SlideShare ist ein Scribd-Unternehmen logo
1 von 33
Downloaden Sie, um offline zu lesen
The Global Leader in Managing Construction Risk ™
Litigation & Claims
Facts & Figures
Paul Lomas-Clarke
FRICS FCIArb FCIOB
CEDR Accredited Mediator
Executive Director
2011
2
The reasons claims arise
•  Inadequate contract preparation
•  Mistakes in documents
•  Optimisms instead of reality
•  Misunderstanding formation of Contract
•  Failure to understand risk
•  Poorly drafted variation instructions
•  Failure to understand basic contractual position
•  Failure to analyse / explain additional entitlements
3
GENERAL PRINCIPLES
Recognising Claims Early
•  Essential to avoid disputes and speed
resolution
•  Allow good record keeping
•  Assists in managing entitlements
•  Burden of proof on claiming party
•  Monitoring procedures
–  (+consequential time / costs)
4
EXTENSION OF TIME CLAIMS
Purpose
Protects contractor against liquidated
damages by excusing delay
Protects Employer’s right to LADs by
maintaining a completion date (a date
from which to calculate LADs)
– Holme V Guppy 1838
– Wells V Army & Navy Co-op 1902
•  Otherwise a penalty
5
Employer’s Claims
LIQUIDATED DAMAGES
Reason for Use of LADs
•  Contractual equivalent of common law damages
•  Benefit for both parties
•  For Employer:
–  a contractual right - no need to prove loss
•  Hadley V Baxendale
•  For Contractor:
–  Obligation known
–  Can advise potential liability to others (ie. special
damages)
6
Employer’s Claims
LIQUIDATED DAMAGES
Rules (cont’d)
Rules for applying LADs
•  Where procedures apply, most be applied strictly
•  Where notice required – condition precedent
–  Principal may lose right to LADs where proper notice not given –
•  Bell v CBF;
•  JF Finnegan Ltd -v- Community Housing Association Ltd
•  Delaying breach where no corresponding provision
•  (Rapid v Ealing Family Housing)
•  Incompatibility between contract and appendix
•  (Sheffield v Bramell & Ogden)
•  ‘NIL’ in appendix
7
Penalties
•  Sum must not be a penalty
–  Dunlop v New Garage & Motor Co (1915)
–  is it a genuine pre-estimate?
- is it ‘in terrorem’ (threat)
–  BFI Group of Companies Ltd -v- DCB
Integration Systems Ltd (1987)
8
Employer’s Claims
LIQUIDATED DAMAGES
•  Need not be actual loss
– Clydebank Engineering and Shipbuilding
Company Limited v Don Jose Ramos
Ysquierdo y Castaneda and Others [1905]
9
EXTENSION OF TIME CLAIMS
Notices
•  Most contracts contain procedures –
normally requirement for notice,
– JCT – forthwith after delay apparent
– MF/1 – as soon as reasonably practicable
– ECC – within 8 wks of becoming aware of
compensation event
– GC Works - Within 56 days
10
EXTENSION OF TIME (cont’d)
Notices (cont’d)
•  Form of notice? – as contract requires
•  Some contracts require detailed notice, eg
–  JCT – particulars and effects, estimate, update
–  ECC – Early warning in writing
–  MF/1 – full supporting details
–  Recommendation- apply as close as possible to event
•  Site minutes?
–  In Haley v Dumfries & Galloway – not good notice
11
EXTENSION OF TIME (cont’d)
Grounds for extension (ie. for excusable
delay)
Some contracts list ‘reasons’ in detail, eg:
Employer (late information)
Neutral (exceptional inclement weather)
•  Some contracts give general grounds, eg:
JCT Minor Works, MF/1
•  Matters beyond contractor’s control
12
EXTENSION OF TIME (cont’d)
•  Use of Float
– First to use gets the benefit
– JCT Architect gives reasonable EOT
•  Use float
– NEC Actual time added to Programme
•  Float Preserved
13
EXTENSION OF TIME (cont’d)
•  Claimant must identify Employer’s liability
that actually causes delay to completion.
– I.E. delay on critical path
Delay on non critical item –
No EOT to contract
Perhaps additional prelims as VO
14
PROGRAMMES
•  Programmes often not ‘agreed’, e.g.
– JCT 05 (clause 2.9.1.2): silent other than
contractor to “provide”
– ICE (clause 14): acceptance of original
– GC Works: agreement of amendments by PM
– NEC3 (clause 31): acceptance of original &
revisions by PM
15
Critical Path Analysis
“The Society of Construction Law Delay and
Disruption Protocol – October 2002”
www.eotprotocol.com
Recommendations
•  A Critical Path Network
•  Uses commercially available Software
•  Identifies All Relevant Activities
•  Tool to Manage Change
16
Schedule of delays
Ref
No
Arch Ins
Or other +
Date
Cause Period of
Delay
(days )
Effect
on
Progrm
Notice
Served
17
Cofferdams
Abutments
Deck Structure
Deck Furniture/E&M
Finishing & Commissioning
At-Grade Approach Roads
Appoint Subcontractor
Construct Approach Road (2km)
Open Bridge & Roads
0 1 2 3 4 5 6 7 8 9 10 11
Bridge
MONTHS
Site Clearance
Delay Analysis “Black Art”
18
Delay Analysis – as built
At-Grade Approach Roads
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
MONTHS
Construct Approach
Roads (3km)
Actual Finish
Month 15Appoint Subcontractor
Deck Structure
Deck Furniture/E&M
Finishing & Commissioning
Site Clearance
Bridge
Cofferdams
Abutments
19
Delay Analysis – Time Slice/Window
30
10
At-Grade Approach Roads
45
6
Open Bridge & Roads
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
Deck Structure
Deck Furniture/E&M
Finishing & Commissioning
Site Clearance
Bridge
Cofferdams
Abutments
MONTHS 40d EoT
Construct Approach
Roads (3km)
Actual Finish
Month 15Appoint Subcontractor
6d EoT
10 Days Denied Access to Site.
30 Days Additional work to
abutments required by
client.
45 Days Additional work to
approach road
6 Days Additional gulley road
approach road.
Progress after 15 months
20
The way NOT to show progress
and delays
21
Variations Claims
Employer / agent changes;
•  the features, scope or complexity of the
project
–  Therefore;
•  Adjustment to the contract price
•  Adjustment to the contract period
22
Claim Problems
•  Viability of Original Programme
•  Original Resources correct?
•  Variation in critical path
•  Subcontractors information
•  Lack of Records
23
Claim Issues
•  JCT
Wide definition of variation
•  Access to site, working space, working hours,
specific order of works
–  Variations must include adjustment of preliminary
items as SMM
–  Change in conditions under which other work is
executed must be taken into account in variations
–  Include fair allowance for any change caused by
variations
–  Exclusion for reimbursement under any other
provision
24
Claim issues
•  GC /Works/1
–  Very wide definition of variation
•  Change, suspension, “any other matter”
–  Disruption to be included in price of variation
–  Allowance for expense only (money expended) not loss
–  Obligation to submit information within 28 days
–  QS to notify within 28 days
–  Contractors objection to QS limited to 14 day “window”
–  Weather delays excluded
–  Embargo on delay claims after completion
25
Claim issues
•  NEC (ECC)
–  Wide range of rights to claim compensation events
–  BUT notice must be given within 8 weeks = condition
precedent to rights
–  References to EOT = Change in Completion Date
–  Contractor can be locked into his quote
–  Project Manager must give decision within one week
26
Claim Problems
•  Acceleration claims are almost impossible
– Nearly all current contracts have special
clauses
•  No instruction – no acceleration
•  Thickening claims
– Include in preliminaries for additional staff in
variations
27
Legal Principles and Case Law
•  Percy Bilton Ltd v Greater London Council
[1982]
–  Lowdell (first Nominated Sub-Contractor) stops
work and is liquidated
–  Crown House (second Nominated Sub-Contractor)
withdraws without starting work
–  Home Counties (third Nominated Sub-Contractor)
completes work
–  Employer must re-nominate in reasonable period
–  Time not at large
28
Legal Principles and Case Law
•  Walter Lawrence & Sons ltd v
Commercial Union Properties Ltd
[1984]
– Contractor defers work into period of bad
weather
– Test: does exceptionally inclement
weather actually give rise to a delay
29
Legal Principles and Case Law
•  Yorkshire Water Authority v Sir Alfred
McAlpine & Son Ltd [1986]
– McAlpine programme and method
statement included in Contract
– Works were impossible to build to
programme sequence
– Change is Variation under Contract
30
Legal Principles and Case Law
•  Glenlion Construction ltd v The
Guiness Trust [1987]
– Glenlion programmed to complete works
early
– Glenlion entitled to work to programme
– Guiness obliged not to hinder or obstruct
– BUT Guiness not obliged to provide
information early
31
Legal Principles and Case Law
•  Ascon Contracting Ltd v Alfred
McAlpine Construction Isle of Man Ltd
[1999]
– Ascon cause McAlpine delay
– McAlpine main contract programme
contains “float”
– McAlpine not entitled to “benefit of “float”
32
Legal Principles and Case Law
•  Great Eastern Hotel Company Ltd v
John Laing [2005]
– Laing used Impacted As-planned analysis
– GEHC used a form of Time Impact
Analysis
– Judge favoured the factual basis of GEHC
and Laing analysis hypothetical
33
So what to do?
•  Question over the probative value of different techniques
•  Remember 'rubbish in rubbish out' especially to computerized
CPA models
•  Don’t get lost in the analyses;
•  Assemble a matrix of facts in the form of planned and as-built
dates
•  Beware of manipulation to create a preferred result;
•  Complex networks can be very difficult to follow and the
relationships between activities difficult to understand
•  Adopt the appropriate one using a level of detail which is both
persuasive and yet proportionate to the scale of the dispute.

