 % 25.20 % Total 850 MW 700 MW 710 MW This is the problem: The differential between tariff and actual generation.
  • 15. CAPACITY GAIN AFTER REHABILITATION Unit No. Capacity Before Rehabilitation MW Capacity After Rehabilitation MW Capacity Gain By March 2013 MW Thermal Efficiency % Before After Gain 1 125 200 75 33.95 35.88 5.70 2 100 170 70 28.47 32.37 13.70 3 170 170 28.47 32.37 13.70 4 170 170 28.47 32.37 13.70 Total 225 710 485 29.84 33.25 11.70 THERMAL POWER STATION JAMSHORO
  • 16. PARAWISE REPLY OF NEPRA’s QUERRIES JPCL (GENCO-I) a. Fuel flow meters have already been installed at units of Power Complex Jamshoro. b. No Gas Chromatograph is installed at TPS Jamshoro. However, the case has been initiated for the procurement and installation of the Choromatograph and successful bidder has been recommended for approval by the competent Authority and will be installed soon. c. Heat rate and initial dependability test of each generating block will be carried out after calibration of fuel (Gas, Oil) flow meters. The case for calibration of fuel flow meters is under process with USAID. d. Gas supply agreement has already been signed with SSGCL on 10Apr 1995, whereas Fuel oil supply agreement with PSO will be initiated shortly. e. Power Purchase Agreement with the NTDC has already been signed on 26 November, 2010. f. Tender for all GENCOs was invited by General Manager (Thermal) office but only a single bidder participated without furnishing the earnest money and the case couldn’t be matured. Keeping in view the Ministry of Water and Power (MoW&P) directions for hiring of independent engineer, USAID was contacted for provision of assistance in this case. The same will now be conducted by the independent engineer M/s PES as is appointed by the USAID. Consent of NEPRA has also been taken on the issue. g. After conducting the heat rate and initial dependable capacity modification in generation license will be applied and thereafter power purchase agreement will be signed with NTDC. Generation Holding Company 16
  • 17. Generation Holding Company 17 Rehabilitation Program Guddu Power Plant (GENCO-2)
  • 18. Generation Holding Company 18 GENERATION GENCO – 2 Guddu Power Plant Unit Tech. Units DOC Fuel Installed capacity Current capacity Block 1 CCGT 11 - 13 1992 - 1994 Gas 415 MW 230 MW Block 2 CCGT 5 - 10 1985 - 1988 Gas 600 MW 370 MW Block 3 ST 3 - 4 1980 & 1985 Gas/RFO 420 MW 270 MW Block 4 ST 1 - 2 1974 Gas 220 MW 110 MW Total 1,655 MW 980 MW Current Status: 13 Units 900-920 MW is available at Gas as a fuel.
  • 19. Generation Holding Company 19 GENERATION GENCO – 2 Guddu Power Plant Block Designed % NEPRA % Present % Expected % Current Capacity Expected Capacity Block-I (GT-11, 12 & ST-13) 48.20 40.00 36.32 40.00 230 385 Block-II (ST-5, GT-7 & GT-8) 44.36 36.00 32.69 36.00 370 570 Block-III (ST-3 and 4) 37.55 30.00 27.24 28.44 270 340 Block-IV (ST-1&2) 37.50 28.00 25.43 27.33 110 180 980 MW 1475 MW Post major Outages & Rehabilitation: An expected gain of 495 MW
  • 20. CAPACITY GAIN AFTER REHABILITATION Unit No. Capacity Before Rehabilitation MW Capacity After Rehabilitation MW Capacity Gain By March 2013 MW Thermal Efficiency % Block No Before After Gain 1 60 90 30 IV 23.05 23.05 00 2 50 90 40 3 140 170 30 III 27.26 28.44 4.15 4 130 170 40 5 0 80 80 II 32.71 36.00 9.137 0 100 100 8 80 100 20 6 75 75 00 37.58 37.77 0.509 105 105 00 10 110 110 00 11 80 130 50 I 36.34 40.15 9.5012 80 130 50 13 70 125 55 Total 980 1475 495 THERMAL POWER STATION GUDDU Note: 1. For modification of Unit No. 1 & 2 by the Russian company, the L/C has been established for carrying out Gas firing improvement. 2. At present Unit No. 5 is under Shutdown for want of repair of generator rotor at GE works Saudi Arabia. Rotor has reached at Port at Karachi. The Unit will come back on bar in April, 2013 & take load 35-40 MW. 3. Unit No. 7 is under shutdown for want of new Torque Converter from M/s Voith Germany and is expected to be back on bar by June 2013 & 90 MW load will be available on this Unit and Total gain at this block will be 125 MW ( ST 5 35 MW + GT 7 90 MW). 4. For Uprate/Upgrade of GE Units 5, 7 & 8, Purchase & Service Order has been placed on M/s GE USA. The job will be completed in 8-10 weeks as per schedule. 5. LOI in favour of M/s MAPNA Iran has been issued to carry out the overhauling job of the Siemens Units 11, 12 & 13. Service order yet to be issued. The job will be carried out one by one on each Unit in 105 days starting from mid April, 2013 .