Weitere ähnliche Inhalte

Was ist angesagt?

Construction claims, disputes and project closure
Construction claims, disputes and project closureConstruction claims, disputes and project closure
Construction claims, disputes and project closuresrinivas2036
 
N.M.Raj's Master Bootcamp - Construction Claims
N.M.Raj's Master Bootcamp - Construction ClaimsN.M.Raj's Master Bootcamp - Construction Claims
N.M.Raj's Master Bootcamp - Construction Claimsrajj13
 
Claims & disputes management
Claims & disputes managementClaims & disputes management
Claims & disputes managementMohammed Tanbouz
 
Why does an eot not automatically entitle a contractor to prolongation costs ...
Why does an eot not automatically entitle a contractor to prolongation costs ...Why does an eot not automatically entitle a contractor to prolongation costs ...
Why does an eot not automatically entitle a contractor to prolongation costs ...Iffat Al Gharbi
 
Fidic yellow vs silver
Fidic yellow vs silverFidic yellow vs silver
Fidic yellow vs silverWeero Koster
 
Eot claims due to scope change under fidic contracts
Eot claims due to scope change under fidic contractsEot claims due to scope change under fidic contracts
Eot claims due to scope change under fidic contractsEssam Lotffy, PMP®, CCP®
 
Advanced training for construction management: CONTRACTS MANAGEMENT part 2 (...
Advanced training for  construction management: CONTRACTS MANAGEMENT part 2 (...Advanced training for  construction management: CONTRACTS MANAGEMENT part 2 (...
Advanced training for construction management: CONTRACTS MANAGEMENT part 2 (...Antonio Coladarce
 
Criterium epc project risks (5.28.13)
Criterium epc project risks (5.28.13)Criterium epc project risks (5.28.13)
Criterium epc project risks (5.28.13)Roland_Nikles
 
FIDIC SIlver Book in Power Projects
FIDIC SIlver Book in Power ProjectsFIDIC SIlver Book in Power Projects
FIDIC SIlver Book in Power ProjectsFrancis Ho
 
Causes of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersCauses of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersIOSR Journals
 
Wind power epc o&m april 2013
Wind power epc o&m  april 2013Wind power epc o&m  april 2013
Wind power epc o&m april 2013Weero Koster
 
Session-02 17-09-2011
Session-02 17-09-2011Session-02 17-09-2011
Session-02 17-09-2011Tahir B Mirza
 
Epc project interdepency and Work Flow- promo
Epc project interdepency and Work Flow- promoEpc project interdepency and Work Flow- promo
Epc project interdepency and Work Flow- promoignitetribes
 
Contracts & Claims Management Workshop (Session-1)
Contracts & Claims Management Workshop (Session-1)Contracts & Claims Management Workshop (Session-1)
Contracts & Claims Management Workshop (Session-1)Tahir B Mirza
 

Was ist angesagt? (19)

Claim Presentation Rev 03 FINAL
Claim Presentation Rev 03 FINALClaim Presentation Rev 03 FINAL
Claim Presentation Rev 03 FINAL
 
Construction claims, disputes and project closure
Construction claims, disputes and project closureConstruction claims, disputes and project closure
Construction claims, disputes and project closure
 
N.M.Raj's Master Bootcamp - Construction Claims
N.M.Raj's Master Bootcamp - Construction ClaimsN.M.Raj's Master Bootcamp - Construction Claims
N.M.Raj's Master Bootcamp - Construction Claims
 
Claims & disputes management
Claims & disputes managementClaims & disputes management
Claims & disputes management
 
Claims and Counterclaims Preparation, Analysis, Assessment and Successful Set...
Claims and Counterclaims Preparation, Analysis, Assessment and Successful Set...Claims and Counterclaims Preparation, Analysis, Assessment and Successful Set...
Claims and Counterclaims Preparation, Analysis, Assessment and Successful Set...
 
Why does an eot not automatically entitle a contractor to prolongation costs ...
Why does an eot not automatically entitle a contractor to prolongation costs ...Why does an eot not automatically entitle a contractor to prolongation costs ...
Why does an eot not automatically entitle a contractor to prolongation costs ...
 
Extension of Time (EOT) & Related Costs in Construction - Presentation Slides
Extension of Time (EOT) & Related Costs in Construction - Presentation SlidesExtension of Time (EOT) & Related Costs in Construction - Presentation Slides
Extension of Time (EOT) & Related Costs in Construction - Presentation Slides
 
Fidic yellow vs silver
Fidic yellow vs silverFidic yellow vs silver
Fidic yellow vs silver
 
Claims
ClaimsClaims
Claims
 
Eot claims due to scope change under fidic contracts
Eot claims due to scope change under fidic contractsEot claims due to scope change under fidic contracts
Eot claims due to scope change under fidic contracts
 
Advanced training for construction management: CONTRACTS MANAGEMENT part 2 (...
Advanced training for  construction management: CONTRACTS MANAGEMENT part 2 (...Advanced training for  construction management: CONTRACTS MANAGEMENT part 2 (...
Advanced training for construction management: CONTRACTS MANAGEMENT part 2 (...
 
Criterium epc project risks (5.28.13)
Criterium epc project risks (5.28.13)Criterium epc project risks (5.28.13)
Criterium epc project risks (5.28.13)
 
FIDIC SIlver Book in Power Projects
FIDIC SIlver Book in Power ProjectsFIDIC SIlver Book in Power Projects
FIDIC SIlver Book in Power Projects
 
Causes of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersCauses of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge Girders
 
Wind power epc o&m april 2013
Wind power epc o&m  april 2013Wind power epc o&m  april 2013
Wind power epc o&m april 2013
 
FIDIC intro author eng. mohammed fadlalla
FIDIC intro  author eng. mohammed fadlallaFIDIC intro  author eng. mohammed fadlalla
FIDIC intro author eng. mohammed fadlalla
 
Session-02 17-09-2011
Session-02 17-09-2011Session-02 17-09-2011
Session-02 17-09-2011
 
Epc project interdepency and Work Flow- promo
Epc project interdepency and Work Flow- promoEpc project interdepency and Work Flow- promo
Epc project interdepency and Work Flow- promo
 
Contracts & Claims Management Workshop (Session-1)
Contracts & Claims Management Workshop (Session-1)Contracts & Claims Management Workshop (Session-1)
Contracts & Claims Management Workshop (Session-1)
 

Ähnlich wie Managing Construction Risk and Claims

Managing the Risks of Delay in Construction Projects
Managing the Risks of Delay in Construction ProjectsManaging the Risks of Delay in Construction Projects
Managing the Risks of Delay in Construction ProjectsFrancis Ho
 
PECDisputeResolution25102018.pptx
PECDisputeResolution25102018.pptxPECDisputeResolution25102018.pptx
PECDisputeResolution25102018.pptxIrfanAwan25
 
GCC2015 Course_Day2
GCC2015 Course_Day2GCC2015 Course_Day2
GCC2015 Course_Day2JB Nartey
 
GCC2015 Course_Day2
GCC2015 Course_Day2GCC2015 Course_Day2
GCC2015 Course_Day2JB Nartey
 
FEDCON Summit: Change Orders & Contract Disruptions/Delays
FEDCON Summit: Change Orders & Contract Disruptions/DelaysFEDCON Summit: Change Orders & Contract Disruptions/Delays
FEDCON Summit: Change Orders & Contract Disruptions/DelaysNC Military Business Center
 
Bridget campbell - Getting the enforcement notice right and best practice at ...
Bridget campbell - Getting the enforcement notice right and best practice at ...Bridget campbell - Getting the enforcement notice right and best practice at ...
Bridget campbell - Getting the enforcement notice right and best practice at ...The Planning Inspectorate
 
Public sector planning club, January 2017
Public sector planning club, January 2017Public sector planning club, January 2017
Public sector planning club, January 2017Browne Jacobson LLP
 
Professional practice 2
Professional practice 2Professional practice 2
Professional practice 2ahmong4
 
Arbitration Dispute Cross Arguments: Asia NGPipeline -Substance of EPC contra...
Arbitration Dispute Cross Arguments: Asia NGPipeline -Substance of EPC contra...Arbitration Dispute Cross Arguments: Asia NGPipeline -Substance of EPC contra...
Arbitration Dispute Cross Arguments: Asia NGPipeline -Substance of EPC contra...César del Riego y Fuentes
 
PP Seminar Tutorial 7
PP Seminar Tutorial 7PP Seminar Tutorial 7
PP Seminar Tutorial 7Farah Sham
 
CFW NEC Management of change under the NEC3
CFW NEC  Management of change under the NEC3 CFW NEC  Management of change under the NEC3
CFW NEC Management of change under the NEC3 Rae Davies
 
Construction Futures Wales - NEC3 Workshop - Understanding Works Information...
Construction Futures Wales  - NEC3 Workshop - Understanding Works Information...Construction Futures Wales  - NEC3 Workshop - Understanding Works Information...
Construction Futures Wales - NEC3 Workshop - Understanding Works Information...Rae Davies
 
HM hub and NPD second masterclass seminar 6.11.15.PPT
HM hub and NPD second masterclass seminar 6.11.15.PPTHM hub and NPD second masterclass seminar 6.11.15.PPT
HM hub and NPD second masterclass seminar 6.11.15.PPTEuan Pirie
 
FIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdf
FIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdfFIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdf
FIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdfBayuDarma4
 
Builders Risk presentation - selected slides
Builders Risk presentation - selected slidesBuilders Risk presentation - selected slides
Builders Risk presentation - selected slidesMichael Pepe
 
Construction Futures Wales - NEC Workshop - Importance of Program Control & M...
Construction Futures Wales - NEC Workshop - Importance of Program Control & M...Construction Futures Wales - NEC Workshop - Importance of Program Control & M...
Construction Futures Wales - NEC Workshop - Importance of Program Control & M...Rae Davies
 

Ähnlich wie Managing Construction Risk and Claims (20)

Ceca Caselaw
Ceca Caselaw Ceca Caselaw
Ceca Caselaw
 
Essentials of EOT Claims
Essentials of EOT ClaimsEssentials of EOT Claims
Essentials of EOT Claims
 
Managing the Risks of Delay in Construction Projects
Managing the Risks of Delay in Construction ProjectsManaging the Risks of Delay in Construction Projects
Managing the Risks of Delay in Construction Projects
 
PECDisputeResolution25102018.pptx
PECDisputeResolution25102018.pptxPECDisputeResolution25102018.pptx
PECDisputeResolution25102018.pptx
 
GCC2015 Course_Day2
GCC2015 Course_Day2GCC2015 Course_Day2
GCC2015 Course_Day2
 
GCC2015 Course_Day2
GCC2015 Course_Day2GCC2015 Course_Day2
GCC2015 Course_Day2
 
FEDCON Summit: Change Orders & Contract Disruptions/Delays
FEDCON Summit: Change Orders & Contract Disruptions/DelaysFEDCON Summit: Change Orders & Contract Disruptions/Delays
FEDCON Summit: Change Orders & Contract Disruptions/Delays
 
Bridget campbell - Getting the enforcement notice right and best practice at ...
Bridget campbell - Getting the enforcement notice right and best practice at ...Bridget campbell - Getting the enforcement notice right and best practice at ...
Bridget campbell - Getting the enforcement notice right and best practice at ...
 