  • 21. PARAWISE REPLY OF NEPRA’s QUERRIES CPGCL (GENCO-II) a. Fuel flow meters have already been installed on steam units and gas turbines of Power Complex Guddu. b. The tender invited fifth time for the procurement of gas chromatograph that was opened on 19- 02-2013 and is in evaluation process. The same will be installed / commissioned in next 4-6 months. The previously called tenders could not be matured due to bid did not received. c. Heat rate and initial dependability test of each generating block will be carried out after calibration of fuel (Gas, Oil) flow meters. The case for calibration of fuel flow meters is under process with USAID. d. Fuel Supply Agreement (FSA) with supplier (PSO) and Gas Supply Agreement with Pakistan Petroleum Limited (PPL) and Sui Northern Gas Pipeline Limited (SNGPL) are in process. e. Draft Power Purchase Agreement between NTDC and CPGCL has been submitted to NTDC on 05- 10-2012. Articles 1 to 7 of the Agreement have been discussed and remaining articles will be discussed on 14-03-2013 as meeting date conveyed by the NTDC. f. Tender for all GENCOs was invited by General Manager (Thermal) office but only a single bidder participated without furnishing the earnest money and the case couldn’t be matured. Keeping in view the Ministry of Water and Power (MoW&P) directions for hiring of independent engineer, USAID was contacted for provision of assistance in this case. The same will now be conducted by the independent engineer M/s PES as is appointed by the USAID. Consent of NEPRA has also been taken on the issue. . g. After conducting the heat rate and initial dependable capacity modification in generation license will be applied and thereafter power purchase agreement will be signed with NTDC. Generation Holding Company 21
  • 22. Generation Holding Company 22 Rehabilitation Program Muzaffargarh Power Plant (GENCO-3)
  • 23. Generation Holding Company 23 GENERATION GENCO – 3 Muzaffargarh Power Plant (1/5) Unit Make DOC Fuel Installed capacity Current capacity Unit 1 Russia 1993 RFO/Gas 210 90 Unit 2 Russia 1994 RFO/Gas 210 160 Unit 3 Russia 1995 RFO/Gas 210 160 Unit 4 China 1997 RFO/Gas 320 160 Unit 5 China 1995 RFO/Gas 210 100 Unit 6 China 1995 RFO/Gas 210 80 Total 1370 MW 750 MW Current Status
  • 24. Generation Holding Company 24 GENERATION GENCO – 3 Muzaffargarh Power Plant (2/5) Block Designed % NEPRA % Present % Expected % Current Capacity Expected Capacity Unit 1 36.77 33.00 30.41 32.41 90 165 Unit 2 36.77 33.00 31.97 32.66 160 170 Unit 3 36.77 33.00 31.26 32.12 160 170 Unit 4 36.70 33.00 28.80 34.02 160 210 Unit 5 31.65 29.00 24.55 26.60 100 140 Unit 6 31.65 29.00 25.01 26.55 80 120 750 MW 975 MW Post major Outages & Rehabilitation
  • 25. CAPACITY GAIN AFTER REHABILITATION Unit No. Capacity Before Rehabilitation MW Capacity After Rehabilitation MW Capacity Gain By March 2013 MW Thermal Efficiency % Before After Gain 1 90 185 80 30.41 32.41 6.57 2 110 185 70 31.97 32.66 2.15 3 110 185 70 31.26 32.12 2.75 4 160 280 100 28.80 34.02 18.12 5 100 170 70 24.55 26.60 8.35 6 80 170 90 25.01 26.55 6.15 Total 650 1175 525 28.66 30.72 7.18 THERMAL POWER STATION MUZAFFARGARH
  • 26. PARAWISE REPLY OF NEPRA’s QUERRIES NPGCL (GENCO-III) Generation Holding Company 26 a. Fuel flow meters have already been installed at units of Power Complex Muzaffargarh. b. No chromatograph meter is installed at TPS Muzaffargarh. Calorimeter is installed by Sui Northern Gas Pipelines Limited (SNGPL) at their gas Station TPS Muzaffargarh. The monthly calibration of the Calorimeter is carried out by the joint metering Committee of SNGPL and TPS Muzaffargarh. Procurement case for chromatograph meter is in process. c. Heat rate and initial dependability test of each generating block will be carried out after calibration of fuel (Gas, Oil) flow meters. The case for calibration of fuel flow meters is under process with USAID. d. Fuel Oil Supply agreement has been signed between NPGCL and Pakistan State Oil Company Limited (PSO) on dated 16.09.2009. Request of Gas Supply Agreement between NPGCL (GENCO- III) and SNGPL has been made several times. SNGPL rejected the request for GSA of even 10 MMCFD with TPS Muzaffargarh due to their system constraints. GSA already exists between WAPDA and SNGPL to supply 25 MMCFD gas to Gas Turbine Power Station Faisalabad, however, GSA is not being implemented on part of SNGPL. e. Power Purchase Agreement was signed in 1999 but expired. The restated PPA is in the process of finalization and Draft PPA is in the process of finalization with CPPA. The finalization of PPA will be after Heat Rate/CDC test. f. Tender for all GENCOs was invited by General Manager (Thermal) office but only a single bidder participated without furnishing the earnest money and the case couldn’t be matured. Keeping in view the Ministry of Water and Power (MoW&P) directions for hiring of independent engineer, USAID was contacted for provision of assistance in this case. The same will now be conducted by the independent engineer M/s PES as is appointed by the USAID. Consent of NEPRA has also been taken on the issue. g. After conducting the heat rate and initial dependable capacity modification in generation license will be applied and thereafter power purchase agreement will be signed with NTDC.
  • 27. Generation Holding Company 27 Genco Holding Company Limited THANKS