Public sector planning club, January 2017
Public sector planning club, January 2017Public sector planning club, January 2017
Public sector planning club, January 2017
 
Epc contracts.
Epc contracts.Epc contracts.
Epc contracts.
 
Professional practice 2
Professional practice 2Professional practice 2
Professional practice 2
 
Arbitration Dispute Cross Arguments: Asia NGPipeline -Substance of EPC contra...
Arbitration Dispute Cross Arguments: Asia NGPipeline -Substance of EPC contra...Arbitration Dispute Cross Arguments: Asia NGPipeline -Substance of EPC contra...
Arbitration Dispute Cross Arguments: Asia NGPipeline -Substance of EPC contra...
 
PP Seminar Tutorial 7
PP Seminar Tutorial 7PP Seminar Tutorial 7
PP Seminar Tutorial 7
 
Recent NEC3 Case Review and its Application
Recent NEC3 Case Review and its ApplicationRecent NEC3 Case Review and its Application
Recent NEC3 Case Review and its Application
 
CFW NEC Management of change under the NEC3
CFW NEC  Management of change under the NEC3 CFW NEC  Management of change under the NEC3
CFW NEC Management of change under the NEC3
 
Construction Futures Wales - NEC3 Workshop - Understanding Works Information...
Construction Futures Wales  - NEC3 Workshop - Understanding Works Information...Construction Futures Wales  - NEC3 Workshop - Understanding Works Information...
Construction Futures Wales - NEC3 Workshop - Understanding Works Information...
 
HM hub and NPD second masterclass seminar 6.11.15.PPT
HM hub and NPD second masterclass seminar 6.11.15.PPTHM hub and NPD second masterclass seminar 6.11.15.PPT
HM hub and NPD second masterclass seminar 6.11.15.PPT
 
FIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdf
FIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdfFIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdf
FIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdf
 
Builders Risk presentation - selected slides
Builders Risk presentation - selected slidesBuilders Risk presentation - selected slides
Builders Risk presentation - selected slides
 
Construction Futures Wales - NEC Workshop - Importance of Program Control & M...
Construction Futures Wales - NEC Workshop - Importance of Program Control & M...Construction Futures Wales - NEC Workshop - Importance of Program Control & M...
Construction Futures Wales - NEC Workshop - Importance of Program Control & M...
 

Mehr von Project Controls Expo

National Grids Project Controls Journey – past, present and future
National Grids Project Controls Journey – past, present and futureNational Grids Project Controls Journey – past, present and future
National Grids Project Controls Journey – past, present and futureProject Controls Expo
 
Case study in Company Project Controls Transformation By Rod Whiting - Region...
Case study in Company Project Controls Transformation By Rod Whiting - Region...Case study in Company Project Controls Transformation By Rod Whiting - Region...
Case study in Company Project Controls Transformation By Rod Whiting - Region...Project Controls Expo
 
Balancing burdens of proof in dispute avoidance and resolution by "Ari Isaacs...
Balancing burdens of proof in dispute avoidance and resolution by "Ari Isaacs...Balancing burdens of proof in dispute avoidance and resolution by "Ari Isaacs...
Balancing burdens of proof in dispute avoidance and resolution by "Ari Isaacs...Project Controls Expo
 
Managing Changes on a Capital Programme by "Iain Cameron - Technical Director...
Managing Changes on a Capital Programme by "Iain Cameron - Technical Director...Managing Changes on a Capital Programme by "Iain Cameron - Technical Director...
Managing Changes on a Capital Programme by "Iain Cameron - Technical Director...Project Controls Expo
 
Navigating BIM waters by "Natacha Redon - Associate / BIM Lead for Identity C...
Navigating BIM waters by "Natacha Redon - Associate / BIM Lead for Identity C...Navigating BIM waters by "Natacha Redon - Associate / BIM Lead for Identity C...
Navigating BIM waters by "Natacha Redon - Associate / BIM Lead for Identity C...Project Controls Expo
 
NEC4: Evolution of the ECC by "Ben Walker - NEC4 Contract Drafter, CEO for CE...
NEC4: Evolution of the ECC by "Ben Walker - NEC4 Contract Drafter, CEO for CE...NEC4: Evolution of the ECC by "Ben Walker - NEC4 Contract Drafter, CEO for CE...
NEC4: Evolution of the ECC by "Ben Walker - NEC4 Contract Drafter, CEO for CE...Project Controls Expo
 
Managing the risk of change by "Simon White - Risk Management Consultant for ...
Managing the risk of change by "Simon White - Risk Management Consultant for ...Managing the risk of change by "Simon White - Risk Management Consultant for ...
Managing the risk of change by "Simon White - Risk Management Consultant for ...Project Controls Expo
 
Economic Value Chains - costing the impact of risk by "Colin Sandall - Senior...
Economic Value Chains - costing the impact of risk by "Colin Sandall - Senior...Economic Value Chains - costing the impact of risk by "Colin Sandall - Senior...
Economic Value Chains - costing the impact of risk by "Colin Sandall - Senior...Project Controls Expo
 
What makes a good plan, and how do you know you’ve got one? by "Paul Kidston ...
What makes a good plan, and how do you know you’ve got one? by "Paul Kidston ...What makes a good plan, and how do you know you’ve got one? by "Paul Kidston ...
What makes a good plan, and how do you know you’ve got one? by "Paul Kidston ...Project Controls Expo
 
Next Generation Planning for Mega Projects by "Dr. Dan Patterson - CEO and Fo...
Next Generation Planning for Mega Projects by "Dr. Dan Patterson - CEO and Fo...Next Generation Planning for Mega Projects by "Dr. Dan Patterson - CEO and Fo...
Next Generation Planning for Mega Projects by "Dr. Dan Patterson - CEO and Fo...Project Controls Expo
 
Project Control Staff – Make or Buy? by "Mike Laws - Project Controls Manager...
Project Control Staff – Make or Buy? by "Mike Laws - Project Controls Manager...Project Control Staff – Make or Buy? by "Mike Laws - Project Controls Manager...
Project Control Staff – Make or Buy? by "Mike Laws - Project Controls Manager...Project Controls Expo
 
Governance: An Enabler? by " Ian Beaumont - Delivery Partner Programme Direc...
Governance: An Enabler? by "	 Ian Beaumont - Delivery Partner Programme Direc...Governance: An Enabler? by "	 Ian Beaumont - Delivery Partner Programme Direc...
Governance: An Enabler? by " Ian Beaumont - Delivery Partner Programme Direc...Project Controls Expo
 
Governance and the art of decision making on Crossrail by "Walter Macharg - H...
Governance and the art of decision making on Crossrail by "Walter Macharg - H...Governance and the art of decision making on Crossrail by "Walter Macharg - H...
Governance and the art of decision making on Crossrail by "Walter Macharg - H...Project Controls Expo
 
Tideway - Transforming the Thames by "Niall Faris - Project Controls Leader f...
Tideway - Transforming the Thames by "Niall Faris - Project Controls Leader f...Tideway - Transforming the Thames by "Niall Faris - Project Controls Leader f...
Tideway - Transforming the Thames by "Niall Faris - Project Controls Leader f...Project Controls Expo
 
Adding Value through the Lower Thames Crossing project by "Iain Minns - Partn...
Adding Value through the Lower Thames Crossing project by "Iain Minns - Partn...Adding Value through the Lower Thames Crossing project by "Iain Minns - Partn...
Adding Value through the Lower Thames Crossing project by "Iain Minns - Partn...Project Controls Expo
 
Governance and Assurance for Nationally Significant Infrastructure Projects b...
Governance and Assurance for Nationally Significant Infrastructure Projects b...Governance and Assurance for Nationally Significant Infrastructure Projects b...
Governance and Assurance for Nationally Significant Infrastructure Projects b...Project Controls Expo
 
A review of whether interdependency exists in effective Project Control Metho...
A review of whether interdependency exists in effective Project Control Metho...A review of whether interdependency exists in effective Project Control Metho...
A review of whether interdependency exists in effective Project Control Metho...Project Controls Expo
 
A Source of Project Cost Integration by "David Hurren - Technical Director fo...
A Source of Project Cost Integration by "David Hurren - Technical Director fo...A Source of Project Cost Integration by "David Hurren - Technical Director fo...
A Source of Project Cost Integration by "David Hurren - Technical Director fo...Project Controls Expo
 
Programmatic Controls Approach to; Fast track Disaster Recovery by "Saurabh B...
Programmatic Controls Approach to; Fast track Disaster Recovery by "Saurabh B...Programmatic Controls Approach to; Fast track Disaster Recovery by "Saurabh B...
Programmatic Controls Approach to; Fast track Disaster Recovery by "Saurabh B...Project Controls Expo
 
Enterprise Scheduling and Risk Management at Los Angeles Metro by "Julie Owen...
Enterprise Scheduling and Risk Management at Los Angeles Metro by "Julie Owen...Enterprise Scheduling and Risk Management at Los Angeles Metro by "Julie Owen...
Enterprise Scheduling and Risk Management at Los Angeles Metro by "Julie Owen...Project Controls Expo
 

Mehr von Project Controls Expo (20)

National Grids Project Controls Journey – past, present and future
National Grids Project Controls Journey – past, present and futureNational Grids Project Controls Journey – past, present and future
National Grids Project Controls Journey – past, present and future
 
Case study in Company Project Controls Transformation By Rod Whiting - Region...
Case study in Company Project Controls Transformation By Rod Whiting - Region...Case study in Company Project Controls Transformation By Rod Whiting - Region...
Case study in Company Project Controls Transformation By Rod Whiting - Region...
 
Balancing burdens of proof in dispute avoidance and resolution by "Ari Isaacs...
Balancing burdens of proof in dispute avoidance and resolution by "Ari Isaacs...Balancing burdens of proof in dispute avoidance and resolution by "Ari Isaacs...
Balancing burdens of proof in dispute avoidance and resolution by "Ari Isaacs...
 
Managing Changes on a Capital Programme by "Iain Cameron - Technical Director...
Managing Changes on a Capital Programme by "Iain Cameron - Technical Director...Managing Changes on a Capital Programme by "Iain Cameron - Technical Director...
Managing Changes on a Capital Programme by "Iain Cameron - Technical Director...
 
Navigating BIM waters by "Natacha Redon - Associate / BIM Lead for Identity C...
Navigating BIM waters by "Natacha Redon - Associate / BIM Lead for Identity C...Navigating BIM waters by "Natacha Redon - Associate / BIM Lead for Identity C...
Navigating BIM waters by "Natacha Redon - Associate / BIM Lead for Identity C...
 
NEC4: Evolution of the ECC by "Ben Walker - NEC4 Contract Drafter, CEO for CE...
NEC4: Evolution of the ECC by "Ben Walker - NEC4 Contract Drafter, CEO for CE...NEC4: Evolution of the ECC by "Ben Walker - NEC4 Contract Drafter, CEO for CE...
NEC4: Evolution of the ECC by "Ben Walker - NEC4 Contract Drafter, CEO for CE...
 
Managing the risk of change by "Simon White - Risk Management Consultant for ...
Managing the risk of change by "Simon White - Risk Management Consultant for ...Managing the risk of change by "Simon White - Risk Management Consultant for ...
Managing the risk of change by "Simon White - Risk Management Consultant for ...
 
Economic Value Chains - costing the impact of risk by "Colin Sandall - Senior...
Economic Value Chains - costing the impact of risk by "Colin Sandall - Senior...Economic Value Chains - costing the impact of risk by "Colin Sandall - Senior...
Economic Value Chains - costing the impact of risk by "Colin Sandall - Senior...
 
What makes a good plan, and how do you know you’ve got one? by "Paul Kidston ...
What makes a good plan, and how do you know you’ve got one? by "Paul Kidston ...What makes a good plan, and how do you know you’ve got one? by "Paul Kidston ...
What makes a good plan, and how do you know you’ve got one? by "Paul Kidston ...
 
Next Generation Planning for Mega Projects by "Dr. Dan Patterson - CEO and Fo...
Next Generation Planning for Mega Projects by "Dr. Dan Patterson - CEO and Fo...Next Generation Planning for Mega Projects by "Dr. Dan Patterson - CEO and Fo...
Next Generation Planning for Mega Projects by "Dr. Dan Patterson - CEO and Fo...
 
Project Control Staff – Make or Buy? by "Mike Laws - Project Controls Manager...
Project Control Staff – Make or Buy? by "Mike Laws - Project Controls Manager...Project Control Staff – Make or Buy? by "Mike Laws - Project Controls Manager...
Project Control Staff – Make or Buy? by "Mike Laws - Project Controls Manager...
 
Governance: An Enabler? by " Ian Beaumont - Delivery Partner Programme Direc...
Governance: An Enabler? by "	 Ian Beaumont - Delivery Partner Programme Direc...Governance: An Enabler? by "	 Ian Beaumont - Delivery Partner Programme Direc...
Governance: An Enabler? by " Ian Beaumont - Delivery Partner Programme Direc...
 
Governance and the art of decision making on Crossrail by "Walter Macharg - H...
Governance and the art of decision making on Crossrail by "Walter Macharg - H...Governance and the art of decision making on Crossrail by "Walter Macharg - H...
Governance and the art of decision making on Crossrail by "Walter Macharg - H...
 
Tideway - Transforming the Thames by "Niall Faris - Project Controls Leader f...
Tideway - Transforming the Thames by "Niall Faris - Project Controls Leader f...Tideway - Transforming the Thames by "Niall Faris - Project Controls Leader f...
Tideway - Transforming the Thames by "Niall Faris - Project Controls Leader f...
 
Adding Value through the Lower Thames Crossing project by "Iain Minns - Partn...
Adding Value through the Lower Thames Crossing project by "Iain Minns - Partn...Adding Value through the Lower Thames Crossing project by "Iain Minns - Partn...
Adding Value through the Lower Thames Crossing project by "Iain Minns - Partn...
 
Governance and Assurance for Nationally Significant Infrastructure Projects b...
Governance and Assurance for Nationally Significant Infrastructure Projects b...Governance and Assurance for Nationally Significant Infrastructure Projects b...
Governance and Assurance for Nationally Significant Infrastructure Projects b...
 
A review of whether interdependency exists in effective Project Control Metho...
A review of whether interdependency exists in effective Project Control Metho...A review of whether interdependency exists in effective Project Control Metho...
A review of whether interdependency exists in effective Project Control Metho...
 
A Source of Project Cost Integration by "David Hurren - Technical Director fo...
A Source of Project Cost Integration by "David Hurren - Technical Director fo...A Source of Project Cost Integration by "David Hurren - Technical Director fo...
A Source of Project Cost Integration by "David Hurren - Technical Director fo...
 
Programmatic Controls Approach to; Fast track Disaster Recovery by "Saurabh B...
Programmatic Controls Approach to; Fast track Disaster Recovery by "Saurabh B...Programmatic Controls Approach to; Fast track Disaster Recovery by "Saurabh B...
Programmatic Controls Approach to; Fast track Disaster Recovery by "Saurabh B...
 
Enterprise Scheduling and Risk Management at Los Angeles Metro by "Julie Owen...
Enterprise Scheduling and Risk Management at Los Angeles Metro by "Julie Owen...Enterprise Scheduling and Risk Management at Los Angeles Metro by "Julie Owen...
Enterprise Scheduling and Risk Management at Los Angeles Metro by "Julie Owen...
 

Kürzlich hochgeladen

Quality by design.. ppt for RA (1ST SEM
Quality by design.. ppt for  RA (1ST SEMQuality by design.. ppt for  RA (1ST SEM
Quality by design.. ppt for RA (1ST SEMCharmi13
 
Don't Miss Out: Strategies for Making the Most of the Ethena DigitalOpportunity
Don't Miss Out: Strategies for Making the Most of the Ethena DigitalOpportunityDon't Miss Out: Strategies for Making the Most of the Ethena DigitalOpportunity
Don't Miss Out: Strategies for Making the Most of the Ethena DigitalOpportunityApp Ethena
 
General Elections Final Press Noteas per M
General Elections Final Press Noteas per MGeneral Elections Final Press Noteas per M
General Elections Final Press Noteas per MVidyaAdsule1
 
A Guide to Choosing the Ideal Air Cooler
A Guide to Choosing the Ideal Air CoolerA Guide to Choosing the Ideal Air Cooler
A Guide to Choosing the Ideal Air Coolerenquirieskenstar
 
THE COUNTRY WHO SOLVED THE WORLD_HOW CHINA LAUNCHED THE CIVILIZATION REVOLUTI...
THE COUNTRY WHO SOLVED THE WORLD_HOW CHINA LAUNCHED THE CIVILIZATION REVOLUTI...THE COUNTRY WHO SOLVED THE WORLD_HOW CHINA LAUNCHED THE CIVILIZATION REVOLUTI...
THE COUNTRY WHO SOLVED THE WORLD_HOW CHINA LAUNCHED THE CIVILIZATION REVOLUTI...漢銘 謝
 
RACHEL-ANN M. TENIBRO PRODUCT RESEARCH PRESENTATION
RACHEL-ANN M. TENIBRO PRODUCT RESEARCH PRESENTATIONRACHEL-ANN M. TENIBRO PRODUCT RESEARCH PRESENTATION
RACHEL-ANN M. TENIBRO PRODUCT RESEARCH PRESENTATIONRachelAnnTenibroAmaz
 
Testing with Fewer Resources: Toward Adaptive Approaches for Cost-effective ...
Testing with Fewer Resources:  Toward Adaptive Approaches for Cost-effective ...Testing with Fewer Resources:  Toward Adaptive Approaches for Cost-effective ...
Testing with Fewer Resources: Toward Adaptive Approaches for Cost-effective ...Sebastiano Panichella
 
Chizaram's Women Tech Makers Deck. .pptx
Chizaram's Women Tech Makers Deck.  .pptxChizaram's Women Tech Makers Deck.  .pptx
Chizaram's Women Tech Makers Deck. .pptxogubuikealex
 
GESCO SE Press and Analyst Conference on Financial Results 2024
GESCO SE Press and Analyst Conference on Financial Results 2024GESCO SE Press and Analyst Conference on Financial Results 2024
GESCO SE Press and Analyst Conference on Financial Results 2024GESCO SE
 
Internship Presentation | PPT | CSE | SE
Internship Presentation | PPT | CSE | SEInternship Presentation | PPT | CSE | SE
Internship Presentation | PPT | CSE | SESaleh Ibne Omar
 
INDIAN GCP GUIDELINE. for Regulatory affair 1st sem CRR
INDIAN GCP GUIDELINE. for Regulatory  affair 1st sem CRRINDIAN GCP GUIDELINE. for Regulatory  affair 1st sem CRR
INDIAN GCP GUIDELINE. for Regulatory affair 1st sem CRRsarwankumar4524
 
05.02 MMC - Assignment 4 - Image Attribution Lovepreet.pptx
05.02 MMC - Assignment 4 - Image Attribution Lovepreet.pptx05.02 MMC - Assignment 4 - Image Attribution Lovepreet.pptx
05.02 MMC - Assignment 4 - Image Attribution Lovepreet.pptxerickamwana1
 
Testing and Development Challenges for Complex Cyber-Physical Systems: Insigh...
Testing and Development Challenges for Complex Cyber-Physical Systems: Insigh...Testing and Development Challenges for Complex Cyber-Physical Systems: Insigh...
Testing and Development Challenges for Complex Cyber-Physical Systems: Insigh...Sebastiano Panichella
 
cse-csp batch4 review-1.1.pptx cyber security
cse-csp batch4 review-1.1.pptx cyber securitycse-csp batch4 review-1.1.pptx cyber security
cse-csp batch4 review-1.1.pptx cyber securitysandeepnani2260
 
Engaging Eid Ul Fitr Presentation for Kindergartners.pptx
Engaging Eid Ul Fitr Presentation for Kindergartners.pptxEngaging Eid Ul Fitr Presentation for Kindergartners.pptx
Engaging Eid Ul Fitr Presentation for Kindergartners.pptxAsifArshad8
 
proposal kumeneger edited.docx A kumeeger
proposal kumeneger edited.docx A kumeegerproposal kumeneger edited.docx A kumeeger
proposal kumeneger edited.docx A kumeegerkumenegertelayegrama
 
Application of GIS in Landslide Disaster Response.pptx
Application of GIS in Landslide Disaster Response.pptxApplication of GIS in Landslide Disaster Response.pptx
Application of GIS in Landslide Disaster Response.pptxRoquia Salam
 

Kürzlich hochgeladen (17)

Quality by design.. ppt for RA (1ST SEM
Quality by design.. ppt for  RA (1ST SEMQuality by design.. ppt for  RA (1ST SEM
Quality by design.. ppt for RA (1ST SEM
 
Don't Miss Out: Strategies for Making the Most of the Ethena DigitalOpportunity
Don't Miss Out: Strategies for Making the Most of the Ethena DigitalOpportunityDon't Miss Out: Strategies for Making the Most of the Ethena DigitalOpportunity
Don't Miss Out: Strategies for Making the Most of the Ethena DigitalOpportunity
 
General Elections Final Press Noteas per M
General Elections Final Press Noteas per MGeneral Elections Final Press Noteas per M
General Elections Final Press Noteas per M
 
A Guide to Choosing the Ideal Air Cooler
A Guide to Choosing the Ideal Air CoolerA Guide to Choosing the Ideal Air Cooler
A Guide to Choosing the Ideal Air Cooler
 
THE COUNTRY WHO SOLVED THE WORLD_HOW CHINA LAUNCHED THE CIVILIZATION REVOLUTI...
THE COUNTRY WHO SOLVED THE WORLD_HOW CHINA LAUNCHED THE CIVILIZATION REVOLUTI...THE COUNTRY WHO SOLVED THE WORLD_HOW CHINA LAUNCHED THE CIVILIZATION REVOLUTI...
THE COUNTRY WHO SOLVED THE WORLD_HOW CHINA LAUNCHED THE CIVILIZATION REVOLUTI...
 
RACHEL-ANN M. TENIBRO PRODUCT RESEARCH PRESENTATION
RACHEL-ANN M. TENIBRO PRODUCT RESEARCH PRESENTATIONRACHEL-ANN M. TENIBRO PRODUCT RESEARCH PRESENTATION
RACHEL-ANN M. TENIBRO PRODUCT RESEARCH PRESENTATION
 
Testing with Fewer Resources: Toward Adaptive Approaches for Cost-effective ...
Testing with Fewer Resources:  Toward Adaptive Approaches for Cost-effective ...Testing with Fewer Resources:  Toward Adaptive Approaches for Cost-effective ...
Testing with Fewer Resources: Toward Adaptive Approaches for Cost-effective ...
 
Chizaram's Women Tech Makers Deck. .pptx
Chizaram's Women Tech Makers Deck.  .pptxChizaram's Women Tech Makers Deck.  .pptx
Chizaram's Women Tech Makers Deck. .pptx
 
GESCO SE Press and Analyst Conference on Financial Results 2024
GESCO SE Press and Analyst Conference on Financial Results 2024GESCO SE Press and Analyst Conference on Financial Results 2024
GESCO SE Press and Analyst Conference on Financial Results 2024
 
Internship Presentation | PPT | CSE | SE
Internship Presentation | PPT | CSE | SEInternship Presentation | PPT | CSE | SE
Internship Presentation | PPT | CSE | SE
 
INDIAN GCP GUIDELINE. for Regulatory affair 1st sem CRR
INDIAN GCP GUIDELINE. for Regulatory  affair 1st sem CRRINDIAN GCP GUIDELINE. for Regulatory  affair 1st sem CRR
INDIAN GCP GUIDELINE. for Regulatory affair 1st sem CRR
 
05.02 MMC - Assignment 4 - Image Attribution Lovepreet.pptx
05.02 MMC - Assignment 4 - Image Attribution Lovepreet.pptx05.02 MMC - Assignment 4 - Image Attribution Lovepreet.pptx
05.02 MMC - Assignment 4 - Image Attribution Lovepreet.pptx
 
Testing and Development Challenges for Complex Cyber-Physical Systems: Insigh...
Testing and Development Challenges for Complex Cyber-Physical Systems: Insigh...Testing and Development Challenges for Complex Cyber-Physical Systems: Insigh...
Testing and Development Challenges for Complex Cyber-Physical Systems: Insigh...
 
cse-csp batch4 review-1.1.pptx cyber security
cse-csp batch4 review-1.1.pptx cyber securitycse-csp batch4 review-1.1.pptx cyber security
cse-csp batch4 review-1.1.pptx cyber security
 
Engaging Eid Ul Fitr Presentation for Kindergartners.pptx
Engaging Eid Ul Fitr Presentation for Kindergartners.pptxEngaging Eid Ul Fitr Presentation for Kindergartners.pptx
Engaging Eid Ul Fitr Presentation for Kindergartners.pptx
 
proposal kumeneger edited.docx A kumeeger
proposal kumeneger edited.docx A kumeegerproposal kumeneger edited.docx A kumeeger
proposal kumeneger edited.docx A kumeeger
 
Application of GIS in Landslide Disaster Response.pptx
Application of GIS in Landslide Disaster Response.pptxApplication of GIS in Landslide Disaster Response.pptx
Application of GIS in Landslide Disaster Response.pptx
 

Managing Construction Risk and Claims

  • 1. The Global Leader in Managing Construction Risk ™ Litigation & Claims Facts & Figures Paul Lomas-Clarke FRICS FCIArb FCIOB CEDR Accredited Mediator Executive Director 2011
  • 2. 2 The reasons claims arise •  Inadequate contract preparation •  Mistakes in documents •  Optimisms instead of reality •  Misunderstanding formation of Contract •  Failure to understand risk •  Poorly drafted variation instructions •  Failure to understand basic contractual position •  Failure to analyse / explain additional entitlements
  • 3. 3 GENERAL PRINCIPLES Recognising Claims Early •  Essential to avoid disputes and speed resolution •  Allow good record keeping •  Assists in managing entitlements •  Burden of proof on claiming party •  Monitoring procedures –  (+consequential time / costs)
  • 4. 4 EXTENSION OF TIME CLAIMS Purpose Protects contractor against liquidated damages by excusing delay Protects Employer’s right to LADs by maintaining a completion date (a date from which to calculate LADs) – Holme V Guppy 1838 – Wells V Army & Navy Co-op 1902 •  Otherwise a penalty
  • 5. 5 Employer’s Claims LIQUIDATED DAMAGES Reason for Use of LADs •  Contractual equivalent of common law damages •  Benefit for both parties •  For Employer: –  a contractual right - no need to prove loss •  Hadley V Baxendale •  For Contractor: –  Obligation known –  Can advise potential liability to others (ie. special damages)
  • 6. 6 Employer’s Claims LIQUIDATED DAMAGES Rules (cont’d) Rules for applying LADs •  Where procedures apply, most be applied strictly •  Where notice required – condition precedent –  Principal may lose right to LADs where proper notice not given – •  Bell v CBF; •  JF Finnegan Ltd -v- Community Housing Association Ltd •  Delaying breach where no corresponding provision •  (Rapid v Ealing Family Housing) •  Incompatibility between contract and appendix •  (Sheffield v Bramell & Ogden) •  ‘NIL’ in appendix
  • 7. 7 Penalties •  Sum must not be a penalty –  Dunlop v New Garage & Motor Co (1915) –  is it a genuine pre-estimate? - is it ‘in terrorem’ (threat) –  BFI Group of Companies Ltd -v- DCB Integration Systems Ltd (1987)
  • 8. 8 Employer’s Claims LIQUIDATED DAMAGES •  Need not be actual loss – Clydebank Engineering and Shipbuilding Company Limited v Don Jose Ramos Ysquierdo y Castaneda and Others [1905]
  • 9. 9 EXTENSION OF TIME CLAIMS Notices •  Most contracts contain procedures – normally requirement for notice, – JCT – forthwith after delay apparent – MF/1 – as soon as reasonably practicable – ECC – within 8 wks of becoming aware of compensation event – GC Works - Within 56 days
  • 10. 10 EXTENSION OF TIME (cont’d) Notices (cont’d) •  Form of notice? – as contract requires •  Some contracts require detailed notice, eg –  JCT – particulars and effects, estimate, update –  ECC – Early warning in writing –  MF/1 – full supporting details –  Recommendation- apply as close as possible to event •  Site minutes? –  In Haley v Dumfries & Galloway – not good notice
  • 11. 11 EXTENSION OF TIME (cont’d) Grounds for extension (ie. for excusable delay) Some contracts list ‘reasons’ in detail, eg: Employer (late information) Neutral (exceptional inclement weather) •  Some contracts give general grounds, eg: JCT Minor Works, MF/1 •  Matters beyond contractor’s control
  • 12. 12 EXTENSION OF TIME (cont’d) •  Use of Float – First to use gets the benefit – JCT Architect gives reasonable EOT •  Use float – NEC Actual time added to Programme •  Float Preserved
  • 13. 13 EXTENSION OF TIME (cont’d) •  Claimant must identify Employer’s liability that actually causes delay to completion. – I.E. delay on critical path Delay on non critical item – No EOT to contract Perhaps additional prelims as VO
  • 14. 14 PROGRAMMES •  Programmes often not ‘agreed’, e.g. – JCT 05 (clause 2.9.1.2): silent other than contractor to “provide” – ICE (clause 14): acceptance of original – GC Works: agreement of amendments by PM – NEC3 (clause 31): acceptance of original & revisions by PM
  • 15. 15 Critical Path Analysis “The Society of Construction Law Delay and Disruption Protocol – October 2002” www.eotprotocol.com Recommendations •  A Critical Path Network •  Uses commercially available Software •  Identifies All Relevant Activities •  Tool to Manage Change
  • 16. 16 Schedule of delays Ref No Arch Ins Or other + Date Cause Period of Delay (days ) Effect on Progrm Notice Served
  • 17. 17 Cofferdams Abutments Deck Structure Deck Furniture/E&M Finishing & Commissioning At-Grade Approach Roads Appoint Subcontractor Construct Approach Road (2km) Open Bridge & Roads 0 1 2 3 4 5 6 7 8 9 10 11 Bridge MONTHS Site Clearance Delay Analysis “Black Art”
  • 18. 18 Delay Analysis – as built At-Grade Approach Roads 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 MONTHS Construct Approach Roads (3km) Actual Finish Month 15Appoint Subcontractor Deck Structure Deck Furniture/E&M Finishing & Commissioning Site Clearance Bridge Cofferdams Abutments
  • 19. 19 Delay Analysis – Time Slice/Window 30 10 At-Grade Approach Roads 45 6 Open Bridge & Roads 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 Deck Structure Deck Furniture/E&M Finishing & Commissioning Site Clearance Bridge Cofferdams Abutments MONTHS 40d EoT Construct Approach Roads (3km) Actual Finish Month 15Appoint Subcontractor 6d EoT 10 Days Denied Access to Site. 30 Days Additional work to abutments required by client. 45 Days Additional work to approach road 6 Days Additional gulley road approach road. Progress after 15 months
  • 20. 20 The way NOT to show progress and delays
  • 21. 21 Variations Claims Employer / agent changes; •  the features, scope or complexity of the project –  Therefore; •  Adjustment to the contract price •  Adjustment to the contract period
  • 22. 22 Claim Problems •  Viability of Original Programme •  Original Resources correct? •  Variation in critical path •  Subcontractors information •  Lack of Records
  • 23. 23 Claim Issues •  JCT Wide definition of variation •  Access to site, working space, working hours, specific order of works –  Variations must include adjustment of preliminary items as SMM –  Change in conditions under which other work is executed must be taken into account in variations –  Include fair allowance for any change caused by variations –  Exclusion for reimbursement under any other provision
  • 24. 24 Claim issues •  GC /Works/1 –  Very wide definition of variation •  Change, suspension, “any other matter” –  Disruption to be included in price of variation –  Allowance for expense only (money expended) not loss –  Obligation to submit information within 28 days –  QS to notify within 28 days –  Contractors objection to QS limited to 14 day “window” –  Weather delays excluded –  Embargo on delay claims after completion
  • 25. 25 Claim issues •  NEC (ECC) –  Wide range of rights to claim compensation events –  BUT notice must be given within 8 weeks = condition precedent to rights –  References to EOT = Change in Completion Date –  Contractor can be locked into his quote –  Project Manager must give decision within one week
  • 26. 26 Claim Problems •  Acceleration claims are almost impossible – Nearly all current contracts have special clauses •  No instruction – no acceleration •  Thickening claims – Include in preliminaries for additional staff in variations
  • 27. 27 Legal Principles and Case Law •  Percy Bilton Ltd v Greater London Council [1982] –  Lowdell (first Nominated Sub-Contractor) stops work and is liquidated –  Crown House (second Nominated Sub-Contractor) withdraws without starting work –  Home Counties (third Nominated Sub-Contractor) completes work –  Employer must re-nominate in reasonable period –  Time not at large
  • 28. 28 Legal Principles and Case Law •  Walter Lawrence & Sons ltd v Commercial Union Properties Ltd [1984] – Contractor defers work into period of bad weather – Test: does exceptionally inclement weather actually give rise to a delay
  • 29. 29 Legal Principles and Case Law •  Yorkshire Water Authority v Sir Alfred McAlpine & Son Ltd [1986] – McAlpine programme and method statement included in Contract – Works were impossible to build to programme sequence – Change is Variation under Contract
  • 30. 30 Legal Principles and Case Law •  Glenlion Construction ltd v The Guiness Trust [1987] – Glenlion programmed to complete works early – Glenlion entitled to work to programme – Guiness obliged not to hinder or obstruct – BUT Guiness not obliged to provide information early
  • 31. 31 Legal Principles and Case Law •  Ascon Contracting Ltd v Alfred McAlpine Construction Isle of Man Ltd [1999] – Ascon cause McAlpine delay – McAlpine main contract programme contains “float” – McAlpine not entitled to “benefit of “float”
  • 32. 32 Legal Principles and Case Law •  Great Eastern Hotel Company Ltd v John Laing [2005] – Laing used Impacted As-planned analysis – GEHC used a form of Time Impact Analysis – Judge favoured the factual basis of GEHC and Laing analysis hypothetical
  • 33. 33 So what to do? •  Question over the probative value of different techniques •  Remember 'rubbish in rubbish out' especially to computerized CPA models •  Don’t get lost in the analyses; •  Assemble a matrix of facts in the form of planned and as-built dates •  Beware of manipulation to create a preferred result; •  Complex networks can be very difficult to follow and the relationships between activities difficult to understand •  Adopt the appropriate one using a level of detail which is both persuasive and yet proportionate to the scale of the dispute.